Timeline Schedule Yokogawa

Mar-17
NO Task Description 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3
First Phase Travelling
1 Travel time
2 Training MSW
3 Training Greencard
4 Collect Database
5 Confirming tagnames with Operator
6 Offline Engineering
Second Phase Travelling
1 Mobilization YIN Team
2 Start Implementation AOA @ CGS 1
3 Start Implementation AOA @ CGS 5

4 Training AOA for Operator @ CGS 1


5 Training AOA for Operator @ CGS 5
6 De-mobilization YIN Team
7 Close out Document & Closing WO (by TOP)
Timeline Schedule Yokogawa
Apr-17
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

Off days Pak Timothy


Timeline Schedule Yokogawa
Mar-17
NO Task Description 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 Travel time
2 Training MSW
3 Training Greencard
4 Collect Database
5 Confirming tagnames with Operator
6 Offline Engineering

1 Mobilization YIN Team


2 Start Implementation AOA @ CGS 1
3 Start Implementation AOA @ CGS 5

4 Training AOA for Operator @ CGS 1


5 Training AOA for Operator @ CGS 5
6 De-mobilization YIN Team
7 Close out Document & Closing WO
8 Travel time

Timeline Schedule Yokogawa


Mar-17
NO Task Description 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 Mobilization YIN Team
2 Start Implementation AOA @ CGS 1
3 Start Implementation AOA @ CGS 5

4 Training AOA for Operator @ CGS 1


5 Training AOA for Operator @ CGS 5
6 De-mobilization YIN Team
7 Close out Document & Closing WO
8 Travel time

Timeline Schedule Yokogawa


Mar-17
NO Task Description 8 9 10 11 12 13 14 15 16 17 18 19 20 21
First Phase Travelling
1 Travel time
2 Training MSW
3 Training Greencard
4 Collect Database
5 Confirming tagnames with Operator
6 Offline Engineering
Second Phase Travelling
1 Mobilization YIN Team
2 Start Implementation AOA @ CGS 1
3 Start Implementation AOA @ CGS 5

4 Training AOA for Operator @ CGS 1


5 Training AOA for Operator @ CGS 5
6 De-mobilization YIN Team
7 Close out Document & Closing WO (by TOP)
8 Travel time
chedule Yokogawa Timeline Schedule Yokogawa
Mar-17 Apr-17
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Off days Pak Timothy

chedule Yokogawa Timeline Schedule Yokogawa


Mar-17 Apr-17
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Off days Pak Timothy

chedule Yokogawa Timeline Schedule Yokogawa


Mar-17 Apr-17
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Off days Pak Timothy
wa

17 18 19 20 21

wa

17 18 19 20 21

wa

17 18 19 20 21
Timeline Schedule Honeywell

NO Task Description 8 9 10 11 12 13 14 15 16 17 18 19 20
1 Mobilization HW Team
2 Disscuss with CPI Team
3 Start Implementation AOA @ CGS 3
- Upload & Download AOA
- Function test alarm

4 Training AOA for Operator @ CGS 3


5 De-mobilization Team
6 Close out Document & Closing WO (By TOP)