L&W CONSTRUCTION PVT LTD

RMZ PLOT-A, BLOCK-4AB & 4C

WORK METHOD STATEMENT FOR


STORE CONSTRUCTION

Total no. of sheets including this sheet : 5

FILE NO: LW/FIP/RMZ/FPS/ 4AB/WMS/001

NOT-APPROVED COMMENTS AS INDICATED / ATTACHED


APPROVED WITH MINOR COMMENTS
APPROVED
TICK BOX DATE DOCUMENT STATUS

R0 05/07/14 For Approval FIREPRO L&W RMZ


REVISION DATE REASON FOR ISSUE ORIGINATOR CHECKED APPROVED

PROJECT : RMZ ECOWORLD PLOT A 4AB

DESIGN & BUILT


SUB-CONTRACTOR OWNER
CONTRACTOR
Page 2 of 5
Doc No.: LW/FIP/RMZ/FPS/
Work Method Statement 4AB/WMS/001
for Store and Office Construction Rev. No. : 00
Date 05th July, 2014

Contents

A. Objective:.......................................................................................................3
B. Scope of work:...............................................................................................3
C. Materials:.......................................................................................................3
D. Tools:..............................................................................................................3
E. Safety Equipment:..........................................................................................4
F. Manpower resources:....................................................................................4
G. Procedure:......................................................................................................4

PREPARED BY & DATE REVIEWED BY & DATE APPROVED BY & DATE

FOR FIREPRO SYSTEMS FOR L and W FOR RMZ


Page 3 of 5
Doc No.: LW/FIP/RMZ/FPS/
Work Method Statement 4AB/WMS/001
for Store and Office Construction Rev. No. : 00
Date 05th July, 2014

A. Objective:
The objective of this statement is to outline the method for construction of a secure temporary
structure capable of housing costlier and sensitive intellectual as well as physical property presently
owned by the contractor which shall be transferred to the ownership of the end-client/owner by
handing over to the main contacting party.

B. Scope of work:
Construction of store and office to house material and important documents pertaining to
the orders received by the party preparing this document.
The store will primarily be used to safeguard fittings and materials that may be removable
secretively like fittings, valves, Fire Alarm material. Pipes will be stored separately outside the
store.
The store will also secure the materials (tools and tackles) of the sub-contractor(s) if the sub-
contractor(s) is (are) unable to create their store.
The store and office structure will have to provide the necessary infrastructure that will be
the bedrock for all works at the site undertaken by the contractor.

C. Materials:
Sheet for Store and office walls: Approved color corrugated sheets
MS B Class pipe 25mm and 40mm dia
Base plate 150mm x 150mm
Clamps (J and/or U-type)
Anchor fastener with bolt, nut and washer M10
Stud rod M10
Welding Rods
Binding wire

D. Tools:
Welding Machine(s)
Drilling Machine(s)
Hammer(s)
Spanner(s)
Aluminium Ladder(s)
Mobile Ladder(s)

PREPARED BY & DATE REVIEWED BY & DATE APPROVED BY & DATE

FOR FIREPRO SYSTEMS FOR L and W FOR RMZ


Page 4 of 5
Doc No.: LW/FIP/RMZ/FPS/
Work Method Statement 4AB/WMS/001
for Store and Office Construction Rev. No. : 00
Date 05th July, 2014

E. Safety Equipment:
Safety shoes
Helmet(s)
Safety Jacket(s)
Welding helmet(s)
Safety Gloves

F. Manpower:
One or more team(s) consisting of:
o One welder (cum-fitter)
o One fitter (if welder is not capable of fit-up)
o One cutter (if reqd.)
o Two unskilled labour

G. Procedure:
Store and office location and space needs to be approved before construction begins. Scope
of power supply will be as per contract and client approvals.
Preferably the store should be within the buildings civil structure and the same is
considered.
The supporting pipe has to have a base plate welded at the end that will be placed on the
floor to prevent damage to the floor.
For a square store at least four vertical pipes will be provided at each corner. For other
layouts at least one vertical pipe needs to support each corner of the floor space.
The pipes will be anchored at the top using a stud rod and anchor fastener anchored in the
ceiling of the store area if within a civil structure.
The corrugated sheets will run over the pipes so as to form the walls of the store and office.
If permissible, there should be provision of ventilation space between the ceiling and the
corrugated sheet provided the corrugated sheet forms at least an 8-10 feet (2.5-3m) height
wall.
Corrugated sheets will be anchored at the pipes by J-clamps or U-clamps.
Repeat the same for construction of the office.
There should be separate doors to the store and the office with an interconnecting door if
they are side-by-side.
Store needs to have adequate storage space for assembly of heavy duty material storage
shelves, material storage before shelving as well as contractor tools and tackles.
The office needs to have adequate space to accommodate two desks, filing shelves and a
filing cabinet/ almirah. One of the desks will be for the onsite computer and printer (if
required). The other desk will be for site team meetings and discussions.
If space is available a third desk should be accommodated for the project managers usage.
PREPARED BY & DATE REVIEWED BY & DATE APPROVED BY & DATE

FOR FIREPRO SYSTEMS FOR L and W FOR RMZ


Page 5 of 5
Doc No.: LW/FIP/RMZ/FPS/
Work Method Statement 4AB/WMS/001
for Store and Office Construction Rev. No. : 00
Date 05th July, 2014

Power supply will reach the store through the appropriate fault protected method and provided at
the main switch board from where electrical connections will be run for store and office lights, fans
and the site computer as well as 3-4 plug points in surplus of the ones provided for the fit-out of the
office.

PREPARED BY & DATE REVIEWED BY & DATE APPROVED BY & DATE

FOR FIREPRO SYSTEMS FOR L and W FOR RMZ