Sunteți pe pagina 1din 3

BORED PILING METHOD STATEMENT.

WORK PROCEDURE
PROJECT: Ref No. FOUN/04
PAGE 1 OF 2
SECTION: DATE OF ISSUE
FOUNDATIONS Dec 2012
SUBJECT: BY:
QA/QC ENGINEER
BORED PILING APPROVED BY:
QEHS MANAGER
ACTION VERIFY

1. SCOPE

The scope of this procedure covers the control of installation


of Bored Cast-in-Situ Concrete piles executed by a sub-
contractor.

2. PROCEDURE

.1 Method Statement:
A method statement shall be submitted by the piling Sub- Project Method
contractor for approval which shall include: Manager Statement

i) Construction procedure.
ii) Pile design with calculations.
iii) Testing procedure.
iv) Documentation to be maintained during the execution
of work.
v) Mix design for concrete.
vi) Specification for reinforcement steel and bentonite
clay.
vii) Any other information required by the specification.

.2 Construction Programme:
The sub-contractor shall submit a programme for approval Sub- Approved
based on the Contract Programme. The subcontractor shall contractor Construction
also indicate the mobilisation time of plant, equipment, Programme
materials and work force.
Project Approval
.3 Piling Sequence: Manager
Approval of piling sequence will be given prior to
commencement of piling by the Subcontractor.

.4 Setting-Out: Subcon/
FCC Field Book
HEE will execute pre-piling setting out and offer for cross- Surveyor
checking by Subcontractors Surveyor and Consultants
Representative.
WORK PROCEDURE

PROJECT: Ref No. FOUN/04


PAGE 2 OF 2
SECTION: DATE OF ISSUE
FOUNDATIONS Dec 2012
SUBJECT: BY:
QA/QC ENGINEER
BORED PILING APPROVED BY:
QHSE MANAGER
ACTION VERIFY

.5 Source Certificates:

Reinforcement steel and Bentonite test certificates if required Project Source


shall be obtained from the Subcontractor and, submitted for Engineer certificate
approval by the Consultant.

.6 Concrete Cube Testing:


Project
Cube results will be assessed and retained. The cube test Engineer/ Test result,
reports shall be clearly identified with the location of pour by Labtech. FOUN/04/A
reference to the checksheet.

.7 Testing of Piles:
Pile testing
The Subcontractor shall carry out a load test and integrity test Subcon. record
as specified in the Contract.

.8 Inspection of Work/Checksheet:

The work shall be inspected using the attached checksheet


as Appendix FOUN/04/A which shall be completed as QA/QC Checksheet
verification and record of compliance.

.9 Non-Conformity:
Non-
Non-conforming workmanship shall be notified to the Conformity
Subcontractor as Appendix 7/3/6/A and corrective action QA/QC Report
taken in accordance with good working practice and
Consultants approval.
PROJECT: SITE NO.:

CHECK SHEET FOR BORED PILING Sheet No.

SUBCONTRACTOR: FATAYERJI

SECTION OF WORK ____________________________LOCATION _________________

Checke
STAGE ITEM d DATE
by

PREPARATION 1. Subcontractors method statement approved. PE

2. Materials approved by the consultant. PE

3. Cross-check location of Pile. SU

APPROVAL TO PROCEED QA/QC


INSTALLATION 4. Check borehole to be filled with Bentonite
slurry at all times. GF

5. Check cleaning of bottom of borehole. GF

6. Check reinforcement cage. SE


7. Check minimum cover while lowering cage
into the borehole. GF

8. Check slump of concrete. Lab

9. Check cut-off level + location. SU

APPROVAL TO PROCEED WITH PILE CAP. CM

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE - Project Engineer, SE Site


Engineer, GF General Foreman, SU - Surveyor, Lab - Laboratory Technician

S-ar putea să vă placă și