Documente Academic
Documente Profesional
Documente Cultură
24 June 2016
Contaminated Land DSI - Metro Sports Facility
Revision History
Revision N Prepared By Description Date
Document Acceptance
Action Name Signed Date
Beca 2015 (unless Beca has expressly agreed otherwise with the Client in writing).
This report has been prepared by Beca on the specific instructions of our Client. It is solely for our Clients use for the purpose for which
it is intended in accordance with the agreed scope of work. Any use or reliance by any person contrary to the above, to which Beca has
not given its prior written consent, is at that person's own risk.
Executive Summary
The historical review of the proposed Metro Sports Facility (MSF) site indicates that the site has largely been
used for commercial and industrial purposes since the 1940s. Several chemical storage areas, motor vehicle
workshops, boiler activities and substations have been onsite, therefore HAIL1 activities include:
Activity A17 Storage tanks or drums for fuel, chemicals and liquid waste
Activity B2 Electrical transformers
Activity B4 Power stations, substations or switchyards
Activity F4 Motor vehicle workshops
This investigation was undertaken to assess the level of contamination present onsite for contaminants
associated with the storage of chemicals, substations and workshops, and also for the fill materials.
These investigations have been undertaken in four phases dependent on site accessibility and demolition of
buildings. The investigations to date were undertaken in July 2014, November 2014, March 2015, and June
2016. Phase 4 (May 2016) investigations were undertaken under the new client company tkaro Limited,
taking works over from CERA. Tonkin & Taylor Ltd (T&T) were engaged by CERA (now tkaro) to assess
asbestos in soils for the site. The investigations were undertaken concurrently with the Beca investigations
and reported separately in Metro Sports Facility, Detailed Site Investigation (Asbestos) - Metro Sports
Facility, July 2016.
A total of 97 test pits and four boreholes were excavated for the investigation up to approximately 3.0 m
deep. The general soil profile consisted of a surface layer of hard fill gravel and crushed demolition material
(0.5 m) placed across most of the site. Construction waste including concrete, brick, rebar and rubbish was
encountered in Phase 1 investigations and an old fill layer (generally 0.5 m-1.0 m depth) comprising dark
brown silt with some brick, ceramic and steel fragments was located in Phase 2 and 3 investigation areas.
Phase 4 pits were similar to Phase 1, with a surface fill layer to approximately 0.5 m depth.
Standing water was encountered at various depths during the Phase 1 and 4 investigations, none was
observed in Phases 2 and 3. In some test pits (notably TP105, TP117 and TP119) a groundwater level of 0.3
m bgl was struck. Significant groundwater flows into test pits made excavation difficult and at times
prevented deeper excavations. Water seeped into six test pits in Phase 2 investigations at approximately
1.4-1.7 m depths and into five test pits in Phase 3 investigations at approximately 1.8-2.6 m depths. Phase 4
had groundwater ingress generally between 1-2 m, but was only observed in 7 of the 16 pits. Only a small
volume of water entered the test pits, therefore may not be sufficient to suggest a permanent shallow
groundwater level.
Soil samples were collected from a range of depths across the soil profile ranging from surface to 3.0 m bgl.
Samples were selected for analysis based on the location of former activities on site, as well as site
observations. Laboratory analysis comprised the following:
1
Hazardous Activities and Industries List, Ministry for the Environment, 2011
The investigation identified five locations out of 101 that exceeded the human health soil contaminant
standards for arsenic, lead or benzo(a)pyrene equivalent for commercial land use. These samples were
generally found in a fill layer and/or on HAIL sites, with the exception of TP409, which is considered a lead
hopspot. The source of this sample has not been confirmed but it is completely inconsistent with the
remaining site distribution of lead. A 95% upper confidence limit was performed on the analytes and the
results (with the exception of TP409) were below the commercial land use soil contaminant standards. It is
therefore considered that, assuming excavation and disposal of soils across the site are undertaken at a
similar time, the overall site is within the commercial land use soil contaminant standards. While gross
contamination was not identified across most of the site, many areas were above background concentrations
and adopted environmental criteria for metals and some hydrocarbons and volatile compounds.
The consenting assessment in this report was made with consideration of the site in a typical regulatory
context without evaluation of the Designation controls and any other special CERA/tkaro frameworks. It is
anticipated that the below planning considerations will require review in the context of the wider MSF
consenting.
While the final design parameters of the development are yet to be confirmed, the volume of material that is
to be excavated from the site is likely to exceed the permitted activity volume thresholds under the Resource
Management (National Environmental Standard for Assessing and Managing Contaminants in Soil to Protect
Human Health) Regulations 2011 (NESCS). Therefore it is highly likely that resource consent will be required
under NESCS for soil disturbance. The interaction between the NESCS with the site designations was not
investigated. There are also some underground storage tanks that may be onsite, and if these have resulted
in gross contamination, it is unlikely that the removal of the tanks will meet the permitted activity
requirements. Resource consent to remove any potential tanks could be obtained as a precaution with the
soil disturbance application.
Resource consent will also need to be obtained for the construction of the development under the proposed
Land and Water Regional Plan for the discharge of contaminants onto or into land from a contaminated site
in circumstances where those contaminants may enter water. The contaminant concentrations onsite are
above background and adopted environmental criteria, therefore cannot meet the permitted activity
requirements. This report will need to be provided to ECan to meet the permitted activity requirements for the
use of land for a site investigation.
Remedial action will be required at the lead hotspot at TP409 and a contaminated soils management plan
will be required for the wider site, particularly in locations where sample results were above the commercial
land use soil contaminant standards for human health (i.e. where arsenic, lead, and B(a)P eq. was found to
exceed human health soil contaminant standards) .
The exposure pathway assessment completed for the soil investigation identified potentially complete
exposure pathways in relation to human health. These could be mitigated and managed through the
implementation of a Contaminated Soils Management Plan and remediation at TP409, which will likely form
part of resource consent conditions for soil disturbance.
The material onsite generally meets the definition of managed fill and may be disposed to an appropriate
facility (currently Burwood Landfill, operated by CCC). Further analysis of soils that do not meet the managed
fill acceptance criteria (e.g. soils at TP409) will require toxicity characteristic leaching procedure (TCLP)
analysis to determine acceptance to Kate Valley Landfill. There are also restrictions with regards to asbestos
material being disposed to managed fill, please refer to the Tonkin & Taylor Ltd asbestos assessment report
for further detail.
Internal streets of the MSF include Horatio Street and Balfour Terrace, which are currently active
carriageways. If access is available, investigation and assessment of the internal roads should also be
undertaken to assess materials for disposal or alternately this testing may be deferred to construction.
1 Introduction 1
1.1 Purpose and Scope 1
3 Site History 5
3.1 Summary of the PSI Findings 5
3.2 Previous Investigations 5
5 Assessment Criteria 10
6 Results 11
6.1 Fieldwork Observations 11
6.2 Summary of Soil Analytical Results 11
6.3 Quality Assurance and Quality Control 14
8 Development Implications 18
8.1 Consents 18
8.2 Contaminated Soil Management Plan (CSMP) 19
8.3 Disposal Options 20
8.4 Further Work 20
9 Conclusions 21
10 Limitations 23
Appendices
Appendix A
Site Plans
Appendix C
Site Photographs
Appendix D
Chain of Custody Documentation
Appendix E
Laboratory Results
Appendix F
Upper Confidence Limit Calculations
A number of buildings were required to be demolished as a result of the Canterbury 2010 and subsequent
earthquakes and the site was designated for MSF purposes. Plans for the MSF are yet to be confirmed, but
the development of the site is likely to include:
A Preliminary Site Investigation (PSI) was prepared by Beca in 2013 for the site and identified a number of
Hazardous Activities and Industries List (HAIL) activities that are known to have occurred within the site
boundary. The development of the site is likely to involve a significant amount of earthworks and will
therefore trigger the need for resource consent under the Resource Management (National Environmental
Standard for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011
(NESCS). The findings of this DSI will also indicate if resource consents will also be required under the City
and Regional Plans. This report can be used to support the resource consent applications.
Tonkin & Taylor Ltd (T&T) were engaged by CERA to assess asbestos in soils for the site. The investigations
were undertaken concurrently with the Beca investigations.
Characterise potential contaminants in soils within the development area as a result of historical activities.
Confirm contaminated land consent requirements for the proposed works under the following legislation
Environment Canterbury (ECan) Natural Resources Regional Plan and proposed Land and Water
Regional Plan
Christchurch City Plan
NESCS
Identify areas of soil contamination which may require management with respect to risks to human health
and to the environment.
Provide advice regarding disposal of waste spoil.
The ground investigation was undertaken in several phases of work, dependent on accessibility and
demolition of buildings. This report presents and assesses the findings of the investigation which comprised
the following:
Phase 1
Excavation of 26 test pits to a maximum depth of 3.0 m below ground level in July 2014;
Collection of 81 soil samples from the test pits;
Phase 2
Excavation of 22 test pits to a maximum depth of 2.2 m below ground level (bgl) in November 2014;
Collection of 61 soil samples from the test pits;
Screening analysis of 44 samples for heavy metals, TPH, BTEX and SVOCs.
Phase 3
Excavation of 37 test pits and drilling of 4 boreholes to a maximum depth of 3.0 m bgl in March 2015;
Collection of 133 soil samples from the test pits;
Screening analysis of 90 samples plus 6 QA/QC samples for heavy metals, TPH, BTEX and SVOCs.
Phase 4
Excavation of 16 test pits to a maximum depth of 2.4 m bgl in May 2016;
Collection of 41 soil samples from the test pits
Screening analysis of 38 samples plus 3 QA/QC samples for heavy metals, TPH, PAHs and SVOCs.
This assessment has been undertaken and reported in general accordance with the Ministry for the
Environment (MfE) Contaminated Land Management Guidelines No. 1 Reporting on Contaminated Sites in
New Zealand (2011) and MfE Contaminated Land Management Guidelines No. 5 Site Investigation and
Analysis (2011).
Figure 1: Proposed Metro Sports Facility site with investigation phases (Image source: ECan GIS)
North Research centres, clinics and offices associated with the Christchurch Central Hospital
2.3.1 Groundwater
Groundwater was initially assessed to not be a sensitive receptor with regard to the potential for petroleum
hydrocarbon contamination based on the following:
Groundwater abstraction both within the site and across the wider area is taken from deeper confined
aquifers.
The aquifer is not artesian.
The shallow water table is less than 10 m bgl.
The intrusive investigations have identified that the underlying shallow groundwater is as shallow as
approximately 0.3 m below ground level (bgl) (see Section 6.1.2 for more detail). To be considered a
sensitive aquifer, the area needs to be used for abstraction purposes or within 100 m of surface water2,
therefore is not considered to be a sensitive receptor. The soil results have also been compared against the
protection of groundwater assessment criteria to assess the potential impacts on groundwater (Section 6).
The geological map of Christchurch (IGNS, 1992) indicates the site is underlain by Holocene (<10,000
years) Springston Formation, which overlies the late Pleistocene (~70,000 years) Riccarton Gravels.
The Springston Formation consists of river channel and overbank sediments which comprise poorly
graded greywacke gravels, sands and silt and is up to 20 m thick. The Riccarton Gravel is the
uppermost confined gravel aquifer that underlies Christchurch and comprises a brown poorly graded
greywacke gravel <100 mm in size. This unit is water bearing with artesian water levels historically
measured at up to 1 m above ground in places around Christchurch (Brown and Weeber, 1992).
Beca also carried out an initial geotechnical assessment3 for the MSF area in March 2014. The assessment
found that the geology at the site was consistent with Christchurch geological conditions as described in the
36 Saint Asaph Street PSI. The investigations also indicated that the groundwater table varied between 1 m
and 2 m below ground level and groundwater flow was assessed to be towards the east.
2
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand
(Revised 2011), Minstry for the Environment.
3
Geotechnical Factual Report Metro Sports Facility, March 2014. Prepared for CERA by Beca.
Property file information supplied by CCC contained evidence of potentially contaminating activities at ten
properties. In addition to the USTs and chemical storage identified in the ECan files, the property information
indicated land use for motor vehicle workshops, boiler activities, a dangerous goods stores (DGS) and
electrical substations.
The historical aerial images reviewed have shown that the MSF site transformed, from primarily residential in
the1940s, to entirely commercial/industrial prior to the September 2010 earthquake. Factory buildings in the
block bounded by Moorhouse Avenue and Horatio Street have undergone several building layouts since
1946, and the Canterbury Brewery has grown over time to encompass most of the block at the corner of
Saint Asaph Street. No direct evidence of potentially contaminating activities is visible in the photographs.
The desk study conducted by Beca (2012) for the Canterbury Brewery site at 36 Saint Asaph Street
identified a number of areas at the property with contamination potential. These included the former site of
the boiler house, USTs, storage of hazardous chemicals and trade waste sumps. The testing investigations
later conducted by Beca (2013) and PDP (2013) confirmed that diesel had leaked from one of the USTs
however contamination concentrations were below relevant assessment criteria for protection of human
health and the environment.
The site walkover was restricted as many buildings within the site area were still in use. Where demolition
had taken place Beca staff were able to assess the ground condition. However in those instances the soil
was often covered by imported gravels or demolition rubble, such as at 36 Saint Asaph Street and on the
corner of Moorhouse Avenue and Antigua Street. Exterior fibre sheeting construction was noted when
observed for existing buildings and was later confirmed to contain asbestos by T&T.
3.2.1 Stage 1 Contamination Desk Study: Lion Canterbury Brewery Christchurch (Beca, February
2012)
The report summarises the comments of a representative of Canterbury Brewery, who advised that the site
was swamp land until 1854 when it was first developed into a brewery. The property was owned by Crown
Breweries until 1923 when it was transferred to New Zealand Breweries.
A site visit was conducted for the investigation during which the manhole covers of two USTs were sighted. It
is reported that they were installed in the late 1970s, and that one contained petrol and the other diesel until
they were emptied and backfilled in the 1980s. Drums and containers of sulphuric acid, ammonia, grease
and lubricant were also observed. The Beca staff member was told that an engine house and main greasing
area also exist which are reported as likely to have used hazardous substances. It is also recorded that three
transformers are situated at the property however no PCB-containing oil has been used there.
The report identifies the activities and areas of the trade waste sumps, USTs, surrounding properties with a
history of fuel or solvent use, and the former boiler house as potentially contaminated areas of concern.
3.2.3 Site Inspection for the Removal of Two Underground Storage Tanks at the Former Canterbury
Brewery Site, 36 St Asaph Street, Christchurch (PDP, July 2013)
Petroleum Solutions Limited (PSL) engaged PDP to report on the soil sampling results following the removal
of two USTs at the Canterbury Brewery site. 21 soil samples were collected in and around the tank pit and
removed fuel lines. Testing detected TPH in the eastern portion of the tank pit, identified as diesel
contamination. A sample taken beneath the removed pipework adjacent to the tank pit exceeded the all
pathways criteria for human health protection, however PDP then assessed the single result against a route-
specific criterion, which it did not exceed. PDP reported an acceptably low risk to ecological receptors also.
Current and former USTs at several Activity A17 Storage tanks or drums Total petroleum hydrocarbons (TPH)
properties including: for fuel, chemicals and liquid waste Polycyclic aromatic hydrocarbons
(PAH)
36 St Asaph Street Metals including arsenic, cadmium,
181 Antigua Street chromium, copper, lead, mercury,
165-167 Antigua Street nickel, zinc
169 Antigua Street
101-103 Moorhouse Avenue (Fuel
tank only noted, may not have been
UST)
Former boilers also noted at:
36 St Asaph Street
181 Anitgua Street
101-103 Moorhouse Avenue
Motor vehicle workshop or sales and Activity F4 Motor vehicle workshops Metals including arsenic, cadmium,
chromium, copper, lead, mercury,
servicing at:
nickel, zinc
15 Horatio Street Total petroleum hydrocarbons (TPH)
107-109 Moorhouse Avenue Semi Volatile Organic Compounds
181 Antigua Street (SVOC)
117 Moorhouse Avenue
Spray painting booth at: Activity A17 Storage tanks or drums Metals including arsenic, cadmium,
chromium, copper, lead, mercury,
17-19 Horatio Street for fuel, chemicals and liquid waste
nickel, zinc
18 Stewart Street
Semi Volatile Organic Compounds
(SVOC)
Electrical substations at: Activity B4 Power stations, Polychlorinated Biphenyls (PCBs)
substations or switchyards Total petroleum hydrocarbons (TPH)
11 Horatio Street
Metals including arsenic, copper,
36 St Asaph Street
lead, mercury
Several electrical transformers at 36 Activity B2 Electrical transformers Polychlorinated Biphenyls (PCBs)
St Asaph Street Total petroleum hydrocarbons (TPH)
Metals including copper, lead,
mercury
Former dangerous goods store at: Activity A17 Storage tanks or drums Metals including arsenic, cadmium,
chromium, copper, lead, mercury,
36 St Asaph Street for fuel, chemicals and liquid waste
nickel, zinc
30 Horatio Street
Semi Volatile Organic Compounds
(SVOC)
Internal roads potentially coal tar Activity I Any other land that has Metals including arsenic, cadmium,
chromium, copper, lead, mercury,
used in the construction been subject to the intentional or
nickel, zinc
accidental release of hazardous Semi Volatile Organic Compounds
Soil samples were collected directly by hand from excavated materials in the centre of the excavator
bucket/placed at the side of the auger pit. A clean pair of nitrile gloves was worn for each sample to prevent
cross-contamination. Samples were placed in laboratory supplied plastic or glass jars as appropriate and
chilled prior to dispatch to R J Hill Laboratories Ltd (Hill Laboratories).
The soil profile was logged for each location and the logs are provided in Appendix B and site photographs
are attached in Appendix C.
Field sampling and relevant sampling management procedures were undertaken in general accordance with
the MfE Contaminated Land Management Guidelines No.5 Site Investigation and Analysis (2011).
Resource Management (National Environment Standard for Assessing and Managing Contaminants in
Soil to Protect Human Health) Regulations 2011. Soil Contaminant Standards for Commercial/industrial
outdoor worker (unpaved) land use scenario.
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand
(MfE, 1999). Values applicable to commercial land use and the protection of groundwater have been
used, where necessary.
Regional Screening Levels, US Environmental Protection Agency (USEPA, 2012). Values applicable to
industrial land use.
Background concentration of selected trace elements in Canterbury soils (ECan, 2006) and Background
concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils (ECan, 2007).
Below the hardfill layer, soil conditions as part of Phase 1 investigations, cobbles were present (0.5- 1 m
thickness) and overlying silts. Construction waste including concrete, brick, rebar and rubbish was
encountered at locations TP104, TP106, TP107, TP108, TP109 and TP115 predominantly in the upper 0.5
m.
Phase 2 and 3 investigations encountered a thin layer of older fill material was noted at most locations below
the hardfill layer and comprised a dark brown silt with some brick, ceramic and steel fragments. Soils below
the older fill layer generally comprised natural silts and sands with fibrous roots and wood. Test pit logs are
attached in Appendix B and site photographs are in Appendix C.
Phase 4 investigations encountered a thin surficial layer of hardfill material to up to 0.5 m bgl. This was
typically followed by natural sandy silt and silty sand layers to approximately 1.5 m bgl. Deeper than 1.5 m
was generally natural sandy silt or fine sand. Timber fragments were encountered in TP401 and TP402, with
a log located at 2.3 m in TP402.
6.1.2 Groundwater
Standing water was encountered a various depths during the Phase 1 investigations. In some test pits
(notably TP105, TP117 and TP119) a water level of 0.3 m bgl was struck. Significant groundwater flows into
test pits made excavation difficult and at times prevented deeper excavations.
Water seeped into six test pits in Phase 2 investigations at approximately 1.4-1.7 m depths and into five test
pits in Phase 3 investigations at approximately 1.8-2.6 m depths. Only a small volume of water entered the
test pits, therefore may not be sufficient to suggest a permanent shallow groundwater level.
The Phase 1 works were undertaken during a time of recently high rainfall and saturated ground conditions.
Phase 4 investigations followed a long period of dry weather in Christchurch, followed by rainfall on the day
and night prior to the investigation. Standing water was encountered in the central northern areas of
sampling of Phase 4. Ground water was not encountered in nine number of the pits (TP412 was excavated
to 2.8 m bgl with no groundwater ingress observed), however where it was encountered groundwater ranged
from 1 m bgl to 2.3 m bgl.
6.2.1 Metals
A total of 231 soil samples were analysed for metals. Table 3 below summarises the maximum
concentrations encountered and the number of exceedances in relation to the range of assessment criteria.
Sample locations with metal concentrations above background are fairly evenly spread across the site. The
elevated metal concentrations were noted in both shallow and deeper samples tested.
Beca 2013 investigations for the Lion Brewery site also had concentrations of arsenic and chromium above
background, but below human health criteria for commercial land use.
Beca and PDP investigations in 2013 also indicated that concentrations of TPH were detected. One sample
from the PDP investigation exceeded the assessment criteria that cover all pathways as the route for
exposure for human health. The concentration for the C10 C14 band was recorded at 2,700 mg/kg where
the all pathways criterion is 1,500 mg/kg. This one sample was higher than all other Beca samples. The soil
sample result was reassessed by PDP against a route-specific criterion (indoor and outdoor inhalation for
commercial land use, dermal contact and ingestion for the protection of maintenance workers and inhalation
for excavation workers). The concentration was below the route-specific human health criteria and all other
Two samples were above the human health soil contaminant standards for commercial use (criterion 35
mg/kg), both were sampled from a layer containing old fill material. These included:
Due to the laboratory detection limit, all samples have technical exceedances above the background
concentration.
The environmental assessment criteria is based on selected PAH compounds. The following exceedances of
the environmental criteria are:
Napthalene four exceedances with maximum of 26 mg/kg where the environmental criteria is
dependent on the soil type and is 1.9 mg/kg for sand and 0.28 mg/kg for sandy silt. These were located at
TP108 S1, TP329 S1, TP332 S2 and TP337 S1.
Phenanthranene two exceedances of environmental criteria (50mg/kg) located at TP329 S1 and TP332
S2. The maximum concentration recorded was 108 mg/kg.
Pyrene two exceedances of environmental criteria (100 mg/kg) located at TP329 S1 and TP332 S2.
The maximum concentration recorded was 178 mg/kg.
Six of the duplicate pairs had RPDs greater than 50%. Four of the duplicate pairs were taken from fill
material and is indicative of the variable nature of the soil. One duplicate pair was sampled from a deeper silt
layer that included organic material. This duplicate pair had low concentrations of copper that were variable
and is also indicative of the variable nature of underlying natural material.
The analytical results therefore provide an indication of the variability of the fill material and should be taken
into account when assessing any fill material onsite.
There is currently limited risk to human health, due toa total of six exceedances of commercial land use
criteria, including:
All samples exceeding the human health SCS, with the exception of TP409, came from fill layers and/or
HAIL sites, which are the likely cause of the contamination observed and can be managed with a
Contaminated Soils Management Plan (CSMP).
TP409 0.5 has been assessed as a hotspot of lead contamination and soils will require removal and
management using a CSMP.
For samples not including TP409 0.5, due to soil contaminant concentrations exceeding the SCS for human
health and disposal criteria for Burwood landfill a 95% Upper Confidence Limit (UCL) of the mean was
calculated for each of the analytes (Appendix F, summarised in Table 4). As MSF is a large site, containing
numerous areas (populations) of sample analysis with multiple samples in each, typically analysis with 95%
UCL would not be used for the site as a whole. However, given that earthworks and disposal of soils is
assumed to be undertaken at a similar time for the site, soils from different site areas may become mixed
and analysis using 95% UCL is considered appropriate for human health and disposal criteria (TP409 lead
concentrations were excluded from the calculation).
This analysis must be considered when MSF design and construction plans are finalised as the end use
activity and the floor covering (e.g. asphalt, concrete, grass etc.) may necessitate remediation or removal of
soils with elevated contaminant levels, to protect human health and/or the environment.
The results showed that the 95% Chebyshev UCL of heavy metals and B(a)P eq. were below the
commercial and recreational land use soil contaminant standards(summarised in the Table 4).
The 95% UCL for each analyte (excluding lead at TP409) does not exceed the relevant SCS criteria, and are
therefore considered to on aggregate be within these criteria based on the assumed construction and
Analyte 95% UCL (mg/kg) Commercial SCS (mg/kg) Recreation SCS (disposal to
Burwood Landfill) (mg/kg
Arsenic 10.15 70 80
Cadmium 0.284 1,300 400
Chromium 19.09 6,300 2,700
Copper 390.3 >10,000 >10,000
Lead 395.7 3,300 880
Mercury 0.649 4,200 1,800
Nickel 16.36 20,000 50
Zinc 275.1 310,000 360
B(a)P eq. 15.9 35 40
Overall, the recorded soil contaminant concentrations will not prohibit the proposed development of the site.
8.1 Consents
Land covered:
(7) The piece of land is a piece of land that is described by 1 of the following:
(a) an activity or industry described in the HAIL is being undertaken on it;
(b) an activity or industry described in the HAIL has been undertaken on it;
(c) it is more likely than not that an activity or industry described in the HAIL is being or has been
undertaken on it.
The following HAIL activities have been identified for this site:
Activity A17 Storage tanks or drums for fuel, chemicals and liquid waste
Activity B2 Electrical transformers
Activity B4 Power stations, substations or switchyards
Activity F4 Motor vehicle workshops
Activity I Any other land that has been subject to the intentional or accidental release of hazardous
substance in sufficient quantity that it could be a risk to human health or the environment.
The NESCS applies to certain activities taking place on HAIL land. The development plans for the site are
yet to be finalised, however the following activities are likely to be triggered for this site:
Soil disturbance
Fuel tank removal
Subdivision
Change in land use
Soil Disturbance
Under Regulation 8(3) of the NESCS, soil disturbance of up to 25 m3 per 500 m2 and disposal of up to 5 m3
per 500 m2 is allowed as a Permitted Activity. For this site approximately 38,041 m2 has been identified as
HAIL activities present onsite. The total volume of soil disturbance is therefore 1,925 m3, of which 385 m3
can be disposed of offsite, as a Permitted Activity. This is based on CCCs interpretation of the piece of land
and that CCC do not apply a pro-rata approach per 500 m2 of the piece of land in determining permitted soil
disturbance volumes under the NESCS. The proposed works are yet to be confirmed, however with the
development of a swimming pool it is highly likely that excavations will exceed these permitted activity
volume thresholds. Each of the HAIL areas would need to be considered on its own piece of land size and
the activities proposed for that area considered for the permitted activity provisions to be applied. Therefore
The activity is undertaken in accordance with Guidelines for Assessing and Managing Petroleum
Hydrocarbon Contaminated Sites in New Zealand;
The territorial authority is notified, between 1 week and 1 month prior to the removal;
Soil must be disposed at a facility authorised to receive that soil;
Duration must not exceed 2 months;
Results of investigation must be provided to the territorial authority within three months.
A PSI must exist and state that it is highly unlikely that there will be a risk to human health resulting from
the subdivision or change in land use;
Report is to be accompanied by a relevant site plan;
Consent authority must be provided with a copy of the above.
The PSI was unable to state that it is highly unlikely that there will be a risk to human health for the site to be
used for the Metro Sports Facility and therefore will not be a permitted activity. Soil concentrations for the site
and taking into account the 95% UCL indicate that the site is within the proposed commercial land use
criteria and therefore is likely to be a controlled activity under the NESCS.
A copy of this report must be provided to ECan to meet the permitted activity requirements under Rule 5.185
for the use of land for a site investigation to assess concentrations of hazardous substances that may be
present in the soil.
Based on the results of the soil investigation, the material onsite is considered to be within the soil
concentrations that are accepted at Burwood Landfill, assuming that earthworks and soils disposal for the
MSF site are undertaken at a similar time.
The managed fill option in Canterbury is currently Burwood Landfill, with acceptance criteria equal to
recreational land use soil contaminant standards. An appropriate waste manifest applications will need to be
made to CCC.
Where material with concentrations exceeding recreational and commercial land use criteria is to be
removed offsite, the soil will not meet managed fill acceptance criteria. The likely alternative in Canterbury is
disposal to Kate Valley Landfill, however acceptance criteria is based on the Toxicity Characteristic Leaching
Procedure (TCLP) test, rather than total concentrations as used to determine human health effects.
Any asbestos contaminated material cannot be disposed to managed fill and currently Kate Valley Landfill is
the only facility able to accept asbestos containing materials in Canterbury. Please refer to the Tonkin &
Taylor Ltd asbestos assessment report for further comment.
Remedial action is required in the form of limited soil removal of soils at TP409 as this is considered a lead
hotspot. Validation sampling will be required in this area, together with landfill acceptance testing (TCLP).
Activity A17 Storage tanks or drums for fuel, chemicals and liquid waste
Activity B2 Electrical transformers
Activity B4 Power stations, substations or switchyards
Activity F4 Motor vehicle workshops
Activity I Any other land that has been subject to the intentional or accidental release of hazardous
substance in sufficient quantity that it could be a risk to human health or the environment.
This investigation was therefore undertaken to assess the level of contamination present onsite for
contaminants associated with the storage of chemicals, substations and workshops, and also for the fill
material identified during excavations for soil sampling.
The investigation identified five locations out of 101 that exceeded the human health soil contaminant
standards for either arsenic, lead or benzo(a)pyrene equivalent for commercial land use. One sample
location (TP409) is considered a lead hotspot and remediation is required in this area. The source of this
sample has not been confirmed but it is completely inconsistent with the remaining site distribution of lead. A
95% upper confidence limit was calculated for the analytes (not including TP409 for lead) and the results
were below the commercial land use soil contaminant standards. It is therefore considered with 95%
confidence that (with the exception of TP409) the aggregate soil contamination status for the overall site is
within the commercial land use soil contaminant standards. While gross contamination was not identified
across most of the site, many areas were above background concentrations and adopted environmental
criteria for metals and some hydrocarbons and volatile compounds. This analysis is based on the
assumption that excavation and disposal works across the site are undertaken at the same time, leading to
mixing of site-wide soils.
Remedial action is required in the form of limited soil removal of soils at TP409 as this is considered a lead
hotspot. Validation sampling will be required in this area, together with landfill acceptance testing (TCLP).The
consenting assessment in this report was made with consideration of the site in a typical regulatory context
without evaluation of the Designation controls and any other special CERA/tkaro frameworks. It is
anticipated that the below planning considerations will require review by the planners responsible for the
wider MSF consenting.
While the final design parameters of the development are yet to be confirmed, the volume of material that is
to be excavated from the site is assumed to be undertaken at the same time and is likely to exceed the
permitted activity volume thresholds. It is highly likely that resource consent will be required under the
NESCS for soil disturbance. There are also some underground storage tanks that may be onsite, and if
these have resulted in gross contamination, it is unlikely that the removal of the tanks will meet the permitted
activity requirements. Resource consent to remove any potential tanks could be obtained as a precaution
with the soil disturbance application.
Resource consent will also need to be obtained for the construction of the development under the ECan
proposed Land and Water Regional Plan for the discharge of contaminants onto or into land from a
contaminated site in circumstances where those contaminants may enter water. The contaminant
concentrations onsite are above background and adopted environmental criteria, therefore cannot meet the
permitted activity requirements. This report will need to be provided to ECan to meet the permitted activity
requirements for the use of land for a site investigation.
The exposure pathway assessment completed for the soil investigation identified potentially complete
exposure pathways in relation to human health. These could be mitigated and managed through the
implementation of a Contaminated Soils Management Plan, which will likely form part of resource consent
conditions for soil disturbance.
The material onsite generally meets the definition of managed fill and may be disposed to an appropriate
facility (currently Burwood Landfill, operated by CCC). Further analysis of soils that do not meet the managed
fill acceptance criteria (such as soils potentially removed from TP409) will require TCLP analysis to
determine acceptance to Kate Valley Landfill. There are also restrictions with regards to asbestos material
being disposed to managed fill, please refer to the Tonkin & Taylor Ltd asbestos assessment report for
further detail.
Internal roads (Balfour Terrace and Horatio Street) are currently (at the time of writing) active carriageways.
If access is available, investigation and assessment of the internal roads should also be undertaken to
assess materials for disposal or alternately this testing may be deferred to construction.
This report is confidential and is prepared solely for the Client. Beca accepts no liability to any other person
for their use of or reliance on this report, and any such use or reliance will be solely at their own risk.
In preparing this report Beca has relied on key information including information held by Environment
Canterbury and Christchurch City Council.
This report contains information obtained by inspection, sampling, testing or other means of investigation.
Unless specifically stated otherwise in this report, Beca has relied on the accuracy, completeness, currency
and sufficiency of all information provided to it by, or on behalf of, the Client or any third party, including the
information listed above, and has not independently verified the information provided. Beca accepts no
responsibility for errors or omissions in, or the currency or sufficiency of, the information provided. Publicly
available records are frequently inaccurate or incomplete.
The contents of this report are based upon our understanding and interpretation of current legislation and
guidelines (Standards) as consulting professionals, and should not be construed as legal opinions or
advice. Unless special arrangements are made, this report will not be updated to take account of
subsequent changes to any such Standards.
This report should be read in full, having regard to all stated assumptions, limitations and disclaimers.
Site Plans
Legend
Site boundary
HAIL Category A
Storage location
HAIL Category B
HAIL Category F
HAIL Category I
Previous investigations
Dangerous
Goods Store
Fuel tank
002
Drawing Plotted: 26 Sep 2011 4:30 p.m.
TP402
TP404 TP337
TP228
TP401 TP336
TP227 TP222
TP223
TP224 TP403
TP105 TP120 TP335
TP110 TP115
TP226 TP225
TP405
TP333
TP104 TP334
TP114 TP221
TP109 TP119 TP126 TP220 TP332 TP331
TP406
TP103 TP407
TP125 TP329
TP408 TP330
TP108
TP113 TP118 TP320 TP321
TP124 TP326 TP328
TP102 TP107
TP325
TP112 TP123 TP327
TP319 TP324
TP117
TP409 TP322
TP318 TP323
TP111 TP122 TP412
TP410
TP106
TP317
TP116 TP411 TP413
TP101 BH341 TP121
BH340 TP316
TP315
TP312 TP313
BH339
TP414 TP415 TP416
TP314
BH338
TP311 TP310
TP309
TP308
TP302
TP208 TP206 Legend
TP301
TP307 Phase 1 Sample Locations
TP207 TP205
TP303 Phase 2 Sample Locations
TP306
TP304
TP203 TP204 Phase 3 Sample Locations
TP305
TP213
TP215
Phase 4 Sample Locations
TP214 TP209
TP202 TP201 TP-- Test Pit
TP212
TP216 BH-- Borehole
Concentrations above
commercial SCS
This map contains data derived in part or wholly from sources other than Beca, and
therefore, no representations or warranties are made by Beca as to the accuracy or
completeness of this information.
Map intended for distribution as a PDF document. Scale may be incorrect when printed
PDFTENDER
FOR ONLY
No. DRAWING2.DWG
NO CONSTRUCTION
NOT FOR DWG FILE
Drawing Originator: Original Design BRW 06/16 Approved For Client: Project: Title: Discipline
Scale (A1)
Drawn BRW 06/16
Construction* INVESTIGATION LOCATIONS CONTAMINATED LAND
BLUEBEAM
Dsg Verifier OTAKARO LIMITED METRO SPORTS FACILITY CONTAMINATED LAND ASSESSMENT
Document
Reduced Drawing No. Rev.
Scale (A3) Dwg Check Date
No. Revision By Chk Appd Date * Refer to Revision 1 for Original Signature
001 A
DO NOT SCALE IF IN DOUBT ASK.
Appendix B
Soil Logs
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded fine to coarse gravelly rounded COBBLES, some fine sand, trace silt;
dark grey; moist; non plastic.
S1
0.5 0.5
1.0 1.0
S2
1.5 1.5
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
0.5 0.5
1.0 1.0
M SILT, trace fine sand; orange brown mottled grey; moist; non plastic.
S2
1.5 1.5
2.0 2.0
M Fine to coarse sandy SILT; grey mottled orange; moist; non plastic.
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
0.5 0.5
D SILT, minor brick fragments; black mottled orange; dry; non plastic.
D SILT, trace fine to coarse sand; orange brown mottled grey; dry; non plastic.
1.0 1.0
S2
1.5 1.5
2.0 2.0
M Becoming moist
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
0.5 M SILT, some refuse; grey mottled black and orange; moist; non plastic. Refuse: clay pipe, brick 0.5
fragments, broken glass and coal.
S1
D SILT, trace fine to coarse sand; orange brown mottled grey; dry; non plastic.
1.0 1.0
S2
1.5 1.5
2.0 2.0
M Becoming moist.
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, minor brick fragments,
trace silt; dark grey; moist; non plastic.
S Becoming saturated.
24/7/14
S1
0.5 0.5
1.0 1.0
1.5 1.5
2.0 2.0
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
M non plastic.
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
0.5 0.5
D CONCRETE
1.0 1.0
M SILT, trace fine to coarse sand; greyish black; moist; non plastic.
S2
1.5 1.5
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
0.5 0.5
1.0 1.0
SILT, some brick fragments and ash; grey mottled orange and black; moist; non plastic. Ash
leaves charcoal smear and has a hydrocarbon odour.
S2
1.5 1.5
D SILT, minor fine to coarse sand; grey mottled orange; dry; non plastic; hydrocarbon odour.
S3
2.0 2.0
S4
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
M SILT, some brick fragments and ash-type material; grey mottled orange and black; moist;
0.5 hydrocarbon odour. 0.5
1.0 1.0
D SILT, trace fine to coarse sand; orange brown mottled grey; dry; non plastic.
S2
1.5 1.5
2.0 2.0
M Becoming moist
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey; dry;
non plastic.
S1
0.5 0.5
1.0 1.0
S2
1.5 1.5
2.0 2.0
S3
END OF LOG @ 2.6 m
3.0 3.0
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, minor construction waste
(rebar, concrete, brick), trace silt; dark grey; moist; non plastic
S1
0.5 0.5
1.0 1.0
S2
1.5 1.5
2.0 2.0
S3
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
M non plastic.
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
0.5 0.5
D SILT, minor fine to coarse sand; black; dry; non plastic; strong organic odour.
1.0 1.0
M Sandy SILT; bluish grey; moist; non plastic; strong organic odour.
M SILT, some fine to coarse sand; orange brown mottled grey; moist; non plastic; faint organic
odour.
S2
1.5 1.5
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
M non plastic.
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
0.5 0.5
SILT; dark grey; moist; non plastic.
1.0 1.0
S2
1.5 1.5
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
M SILT, some fine to coarse sand, minor fine to coarse gravel; moist; non plastic.
0.5 0.5
1.0 1.0
S2
1.5 1.5
W SILT, minor fine to coarse sand; orange brown mottled grey; wet; non plastic.
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
non plastic.
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, minor concrete blocks,
trace silt; dark grey; moist; non plastic.
0.5 0.5
S1
Excavtor bucket broke clay pipe containing water. Free phase hydrocarbons were observed on
the water.
S SILT, some fine to coarse sand; dark brown; saturated; non plastic.
1.0 1.0
S2
S SILT, some fine to coarse sand; dark greyish black; saturated; non plastic; hydrocarbon odour.
1.5 1.5
2.0 2.0
S4 S3
S Fine to coarse sandy SILT; orange brown mottled grey; saturated; non plastic.
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
M non plastic.
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, minor plastic bags and
bricks, trace silt; dark grey; moist; non plastic.
S1
D SILT; orange brown mottled grey; dry; non plastic.
0.5 0.5
1.0 1.0
S Becoming saturated.
S2
Becomes grey mottled orange.
1.5 1.5
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
M non plastic.
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
0.5 0.5
1.0 1.0
S2
1.5 1.5
W SILT, some fine to coarse sand; orange brown mottled grey; wet; non plastic.
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
D non plastic.
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey; dry;
non plastic.
S Becomes saturated.
S1
0.5 0.5
1.0 1.0
S2
W Sandy SILT; grey mottled orange; wet; non plastic.
1.5 1.5
2.0 2.0
S3
2.5 2.5
3.0 3.0
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
M non plastic.
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
M SILT, some fine to coarse sand; dark greyish black; moist; non plastic.
0.5 0.5
1.0 1.0
S2
1.5 1.5
2.0 2.0
Becoming grey.
S3
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
M non plastic.
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
W SILT, some fine to coarse sand, minor clay; dark grey; wet; low plasticity.
0.5 0.5
1.0 1.0
S2
1.5 1.5
S SILT, some fine to coarse sand; dark grey; saturated; non plastic.
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
non plastic.
S1
0.5 0.5
W SILT, trace fine to coarse sand; bluish grey; wet; non plastic.
1.0 1.0
S2
1.5 1.5
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
M non plastic.
Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
W SILT, some fine to coarse sand, minor clay; orange brown; wet; low plasticity.
0.5 0.5
1.0 1.0
S2
Fine to coarse sandy SILT, grey mottled orange; wet; non plastic. Organics: fibrous.
1.5 1.5
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
0.5 0.5
1.0 1.0
W Fine to coarse sandy SILT; greyish brown; wet; non plastic.
S2
1.5 1.5
2.0 2.0
S3
S Fine to coarse SAND, some silt; dark grey mottled orange brown; saturated; non plastic.
2.5 2.5
3.0 3.0
END OF LOG @ 2.4 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
0.5 0.5
W Fine to coarse sandy SILT; dark grey mottled orange; wet; non plastic.
1.0 1.0
S2
1.5 1.5
2.0 2.0
W Fine to coarse SAND, some silt; bluish grey; wet; non plastic.
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse angular to sub angular GRAVEL, minor fine to coarse sand; light grey; moist;
W non plastic.
SILT, minor fine to coarse sand, orange brown mottled grey; wet; non plastic.
S1
Becoming grey
0.5 0.5
1.0 1.0
S2
1.5 1.5
Slow inflow of water to testpit
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
0.5 0.5
M SILT, minor fine to coarse sand; bluish grey; moist; non plastic.
1.0 1.0
S2
1.5 1.5
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse rounded gravelly rounded COBBLES, some fine sand, trace silt; dark grey;
moist; non plastic.
S1
M SILT, some fine to coarse sand, minor plastic and wire; dark grey; moist; non plastic; strong
0.5 organic odour. 0.5
W SILT, some fine to coarse sand; bluish grey; wet; non plastic.
1.0 1.0
S2
1.5 1.5
2.0 2.0
S3
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
3.5 3.5
TEST_PIT P:\539\5394066\ENV\DSI\GINT\LOGS.GPJ BECA.GDT 22/8/14
4.0 4.0
4.5 4.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Cobbley fine to coarse angular to rounded GRAVEL, minor silt; light grey; dry; non plastic
D Silty fine to coarse SAND, trace cobbles; dark brown mottled light brown and dark grey; dry; non
plastic
S1
0.5 0.5
S2
1.0 1.0
M Becoming moist
1.5 1.5
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Cobbley fine to coarse angular to rounded GRAVEL, minor silt; light grey; dry; non plastic
M Silty fine to coarse SAND, trace cobbles, trace coarse rounded gravel; dark bluish grey; moist;
non plastic
S1
0.5 0.5
S2
1.0 1.0
1.5 1.5
S3
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Cobbley fine- to coarse angular to rounded GRAVEL, minor silt; light grey; dry; non plastic
M Fine sandy SILT, trace clay, trace cobbles, trace refuse material; dark bluish grey mottled light
grey; moist; low plasticity; refuse: bricks and metal fragments
S1
0.5 0.5
S2
1.0 1.0
M Silty fine-coarse SAND; dark bluish grey mottled bown; moist; non-plastic
1.5 1.5
S3
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Cobbley fine to coarse angular to rounded GRAVEL, minor silt; light grey; dry; non plastic
M Fine sandy SILT, minor fine-coarse gravel, trace refuse material; dark grey; moist; non plastic;
refuse: bricks, concrete pipe, timber, nails, glass
S1
0.5 0.5
M Fine sandy SILT, trace coarse gravel; dark grey mottled light and dark brown; moist; non plastic
1.0 1.0
Soil becoming light brown mottled dark brown
S2
W SILT, minor fine sand, trace clay, trace cobbles; brown mottled grey; wet; low plasticity
1.5 1.5
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Cobbley fine to coarse angular to rounded GRAVEL, minor silt; light grey; dry; non plastic
M Fine sandy SILT, minor fine to coarse gravel, trace clay; grey mottled brown; moist; low
plasticity
S1
0.5 0.5
M No gravel
1.0 1.0
S2
1.5 1.5
S3
END OF LOG @ 1.7 m
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Cobbley fine to coarse angular to rounded GRAVEL, minor silt; light grey; dry; non plastic
M Silty fine SAND, trace clay, trace refuse material; brown mottled bluish grey; moist; low plasticity;
S1
refuse: clay piping, glass, bricks and wire
0.5 0.5
1.0 1.0
S2
M Fine sandy SILT, minor fine to coarse gravel; bluish grey mottled brown; moist; non plastic
1.5 1.5
S3
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Cobbley fine to coarse angular to rounded GRAVEL, minor silt; light grey; dry; non plastic
M SILT, minor clay, trace cobbles; bluish grey mottled light grey; moist; low plasticity
S1
0.5 0.5
1.0 1.0
S2
W Fine to coarse SAND; grey mottled brown; wet; non plastic
1.5 1.5
S3
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Fine to coarse GRAVEL, minor silt, trace cobbles; light grey; dry; non plastic
D Silty fine SAND; brown mottled dark grey; dry; non plastic
S1
0.5 0.5
1.0 1.0
S2
M Fine to coarse SAND, minor silt, trace clay; light brown mottled grey; moist; low plasticity
1.5 1.5
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Fine to coarse GRAVEL, minor silt, trace cobbles; light grey; dry; non plastic
S1
0.5 0.5
D Fine sandy SILT, trace cobbles; grey mottled brown; dry; non plastic
1.0 1.0
S2
M Fine sandy SILT, trace cobbles, trace clay; grey; moist; low plasticity; very compact layer
M Fine sandy SILT, minor fine-coarse gravel; dark bluish grey mottled brown; moist; non-plastic
1.5 1.5
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
S3
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Fine to coarse GRAVEL, minor silt, trace cobbles; light grey; dry; non plastic
M Silty fine SAND, minor fine to coarse gravel, trace clay; dark brown mottled light brown and dark
S1
grey; moist; low plasticity
0.5 0.5
1.0 1.0
S2
1.5 1.5
W Fine sandy SILT, minor clay; grey mottled brown; wet; low plasticity
S3
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Fine to coarse GRAVEL, minor silt, trace cobbles; light grey; dry; non plastic
M Fine sandy SILT, minor clay, trace fine to coarse gravel; grey mottled brown; moist; low
S1
plasticity
0.5 0.5
1.0 1.0
S2
M Silty fine to medium SAND; grey mottled brown; moist; non plastic
1.5 1.5
S3
END OF LOG @ 1.7 m
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Fine to coarse GRAVEL, minor silt, trace cobbles; light grey; dry; non plastic
M SILT, minor fine sand, minor clay, minor fine to coarse gravel, trace cobbles; dark grey mottled
brown; moist; low plasticity
S1
0.5 0.5
M Clayey SILT, minor fine sand; dark to light grey mottled brown; moist; low plasticity
1.0 1.0
S2
1.5 1.5
S3
END OF LOG @ 1.7 m
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
D Fine to coarse GRAVEL, minor silt, trace cobbles; light grey; dry; non plastic
M Fine sandy SILT, minor fine to coarse gravels; dark grey; moist; non plastic
S1
0.5 0.5
M Silty fine to coarse SAND; grey mottled brown; moist; non plastic
1.0 1.0
S2
1.5 1.5
W SILT, some fine sand, minor clay; wet; low plasticity
Groundwater seepage
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse GRAVEL, minor silt, trace cobbles; light brown; moist; non plastic
M Fine to coarse GRAVEL, some cobbles, minor silt; light grey; moist; non plastic
S1
0.5 0.5
M Clayey SILT, minor organics, trace cobbles, trace coarse gravel; very dark brown; moist; non
plastic; organics: roots and branches
S2
W SILT, minor clay, trace organics; light grey mottled light brown; wet; low plasticity; organics:
roots and branches
1.0 1.0
1.5 1.5
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse GRAVEL, minor silt, trace cobbles; light brown; moist; non plastic
0.5 0.5
M Fine sandy SILT, minor fine to coarse gravel, minor organics, trace cobbles; grey mottled dark
S1
brown; moist; non plastic; organics: roots and branches
1.0 1.0
S2
1.5 1.5
M Clayey SILT, minor fine to coarse gravel, trace organics; grey; moist; low plasticity; organics:
roots and branches
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
S3
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse GRAVEL, minor silt, trace cobbles; light brown; moist; non plastic
0.5 0.5
Groundwater seepage
M Fine sandy SILT, some fine to coarse gravel, minor clay, trace organics, trace cobbles, trace
S1
boulders; grey mottled dark brown; moist; low plasticity; organics: roots and branches
1.0 1.0
Groundwater seepage
1.5 1.5
S2
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse GRAVEL, minor silt, trace cobbles; light brown; moist; non plastic
0.5 0.5
M Cobbley fine to coarse SAND, some fine to coarse gravel, minor silt; light grey mottled dark
S1
grey; moist; non plastic
1.0 1.0
1.5 1.5
Groundwater seepage
M CLAY, minor silt, minor organics, trace cobbles; grey; moist; high plasticity; organics: roots and
S2
branches
2.0 2.0
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse GRAVEL, minor cobbles, minor fine to coarse sand, minor silt; grey; moist; non
plastic
S1
Some cobbles; becomes dark grey
0.5 0.5
M Silty CLAY, trace organics, trace cobbles; dark grey; moist; high plasticity; organics: roots and
branches
1.0 1.0
1.5 1.5
2.0 2.0
S2
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse GRAVEL, minor cobbles, minor fine to coarse sand, minor silt; grey; moist; non
plastic
S1
M SILT, trace clay, trace cobbles; very dark grey; moist; non plastic
0.5 0.5
S2
M CLAY, minor silt, minor cobbles, minor large gravel, trace organics; grey; moist; high plasticity;
organics: roots and branches
1.0 1.0
1.5 1.5
S3
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse GRAVEL, minor cobbles, minor fine to coarse sand, minor silt; grey; moist; non
plastic
0.5 0.5
M Fine sandy SILT, minor cobbles, trace clay, trace refuse; dark grey mottled brown; moist; low
plasticity; Refuse: bricks and clay piping
1.0 1.0
S1
1.5 1.5
M CLAY, minor silt, minor cobbles, minor coarse gravel, trace organics; grey; moist; high plasticity;
organics: roots and branches
S2
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse GRAVEL, minor cobbles, minor fine to coarse sand, minor silt; grey; moist; non
plastic
0.5 0.5
M CLAY, minor medium sand, minor silt, minor cobbles, minor coarse gravel, minor organics;
S1
grey; moist; high plasticity; organics: roots and branches
1.0 1.0
1.5 1.5
2.0 2.0
S2
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
M Fine to coarse GRAVEL, minor cobbles, minor fine to coarse sand, minor silt, trace refuse; grey;
moist; non plastic; refuse: bricks and clay piping
S1
M Fine sandy SILT, trace clay, trace organics; very dark grey; moist; low plasticity; organics: roots
0.5 0.5
S2
1.0 1.0
M CLAY, minor medium sand, minor silt, minor cobbles, minor coarse gravel, minor organics;
grey; moist; high plasticity; organics: roots and branches
1.5 1.5
S3
2.0 2.0
END OF LOG @ 2 m
TEST_PIT P:\539\5394066\ENV\DSI\GINT\PHASE 2\LOGS.GPJ BECA.GDT 18/11/14
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL; grey; dry. Organics: Rootlets. Contained demolition waste - bricks, concrete,
ceramics, glass, minor charcoal.
TP301 S1 0.5
0.5 0.5
1.0 1.0
TP301 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP301 S3 2.5
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Gravelly SAND; dark grey orange, mottled; dry. Contained demolition waste - glass, ceramis,
coal fragments.
TP302 S1 0.5
0.5 0.5
SAND; brown; dry.
1.0 1.0
TP302 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP302 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL; grey; dry. Contained crushed demolition waste - brick, concrete, underlain by
geotextile.
TP303 S1 0.5
0.5 0.5
1.0 1.0
Silty SAND; bluish grey; moist.
TP303 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
SILT, some fine sand; bluish grey; moist.
TP303 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
COBBLES; Hardfill with topsoil - gravel, crushed demolition material, some plastic and concrete.
GRAVEL; Hardfill with topsoil - crushed demolition material, some plastic and concrete.
0.5 0.5
TP304 S1 0.6
SAND, some silt; brown; moist.
1.0 1.0
1.5 1.5
TP304 S2 1.8
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP304 S3 2.5
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
SILT, trace sand; dark brown; dry, low plasticity. Some charcoal.
TP305 S1 0.5
0.5 0.5
1.0 1.0
1.5 1.5
TP305 S2 1.7
SILT; bluish grey; wet, high plasticity.
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP305 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP306 S1 0.5
0.5 0.5
Silty SAND; bluish grey mottled orange; moist, non plastic.
1.0 1.0
TP306 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP306 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP307 S1 0.5
0.5 0.5
1.0 1.0
SILT, some sand; bluish grey mottled orange; moist, low plasticity.
TP307 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP307 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
Hardfill - soft steel, ceramics. North wall only: dark-stained fill.
TP308 S1 0.6
TP308 S2 0.8
1.0 1.0
SAND; greyish blue mottled orange; moist, non plastic.
TP308 S3 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP308 S4 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP309 S1 0.5
0.5 0.5
Silty SAND; brown mottled orange; dry, non plastic.
1.0 1.0
TP309 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
2.5 2.5
TP309 S3 2.6
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP310 S1 0.5
0.5 0.5
SAND; brownish grey; dry, non plastic.
1.0 1.0
SILT, some sand; bluish grey mottled brown; moist, high plasticity. Organics: Fibrous,
TP310 S2 1.5
carbonaceous.
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP311 S1 0.5
0.5 0.5
Silty SAND; bluish grey; moist, non plastic.
TP311 S2 0.8
SAND; bluish grey; moist, non plastic.
1.0 1.0
1.5 1.5
TP311 S3 1.6
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP311 S4 2.5
2.5 2.5
SAND; bluish grey; moist, low plasticity. Organics: Fibrous, carbonaceous.
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP312 S1 0.5
SILT; grey mottled orange; dry, non plastic.
0.5 0.5
1.0 1.0
1.5 1.5
TP312 S2 1.6
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
SAND; grey mottled brown; moist, low plasticity. Organics: Fibrous, carbonaceous.
2.0 2.0
2.5 2.5
TP312 S3 2.6
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP313 S1 0.5
0.5 0.5
SAND; bluish grey; moist, non plastic. Dark silt, crueshed brick in SW corner at 0.5 m - 0.8 m.
1.0 1.0
TP313 S2 1.5
1.5 1.5
SILT; grey; moist, non plastic. Organics: Fibrous, carbonaceous.
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
SILT; dark brown; moist, non plastic. Some waste - brick fragments, old spanner.
TP314 S1 0.5
0.5 0.5
SAND; bluish grey; moist, non plastic.
1.0 1.0
SILT, some sand; bluish grey; wet, low plasticity. Organics: Fibrous, carbonaceous.
1.5 1.5
TP314 S2 1.7
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP314 S3 2.5
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP315 S1 0.5
0.5 0.5
SAND; bluish grey mottled orange; moist, non plastic.
1.5 1.5
TP315 S2 1.6
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL, minor cobbles; brown; moist, non plastic. minor crushed concrete.
TP316 S1 0.5
0.5 0.5
1.0 1.0
TP316 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP316 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL; brown; moist, non plastic. Some hardfill - crushed concrete.
TP317 S1 0.5
0.5 0.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
TP317 S2 2.0
2.0 2.0
2.5 2.5
TP317 S3 2.7
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL, some cobbles; brown; moist, non plastic. Some hard fill - crushed concrete.
TP318 S1 0.5
0.5 0.5
SAND; bluish grey; moist, non plastic.
1.0 1.0
1.5 1.5
TP318 S2 1.7
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL, some cobbles; brownish grey; dry, non plastic. Some hardfill - crushed
concrete.
TP319 S1 0.5
0.5 0.5
SILT; dark brown; moist, non plastic.
1.0 1.0
TP319 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Brown; dry, non plastic. Hardfill (bricks, glass, timber) with some sand and topsoil.
SILT; dark brown; dry, non plastic. Some hardfill - ceramic tiles, bricks.
TP320 S1 0.5
0.5 0.5
1.0 1.0
TP320 S2 1.5
1.5 1.5
2.0 2.0
TP320 S3 2.5
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL; dark brown; moist, non plastic. Hardfill - bricks, ceramics.
TP321 S1 0.5
0.5 0.5
1.0 1.0
TP321 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP321 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Gravelly COBBLES, some sand; brown; dry, non plastic. Trace hardfill - concrete.
TP322 S1 0.45
Sandy SILT; brown; dry, low plasticity.
0.5 0.5
SILT; grey; moist, high plasticity. Organics: Fibrous, rootlets and amorphous
material.
1.0 1.0
TP322 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP322 S3 2.5
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Silty SAND, some gravel; dark brown; dry, non plastic. Minor fill - plastics.
TP323 S1 0.5
0.5 0.5
1.0 1.0
TP323 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
2.5 2.5
TP323 S3 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Silty sandy GRAVEL; brown; dry, non plastic. rootlets. Some crushed concrete.
TP324 S1 0.45
SILT; dark brownish black; dry, non plastic. Some hardfill - ceramics, brick fragments.
0.5 0.5
SAND; grey; moist, low plasticity. Organics: Fibrous, carbonaceous.
1.0 1.0
TP324 S2 1.5
1.5 1.5
SILT; grey; moist, high plasticity. Organics: Fibrous, carbonaceous.
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP324 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL, some cobbles; brown; moist, non plastic. Asphalt surface.
TP325 S1 0.5
0.5 0.5
SAND; grey; moist, non plastic.
1.0 1.0
SILT; grey; moist, low plasticity.
TP325 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP325 S3 2.5
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL, some cobbles; brown; dry, non plastic. Asphalt surface, some brick.
TP326 S1 0.5
0.5 0.5
SAND; grey; moist, non plastic.
TP326 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP326 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP327 S1 0.5
SILT; dark brownish black; some bluish grey sand present.
0.5 0.5
SAND; grey.
1.0 1.0
SILT; grey; Organics: Fibrous, carbonaceous.
TP327 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
2.5 2.5
TP327 S3 2.6
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL, some cobbles; brown; dry, non plastic. Sealed asphalt surface.
TP328 S1 0.5
SILT; grey mottled orange; dry, non plastic.
0.5 0.5
SILT, some fine sand; grey; moist, non plastic. Organics: Fibrous, carbonaceous.
1.0 1.0
1.5 1.5
TP328 S2 1.7
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
2.5 2.5
TP328 S3 2.6
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP329 S1 0.4
0.5 0.5
1.0 1.0
TP329 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
2.5 2.5
TP329 S3 2.7
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Dry, non plastic. Crushed demolition waste - concrete, asbestos containing material.
SILT; brown; moist, non plastic. Some fill with brick fragments.
TP330 S1 0.45
SAND; grey; moist, non plastic.
0.5 0.5
SILT; grey; moist, high plasticity. Organics: Fibrous, carbonaceous. Water entry at 1.7 m.
1.0 1.0
1.5 1.5
TP330 S2 1.6
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP330 S3 2.5
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Dry, non plastic. rootlets. Crushed demolition waste - brick, asbestos containing material.
TP331 S1 0.5
0.5 0.5
1.0 1.0
SILT; grey; moist, high plasticity. Organics: Fibrous, carbonaceous.
TP331 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP331 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL; brown; dry, non plastic. Crushed demolition waste - brisk, concrete, asbestos
containing material.
S2 1.6S1 0.5
0.5 0.5
Silty GRAVEL; dark brown; dry, non plastic.
TP332TP332
SAND; grey; moist, non plastic.
1.0 1.0
SILT; grey; moist, low plasticity. Organics: Fibrous, carbonaceous.
TP332 S3 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP332 S4 2.5
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP333 S1 0.5
0.5 0.5
SAND; grey; moist, non plastic.
1.0 1.0
SILT; grey; moist, high plasticity. Organics: Fibrous, rootlets and amorphous
material.
TP333 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP333 S3 2.5
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP334 S1 0.5
0.5 0.5
SAND; bluish grey; dry, non plastic.
SILT; bluish grey; moist, low plasticity. Organics: Fibrous, rootlets and amorphous
material.
1.0 1.0
TP334 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP334 S3 2.5
2.5 2.5
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL; brown; dry, non plastic. Chipseal surface with hardfill.
SILT; dark brown; moist, non plastic. Some fill - coal, brick fragments.
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP335 S3 2.5
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL; grey; dry, non plastic. Some fill - brick, ceramics.
TP336 S1 0.5
0.5 0.5
Sandy GRAVEL; dark brown; dry, non plastic.
1.0 1.0
TP336 S2 1.5
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
Silty fine SAND; grey; moist, low plasticity. Organics: Fibrous, carbonaceous.
TP336 S3 2.5
2.5 2.5
END OF LOG @ 2.5 m
3.0 3.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Silty GRAVEL; brown; dry, non plastic. Organics: Amorphous, carbonaceous. Some old fill -
brick, coal, timber fragments. MEdium-strong hydrocarbon odour.
TP337 S1 0.45
Sandy SILT; grey; moist, low plasticity.
0.5 0.5
1.0 1.0
TP337 S2 1.5
1.5 1.5
2.0 2.0
TP337 S3 2.5
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
TP338 S1 1.4
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP338 S2 2.4
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
TP339 S1 0.4
SILT; grey mottled orange; dry, low plasticity.
0.5 0.5
1.0 1.0
TP338 S2 1.3
1.5 1.5
SILT; grey; moist, low plasticity. Organics: Fibrous, carbonaceous.
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP338 S3 2.5
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL; grey; dry, non plastic. Hardfill - demolition fill, crushed concrete.
TP340 S1 0.4
0.5 0.5
GRAVEL, some cobbles; grey; dry, non plastic. Demolition fill.
TP340 S2 1.0
1.0 1.0
SILT; bluish grey; moist, low plasticity. Slight hydrocarbon odour.
2.0 2.0
SILT; grey mottled orange; moist, high plasticity. Organics: Fibrous, carbonaceous.
TP340 S3 2.4
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
Sandy GRAVEL, some silt; brown; dry, non plastic. Demolition fill - crushed concrete, asphalt,
brick fragments.
0.5 0.5
TP341 S1 0.6
1.0 1.0
Soil core loss.
TP341 S2 1.5
1.5 1.5
SILT; grey mottled orange; moist, high plasticity. Organics: Fibrous, carbonaceous.
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 3\GINT\METRO PHASE 3 SOIL LOGS.GPJ BECA.GDT 31/3/15
2.0 2.0
TP341 S3 2.4
2.5 2.5
3.0 3.0
END OF LOG @ 3 m
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
17/05/2016
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
1.5 1.5
17/05/2016
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
17/05/2016
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
M Fine sandy SILT, grey, non-plastic
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
W Medium-fine silty SAND, grey, non-plastic
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
M Fine sandy SILT, grey, slightly plastic
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
1.5 1.5
17/05/16
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
17/05/2016
2.0 2.0
END OF LOG @ 2 m
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
2.0 2.0
END OF LOG @ 2 m
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
M Fine sandy SILT, grey, slightly plastic
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
M Fine sandy SILT, grey mottled orange, non-plastic
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
M Silty fine SAND, grey to dark-grey, slightly plastic
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
END OF LOG @ 2 m
2.5 2.5
GEOLOGICAL UNIT
GRAPHIC LOG
WATER LEVEL
DEPTH (m)
SAMPLES
USCS
Scala
SV (kPa)
0.5 0.5
M Fine sandy SILT, grey, non-plastic
1.0 1.0
1.5 1.5
TEST_PIT P:\539\5394066\ENV\DSI\PHASE 4\SOIL LOGS\METRO SPORT FACILITY PHASE 4.GPJ BECA.GDT 14/6/16
2.0 2.0
2.5 2.5
Site Photographs
Phase 1
Photograph 12: TP 320 dark fill material with brick and ceramic
fragments, underlying top hardfill layer.
Photograph 11: TP308 hardfill and cobbles underlain by geotextile
then sands. Fill material noted in north wall only including steel and
ceramic fragments
Photograph 17: TP402 showing fin sandy silts from approximately 0.5 m
bgl
Photograph 18: TP405 showing fill layer typical of the site, leading to
natural ands and silts at greater depths
Chain of Custody
Documentation
Samples
Sample Types
Waters E Effluent G Geothermal Pot1 Potable Water (LAS/EU) Pot2 Potable Water (NZDWS)
GW Ground Water L Leachate Audit Monitoring Pot3 Potable Water (other)
SW Surface Water S Saline Check Monitoring Pool Swimming/Spa Pool
TW Trade Waste
Solids ES Soil SE Sediment SL Sludge PL Plant
Other O O Oil M Miscellaneous FS FS Fish/shellfish/biota BM BM Biological Material
Sample Sample
No. Sample Name Date & Time Type Tests Required
1 14:120:MTP201:S1 3/11/2014 Soil Suite 1
Sample Types
Waters E Effluent G Geothermal Pot1 Potable Water (LAS/EU) Pot2 Potable Water (NZDWS)
GW Ground Water L Leachate Audit Monitoring Pot3 Potable Water (other)
SW Surface Water S Saline Check Monitoring Pool Swimming/Spa Pool
TW Trade Waste
Solids ES Soil SE Sediment SL Sludge PL Plant
Other O O Oil M Miscellaneous FS FS Fish/shellfish/biota BM BM Biological Material
Sample Sample
No. Sample Name Date & Time Type Tests Required
1 14:120:MTP220:S2 4/11/2014 Soil Suite 3
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
38 16:056 TP411 1.9 17-May-2016 Soil GSoil300, PSoil250 Heavy Metals with Mercury, Screen Level
39 16:056 TP413 1.7 18-May-2016 Soil GSoil300, cPSoil Heavy Metals with Mercury, Screen Level
40 16:056 TP414 1.8 18-May-2016 Soil GSoil300, PSoil250 Heavy Metals with Mercury, Screen Level
41 16:056 TP415 1.25 18-May-2016 Soil GSoil300, cPSoil Heavy Metals with Mercury, Screen Level
SUMMARY OF METHODS
The following table(s) gives a brief description of the methods used to conduct the analyses for this job. The detection limits given below are those attainable in a relatively clean matrix.
Detection limits may be higher for individual samples should insufficient sample be available, or if the matrix requires that dilutions be performed during analysis.
Laboratory Results
(1,500) (sand)5
C10 - C14 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 - -
(1,700) (sandy silt)5
NA (sand)5
C15 - C36 < 40 < 40 240 < 40 620 < 40 48 < 40 76 90 - -
NA (sandy silt)5
Total hydrocarbons (C7 - C36) < 70 < 70 240 < 70 620 < 70 < 70 < 70 76 90 - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011).
Module 4, Tier 1 Soil acceptance criteria for Protection of Groundwater and Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used, groundwater depth of 2m.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
NA indicates estimated criterion exceeds 20,000mg/kg.
The following notes indicate the limiting pathway for each criterion: v - Volatilisation, s - Soil Ingestion, d - Dermal, p - Produce, m - Maintenance/Excavation
Brackets denote values exceed threshold likely to correspond to formation of residual separate phase hydrocarbons.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 1
Sample Date 24/07/2014 24/07/2014 24/07/2014 24/07/2014 24/07/2014 24/07/2014 24/07/2014 24/07/2014 24/07/2014 24/07/2014
Test Pit Number MSF TP106 S1 MSF TP002 S1 MSF TP106 S2 MSF TP107 S1 MSF TP107 S2 MSF TP107 S3 MSF TP108 S1 MSF TP108 S2 MSF TP109 S1 MSF TP109 S2 Assessment Criteria
Laboratory Number: 1301384.74 1301384.77 1301384.75 1301384.67 1301384.68 1301384.69 1301384.71 1301384.72 1301384.64 1301384.65
Sample Depth (m) 0.5 0.5 1.5 0.5 1.3 1.7 0.5 1.5 0.5 1.5
Adopted
Soil Type Gravel Gravel Silt Gravel Silt Silt Gravel Silt Gravel Gravel Background Human Health
Environmental
Soil Type used in the Assessment1 Sand Sand Sandy Silt Sand Sandy Silt Sandy Silt Sand Sandy Silt Sand Sand Range Assessment
Criteria
Heavy metals (mg/kg dry weight)
Arsenic 8 14 7 6 11 6 11 6 5 7 5.9 - 16.32 124 70 6
Cadmium 0.26 0.2 < 0.10 < 0.10 < 0.10 < 0.10 0.26 0.13 0.13 0.15 0.07 - 0.212 224 1,300 6
Chromium 18 21 19 46 45 27 15 20 19 24 12.7 - 25.42 874 6,300 6
Copper 25 35 16 13 16 10 20 6 15 21 10.2 - 252 914 >10,000 6
Lead 4,300 7,900 39 280 155 32 160 25 134 107 25.3 - 128.32 6004 3,300 6
Mercury < 0.10 < 0.10 0.12 < 0.10 0.67 < 0.10 0.16 < 0.10 0.68 0.26 0.09 - 0.22 244 4,200 6
Nickel 19 23 18 11 12 17 12 17 13 17 12.3 - 182 504 20,000 7
Zinc 250 2,600 100 113 88 95 158 190 139 230 62.6 - 166.82 3604 310,000 7
BTEX (mg/kg dry weight)
All compounds - - - Below Detection Below Detection - Below Detection Below Detection - - - - -
Polychlorinated Biphenyls (mg/kg dry weight)
Total PCB (Sum of 35 congeners) - - - - - - - - - - - 3606
Semi-Volatile Organic Compounds (SVOC) (mg/kg dry weight)
Polycyclic Aromatic Hydrocarbons
1.9 (sand)5 (190) (sand) 5
Naphthalene - - - < 0.6 < 0.8 - 3.7 < 0.7 - - -
0.28 (sandy silt)5 (210) (sandy silt)5
Phenanthrene - - - 4.4 < 0.8 - 28 < 0.7 - - - 50 4 -
NA (sandy)5
Pyrene - - - 5.6 < 0.8 - 19 < 0.7 - - - 100 4
NA (sandy silt)5
BAP Equivalent (incl. Fluoranthene) - - - 6.3 <1.8 - 10.9 <1.6 - - - - 356
BAP Equivalent (excl. Fluoranthene) - - - 6.4 <1.8 - 11 <1.7 - - 0.9223 - -
Other compounds
Carbazole - - - < 1.2 < 1.5 - 2.5 < 1.4 - - - - -
Dibenzofuran - - - < 1.2 < 1.5 - 4.2 < 1.4 - - - - 1,000 7
All other compounds - - - Below Detection Below Detection - Below Detection Below Detection - - - - -
Total Petroleum Hydrocarbons (mg/kg)
120 (sand)5
C7 - C9 <8 <8 <9 <8 <9 <8 <8 <9 <8 <8 - -
(500) (sandy silt)5
(1,500) (sand)5
C10 - C14 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 25 - -
(1,700) (sandy silt)5
NA (sand)5
C15 - C36 < 40 300 < 40 101 < 40 < 40 450 < 40 110 560 - -
NA (sandy silt)5
Total hydrocarbons (C7 - C36) < 70 300 < 70 101 < 70 < 70 450 < 70 110 580 - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011).
Module 4, Tier 1 Soil acceptance criteria for Protection of Groundwater and Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used, groundwater depth of 2m.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
NA indicates estimated criterion exceeds 20,000mg/kg.
The following notes indicate the limiting pathway for each criterion: v - Volatilisation, s - Soil Ingestion, d - Dermal, p - Produce, m - Maintenance/Excavation
Brackets denote values exceed threshold likely to correspond to formation of residual separate phase hydrocarbons.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 1
Sample Date 24/07/2014 24/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014 21/07/2014 21/07/2014 21/07/2014 21/07/2014
Test Pit Number MSF TP110 S1 MSF TP110 S2 MSF TP111 S1 MSF TP111 S2 MSF TP112 S1 MSF TP112 S2 MSF TP113 S1 MSF TP113 S2 MSF TP114 S1 MSF TP114 S2 Assessment Criteria
Laboratory Number: 1301384.61 1301384.62 1301384.18 1301384.19 1301384.21 1301384.22 1301384.1 1301384.2 1301384.4 1301384.5
Sample Depth (m) 0.5 1.5 0.5 1.5 0.5 1.5 0.5 1.5 0.6 1.5
Adopted
Soil Type Gravel Gravel Silt Gravel Silt Sand Silt Silt Gravel Silt Background Human Health
Environmental
Soil Type used in the Assessment1 Sand Sand Sandy silt Sand Sandy silt Sand Sandy silt Sandy silt Sand Sandy silt Range Assessment
Criteria
Heavy metals (mg/kg dry weight)
Arsenic 7 5 5 7 9 3 9 15 16 3 5.9 - 16.32 124 70 6
Cadmium 0.45 0.12 0.37 < 0.10 0.15 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.07 - 0.212 224 1,300 6
Chromium 18 20 23 16 19 12 19 19 20 15 12.7 - 25.42 874 6,300 6
Copper 15 14 103 14 22 9 12 14 9 11 10.2 - 252 914 >10,000 6
Lead 62 31 630 32 54 12.5 37 22 56 16 25.3 - 128.32 6004 3,300 6
Mercury 0.21 0.12 0.53 < 0.10 0.12 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.09 - 0.22 244 4,200 6
Nickel 14 17 49 15 20 11 14 16 15 13 12.3 - 182 504 20,000 7
Zinc 760 115 310 68 129 44 84 70 140 59 62.6 - 166.82 3604 310,000 7
BTEX (mg/kg dry weight)
All compounds - - - - - - Below Detection Below Detection Below Detection Below Detection - - -
Polychlorinated Biphenyls (mg/kg dry weight)
Total PCB (Sum of 35 congeners) - - - - - - - - - - - - 3606
Semi-Volatile Organic Compounds (SVOC) (mg/kg dry weight)
Polycyclic Aromatic Hydrocarbons
1.9 (sand)5 (190) (sand) 5
Naphthalene - - - - - - - - < 0.7 - -
0.28 (sandy silt)5 (210) (sandy silt)5
Phenanthrene - - - - - - - - < 0.7 - - 50 4 -
NA (sandy)5
Pyrene - - - - - - - - < 0.7 - - 100 4
NA (sandy silt)5
BAP Equivalent (incl. Fluoranthene) - - - - - - - - <1.5 - - - 356
BAP Equivalent (excl. Fluoranthene) - - - - - - - - <1.6 - 0.9223 - -
Other compounds
Carbazole - - - - - - - - < 1.4 - - - -
Dibenzofuran - - - - - - - - < 1.4 - - - 1,000 7
All other compounds - - - - - - - - Below Detection - - - -
Total Petroleum Hydrocarbons (mg/kg)
120 (sand)5
C7 - C9 <8 <8 <8 <8 <9 <9 <9 <9 <9 <9 - -
(500) (sandy silt)5
(1,500) (sand)5
C10 - C14 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 250 - -
(1,700) (sandy silt)5
NA (sand)5
C15 - C36 310 < 40 820 < 40 < 40 < 40 < 40 < 40 < 40 570 - -
NA (sandy silt)5
Total hydrocarbons (C7 - C36) 310 < 70 820 < 70 < 70 < 70 < 70 < 70 < 70 820 - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011).
Module 4, Tier 1 Soil acceptance criteria for Protection of Groundwater and Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used, groundwater depth of 2m.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
NA indicates estimated criterion exceeds 20,000mg/kg.
The following notes indicate the limiting pathway for each criterion: v - Volatilisation, s - Soil Ingestion, d - Dermal, p - Produce, m - Maintenance/Excavation
Brackets denote values exceed threshold likely to correspond to formation of residual separate phase hydrocarbons.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 1
Sample Date 21/07/2014 21/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014 21/07/2014 21/07/2014 23/07/2014 23/07/2014
Test Pit Number MSF TP114 S3 MSF TP114 S4 MSF TP115 S1 MSF TP001 S1 MSF TP115 S2 MSF TP115 S3 MSF TP116 S1 MSF TP116 S2 MSF TP117 S1 MSF TP117 S2 Assessment Criteria
Laboratory Number: 1301384.6 1301384.7 1301384.16 1301384.5 1301384.48 1301384.49 1301384.8 1301384.9 1301384.24 1301384.25
Sample Depth (m) 2.1 2.5 0.5 0.5 1.5 2.5 0.5 1.5 0.3 1.5
Adopted
Soil Type Sandy silt Sandy silt Gravel Gravel Silt Silt Gravel Gravel Gravel Sandy silt Background Human Health
Environmental
Soil Type used in the Assessment1 Sandy silt Sandy silt Sand Sand Sandy silt Sandy silt Sand Sand Sand Sandy silt Range Assessment
Criteria
Heavy metals (mg/kg dry weight)
Arsenic 5 6 6 5 6 12 4 6 4 5 5.9 - 16.32 124 70 6
Cadmium < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.07 - 0.212 224 1,300 6
Chromium 18 16 18 19 15 20 15 16 13 18 12.7 - 25.42 874 6,300 6
Copper 11 15 4 4 9 15 9 11 7 13 10.2 - 252 914 >10,000 6
Lead 22 17.6 46 32 15.4 26 18 20 17.9 23 25.3 - 128.32 6004 3,300 6
Mercury < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.09 - 0.22 244 4,200 6
Nickel 15 13 12 13 12 17 11 14 10 17 12.3 - 182 504 20,000 7
Zinc 73 61 115 111 51 83 47 60 42 75 62.6 - 166.82 3604 310,000 7
BTEX (mg/kg dry weight)
All compounds Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection - - - - - - -
Polychlorinated Biphenyls (mg/kg dry weight)
Total PCB (Sum of 35 congeners) - - - - - - - - - - - - 3606
Semi-Volatile Organic Compounds (SVOC) (mg/kg dry weight)
Polycyclic Aromatic Hydrocarbons
1.9 (sand)5 (190) (sand) 5
Naphthalene - - - - - - - - - - -
0.28 (sandy silt)5 (210) (sandy silt)5
Phenanthrene - - - - - - - - - - - 50 4 -
NA (sandy)5
Pyrene - - - - - - - - - - - 100 4
NA (sandy silt)5
BAP Equivalent (incl. Fluoranthene) - - - - - - - - - - - - 356
BAP Equivalent (excl. Fluoranthene) - - - - - - - - - - 0.9223 - -
Other compounds
Carbazole - - - - - - - - - - - -
Dibenzofuran - - - - - - - - - - - 1,000 7
All other compounds - - - - - - - - - - - - -
Total Petroleum Hydrocarbons (mg/kg)
120 (sand)5
C7 - C9 <9 <9 <8 <8 <9 <9 <8 < 10 <8 <9 - -
(500) (sandy silt)5
(1,500) (sand)5
C10 - C14 69 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 - -
(1,700) (sandy silt)5
NA (sand)5
C15 - C36 260 < 40 < 40 < 40 < 40 < 40 < 40 < 40 < 40 < 40 - -
NA (sandy silt)5
Total hydrocarbons (C7 - C36) 320 < 70 < 70 < 70 < 70 < 70 < 70 < 70 < 70 < 70 - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011).
Module 4, Tier 1 Soil acceptance criteria for Protection of Groundwater and Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used, groundwater depth of 2m.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
NA indicates estimated criterion exceeds 20,000mg/kg.
The following notes indicate the limiting pathway for each criterion: v - Volatilisation, s - Soil Ingestion, d - Dermal, p - Produce, m - Maintenance/Excavation
Brackets denote values exceed threshold likely to correspond to formation of residual separate phase hydrocarbons.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 1
Sample Date 21/07/2014 21/07/2014 21/07/2014 21/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014
Test Pit Number MSF TP118 S1 MSF TP118 S2 MSF TP119 S1 MSF TP119 S2 MSF TP119 S3 MSF TP120 S1 MSF TP120 S2 MSF TP121 S1 MSF TP121 S2 MSF TP122 S1 Assessment Criteria
Laboratory Number: 1301384.11 1301384.12 1301384.14 1301384.15 1301384.17 1301384.45 1301384.46 1301384.27 1301384.28 1301384.3
Sample Depth (m) 0.5 1.5 0.5 1.5 2.5 0.5 1.5 0.5 1.5 0.5
Adopted
Soil Type Silt Silt Silt Silt Silt Silt Silt Silt Sandy silt Gravel Background Human Health
Environmental
Soil Type used in the Assessment1 Sandy silt Sandy silt Sandy silt Sandy silt Sandy silt Sandy silt Sandy silt Sandy silt Sandy silt Sand Range Assessment
Criteria
Heavy metals (mg/kg dry weight)
Arsenic 8 4 6 2 5 23 7 6 7 14 5.9 - 16.32 124 70 6
Cadmium 0.26 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.07 - 0.212 224 1,300 6
Chromium 19 15 21 13 15 18 20 17 20 17 12.7 - 25.42 874 6,300 6
Copper 50 10 10 7 8 11 15 7 14 6 10.2 - 252 914 >10,000 6
Lead 260 15.7 41 13.5 15.2 34 26 17.7 26 19.3 25.3 - 128.32 6004 3,300 6
Mercury 0.75 < 0.10 < 0.10 < 0.10 < 0.10 0.15 < 0.10 < 0.10 < 0.10 < 0.10 0.09 - 0.22 244 4,200 6
Nickel 35 12 16 11 12 12 16 13 17 12 12.3 - 182 504 20,000 7
Zinc 250 54 101 53 53 109 77 63 78 64 62.6 - 166.82 3604 310,000 7
BTEX (mg/kg dry weight)
All compounds - - - - - - - - - - - - -
Polychlorinated Biphenyls (mg/kg dry weight)
Total PCB (Sum of 35 congeners) - - - - - < 0.4 - - - - - - 3606
Semi-Volatile Organic Compounds (SVOC) (mg/kg dry weight)
Polycyclic Aromatic Hydrocarbons
1.9 (sand)5 (190) (sand) 5
Naphthalene - - - - - < 0.7 - - - - -
0.28 (sandy silt)5 (210) (sandy silt)5
Phenanthrene - - - - - < 0.7 - - - - - 50 4 -
NA (sandy)5
Pyrene - - - - - < 0.7 - - - - - 100 4
NA (sandy silt)5
BAP Equivalent (incl. Fluoranthene) - - - - - <1.5 - - - - - - 356
BAP Equivalent (excl. Fluoranthene) - - - - - <1.6 - - - - 0.9223 - -
Other compounds
Carbazole - - - - - < 1.4 - - - - - -
Dibenzofuran - - - - - < 1.4 - - - - - 1,000 7
All other compounds - - - - - Below Detection - - - - - - -
Total Petroleum Hydrocarbons (mg/kg)
120 (sand)5
C7 - C9 <9 <9 <9 <9 <9 <9 <9 <9 <9 <9 - -
(500) (sandy silt)5
(1,500) (sand)5
C10 - C14 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 - -
(1,700) (sandy silt)5
NA (sand)5
C15 - C36 260 < 40 < 40 < 40 < 40 < 40 < 40 < 40 < 40 < 40 - -
NA (sandy silt)5
Total hydrocarbons (C7 - C36) 260 < 70 < 70 < 70 < 70 < 70 < 70 < 70 < 70 < 70 - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011).
Module 4, Tier 1 Soil acceptance criteria for Protection of Groundwater and Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used, groundwater depth of 2m.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
NA indicates estimated criterion exceeds 20,000mg/kg.
The following notes indicate the limiting pathway for each criterion: v - Volatilisation, s - Soil Ingestion, d - Dermal, p - Produce, m - Maintenance/Excavation
Brackets denote values exceed threshold likely to correspond to formation of residual separate phase hydrocarbons.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 1
Sample Date 23/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014 23/07/2014
Test Pit Number MSF TP122 S2 MSF TP123 S1 MSF TP123 S2 MSF TP124 S1 MSF TP124 S2 MSF TP125 S1 MSF TP125 S2 MSF TP126 S1 MSF TP126 S2 MSF TP126 S3 Assessment Criteria
Laboratory Number: 1301384.31 1301384.33 1301384.34 1301384.42 1301384.43 1301384.39 1301384.4 1301384.36 1301384.37 1301384.38
Sample Depth (m) 1.5 0.5 1.5 0.3 1.5 0.5 1.5 0.5 1.5 2.5
Adopted
Soil Type Sandy silt Gravel Sandy silt Silt Silt Gravel Silt Silt Silt Silt Background Human Health
Environmental
Soil Type used in the Assessment1 Sandy silt Sand Sandy silt Sandy silt Sandy silt Sand Sandy silt Sandy silt Sandy silt Sandy silt Range Assessment
Criteria
Heavy metals (mg/kg dry weight)
Arsenic 3 4 9 6 5 3 2 9 3 9 5.9 - 16.32 124 70 6
Cadmium < 0.10 < 0.10 < 0.10 0.33 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.07 - 0.212 224 1,300 6
Chromium 15 13 19 22 20 11 15 19 18 22 12.7 - 25.42 874 6,300 6
Copper 11 7 14 87 15 6 9 22 13 16 10.2 - 252 914 >10,000 6
Lead 22 29 24 650 26 13.3 15.3 89 21 29 25.3 - 128.32 6004 3,300 6
Mercury < 0.10 < 0.10 < 0.10 0.51 < 0.10 < 0.10 < 0.10 0.14 < 0.10 < 0.10 0.09 - 0.22 244 4,200 6
Nickel 12 10 16 35 18 8 13 14 14 19 12.3 - 182 504 20,000 7
Zinc 55 51 79 350 78 34 52 84 69 88 62.6 - 166.82 3604 310,000 7
BTEX (mg/kg dry weight)
All compounds - - - - - - - - - - - - -
Polychlorinated Biphenyls (mg/kg dry weight)
Total PCB (Sum of 35 congeners) - - - - - - - - - - - - 3606
Semi-Volatile Organic Compounds (SVOC) (mg/kg dry weight)
Polycyclic Aromatic Hydrocarbons
1.9 (sand)5 (190) (sand) 5
Naphthalene - - - - - - - - - - -
0.28 (sandy silt)5 (210) (sandy silt)5
Phenanthrene - - - - - - - - - - - 50 4 -
NA (sandy)5
Pyrene - - - - - - - - - - - 100 4
NA (sandy silt)5
BAP Equivalent (incl. Fluoranthene) - - - - - - - - - - - - 356
BAP Equivalent (excl. Fluoranthene) - - - - - - - - - - 0.9223 - -
Other compounds
Carbazole - - - - - - - - - - - -
Dibenzofuran - - - - - - - - - - - 1,000 7
All other compounds - - - - - - - - - - - - -
Total Petroleum Hydrocarbons (mg/kg)
120 (sand)5
C7 - C9 <9 <8 <9 <9 < 10 <9 <9 < 10 < 10 <9 - -
(500) (sandy silt)5
(1,500) (sand)5
C10 - C14 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 - -
(1,700) (sandy silt)5
NA (sand)5
C15 - C36 < 40 < 40 < 40 270 < 40 < 40 < 40 1,060 61 < 40 - -
NA (sandy silt)5
Total hydrocarbons (C7 - C36) < 70 < 70 < 70 270 < 70 < 70 < 70 1,060 < 70 < 70 - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011).
Module 4, Tier 1 Soil acceptance criteria for Protection of Groundwater and Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used, groundwater depth of 2m.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
NA indicates estimated criterion exceeds 20,000mg/kg.
The following notes indicate the limiting pathway for each criterion: v - Volatilisation, s - Soil Ingestion, d - Dermal, p - Produce, m - Maintenance/Excavation
Brackets denote values exceed threshold likely to correspond to formation of residual separate phase hydrocarbons.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 2
Sample Date 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014
Assessment Criteria
Sample Name MTP201 S1 MTP201 S2 MTP202 S1 MTP202 S2 MTP203 S1 MTP203 S2 MTP204 S1 MTP204 S2 MTP205 S1 MTP205 S2
Laboratory Number 1346648.1 1346648.2 1346648.4 1346648.5 1346648.7 1346648.8 1346648.1O 1346648.11 1346648.13 1346648.14
Adopted
Sample Depth (m) 0.45-0.55 0.85-1.0 0.45-0.55 0.7-0.8 0.4-0.5 0.8-1.0 0.4-0.5 1.0-1.1 0.4-0.5 1.0-1.1 Background Human Health
Environmental
Soil Type Silty sand Silty sand Silty sand Silty sand Sandy silt Sandy silt Sandy silt with fill Sandy silt Sandy silt Sandy silt Range Assessment
1 Criteria
Soil Type used in Assessment Sand Sand Sand Sand Sandy silt Sandy silt Sandy silt Sandy silt Sandy silt Sandy silt
Heavy metals (mg/kg)
Arsenic <2 <2 7 2 8 7 9 3 7 4 5.9 - 16.32 124 70 6
Cadmium < 0.10 < 0.10 0.12 < 0.10 0.38 0.2 0.41 < 0.10 0.39 < 0.10 0.07 - 0.212 224 1,300 6
4
Chromium 13 11 16 15 18 16 18 16 18 17 12.7 - 25.42 87 6,300 6
Copper 8 6 19 8 41 23 52 8 93 12 10.2 - 252 914 >10,000 6
Lead 13.8 11 98 16.1 460 330 1,000 30 186 28 25.3 - 128.3
2
6004 3,300
6
Mercury < 0.10 < 0.10 0.21 < 0.10 0.28 0.23 0.91 < 0.10 0.11 < 0.10 0.09 - 0.2 2
244 4,200 6
Nickel 11 11 13 14 15 13 14 12 11 14 12.3 - 18
2
504 20,000
7
4
Zinc 43 39 125 55 320 195 440 79 260 80 62.6 - 166.82 360 310,000 7
BTEX (mg/kg)
All compounds Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection - - -
Semi-Volatile Organic Compounds (SVOC) (mg/kg dry weight)
Polycyclic Aromatic Hydrocarbons
1.9 (sand)5 (190) (sand) 5
Naphthalene < 0.7 < 0.7 < 0.7 < 0.7 < 0.7 < 0.7 < 0.7 < 0.7 < 0.7 < 0.7 -
0.28 (sandy silt)5 (210) (sandy silt)5
Phenanthrene < 0.7 < 0.7 < 0.7 < 0.7 0.9 2.2 < 0.7 < 0.7 0.9 < 0.7 - 50 4 -
NA (sandy)5 NA
Pyrene < 0.7 < 0.7 < 0.7 < 0.7 2.2 3.3 4.8 < 0.7 1 < 0.7 - 100 4
(sandy silt)5
6
BAP Equivalent (incl. Fluoranthene) <1.537 <1.652 <1.652 <1.652 1.712 2.867 5.45 <1.652 1.658 <1.652 - - 35
BAP Equivalent (excl. Fluoranthene) <1.534 <1.649 <1.649 <1.649 1.69 2.836 5.421 <1.649 <1.649 <1.649 0.9223 - -
Other Compounds
Carbazole < 1.3 < 1.4 < 1.4 < 1.4 < 1.3 < 1.4 < 1.4 < 1.4 < 1.4 < 1.4 - - -
Dibenzofuran < 1.3 < 1.4 < 1.4 < 1.4 < 1.3 < 1.4 < 1.4 < 1.4 < 1.4 < 1.4 - - 1,000 7
All other compounds Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection Below Detection - - -
Total Petroleum Hydrocarbons (mg/kg)
5
120 (sand)
C7 - C9 <8 <9 <9 <8 <8 <9 <9 <8 <8 <8 - -
(500) (sandy silt)5
(1,500) (sand)5
C10 - C14 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 - -
(1,700) (sandy silt)5
5
NA (sand)
C15 - C36 < 40 < 40 < 40 < 40 54 57 97 < 40 < 40 < 40 - -
NA (sandy silt)5
Total hydrocarbons (C7 - C36) < 70 < 70 < 70 < 70 < 70 < 70 97 < 70 < 70 < 70 - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011).
Module 4, Tier 1 Soil acceptance criteria for Protection of Groundwater and Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used, groundwater depth of 2m.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
NA indicates estimated criterion exceeds 20,000mg/kg.
The following notes indicate the limiting pathway for each criterion: v - Volatilisation, s - Soil Ingestion, d - Dermal, p - Produce, m - Maintenance/Excavation
Brackets denote values exceed threshold likely to correspond to formation of residual separate phase hydrocarbons.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 2
Sample Date 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014 3/11/2014
Assessment Criteria
Sample Name MTP206 S1 MTP206 S2 MTP208 S1 MTP208 S2 MTP209 S1 MTP209 S2 MTP212 S1 MTP212 S2 MTP213 S1 MTP213 S2
Hills Lab Number 1346648.16 1346648.17 1346648.19 1346648.2O 1346648.22 1346648.23 1346648.25 1346648.26 1346648.28 1346648.29
Adopted
Sample Depth (m) 0.4-0.5 1.0-1.1 0.4-0.5 1.0-1.1 0.4-0.5 1.0-1.1 0.4-0.5 1.0-1.1 0.4-0.5 1.0-1.1 Background Human Health
Environmental
Soil Type Silty sand Silty sand Silt with gravel Silt with gravel Silty sand Silty sand Gravel with silt Sandy silt Silty sand Silty sand Range Assessment
1 Criteria
Soil Type used in Assessment Sand Sand Sandy silt Sandy silt Sand Sand Sandy silt Sandy silt Sand Sand
Heavy metals (mg/kg)
4
Arsenic 6 3 6 4 11 9 7 3 11 7 5.9 - 16.32 12 70 6
Cadmium < 0.10 < 0.10 0.25 < 0.10 0.53 < 0.10 < 0.10 < 0.10 0.13 < 0.10 0.07 - 0.212 224 1,300 6
4
Chromium 19 16 19 16 19 16 18 13 16 14 12.7 - 25.42 87 6,300 6
Copper 18 10 36 14 30 10 12 10 18 8 10.2 - 252 914 >10,000 6
Lead 48 15 200 31 2,700 23 19 12.5 134 16.2 25.3 - 128.3
2
6004 3,300
6
Mercury 0.3 < 0.10 0.11 < 0.10 0.6 < 0.10 < 0.10 < 0.10 0.13 < 0.10 0.09 - 0.2 2
244 4,200 6
Nickel 17 12 15 11 12 14 15 12 13 12 12.3 - 18
2
504 20,000
7
4
Zinc 97 59 260 84 630 66 61 42 128 49 62.6 - 166.82 360 310,000 7
BTEX (mg/kg)
All compounds - - - - - - - - - - - - -
Semi-Volatile Organic Compounds (SVOC) (mg/kg dry weight)
Polycyclic Aromatic Hydrocarbons
1.9 (sand)5 (190) (sand) 5
Naphthalene - - - - - - - - - - -
0.28 (sandy silt)5 (210) (sandy silt)5
Phenanthrene - - - - - - - - - - - 50 4 -
NA (sandy)5
Pyrene - - - - - - - - - - - 100 4
NA (sandy silt)5
6
BAP Equivalent (incl. Fluoranthene) - - - - - - - - - - - - 35
BAP Equivalent (excl. Fluoranthene) - - - - - - - - - - 0.9223 - -
Other Compounds
Carbazole - - - - - - - - - - - - -
Dibenzofuran - - - - - - - - - - - - 1,000 7
All other compounds - - - - - - - - - - - - -
Total Petroleum Hydrocarbons (mg/kg)
5
120 (sand)
C7 - C9 <9 <9 <9 <9 <8 <9 <8 <8 <8 <8 - -
(500) (sandy silt)5
(1,500) (sand)5
C10 - C14 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 - -
(1,700) (sandy silt)5
5
NA (sand)
C15 - C36 < 40 < 40 151 < 40 250 < 40 < 40 < 40 < 40 < 40 - -
NA (sandy silt)5
Total hydrocarbons (C7 - C36) < 70 < 70 151 < 70 250 < 70 < 70 < 70 < 70 < 70 - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011).
Module 4, Tier 1 Soil acceptance criteria for Protection of Groundwater and Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used, groundwater depth of 2m.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
NA indicates estimated criterion exceeds 20,000mg/kg.
The following notes indicate the limiting pathway for each criterion: v - Volatilisation, s - Soil Ingestion, d - Dermal, p - Produce, m - Maintenance/Excavation
Brackets denote values exceed threshold likely to correspond to formation of residual separate phase hydrocarbons.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 2
Sample Date 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014
Assessment Criteria
Sample Name MTP214 S1 MTP214 S2 MTP215 S1 MTP215 S2 MTP216 S1 MTP216 S2 MTP220 S1 MTP220 S2 MTP221 S1 MTP221 S2
Hills Lab Number 1346648.31 1346648.32 1346648.34 1346648.35 1346648.37 1346648.38 1346648.4O 1346648.41 1346648.43 1346648.44
Adopted
Sample Depth (m) 0.4-0.5 1.0-1.1 0.4-0.5 1.0-1.1 0.4-0.5 1.0-1.1 0.6-0.7 0.8-0.9 0.8-0.9 1.1-1.2 Background Human Health
Environmental
Soil Type Sandy silt Sandy silt Silt minor sand Silt minor sand Sandy silt Silty sand Gravel Silt with trace gravel Sandy silt Sandy silt Range Assessment
1 Criteria
Soil Type used in Assessment Sandy silt Sandy silt Sandy silt Sandy silt Sandy silt Sand Sand Sandy silt Sandy silt Sandy silt
Heavy metals (mg/kg)
Arsenic 10 11 12 6 10 6 50 10 8 4 5.9 - 16.32 124 70 6
Cadmium < 0.10 < 0.10 0.78 < 0.10 0.32 < 0.10 0.16 0.13 0.7 < 0.10 0.07 - 0.212 224 1,300 6
4
Chromium 17 15 21 14 20 14 25 19 21 15 12.7 - 25.42 87 6,300 6
Copper 9 11 90 11 38 13 29 15 53 12 10.2 - 252 914 >10,000 6
Lead 34 31 740 18.7 350 14.8 37 30 1,020 49 25.3 - 128.3
2
6004 3,300
6
Mercury < 0.10 < 0.10 0.92 < 0.10 0.27 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.09 - 0.2 2
244 4,200 6
Nickel 13 14 18 12 15 13 26 18 45 14 12.3 - 18
2
504 20,000
7
4
Zinc 120 60 730 68 340 54 200 123 156 77 62.6 - 166.82 360 310,000 7
BTEX (mg/kg)
All compounds - - - - - - Below Detection Below Detection Below Detection Below Detection - - -
Semi-Volatile Organic Compounds (SVOC) (mg/kg dry weight)
Polycyclic Aromatic Hydrocarbons
1.9 (sand)5 (190) (sand) 5
Naphthalene - - - - - - - - - - -
0.28 (sandy silt)5 (210) (sandy silt)5
Phenanthrene - - - - - - - - - - - 50 4 -
NA (sandy)5
Pyrene - - - - - - - - - - - 100 4
NA (sandy silt)5
6
BAP Equivalent (incl. Fluoranthene) - - - - - - - - - - - - 35
BAP Equivalent (excl. Fluoranthene) - - - - - - - - - - 0.9223 - -
Other Compounds
Carbazole - - - - - - - - - - - - -
Dibenzofuran - - - - - - - - - - - - 1,000 7
All other compounds - - - - - - - - - - - - -
Total Petroleum Hydrocarbons (mg/kg)
5
120 (sand)
C7 - C9 <8 <8 <8 <8 <9 <8 < 18 <9 < 11 <9 - -
(500) (sandy silt)5
(1,500) (sand)5
C10 - C14 < 20 < 20 < 20 < 20 < 20 < 20 < 40 < 20 < 30 < 20 - -
(1,700) (sandy silt)5
5
NA (sand)
C15 - C36 < 40 < 40 65 < 40 85 < 40 151 < 40 < 50 < 40 - -
NA (sandy silt)5
Total hydrocarbons (C7 - C36) < 70 < 70 < 70 < 70 85 < 70 151 < 70 < 80 < 70 - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011).
Module 4, Tier 1 Soil acceptance criteria for Protection of Groundwater and Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used, groundwater depth of 2m.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
NA indicates estimated criterion exceeds 20,000mg/kg.
The following notes indicate the limiting pathway for each criterion: v - Volatilisation, s - Soil Ingestion, d - Dermal, p - Produce, m - Maintenance/Excavation
Brackets denote values exceed threshold likely to correspond to formation of residual separate phase hydrocarbons.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 2
Sample Date 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014 4/11/2014
Assessment Criteria
Sample Name MTP222 S1 MTP222 S2 MTP223 S1 MTP223 S2 MTP224 S1 MTP224 S2 MTP225 S1 MTP225 S2 MTP226 S1 MTP226 S2
Hills Lab Number 1346648.46 1346648.47 1346648.48 1346648.49 1346648.5O 1346648.51 1346648.52 1346648.53 1346648.55 1346648.56
Adopted
Sample Depth (m) 0.9-1.0 1.8-1.9 0.5-0.6 1.55-1.65 0.2-0.4 2.0-2.1 0.2-0.3 0.6-0.7 1.0-1.1 1.8-1.9 Background Human Health
Environmental
Soil Type Sandy silt Sandy silt Sand Silty clay Sandy gravel Silty clay Sandy gravel Silt with cobbles and clay Sandy silt Clay minor silt Range Assessment
1 Criteria
Soil Type used in Assessment Sandy silt Sandy silt Sand Silty clay Sand Silty clay Sand Sandy silt Sandy silt Silty clay
Heavy metals (mg/kg)
4
Arsenic 7 4 3 11 6 9 4 11 7 5 5.9 - 16.32 12 70 6
Cadmium < 0.10 < 0.10 < 0.10 0.11 0.14 < 0.10 < 0.10 0.15 0.11 0.3 0.07 - 0.212 224 1,300 6
4
Chromium 20 19 13 21 15 21 13 16 23 17 12.7 - 25.42 87 6,300 6
Copper 13 15 9 16 13 18 10 22 22 49 10.2 - 252 914 >10,000 6
Lead 20 22 15.2 27 34 28 35 76 33 80 25.3 - 128.3
2
6004 3,300
6
Mercury < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.12 < 0.10 0.28 0.09 - 0.2 2
244 4,200 6
Nickel 17 15 11 18 12 20 11 13 21 13 12.3 - 18
2
504 20,000
7
Page 1
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 3
Sample Date 23/03/2015 23/03/2015 23/03/2015 23/03/2015 23/03/2015 23/03/2015 23/03/2015 23/03/2015 23/03/2015 23/03/2015
Assessment Criteria
Sample Name TP306 S1 TP306 S1 TP307 S1 TP307 S2 TP308 S1 TP308 S2 TP308 S3 TP309 S1 TP309 S2 TP004 S1
Hills Lab Number 1402615.16 1402615.17 1402615.19 1402615.2 1402615.22 1402615.23 1402615.24 1402615.26 1402615.27 1402615.29
0.6 - QA/QC of Adopted
Sample Depth (m) 0.5 1.5 0.5 1.5 0.6 0.8 1.5 0.5 1.5 Human Health
TP304 0.6 Background Environmental
Assessment
Soil Type Silty sand Silty sand Silty sand Silt Sandy gravel Sandy gravel Sand Silty sand Silt Gravel Range Criteria
Soil Type used in Assessment1 Sand Sand Sand Sandy silt Sand Sand Sand Sand Sandy silt Sand
Heavy metals (mg/kg)
Arsenic 3 4 4 6 2 42 7 14 8 10 5.9 - 16.3
2
124 70
6
Cadmium < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 2.2 < 0.10 0.72 < 0.10 0.14 0.07 - 0.212 224 1,300 6
2 4 6
Chromium 13 16 17 21 14 39 22 21 20 19 12.7 - 25.4 87 6,300
Copper 7 11 13 16 8 300 17 56 16 13 10.2 - 252
914 >10,000 6
2 4 6
Lead 54 18.5 39 24 17.2 550 26 530 25 79 25.3 - 128.3 600 3,300
2 4
Mercury 0.24 < 0.10 < 0.10 < 0.10 < 0.10 1.37 < 0.10 0.28 < 0.10 0.14 0.09 - 0.2 24 4,200 6
2 4 7
Nickel 9 13 13 18 11 38 18 18 17 12 12.3 - 18 50 20,000
4
Zinc 76 61 76 78 64 1,630 84 550 78 230 62.6 - 166.82 360 310,000 7
BTEX (mg/kg)
0.17 (sand) 5 3 (sand) 5,m
Benzene - - - - - - - - - - -
0.029 (sandy silt) 5 3.6 (sandy silt) 5,v
(39) (sand) 5 (94) (sand) 5,m
Toluene - - - - - - - - - - -
6 (sandy silt) 5 (270) (sandy silt) 5,v
Page 2
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 3
Sample Date 23/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015
Assessment Criteria
Sample Name TP005 S1 TP310 S1 TP310 S2 TP311 S1 TP311 S2 TP311 S3 TP312 S1 TP312 S2 TP313 S1 TP313 S2
Hills Lab Number 1402615.3 1402615.31 1402615.32 1402615.34 1402615.35 1402615.36 1402615.38 1402615.39 1402615.41 1402615.42
0.6 - QA/QC of Adopted
Sample Depth (m) 0.5 1.5 0.5 0.8 1.6 0.5 1.6 0.5 1.5 Background Human Health
TP308 0.6 Environmental
Range Assessment
Soil Type Sandy gravel Sand Silt Silty sand Silt and fill Silt Silt Sand Silt Sand Criteria
1
Soil Type used in Assessment Sand Sand Sandy silt Sand Sandy silt Sandy silt Sandy silt Sand Sandy silt Sand
Heavy metals (mg/kg)
4
Arsenic 3 16 4 9 115 3 2 6 9 6 5.9 - 16.32 12 70 6
Cadmium < 0.10 < 0.10 < 0.10 0.59 2.8 < 0.10 < 0.10 < 0.10 0.15 < 0.10 0.07 - 0.21
2
224 1,300
6
Page 3
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 3
Sample Date 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015
Assessment Criteria
Sample Name TP314 S1 TP314 S2 TP315 S1 TP315 S2 TP316 S1 TP316 S2 TP317 S1 TP317 S2 TP318 S1 TP318 S2
Hills Lab Number 1402615.44 1402615.45 1402615.47 1402615.48 1402615.5 1402615.51 1402615.53 1402615.54 1402615.56 1402615.57
Adopted
Sample Depth (m) 0.5 1.5 0.5 1.5 0.6 1.8 0.5 1.7 0.5 1.7 Background Human Health
Environmental
Range Assessment
Soil Type Sand Silt Sand Silt Sandy gravel Silt Sandy gravel Silt Sand Silt Criteria
1
Soil Type used in Assessment Sand Sandy silt Sand Sandy silt Sand Sandy silt Sand Sandy silt Sand Sandy silt
Heavy metals (mg/kg)
Arsenic 10 8 10 6 4 14 3 6 2 11 5.9 - 16.32 124 70 6
Cadmium 0.15 < 0.10 0.24 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.11 0.07 - 0.21
2
224 1,300
6
Page 4
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 3
Sample Date 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015 26/03/2015 26/03/2015
Assessment Criteria
Sample Name TP319 S1 TP319 S2 TP320 S1 TP320 S2 TP321 S1 TP321 S2 TP007 S1 TP008 S1 TP322 S1 TP322 S2
Hills Lab Number 1402615.59 1402615.6 1402615.62 1402615.63 1402615.65 1402615.66 1402615.68 1402615.69 1402615.99 1402615.1
1.6 - QA/QC 0.5 - QA/QC Adopted
Sample Depth (m) 0.5 1.5 0.5 1.5 0.5 1.5 0.45 1.5 Background Human Health
of TP311 1.6 of TP318 0.5 Environmental
Range Assessment
Soil Type Silt Silt Silt Sand Sandy gravel Silt Silt Sand Sandy silt Silt Criteria
1
Soil Type used in Assessment Sandy silt Sandy silt Sandy silt Sand Sand Sandy silt Sandy silt Sand Sandy silt Sandy silt
Heavy metals (mg/kg)
4
Arsenic 17 13 31 4 25 7 2 <2 3 9 5.9 - 16.32 12 70 6
Cadmium 0.16 < 0.10 0.67 < 0.10 0.27 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.07 - 0.21
2
224 1,300
6
Page 5
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 3
Sample Date 26/03/2015 26/03/2015 26/03/2015 26/03/2015 26/03/2015 26/03/2015 26/03/2015 26/03/2015 26/03/2015 26/03/2015
Assessment Criteria
Sample Name TP323 S1 TP323 S2 TP324 S1 TP324 S2 TP325 S1 TP325 S2 TP326 S1 TP326 S2 TP327 S1 TP327 S2
Hills Lab Number 1402615.102 1402615.103 1402615.105 1402615.106 1402615.108 1402615.109 1402615.111 1402615.112 1402615.114 1402615.115
Adopted
Sample Depth (m) 0.5 1.5 0.45 1.5 0.5 1.5 0.5 1.6 0.5 1.5 Background Human Health
Environmental
Range Assessment
Soil Type Sandy gravel Silt Silt Silt Sand Silt Sand Silt Silt Silt Criteria
1
Soil Type used in Assessment Sand Sandy silt Sandy silt Sandy silt Sand Sandy silt Sand Sandy silt Sandy silt Sandy silt
Heavy metals (mg/kg)
4
Arsenic 4 2 16 5 <2 4 2 7 6 9 5.9 - 16.32 12 70 6
Cadmium < 0.10 < 0.10 1.66 < 0.10 < 0.10 < 0.10 < 0.10 0.11 0.3 0.1 0.07 - 0.21
2
224 1,300
6
Phenanthrene - - 1 - - - - - 3.3 - - 50 4 -
NA (sandy)5 NA
Pyrene - - 2.2 - - - - - 9.9 - - 100 4 5
(sandy silt)
BAP Equivalent (incl. Fluoranthene) - - 2.314 - - - - - 13.106 - - - 356
BAP Equivalent (excl. Fluoranthene) - - 2.293 - - - - - 13.011 - 0.9223 - -
Other Compounds
Carbazole - - < 1.8 - - - - - < 1.6 - - -
Dibenzofuran - - < 1.8 - - - - - < 1.6 - - 1,000 7
All other compounds - - Below Detection - - - - - Below Detection - - - -
Total Petroleum Hydrocarbons (mg/kg)
5
120 (sand)
C7 - C9 <8 - < 11 - <9 - <8 - < 10 - - -
(500) (sandy silt)5
5
(1,500) (sand)
C10 - C14 < 20 - < 30 - < 20 - < 20 - < 20 - - - 5
(1,700) (sandy silt)
5
NA (sand)
C15 - C36 < 40 - 197 - < 40 - < 40 - 240 - - -
NA (sandy silt)5
Total hydrocarbons (C7 - C36) < 70 - 197 - < 70 - < 70 - 240 - - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011).
Module 4, Tier 1 Soil acceptance criteria for Protection of Groundwater and Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used, groundwater depth of 2m.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
NA indicates estimated criterion exceeds 20,000mg/kg.
The following notes indicate the limiting pathway for each criterion: v - Volatilisation, s - Soil Ingestion, d - Dermal, p - Produce, m - Maintenance/Excavation
Brackets denote values exceed threshold likely to correspond to formation of residual separate phase hydrocarbons.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
Page 6
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 3
Sample Date 26/03/2015 26/03/2015 26/03/2015 25/03/2015 25/03/2015 25/03/2015 25/03/2015 25/03/2015 25/03/2015 25/03/2015
Assessment Criteria
Sample Name TP328 S1 TP328 S2 TP010 S1 TP329 S1 TP329 S2 TP330 S1 TP330 S2 TP331 S1 TP331 S2 TP332 S1
Hills Lab Number 1402615.117 1402615.118 1402615.12 1402615.7 1402615.71 1402615.73 1402615.74 1402615.76 1402615.77 1402615.79
0.45 - QA/QC of Adopted
Sample Depth (m) 0.5 1.7 0.4 1.5 0.45 1.6 0.5 1.5 0.5 Background Human Health
TP324 0.45 Environmental
Range Assessment
Soil Type Silt Silt Silt Silt Silt Sand Silt Sand Silt Silty gravel Criteria
1
Soil Type used in Assessment Sandy silt Sandy silt Sandy silt Sandy silt Sandy silt Sand Sandy silt Sand Sandy silt Sand
Heavy metals (mg/kg)
Arsenic 4 10 16 9 4 6 6 3 7 3 5.9 - 16.32 124 70 6
Cadmium < 0.10 0.13 1.1 0.33 < 0.10 0.15 < 0.10 < 0.10 < 0.10 < 0.10 0.07 - 0.21
2
224 1,300
6
Page 7
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 3
Sample Date 25/03/2015 25/03/2015 25/03/2015 25/03/2015 25/03/2015 25/03/2015 25/03/2015 25/03/2015 25/03/2015 25/03/2015
Assessment Criteria
Sample Name TP332 S2 TP332 S3 TP333 S1 TP333 S2 TP334 S1 TP334 S2 TP335 S1 TP335 S2 TP336 S1 TP336 S2
Hills Lab Number 1402615.8 1402615.81 1402615.83 1402615.84 1402615.86 1402615.87 1402615.89 1402615.9 1402615.92 1402615.93
Adopted
Sample Depth (m) 0.6 1.5 0.5 1.5 0.5 1.5 0.45 0.7 0.5 1.5 Background Human Health
Environmental
Range Assessment
Soil Type Silty gravel Silt Sand Silt Sand Silt Silt Sand Sand Silt Criteria
1
Soil Type used in Assessment Sand Sandy silt Sand Sandy silt Sand Sandy silt Sandy silt Sand Sand Sandy silt
Heavy metals (mg/kg)
Arsenic 13 5 12 4 3 10 11 7 6 6 5.9 - 16.32 124 70 6
Cadmium 0.37 < 0.10 0.5 < 0.10 < 0.10 < 0.10 0.41 0.12 < 0.10 < 0.10 0.07 - 0.21
2
224 1,300
6
Page 8
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 3
Sample Date 25/03/2015 25/03/2015 25/03/2015 27/03/2015 27/03/2015 27/03/2015 27/03/2015 27/03/2015 27/03/2015 27/03/2015
Assessment Criteria
Sample Name TP337 S1 TP337 S2 TP009 S1 BH338 S1 BH338 S2 BH339 S1 BH339 S2 BH340 S2 BH340 S3 BH341 S2
Hills Lab Number 1402615.95 1402615.96 1402615.98 1402615.121 1402615.122 1402615.124 1402615.125 1402615.128 1402615.129 1402615.132
1.5 - QA/QC of Adopted Human Health
Sample Depth (m) 0.45 1.5 0.2-0.45 1.4-1.5 0.4 1.3 1.0-1.1 1.5-1.6 1.5-1.6 Background
TP333 1.5 Environmental Assessment
Range
Soil Type Sandy silt Silt Silt Sandy gravel Silt Silt Silt Sandy gravel Silt Silt Criteria
1
Soil Type used in Assessment Sandy silt Sandy silt Sandy silt Sand Sandy silt Sandy silt Sandy silt Sand Sandy silt Sandy silt
Heavy metals (mg/kg)
Arsenic 5 5 4 7 5 4 5 7 5 18 5.9 - 16.32 124 70 6
Cadmium 0.14 < 0.10 < 0.10 0.2 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 < 0.10 0.07 - 0.21
2
224 1,300
6
Page 9
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 4
Sample Date 17/05/2016 17/05/2016 24/03/2015 17/05/2016 17/05/2016 17/05/2016 17/05/2016 17/05/2016 17/05/2016 17/05/2016 17/05/2016 17/05/2016 24/03/2015 17/05/2016
Assessment Criteria
Sample Name TP401 TP401 TP401 TP402 TP402 TP403 TP403 TP404 TP404 TP405 TP405 TP406 TP406 TP406
Sample Reference 16:056 16:056 16:061 16:056 16:056 16:056 16:056 16:056 16:056 16:056 16:056 16:056 16:062 16:056
Sample Depth (m) 0.5 2.3 (QC 2.3) 0.5 2 0.5 2 0.4 1.8 0.6 1.8 0.5 (QC 0.5) 1.8
Adopted
Hills Lab Number 1585990.1 1585990.2 1585990.34 1585990.3 1585990.4 1585990.5 1585990.6 1585990.7 1585990.8 1585990.9 1585990.1 1585990.11 1585990.35 1585990.12 Background Human Health
Environmental
Soil Type Sandy Silt Sandy Silt Silt Sandy Silt Sandy Silt Sandy Silt Sandy Silt Sandy Silt Sandy Silt Sandy Silt Sandy Silt Sandy Silt Sandy gravel Sandy Silt Range Assessment
Criteria
Soil Type used in Assessment 1 Sand Sand Sandy silt Sand Sand Sand Sand Sand Sand Sand Sand Sand Sand Sand
Heavy metals (mg/kg)
Arsenic 6 6 6 6 9 8 8 7 4 6 5 6 7 8 5.9 - 16.32 124 70 5
Cadmium 0.17 0.11 < 0.10 < 0.10 < 0.10 0.56 < 0.10 1.22 0.11 < 0.10 < 0.10 0.13 0.1 0.1 0.07 - 0.212 224 1,300 5
Chromium 16 20 21 18 24 18 20 19 18 19 18 20 18 18 12.7 - 25.42 874 6,300 5
Copper 35 17 16 9 19 131 15 47 14 13 12 21 20 16 10.2 - 252 914 >10,000 5
Lead 510 51 28 32 30 590 28 2,100 46 24 23 73 66 25 25.3 - 128.32 6004 3,300 5
Mercury 0.18 < 0.10 < 0.10 < 0.10 < 0.10 0.61 < 0.10 0.74 < 0.10 < 0.10 < 0.10 < 0.10 0.1 < 0.10 0.09 - 0.22 244 4,200 5
Nickel 12 16 18 12 23 14 21 14 16 15 15 15 13 16 12.3 - 182 504 22,000 6
Zinc 340 95 77 67 100 560 87 1,030 88 80 73 140 148 80 62.6 - 166.82 3604 350,000 6
Total Petroleum Hydrocarbons (mg/kg) Surface Soil
120 (sand)7
C7 - C9 <9 - - <9 - <8 - <8 - < 10 - <9 - - - -
500 (sandy silt)7
6,500 (sand)7
C10 - C14 < 20 - - < 20 - < 20 - < 20 - < 20 - < 20 - - - - 31,000 (sandy
silt)7
NA (sand)7
C15 - C36 120 - - < 40 - 141 - 320 - < 40 - 42 - - - -
NA (sandy silt)7
Total hydrocarbons (C7 - C36) 120 - - < 70 - 141 - 320 - < 70 - < 70 - - - - -
Polycyclic Aromatic Hydrocarbons
Acenaphthene < 0.5 - - < 0.5 - < 0.5 - < 0.5 - < 0.5 - < 0.5 - - - - -
Acenaphthylene < 0.5 - - < 0.5 - < 0.5 - 0.5 - < 0.5 - < 0.5 - - - - -
Anthracene 0.7 - - < 0.5 - < 0.5 - 0.6 - < 0.5 - < 0.5 - - - 32 4 -
Benzo[a]anthracene 3.7 - - < 0.5 - 1.2 - 3.6 - < 0.5 - 1.2 - - - - -
Benzo[a]pyrene (BAP) 3.6 - - < 0.5 - 1.4 - 3.7 - < 0.5 - 1.2 - - - 724 -
Benzo[b]fluoranthene + Benzo[j]fluoranthene 3.5 - - < 0.5 - 1.5 - 3.9 - < 0.5 - 1.2 - - - - -
Benzo[g,h,i]perylene 2.3 - - < 0.5 - 1 - 2.6 - < 0.5 - 0.8 - - - -
Benzo[k]fluoranthene 1.4 - - < 0.5 - 0.6 - 1.4 - < 0.5 - < 0.5 - - - - -
2-Chloronaphthalene < 0.5 - - < 0.5 - < 0.5 - < 0.5 - < 0.5 - < 0.5 - - - - -
Chrysene 3.5 - - < 0.5 - 1.4 - 3.8 - < 0.5 - 1.2 - - - - -
Dibenzo[a,h]anthracene 0.5 - - < 0.5 - < 0.5 - 0.6 - < 0.5 - < 0.5 - - - - -
Fluoranthene 6.4 - - 0.5 - 2.3 - 7.2 - < 0.5 - 2.2 - - - 180 4 -
Fluorene < 0.5 - - < 0.5 - < 0.5 - < 0.5 - < 0.5 - < 0.5 - - - - -
Indeno(1,2,3-c,d)pyrene 2.3 - - < 0.5 - 1 - 2.6 - < 0.5 - 0.8 - - - - -
2-Methylnaphthalene < 0.5 - - < 0.5 - < 0.5 - < 0.5 - < 0.5 - < 0.5 - - - - -
3.7 (sand)7
53 (sand)7
0.62 190 (sand) 7
Naphthalene < 0.5 - - < 0.5 - < 0.5 - < 0.5 - < 0.5 - < 0.5 - - - 16 (sandy
(sandy 210 (sandy silt)7
silt)7
silt)7
Phenanthrene 1.5 - - < 0.5 - 1 - 2.9 - < 0.5 - 0.7 - - - 50 4 -
Pyrene 7.6 - - 0.6 - 2.7 - 8.2 - < 0.5 - 2.6 - - - 100 4 NA (sandy silt)8
BAP Equivalent (incl. Fluoranthene) 5.309 - - 0.608 - 1.867 - 5.56 - <0.605 - 1.829 - - - 353
BAP Equivalent (excl. Fluoranthene) 5.245 - - 0.603 - 1.844 - 5.488 - <0.603 - 1.807 - 0.9223 - -
Other SVOCs
All Below Detection - - - - - - - - - - - - - - - - -
Annotations:
1
The Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand provides a series of guideline values based on specific soil types. The soil type encountered onsite is described in the testpit logs and can vary from the
specific types described in the guidelines. To undertake the assessment the guideline soil type which matches most closely the soils encountered at that location and depth has been selected.
2
Background concentration of selected trace elements in Canterbury soils, ECan, 2006.
3
Background concentration of polycyclic aromatic hydrocarbons in Christchurch urban soils, ECan, 2007.
4
Canadian Soil Quality Guidelines for the Protection of Environmental and Human Health, CCME 1999. Values applicable to 'Commercial' land use have been used.
5
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, Ministry for the Environment (MfE), 1999 (Revised 2011). Module 4, Table 4.11 - Tier 1 Soil acceptance criteria for Commercial / Industrial Landuse - All Pathways. Sand and sandy silt soil types have been used.
6
Resource Management (National Environmental Standards for Assessing and Managing Contaminants in Soil to Protect Human Health) Regulations 2011. Values applicable to 'commercial / industrial outdoor worker' have been used.
7
US EPA Regional Screening Level for Industrial Landuse
8
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New Zealand, MfE 1999. Values applicable to 'maintenance/excavation worker' and sand and sandy silt soil type have been used.
NA indicates estimated criterion exceeds 20,000mg/kg.
Underlining indicates result exceeds background range
Grey shading indicates result exceeds regional discharge assessment criteria
Bold indicates result exceeds human health assessment criteria
SOIL ANALYSIS RESULTS: METRO SPORTS FACILITY PHASE 4
Sample Date 17/05/2016 17/05/2016 23/03/2015 23/03/2015 23/03/2015 23/03/2015 24/03/2015 23/03/2015 23/03/2015 24/03/2015 23/03/2015 24/03/2015 24/03/2015 24/03/2015 24/03/2015
Assessment Criteria
Sample Name TP407 TP407 TP408 TP408 TP409 TP409 TP409 TP410 TP410 TP410 TP411 TP411 TP411 TP412 TP412
Sample Reference 16:056 16:056 16:056 16:056 16:056 16:056 16:063 16:056 16:056 16:064 16:056 16:056 16:065 16:056 16:056
Sample Depth (m) 0.5 1.8 0.5 1.8 0.3 0.5 1.8 0.3 0.5 1.9 0.5 0.6 1.9 0.5 1.8
Hills Lab Number 1585990.13 1585990.14 1585990.15 1585990.16 1585990.17 1585990.18 1585990.36 1585990.19 1585990.2 1585990.37 1585990.21 1585990.22 1585990.38 1585990.23 1585990.24 Background Adopted Human Health
Soil Type Silty Sand Silty Sand Silty Sand Silty Sand Silty Sand Silty Sand Silt Silty Sand Silty Sand Sandy gravel Silty Sand Silty Sand Silt Silty Sand Silty Sand Range Environmental Criteria Assessment
Soil Type used in Assessment 1 Sand Sand Sand Sand Sand Sand Sandy silt Sand Sand Sand Sand Sand Sandy silt Sand Sand
Heavy metals (mg/kg)
Arsenic 5 4 7 <2 5 19 6 4 11 3 6 7 2 3 7 5.9 - 16.32 124 70 5
Cadmium 0.13 < 0.10 0.21 < 0.10 0.26 1.86 < 0.10 0.24 1.25 0.11 0.27 0.36 < 0.10 < 0.10 0.12 0.07 - 0.212 224 1,300 5
Chromium 15 16 17 16 16 24 20 22 34 15 16 16 15 13 19 12.7 - 25.42 874 6,300 5
Copper 14 11 23 10 39 199 16 37 186 13 39 38 12 8 14 10.2 - 252 914 >10,000 5
Lead 59 23 127 21 210 14,600 25 128 1,020 17.2 220 360 152 27 21 25.3 - 128.32 6004 3,300 5
Mercury < 0.10 < 0.10 0.13 < 0.10 0.24 8.1 < 0.10 0.13 13.4 < 0.10 < 0.10 0.14 < 0.10 < 0.10 < 0.10 0.09 - 0.22 244 4,200 5
Nickel 12 14 14 12 12 21 17 20 21 14 15 13 13 10 17 12.3 - 182 504 22,000 6
Zinc 166 66 220 64 250 1,750 79 135 620 127 230 270 151 54 75 62.6 - 166.82 3604 350,000 6
Total Petroleum Hydrocarbons (mg/kg) Surface Soil
120 (sand)7
C7 - C9 <9 - <9 - - - - - <9 - - - - - - - -
500 (sandy silt)7
6,500 (sand)7
C10 - C14 < 20 - < 20 - - - - - < 20 - - - - - - - - 31,000 (sandy
silt)7
NA (sand)7
C15 - C36 < 40 - < 40 - - - - - 93 - - - - - - - -
NA (sandy silt)7
Total hydrocarbons (C7 - C36) < 70 - < 70 - - - - - 93 - - - - - - - - -
Polycyclic Aromatic Hydrocarbons
Acenaphthene < 0.5 - < 0.5 - - - - - - - - - - - - - - -
Acenaphthylene < 0.5 - < 0.5 - - - - - - - - - - - - - - -
Anthracene < 0.5 - < 0.5 - - - - - - - - - - - - - 32 4 -
Benzo[a]anthracene < 0.5 - 0.6 - - - - - - - - - - - - - - -
Benzo[a]pyrene (BAP) < 0.5 - 0.5 - - - - - - - - - - - - - 724 -
Benzo[b]fluoranthene + Benzo[j]fluoranthene < 0.5 - 0.6 - - - - - - - - - - - - - - -
Benzo[g,h,i]perylene < 0.5 - < 0.5 - - - - - - - - - - - - - -
Benzo[k]fluoranthene < 0.5 - < 0.5 - - - - - - - - - - - - - - -
2-Chloronaphthalene < 0.5 - < 0.5 - - - - - - - - - - - - - - -
Chrysene < 0.5 - 0.6 - - - - - - - - - - - - - - -
Dibenzo[a,h]anthracene < 0.5 - < 0.5 - - - - - - - - - - - - - - -
Fluoranthene < 0.5 - 1 - - - - - - - - - - - - - 180 4 -
Fluorene < 0.5 - < 0.5 - - - - - - - - - - - - - - -
Indeno(1,2,3-c,d)pyrene < 0.5 - < 0.5 - - - - - - - - - - - - - - -
2-Methylnaphthalene < 0.5 - < 0.5 - - - - - - - - - - - - - - -
This Laboratory is accredited by International Accreditation New Zealand (IANZ), which represents New Zealand in the International
Laboratory Accreditation Cooperation (ILAC). Through the ILAC Mutual Recognition Arrangement (ILAC-MRA) this accreditation is
internationally recognised.
The tests reported herein have been performed in accordance with the terms of accreditation, with the exception of tests marked *, which
are not accredited.
Sample Type: Soil
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP113 S1 0.5m TP113 S2 1.5m TP114 S1 0.6m TP114 S2 1.5m TP114 S3 2.1m
21-Jul-2014 21-Jul-2014 21-Jul-2014 21-Jul-2014 21-Jul-2014
Lab Number: 1301384.1 1301384.2 1301384.4 1301384.5 1301384.6
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
4,4'-DDE mg/kg dry wt - - < 1.4 - -
4,4'-DDT mg/kg dry wt - - <3 - -
Dieldrin mg/kg dry wt - - < 1.4 - -
Endosulfan I mg/kg dry wt - - <3 - -
Endosulfan II mg/kg dry wt - - <3 - -
Endosulfan sulphate mg/kg dry wt - - <3 - -
Endrin mg/kg dry wt - - <3 - -
Endrin ketone mg/kg dry wt - - <3 - -
Heptachlor mg/kg dry wt - - < 1.4 - -
Heptachlor epoxide mg/kg dry wt - - < 1.4 - -
Hexachlorobenzene mg/kg dry wt - - < 1.4 - -
Polycyclic Aromatic Hydrocarbons in SVOC Soil Samples by GC-MS
Acenaphthene mg/kg dry wt - - < 0.7 - -
Acenaphthylene mg/kg dry wt - - < 0.7 - -
Anthracene mg/kg dry wt - - < 0.7 - -
Benzo[a]anthracene mg/kg dry wt - - < 0.7 - -
Benzo[a]pyrene (BAP) mg/kg dry wt - - < 1.4 - -
Benzo[b]fluoranthene + Benzo[j] mg/kg dry wt - - < 1.4 - -
fluoranthene
Benzo[g,h,i]perylene mg/kg dry wt - - < 1.4 - -
Benzo[k]fluoranthene mg/kg dry wt - - < 1.4 - -
2-Chloronaphthalene mg/kg dry wt - - < 0.7 - -
Chrysene mg/kg dry wt - - < 0.7 - -
Dibenzo[a,h]anthracene mg/kg dry wt - - < 1.4 - -
Fluoranthene mg/kg dry wt - - < 0.7 - -
Fluorene mg/kg dry wt - - < 0.7 - -
Indeno(1,2,3-c,d)pyrene mg/kg dry wt - - < 1.4 - -
2-Methylnaphthalene mg/kg dry wt - - < 0.7 - -
Naphthalene mg/kg dry wt - - < 0.7 - -
Phenanthrene mg/kg dry wt - - < 0.7 - -
Pyrene mg/kg dry wt - - < 0.7 - -
Phenols in SVOC Soil Samples by GC-MS
4-Chloro-3-methylphenol mg/kg dry wt - - <5 - -
2-Chlorophenol mg/kg dry wt - - < 1.4 - -
2,4-Dichlorophenol mg/kg dry wt - - < 1.4 - -
2,4-Dimethylphenol mg/kg dry wt - - <3 - -
3 & 4-Methylphenol (m- + p- mg/kg dry wt - - <3 - -
cresol)
2-Methylphenol (o-Cresol) mg/kg dry wt - - < 1.4 - -
2-Nitrophenol mg/kg dry wt - - <5 - -
Pentachlorophenol (PCP) mg/kg dry wt - - < 30 - -
Phenol mg/kg dry wt - - <3 - -
2,4,5-Trichlorophenol mg/kg dry wt - - <3 - -
2,4,6-Trichlorophenol mg/kg dry wt - - <3 - -
Plasticisers in SVOC Soil Samples by GC-MS
Bis(2-ethylhexyl)phthalate mg/kg dry wt - - <6 - -
Butylbenzylphthalate mg/kg dry wt - - <3 - -
Di(2-ethylhexyl)adipate mg/kg dry wt - - < 1.4 - -
Diethylphthalate mg/kg dry wt - - <3 - -
Dimethylphthalate mg/kg dry wt - - <3 - -
Di-n-butylphthalate mg/kg dry wt - - <3 - -
Di-n-octylphthalate mg/kg dry wt - - <3 - -
Other Halogenated compounds in SVOC Soil Samples by GC-MS
1,2-Dichlorobenzene mg/kg dry wt - - <3 - -
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP114 S4 2.5m TP116 S1 0.5m TP116 S2 1.5m TP118 S1 0.5m TP118 S2 1.5m
21-Jul-2014 21-Jul-2014 21-Jul-2014 21-Jul-2014 21-Jul-2014
Lab Number: 1301384.7 1301384.8 1301384.9 1301384.11 1301384.12
Individual Tests
Dry Matter g/100g as rcvd 77 90 75 84 78
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 6 4 6 8 4
Total Recoverable Cadmium mg/kg dry wt < 0.10 < 0.10 < 0.10 0.26 < 0.10
Total Recoverable Chromium mg/kg dry wt 16 15 16 19 15
Total Recoverable Copper mg/kg dry wt 15 9 11 50 10
Total Recoverable Lead mg/kg dry wt 17.6 18.0 20 260 15.7
Total Recoverable Mercury mg/kg dry wt < 0.10 < 0.10 < 0.10 0.75 < 0.10
Total Recoverable Nickel mg/kg dry wt 13 11 14 35 12
Total Recoverable Zinc mg/kg dry wt 61 47 60 250 54
BTEX in Soil by Headspace GC-MS
Benzene mg/kg dry wt < 0.06 - - - -
Toluene mg/kg dry wt < 0.06 - - - -
Ethylbenzene mg/kg dry wt < 0.06 - - - -
m&p-Xylene mg/kg dry wt < 0.11 - - - -
o-Xylene mg/kg dry wt < 0.06 - - - -
Total Petroleum Hydrocarbons in Soil
C7 - C9 mg/kg dry wt <9 <8 < 10 <9 <9
C10 - C14 mg/kg dry wt < 20 < 20 < 20 < 20 < 20
C15 - C36 mg/kg dry wt < 40 < 40 < 40 260 < 40
Total hydrocarbons (C7 - C36) mg/kg dry wt < 70 < 70 < 70 260 < 70
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP119 S1 0.5m TP119 S2 1.5m TP115 S1 0.5m TP119 S3 2.5m TP111 S1 0.5m
21-Jul-2014 21-Jul-2014 23-Jul-2014 23-Jul-2014 23-Jul-2014
Lab Number: 1301384.14 1301384.15 1301384.16 1301384.17 1301384.18
Individual Tests
Dry Matter g/100g as rcvd 76 77 82 78 86
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 6 2 6 5 5
Total Recoverable Cadmium mg/kg dry wt < 0.10 < 0.10 < 0.10 < 0.10 0.37
Total Recoverable Chromium mg/kg dry wt 21 13 18 15 23
Total Recoverable Copper mg/kg dry wt 10 7 4 8 103
Total Recoverable Lead mg/kg dry wt 41 13.5 46 15.2 630
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP111 S2 1.5m TP112 S1 0.5m TP112 S2 1.5m TP117 S1 0.3m TP117 S2 1.5m
23-Jul-2014 23-Jul-2014 23-Jul-2014 23-Jul-2014 23-Jul-2014
Lab Number: 1301384.19 1301384.21 1301384.22 1301384.24 1301384.25
Individual Tests
Dry Matter g/100g as rcvd 80 73 78 94 78
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 7 9 3 4 5
Total Recoverable Cadmium mg/kg dry wt < 0.10 0.15 < 0.10 < 0.10 < 0.10
Total Recoverable Chromium mg/kg dry wt 16 19 12 13 18
Total Recoverable Copper mg/kg dry wt 14 22 9 7 13
Total Recoverable Lead mg/kg dry wt 32 54 12.5 17.9 23
Total Recoverable Mercury mg/kg dry wt < 0.10 0.12 < 0.10 < 0.10 < 0.10
Total Recoverable Nickel mg/kg dry wt 15 20 11 10 17
Total Recoverable Zinc mg/kg dry wt 68 129 44 42 75
Total Petroleum Hydrocarbons in Soil
C7 - C9 mg/kg dry wt <8 <9 <9 <8 <9
C10 - C14 mg/kg dry wt < 20 < 20 < 20 < 20 < 20
C15 - C36 mg/kg dry wt < 40 < 40 < 40 < 40 < 40
Total hydrocarbons (C7 - C36) mg/kg dry wt < 70 < 70 < 70 < 70 < 70
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP121 S1 0.5m TP121 S2 1.5m TP122 S1 0.5m TP122 S2 1.5m TP123 S1 0.5m
23-Jul-2014 23-Jul-2014 23-Jul-2014 23-Jul-2014 23-Jul-2014
Lab Number: 1301384.27 1301384.28 1301384.30 1301384.31 1301384.33
Individual Tests
Dry Matter g/100g as rcvd 78 76 78 80 91
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 6 7 14 3 4
Total Recoverable Cadmium mg/kg dry wt < 0.10 < 0.10 < 0.10 < 0.10 < 0.10
Total Recoverable Chromium mg/kg dry wt 17 20 17 15 13
Total Recoverable Copper mg/kg dry wt 7 14 6 11 7
Total Recoverable Lead mg/kg dry wt 17.7 26 19.3 22 29
Total Recoverable Mercury mg/kg dry wt < 0.10 < 0.10 < 0.10 < 0.10 < 0.10
Total Recoverable Nickel mg/kg dry wt 13 17 12 12 10
Total Recoverable Zinc mg/kg dry wt 63 78 64 55 51
Total Petroleum Hydrocarbons in Soil
C7 - C9 mg/kg dry wt <9 <9 <9 <9 <8
C10 - C14 mg/kg dry wt < 20 < 20 < 20 < 20 < 20
C15 - C36 mg/kg dry wt < 40 < 40 < 40 < 40 < 40
Total hydrocarbons (C7 - C36) mg/kg dry wt < 70 < 70 < 70 < 70 < 70
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP125 S2 1.5m TP124 S1 0.3m TP124 S2 1.5m TP120 S1 0.5m TP120 S2 1.5m
23-Jul-2014 23-Jul-2014 23-Jul-2014 23-Jul-2014 23-Jul-2014
Lab Number: 1301384.40 1301384.42 1301384.43 1301384.45 1301384.46
Individual Tests
Dry Matter g/100g as rcvd 78 74 74 77 74
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 2 6 5 23 7
Total Recoverable Cadmium mg/kg dry wt < 0.10 0.33 < 0.10 < 0.10 < 0.10
Total Recoverable Chromium mg/kg dry wt 15 22 20 18 20
Total Recoverable Copper mg/kg dry wt 9 87 15 11 15
Total Recoverable Lead mg/kg dry wt 15.3 650 26 34 26
Total Recoverable Mercury mg/kg dry wt < 0.10 0.51 < 0.10 0.15 < 0.10
Total Recoverable Nickel mg/kg dry wt 13 35 18 12 16
Total Recoverable Zinc mg/kg dry wt 52 350 78 109 77
Polychlorinated Biphenyls Screening in Soil
PCB-18 mg/kg dry wt - - - < 0.010 -
PCB-28 mg/kg dry wt - - - < 0.010 -
PCB-31 mg/kg dry wt - - - < 0.010 -
PCB-44 mg/kg dry wt - - - < 0.010 -
PCB-49 mg/kg dry wt - - - < 0.010 -
PCB-52 mg/kg dry wt - - - < 0.010 -
PCB-60 mg/kg dry wt - - - < 0.010 -
PCB-77 mg/kg dry wt - - - < 0.010 -
PCB-81 mg/kg dry wt - - - < 0.010 -
PCB-86 mg/kg dry wt - - - < 0.010 -
PCB-101 mg/kg dry wt - - - < 0.010 -
PCB-105 mg/kg dry wt - - - < 0.010 -
PCB-110 mg/kg dry wt - - - < 0.010 -
PCB-114 mg/kg dry wt - - - < 0.010 -
PCB-118 mg/kg dry wt - - - < 0.010 -
PCB-121 mg/kg dry wt - - - < 0.010 -
PCB-123 mg/kg dry wt - - - < 0.010 -
PCB-126 mg/kg dry wt - - - < 0.010 -
PCB-128 mg/kg dry wt - - - < 0.010 -
PCB-138 mg/kg dry wt - - - < 0.010 -
PCB-141 mg/kg dry wt - - - < 0.010 -
PCB-149 mg/kg dry wt - - - < 0.010 -
PCB-151 mg/kg dry wt - - - < 0.010 -
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP115 S2 1.5m TP115 S3 2.5m TP001 S1 0.5m TP102 S1 0.5m TP102 S2 1.5m
23-Jul-2014 23-Jul-2014 23-Jul-2014 24-Jul-2014 24-Jul-2014
Lab Number: 1301384.48 1301384.49 1301384.50 1301384.51 1301384.52
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP103 S1 0.5m TP103 S2 1.5m TP104 S1 0.5m TP104 S2 1.3m TP105 S1 0.5m
24-Jul-2014 24-Jul-2014 24-Jul-2014 24-Jul-2014 24-Jul-2014
Lab Number: 1301384.54 1301384.55 1301384.57 1301384.58 1301384.60
Individual Tests
Dry Matter g/100g as rcvd 91 81 84 77 90
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 7 6 13 14 8
Total Recoverable Cadmium mg/kg dry wt 0.17 < 0.10 0.13 < 0.10 0.23
Total Recoverable Chromium mg/kg dry wt 22 22 13 23 20
Total Recoverable Copper mg/kg dry wt 35 12 61 14 28
Total Recoverable Lead mg/kg dry wt 174 31 450 40 102
Total Recoverable Mercury mg/kg dry wt 0.22 < 0.10 3.8 < 0.10 0.33
Total Recoverable Nickel mg/kg dry wt 24 19 13 20 20
Total Recoverable Zinc mg/kg dry wt 155 91 144 100 151
Total Petroleum Hydrocarbons in Soil
C7 - C9 mg/kg dry wt <8 <9 <8 <9 <8
C10 - C14 mg/kg dry wt < 20 < 20 < 20 < 20 < 20
C15 - C36 mg/kg dry wt 620 < 40 48 < 40 76
Total hydrocarbons (C7 - C36) mg/kg dry wt 620 < 70 < 70 < 70 76
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP110 S1 0.5m TP110 S2 1.5m TP109 S1 0.5m TP109 S2 1.5m TP107 S1 0.5m
24-Jul-2014 24-Jul-2014 24-Jul-2014 24-Jul-2014 24-Jul-2014
Lab Number: 1301384.61 1301384.62 1301384.64 1301384.65 1301384.67
Individual Tests
Dry Matter g/100g as rcvd 87 84 89 83 91
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 7 5 5 7 6
Total Recoverable Cadmium mg/kg dry wt 0.45 0.12 0.13 0.15 < 0.10
Total Recoverable Chromium mg/kg dry wt 18 20 19 24 46
Total Recoverable Copper mg/kg dry wt 15 14 15 21 13
Total Recoverable Lead mg/kg dry wt 62 31 134 107 280
Total Recoverable Mercury mg/kg dry wt 0.21 0.12 0.68 0.26 < 0.10
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP107 S2 1.3m TP107 S3 1.7m TP108 S1 0.5m TP108 S2 1.5m TP106 S1 0.5m
24-Jul-2014 24-Jul-2014 24-Jul-2014 24-Jul-2014 24-Jul-2014
Lab Number: 1301384.68 1301384.69 1301384.71 1301384.72 1301384.74
Individual Tests
Dry Matter g/100g as rcvd 71 82 88 80 91
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 11 6 11 6 8
Total Recoverable Cadmium mg/kg dry wt < 0.10 < 0.10 0.26 0.13 0.26
Total Recoverable Chromium mg/kg dry wt 45 27 15 20 18
Sample Name: 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF 14:096 MSF
TP106 S2 1.5m TP002 S1 0.5m TP003 S1 0.5m TP101 S1 0.5m TP101 S2 1.5m
24-Jul-2014 24-Jul-2014 24-Jul-2014 24-Jul-2014 24-Jul-2014
Lab Number: 1301384.75 1301384.77 1301384.78 1301384.79 1301384.80
Individual Tests
Dry Matter g/100g as rcvd 75 91 91 94 77
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Analyst's Comments
Appendix No.1 - Total Petroleum Hydrocarbon Chromatograms
SUMMARY OF METHODS
The following table(s) gives a brief description of the methods used to conduct the analyses for this job. The detection limits given below are those attainable in a relatively clean matrix.
Detection limits may be higher for individual samples should insufficient sample be available, or if the matrix requires that dilutions be performed during analysis.
These samples were collected by yourselves (or your agent) and analysed as received at the laboratory.
Samples are held at the laboratory after reporting for a length of time depending on the preservation used and the stability of
the analytes being tested. Once the storage period is completed the samples are discarded unless otherwise advised by the
client.
This report must not be reproduced, except in full, without the written consent of the signatory.
Sample : 1301384.5
Sample : 1301384.6
Sample : 1301384.11
Sample : 1301384.18
Sample : 1301384.36
Sample : 1301384.37
Sample : 1301384.42
Sample : 1301384.51
Sample : 1301384.54
Sample : 1301384.57
Sample : 1301384.60
Sample : 1301384.61
Sample : 1301384.64
Sample : 1301384.65
Sample : 1301384.67
Sample : 1301384.71
Sample : 1301384.77
Sample : 1301384.78
This Laboratory is accredited by International Accreditation New Zealand (IANZ), which represents New Zealand in the International
Laboratory Accreditation Cooperation (ILAC). Through the ILAC Mutual Recognition Arrangement (ILAC-MRA) this accreditation is
internationally recognised.
The tests reported herein have been performed in accordance with the terms of accreditation, with the exception of tests marked *, which
are not accredited.
Sample Type: Soil
Sample Name: 14:120: MTP201 14:120: MTP201 14:120: MTP202 14:120: MTP202 14:120: MTP203
S1 03-Nov-2014 S2 03-Nov-2014 S1 03-Nov-2014 S2 03-Nov-2014 S1 03-Nov-2014
10:10 am 10:12 am 10:30 am 10:45 am 11:05 am
Lab Number: 1346648.1 1346648.2 1346648.4 1346648.5 1346648.7
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
4,4'-DDE mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
4,4'-DDT mg/kg dry wt <3 <3 <3 <3 <3
Dieldrin mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
Endosulfan I mg/kg dry wt <3 <3 <3 <3 <3
Endosulfan II mg/kg dry wt <3 <3 <3 <3 <3
Endosulfan sulphate mg/kg dry wt <3 <3 <3 <3 <3
Endrin mg/kg dry wt <3 <3 <3 <3 <3
Endrin ketone mg/kg dry wt <3 <3 <3 <3 <3
Heptachlor mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
Heptachlor epoxide mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
Hexachlorobenzene mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
Polycyclic Aromatic Hydrocarbons in SVOC Soil Samples by GC-MS
Acenaphthene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 < 0.7
Acenaphthylene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 < 0.7
Anthracene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 < 0.7
Benzo[a]anthracene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 1.0
Benzo[a]pyrene (BAP) mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
Benzo[b]fluoranthene + Benzo[j] mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 1.5
fluoranthene
Benzo[g,h,i]perylene mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
Benzo[k]fluoranthene mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
2-Chloronaphthalene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 < 0.7
Chrysene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 1.0
Dibenzo[a,h]anthracene mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
Fluoranthene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 2.2
Fluorene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 < 0.7
Indeno(1,2,3-c,d)pyrene mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
2-Methylnaphthalene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 < 0.7
Naphthalene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 < 0.7
Phenanthrene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 0.9
Pyrene mg/kg dry wt < 0.7 < 0.7 < 0.7 < 0.7 2.2
Phenols in SVOC Soil Samples by GC-MS
4-Chloro-3-methylphenol mg/kg dry wt <5 <5 <5 <5 <5
2-Chlorophenol mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
2,4-Dichlorophenol mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
2,4-Dimethylphenol mg/kg dry wt <3 <3 <3 <3 <3
3 & 4-Methylphenol (m- + p- mg/kg dry wt <3 <3 <3 <3 <3
cresol)
2-Methylphenol (o-Cresol) mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
2-Nitrophenol mg/kg dry wt <5 <5 <5 <5 <5
Pentachlorophenol (PCP) mg/kg dry wt < 30 < 30 < 30 < 30 < 30
Phenol mg/kg dry wt <3 <3 <3 <3 <3
2,4,5-Trichlorophenol mg/kg dry wt <3 <3 <3 <3 <3
2,4,6-Trichlorophenol mg/kg dry wt <3 <3 <3 <3 <3
Plasticisers in SVOC Soil Samples by GC-MS
Bis(2-ethylhexyl)phthalate mg/kg dry wt <5 <6 <6 <6 <6
Butylbenzylphthalate mg/kg dry wt <3 <3 <3 <3 <3
Di(2-ethylhexyl)adipate mg/kg dry wt < 1.3 < 1.4 < 1.4 < 1.4 < 1.3
Diethylphthalate mg/kg dry wt <3 <3 <3 <3 <3
Dimethylphthalate mg/kg dry wt <3 <3 <3 <3 <3
Di-n-butylphthalate mg/kg dry wt <3 <3 <3 <3 <3
Di-n-octylphthalate mg/kg dry wt <3 <3 <3 <3 <3
Other Halogenated compounds in SVOC Soil Samples by GC-MS
1,2-Dichlorobenzene mg/kg dry wt <3 <3 <3 <3 <3
Sample Name: 14:120: MTP203 14:120: MTP204 14:120: MTP204 14:120: MTP205 14:120: MTP205
S2 03-Nov-2014 S1 03-Nov-2014 S2 03-Nov-2014 S1 03-Nov-2014 S2 03-Nov-2014
11:10 am 11:45 am 11:50 am 1:00 pm 1:05 pm
Lab Number: 1346648.8 1346648.10 1346648.11 1346648.13 1346648.14
Individual Tests
Dry Matter g/100g as rcvd 78 79 81 80 80
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 7 9 3 7 4
Total Recoverable Cadmium mg/kg dry wt 0.20 0.41 < 0.10 0.39 < 0.10
Total Recoverable Chromium mg/kg dry wt 16 18 16 18 17
Total Recoverable Copper mg/kg dry wt 23 52 8 93 12
Total Recoverable Lead mg/kg dry wt 330 1,000 30 186 28
Total Recoverable Mercury mg/kg dry wt 0.23 0.91 < 0.10 0.11 < 0.10
Total Recoverable Nickel mg/kg dry wt 13 14 12 11 14
Total Recoverable Zinc mg/kg dry wt 195 440 79 260 80
BTEX in Soil by Headspace GC-MS
Benzene mg/kg dry wt < 0.06 < 0.06 < 0.05 < 0.06 < 0.05
Toluene mg/kg dry wt < 0.06 < 0.06 < 0.05 < 0.06 < 0.05
Ethylbenzene mg/kg dry wt < 0.06 < 0.06 < 0.05 < 0.06 < 0.05
m&p-Xylene mg/kg dry wt < 0.11 < 0.11 < 0.10 < 0.11 < 0.10
o-Xylene mg/kg dry wt < 0.06 < 0.06 < 0.05 < 0.06 < 0.05
Haloethers in SVOC Soil Samples by GC-MS
Bis(2-chloroethoxy) methane mg/kg dry wt < 1.4 < 1.4 < 1.4 < 1.4 < 1.4
Bis(2-chloroethyl)ether mg/kg dry wt < 1.4 < 1.4 < 1.4 < 1.4 < 1.4
Bis(2-chloroisopropyl)ether mg/kg dry wt < 1.4 < 1.4 < 1.4 < 1.4 < 1.4
4-Bromophenyl phenyl ether mg/kg dry wt < 1.4 < 1.4 < 1.4 < 1.4 < 1.4
4-Chlorophenyl phenyl ether mg/kg dry wt < 1.4 < 1.4 < 1.4 < 1.4 < 1.4
Nitrogen containing compounds in SVOC Soil Samples by GC-MS
3,3'-Dichlorobenzidine mg/kg dry wt <7 <7 <7 <7 <7
2,4-Dinitrotoluene mg/kg dry wt <3 <3 <3 <3 <3
2,6-Dinitrotoluene mg/kg dry wt <3 <3 <3 <3 <3
Nitrobenzene mg/kg dry wt < 1.4 < 1.4 < 1.4 < 1.4 < 1.4
N-Nitrosodi-n-propylamine mg/kg dry wt <3 <3 <3 <3 <3
N-Nitrosodiphenylamine mg/kg dry wt <3 <3 <3 <3 <3
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Aldrin mg/kg dry wt < 1.4 < 1.4 < 1.4 < 1.4 < 1.4
alpha-BHC mg/kg dry wt < 1.4 < 1.4 < 1.4 < 1.4 < 1.4
beta-BHC mg/kg dry wt < 1.4 < 1.4 < 1.4 < 1.4 < 1.4
Sample Name: 14:120: MTP206 14:120: MTP206 14:120: MTP208 14:120: MTP208 14:120: MTP209
S1 03-Nov-2014 S2 03-Nov-2014 S1 03-Nov-2014 S2 03-Nov-2014 S1 03-Nov-2014
1:25 pm 1:30 pm 2:20 pm 2:25 pm 3:00 pm
Lab Number: 1346648.16 1346648.17 1346648.19 1346648.20 1346648.22
Individual Tests
Dry Matter g/100g as rcvd 75 77 77 77 86
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 6 3 6 4 11
Total Recoverable Cadmium mg/kg dry wt < 0.10 < 0.10 0.25 < 0.10 0.53
Total Recoverable Chromium mg/kg dry wt 19 16 19 16 19
Total Recoverable Copper mg/kg dry wt 18 10 36 14 30
Total Recoverable Lead mg/kg dry wt 48 15.0 200 31 2,700
Total Recoverable Mercury mg/kg dry wt 0.30 < 0.10 0.11 < 0.10 0.60
Total Recoverable Nickel mg/kg dry wt 17 12 15 11 12
Total Recoverable Zinc mg/kg dry wt 97 59 260 84 630
Total Petroleum Hydrocarbons in Soil
C7 - C9 mg/kg dry wt <9 <9 <9 <9 <8
C10 - C14 mg/kg dry wt < 20 < 20 < 20 < 20 < 20
C15 - C36 mg/kg dry wt < 40 < 40 151 < 40 250
Total hydrocarbons (C7 - C36) mg/kg dry wt < 70 < 70 151 < 70 250
Sample Name: 14:120: MTP209 14:120: MTP212 14:120: MTP212 14:120: MTP213 14:120: MTP213
S2 03-Nov-2014 S1 03-Nov-2014 S2 03-Nov-2014 S1 03-Nov-2014 S2 03-Nov-2014
3:05 pm 3:40 pm 3:45 pm 4:00 pm 4:05 pm
Lab Number: 1346648.23 1346648.25 1346648.26 1346648.28 1346648.29
Individual Tests
Dry Matter g/100g as rcvd 81 82 82 87 84
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 9 7 3 11 7
Total Recoverable Cadmium mg/kg dry wt < 0.10 < 0.10 < 0.10 0.13 < 0.10
Total Recoverable Chromium mg/kg dry wt 16 18 13 16 14
Total Recoverable Copper mg/kg dry wt 10 12 10 18 8
Total Recoverable Lead mg/kg dry wt 23 19.0 12.5 134 16.2
Total Recoverable Mercury mg/kg dry wt < 0.10 < 0.10 < 0.10 0.13 < 0.10
Total Recoverable Nickel mg/kg dry wt 14 15 12 13 12
Total Recoverable Zinc mg/kg dry wt 66 61 42 128 49
1346648.7 1346648.8
14:120: MTP203 S1 03-Nov-2014 11:05 am 14:120: MTP203 S2 03-Nov-2014 11:10 am
Client Chromatogram for TPH by FID Client Chromatogram for TPH by FID
1346648.22 1346648.34
14:120: MTP209 S1 03-Nov-2014 3:00 pm 14:120: MTP215:S1 04-Nov-2014 8:05 am
Client Chromatogram for TPH by FID Client Chromatogram for TPH by FID
1346648.37 1346648.40
14:120: MTP216:S1 04-Nov-2014 8:50 am 14:120: MTP220:S1 04-Nov-2014 9:30 am
Client Chromatogram for TPH by FID Client Chromatogram for TPH by FID
1346648.56 1346648.59
14:120: MTP226:S2 04-Nov-2014 2:10 pm 14:120: MTP228:S1 04-Nov-2014 3:00 pm
Client Chromatogram for TPH by FID Client Chromatogram for TPH by FID
SUMMARY OF METHODS
The following table(s) gives a brief description of the methods used to conduct the analyses for this job. The detection limits given below are those attainable in a relatively clean matrix.
Detection limits may be higher for individual samples should insufficient sample be available, or if the matrix requires that dilutions be performed during analysis.
Samples are held at the laboratory after reporting for a length of time depending on the preservation used and the stability of
the analytes being tested. Once the storage period is completed the samples are discarded unless otherwise advised by the
client.
This report must not be reproduced, except in full, without the written consent of the signatory.
Amended Report
This report replaces an earlier report issued on the 14 Apr 2015 at 2:36 pm
The sample name for 1402615.132 has been amended.
This Laboratory is accredited by International Accreditation New Zealand (IANZ), which represents New Zealand in the International
Laboratory Accreditation Cooperation (ILAC). Through the ILAC Mutual Recognition Arrangement (ILAC-MRA) this accreditation is
internationally recognised.
The tests reported herein have been performed in accordance with the terms of accreditation, with the exception of tests marked *, which
are not accredited.
Sample Type: Soil
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP301 S1 0.5 TP301 S2 1.5 TP302 S1 0.5 TP302 S2 1.5 TP303 S1 0.5
23-Mar-2015 23-Mar-2015 23-Mar-2015 23-Mar-2015 23-Mar-2015
Lab Number: 1402615.1 1402615.2 1402615.4 1402615.5 1402615.7
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Endosulfan II mg/kg dry wt <3 - <3 - -
Endosulfan sulphate mg/kg dry wt <3 - <3 - -
Endrin mg/kg dry wt <3 - <3 - -
Endrin ketone mg/kg dry wt <3 - <3 - -
Heptachlor mg/kg dry wt < 1.4 - < 1.3 - -
Heptachlor epoxide mg/kg dry wt < 1.4 - < 1.3 - -
Hexachlorobenzene mg/kg dry wt < 1.4 - < 1.3 - -
Polycyclic Aromatic Hydrocarbons in SVOC Soil Samples by GC-MS
Acenaphthene mg/kg dry wt < 0.7 - < 0.7 - -
Acenaphthylene mg/kg dry wt < 0.7 - < 0.7 - -
Anthracene mg/kg dry wt < 0.7 - < 0.7 - -
Benzo[a]anthracene mg/kg dry wt 0.7 - < 0.7 - -
Benzo[a]pyrene (BAP) mg/kg dry wt < 1.4 - < 1.3 - -
Benzo[b]fluoranthene + Benzo[j] mg/kg dry wt < 1.4 - < 1.3 - -
fluoranthene
Benzo[g,h,i]perylene mg/kg dry wt < 1.4 - < 1.3 - -
Benzo[k]fluoranthene mg/kg dry wt < 1.4 - < 1.3 - -
2-Chloronaphthalene mg/kg dry wt < 0.7 - < 0.7 - -
Chrysene mg/kg dry wt 0.8 - < 0.7 - -
Dibenzo[a,h]anthracene mg/kg dry wt < 1.4 - < 1.3 - -
Fluoranthene mg/kg dry wt 1.4 - < 0.7 - -
Fluorene mg/kg dry wt < 0.7 - < 0.7 - -
Indeno(1,2,3-c,d)pyrene mg/kg dry wt < 1.4 - < 1.3 - -
2-Methylnaphthalene mg/kg dry wt < 0.7 - < 0.7 - -
Naphthalene mg/kg dry wt < 0.7 - < 0.7 - -
Phenanthrene mg/kg dry wt 1.0 - < 0.7 - -
Pyrene mg/kg dry wt 1.4 - < 0.7 - -
Phenols in SVOC Soil Samples by GC-MS
4-Chloro-3-methylphenol mg/kg dry wt <5 - <5 - -
2-Chlorophenol mg/kg dry wt < 1.4 - < 1.3 - -
2,4-Dichlorophenol mg/kg dry wt < 1.4 - < 1.3 - -
2,4-Dimethylphenol mg/kg dry wt <3 - <3 - -
3 & 4-Methylphenol (m- + p- mg/kg dry wt <3 - <3 - -
cresol)
2-Methylphenol (o-Cresol) mg/kg dry wt < 1.4 - < 1.3 - -
2-Nitrophenol mg/kg dry wt <5 - <5 - -
Pentachlorophenol (PCP) mg/kg dry wt < 30 - < 30 - -
Phenol mg/kg dry wt <3 - <3 - -
2,4,5-Trichlorophenol mg/kg dry wt <3 - <3 - -
2,4,6-Trichlorophenol mg/kg dry wt <3 - <3 - -
Plasticisers in SVOC Soil Samples by GC-MS
Bis(2-ethylhexyl)phthalate mg/kg dry wt <6 - <6 - -
Butylbenzylphthalate mg/kg dry wt <3 - <3 - -
Di(2-ethylhexyl)adipate mg/kg dry wt < 1.4 - < 1.3 - -
Diethylphthalate mg/kg dry wt <3 - <3 - -
Dimethylphthalate mg/kg dry wt <3 - <3 - -
Di-n-butylphthalate mg/kg dry wt <3 - <3 - -
Di-n-octylphthalate mg/kg dry wt <3 - <3 - -
Other Halogenated compounds in SVOC Soil Samples by GC-MS
1,2-Dichlorobenzene mg/kg dry wt <3 - <3 - -
1,3-Dichlorobenzene mg/kg dry wt <3 - <3 - -
1,4-Dichlorobenzene mg/kg dry wt <3 - <3 - -
Hexachlorobutadiene mg/kg dry wt <3 - <3 - -
Hexachlorocyclopentadiene mg/kg dry wt <7 - <7 - -
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP303 S2 1.5 TP304 S1 0.6 TP304 S2 1.8 TP305 S1 0.5 TP305 S2 1.7
23-Mar-2015 23-Mar-2015 23-Mar-2015 23-Mar-2015 23-Mar-2015
Lab Number: 1402615.8 1402615.10 1402615.11 1402615.13 1402615.14
Individual Tests
Dry Matter g/100g as rcvd - 88 - 80 -
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 5 <2 3 4 3
Total Recoverable Cadmium mg/kg dry wt < 0.10 0.33 < 0.10 < 0.10 < 0.10
Total Recoverable Chromium mg/kg dry wt 18 17 19 17 18
Total Recoverable Copper mg/kg dry wt 11 9 13 11 9
Total Recoverable Lead mg/kg dry wt 17.0 16.1 19.4 16.5 14.8
Total Recoverable Mercury mg/kg dry wt < 0.10 < 0.10 < 0.10 < 0.10 < 0.10
Total Recoverable Nickel mg/kg dry wt 15 13 17 16 14
Total Recoverable Zinc mg/kg dry wt 61 350 67 58 55
Haloethers in SVOC Soil Samples by GC-MS
Bis(2-chloroethoxy) methane mg/kg dry wt - < 1.3 - < 1.4 -
Bis(2-chloroethyl)ether mg/kg dry wt - < 1.3 - < 1.4 -
Bis(2-chloroisopropyl)ether mg/kg dry wt - < 1.3 - < 1.4 -
4-Bromophenyl phenyl ether mg/kg dry wt - < 1.3 - < 1.4 -
4-Chlorophenyl phenyl ether mg/kg dry wt - < 1.3 - < 1.4 -
Nitrogen containing compounds in SVOC Soil Samples by GC-MS
3,3'-Dichlorobenzidine mg/kg dry wt - <7 - <7 -
2,4-Dinitrotoluene mg/kg dry wt - <3 - <3 -
2,6-Dinitrotoluene mg/kg dry wt - <3 - <3 -
Nitrobenzene mg/kg dry wt - < 1.3 - < 1.4 -
N-Nitrosodi-n-propylamine mg/kg dry wt - <3 - <3 -
N-Nitrosodiphenylamine mg/kg dry wt - <3 - <3 -
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Aldrin mg/kg dry wt - < 1.3 - < 1.4 -
alpha-BHC mg/kg dry wt - < 1.3 - < 1.4 -
beta-BHC mg/kg dry wt - < 1.3 - < 1.4 -
delta-BHC mg/kg dry wt - < 1.3 - < 1.4 -
gamma-BHC (Lindane) mg/kg dry wt - < 1.3 - < 1.4 -
4,4'-DDD mg/kg dry wt - < 1.3 - < 1.4 -
4,4'-DDE mg/kg dry wt - < 1.3 - < 1.4 -
4,4'-DDT mg/kg dry wt - <3 - <3 -
Dieldrin mg/kg dry wt - < 1.3 - < 1.4 -
Endosulfan I mg/kg dry wt - <3 - <3 -
Endosulfan II mg/kg dry wt - <3 - <3 -
Endosulfan sulphate mg/kg dry wt - <3 - <3 -
Endrin mg/kg dry wt - <3 - <3 -
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP306 S1 0.5 TP306 S2 1.5 TP307 S1 0.5 TP307 S2 1.5 TP308 S1 0.6
23-Mar-2015 23-Mar-2015 23-Mar-2015 23-Mar-2015 23-Mar-2015
Lab Number: 1402615.16 1402615.17 1402615.19 1402615.20 1402615.22
Individual Tests
Dry Matter g/100g as rcvd 77 - 80 - 84
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 3 4 4 6 2
Total Recoverable Cadmium mg/kg dry wt < 0.10 < 0.10 < 0.10 < 0.10 < 0.10
Total Recoverable Chromium mg/kg dry wt 13 16 17 21 14
Total Recoverable Copper mg/kg dry wt 7 11 13 16 8
Total Recoverable Lead mg/kg dry wt 54 18.5 39 24 17.2
Total Recoverable Mercury mg/kg dry wt 0.24 < 0.10 < 0.10 < 0.10 < 0.10
Total Recoverable Nickel mg/kg dry wt 9 13 13 18 11
Total Recoverable Zinc mg/kg dry wt 76 61 76 78 64
Haloethers in SVOC Soil Samples by GC-MS
Bis(2-chloroethoxy) methane mg/kg dry wt < 1.4 - - - -
Bis(2-chloroethyl)ether mg/kg dry wt < 1.4 - - - -
Bis(2-chloroisopropyl)ether mg/kg dry wt < 1.4 - - - -
4-Bromophenyl phenyl ether mg/kg dry wt < 1.4 - - - -
4-Chlorophenyl phenyl ether mg/kg dry wt < 1.4 - - - -
Nitrogen containing compounds in SVOC Soil Samples by GC-MS
3,3'-Dichlorobenzidine mg/kg dry wt <7 - - - -
2,4-Dinitrotoluene mg/kg dry wt <3 - - - -
2,6-Dinitrotoluene mg/kg dry wt <3 - - - -
Nitrobenzene mg/kg dry wt < 1.4 - - - -
N-Nitrosodi-n-propylamine mg/kg dry wt <3 - - - -
N-Nitrosodiphenylamine mg/kg dry wt <3 - - - -
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Aldrin mg/kg dry wt < 1.4 - - - -
alpha-BHC mg/kg dry wt < 1.4 - - - -
beta-BHC mg/kg dry wt < 1.4 - - - -
delta-BHC mg/kg dry wt < 1.4 - - - -
gamma-BHC (Lindane) mg/kg dry wt < 1.4 - - - -
4,4'-DDD mg/kg dry wt < 1.4 - - - -
4,4'-DDE mg/kg dry wt < 1.4 - - - -
4,4'-DDT mg/kg dry wt <3 - - - -
Dieldrin mg/kg dry wt < 1.4 - - - -
Endosulfan I mg/kg dry wt <3 - - - -
Endosulfan II mg/kg dry wt <3 - - - -
Endosulfan sulphate mg/kg dry wt <3 - - - -
Endrin mg/kg dry wt <3 - - - -
Endrin ketone mg/kg dry wt <3 - - - -
Heptachlor mg/kg dry wt < 1.4 - - - -
Heptachlor epoxide mg/kg dry wt < 1.4 - - - -
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP308 S2 0.8 TP308 S3 1.5 TP309 S1 0.5 TP309 S2 1.5 TP004 S1 0.6
23-Mar-2015 23-Mar-2015 23-Mar-2015 23-Mar-2015 23-Mar-2015
Lab Number: 1402615.23 1402615.24 1402615.26 1402615.27 1402615.29
Individual Tests
Dry Matter g/100g as rcvd 49 - 72 - 85
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 42 7 14 8 10
Total Recoverable Cadmium mg/kg dry wt 2.2 < 0.10 0.72 < 0.10 0.14
Total Recoverable Chromium mg/kg dry wt 39 22 21 20 19
Total Recoverable Copper mg/kg dry wt 300 17 56 16 13
Total Recoverable Lead mg/kg dry wt 550 26 530 25 79
Total Recoverable Mercury mg/kg dry wt 1.37 < 0.10 0.28 < 0.10 0.14
Total Recoverable Nickel mg/kg dry wt 38 18 18 17 12
Total Recoverable Zinc mg/kg dry wt 1,630 84 550 78 230
Haloethers in SVOC Soil Samples by GC-MS
Bis(2-chloroethoxy) methane mg/kg dry wt <3 - - - < 1.3
Bis(2-chloroethyl)ether mg/kg dry wt <3 - - - < 1.3
Bis(2-chloroisopropyl)ether mg/kg dry wt <3 - - - < 1.3
4-Bromophenyl phenyl ether mg/kg dry wt <3 - - - < 1.3
4-Chlorophenyl phenyl ether mg/kg dry wt <3 - - - < 1.3
Nitrogen containing compounds in SVOC Soil Samples by GC-MS
3,3'-Dichlorobenzidine mg/kg dry wt < 11 - - - <7
2,4-Dinitrotoluene mg/kg dry wt <5 - - - <3
2,6-Dinitrotoluene mg/kg dry wt <5 - - - <3
Nitrobenzene mg/kg dry wt <3 - - - < 1.3
N-Nitrosodi-n-propylamine mg/kg dry wt <5 - - - <3
N-Nitrosodiphenylamine mg/kg dry wt <5 - - - <3
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Aldrin mg/kg dry wt <3 - - - < 1.3
alpha-BHC mg/kg dry wt <3 - - - < 1.3
beta-BHC mg/kg dry wt <3 - - - < 1.3
delta-BHC mg/kg dry wt <3 - - - < 1.3
gamma-BHC (Lindane) mg/kg dry wt <3 - - - < 1.3
4,4'-DDD mg/kg dry wt <3 - - - < 1.3
4,4'-DDE mg/kg dry wt <3 - - - < 1.3
4,4'-DDT mg/kg dry wt <5 - - - <3
Dieldrin mg/kg dry wt <3 - - - < 1.3
Endosulfan I mg/kg dry wt <5 - - - <3
Endosulfan II mg/kg dry wt <5 - - - <3
Endosulfan sulphate mg/kg dry wt <5 - - - <3
Endrin mg/kg dry wt <5 - - - <3
Endrin ketone mg/kg dry wt <5 - - - <3
Heptachlor mg/kg dry wt <3 - - - < 1.3
Heptachlor epoxide mg/kg dry wt <3 - - - < 1.3
Hexachlorobenzene mg/kg dry wt <3 - - - < 1.3
Polycyclic Aromatic Hydrocarbons in SVOC Soil Samples by GC-MS
Acenaphthene mg/kg dry wt < 1.1 - - - < 0.7
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP005 S1 0.6 TP310 S1 0.5 TP310 S2 1.5 TP311 S1 0.5 TP311 S2 0.8
23-Mar-2015 24-Mar-2015 24-Mar-2015 24-Mar-2015 24-Mar-2015
Lab Number: 1402615.30 1402615.31 1402615.32 1402615.34 1402615.35
Individual Tests
Dry Matter g/100g as rcvd 84 77 - 77 67
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 3 16 4 9 115
Total Recoverable Cadmium mg/kg dry wt < 0.10 < 0.10 < 0.10 0.59 2.8
Total Recoverable Chromium mg/kg dry wt 15 17 17 25 41
Total Recoverable Copper mg/kg dry wt 9 4 10 96 200
Total Recoverable Lead mg/kg dry wt 34 41 14.3 300 3,100
Total Recoverable Mercury mg/kg dry wt < 0.10 < 0.10 < 0.10 0.13 10.2
Total Recoverable Nickel mg/kg dry wt 11 10 12 14 66
Total Recoverable Zinc mg/kg dry wt 58 77 55 400 2,300
Haloethers in SVOC Soil Samples by GC-MS
Bis(2-chloroethoxy) methane mg/kg dry wt - < 1.4 - < 1.4 < 1.6
Bis(2-chloroethyl)ether mg/kg dry wt - < 1.4 - < 1.4 < 1.6
Bis(2-chloroisopropyl)ether mg/kg dry wt - < 1.4 - < 1.4 < 1.6
4-Bromophenyl phenyl ether mg/kg dry wt - < 1.4 - < 1.4 < 1.6
4-Chlorophenyl phenyl ether mg/kg dry wt - < 1.4 - < 1.4 < 1.6
Nitrogen containing compounds in SVOC Soil Samples by GC-MS
3,3'-Dichlorobenzidine mg/kg dry wt - <7 - <7 <8
2,4-Dinitrotoluene mg/kg dry wt - <3 - <3 <4
2,6-Dinitrotoluene mg/kg dry wt - <3 - <3 <4
Nitrobenzene mg/kg dry wt - < 1.4 - < 1.4 < 1.6
N-Nitrosodi-n-propylamine mg/kg dry wt - <3 - <3 <4
N-Nitrosodiphenylamine mg/kg dry wt - <3 - <3 <4
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Aldrin mg/kg dry wt - < 1.4 - < 1.4 < 1.6
alpha-BHC mg/kg dry wt - < 1.4 - < 1.4 < 1.6
beta-BHC mg/kg dry wt - < 1.4 - < 1.4 < 1.6
delta-BHC mg/kg dry wt - < 1.4 - < 1.4 < 1.6
gamma-BHC (Lindane) mg/kg dry wt - < 1.4 - < 1.4 < 1.6
4,4'-DDD mg/kg dry wt - < 1.4 - < 1.4 < 1.6
4,4'-DDE mg/kg dry wt - < 1.4 - < 1.4 < 1.6
4,4'-DDT mg/kg dry wt - <3 - <3 <4
Dieldrin mg/kg dry wt - < 1.4 - < 1.4 < 1.6
Endosulfan I mg/kg dry wt - <3 - <3 <4
Endosulfan II mg/kg dry wt - <3 - <3 <4
Endosulfan sulphate mg/kg dry wt - <3 - <3 <4
Endrin mg/kg dry wt - <3 - <3 <4
Endrin ketone mg/kg dry wt - <3 - <3 <4
Heptachlor mg/kg dry wt - < 1.4 - < 1.4 < 1.6
Heptachlor epoxide mg/kg dry wt - < 1.4 - < 1.4 < 1.6
Hexachlorobenzene mg/kg dry wt - < 1.4 - < 1.4 < 1.6
Polycyclic Aromatic Hydrocarbons in SVOC Soil Samples by GC-MS
Acenaphthene mg/kg dry wt - < 0.7 - < 0.7 < 0.8
Acenaphthylene mg/kg dry wt - < 0.7 - < 0.7 < 0.8
Anthracene mg/kg dry wt - < 0.7 - < 0.7 < 0.8
Benzo[a]anthracene mg/kg dry wt - < 0.7 - < 0.7 < 0.8
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP316 S2 1.5 TP317 S1 0.5 TP317 S2 2.0 TP318 S1 0.5 TP318 S2 1.7
24-Mar-2015 24-Mar-2015 24-Mar-2015 24-Mar-2015 24-Mar-2015
Lab Number: 1402615.51 1402615.53 1402615.54 1402615.56 1402615.57
Individual Tests
Dry Matter g/100g as rcvd - 94 - 82 -
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 14 3 6 2 11
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP319 S1 0.5 TP319 S2 1.5 TP320 S1 0.5 TP320 S2 1.5 TP321 S1 0.5
24-Mar-2015 24-Mar-2015 24-Mar-2015 24-Mar-2015 24-Mar-2015
Lab Number: 1402615.59 1402615.60 1402615.62 1402615.63 1402615.65
Individual Tests
Dry Matter g/100g as rcvd 60 - 61 - 65
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 17 13 31 4 25
Total Recoverable Cadmium mg/kg dry wt 0.16 < 0.10 0.67 < 0.10 0.27
Total Recoverable Chromium mg/kg dry wt 20 23 18 11 21
Total Recoverable Copper mg/kg dry wt 24 18 93 5 86
Total Recoverable Lead mg/kg dry wt 61 29 690 11.0 530
Total Recoverable Mercury mg/kg dry wt 0.28 < 0.10 1.87 < 0.10 0.13
Total Recoverable Nickel mg/kg dry wt 12 20 19 8 25
Total Recoverable Zinc mg/kg dry wt 66 93 1,010 39 198
Haloethers in SVOC Soil Samples by GC-MS
Bis(2-chloroethoxy) methane mg/kg dry wt - - < 1.8 - < 1.7
Bis(2-chloroethyl)ether mg/kg dry wt - - < 1.8 - < 1.7
Bis(2-chloroisopropyl)ether mg/kg dry wt - - < 1.8 - < 1.7
4-Bromophenyl phenyl ether mg/kg dry wt - - < 1.8 - < 1.7
4-Chlorophenyl phenyl ether mg/kg dry wt - - < 1.8 - < 1.7
Nitrogen containing compounds in SVOC Soil Samples by GC-MS
3,3'-Dichlorobenzidine mg/kg dry wt - - <9 - <9
2,4-Dinitrotoluene mg/kg dry wt - - <4 - <4
2,6-Dinitrotoluene mg/kg dry wt - - <4 - <4
Nitrobenzene mg/kg dry wt - - < 1.8 - < 1.7
N-Nitrosodi-n-propylamine mg/kg dry wt - - <4 - <4
N-Nitrosodiphenylamine mg/kg dry wt - - <4 - <4
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Aldrin mg/kg dry wt - - < 1.8 - < 1.7
alpha-BHC mg/kg dry wt - - < 1.8 - < 1.7
beta-BHC mg/kg dry wt - - < 1.8 - < 1.7
delta-BHC mg/kg dry wt - - < 1.8 - < 1.7
gamma-BHC (Lindane) mg/kg dry wt - - < 1.8 - < 1.7
4,4'-DDD mg/kg dry wt - - < 1.8 - < 1.7
4,4'-DDE mg/kg dry wt - - < 1.8 - < 1.7
4,4'-DDT mg/kg dry wt - - <4 - <4
Dieldrin mg/kg dry wt - - < 1.8 - < 1.7
Endosulfan I mg/kg dry wt - - <4 - <4
Endosulfan II mg/kg dry wt - - <4 - <4
Endosulfan sulphate mg/kg dry wt - - <4 - <4
Endrin mg/kg dry wt - - <4 - <4
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP321 S2 1.5 TP007 S1 0.4 TP008 S1 1.5 TP329 S1 0.4 TP329 S2 1.5
24-Mar-2015 24-Mar-2015 24-Mar-2015 25-Mar-2015 25-Mar-2015
Lab Number: 1402615.66 1402615.68 1402615.69 1402615.70 1402615.71
Individual Tests
Dry Matter g/100g as rcvd - 74 94 91 -
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 7 2 <2 9 4
Total Recoverable Cadmium mg/kg dry wt < 0.10 < 0.10 < 0.10 0.33 < 0.10
Total Recoverable Chromium mg/kg dry wt 19 14 13 25 15
Total Recoverable Copper mg/kg dry wt 15 6 5 260 10
Total Recoverable Lead mg/kg dry wt 27 14.7 13.7 360 16.8
Total Recoverable Mercury mg/kg dry wt < 0.10 < 0.10 < 0.10 0.17 < 0.10
Total Recoverable Nickel mg/kg dry wt 18 10 9 40 11
Total Recoverable Zinc mg/kg dry wt 76 70 56 230 60
Haloethers in SVOC Soil Samples by GC-MS
Bis(2-chloroethoxy) methane mg/kg dry wt - - - < 1.2 -
Bis(2-chloroethyl)ether mg/kg dry wt - - - < 1.2 -
Bis(2-chloroisopropyl)ether mg/kg dry wt - - - < 1.2 -
4-Bromophenyl phenyl ether mg/kg dry wt - - - < 1.2 -
4-Chlorophenyl phenyl ether mg/kg dry wt - - - < 1.2 -
Nitrogen containing compounds in SVOC Soil Samples by GC-MS
3,3'-Dichlorobenzidine mg/kg dry wt - - - <6 -
2,4-Dinitrotoluene mg/kg dry wt - - - <3 -
2,6-Dinitrotoluene mg/kg dry wt - - - <3 -
Nitrobenzene mg/kg dry wt - - - < 1.2 -
N-Nitrosodi-n-propylamine mg/kg dry wt - - - <3 -
N-Nitrosodiphenylamine mg/kg dry wt - - - <3 -
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Aldrin mg/kg dry wt - - - < 1.2 -
alpha-BHC mg/kg dry wt - - - < 1.2 -
beta-BHC mg/kg dry wt - - - < 1.2 -
delta-BHC mg/kg dry wt - - - < 1.2 -
gamma-BHC (Lindane) mg/kg dry wt - - - < 1.2 -
4,4'-DDD mg/kg dry wt - - - < 1.2 -
4,4'-DDE mg/kg dry wt - - - < 1.2 -
4,4'-DDT mg/kg dry wt - - - <3 -
Dieldrin mg/kg dry wt - - - < 1.2 -
Endosulfan I mg/kg dry wt - - - <3 -
Endosulfan II mg/kg dry wt - - - <3 -
Endosulfan sulphate mg/kg dry wt - - - <3 -
Endrin mg/kg dry wt - - - <3 -
Endrin ketone mg/kg dry wt - - - <3 -
Heptachlor mg/kg dry wt - - - < 1.2 -
Heptachlor epoxide mg/kg dry wt - - - < 1.2 -
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP330 S1 0.45 TP330 S2 1.6 TP331 S1 0.5 TP331 S2 1.5 TP332 S1 0.5
25-Mar-2015 25-Mar-2015 25-Mar-2015 25-Mar-2015 25-Mar-2015
Lab Number: 1402615.73 1402615.74 1402615.76 1402615.77 1402615.79
Individual Tests
Dry Matter g/100g as rcvd 86 - 84 - 93
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 6 6 3 7 3
Total Recoverable Cadmium mg/kg dry wt 0.15 < 0.10 < 0.10 < 0.10 < 0.10
Total Recoverable Chromium mg/kg dry wt 17 23 18 18 11
Total Recoverable Copper mg/kg dry wt 19 14 8 13 6
Total Recoverable Lead mg/kg dry wt 80 27 22 23 15.0
Total Recoverable Mercury mg/kg dry wt 0.16 < 0.10 < 0.10 < 0.10 < 0.10
Total Recoverable Nickel mg/kg dry wt 12 17 13 17 8
Total Recoverable Zinc mg/kg dry wt 115 83 78 72 38
Haloethers in SVOC Soil Samples by GC-MS
Bis(2-chloroethoxy) methane mg/kg dry wt < 1.3 - - - -
Bis(2-chloroethyl)ether mg/kg dry wt < 1.3 - - - -
Bis(2-chloroisopropyl)ether mg/kg dry wt < 1.3 - - - -
4-Bromophenyl phenyl ether mg/kg dry wt < 1.3 - - - -
4-Chlorophenyl phenyl ether mg/kg dry wt < 1.3 - - - -
Nitrogen containing compounds in SVOC Soil Samples by GC-MS
3,3'-Dichlorobenzidine mg/kg dry wt <7 - - - -
2,4-Dinitrotoluene mg/kg dry wt <3 - - - -
2,6-Dinitrotoluene mg/kg dry wt <3 - - - -
Nitrobenzene mg/kg dry wt < 1.3 - - - -
N-Nitrosodi-n-propylamine mg/kg dry wt <3 - - - -
N-Nitrosodiphenylamine mg/kg dry wt <3 - - - -
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Aldrin mg/kg dry wt < 1.3 - - - -
alpha-BHC mg/kg dry wt < 1.3 - - - -
beta-BHC mg/kg dry wt < 1.3 - - - -
delta-BHC mg/kg dry wt < 1.3 - - - -
gamma-BHC (Lindane) mg/kg dry wt < 1.3 - - - -
4,4'-DDD mg/kg dry wt < 1.3 - - - -
4,4'-DDE mg/kg dry wt < 1.3 - - - -
4,4'-DDT mg/kg dry wt <3 - - - -
Dieldrin mg/kg dry wt < 1.3 - - - -
Endosulfan I mg/kg dry wt <3 - - - -
Endosulfan II mg/kg dry wt <3 - - - -
Endosulfan sulphate mg/kg dry wt <3 - - - -
Endrin mg/kg dry wt <3 - - - -
Endrin ketone mg/kg dry wt <3 - - - -
Heptachlor mg/kg dry wt < 1.3 - - - -
Heptachlor epoxide mg/kg dry wt < 1.3 - - - -
Hexachlorobenzene mg/kg dry wt < 1.3 - - - -
Polycyclic Aromatic Hydrocarbons in SVOC Soil Samples by GC-MS
Acenaphthene mg/kg dry wt < 0.7 - - - -
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP332 S2 0.6 TP332 S3 1.5 TP333 S1 0.5 TP333 S2 1.5 TP334 S1 0.5
25-Mar-2015 25-Mar-2015 25-Mar-2015 25-Mar-2015 25-Mar-2015
Lab Number: 1402615.80 1402615.81 1402615.83 1402615.84 1402615.86
Individual Tests
Dry Matter g/100g as rcvd 89 - 64 - 92
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 13 5 12 4 3
Total Recoverable Cadmium mg/kg dry wt 0.37 < 0.10 0.50 < 0.10 < 0.10
Total Recoverable Chromium mg/kg dry wt 28 24 22 18 14
Total Recoverable Copper mg/kg dry wt 119 18 82 12 10
Total Recoverable Lead mg/kg dry wt 540 30 540 22 28
Total Recoverable Mercury mg/kg dry wt 0.14 < 0.10 0.76 < 0.10 < 0.10
Total Recoverable Nickel mg/kg dry wt 39 18 14 14 12
Total Recoverable Zinc mg/kg dry wt 250 92 310 69 57
Haloethers in SVOC Soil Samples by GC-MS
Bis(2-chloroethoxy) methane mg/kg dry wt < 1.3 - < 1.7 - -
Bis(2-chloroethyl)ether mg/kg dry wt < 1.3 - < 1.7 - -
Bis(2-chloroisopropyl)ether mg/kg dry wt < 1.3 - < 1.7 - -
4-Bromophenyl phenyl ether mg/kg dry wt < 1.3 - < 1.7 - -
4-Chlorophenyl phenyl ether mg/kg dry wt < 1.3 - < 1.7 - -
Nitrogen containing compounds in SVOC Soil Samples by GC-MS
3,3'-Dichlorobenzidine mg/kg dry wt <7 - <9 - -
2,4-Dinitrotoluene mg/kg dry wt <3 - <4 - -
2,6-Dinitrotoluene mg/kg dry wt <3 - <4 - -
Nitrobenzene mg/kg dry wt < 1.3 - < 1.7 - -
N-Nitrosodi-n-propylamine mg/kg dry wt <3 - <4 - -
N-Nitrosodiphenylamine mg/kg dry wt <3 - <4 - -
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Aldrin mg/kg dry wt < 1.3 - < 1.7 - -
alpha-BHC mg/kg dry wt < 1.3 - < 1.7 - -
beta-BHC mg/kg dry wt < 1.3 - < 1.7 - -
delta-BHC mg/kg dry wt < 1.3 - < 1.7 - -
gamma-BHC (Lindane) mg/kg dry wt < 1.3 - < 1.7 - -
4,4'-DDD mg/kg dry wt < 1.3 - < 1.7 - -
4,4'-DDE mg/kg dry wt < 1.3 - < 1.7 - -
4,4'-DDT mg/kg dry wt <3 - <4 - -
Dieldrin mg/kg dry wt < 1.3 - < 1.7 - -
Endosulfan I mg/kg dry wt <3 - <4 - -
Endosulfan II mg/kg dry wt <3 - <4 - -
Endosulfan sulphate mg/kg dry wt <3 - <4 - -
Endrin mg/kg dry wt <3 - <4 - -
Endrin ketone mg/kg dry wt <3 - <4 - -
Heptachlor mg/kg dry wt < 1.3 - < 1.7 - -
Heptachlor epoxide mg/kg dry wt < 1.3 - < 1.7 - -
Hexachlorobenzene mg/kg dry wt < 1.3 - < 1.7 - -
Polycyclic Aromatic Hydrocarbons in SVOC Soil Samples by GC-MS
Acenaphthene mg/kg dry wt 9.9 - < 0.9 - -
Acenaphthylene mg/kg dry wt 8.6 - < 0.9 - -
Anthracene mg/kg dry wt 30 - < 0.9 - -
Benzo[a]anthracene mg/kg dry wt 47 - 1.7 - -
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP337 S1 0.45 TP337 S2 1.5 TP009S1 TP322 S1 0.45 TP322 S2 1.5
25-Mar-2015 25-Mar-2015 25-Mar-2015 26-Mar-2015 26-Mar-2015
Lab Number: 1402615.95 1402615.96 1402615.98 1402615.99 1402615.100
Individual Tests
Dry Matter g/100g as rcvd 91 - 74 85 -
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 5 5 4 3 9
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP323 S1 0.5 TP323 S2 1.5 TP324 S1 0.45 TP324 S2 1.5 TP325 S1 0.5
26-Mar-2015 26-Mar-2015 26-Mar-2015 26-Mar-2015 26-Mar-2015
Lab Number: 1402615.102 1402615.103 1402615.105 1402615.106 1402615.108
Individual Tests
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP325 S2 1.5 TP326 S1 0.5 TP326 S2 1.6 TP327 S1 0.5 TP327 S2 1.5
26-Mar-2015 26-Mar-2015 26-Mar-2015 26-Mar-2015 26-Mar-2015
Lab Number: 1402615.109 1402615.111 1402615.112 1402615.114 1402615.115
Individual Tests
Dry Matter g/100g as rcvd - 91 - 68 -
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 4 2 7 6 9
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
TP328 S1 0.5 TP328 S2 1.7 TP010 S1 BH338 S1 BH338 S2
26-Mar-2015 26-Mar-2015 26-Mar-2015 27-Mar-2015 27-Mar-2015
Lab Number: 1402615.117 1402615.118 1402615.120 1402615.121 1402615.122
Individual Tests
Dry Matter g/100g as rcvd 82 - 64 95 -
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 4 10 16 7 5
Total Recoverable Cadmium mg/kg dry wt < 0.10 0.13 1.10 0.20 < 0.10
Total Recoverable Chromium mg/kg dry wt 19 19 28 17 21
Total Recoverable Copper mg/kg dry wt 10 14 390 23 16
Sample Name: 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF 15:041 MSF
BH339 S1 BH339 S2 BH340 S2 BH340 S3 BH341 S2
27-Mar-2015 27-Mar-2015 27-Mar-2015 27-Mar-2015 27-Mar-2015
Lab Number: 1402615.124 1402615.125 1402615.128 1402615.129 1402615.132
Individual Tests
Dry Matter g/100g as rcvd 95 - 73 - -
Heavy metals, screen As,Cd,Cr,Cu,Ni,Pb,Zn,Hg
Total Recoverable Arsenic mg/kg dry wt 4 5 7 5 18
Total Recoverable Cadmium mg/kg dry wt < 0.10 < 0.10 < 0.10 < 0.10 < 0.10
Total Recoverable Chromium mg/kg dry wt 20 20 23 18 17
Total Recoverable Copper mg/kg dry wt 9 16 12 10 12
Total Recoverable Lead mg/kg dry wt 21 22 47 22 22
Total Recoverable Mercury mg/kg dry wt < 0.10 0.10 < 0.10 < 0.10 < 0.10
Total Recoverable Nickel mg/kg dry wt 10 15 19 13 14
1402615.16
15:041 MSF TP306 S1 0.5 23-Mar-2015
Client Chromatogram for TPH by FID
1402615.23
15:041 MSF TP308 S2 0.8 23-Mar-2015
Client Chromatogram for TPH by FID
1402615.35
15:041 MSF TP311 S2 0.8 24-Mar-2015
Client Chromatogram for TPH by FID
1402615.41
15:041 MSF TP313 S1 0.5 24-Mar-2015
Client Chromatogram for TPH by FID
1402615.59
15:041 MSF TP319 S1 0.5 24-Mar-2015
Client Chromatogram for TPH by FID
1402615.62
15:041 MSF TP320 S1 0.5 24-Mar-2015
Client Chromatogram for TPH by FID
1402615.69
15:041 MSF TP008 S1 1.5 24-Mar-2015
Client Chromatogram for TPH by FID
1402615.70
15:041 MSF TP329 S1 0.4 25-Mar-2015
Client Chromatogram for TPH by FID
1402615.80
15:041 MSF TP332 S2 0.6 25-Mar-2015
Client Chromatogram for TPH by FID
1402615.83
15:041 MSF TP333 S1 0.5 25-Mar-2015
Client Chromatogram for TPH by FID
1402615.92
15:041 MSF TP336 S1 0.5 25-Mar-2015
Client Chromatogram for TPH by FID
1402615.95
15:041 MSF TP337 S1 0.45 25-Mar-2015
Client Chromatogram for TPH by FID
1402615.114
15:041 MSF TP327 S1 0.5 26-Mar-2015
Client Chromatogram for TPH by FID
1402615.120
15:041 MSF TP010 S1 26-Mar-2015
Client Chromatogram for TPH by FID
1402615.124
15:041 MSF BH339 S1 27-Mar-2015
Client Chromatogram for TPH by FID
1402615.128
15:041 MSF BH340 S2 27-Mar-2015
Client Chromatogram for TPH by FID
SUMMARY OF METHODS
The following table(s) gives a brief description of the methods used to conduct the analyses for this job. The detection limits given below are those attainable in a relatively clean matrix.
Detection limits may be higher for individual samples should insufficient sample be available, or if the matrix requires that dilutions be performed during analysis.
These samples were collected by yourselves (or your agent) and analysed as received at the laboratory.
Samples are held at the laboratory after reporting for a length of time depending on the preservation used and the stability of
the analytes being tested. Once the storage period is completed the samples are discarded unless otherwise advised by the
client.
This report must not be reproduced, except in full, without the written consent of the signatory.
This Laboratory is accredited by International Accreditation New Zealand (IANZ), which represents New Zealand in
the International Laboratory Accreditation Cooperation (ILAC). Through the ILAC Mutual Recognition Arrangement
(ILAC-MRA) this accreditation is internationally recognised.
The tests reported herein have been performed in accordance with the terms of accreditation, with the exception of
tests marked *, which are not accredited.
Sample Type: Soil
Sample Name: 16:056 TP401 0.5 16:056 TP401 2.3 16:056 TP402 0.5 16:056 TP402 2.0
17-May-2016 17-May-2016 17-May-2016 17-May-2016
Lab Number: 1585990.1 1585990.2 1585990.3 1585990.4
Nitrogen containing compounds in SVOC Soil Samples by GC-MS
2,4-Dinitrotoluene mg/kg dry wt < 1.0 0.67 - < 1.0 0.67 -
2,6-Dinitrotoluene mg/kg dry wt < 1.0 0.67 - < 1.0 0.67 -
Nitrobenzene mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
N-Nitrosodi-n-propylamine mg/kg dry wt < 0.7 0.35 - < 0.7 0.36 -
N-Nitrosodiphenylamine + mg/kg dry wt < 0.7 0.45 - < 0.7 0.46 -
Diphenylamine
Organochlorine Pesticides in SVOC Soil Samples by GC-MS
Aldrin mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
alpha-BHC mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
beta-BHC mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
delta-BHC mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
gamma-BHC (Lindane) mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
4,4'-DDD mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
4,4'-DDE mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
4,4'-DDT mg/kg dry wt < 1.0 0.67 - < 1.0 0.67 -
Dieldrin mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
Endosulfan I mg/kg dry wt < 1.0 0.67 - < 1.0 0.67 -
Endosulfan II mg/kg dry wt < 2 1.4 - < 2 1.4 -
Endosulfan sulphate mg/kg dry wt < 1.0 0.67 - < 1.0 0.67 -
Endrin mg/kg dry wt < 0.7 0.41 - < 0.7 0.42 -
Endrin ketone mg/kg dry wt < 1.0 0.67 - < 1.0 0.67 -
Heptachlor mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
Heptachlor epoxide mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
Hexachlorobenzene mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
Polycyclic Aromatic Hydrocarbons in SVOC Soil Samples by GC-MS
Acenaphthene mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
Acenaphthylene mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
Anthracene mg/kg dry wt 0.73 0.37 - < 0.5 0.34 -
Benzo[a]anthracene mg/kg dry wt 3.7 1.3 - < 0.5 0.34 -
Benzo[a]pyrene (BAP) mg/kg dry wt 3.6 1.9 - < 0.5 0.34 -
Benzo[b]fluoranthene + Benzo[j] mg/kg dry wt 3.5 1.9 - < 0.5 0.34 -
fluoranthene
Benzo[g,h,i]perylene mg/kg dry wt 2.3 1.1 - < 0.5 0.34 -
Benzo[k]fluoranthene mg/kg dry wt 1.35 0.65 - < 0.5 0.34 -
1&2-Chloronaphthalene mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
Chrysene mg/kg dry wt 3.5 1.3 - < 0.5 0.34 -
Dibenzo[a,h]anthracene mg/kg dry wt 0.52 0.35 - < 0.5 0.34 -
Fluoranthene mg/kg dry wt 6.4 2.3 - 0.52 0.34 -
Fluorene mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
Indeno(1,2,3-c,d)pyrene mg/kg dry wt 2.3 1.5 - < 0.5 0.34 -
2-Methylnaphthalene mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
Naphthalene mg/kg dry wt < 0.5 0.34 - < 0.5 0.34 -
Phenanthrene mg/kg dry wt 1.51 0.50 - < 0.5 0.34 -
Pyrene mg/kg dry wt 7.6 2.4 - 0.63 0.36 -
Phenols in SVOC Soil Samples by GC-MS
4-Chloro-3-methylphenol mg/kg dry wt < 5 3.4 - < 5 3.4 -
2-Chlorophenol mg/kg dry wt < 1.0 0.67 - < 1.0 0.67 -
2,4-Dichlorophenol mg/kg dry wt < 1.0 0.67 - < 1.0 0.67 -
2,4-Dimethylphenol mg/kg dry wt < 3 1.2 - < 3 1.2 -
3 & 4-Methylphenol (m- + p- mg/kg dry wt < 3 1.2 - < 3 1.2 -
cresol)
2-Methylphenol (o-Cresol) mg/kg dry wt < 1.0 0.67 - < 1.0 0.67 -
2-Nitrophenol mg/kg dry wt < 5 3.4 - < 5 3.4 -
Pentachlorophenol (PCP) mg/kg dry wt < 30 68 - < 30 68 -
Phenol mg/kg dry wt < 1.0 0.67 - < 1.0 0.67 -
Sample Name: 16:056 TP403 0.5 16:056 TP403 2.0 16:056 TP404 0.4 16:056 TP404 1.8
17-May-2016 17-May-2016 17-May-2016 17-May-2016
Lab Number: 1585990.5 1585990.6 1585990.7 1585990.8
Individual Tests
Dry Matter g/100g as rcvd 84.2 5.0 - 84.6 5.0 -
Heavy Metals with Mercury, Screen Level
Total Recoverable Arsenic mg/kg dry wt 7.9 1.6 8.0 1.6 7.4 1.6 4.4 1.4
Total Recoverable Cadmium mg/kg dry wt 0.56 0.12 < 0.10 0.067 1.22 0.23 0.107 0.068
Total Recoverable Chromium mg/kg dry wt 17.7 2.3 20.3 2.5 18.9 2.4 18.0 2.3
Total Recoverable Copper mg/kg dry wt 131 19 15.5 2.6 47.2 6.8 13.9 2.4
Total Recoverable Lead mg/kg dry wt 591 83 27.8 3.9 2,120 300 45.7 6.5
Total Recoverable Mercury mg/kg dry wt 0.610 0.099 < 0.10 0.067 0.74 0.12 < 0.10 0.067
Total Recoverable Nickel mg/kg dry wt 13.6 2.4 20.8 3.2 14.0 2.4 15.6 2.6
Total Recoverable Zinc mg/kg dry wt 563 57 87.1 9.2 1,030 110 87.6 9.2
Polycyclic Aromatic Hydrocarbons Screening in Soil
Acenaphthene mg/kg dry wt < 0.03 0.0094 - 0.038 0.013 -
Acenaphthylene mg/kg dry wt 0.0584 0.0085 - 0.818 0.074 -
Anthracene mg/kg dry wt 0.098 0.031 - 1.96 0.60 -
Benzo[a]anthracene mg/kg dry wt 0.90 0.24 - 8.0 2.1 -
Benzo[a]pyrene (BAP) mg/kg dry wt 1.178 0.090 - 8.52 0.65 -
Benzo[b]fluoranthene + Benzo[j] mg/kg dry wt 1.37 0.28 - 9.4 2.0 -
fluoranthene
Benzo[g,h,i]perylene mg/kg dry wt 0.75 0.13 - 4.96 0.86 -
Benzo[k]fluoranthene mg/kg dry wt 0.462 0.059 - 3.42 0.44 -
Chrysene mg/kg dry wt 0.84 0.13 - 7.0 1.1 -
Dibenzo[a,h]anthracene mg/kg dry wt 0.103 0.015 - 0.84 0.11 -
Fluoranthene mg/kg dry wt 1.70 0.18 - 19.1 2.0 -
Sample Name: 16:056 TP405 0.6 16:056 TP405 1.8 16:056 TP406 0.5 16:056 TP406 1.8
17-May-2016 17-May-2016 17-May-2016 17-May-2016
Lab Number: 1585990.9 1585990.10 1585990.11 1585990.12
Individual Tests
Dry Matter g/100g as rcvd 70.1 5.0 - 73.2 5.0 -
Heavy Metals with Mercury, Screen Level
Total Recoverable Arsenic mg/kg dry wt 5.7 1.5 5.0 1.5 5.7 1.5 8.3 1.6
Total Recoverable Cadmium mg/kg dry wt < 0.10 0.067 < 0.10 0.067 0.125 0.069 0.101 0.067
Total Recoverable Chromium mg/kg dry wt 19.2 2.4 17.8 2.3 19.8 2.4 18.3 2.3
Total Recoverable Copper mg/kg dry wt 12.7 2.3 12.4 2.2 20.7 3.2 16.0 2.6
Total Recoverable Lead mg/kg dry wt 23.8 3.4 22.9 3.3 73 11 24.6 3.5
Total Recoverable Mercury mg/kg dry wt < 0.10 0.067 < 0.10 0.067 < 0.10 0.067 < 0.10 0.067
Total Recoverable Nickel mg/kg dry wt 15.2 2.5 15.2 2.5 15.1 2.5 15.6 2.6
Total Recoverable Zinc mg/kg dry wt 79.7 8.4 72.8 7.8 140 15 79.6 8.4
Sample Name: 16:056 TP409 0.3 16:056 TP409 0.5 16:056 TP410 0.3 16:056 TP410 0.5
17-May-2016 17-May-2016 17-May-2016 17-May-2016
Lab Number: 1585990.17 1585990.18 1585990.19 1585990.20
Individual Tests
Dry Matter g/100g as rcvd - - - 70.4 5.0
Heavy Metals with Mercury, Screen Level
Total Recoverable Arsenic mg/kg dry wt 5.0 1.5 18.8 2.3 4.4 1.4 11.2 1.8
Total Recoverable Cadmium mg/kg dry wt 0.262 0.080 1.86 0.35 0.241 0.078 1.25 0.24
Total Recoverable Chromium mg/kg dry wt 15.9 2.1 24.3 2.8 21.6 2.6 34.3 3.7
Total Recoverable Copper mg/kg dry wt 39.3 5.7 199 28 36.9 5.4 186 27
Total Recoverable Lead mg/kg dry wt 206 29 14,600 2,100 128 18 1,020 150
Total Recoverable Mercury mg/kg dry wt 0.243 0.072 8.06 0.97 0.131 0.068 13.4 1.7
Total Recoverable Nickel mg/kg dry wt 12.5 2.2 20.5 3.2 20.2 3.2 20.9 3.3
Total Recoverable Zinc mg/kg dry wt 250 26 1,750 180 135 14 622 63
Total Petroleum Hydrocarbons in Soil
C7 - C9 mg/kg dry wt - - - < 9 5.5
C10 - C14 mg/kg dry wt - - - < 20 7.7
C15 - C36 mg/kg dry wt - - - 93 12
Total hydrocarbons (C7 - C36) mg/kg dry wt - - - 93 15
Sample Name: 16:056 TP411 0.5 16:056 TP411 0.6 16:056 TP412 0.5 16:056 TP412 1.8
17-May-2016 17-May-2016 18-May-2016 18-May-2016
Lab Number: 1585990.21 1585990.22 1585990.23 1585990.24
Heavy Metals with Mercury, Screen Level
Total Recoverable Arsenic mg/kg dry wt 5.6 1.5 6.9 1.5 3.5 1.4 7.1 1.5
Total Recoverable Cadmium mg/kg dry wt 0.271 0.081 0.357 0.091 < 0.10 0.067 0.124 0.068
Total Recoverable Chromium mg/kg dry wt 16.1 2.1 15.8 2.1 13.0 1.9 18.5 2.3
Total Recoverable Copper mg/kg dry wt 39.2 5.7 37.9 5.5 7.6 1.7 13.6 2.4
Total Recoverable Lead mg/kg dry wt 222 32 361 51 27.4 3.9 21.5 3.1
Total Recoverable Mercury mg/kg dry wt < 0.10 0.067 0.138 0.068 < 0.10 0.067 < 0.10 0.067
Total Recoverable Nickel mg/kg dry wt 15.0 2.5 13.2 2.3 9.5 1.9 16.7 2.7
Total Recoverable Zinc mg/kg dry wt 228 23 267 27 53.6 6.0 75.3 8.0
Sample Name: 16:056 TP413 0.4 16:056 TP413 1.0 16:056 TP414 0.4 16:056 TP414 0.7
18-May-2016 18-May-2016 18-May-2016 18-May-2016
Lab Number: 1585990.25 1585990.26 1585990.27 1585990.28
Individual Tests
Dry Matter g/100g as rcvd 70.6 5.0 - 93.8 5.0 -
Heavy Metals with Mercury, Screen Level
Total Recoverable Arsenic mg/kg dry wt 5.6 1.5 5.3 1.5 3.0 1.4 3.2 1.4
Total Recoverable Cadmium mg/kg dry wt < 0.10 0.067 < 0.10 0.067 0.127 0.069 < 0.10 0.067
Total Recoverable Chromium mg/kg dry wt 15.7 2.1 20.2 2.5 13.6 1.9 16.2 2.1
Total Recoverable Copper mg/kg dry wt 10.8 2.0 17.6 2.8 16.3 2.7 9.7 1.9
Total Recoverable Lead mg/kg dry wt 21.0 3.0 25.2 3.6 43.8 6.2 15.3 2.2
Total Recoverable Mercury mg/kg dry wt 0.103 0.067 < 0.10 0.067 < 0.10 0.067 < 0.10 0.067
Total Recoverable Nickel mg/kg dry wt 11.9 2.2 18.5 2.9 10.5 2.0 15.4 2.6
Total Recoverable Zinc mg/kg dry wt 546 55 79.2 8.4 81.6 8.6 54.6 6.1
Sample Name: 16:056 TP416 1.7 16:056 TP401 2.4 16:056 TP406 0.55 16:056 TP409 1.8
18-May-2016 17-May-2016 17-May-2016 17-May-2016
Lab Number: 1585990.33 1585990.34 1585990.35 1585990.36
Heavy Metals with Mercury, Screen Level
Total Recoverable Arsenic mg/kg dry wt 3.1 1.4 5.9 1.5 6.8 1.5 5.9 1.5
Total Recoverable Cadmium mg/kg dry wt < 0.10 0.067 < 0.10 0.067 0.104 0.067 < 0.10 0.067
Total Recoverable Chromium mg/kg dry wt 16.8 2.2 21.0 2.5 18.4 2.3 19.8 2.4
Total Recoverable Copper mg/kg dry wt 11.5 2.1 16.0 2.6 19.9 3.1 16.0 2.6
Total Recoverable Lead mg/kg dry wt 18.2 2.6 28.4 4.0 65.8 9.3 25.4 3.6
Total Recoverable Mercury mg/kg dry wt < 0.10 0.067 < 0.10 0.067 0.103 0.067 < 0.10 0.067
Total Recoverable Nickel mg/kg dry wt 14.2 2.4 17.8 2.9 13.5 2.3 16.9 2.7
Total Recoverable Zinc mg/kg dry wt 62.1 6.8 77.3 8.2 148 15 79.4 8.4
Sample Name: 16:056 TP410 1.9 16:056 TP411 1.9 16:056 TP413 1.7 16:056 TP414 1.8
17-May-2016 18-May-2016 18-May-2016
Lab Number: 1585990.37 1585990.38 1585990.39 1585990.40
Heavy Metals with Mercury, Screen Level
Total Recoverable Arsenic mg/kg dry wt 2.5 1.4 2.5 1.4 2.6 1.4 7.5 1.6
Total Recoverable Cadmium mg/kg dry wt 0.112 0.068 < 0.10 0.067 < 0.10 0.067 < 0.10 0.067
Total Recoverable Chromium mg/kg dry wt 14.9 2.0 15.0 2.0 15.4 2.1 21.6 2.6
Total Recoverable Copper mg/kg dry wt 12.9 2.3 11.6 2.1 8.3 1.8 18.7 3.0
Total Recoverable Lead mg/kg dry wt 17.2 2.5 152 22 15.3 2.2 29.4 4.2
Total Recoverable Mercury mg/kg dry wt < 0.10 0.067 < 0.10 0.067 < 0.10 0.067 < 0.10 0.067
Total Recoverable Nickel mg/kg dry wt 14.0 2.4 12.7 2.3 14.4 2.4 18.7 3.0
Total Recoverable Zinc mg/kg dry wt 127 13 151 16 58.8 6.5 95.1 9.9
The reported uncertainty is an expanded uncertainty with a level of confidence of approximately 95 percent (i.e. two standard
deviations, calculated using a coverage factor of 2). Reported uncertainties are calculated from the performance of typical
matrices, and do not include variation due to sampling.
For further information on uncertainty of measurement at Hill Laboratories, refer to the technical note on our website:
www.hill-laboratories.com/files/Intro_To_UOM.pdf, or contact the laboratory.
1585990.5
16:056 TP403 0.5 17-May-2016
Client Chromatogram for TPH by FID
1585990.7
16:056 TP404 0.4 17-May-2016
Client Chromatogram for TPH by FID
1585990.13
16:056 TP407 0.5 17-May-2016
Client Chromatogram for TPH by FID
1585990.20
16:056 TP410 0.5 17-May-2016
Client Chromatogram for TPH by FID
SUMMARY OF METHODS
The following table(s) gives a brief description of the methods used to conduct the analyses for this job. The detection limits given below are those attainable in a relatively clean matrix.
Detection limits may be higher for individual samples should insufficient sample be available, or if the matrix requires that dilutions be performed during analysis.
These samples were collected by yourselves (or your agent) and analysed as received at the laboratory.
Samples are held at the laboratory after reporting for a length of time depending on the preservation used and the stability of
the analytes being tested. Once the storage period is completed the samples are discarded unless otherwise advised by the
client.
This report must not be reproduced, except in full, without the written consent of the signatory.
Arsenic
General Statistics
Total Number of Observations 235 Number of Distinct Observations 25
Number of Missing Observations 0
Minimum 1 Mean 7.6
Maximum 115 Median 6
SD 8.955 Std. Error of Mean 0.584
Coefficient of Variation 1.178 Skewness 8.276
Gamma Statistics
k hat (MLE) 2.133 k star (bias corrected MLE) 2.108
Theta hat (MLE) 3.564 Theta star (bias corrected MLE) 3.605
nu hat (MLE) 1002 nu star (bias corrected) 990.9
MLE Mean (bias corrected) 7.6 MLE Sd (bias corrected) 5.234
Approximate Chi Square Value (0.05) 918.8
Adjusted Level of Significance 0.049 Adjusted Chi Square Value 918.4
Lognormal Statistics
Minimum of Logged Data 0 Mean of logged Data 1.776
Maximum of Logged Data 4.745 SD of logged Data 0.661
Note: Suggestions regarding the selection of a 95% UCL are provided to help the user to select the most appropriate 95% UCL.
These recommendations are based upon the results of the simulation studies summarized in Singh, Singh, and Iaci (2002)
and Singh and Singh (2003). However, simulations results will not cover all Real World data sets.
For additional insight the user may want to consult a statistician.
Cadmium
General Statistics
Total Number of Observations 235 Number of Distinct Observations 45
Number of Missing Observations 0
Minimum 0.045 Mean 0.182
Maximum 2.8 Median 0.05
SD 0.358 Std. Error of Mean 0.0233
Coefficient of Variation 1.965 Skewness 4.681
Gamma Statistics
k hat (MLE) 0.866 k star (bias corrected MLE) 0.858
Theta hat (MLE) 0.21 Theta star (bias corrected MLE) 0.212
nu hat (MLE) 407 nu star (bias corrected) 403.2
MLE Mean (bias corrected) 0.182 MLE Sd (bias corrected) 0.196
Approximate Chi Square Value (0.05) 357.6
Adjusted Level of Significance 0.049 Adjusted Chi Square Value 357.4
Lognormal Statistics
Minimum of Logged Data -3.101 Mean of logged Data -2.382
Maximum of Logged Data 1.03 SD of logged Data 0.949
Note: Suggestions regarding the selection of a 95% UCL are provided to help the user to select the most appropriate 95% UCL.
These recommendations are based upon the results of the simulation studies summarized in Singh, Singh, and Iaci (2002)
and Singh and Singh (2003). However, simulations results will not cover all Real World data sets.
For additional insight the user may want to consult a statistician.
Chromium
General Statistics
Total Number of Observations 235 Number of Distinct Observations 24
Number of Missing Observations 0
Minimum 10 Mean 18.58
Maximum 46 Median 18
SD 4.787 Std. Error of Mean 0.312
Coefficient of Variation 0.258 Skewness 2.399
Gamma Statistics
k hat (MLE) 18.55 k star (bias corrected MLE) 18.32
Theta hat (MLE) 1.002 Theta star (bias corrected MLE) 1.014
nu hat (MLE) 8718 nu star (bias corrected) 8608
MLE Mean (bias corrected) 18.58 MLE Sd (bias corrected) 4.341
Approximate Chi Square Value (0.05) 8394
Adjusted Level of Significance 0.049 Adjusted Chi Square Value 8392
Lognormal Statistics
Minimum of Logged Data 2.303 Mean of logged Data 2.895
Maximum of Logged Data 3.829 SD of logged Data 0.226
Assuming Lognormal Distribution
95% H-UCL 19.02 90% Chebyshev (MVUE) UCL 19.38
95% Chebyshev (MVUE) UCL 19.76 97.5% Chebyshev (MVUE) UCL 20.28
99% Chebyshev (MVUE) UCL 21.31
Note: Suggestions regarding the selection of a 95% UCL are provided to help the user to select the most appropriate 95% UCL.
These recommendations are based upon the results of the simulation studies summarized in Singh, Singh, and Iaci (2002)
and Singh and Singh (2003). However, simulations results will not cover all Real World data sets.
For additional insight the user may want to consult a statistician.
Copper
General Statistics
Total Number of Observations 235 Number of Distinct Observations 60
Number of Missing Observations 0
Minimum 4 Mean 100.3
Maximum 15600 Median 14
SD 1020 Std. Error of Mean 66.52
Coefficient of Variation 10.16 Skewness 15.14
Gamma Statistics
k hat (MLE) 0.379 k star (bias corrected MLE) 0.377
Theta hat (MLE) 265 Theta star (bias corrected MLE) 266.5
nu hat (MLE) 177.9 nu star (bias corrected) 177
MLE Mean (bias corrected) 100.3 MLE Sd (bias corrected) 163.5
Approximate Chi Square Value (0.05) 147.2
Adjusted Level of Significance 0.049 Adjusted Chi Square Value 147.1
Note: Suggestions regarding the selection of a 95% UCL are provided to help the user to select the most appropriate 95% UCL.
These recommendations are based upon the results of the simulation studies summarized in Singh, Singh, and Iaci (2002)
and Singh and Singh (2003). However, simulations results will not cover all Real World data sets.
For additional insight the user may want to consult a statistician.
Lead
General Statistics
Total Number of Observations 234 Number of Distinct Observations 129
Number of Missing Observations 0
Minimum 11 Mean 200.8
Maximum 7900 Median 28
SD 683.9 Std. Error of Mean 44.71
Coefficient of Variation 3.405 Skewness 7.851
Gamma Statistics
k hat (MLE) 0.454 k star (bias corrected MLE) 0.451
Theta hat (MLE) 442.8 Theta star (bias corrected MLE) 445.7
nu hat (MLE) 212.3 nu star (bias corrected) 210.9
MLE Mean (bias corrected) 200.8 MLE Sd (bias corrected) 299.2
Approximate Chi Square Value (0.05) 178.3
Adjusted Level of Significance 0.049 Adjusted Chi Square Value 178.1
Lognormal Statistics
Minimum of Logged Data 2.398 Mean of logged Data 3.881
Maximum of Logged Data 8.975 SD of logged Data 1.34
Note: Suggestions regarding the selection of a 95% UCL are provided to help the user to select the most appropriate 95% UCL.
These recommendations are based upon the results of the simulation studies summarized in Singh, Singh, and Iaci (2002)
and Singh and Singh (2003). However, simulations results will not cover all Real World data sets.
For additional insight the user may want to consult a statistician.
Mercury
General Statistics
Total Number of Observations 235 Number of Distinct Observations 44
Number of Missing Observations 0
Minimum 0.045 Mean 0.294
Maximum 13.4 Median 0.05
SD 1.249 Std. Error of Mean 0.0814
Coefficient of Variation 4.248 Skewness 8.311
Gamma Statistics
k hat (MLE) 0.517 k star (bias corrected MLE) 0.513
Theta hat (MLE) 0.569 Theta star (bias corrected MLE) 0.573
nu hat (MLE) 243 nu star (bias corrected) 241.2
MLE Mean (bias corrected) 0.294 MLE Sd (bias corrected) 0.41
Approximate Chi Square Value (0.05) 206.3
Adjusted Level of Significance 0.049 Adjusted Chi Square Value 206.1
Assuming Gamma Distribution
95% Approximate Gamma UCL (use when n>=50)) 0.344 95% Adjusted Gamma UCL (use when
0.344
n<50)
Lognormal Statistics
Minimum of Logged Data -3.101 Mean of logged Data -2.447
Maximum of Logged Data 2.595 SD of logged Data 1.048
Note: Suggestions regarding the selection of a 95% UCL are provided to help the user to select the most appropriate 95% UCL.
These recommendations are based upon the results of the simulation studies summarized in Singh, Singh, and Iaci (2002)
and Singh and Singh (2003). However, simulations results will not cover all Real World data sets.
For additional insight the user may want to consult a statistician.
Nickel
General Statistics
Total Number of Observations 235 Number of Distinct Observations 27
Number of Missing Observations 0
Minimum 8 Mean 15.63
Maximum 66 Median 14
SD 6.725 Std. Error of Mean 0.439
Coefficient of Variation 0.43 Skewness 3.578
Gamma Statistics
k hat (MLE) 8.616 k star (bias corrected MLE) 8.509
Theta hat (MLE) 1.815 Theta star (bias corrected MLE) 1.837
nu hat (MLE) 4049 nu star (bias corrected) 3999
MLE Mean (bias corrected) 15.63 MLE Sd (bias corrected) 5.36
Approximate Chi Square Value (0.05) 3853
Adjusted Level of Significance 0.049 Adjusted Chi Square Value 3852
Lognormal Statistics
Minimum of Logged Data 2.079 Mean of logged Data 2.69
Maximum of Logged Data 4.19 SD of logged Data 0.318
Note: Suggestions regarding the selection of a 95% UCL are provided to help the user to select the most appropriate 95% UCL.
These recommendations are based upon the results of the simulation studies summarized in Singh, Singh, and Iaci (2002)
and Singh and Singh (2003). However, simulations results will not cover all Real World data sets.
For additional insight the user may want to consult a statistician.
Zinc
General Statistics
Total Number of Observations 235 Number of Distinct Observations 118
Number of Missing Observations 0
Minimum 34 Mean 183
Maximum 2600 Median 83
SD 324 Std. Error of Mean 21.14
Coefficient of Variation 1.771 Skewness 4.776
Gamma Statistics
k hat (MLE) 1.095 k star (bias corrected MLE) 1.083
Theta hat (MLE) 167.2 Theta star (bias corrected MLE) 168.9
nu hat (MLE) 514.4 nu star (bias corrected) 509.2
MLE Mean (bias corrected) 183 MLE Sd (bias corrected) 175.8
Approximate Chi Square Value (0.05) 457.9
Adjusted Level of Significance 0.049 Adjusted Chi Square Value 457.6
Lognormal Statistics
Minimum of Logged Data 3.526 Mean of logged Data 4.687
Maximum of Logged Data 7.863 SD of logged Data 0.826
Note: Suggestions regarding the selection of a 95% UCL are provided to help the user to select the most appropriate 95% UCL.
These recommendations are based upon the results of the simulation studies summarized in Singh, Singh, and Iaci (2002)
and Singh and Singh (2003). However, simulations results will not cover all Real World data sets.
For additional insight the user may want to consult a statistician.
B(a)P eq
General Statistics
Total Number of Observations 60 Number of Distinct Observations 40
Number of Missing Observations 0
Minimum 0.302 Mean 5.564
Maximum 114.1 Median 0.97
SD 17.11 Std. Error of Mean 2.209
Coefficient of Variation 3.075 Skewness 5.47
Gamma Statistics
k hat (MLE) 0.534 k star (bias corrected MLE) 0.518
Theta hat (MLE) 10.42 Theta star (bias corrected MLE) 10.73
nu hat (MLE) 64.08 nu star (bias corrected) 62.21
MLE Mean (bias corrected) 5.564 MLE Sd (bias corrected) 7.728
Approximate Chi Square Value (0.05) 45.07
Adjusted Level of Significance 0.046 Adjusted Chi Square Value 44.71
Lognormal Statistics
Minimum of Logged Data -1.197 Mean of logged Data 0.539
Maximum of Logged Data 4.737 SD of logged Data 1.221
Note: Suggestions regarding the selection of a 95% UCL are provided to help the user to select the most appropriate 95% UCL.
These recommendations are based upon the results of the simulation studies summarized in Singh, Singh, and Iaci (2002)
and Singh and Singh (2003). However, simulations results will not cover all Real World data sets.
For additional insight the user may want to consult a statistician.
REPORT
1 Introduction 1
1.1 Background 1
1.2 Objective and scope of work 2
1.3 Regulatory compliance 3
2 Site description 4
2.1 Surrounding land use 4
2.2 Geology 4
2.3 Hydrogeology and hydrology 4
2.4 Site history 5
3 Field investigations 6
3.1 Sampling plan and rationale 6
3.2 Investigation method 6
3.2.1 Sampling methodology 6
3.3 Observations 8
3.3.1 Phase 1 8
3.3.2 Phase 2 8
3.3.3 Phase 3 8
3.3.4 Phase 4 10
4 Laboratory testing 11
4.1 Assessment criteria 11
4.2 Results 12
4.2.1 Phase 1 12
4.2.2 Phase 2 13
4.2.3 Phase 3 14
4.2.4 Phase 4 16
5 Discussion and implications 18
5.1 Nature and extent of contamination 18
5.2 Human health risk 19
5.3 Management of human health risk 19
5.3.1 Long term 19
5.3.2 Interim 19
5.4 Regulatory and development requirements 20
5.4.1 Asbestos Regulations (2016) 20
5.4.2 NES Soil 20
5.4.3 Regional and district plans 20
5.4.4 Works and development constraints 21
6 Conclusions 23
7 Applicability 25
1 Introduction
Tonkin & Taylor Ltd (T&T) has been engaged by karo Limited to undertake an investigation of
asbestos in soil at the proposed Metro Sports Facility (MSF, the site), Christchurch. Figure 1 shows
the location of the site.
The asbestos investigation has being undertaken in phases as a result of a staged demolition
programme. This report provides results of all four Phases (1 4) in accordance with of our proposal
dated 28 May 2014. One small area remains un-investigated as indicated on Figure 1 (non-hashed
area) and on Figure 2 (labelled).
1.1 Background
karo Limited is developing the site for the Metro Sports Facility (MFS). The site was formerly
occupied by the Canterbury Brewery and other commercial/industrial operations.
Beca produced a Preliminary Site Investigation (PSI)1 for the site that identified a number of historic
land uses included on the Ministry for the Environment (MfE) Hazardous Activities and Industries List
(HAIL), activities known to potentially to cause ground contamination. Beca has undertaken a
Detailed Site Investigation (DSI)2 to investigate further the potential for ground contamination, other
than asbestos, and the implications any might have on development of the MFS.
1 Beca, 2014: Metro Sports Facility Taiwhanga Rehia - Preliminary Site Investigation (Contamination), Prepared for
Canterbury Earthquake Recovery Authority, 12 June 2014.
2 Beca, 2016: Detailed Site Investigation (Contamination), Metro Sports Facility, Prepared for karo Limited, 30 June
2016.
Many of the buildings within the MSF contained asbestos containing materials (ACM). The presence
of ACM in a deteriorating condition and demolition activities themselves can cause contamination of
soils by asbestos fibres as well as fragments of bonded products. The asbestos-in-soils investigation
reported here was undertaken concurrent with the Beca DSI and reports on investigations in the
Phase 1 4 area as shown in Figures 2 and 3.
An outstanding area of the site that has not been subject to investigations is shown on Figures 1 4.
Figure 2: Site layout prior to demolition and delineation of Phase 1-3 areas (Source: Google Earth)
3 Ministry for the Environment, revised 2011: Contaminated Land Management Guideline No. 5 Site Investigation and
Analysis of Soils
4 Western Australian Department of Health, 2009: Guidelines for Assessment, Remediation and Management of Asbestos-
2 Site description
The site is located within Christchurch City and is bounded by St Asaph Street, Antigua Street,
Moorhouse Ave and part of Stewart Street (refer Figure 2). The site is approximately 71,703 m 2 in
area. There are around 46 individual property titles within the MSF landholding encompassing the
following street addresses:
26 36 St Asaph Street;
16 28 Stewart Street;
2 28 Balfour Terrace;
3 19 Horatio Street;
103 139 Moorhouse Avenue;
185 189 Antigua Street.
Full legal descriptions of the site are provided in the Beca DSI.
At the time of preparing this report all structures (excluding fencing) have been removed. The site
surfacing comprises a mixture of hard surfaces such as residual concrete and asphalt along with
crushed demolition material including concrete, some plastics and tiles and run-of-pit quarry rock.
At the time of preparation of this report land at 26 36 St Asaph Street and 161 189 Antigua Street
is being used by Canterbury District Health Board (CDHB) for public and staff parking, The balance of
land is fenced and vacant (unused).
2.2 Geology
Published geology for the site is described by Forsyth et al 5 as grey river alluvium beneath plains or
low-level terraces (refer geological map, Figure 3). Onsite this is expressed as natural gravelly silt
and silt that is in places overlain by historic fill materials (gravelly silt with some deleterious
materials) and hardfill (crushed demolition material including concrete, some plastics and tiles and
run-of-pit quarry rock).
5 Forsyth, P.J.; Barrell, D.J.A.; Jongens, R. (compilers) 2008. Geology of the Christchurch area. Institute of Geological &
Nuclear Sciences
6 Environment Canterbury; GIS viewer; http://canterburymaps.co.nz/Portal/FlexViewer/Index.html
3 Field investigations
Field investigations were undertaken by contaminated land specialists from Tonkin & Taylor in four
stages:
Phase 1 21 to 24 July 2014;
Phase 2 3 to 4 November 2014;
Phase 3 23 to 27 March 2015; and
Phase 4 17 and 18 May 2016.
The work was undertaken in conjunction with Beca ground contamination investigations and
involved an initial detailed site walkover and soil sampling from test pits and boreholes.
LEGEND
ANTIGUA STREE
STEWART STREET
PHASE 1
BH339
TP111
TP113 TP114 TP115
TP112
T
TP120
TP116 TP119
TP118
BH341 TP117
TP226 TP227
TP122 TP124 185-189
TP225 Antigua Street
TP228
PHASE 4 TP121
TP123 TP125 PHASE 2
TP126
TP224
BALFOUR STREET
TP216
TP306
TP215 TP220 TP223
TP308 TP312 TP318 TP320
PHASE 2 TP305
TP307 PHASE 3
TP214 PHASE 2
16-24 Stewart Street TP311
TP316 TP319
TP212 TP213
TP302 TP221 TP222
TP304 TP313 TP317
TP309 TP321
TP209
TP303
TP301 TP310 TP314 TP315
3-26 Horatio Street HORATIO STREET
TP409 TP408 TP406
TP411 TP404
TP325 TP405
TP208 TP414
TP202 TP203 TP410 TP407
PHASE 4
TP326 TP401
TP324
TP207 PHASE 4 TP332
TP323 TP402
TP415 TP329 TP403
TP413
PHASE 2 TP206 TP327 PHASE 3 TP333 TP336
TP412
TP201 TP204 TP416 TP335
TP205 TP328
TP331 TP337
TP322 TP334
TP330
161-163 Antigua Street
101-103
125-139 Moorhouse Avenue
Moorhouse Avenue
L:\53556\CAD\FIGS\53556-DSI-F4.dwg F4 4/07/2016 3:55:57 p.m.
MOORHOUSE AVENUE
3.3 Observations
3.3.1 Phase 1
Recycled crushed concrete demolition fill, mixed with run-of-pit quarry rock, is present across the
whole Phase 1 area to varying depths, typically around 300 mm thick but extending up to 2.5 m
below existing ground level. The recycled crushed demolition materials, in the top 300 mm of the
profile, are consistent in nature across the Phase 1 area.
An underlying layer of older pre-demolition fill was observed in seven of the test pits, primarily
located on the northern half of the site.
Natural soil comprising silt was encountered in most test pits, except TP105 and TP110. The natural
silt varies in depth from 0.3 m below ground level to greater than 2.5 m below ground level. A list of
the samples taken and their lithology is provided in Table 2.
No suspected ACM fragments were noted during visual inspection of the site surface and excavated
material from each test pit, nor was any ACM visible in the >7 mm fraction during sieving.
3.3.2 Phase 2
Observations over the Phase 2 area differed slightly as illustrated below.
101-103 Moorhouse Avenue: A relatively uniform layer of imported quarry-source hardfill
(greywacke gravel; 0.3 0.4 m thick) is present across the surface of this area, generally
overlying natural silty sand. Demolition fill (as indicated by the presence of brick, timber and
metal fragments) was observed in three of the seven test pits, between 0.4 to 1.2 m bgl.
Natural silts were encountered between 0.4 and 1.2 m below ground level. A list of the
samples taken and their lithology is provided in Table 3.
Suspected, and later confirmed (refer Section 4), ACM fragments were abundant in the west
of the 101-103 Moorhouse Avenue block with occasional fragments also noted in the east of
the same block (refer Figure 5 for fragment locations). An area of concentrated ACM
fragments was noted in the west of the block (refer Photograph 1 and Figure 5) outside the
area used at that time by Wilsons as a public carpark. Hand digging at this location
determined the sheeting materials likely extended to 150-300 mm depth below ground level.
16-24 Stewart Street: Imported quarry-source hardfill (greywacke gravels, some silt) is
present across the area, ranging from 0.3 to 0.9 m thick. The gravelly fill directly overlies
natural materials, comprised of silts and sands with some gravels. Clayey materials, along with
tree roots and branches, were encountered near the bottom (0.9-1.9 m bgl) of all four test pits
excavated in the block nearest Antigua Street (TP220-TP223).
185-189 Antigua Street: A layer of imported quarry-source hardfill (greywacke gravel; 0.4
0.7 m thick) is present across the area, generally underlain by natural silty clays. Pre-
demolition fill was encountered in the northwest corner (TP226) of this block, between 0.7
and 1.5 m deep.
3.3.3 Phase 3
Observations over the Phase 3 area differed slightly as illustrated below.
3-26 Horatio Street: Recycled crushed demolition fill (sandy gravel with crushed demolition
wastes) is present across the area, between 0.2 0.5 m thick, generally underlain by natural
silty/sandy materials.
Demolition materials were encountered within the silts below the upper hardfill layer in
TP301, TP302, TP304, TP314, TP320 and TP321. The maximum depth that demolition
materials were encountered in these test pits was 0.7 m bgl. A layer of demolition fill was
encountered in TP311, between 0.7-0.9 m bgl. This contained brick, steel and ceramics within
a silty matrix.
125-139 Moorhouse Ave and 161-163 Antigua Street inclusive: A layer of demolition/hardfill
between 0.25-0.5 m thick, overlies natural sandy/silty materials in TP322, TP325, TP327,
TP328, TP331, TP333, and TP334.
Varying fill materials principally comprising gravelly inclusions within a silt matrix were
between 0.45-0.7 m across the remainder of the area.
Suspected, and later confirmed (refer Section 4), ACM fragments were noted on the ground
surface around an existing building at 139 Moorhouse Avenue and 161 Antigua Street and
noted as cladding materials on the building (refer Figure 5 for locations of ACM fragments).
No other fragments of suspected ACM were observed in the Phase 3 area. A further building
with suspected asbestos cladding remained at the boundary between the Phase 3 and 4 area
at 161 Antigua Street (refer Figure 4).
26 St Asaph Street (CDHB carpark): Surface materials on the western portion of this area
(BH338 and BH339) comprised of 0.35-0.4 m of quarry-source hardfill overlying natural silts,
while the eastern portion (BH340 and BH341) had 1-1.5 m of recycled crushed demolition fill
overlying natural silts; some core-loss was experienced, thus 1.5 m is an upper estimate of fill
depth at BH341.
Photograph 1: ACM pieces in the west of 101-103 Moorhouse Avenue (refer Figure 5).
Photograph 2: ACM fragments at 139 Moorhouse Avenue and 161 Antigua Street.
3.3.4 Phase 4
A similar subsurface profile was observed across the Phase 4 area, that comprising hardfill (either
quarry rock or crushed demolition materials) underlain by a thin (up to 400 mm) layer of historic fill.
Historic fill contained metal, brick, glass, ceramics in a gravelly organic silt matrix. At one location
(TP408) a residual topsoil layer was noted at 350 mm bgl. Fill materials were underlain by silt and
river gravels.
One ACM fragment was noted and collected from the surface at 169 Antigua Street.
4 Laboratory testing
To date 188 samples have been tested for asbestos over the investigated areas (refer Figure 4).
Laboratory testing was undertaken at IANZ accredited Precise Consulting & Laboratory Ltd in
Christchurch. Full laboratory transcripts from Precise Consulting and Laboratory are available in
Appendices A-D.
Testing was predominantly for the quantitative assessment of asbestos content. However, samples
collected from the four boreholes were tested qualitatively (presence or absence) for asbestos as
insufficient material for quantitative testing was able to be extracted. Representative samples of
ACM fragments observed at discrete positions within the Phase 2 and 3 areas were also tested
qualitatively for asbestos presence (refer Table 1 and Appendix A).
All sample analysis was performed using polarised light microscopy with dispersion staining in
compliance with AS4964-2004 Method for the qualitative identification of asbestos in bulk samples.
In accordance with the WA guidance2 quantitative assessment was made in terms of the weight of
asbestos, reported for the 2-7 mm sub sample and < 2 mm sub sample.
7 MfE, Hierarchy and Application in New Zealand of Environmental Guideline Values (Revised 2011)
8 Resource Management (National Environmental Standard for Assessing and Managing Contaminants in Soil to Protect
Human Health) Regulations 2011
9 NEPM, 2013, Schedule B1, Guideline for Investigation Levels for Soil and Groundwater
10 WA guidance and NEPM defines AF as free fibres of asbestos, small fibre bundles and also ACM fragments that pass
that it can be broken or crumbled by hand pressure), and asbestos in the form of loose fibrous material such as insulation
products
4.2 Results
For each sieved sample collected, the laboratory then further sieves the sample into two fractions,
2-7 mm and <2 mm. Both fractions are referred to as AF/FA. Results for these two sieved fractions
are provided in Tables 2-4 below.
4.2.1 Phase 1
The laboratory results for the Phase 1 area, summarised in Table 2 below, show that:
In 10 surface samples chrysotile (white asbestos) AF/ FA was detected;
At 3 of the 10 locations where asbestos was detected (test pits TP105, TP107 and TP113)
asbestos fibre concentrations are greater than the assessment criteria relevant for all site uses
(0.001%).
The location of the samples containing asbestos fibres is shown in Figure 5.
Table notes:
Results expressed as %
Bold values exceed the assessment criteria
4.2.2 Phase 2
The laboratory results for the Phase 2 area, summarised in Table 3 below, show that:
Surface hardfill at 2 locations (testpits TP203 and TP228) contain chrysotile (white asbestos)
AF/ FA either as free fibres or cement bound.
Asbestos fibre concentrations are at or below the assessment criteria relevant for all site uses
(0.001%).
Discrete cement sheeting fragments collected from the surface of 101-103 Moorhouse Avenue (not
included in Table 3 below but included on laboratory transcripts in Appendix B) returned positive for
the presence of chrysotile, amosite and crocidolite asbestos.
4.2.3 Phase 3
The laboratory results for the Phase 3 area, summarised in Table 4 below show that:
In 9 samples chrysotile asbestos fibres were detected, including one sample also containing
crocidolite AF/ FA:
All 9 samples where asbestos was detected contained free fibres in either the 2-7 mm fraction
or the <2 mm fraction, at or below the acceptance criteria of 0.001%;
In all but one sample (TP301) fibres were detected in the surface hardfill.
4.2.4 Phase 4
The laboratory results for the Phase 4 area, summarised in Table 5 below show that:
In 4 samples AF/ FA exceeded the risk based criteria;
In a further 8 samples asbestos was detected but below the risk based criteria; and
In one sample (TP404) bonded ACM in the >7 mm fraction was detected in surface hardfill.
At discrete locations within the Phase 2 and 3 areas (refer Figure 5) there are ACM fragments at
surface. Trafficking over these materials could result in them breaking up and fibres becoming
airborne.
5.3.2 Interim
There is currently interim use of the MSF land. Given that asbestos fines, and in localised areas
bonded ACM, are present control and implementation of management measures is required to
mitigate against the generation of dust and to protect site users and the general public from
exposure to asbestos fines.
Interim remediation works along with air monitoring were undertaken following identification of
asbestos within investigation areas Phase 1 - 3. The remedial works were completed as soon as
practicable following identification. A summary of the works undertaken in detailed in a letter
report prepared by T&T entitled Metro Sports Facility, Interim Remedial Measures Implemented,
(dated 30 June 2015).
An Interim Site Management Plan (ISMP) for ground contaminating was prepared for CERA (now
Otakaro Ltd) in January 201612. The ISMP sets out procedures for use of the site in the interim until
development of the MSF commences.
12 T+T, 2016: Report prepared for CERA Metro Sports Facility, Interim Site Management Plan Ground contamination,
January 2016, T+T ref. 52556.002.
13 Position Statement Remediating asbestos contaminated sites (third edition, April 2016)
14 Resource Management (National Environmental Standard for Assessing and Managing Contaminants in Soils to Protect
Environment Canterbury (ECan) Regional Plans have rules pertaining to protection of ground and
surface water. ACM identified at the site is shallow, thus impacts on groundwater are considered
unlikely. Thus consent applications for the MSF are unlikely to require groundwater-related consent
in respect of asbestos. Consent for construction-phase stormwater discharges for any proposed
works would however be required. The construction-phase stormwater consents are to ensure
management of potential contaminants in surface water and authorise any subsequent offsite
discharges of stormwater during temporary works.
LEGEND
Asbestos detected
PHASE 3
PHASE 1
BH339
TP112
TP111
TP113 TP114 TP115
TP119 TP120
TP116 TP118
TP117
BH341
TP226 TP227
TP121 TP124
ANTIGUA STREE
TP122 TP225 TP228
TP125
PHASE 4
TP123
TP126 PHASE 2
TP224
BALFOUR STREET
T
TP216
TP306
TP215
TP308 TP312 TP318 TP320
TP220 TP223
PHASE 2 TP305
TP307 PHASE 3
TP214 PHASE 2
TP311 TP319
TP316
TP213
TP212 TP304 TP313 TP222
TP302 TP317 TP321 TP221
TP309
Concentration of
HORATIO STREET
ACM fragments TP409 TP408 TP406
TP411 TP325
TP208 TP404
TP414 TP405
TP326
TP410 TP324 TP407
TP202 TP203 PHASE 4
TP401
TP332
PHASE 4 TP323 TP329
TP207 TP402
TP415 TP413 TP403
TP327
PHASE 2 TP206 PHASE 3 TP336
TP333
TP412
TP201 TP328 TP335
TP204 TP416 TP331
TP205
TP337
TP322 TP330 TP334
L:\53556\CAD\FIGS\53556-DSI-F5.dwg F5 4/07/2016 3:55:07 p.m.
MOORHOUSE AVENUE
6 Conclusions
This detailed site investigation (asbestos) was undertaken to confirm whether asbestos is present at
the Metro Sports Facility site as a result of historic use and recent demolition of buildings containing
asbestos containing materials (ACM). The investigation has been undertaken in general accordance
with a DSI as described in the NES for Assessing and Managing Contaminants in Soil Users Guide
(2012) and MfE Guidelines for Reporting on Contaminated Sites in New Zealand.
The key findings of the investigations are that:
Of the 104 surface samples tested 31 detected the presence of asbestos fines, with 9 of these
(within the Phase 1 and 4 areas) containing asbestos fibre concentrations greater than the risk
based acceptance criteria for all uses of 0.001%;
Non-visible fragments of ACM, greater than the sieved fraction of 7 mm, were detected at
surface within the 101-103 Moorhouse Avenue block and at 169 Antigua Street. Visible
fragments of ACM were also noted and as indicated in the Tonkin & Taylor remedial works
update letter dated 30 June 2015. Visible fragments were removed immediately during and
following the Phase 2 and 4 investigation works (November 2014 and May 2016);
Visible fragments noted around buildings at 139 Moorhouse Avenue and 161 Antigua Street,
as documented in the Tonkin & Taylor remedial works update letter dated 30 June 2015 were
removed during the Phase 4 demolition works and confirmed during the Phase 4
investigations.
Underlying silty fill containing minor demolition materials (historic fill) was tested for the
presence of asbestos fibres and only 1 of the 68 tested contained fibres. The concentration of
fibres in that sample was well below the risk based acceptance criteria of 0.001%;
The results indicate that for the Phase 1 and 4 areas there is potential for human health
effects from asbestos in surface hardfill. The key risk identified was the potential for fibres to
become airborne and be inhaled by people during disturbance of surface materials such as
vehicle parking and during future construction. As detailed in the Tonkin & Taylor remedial
works update letter dated 30 June 2015 a polymer was added to the surface of the Phase 1
area as an interim dust suppressant so that it could be used for vehicle parking. An interim site
management plan for ground contamination was prepared by T+T in January 2016 and the
measures in this plan have been implemented.
Long-term remedial options for the site are to be set out under a separate cover. Given the
bulk of detected asbestos was below the risk based criteria, onsite retention is a viable option.
Consents under the NES Soil Regulation, District Plan and Regional Plans Regulatory will be
required for the development works in respect of asbestos contamination present on the
Metro Sports Facility site. To support consent applications and construction works an
Asbestos Site Management Plan (ASMP) will need to be prepared. The ASMP will need to be
prepared by a suitably qualified contaminated land practitioner according to MfE
Contaminated land Management Guidelines, NES Soil and the Asbestos Regulation (2016);
Given the levels of asbestos present are generally below the risk based criteria, areas of the
MSF works may not be subject to Class A removal controls (Asbestos Regulations), instead
asbestos-related-works measures may be relevant. Worksafe NZ will need to be kept
informed of the progress, during consenting and pre-works to ensure the ASMP complies with
their requirements. The contractor undertaking the development works will need to take all
practicable steps to manage potential effects, of which management of dust is the key human
health related risk. The ASMP will be require to set out procedures for managing and
monitoring dust during the development;
Disposal of asbestos containing soils, even those where fibre content is below the risk based
criteria, during development could be expensive as currently the only location available for
disposal of ACM is Kate Valley Landfill;
On completion of development of the Metro Sports Facility remedial works in respect of
asbestos will need to be documented in a Site Validation report (SVR) and provided to Council
so that the LLUR can be updated to reflect the new condition of the site;
If contaminated materials are contained onsite then a Long Term Monitoring and
Management Plan would also be required to ensure containment measures are maintained.
7 Applicability
This report has been prepared for the benefit of our client karo Limited with respect to the
particular brief given to us and it may not be relied upon in other contexts or for any other purpose
without our prior review and agreement.
Recommendations and opinions in this report are based on the visual inspections, exploratory test
pit, borehole and testing data. The nature and continuity of subsoil away from the sample locations
are inferred and it must be appreciated that actual conditions could vary from the assumed model.
The persons undertaking, managing reviewing and certifying this report are suitably qualified and
experienced practitioners as defined in the NES Soil.
Report prepared by: Authorised for Tonkin & Taylor Ltd by:
.......................................................... .................................................
Wendi Williamson Peter Cochrane
Senior Contaminated Land Specialist Project Director
wmw
\\ttgroup.local\corporate\christchurch\tt projects\53556\issueddocuments\phase 1-4 dsi\wmw050616.dsi.final.docx
Twelve (12) samples were received on Thursday, 24th July 2014 by Laura Viney.
The results of fibre analysis were performed by Adam Maurice of Precise Consulting and Laboratory Ltd.
The address for the samples was not stated on submitted chain of custody.
The sampling method is independent of Precise Consulting and Laboratories and is outside the scope of
IANZ accreditation #1097. Sample analysis was performed using polarised light microscopy with
dispersion staining in accordance with Precise Consulting and Laboratory test Method: LAB0002 Asbestos
Identification Analysis and in compliance of AS4964-2004 Method for the qualitative identification of
asbestos in bulk samples.
The results of the fibre analysis are presented in the appended table.
Yours sincerely
..
Adam Maurice
PRECISE LABORATORY IDENTIFIER
Page 1 of 5
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Accredited by International Accreditation New Zealand (IANZ)
Page 2 of 5
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Accredited by International Accreditation New Zealand (IANZ)
Page 3 of 5
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Accredited by International Accreditation New Zealand (IANZ)
Sample result is lower than the limit of detection for this method.
Page 4 of 5
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Accredited by International Accreditation New Zealand (IANZ)
Note 1: The reporting limit for this analysis is 0.1g/kg (0.01%) by application of polarised light microscopy, dispersion
staining and trace analysis techniques.
Note 2: Confirmation by another analytical technique may be required due to nature of the sample.
Note 3: Mineral fibres of unknown type detected by PLM and dispersion staining may or may not be asbestos fibres.
To confirm the identity of this fibre, another independent analytical technique such as XRD analysis is advised.
Note 4: The samples in this report as reported As Received Precise Consulting does not take responsibility for the
sampling procedure or accuracy of sample location description as these have been provided by the client.
This document may not be reproduced except in full.
. .
Adam Maurice (Dip. Lab Tech) Joseph Feltham (B.E. (Env))
Approved Identifier Key Technical Person
Page 5 of 5
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Appendix 1
Page 1 of 1
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Accredited by International Accreditation New Zealand (IANZ)
Seven (7) samples were received on Monday, 21st July 2014 by Laura Viney.
The results of fibre analysis were performed by Adam Maurice of Precise Consulting and Laboratory Ltd.
A site address was not supplied for the original location of the samples.
The sampling method is independent of Precise Consulting and Laboratories and is outside the scope of
IANZ accreditation #1097. Sample analysis was performed using polarised light microscopy with
dispersion staining in accordance with Precise Consulting and Laboratory test Method: LAB0002 Asbestos
Identification Analysis and in compliance of AS4964-2004 Method for the qualitative identification of
asbestos in bulk samples.
The results of the fibre analysis are presented in the appended table.
Yours sincerely
..
Adam Maurice
PRECISE LABORATORY IDENTIFIER
Page 1 of 5
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Version 2.0 July 2014
Accredited by International Accreditation New Zealand (IANZ)
Page 2 of 5
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Version 2.0 July 2014
Accredited by International Accreditation New Zealand (IANZ)
0.013g
Non-homogenous Soil Chrysotile (White Asbestos) <0.001g
ID003717.5 TP118 Fibrous 98.18g
722.24g Organic Fibres Free Fibres
Material
Sample result is lower than the limit of detection for this method.
Page 3 of 5
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Version 2.0 July 2014
Accredited by International Accreditation New Zealand (IANZ)
Note 1: The reporting limit for this analysis is 0.1g/kg (0.01%) by application of polarised light microscopy, dispersion
staining and trace analysis techniques.
Note 2: Mineral fibres of unknown type detected by PLM and dispersion staining may or may not be asbestos fibres.
To confirm the identity of this fibre, another independent analytical technique such as XRD analysis is advised.
Note 3: The samples in this report as reported As Received Precise Consulting does not take responsibility for the
sampling procedure or accuracy of sample location description as these have been provided by the client.
This document may not be reproduced except in full.
. .
Adam Maurice (Dip. Lab Tech) Joseph Feltham (B.E. (Env))
Approved Identifier Key Technical Person
Page 4 of 5
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Version 2.0 July 2014
Appendix 1
Note: Method for asbestos % determination is outside the scope of IANZ accreditation #1097 and
Is therefore not endorsed by IANZ.
Page 1 of 1
Precise Consulting & Laboratory Limited Unit 5 / 161 Waltham Rd, Sydenham Christchurch City, 8023
P: (03) 669 2721 M: 022 108 1904 W: www.preciseconsulting.co.nz
Appendix B: Phase 2 laboratory transcripts
DATE: 10/11/2014
33 Parkhouse Road
Wigram
Christchurch
Twenty-six (26) samples were received on Monday, 3rd November 2014 by Laura Viney.
The results of fibre analysis were performed by Adam Maurice of Precise Consulting and Laboratory Ltd.
The address for the samples were not stated on submitted chain of custody.
The sampling method is independent of Precise Consulting and Laboratorys, and is outside the scope of, IANZ accreditation
#1097.Sample analysis was performed using polarised light microscopy with dispersion staining in accordance with Precise
Consulting and laboratory test method: LAB002 Asbestos Identification Analysis and following the guidelines of AS4964-2004
The results of the fibre analysis are presented in the appended table.
Yours sincerely
ADAM MAURICE
<2mm
Client Sample
Sample ID Sample Location/Description/Dimensions Analysis Results 2-7mm Sub-sample <2mm
Number
Weight (g)
TP201 SURF
No Asbestos Detected No Asbestos No Asbestos
ID005976.1 TP201 - SURF Non-homogenous Soil 105.64g
Organic Fibres Detected Detected
905.15g
TP201 SUB
No Asbestos Detected No Asbestos No Asbestos
ID005976.3 TP201 - SUB Non-homogenous Soil 105.92g
Organic Fibres Detected Detected
323.84g
TP202 SURF
No Asbestos Detected No Asbestos No Asbestos
ID005976.4 TP202 - SURF Non-homogenous Soil 107.73g
Organic Fibres Detected Detected
575.20g
TP202 SUB
No Asbestos Detected No Asbestos No Asbestos
ID005976.6 TP202 - SUB Non-homogenous Soil 101.64g
Organic Fibres Detected Detected
401.06g
TP203 SURF
Chrysotile (White Asbestos) 0.011g No Asbestos
ID005976.7 TP203 - SURF Non-homogenous Soil 105.87g
Organic Fibres Cement Sheet Detected
886.02g
TP203 SURF
Chrysotile (White Asbestos)
ID005976.8 TP203 SURF >7mm Fragments N/A N/A N/A
Organic Fibres
8.55g
TP203 SUB
No Asbestos Detected No Asbestos No Asbestos
ID005976.9 TP203 - SUB Non-homogenous Soil 105.00g
Organic Fibres Detected Detected
544.83g
TP204 SURF
No Asbestos Detected No Asbestos No Asbestos
ID005976.10 TP204 - SURF Non-homogenous Soil 106.98g
Organic Fibres Detected Detected
840.23g
TP204 SUB
No Asbestos Detected No Asbestos No Asbestos
ID005976.11 TP204 - SUB Non-homogenous Soil 102.95g
Organic Fibres Detected Detected
339.08g
TP205 SUB
No Asbestos Detected No Asbestos No Asbestos
ID005976.13 TP205 - SUB Non-homogenous Soil 102.78g
Organic Fibres Detected Detected
500.88g
TP206 SURF
No Asbestos Detected No Asbestos No Asbestos
ID005976.14 TP206 - SURF Non-homogenous Soil 104.44g
Organic Fibres Detected Detected
788.16g
TP206 SUB
No Asbestos Detected No Asbestos No Asbestos
ID005976.15 TP206 - SUB Non-homogenous Soil 98.50g
Organic Fibres Detected Detected
549.74g
TP208 SURF
No Asbestos Detected No Asbestos No Asbestos
ID005976.16 TP208 - SURF Non-homogenous Soil 100.62g
Organic Fibres Detected Detected
862.62g
TP208 SUB
No Asbestos Detected No Asbestos No Asbestos
ID005976.17 TP208 - SUB Non-homogenous Soil 101.62g
Organic Fibres Detected Detected
523.66g
TP209 SURF
No Asbestos Detected No Asbestos No Asbestos
ID005976.18 TP209 - SURF Non-homogenous Soil 106.64g
Organic Fibres Detected Detected
787.45g
TP212 SURF
No Asbestos Detected No Asbestos No Asbestos
ID005976.20 TP212 - SURF Non-homogenous Soil 100.33g
Organic Fibres Detected Detected
802.52g
TP212 SURF
No Asbestos Detected
ID005976.21 TP212 - SURF >7mm Fragments N/A N/A N/A
Organic Fibres
38.52g
TP212 SUB
No Asbestos Detected No Asbestos No Asbestos
ID005976.22 TP212 - SUB Non-homogenous Soil 100.80g
Organic Fibres Detected Detected
478.43g
TP213 SURF
No Asbestos Detected No Asbestos No Asbestos
ID005976.23 TP213 - SURF Non-homogenous Soil 107.01g
Organic Fibres Detected Detected
740.52g
TP213 SUB
No Asbestos Detected No Asbestos No Asbestos
ID005976.24 TP213 - SUB Non-homogenous Soil 104.54g
Organic Fibres Detected Detected
483.62g
Note 2: If mineral fibres of unknown type are detected (UMF), by PLM and dispersion staining, these may or may not be asbestos
fibres. To confirm the identity of these fibres, another independent analytical technique such as XRD analysis is advised.
Note 3: The samples in this report are reported As Received and Precise Consulting does not take responsibility for the sampling
procedure or accuracy of the sample location description, as these have been provided by the client.
Client
Sample ID Sample Fraction and % Asbestos
Number
Fragments
ID005976.25 >7mm Fragments Cement Sheet 35%
(1-4)
Note: Method for asbestos percentage determination is outside the scope of IANZ accreditation #1097 and is therefore
not endorsed by IANZ.
33 Parkhouse Rd
Wigram
Twenty-four (24) samples were received on Tuesday, 4th November 2014 by Laura Viney.
The results of fibre analysis were performed by Adam Maurice of Precise Consulting and Laboratory Ltd.
The address for the samples were not stated on submitted chain of custody.
The sampling method is independent of Precise Consulting and Laboratorys, and is outside the scope of, IANZ accreditation
#1097.Sample analysis was performed using polarised light microscopy with dispersion staining in accordance with Precise
Consulting and laboratory test method: LAB002 Asbestos Identification Analysis and following the guidelines of AS4964-2004
The results of the fibre analysis are presented in the appended table.
Yours sincerely
ADAM MAURICE
Client <2mm
Sample ID Sample Sample Location/Description/Dimensions Analysis Results 2-7mm Sub-sample <2mm
Number Weight (g)
TP214 SURF
TP214 No Asbestos Detected No Asbestos No Asbestos
ID005976.27 Non-homogenous Soil 100.07g
SURF Organic Fibres Detected Detected
618.80g
TP214 SUB
TP214 No Asbestos Detected No Asbestos No Asbestos
ID005976.28 Non-homogenous Soil 107.03g
SUB Organic Fibres Detected Detected
630.64g
TP215 SUB
TP215 No Asbestos Detected No Asbestos No Asbestos
ID005976.30 Non-homogenous Soil 102.04g
SUB Organic Fibres Detected Detected
448.50g
TP216 SUB
TP216 No Asbestos Detected No Asbestos No Asbestos
ID005976.32 Non-homogenous Soil 99.15g
SUB Organic Fibres Detected Detected
469.23g
TP220 SURF
TP220 No Asbestos Detected No Asbestos No Asbestos
ID005976.33 Non-homogenous Soil 106.16g
SURF Organic Fibres Detected Detected
714.27g
TP220 SUB
TP220 No Asbestos Detected No Asbestos No Asbestos
ID005976.34 Non-homogenous Soil 98.35g
SUB Organic Fibres Detected Detected
446.13g
TP221 SURF
TP221 No Asbestos Detected No Asbestos No Asbestos
ID005976.35 Non-homogenous Soil 105.30g
SURF Organic Fibres Detected Detected
662.82g
TP221 SUB
TP221 No Asbestos Detected No Asbestos No Asbestos
ID005976.36 Non-homogenous Soil 104.02g
SUB Organic Fibres Detected Detected
685.43g
TP222 SURF
TP222 No Asbestos Detected No Asbestos No Asbestos
ID005976.37 Non-homogenous Soil 103.21g
SURF Organic Fibres Detected Detected
695.30g
TP223 SURF
TP223 No Asbestos Detected No Asbestos No Asbestos
ID005976.39 Non-homogenous Soil 104.01g
SURF Organic Fibres Detected Detected
657.46g
TP223 SUB
TP223 No Asbestos Detected No Asbestos No Asbestos
ID005976.40 Non-homogenous Soil 102.99g
SUB Organic Fibres Detected Detected
612.67g
TP224 SURF
TP224 No Asbestos Detected No Asbestos No Asbestos
ID005976.41 Non-homogenous Soil 100.57g
SURF Organic Fibres Detected Detected
583.22g
TP224 SURF
TP224 No Asbestos Detected
ID005976.42 >7mm Fragments N/A N/A N/A
SURF Organic Fibres
11.03g
TP224 SUB
TP224 No Asbestos Detected No Asbestos No Asbestos
ID005976.43 Non-homogenous Soil 102.45g
SUB Organic Fibres Detected Detected
356.28g
TP224 SUB
TP224 No Asbestos Detected
ID005976.44 >7mm Fragments N/A N/A N/A
SUB Organic Fibres
31.46g
TP225 SUB
TP225 No Asbestos Detected No Asbestos No Asbestos
ID005976.46 Non-homogenous Soil 104.03g
SUB Organic Fibres Detected Detected
494.50g
TP226 SURF
TP226 No Asbestos Detected No Asbestos No Asbestos
ID005976.47 Non-homogenous Soil 104.63g
SURF Organic Fibres Detected Detected
759.95g
TP226 SUB
TP226 No Asbestos Detected No Asbestos No Asbestos
ID005976.48 Non-homogenous Soil 107.03g
SUB Organic Fibres Detected Detected
635.57g
TP227 SURF
TP227 - No Asbestos Detected No Asbestos No Asbestos
ID005976.49 Non-homogenous Soil 105.48g
SURF Organic Fibres Detected Detected
690.59g
TP227 SUB
TP227 - No Asbestos Detected No Asbestos No Asbestos
ID005976.50 Non-homogenous Soil 105.14g
SUB Organic Fibres Detected Detected
666.88g
TP228 SURF
TP228 - Chrysotile (White Asbestos) 0.159g <0.001g
ID005976.51 Non-homogenous Soil 98.28g
SURF Organic Fibres Free Fibres Free Fibres
654.85g
TP228 SUB
TP228 - No Asbestos Detected No Asbestos No Asbestos
ID005976.53 Non-homogenous Soil 98.38g
SUB Organic Fibres Detected Detected
571.66g
* Sample result is lower than the limit of detection for this method.
Note 2: If mineral fibres of unknown type are detected (UMF), by PLM and dispersion staining, these may or may not be asbestos
fibres. To confirm the identity of these fibres, another independent analytical technique such as XRD analysis is advised.
Note 3: The samples in this report are reported As Received and Precise Consulting does not take responsibility for the sampling
procedure or accuracy of the sample location description, as these have been provided by the client.
Client
Sample ID Sample Fraction and % Asbestos
Number
Note: Method for asbestos percentage determination is outside the scope of IANZ accreditation #1097 and is therefore
not endorsed by IANZ.
33 Parkhouse Road
Wigram 8042
Christchurch
Eighteen (18) samples were received on Tuesday, 24th March 2015 by Nikita Davis.
The results of fibre analysis were performed by Adam Maurice of Precise Consulting and Laboratory Ltd.
The address for the samples were not stated on submitted chain of custody.
The sampling method is independent of Precise Consulting and Laboratorys, and is outside the scope of, IANZ accreditation
#1097. Sample analysis was performed using polarised light microscopy with dispersion staining in accordance with Precise
Consulting and laboratory test method: LAB002 Asbestos Identification Analysis and following the guidelines of AS4964-2004
The results of the fibre analysis are presented in the appended table.
Yours sincerely
ADAM MAURICE
Client <2mm
Sample ID Sample Sample Location/Description/Dimensions Analysis Results 2-7mm Sub-sample <2mm
Number Weight (g)
TP304 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007513.7 TP304 Non-homogenous Soil 103.68g
Organic Fibres Detected Detected
708.56g
TP304 0.4-0.5
No Asbestos Detected No Asbestos No Asbestos
ID007513.8 TP304 Non-homogenous Soil 102.75g
Organic Fibres Detected Detected
546.10g
TP305 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007513.9 TP305 Non-homogenous Soil 104.71g
Organic Fibres Detected Detected
812.63g
* Sample result is lower than the limit of detection for this method.
Note 2: If mineral fibres of unknown type are detected (UMF), by PLM and dispersion staining, these may or may not be asbestos
fibres. To confirm the identity of these fibres, another independent analytical technique such as XRD analysis is advised.
Note 3: The samples in this report are reported As Received and Precise Consulting does not take responsibility for the sampling
procedure or accuracy of the sample location description, as these have been provided by the client.
Client
Sample ID Sample Fraction and % Asbestos
Number
Note: Method for asbestos percentage determination is outside the scope of IANZ accreditation #1097 and is therefore
not endorsed by IANZ.
33 Parkhouse Road
Wigram 8042
Christchurch
Twenty Five (25) samples were received on Tuesday, 24th March 2015 by Nikita Davis.
The results of fibre analysis were performed by Adam Maurice of Precise Consulting and Laboratory Ltd.
The address for the samples were not stated on submitted chain of custody.
The sampling method is independent of Precise Consulting and Laboratorys, and is outside the scope of, IANZ accreditation
#1097. Sample analysis was performed using polarised light microscopy with dispersion staining in accordance with Precise
Consulting and laboratory test method: LAB002 Asbestos Identification Analysis and following the guidelines of AS4964-2004
The results of the fibre analysis are presented in the appended table.
Yours sincerely
ADAM MAURICE
Client <2mm
Sample ID Sample Sample Location/Description/Dimensions Analysis Results 2-7mm Sub-sample <2mm
Number Weight (g)
TP314 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007515.10 TP314 Non-homogenous Soil 104.21g
Organic Fibres Detected Detected
892.97g
* Sample result is lower than the limit of detection for this method.
Note 2: If mineral fibres of unknown type are detected (UMF), by PLM and dispersion staining, these may or may not be asbestos
fibres. To confirm the identity of these fibres, another independent analytical technique such as XRD analysis is advised.
Note 3: The samples in this report are reported As Received and Precise Consulting does not take responsibility for the sampling
procedure or accuracy of the sample location description, as these have been provided by the client.
Client
Sample ID Sample Fraction and % Asbestos
Number
Note: Method for asbestos percentage determination is outside the scope of IANZ accreditation #1097 and is therefore
not endorsed by IANZ.
33 Parkhouse Road
Wigram 8042
Christchurch
Nineteen (19) samples were received on Wednesday, 25th March 2015 by Nikita Davis.
The results of fibre analysis were performed by Adam Maurice of Precise Consulting and Laboratory Ltd.
The address for the samples were not stated on submitted chain of custody.
The sampling method is independent of Precise Consulting and Laboratorys, and is outside the scope of, IANZ accreditation
#1097. Sample analysis was performed using polarised light microscopy with dispersion staining in accordance with Precise
Consulting and laboratory test method: LAB002 Asbestos Identification Analysis and following the guidelines of AS4964-2004
The results of the fibre analysis are presented in the appended table.
Yours sincerely
ADAM MAURICE
Client <2mm
Sample ID Sample Sample Location/Description/Dimensions Analysis Results 2-7mm Sub-sample <2mm
Number Weight (g)
TP336 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007519.1 TP336 Non-homogenous Soil 100.58g
Organic Fibres Detected Detected
979.91g
TP336 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007519.2 TP336 Non-homogenous Soil 100.17g
Organic Fibres Detected Detected
784.99g
TP337 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007519.3 TP337 Non-homogenous Soil 100.30g
Organic Fibres Detected Detected
959.47g
TP337 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007519.4 TP337 Non-homogenous Soil 100.76g
Organic Fibres Detected Detected
796.03g
TP335 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007519.6 TP335 Non-homogenous Soil 102.08g
Organic Fibres Detected Detected
388.32g
TP334 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007519.7 TP334 Non-homogenous Soil 102.53g
Organic Fibres Detected Detected
1142.62g
TP334 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007519.8 TP334 Non-homogenous Soil 103.68g
Organic Fibres Detected Detected
1180.47g
TP333 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007519.9 TP333 Non-homogenous Soil 102.72g
Organic Fibres Detected Detected
1037.79g
TP333 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007519.10 TP333 Non-homogenous Soil 102.77g
Organic Fibres Detected Detected
886.01g
TP332 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007519.11 TP332 Non-homogenous Soil 100.48g
Organic Fibres Detected Detected
675.72g
TP332 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007519.13 TP332 Non-homogenous Soil 123.72g
Organic Fibres Detected Detected
964.55g
TP331 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007519.14 TP331 Non-homogenous Soil 100.97g
Organic Fibres Detected Detected
693.14g
TP331 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007519.15 TP331 Non-homogenous Soil 103.33g
Organic Fibres Detected Detected
1127.16g
TP330 SURF
Chrysotile (White Asbestos) No Asbestos <0.001g*
ID007519.16 TP330 Non-homogenous Soil 104.70g
Organic Fibres Detected Free Fibres
840.91g
TP330 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007519.17 TP330 Non-homogenous Soil 100.45g
Organic Fibres Detected Detected
488.22g
TP329 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007519.18 TP329 Non-homogenous Soil 101.52g
Organic Fibres Detected Detected
694.65g
* Sample result is lower than the limit of detection for this method.
Note 2: If mineral fibres of unknown type are detected (UMF), by PLM and dispersion staining, these may or may not be asbestos
fibres. To confirm the identity of these fibres, another independent analytical technique such as XRD analysis is advised.
Note 3: The samples in this report are reported As Received and Precise Consulting does not take responsibility for the sampling
procedure or accuracy of the sample location description, as these have been provided by the client.
Client
Sample ID Sample Fraction and % Asbestos
Number
Note: Method for asbestos percentage determination is outside the scope of IANZ accreditation #1097 and is therefore
not endorsed by IANZ.
33 Parkhouse Road
Wigram 8042
Christchurch
Fourteen (14) samples were received on Thursday, 26th March 2015 by Nikita Davis.
The results of fibre analysis were performed by Adam Maurice of Precise Consulting and Laboratory Ltd.
The address for the samples were not stated on submitted chain of custody.
The sampling method is independent of Precise Consulting and Laboratorys, and is outside the scope of, IANZ accreditation
#1097. Sample analysis was performed using polarised light microscopy with dispersion staining in accordance with Precise
Consulting and laboratory test method: LAB002 Asbestos Identification Analysis and following the guidelines of AS4964-2004
The results of the fibre analysis are presented in the appended table.
Yours sincerely
ADAM MAURICE
Client <2mm
Sample ID Sample Sample Location/Description/Dimensions Analysis Results 2-7mm Sub-sample <2mm
Number Weight (g)
TP322 SURF
Chrysotile (White Asbestos) No Asbestos <0.001g*
ID007521.1 TP322 Non-homogenous Soil 101.62g
Organic Fibres Detected Free Fibres
1061.39g
TP322 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007521.2 TP322 Non-homogenous Soil 101.26g
Organic Fibres Detected Detected
840.72
TP323 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007521.3 TP323 Non-homogenous Soil 103.68g
Organic Fibres Detected Detected
872.28g
TP323 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007521.4 TP323 Non-homogenous Soil 100.70g
Organic Fibres Detected Detected
801.55g
TP324 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007521.6 TP324 Non-homogenous Soil 101.37g
Organic Fibres Detected Detected
311.76g
TP325 SURF
Chrysotile (White Asbestos) No Asbestos <0.001g*
ID007521.7 TP325 Non-homogenous Soil 104.15g
Organic Fibres Detected Free Fibres
835.28g
TP325 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007521.8 TP325 Non-homogenous Soil 101.67g
Organic Fibres Detected Detected
1276.05g
TP326 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007521.9 TP326 Non-homogenous Soil 104.31g
Organic Fibres Detected Detected
920.51g
TP326 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007521.10 TP326 Non-homogenous Soil 103.5g
Organic Fibres Detected Detected
916.11g
TP327 SURF
Chrysotile (White Asbestos) No Asbestos <0.001g*
ID007521.11 TP327 Non-homogenous Soil 106.61g
Organic Fibres Detected Free Fibres
862.39g
TP328 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007521.13 TP328 Non-homogenous Soil 104.06g
Organic Fibres Detected Detected
843.29g
TP328 SUB
No Asbestos Detected No Asbestos No Asbestos
ID007521.14 TP328 Non-homogenous Soil 100.06g
Organic Fibres Detected Detected
808.68g
* Sample result is lower than the limit of detection for this method.
Note 2: If mineral fibres of unknown type are detected (UMF), by PLM and dispersion staining, these may or may not be asbestos
fibres. To confirm the identity of these fibres, another independent analytical technique such as XRD analysis is advised.
Note 3: The samples in this report are reported As Received and Precise Consulting does not take responsibility for the sampling
procedure or accuracy of the sample location description, as these have been provided by the client.
Client
Sample ID Sample Fraction and % Asbestos
Number
Note: Method for asbestos percentage determination is outside the scope of IANZ accreditation #1097 and is therefore
not endorsed by IANZ.
33 Parkhouse Road
Wigram 8042
Christchurch
Eight (8) samples were received on Friday, 27th March 2015 by Nikita Davis.
The results of fibre analysis were performed by Tim Trembath of Precise Consulting and Laboratory Ltd.
The address for the samples were not stated on submitted chain of custody.
The sampling method is independent of Precise Consulting and Laboratorys, and is outside the scope of, IANZ accreditation
#1097. Sample analysis was performed using polarised light microscopy with dispersion staining in accordance with Precise
Consulting and laboratory test method: LAB002 Asbestos Identification Analysis and following the guidelines of AS4964-2004
The results of the fibre analysis are presented in the appended table.
Yours sincerely
TIM TREMBATH
Client <2mm
Sample ID Sample Sample Location/Description/Dimensions Analysis Results 2-7mm Sub-sample <2mm
Number Weight (g)
BH 338 SURF
No Asbestos Detected
ID007522.1 BH 338 Non-homogenous Soil N/A N/A N/A
Organic Fibres
484.82g
BH 338 SUB
No Asbestos Detected N/A N/A N/A
ID007522.2 BH 338 Non-homogenous Soil
Organic Fibres
164.61g
BH 339 SURF
No Asbestos Detected
ID007522.3 BH 339 Non-homogenous Soil N/A N/A N/A
Organic Fibres
872.06g
BH339 SUB
No Asbestos Detected
ID007522.4 BH 339 Non-homogenous Soil N/A N/A N/A
Organic Fibres
354.08g
BH 340 SUB
No Asbestos Detected
ID007522.6 BH 340 Non-homogenous Soil N/A N/A N/A
Organic Fibres
320.39g
BH 341 SURF
No Asbestos Detected No Asbestos No Asbestos
ID007522.7 BH 341 Non-homogenous Soil 102.02g
Organic Fibres Detected Detected
1119.08g
BH 341 SUB
No Asbestos Detected
ID007522.8 BH 341 Non-homogenous Soil N/A N/A N/A
Organic Fibres
363.47g
* Sample result is lower than the limit of detection for this method.
Note 2: If mineral fibres of unknown type are detected (UMF), by PLM and dispersion staining, these may or may not be asbestos
fibres. To confirm the identity of these fibres, another independent analytical technique such as XRD analysis is advised.
Note 3: The samples in this report are reported As Received and Precise Consulting does not take responsibility for the sampling
procedure or accuracy of the sample location description, as these have been provided by the client.
Client
Sample ID Sample Fraction and % Asbestos
Number
Note: Method for asbestos percentage determination is outside the scope of IANZ accreditation #1097 and is therefore
not endorsed by IANZ.
33 Parkhouse Road
Wigram
Christchurch
8042
The results of fibre analysis were performed by Andy Straker of Precise Consulting and Laboratory Ltd on 24th May 2016.
Sample analysis was performed using polarised light microscopy with dispersion staining in accordance with the guidelines of
AS4964-2004 Method for the qualitative identification of asbestos in bulk samples.
The results of the fibre analysis are presented in the appended table.
Yours sincerely
Andy Straker
PRECISE LABORATORY IDENTIFIER
21 June 2016
Note 1: The reporting limit for this analysis is 0.1g/kg (0.01%) by application of polarised light microscopy, dispersion staining
and trace analysis techniques.
Note 2: If mineral fibres of unknown type are detected (UMF), by PLM and dispersion staining, these may or may not be
asbestos fibres. To confirm the identity of this fibre, another independent analytical technique such as XRD analysis is
advised.
Note 3: The samples in this report are As Received the laboratory does not take responsibility for the sampling procedure
or accuracy of sample location description.
This document may not be reproduced except in full.
Client
Sample
Sample ID Sample Analysis Results
Location/Description/Dimensions
Number
Chrysotile
TP401-
BS049689 Non-Homogeneous Soil (White Asbestos)
0.1
579.65g Organic Fibre Type
Unsieved
TP401- No Asbestos Detected
BS049690 Non-Homogeneous Soil
0.5 Organic Fibre Type
941.96g
21 June 2016
Client
Sample
Sample ID Sample Analysis Results
Location/Description/Dimensions
Number
Chrysotile
TP402-
BS049691 Non-Homogeneous Soil (White Asbestos)
0.1
857.61g Organic Fibre Type
Unsieved
TP402- No Asbestos Detected
BS049692 Non-Homogeneous Soil
0.3 Organic Fibre Type
1010.25g
Chrysotile + Amosite
TP403- (White & Brown
BS049693 Non-Homogeneous Soil
0.1 Asbestos)
682.31g
Organic Fibre Type
Unsieved
TP403- No Asbestos Detected
BS049694 Non-Homogeneous Soil
0.3 Organic Fibre Type
840.12g
Amosite + Chrysotile +
Crocidolite
TP404-
BS049695 Non-Homogeneous Soil (Brown,White & Blue
0.1
1147.94g Asbestos)
Organic Fibre Type
Unsieved
TP404- No Asbestos Detected
BS049696 Non-Homogeneous Soil
0.3 Organic Fibre Type
1194.65g
21 June 2016
Client
Sample
Sample ID Sample Analysis Results
Location/Description/Dimensions
Number
Chrysotile + Amosite
TP405- (White & Brown
BS049697 Non-Homogeneous Soil
0.1 Asbestos)
359.08g
Organic Fibre Type
Unsieved
TP405- No Asbestos Detected
BS049698 Non-Homogeneous Soil
0.3 Organic Fibre Type
891.52g
Chrysotile
TP406- (White Asbestos)
BS049699 Non-Homogeneous Soil
0.1 Man-Made Mineral Fibre
698.50g
Organic Fibre Type
Unsieved
TP406- No Asbestos Detected
BS049700 Non-Homogeneous Soil
0.3 Organic Fibre Type
1045.41g
Chrysotile
TP407-
BS049701 Non-Homogeneous Soil (White Asbestos)
0.1
640.20g Organic Fibre Type
Unsieved
TP407- No Asbestos Detected
BS049702 Non-Homogeneous Soil
0.4 Organic Fibre Type
685.91g
21 June 2016
Client
Sample
Sample ID Sample Analysis Results
Location/Description/Dimensions
Number
No Asbestos Detected
TP408-
BS049703 Non-Homogeneous Soil Man-Made Mineral Fibre
0.1
590.25g Organic Fibre Type
Amosite + Chrysotile +
Crocidolite
TP409-
BS049705 Non-Homogeneous Soil (Brown,White & Blue
0.1
716.48g Asbestos)
Organic Fibre Type
Unsieved
TP409- No Asbestos Detected
BS049706 Non-Homogeneous Soil
0.4 Organic Fibre Type
843.95g
No Asbestos Detected
TP410-
BS049707 Non-Homogeneous Soil Man-Made Mineral Fibre
0.1
791.07g Organic Fibre Type
21 June 2016
Client
Sample
Sample ID Sample Analysis Results
Location/Description/Dimensions
Number
Chrysotile
Unsieved
TP411- (White Asbestos)
BS049710 Non-Homogeneous Soil
0.7 Man-Made Mineral Fibre
1155.73g
Organic Fibre Type
Chrysotile
TP412-
BS049711 Non-Homogeneous Soil (White Asbestos)
0.1
731.29g Organic Fibre Type
Unsieved Chrysotile
TP412-
BS049712 Non-Homogeneous Soil (White Asbestos)
0.8
889.22g Organic Fibre Type
21 June 2016
Client
Sample
Sample ID Sample Analysis Results
Location/Description/Dimensions
Number
Chrysotile
TP414-
BS049715 Non-Homogeneous Soil (White Asbestos)
0.1
711.05g Organic Fibre Type
Unsieved
TP414- No Asbestos Detected
BS049716 Non-Homogeneous Soil
0.5 Organic Fibre Type
997.73g
Unsieved
TP415- No Asbestos Detected
BS049718 Non-Homogeneous Soil
0.5 Organic Fibre Type
911.56g
Unsieved
TP416- No Asbestos Detected
BS049720 Non-Homogeneous Soil
0.5 Organic Fibre Type
823.87g
1 Introduction 1
1.1 Background 1
1.2 Site identification 1
1.3 Purpose and scope 1
2 Proposed activities 2
2.1 Works overview 2
2.2 Construction activities 2
2.3 Construction programme 3
3 Discharges to air 4
3.1 Potential dust sources 4
3.2 Factors influencing dust generation 4
3.3 Contaminated dust 5
4 Environmental Setting 6
4.1 Adjacent activities and sensitivity to dust 6
4.2 Meteorology and topography 7
5 Assessment of environmental effects 9
5.1 Assessment methodology 9
5.2 Potential effects of dust emissions 9
5.3 Identified effects of discharges from the preceding early works phase 10
5.4 Potential effects of residual contaminated dust emissions 10
5.5 Consideration of FIDOL factors and summary of dust nuisance effects 11
6 Mitigation and alternatives 13
6.1 Dust control measures 13
6.2 Construction Dust Management Plan 14
7 Conclusions 15
8 Applicability 16
1 Introduction
1.1 Background
karo Limited proposes to construct the Metro Sports Facility (herein referred to as the site or
MSF) at the block bordered by Moorhouse Avenue, Antigua Street and St Asaph Street in the
Christchurch Central Business District.
As an anchor project of the Christchurch rebuild, the MSF will house an aquatic and indoor
recreation and leisure centre, outdoor recreation areas and car parking. Enabling works are currently
underway and resource consents are now being sought for the subsequent construction phase.
The consent requirements include resource consent for discharges of dust to air from the
construction phase. Tonkin & Taylor Ltd (T+T) has been commissioned by karo Limited to prepare
this assessment of the impacts of the dust discharges on air quality to inform the application for this
consent.
Resource consent CRC173564 was granted in December 2016 for the purpose: To discharge dust to
air associated with site remediation for the site. This application is to authorise the subsequent
discharges from the construction phase of the project.
2 Proposed activities
3 Discharges to air
1 T+T. 2017. Metro Sports Facility - Construction Phase: Site Management Plan for Ground Contamination.
4 Environmental Setting
The site is located in the Central City Mixed Used Zone under the new Christchurch City District Plan.
The site is located within the Christchurch Airshed as gazetted under the Resource Management
(National Environmental Standards for Air Quality) Regulations 2004 (NESAQ). The site is located
within the Christchurch/ tautahi Clean Air Zone under the pCARP.
As noted in section 5.1, the majority of dust emissions from construction activities at the site are
likely to deposit out of air within 100 m of the discharge point. An illustration of the area within
100 m of the site is provided in Appendix B. The zoning and activities within 100 m of the site include
the following:
The adjacent properties to the east (across Antigua St) and west also lie within the Central City
Mixed Used Zone and are occupied by a range of commercial and light industrial activities.
Activities are likely to range in sensitivity to dust from food outlets (high sensitivity) to light
industrial and workshop activities (relatively low sensitivity). Activities such as motor vehicle
retail may also be particularly sensitivity to dust deposition on cars. The Central City Mixed
Used Zone also allows residential activities, and a dwelling was identified in the application for
consent CRC173564 for the remediation phase dust discharges. This residential property and
any others that may be present in the area are likely to be highly sensitive to dust. The
Majestic Church located at the corner of Moorhouse Avenue and Waller Terrace was also
identified as a sensitive receptor in the previous application. However although this site will
be used regularly for public congregation, the church is housed within a former commercial
building and is likely to have moderate sensitivity to dust similar to commercial office
activities.
Health activities associated with Christchurch Hospital, including eye care and endocrinology
are located to the north across St Asaph St. These activities are likely to be of high sensitivity
to dust. The energy centre (including large scale combustion appliances) servicing the hospital
is located at the corner of St Asaph and Antigua Streets.
Hagley Community College (Central City Education Zone) is located to northwest and is also
likely to be reasonably sensitive to dust emissions.
Overall, the area surrounding the site currently features or is intended to feature a variety of
activities, ranging from low to high sensitivity to dust. Sensitivity to dust is likely to be highest at the
hospital facilities to the north of St Asaph Street and where (if) residential activities occur in the
mixed use zone. Sensitivity to dust may also be elevated at Hagley Community College to the
northwest and at certain commercial activities such as food outlets and car yards within the
surrounding commercial areas.
Figure 2: Frequency of wind speeds and directions measured at Christchurch Airport in 2012 (1-hour average
data)
This meteorological monitoring station is situated approximately 9 km to the northwest of the site.
Given the lack of topographical variation between central Christchurch and the airport, wind
direction observations at the airport are likely to be broadly representative of conditions at the site.
However, given the airport site is generally free of adjacent buildings and structure, measured wind
speeds are likely to be higher than those that occur in central Christchurch.
As illustrated in Figure 2, there is a reasonably strong prevalence of winds from the northeast. This is
also the predominant direction for fresh to strong winds (of speeds greater than 5 m/s), in which
dust transport is most likely to occur. There is secondary prevalence of wind from the southwest
quadrant in winds observed at Christchurch Airport and little wind from the southeast quadrant.
wind speed conditions). The effects of deposited dust are therefore generally localised within this
distance. Potential nuisance and property effects of deposited dust include the visible soiling of
surfaces such as house, furniture, cars and the visible deposition of dust on flowers and vegetable
gardens.
Deposited dust can also impact on visibility when it is re-entrained by wind or vehicle movements.
While most dust is generally biologically inert in nature, the extent of soiling may increase corrosion
or damage protective surface coatings such as paintwork. High levels of dust deposition on plants
have been shown to reduce plant growth and the effectiveness of pesticide sprays and increase the
incidence of plant pests and diseases all of which results in reduced product quality (McCrea, 1984,
cited in MfE, 2001).
5.3 Identified effects of discharges from the preceding early works phase
The early works/site remediation phase of the MSF development (and associated dust discharges)
have been undertaken under consent CRC173564 since January 2017. This phase of work involves
similar dust generating activities to those described in section 3.1.
Given the similarity of activities over the two project phases, the nature and scale of dust effects
observed during the preceding phase is likely to provide an indication of potential effects during the
construction phase.
The early works dust discharges are managed in accordance with the Dust Management and Erosion
and Sediment Control Plan (DMP/ESCP) for this phase2. The management measures include:
Suppression of dust from excavation areas and unsealed vehicle routes through watering and
suppression of other exposed areas with polymer suppressants.
Covering of truck loads and stockpiled material.
Except where they relate to management of identified contaminated material, similar management
methods are to be employed to manage dust during the construction phase.
As of 29 March 2017, ECan records indicate that it had not received any complaints relating to dust.
Although not a conclusive indicator, the lack of complaints would support that the environmental
effects of dust discharges during the preceding phase have been appropriately managed.
Given that similar management measures are to be implemented over the subsequent construction
phase, this would also indicate that the environmental effects of dust discharges of the construction
phase are also likely to be appropriately managed.
2 T+T. 2016. Dust Management and Erosion and Sediment Control Plan: Metro Sports Facility - Enabling works.
Factor Consideration
Frequency/duration The frequency and duration of dust observations at off-site receptor locations will
be dictated by the frequency of emissions and by wind conditions.
The frequency of dust emissions will vary depending on the nature and location
of activities undertaken (whether activities described in section 3.1 are occurring
near the site boundary).
The wind conditions described in section 4.2 will influence the frequency of dust
observation at locations off-site. The frequency of winds over 5 m/s is greatest
from the northeast notwithstanding the activities occurring on-site, the
frequency of dust emissions is therefore likely to be highest towards the
southwest.
In terms of duration of emissions, wind conditions conducive to dust transport
are most likely to occur consistently in sea breeze conditions. These conditions
will tend to occur on sunny afternoons and would transport dust towards the
southwest. In the long term, the dust generating activities will be temporary. The
construction works are scheduled for completion in 2020, with the bulk of dust
generating activities likely to be undertaken between July 2017 and March 2018
and from February to October 2019.
Intensity The intensity of dust deposition (or suspension in air) at locations beyond the site
boundary will be a function of intensity of dust emissions and the degree of
dispersion of emissions, which in turn will be a function of geographical
separation (dust deposition due to emissions from the works will reduce with
distance from the site).
Dust emissions will vary in intensity depending on the nature and location of
activities undertaken and wind conditions (the potential for dust emissions will
increase with wind speed). The proposed works do not include demolition works,
which may increase the intensity of dust emissions. Furthermore, excavations are
scheduled to require dewatering and are likely to be well wetted on excavation,
which would tend to supress emissions from this activity. Provided dust controls
are implemented diligently, the intensity of dust emissions from the proposed
works are likely to be low.
Offensiveness/character The dust will be derived from soil and, given the contaminated soil remediation
will have occurred in the preceding early works phase, should be free of other
contaminants that could result in a more offensive nature of discharge.
Locational sensitivity The sensitivity of adjacent activities to dust is described in section 4.1 and varies
in adjacent areas. Sensitivity to dust is likely to be highest at the hospital facilities
to the north of St Asaph Street and where residential activities are located in the
mixed use zone. Sensitivity to dust may also be elevated at Hagley Community
College to the northwest and at certain commercial activities such as food outlets
and car yards within the surrounding commercial areas. The majority of these
activities are not downwind of the site in most wind conditions. However, a car
yard is situated to the southwest of the site at the corner of Moorhouse Avenue
and Stewart Street, which will be downwind in the predominant wind direction.
Factor Consideration
Greater attention to management of dust is likely to be required if dust
generating activities are carried out in the southwest corner of the site, near the
boundary. Other activities surrounding the site are likely to be of low to
moderate sensitivity to dust.
Overall, the frequency, duration and intensity of the (primarily soil-based) dust emissions from the
proposed construction works should be able to be managed such that in this environmental setting
of varying sensitivity, any dust nuisance effects are less than minor. Measures to manage dust
emissions in this manner are described in section 6.
Alternative measures may be available such as continuous instrumental monitoring of dust levels.
Given the nature of the construction activities, the diffuse nature of resulting emissions and varying
wind conditions, this type of monitoring is not recommended in this instance. However, if dust
nuisance effects were identified to be occurring during the construction works, this type of
monitoring could be considered in order to provide a more detailed understanding of the effects and
to enable management measures to be modified accordingly.
No practicable alternative locations or methods of discharge are considered to be available and the
proposed method of discharge is considered to be appropriate.
7 Conclusions
This air quality impact assessment has been prepared on behalf of karo Limited to inform an
application for resource consent for discharges of dust to air from the construction of the MSF. The
following conclusions are drawn from the assessment:
Resource consent is required for discharges of dust to air of the construction phase of the
project. The equivalent discharges from site remediation activities in the preceding early
works phase are already consented (reference: CRC173564).
A range of proposed construction activities have the potential to generate dust, particularly
during the initial site works/in-ground works stage from mid-2017 to early 2018 and later
during the external works and landscaping stage that is scheduled to occur in 2019.
The area surrounding the site features or is intended to feature activities of varying sensitivity
to dust. Sensitivity to dust is likely to be highest at the hospital facilities to the north of St
Asaph Street and where residential activities are located in the surrounding mixed use zone.
Sensitivity to dust may also be elevated at Hagley Community College to the northwest and at
as food outlets and car yards within the surrounding commercial areas. Otherwise the
sensitivity of activities is likely to be low to moderate.
Similar dust discharges are generated from the preceding early works phase and similar
management measures are to be employed to manage dust during the construction phase. To
date (as of 29 March 2017), no complaints have been recorded by ECan in relation to dust
nuisance from the early works phase, which would indicate the dust management measures
proposed for the construction phase are effective and dust nuisance effects will continue to
be well managed.
Residual soil contamination could be encountered during the works and result in
contaminated dust emissions. However, given soil remediation is to be completed in the
preceding early works phase and subsequent construction works are to be managed in
accordance with the SMP, there are unlikely to be any additional adverse health effects of the
discharges as a result of on-site soil contamination.
A consideration of the FIDOL factors for assessing the potential for dust nuisance effects
indicates that the frequency, duration and intensity of dust emissions from the proposed
works should be able to be managed such that dust nuisance effects are less than minor.
A range of dust management measures are recommended to achieve this and will be
incorporated into a Construction Dust Management Plan prior to commencement of
construction.
Provided that the recommended dust management measures are rigorously implemented, the
adverse effects of dust discharges are assessed as being less than minor and appropriately mitigated.
8 Applicability
This report has been prepared for the exclusive use of our client karo Limited, with respect to the
particular brief given to us and it may not be relied upon in other contexts or for any other purpose,
or by any person other than our client, without our prior written agreement.
Report prepared by: Authorised for Tonkin & Taylor Ltd by:
.......................................................... .................................................
Jason Pene Peter Cochrane
Senior Environmental Engineer Project Director
JAP
\\ttgroup.local\corporate\christchurch\tt projects\53556\53556.0020\issueddocuments\construction dust assessment\final\53556-002-
msf construction dust assessment-final.docx
Disclaim er:
I
nf ormat i
on i n thi
s map h as been deri ved f rom various sources
i
n cluding t h eKai kouraDi strict,Hurun uiDistrict
,W aimak aririDi
strict,
Ch ristch urch Di st
ri
ct,En vi ron men tCan terbury Reg ion al Coun cil,
Selw yn Di strict
,Ash burton Di stri
ct,W aimat e Dist
ri
ct,Mack en zie
District,Ti maru Di stri
ctan dW ai takiDistri
cts databases.
Informat i
on on this map may n otbe used f or th epurposes ofan y
leg al di
sputes. Th euser sh ouldi n depen den t
ly verif
yth eaccuracy
ofan y informati
on beforetak i
n g an y act
ion i
n relian c
eupon it.
0 0.
04 0.
08 0.
12 0.
16
Ki
lomet
res
Scale:1:
4,000@A4
Copyrig h tCan t
erbury Maps
En vi
ron men tCan terbury 2017
Map Creat
edby Can t
erbury Maps on 2:
55:
00p.
m.
Appendix C: Consideration of assessment
methodology against pCARP
requirements
Application to
Christchurch City Council
5 July 2017
Prepared By: Melanie Foote Resource Management Group
Consultant Planner Level 4, 69 Cambridge Terrace
Resource Management Group Limited PO Box 908, Christchurch Box Lobby
Christchurch 8140
tkaro Limited hereby applies for an earthworks NES consent as described below.
3. The owner and occupier of the site to which the application relates:
The site is bounded by St Asaph Street, Antigua Street, Moorhouse Avenue and Part of
Stewart Street. See Appendix One for copies of the Certificate of Titles and list of properties.
5. Resource consent will be sought concurrently from Environment Canterbury (ECan) for de-
watering and stormwater activities. An Outline Plan has been submitted to Christchurch City
Council (CCC) and includes the proposed earthworks activities.
Page | 5
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
______________________________ ______________________________
Melanie Foote Darryl Millar
Consultant Planner Director
Resource Management Group Ltd Resource Management Group Ltd
Page | 6
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
TABLE OF CONTENTS
INTRODUCTION ............................................................................................................................................... 8
THE SITE AND SURROUNDING AREA ................................................................................................................ 8
DESCRIPTION OF PROPOSED WORKS ............................................................................................................. 10
COMPLIANCE ASSESSMENT ........................................................................................................................... 13
STATUTORY CONSIDERATIONS ...................................................................................................................... 14
ASSESSMENT OF EFFECTS............................................................................................................................... 14
OBJECTIVES AND POLICIES ............................................................................................................................. 18
PART TWO MATTERS ..................................................................................................................................... 19
CONCLUSION ................................................................................................................................................. 20
Appendix One: List of property addresses and legal descriptions and Computer Freehold
Registers
Appendix Two: Preliminary Site Investigation
Detailed Site Investigations
Remediation Action Plan
Appendix Three: Construction Methodology
Appendix Four: Site Management Plan for Ground Contamination (Version 2)
Appendix Five: Air Quality Impact Assessment
Appendix Six: Proposed Conditions of Consent
Page | 7
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
INTRODUCTION
Background
1. The Metro Sports Facility (MSF) will be a world class sporting venue and centre of excellence.
It will provide for aquatic and indoor sports facilities, day to day needs for recreational,
educational and high performance sporting communities as well as hosting both national and
international sporting events. The opportunity to develop the MSF has arisen as a result of the
Canterbury Earthquakes which caused the loss of numerous sports and leisure facilities
throughout Christchurch.
2. The MSF is identified as an Anchor Project identified in the Central Christchurch Recovery Plan
(CCRP). MSF will comprise of two large rectangular buildings joined through the central
portion. The eastern building will comprise a range of swimming pools, including an Olympic
pool, dive pool, leisure pools and hydroslides. The western building will contain sports courts,
fitness centre and various administration facilities.
3. By way of background site remediation consents and associated site remediation NES
consents were approved by both ECan and CCC in late 2016. The site is currently under
remediation to remove asbestos containing granular materials and localised pockets of
underlying metals, PAHs and contaminated historic fill with the objective of reducing health
and safety controls during the construction of the MSF. As part of the approved site
remediation consenting a Preliminary Site Investigation (PSI) and two Detailed Site
Investigations (DSIs) were completed along with a Remediation Action Plan (RAP) with
respect to ground contamination for the site remediation works. A copy of these reports are
contained in Appendix Two. As part of the site remediation works that precede the
construction phase works proposed under this NES consent, an Interim Site Validation Report
(SVR), will be completed prior to commencement of the construction phase works. The SVR
will confirm that the condition of the site post remediation and will be finalised on completion
of the construction related earthworks.
4. As part of the proposed construction phase consents a Site Management Plan (SMP) and Air
Discharge Assessment have been prepared by T+T and attached in Appendix Four and Five
respectively.
5. This NES consent relates to the construction phase of the MSF project covering all site ground
development works.
6. Consents will be lodged with ECan concurrently covering stormwater and dewatering and air
quality matters.
The Site
8. The MSF site is approximately 71,703m2 in area and is bound by St Asaph Street, Antigua
Street, Moorhouse Avenue and part of Stewart Street. The site has a flat topography. See
Page | 8
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
9. The site addresses and legal descriptions are listed in the table contained in Appendix One
Also refer to Appendix One for copies of the Certificates of Title and table listing the street
addresses and legal descriptions.
11. The Christchurch City Plan does not identify any historic buildings, places or objects on the
site.
12. The Mahaanui Iwi Management (IMP) plan does not identify any culturally significant sites of
interest to local Iwi.
Page | 9
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Site Contamination
13. A site remediation and NES consent were granted in December 2016 and as part of that
consent the site history was documented in the PSI. Detailed site investigation reports were
also provided along with a Remediation Action Plan (RAP). Copies of these reports are
attached as Appendix Two.
14. In summary the land, prior to the Canterbury earthquake sequence and acquisition by the
Crown was used by a range of commercial and industrial activities; the largest being the
Canterbury Brewery. Other activities included motor vehicle workshops and the storage of
hazardous substances such as fuels for heating. The land was also raised and levelled during
its early development involving placement of fill and the demolition of buildings and crushing
of demolition materials followed by vacant areas of land used for vehicle parking.
Historic fill which typically contained low levels of Poly Aromatic Hydrocarbonss (PAHS)
and metals and generally below the commercial land use criteria. However, four localised
hot spots were identified where contaminant levels exceeded the commercial criteria;
Various levels of asbestos fines were found in recently recycled demolition wastes. A small
proportion of the materials contained asbestos levels above the risk based criterion;
At surface level several locations of asbestos containing material fragments were left at
surface level after demolition of the buildings;
In soil and groundwater surrounding underground storage tanks (USTs);
In groundwater some or all of, arsenic, copper, lead and nickel levels are above fresh water
guidelines for the 95% level of aquatic protection, and in several wells, groundwater was
above the 80% level of aquatic protection around the perimeter and within the site.
16. Remediation works have been completed within the northern and central blocks (i.e. land
north of Horatio Street), while some further materials removal is required in the southern
block of the site. T+T have completed an interim Site Validation Report in May 2017 and this
report documents the remediation works undertaken and confirms the current status of the
site. In summary, T+T state the validation programme for the northern block has confirmed
that bonded asbestos containing materials, where identified. T+ T note that asbestos fibre test
results in unexcavated grid squares are at or below the laboratory detection limit and the risk
based all uses criterion 0.001% weight by weight.
17. The southern block of the site contains stockpiled materials containing low levels of asbestos
that are awaiting removal and off-site disposal. T+T will update the site status on completion
of the removal of materials from the southern block and again after completion of the
construction of the MSF.
18. This consent is for the construction phase earthworks across the entire site. Works are
proposed to commence upon completion of the consented site remediation works.
19. The goal of the consented site remediation works is to provide the contractor with a site that
Page | 10
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
has contaminant levels appropriate to the sites future commercial land use. This means that
contamination will still remain on site; that being contaminants at levels above background,
but below a level that could cause health effects for workers and users of the MSF facility.
Site establishment;
Earthworks: large volumes of earthworks are proposed to construct the MSF foundations,
deeper dive pool and general site works to form car parking areas, outdoor recreation areas
and landscaping.
Ground improvement: including sheet piling, de-watering and installation of stone columns;
Stockpiling: limited stockpiling is proposed as part of the construction phase and comprises
stockpiling up to 500m3 of imported aggregate and further excavated fill stockpiles of up to
200m3;
Landscaping procedures: the SMP notes that residual contaminated materials may remain in
areas proposed to be landscaped. While the remedial works will reduce contaminant levels
to commercial land use criteria, any area where soil is to be left exposed may not be suitable
for contact.
Building Construction: The main floor levels for the building will be at RL 17.7 for the pool
area, the central hub and the competition courts. The community court floor level will be at
RL 16.7. Typically, there will be 0.8m to 1m of fill placed to achieve the floor level of RL 17.7
and 0.5m to 1m of fill placed to achieve the floor level of RL 16.7.
Pool construction including subgrade and sub-base development for the pool hall,
hydroslides, and construction of the pool and sports courts. The pools will vary in depth with
the leisure pools typically being constructed above ground water levels. The competition
pool will require deeper excavation below the groundwater table and the dive pool will be
well below the water table;
The pools will have varying depths. The pools in the leisure area will typically be above the
groundwater table and are expected to be constructed in the dry. The competition pool has
a moveable floor at the north end, which will require excavation slightly below the
groundwater table. The floor of the dive pool is at RL12.7 and the excavation will be well
below the water table. There is also a plant room running along the length of the
competition pool with a floor level of RL 13.55m to RL 14.05m, which will also require
excavation and construction below the water table. See Appendix Three for a copy of the
Construction Methodology.
Pool hall completion including hydroslides, pool services and finishes, and commence site
entry and car parking.
Hours of operation: works will generally be undertaken between 7.30am and 6.00pm
Monday to Saturday, however some works may be required outside these times on Sunday
and public holidays as required.
Page | 11
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
21. The above works are expected to commence in July 2017 with completion in March 2018.
Earthworks: large volumes of earthworks are proposed to construct the MSF foundations,
deeper dive pool and general site works to form car parking areas, outdoor recreation areas
and landscaping. A copy of the Construction Methodology is attached as Appendix Three
and contains a plan showing the in ground sequence of works.
Ground improvement: including sheet piling, de-watering and installation of stone columns;
Stockpiling: limited stockpiling is proposed as part of the construction phase and comprises
stockpiling up to 500m3 of imported aggregate and further excavated fill stockpiles of up to
200m3;
Erosion and Sediment control: all earthworks will be in accordance with ECans Erosion and
Sediment Control Guidelines (ESCG). The contractor will provide a detailed Erosion and
Sediment Control Plan (ESCP) prior to commencing works on site. The details of what the
ESCG will include are detailed with the T+T SMP contained in Appendix Four;
Soil Disposal: whilst the goal is to retain as much material on site as possible, should off-site
disposal be required, Table 7.2 in the SMP has been developed to provide guidelines to the
contractor;
Landscaping procedures: the SMP notes that residual contaminated materials may remain in
areas proposed to be landscaped. While the remedial works will reduce contaminant levels
to commercial land use criteria, any area where soil is to be left exposed may not be suitable
for contact. T+T have, therefore, recommended a number of procedures in the SMP which
include a layer of geotextile to be laid over landscaped areas, covering geotextile with a
minimum of 300m of clean imported top soil;
Dust: While demolition material containing asbestos fines and historic fill containing levels
above the land use criterion will have been removed as part of the site remediation, there
remains potential for any dust generated to contain traces of metals, PAHs and asbestos
fibres. T +T have produced an Air Quality Impact Assessment contained in Appendix Five and
this plan recommends a number of dust mitigation and control measures. Prior to any works
commencing on site as part of the construction phase a construction Dust Management Plan
will be developed by the contractor;
Water Management:
o Surface water diversion: diversion of clean stormwater away from areas of ground
disturbance will take place;
o Dewatering: construction will require dewatering well below the groundwater table
to control inflows of water in to the excavation site and with regard to water
pressures on the underside of the slabs and foundations;
Page | 12
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
COMPLIANCE ASSESSMENT
24. A breach of this rule makes the proposed activities a restricted discretionary activity.
Councils discretion is limited to a number of matters and of relevance are nuisance and
amenity which will be assessed further in this AEE from paragraph 37.
27. Under regulation 8(3)(c), the volume of soil disturbed must be no more than 25m3 per 500m2
of land. The proposal will exceed this.
28. Regulation 8(3)(f) specifies a time limit of 2 months for the duration of the activity. The
proposed earthworks and site development and construction works will exceed two months.
29. Regulation 9 (1) and 10(2) requires a detailed site investigation to exist for the piece of land
for the activity to meet the Controlled or Restricted Discretionary provisions. DSIs were
completed as parts of the approved site remediation works previously consented and are
attached as Appendix Two to this application.
30. Regulation 11 provides for activities to be considered as a discretionary activity when they do
not meet the permitted, controlled or restricted discretionary standards. Overall the proposed
works are to be considered as a restricted discretionary activity.
31. Overall, on the basis of the above compliance assessment, the application is to be assessed as
a restricted discretionary activity.
Page | 13
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
STATUTORY CONSIDERATIONS
32. The NES Soil is relevant to the proposal given the site is contaminated. The NES provides a
national planning control that directs the requirement for consent for activities on
contaminated or potentially contaminated land. All territorial authorities are required to give
effect to and enforce the requirements of the NES in accordance with their functions under
the RMA relating to contaminated land.
33. Section 104(1) of the Act sets out the matters which the consent authority must have regard
to in considering an application for resource consent. In this case it is considered that regard
shall be had to:
Any actual and potential effects of allowing the activity (Section 104(1)(a));
Any relevant objectives, policies, rules or other provisions of the District Plan (Section
104(1)(b)) and:
Any other relevant matters reasonably necessary to determine the application
(Section 104(1)(c)).
34. All matters listed in Section 104(1) are subject to Part 2 of the Act, which sets out the
overarching purpose and principles of sustainable management as follows:
(1) The purpose of the Act is to promote the sustainable management of natural and physical
resources.
(2) In this Act, sustainable management means managing the use, development, and
protection of natural and physical resources in a way, or a rate, which enables people and
communities to provide for their social, economic and cultural wellbeing and for their
health and safety while
(a) Sustaining the potential of natural and physical resources (excluding minerals) to meet
the reasonably foreseeable needs of future generations; and
(b) Safeguarding the life supporting capacity of air, water, soil, and ecosystems; and
(c) Avoiding, remedying, or mitigating any adverse effects of activities on the
environment.
35. Section 6, 7 and 8, the principles, set out various matters to be considered when assessing
whether or not a particular proposal achieves the purpose of the RMA.
36. An assessment of the proposal under Section 104 and Part 2 of the RMA is set out in the
following sections.
ASSESSMENT OF EFFECTS
37. Section 88 of the RMA requires the applicant to undertake an assessment of any actual or
potential effects on the environment that may arise from a proposal, and the ways in which
any adverse effects may be avoided, remedied or mitigated. As a restricted discretionary
activity, Councils discretion is limited therefore the assessment of effects is also limited to the
matters of discretion.
Page | 14
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
(a) The adequacy of the detailed site investigation, including site sampling, laboratory analysis
and risk assessment;
(b) The suitability of the piece of and for the proposed activity, given the amount of soil
contamination;
(c) The approach to the remediation or ongoing management of the piece of land, including
the remediation or management methods to address the risk posed by the contaminants
to human health, timing of the remediation, the standard of the remediation on
completion, mitigation methods to address risk posed by the contaminants to human
health, and the mitigation measures for the piece of and, including the frequency and
location of monitoring of specified contaminants.
(d) The adequacy of the site management plan or the site validation report;
(e) The transport, disposal, and tracking of soil and other materials taken away in the course
of the activity;
(f) The requirement for conditions of a financial bond;
(g) The timing and nature of the review of the conditions in the resource consent; and
(h) The duration of the consent.
40. As outlined previously, the site is currently under remediation to remove asbestos granular
materials and localised other pockets of underlying metal and PAHs, contaminated hardfill,
with the objective of reducing health and safety controls during the construction phase of the
MSF. T+T state that contamination will still remain on site above background levels, but below
a level that could cause health effects. T+T also note that there is potential for unexpected
contamination to occur. Therefore, an SMP has been prepared by T+T to provide procedures
for managing any unexpected contamination, for characterising any soil requiring offsite
disposal, and confirming earthworks and health and safety controls during soil disturbance.
Further, the SMP contains procedures for documenting ground contamination related works
that occur during the bulk earthworks, such as unexpected contamination encounters (if any).
41. The SMP provides a basis for procedures that will be followed by contractors should
contamination be found on site during construction phase works. Unexpected contamination
that could be encountered could include abandoned USTs or localised areas of contaminated
historic or demolition fill not previously identified by the DSIs. T+T note that all site staff will
be inducted prior to works commencing as to the protocols for reporting on and managing any
unexpected contamination. It is noted that an interim site validation report will be completed
Page | 15
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
once remediation works are completed then a final site validation report will be completed
once the MSF has been completed.
42. On this basis provided the controls and procedures are followed within the SMP any adverse
effects with regard to earthworks and contamination will be less than minor.
44. Construction phase stormwater and dewatering water, (both treated as required), will be
discharged to the CCC reticulated stormwater network where it will mix with other
stormwater being conveyed through the network prior to being discharged to the Avon River.
This mixing will further dilute any contaminants remaining in the discharge following
treatment. Consultation has been ongoing with Mr Norton at the CCC and he has provided the
Councils approval for a discharge volume of up 150l/sec from the whole site, subject to
applying for a stormwater discharge consent form ECan.
45. Given the mitigation measures proposed, proposed conditions and the temporary nature of
the discharges, the effect on the water quality of the Avon River is considered to be less than
minor.
47. The proposed works do not involve any substantial dewatering of groundwater from the
Riccarton Gravels (Aquifer 1) or deeper. It is noted Aquifer 1 is generally the uppermost
confined gravel aquifer encountered in central Christchurch, and lies approximately 20m bgl,
which is deeper than the proposed excavations proposed as part of this application.
48. Some construction phase stormwater may percolate into the land within the area of works,
however, the coastal confined aquifer system will not be adversely affected as it will be
protected by its confining layer. Given the temporary nature of the construction phase and
flat topography of the site adverse effects on groundwater quality are considered to be less
than minor.
Page | 16
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
50. T+T have prepared an Air Quality Impact Assessment, attached as Appendix Five, and have
considered the FIDOL factors along with proposing a number of mitigation measures. In
summary these measures include:
51. A Construction Dust Management Plan will be prepared as required and at minimum will
include the following:
52. Provided the recommended dust management measures are implemented, the adverse
effects of the dust discharges are assessed as being less than minor and able to be
appropriately mitigated. The location of the stockpiles will be limited on site to exclude areas
within 100m of a sensitive activity as required by the proposed Canterbury Air Regional Plan.
54. Matapopore has been working with the MSF project team to provide such advice as well as
interpretation on the Ngi Thuriri/Ngi Tahu historical narratives and, key kaupapa and
values such as whakapapa, mahinga kai, manaakitanga, mana motuhake and ture wairua to
achieve design outcomes which meet the Ngi Tahu objectives of the Recovery Plan and are
ultimately more meaningful and respectful of the history and cultural landscape in which the
projects are located.
Page | 17
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Positive Effects
56. The MSF is one of the Anchor Projects of the CCRP and the proposed works will enable the
development of the MSF, thereby providing significant social, cultural and economic benefits
for both the regional and local economy. Further the proposed operational stormwater
system proposed will result in improved stormwater water quality being discharged from
the site compared to the pre-development site where no treatment was provided.
Summary
57. The proposed construction phase works will provide for the development of the MSF. While
the proposed works will result in temporary adverse construction effects, this assessment has
concluded that such effects can be appropriately managed. In particular, the SMP and Dust
Assessment recommend procedures that will be adhered to which will mitigate the effects
associated with any unforeseen contamination, erosion and sediment control, discharge of
construction phase stormwater and dewatering discharges.
58. In summary, this assessment concludes that the adverse effects of the proposed works will be
less than minor.
59. The discussion below assesses the proposal against the relevant objectives and policies of the
Christchurch District Plan.
Page | 18
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Objective 13.11.1.1- Health Seeks to ensure people and Strict health and safety
and Safety property are protected measures will be
during, and subsequent to, implemented on site. The
the works, while recognising SMP provides recommended
the benefits of some procedures to be adhered to.
activities involving
earthworks,
Policy 13.11.1.2.2 Nuisance Earthworks shall not Measures will be put in place
generate continuous or to avoid, remedy and mitigate
persistent nuisance, potential nuisance effects
including noise, vibration, including;
dust or odour, that have
more than minor adverse A dust management
effects on the amenity values will be prepared.
and the health and safety of The district plan
people and their property construction noise
while recognising the and vibration
benefits of some activities standards will be
involving earthworks in the complied with.
repair, rebuild and recovery Erosion and sediment
of the district. control will adhere to
ECans guidelines.
60. Overall, the proposed works are considered to be consistent with the relevant objectives and
Policies of the Christchurch district Plan.
61. The proposal does not give rise to any effects that would be considered to be in conflict with
any matters contained in Part 2 of the RMA. It provides for the health and safety of
communities while mitigating the adverse effects in accordance with Section 5(2)(c) by
managing the effects of earthworks and any potentially contaminated land post site
Page | 19
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
remediation. Further the proposal will maintain and enhance the quality of the environmental
accordance with section 7(f) by proposing procedures and controls should any unexpected
contamination be discovered as part of the construction phase earthworks.
62. The proposed construction phase earthworks will not impact on any matters of national
importance contained within section 6.
63. In terms of section 7 matters to have particular regard to, it is noted that the proposal is
consistent with the matters outlined in particular the following:
a. 7(b) The efficient use and development of natural and physical resources; and
b. 7(c) The maintenance and enhancement of amenity values;
64. The other matters contained within section 7 and section 8 are not considered to be relevant
to the proposal.
65. Overall it is considered that this early works consenting will be consistent with the purpose
and principles the Act.
CONCLUSION
66. The proposal involves the construction phase earthworks across the whole MSF site related
to the development of the MSF. Site remediation works have commenced on site and are
authorised by various consents granted earlier this year.
67. As concluded above, any adverse effects of the proposal with regard to effects on human
health are considered to be less than minor given the site will be remediated prior to
commencement of construction phase earthworks and activities.
68. Overall as the proposed construction phase activities will result in less than minor effects on
the environment, it is considered appropriate that the application be approved.
Page | 20
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Part Town Reserve 113 and Part Town Reserve 114 Town
123/123A Moorhouse Avenue
of Christchurch
Page | 21
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Part Town Reserve 113 and Part Town Reserve 114 Town
28 Balfour Terrace
of Christchurch
Part Town Reserve 113 and Part Town Reserve 114 Town
24 Horatio Street
of Christchurch
Page | 22
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Page | 23
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Page | 24
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Page | 25
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Page | 26
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Page | 27
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
The application be granted pursuant to Sections 104, 104C, and 108 of the Resource Management
Act 1991, subject to the following condition:
1. The development shall proceed in accordance with the information and plans submitted with the
Application including the Site Management Plan for Ground Contamination (version 2) dated May
2017, Construction Phase Air Quality Assessment, dated (XXX) and the Approved Consent
Documentation has been entered into Council records as RMA/XXX.
2. All works shall adhere to the procedures and measures set out in the Site Management Plan for
Ground contamination (Version 2) dated May 2017 by Tonkin and Taylor. A copy of the SMP must
be accessible to all workers and contractors on site and remain on site.
3. Any soils removed from the site during the course of the activity which are contaminated must
be disposed of to a facility authorised to accept the material.
4. The consent holder shall submit to Christchurch City Council a Site Validation Report (SVR) three
months after completion of the project outlining the works undertaken and any particular issues
that arose. The report shall include at least the following:
a. An approximate volume of soil moved off site and the disposal facility;
b. Validation of areas exceeding NES standards and WA Guideline;
c. Records of any additional testing results and reports;
d. Thickness and volume of clean fill material;
e. Location and description of any unexpected contamination encountered; and
f. Evidence of disposal of any contaminated materials to an authorised facility.
g. The report shall be sent to envresourcemonitoring@ccc.govt.nz
5. Standard construction methods for controlling erosion and sediment migration shall be
implemented prior to the commencement of soil disturbance work and maintained until the soil
is reinstated to an erosion-free state, in accordance with ECans Erosion and Sediment Control
Guide.
6. Any investigations with respect to the removal of underground storage tanks (USTs) at the site
shall be carried out in accordance with the current edition of the Ministry for the Environment,
Guidelines for Assessing and Managing Petroleum Hydrocarbon Contaminated Sites in New
Zealand. The results of the investigation must be emailed to
envresourcemonitoring@ccc.govt.nz within three months of the completion of works.
7. In the event that soils are found that have visible staining, odours and/or other conditions that
indicate soil contamination, then work must cease until a Suitably Qualified and Experienced
Practitioner (SQEP) has assessed the matter and advised of the appropriate remediation and/or
disposal options for these soils. The applicant shall immediately notify the Environmental
Compliance Team by email to envresourcemonitoring@ccc.govt.nz of this matter. Any
measures to manage the risk from potential soil contamination must be approved by the
Christchurch City Council.
Page | 28
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
8. Only cleanfill material as defined in the MfE Guideline can be used as imported fill.
9. All measures included in the SMP for Ground contamination and the Air Discharge Assessment to
manage noise, dust, erosion, sediment, surface water treatment, vapour and odour shall cover
all consented earthworks. The ESCP prepared under the SMP shall be provided to
envresourcemonitoring@ccc.govt.nz prior to any work starting on site.
10. A Traffic Management Plan (TMP) shall be prepared and shall be accepted prior to any
transportation of fill to the application site. The TMP shall be submitted to the Christchurch
Transport Operations Centre through www.tmpforchch.co.nz. Traffic movements shall be
planned to cause minimum disruption to road users without compromising safety. In particular
the traffic plan shall include avoiding the morning and afternoon rush hours, between 8am and
9am and 3pm - 4pm.
11. The content of the Traffic Management Plan shall be communicated to all Transportation
contractors and a copy given to them to utilise for the duration of the consent. This shall be the
responsibility of the site supervisor (see attachment 1 at the end of this report, or icon below).
12. Should any archaeological material or sites be discovered during the course of work on the site,
work in that area of the site shall stop immediately and the appropriate agencies, including
Heritage New Zealand Pouhere Taonga and the Mana Whenua, shall be contacted immediately.
Contact Heritage New Zealand Pouhere Taonga on infosouthern@heritage.org.nz or (03) 357
9629. The consent holder is also directed to the Accidental Discovery Protocol set out in
Appendix 3 of the Mahaanui Iwi Management Plan: http://mkt.co.nz/mahaanui-iwi-
management-plan/ .
13. Works shall be undertaken between the hours of 7.30am and 6pm, Monday to Saturday. On
Sunday and public holidays works shall only occur if they are necessary measures to mitigate
adverse nuisance and health effects from the works.
14. The road outside the site shall be kept clear of debris from the earthworks at all times.
Advice notes:
1. If contaminants are left onsite, a separate consent under the NES may be required during any
future land disturbance activities.
2. This resource consent covers soil disturbance/earthworks only. A separate consent is required for
any bulk and location non-compliances on the site.
3. This may be an archaeological site as specified in the Historic Places Act 1993. An archaeological
site is any place in New Zealand that was associated with human activity that occurred before
1900,and is or may be able through investigation by archaeological methods to provide evidence
relating to the history of New Zealand. Sections 10 to 20 of the Historic Places Act apply, and any
destruction, damage, or modification of any part of the site must first be authorised by Heritage
New Zealand. Please contact Heritage New Zealand on ph. 365-2897 before commencing any
further work on the land.
Page | 29
tkaro Limited, Metro Sports Facility
Construction Phase NES Consent Application to CCC
Page | 30
REPORT (version 2)
1 Introduction 1
1.1 Site identification 1
1.2 Objective and scope of this report 1
1.3 Regulatory compliance 2
2 Roles and responsibilities 3
2.1 General 3
2.2 Distribution and implementation 4
2.3 Review and update 4
2.4 Licensed Asbestos Removal Supervisor 4
2.5 Contaminated land specialist 4
3 Site history and condition 5
3.1 Pre-remediation 5
3.2 Post-remediation 6
4 MSF Construction 9
4.1 Works overview 9
4.2 Construction programme 9
4.3 Basis for procedures 9
5 Site management 11
5.1 Site establishment 11
5.1.1 Notifications and approval process 11
5.1.2 Induction and training 12
5.1.3 Vehicle wash facilities 12
5.1.4 Health and safety facilities 12
6 Managing unexpected contamination 13
6.1 Indicators of contamination 13
6.2 First response procedures 13
7 Controls and procedures 15
7.1 Earthworks controls 15
7.1.1 Dust controls 15
7.1.2 Erosion and sediment control 15
7.2 Water management 16
7.2.1 Diversion of surface water 16
7.2.2 Disposal of groundwater 16
7.2.3 Water treatment and disposal 16
7.3 Earthworks procedures 17
7.4 Soil disposal 18
7.5 Imported material procedures 18
7.6 Landscaping procedures 19
7.7 Underground storage tank removal 19
7.8 Vapour and odour management 20
7.9 Soil and groundwater sampling procedures 21
7.9.1 General soil sampling methods 21
7.9.2 Asbestos sampling methods 21
7.9.3 Ground and surface water sampling methods 22
7.9.4 Reporting and data evaluation 22
8 Monitoring and control 25
8.1 Monitoring requirements 25
This report has been prepared for the exclusive use of our client tkaro Limited, with respect to the
particular brief given to us and it may not be relied upon in other contexts or for any other purpose,
or by any person other than our client, without our prior written agreement.
Recommendations and opinions contained in this report are based on our visual inspection and
sampling of material during validation of the site. The nature and continuity of the subsoil away
from the test and sample locations is inferred but it must be appreciated that actual conditions may
vary from the assumed model.
Technical review and certification by a suitably qualified and experienced practitioner as prescribed
under the NES Soil:
..........................................................
Wendi Williamson
Senior Contaminated Land Specialist
Authorised by:
.................................................
Peter Cochrane
Project Director
1 Introduction
Tonkin & Taylor Ltd (T+T) has been commissioned by tkaro Limited (tkaro) to prepare this Site
Management Plan (SMP) for ground contamination to be implemented during construction of the
Metro Sports Facility (herein referred to as the site or MSF). The location of the site is shown in
Figure 1.1.
Remediation has been undertaken to remove asbestos-containing granular materials and localised
pockets of underlying metal and polycyclic aromatic hydrocarbons (PAHs) contaminated historic fill,
to reduce health and safety controls during construction of the MSF. Remediation of the site was
undertaken according to the T+T Remediation Action Plan1. Further details about the sites pre-
remediation condition can be found in the RAP and about its post remediation condition in the
Interim SVR2 (iSVR).
This SMP has been prepared to:
Support application for resource consent for groundworks associated with construction of the
MSF;
Provide procedures for construction contractors to follow in the event that unexpected
contamination is encountered during the works; and
Set out general earthworks controls, disposal requirements and management of soil and
groundwater during the groundworks phase.
1 Tonkin & Taylor Ltd, December 2016. Metro Sports Facility, Remediation Action Plan Enabling Works. Prepared for
tkaro Limited. T+T Reference 53556.002 version 5.
2 Tonkin & Taylor Ltd, May 2017: Metros Sports Facility, Interim Site Validation Report. Prepared for tkaro Limited. T+T
4 Resource Management (National Environmental Standard for Assessing and Managing Contaminants in Soil to Protect
Human Health) Regulations 2011.
2.1 General
This SMP has been prepared to support construction of the MSF, Christchurch. A summary of the
organisations involved in the works and their roles and responsibilities under the SMP is provided in
Table 2.1.
6 A supervisor must hold a current asbestos removal license for Class A works. An up to date list is held by Worksafe NZ
http://www.business.govt.nz/worksafe/information-guidance/all-guidance-items/certified-asbestos-
contractors.pdf/view.
3.1 Pre-remediation
The history of the site is provided in the Beca PSI7. In summary, the land prior to the Canterbury
Earthquake Sequence (CES) and acquisition by tkaro was a range of commercial and industrial
activities, the largest of which was the Canterbury Brewery. Other activities included motor vehicle
workshops and land uses that included storage of hazardous substances such as fuels for heating.
The land was also raised and levelled during its early development involving placement of fill
(termed historic fill). The most recent activity on the land was demolition of buildings and crushing
of demolition materials followed by use of vacant areas of land for vehicle parking.
The pre-remediation condition of the site is documented in the Beca and T+T detailed site
investigation reports8,9,10,11 with a summary provided in the T+T RAP. In brief, ground contamination
was identified:
1 In historic fill which typically contained low levels of metals and PAHs, generally below the
commercial land use criteria, however four localised areas were identified where contaminant
levels exceeded the commercial criteria;
2 In recent recycled (crushed) demolition materials which contained variable levels of asbestos
fines. A small proportion of the materials contained asbestos levels above the risk-based
criterion 12, with approximately half the remaining area containing asbestos fines but at levels
below the risk based criteria;
3 At surface at several locations where fragments of ACM were left at surface post demolition of
the buildings;
4 In soil and groundwater surrounding underground storage tanks (USTs). USTs, predominantly
for diesel/ kerosene (heating oil) storage, were recorded on the ECan listed land use register
to be present at a number of locations over the MSF. One was recently removed from the
southeast of the site (pre-remediation) by demolition contractors CERES. There is potential,
albeit low, that others may exist and require removal during the construction; and
5 In groundwater where, some or all of, arsenic, copper, lead and nickel levels are above fresh
water guidelines for a 95% level of aquatic protection and, in several wells, above the 80%
level of aquatic protection in wells positioned around perimeter and within the site. The
results indicate a local (wider than the site) as well as a site-wide impact on water quality,
assuming groundwater flow is to the northeast and the Avon River, as all wells from the site
boundaries contained elevated levels of metals. Low levels of hydrocarbons, containing a
range of compounds that are consistent with heating oil and kerosene were noted in wells in
the south of the site.
7 Beca, 2014. Metro Sports Facility Taiwhanga Rehia - Preliminary Site Investigation (Contamination). Prepared for
Canterbury Earthquake Recovery Authority, 12 June 2014.
8 Tonkin & Taylor Ltd, July 2016. Metro Sports Facility Detailed Site Investigation (Asbestos). Prepared for tkaro
Asbestos-Contaminated Sites in Western Australia. All uses criterion of 0.001% weigh by weight.
3.2 Post-remediation
Remediation works are complete within the northern and central blocks, (i.e. land north of Horatio
Street), while some further materials removal is required in the southern block at the site. The iSVR
(May 2017) documents the remediation works undertaken and confirms the current status of the
site. In summary, the validation programme for the northern block has confirmed that bonded ACM,
where identified, has been removed. Asbestos fibre test results in un-excavated grid squares (refer
Figure 3.1) are at or below the laboratory detection limit and the risk based all uses criterion of
0.001% weight by weight.
The southern block still contains stockpiled materials containing low levels of asbestos that are
awaiting removal and offsite disposal. Granular materials from grid squares for which asbestos test
results were above the risk based criteria, shown in red in Figure 3.1, are being removed from the
southern block and disposed to licensed landfill. These works are anticipated to be completed by
end May 2017.
The site status will be updated in a revised iSVR on completion of removal of materials from the
southern block and again following completion of all groundworks associated with construction of
the MSF (with the preparation of a final SVR, anticipated to be issued during 2018).
This SMP has been produced on the basis that the remedial goals and objectives have been met and
that test results indicate that residual contaminant levels post remediation are below the
commercial land use criteria for metals and organic compounds, and asbestos levels are at or below
the all uses criteria.
A4 B4 C4 D4 E4 F4 G4 H4
Asbestos detected
BH340 TP107
PHASE 3 A6 B6 C6 D6 E6 F6 G6 H6
PHASE 1
BH339
STEWART STREET
A7 B7 C7 D7 E7 F7 G7 H7
TP112
TP111
A8 TP113 E8 TP114 G8 TP115
A9 B9 C9 D9 E9 F9 G9 H9
TP119 TP120
D10 TP118
TP116 B10 G10
TP117
TP226 TP227
TP417 TP418 A12 B12 C12 D12 E12 F12
ANTIGUA STREE
TP121 TP122 TP124 TP225 TP228
TP123 TP125
PHASE 4 A13 B13 D13 E13
TP126
TP419 TP420 C13
PHASE 2
TP224
A14 B14 C14 D14 E14 F14
BALFOUR STREET
T
TP216
TP306
TP215
TP308 TP312 TP318 TP320
TP220 TP223
PHASE 2 TP305
TP307 PHASE 3
TP214 PHASE 2
TP311 TP319
TP316
TP213
TP212 TP304
TP302 TP313 TP317 TP221 TP222
TP321
TP309
Concentration of
HORATIO STREET
ACM fragments TP408 TP406
TP411 TP409
TP325
TP404
TP208 TP414 TP405
TP326
TP202 TP410 TP324 TP407 PHASE 4
TP203
TP401
TP332
PHASE 4 TP323 TP329
TP207 TP402
TP415 TP403
TP413
TP327
PHASE 2 TP206 PHASE 3 TP336
TP333
TP412
TP328 TP335
TP201 TP204 TP416 TP331
TP205
TP337
L:\53556\CAD\FIGS\53556-SMP-F3.1.dwg F3.1 17/03/2017 7:20:28 a.m.
MOORHOUSE AVENUE
B2 C2
Temporary stockpile BH338
F3 G3
ACM pipe removed
E4 G4
BH340 TP107
B5 G5
TP106 TP108
PHASE 1
BH339
STEWART STREET
B7 C7 E7 F7 G7 H7
A8 TP113
B9 C9 E9 F9 G9
TP118
B10 G10
TP117
BH341 C11
ANTIGUA STREE
TP121 TP122 TP228
TP125
PHASE 4 E13
TP126
TP420
PHASE 2
B14 E14
BALFOUR STREET
PHASE 2 T
PHASE 3
PHASE 2
TP311
Central Block
TP302 TP313
TP309
TP303 TP315
TP301 TP310 TP314
Concentration of
HORATIO STREET
ACM fragments TP408 TP406
TP411 TP409
TP325
TP404
TP414 TP405
TP326
TP202 TP410 TP324 TP407 PHASE 4
TP203
TP401
TP332
PHASE 4 TP323 TP329
TP402
TP415 TP403
TP413
TP322 TP330
MOORHOUSE AVENUE
4 MSF Construction
The MSF is one of the anchor projects for the Christchurch central city rebuild. The sports facility
will comprise two large rectangular buildings joined through the central portion. The eastern
building will comprise a range of swimming pools, including an Olympic pool, dive pool, leisure pools
and a hydroslide. The western building will contain squash and badminton courts, a fitness centre
and administration facilities. There will be extensive landscaping around the facility and on-grade
carparking south of the building.
package by Protranz Earthmoving Ltd for tkaro Limited. The goal of the contamination remedial
works was to provide the Contractor with a site that has contaminant levels appropriate to the sites
future commercial land use. This means that contamination will still remain on site at levels above
background, but below levels that could cause health effects for workers and users of a commercial
facility. As contaminants will exist, principally in fill materials, there are basic hygiene and
environmental controls that shall be implemented by the contractor to ensure compliance with
industry best practice.
The basis for procedures in this SMP is:
To use standard industry good practice measures to mitigate environmental effects of
earthworks, such as for dust, sediment and surface water runoff;
To provide protection measures for workers and the general public should unexpected
contamination be uncovered; and
To document the works so that regulatory compliance can be measured.
5 Site management
The Contractor has prepared a CMP that shall be followed during the construction works. The
measures below are construction earthworks-related site management requirements.
The notification/approval process illustrated in Figure 6.2 is to be followed in the event of:
Any variations to the SMP proposed, either prior to or during works;
Any contamination incident occurring during works on the site; or
Any unexpected contamination being identified.
ECan/ CCC
Contaminated land
Project Manager Otakaro specialist
Contractor
(Site Manager)
Licensed asbestos
removal supervisor (if
required)
Worksafe NZ
Erosion and sediment control measures shall remain in place until the site surfaces are returned to a
stabilised condition, including sealing with impermeable surfaces (e.g. concrete floor slabs).
Table 7.1: Water collection and treatment procedures for short term discharges
Natural granular materials which are sourced directly from a licensed quarry. Such material will
not require testing, provided documentation confirming the source of the material (for example
weighbridge dockets or invoices and a summary sheet) is retained for inclusion in the validation
report (refer to Section 11.3); or
If soil needs to be imported, then any imported soil shall either:
o Be derived from a source which has been previously verified in accordance with the
methods described in the NES Soil regulations as being a piece of land to which the NES
Soil regulations do not apply; or
o Be sampled by a suitably qualified Contaminated Land Specialist at a rate of 1 composite
sample (made up of no less than 3 and no more than 4 subsamples) for every 1,000 m3
(from each source location) and tested to confirm that contamination concentrations
are suitable for the proposed use. A higher sampling density will be required for smaller
imported materials volumes. I t is preferable if the soil is tested at its source prior to its
disposal at the site. However, if not, the materials shall be stockpiled on site until test
results are available.
Soil underlying the tank shall be tested by the Contaminated Land Specialist prior to soil removal
from site or backfilling of the tank pit; and
The tank shall be disposed of by a specialist contractor to an appropriately licenced disposal
facility.
Table 7.3: Applicable acceptance criteria for soils (mg/kg unless stated otherwise)
The acceptance criteria for water in Table 7.4 are typical performance standards required by ECan.
Action shall be taken as required to notify the relevant parties and rectify any controls if monitoring
identifies that it is needed. Contingency measures are defined in Section 10.
Odour Action
(at nominated downwind station) (if exceeded for more than 30 seconds)
No Odour Works continue without modification.
Slight Odour Works may continue however modification of odour abatement
measures should be implemented (refer Section 7.8). Consider
vapour monitoring as per Section 8.7.
Strong Odour Works MUST CEASE until additional odour abatement measures
have been implemented (refer below).
It should be noted that after periods longer than around 30 seconds, even strong odours may no
longer seem detectable. This is due to a condition known as odour fatigue which is often noted
during long periods of odour detection. This condition is not indicating adverse health effects from
detection of the odour (unless the odour is very strong which is only likely if the assessor is very
close to heavily contaminated material) but is simply caused by a prolonged olfactory sense
stimulation. A simple means of relieving odour fatigue is to leave the area where the odour is noted
for a period of at least 10 minutes.
HALT OPERATIONS: Switch off all mechanical and electrical equipment. Evacuate the
immediate area and, assuming discharges are not that extending beyond the site boundary,
allow the area to ventilate for at least 15 minutes, then resample. If conditions fall and remain
below the required level works can be recommenced, otherwise additional mitigation measures
shall be implemented. If discharges are impinging on the site boundary additional control
measures, as described in the following sections, shall be implemented immediately.
In some circumstances, hot works activities, (such as the use of, oxy-acetylene equipment, or use of
steel cutting or grinding equipment) may be required. In these situations Lower Explosive Limit (LEL)
readings of less than 0.1% should be achieved prior to undertaking the tasks.
9.1 General
The contractor shall prepare and implement a health and safety plan in compliance with the Health
and Safety at Work Act (2015), associated regulations, and other applicable legislation, regulations,
codes and guidelines. The health and safety plan should cover hazards associated with the work
(e.g. equipment) and working practises/activities.
General protocols relating to the presence of contaminated material including asbestos are
described in this section and should be included or referenced in the project-specific health and
safety plan(s). The relevance of these protocols and level of protection required should be reviewed
during the preparation of project specific health and safety plan. These protocols are not intended
to relieve the controller of the place or work of either their responsibility for the health and safety of
their workers, contractors and the public, or their responsibility for protection of the environment.
Note: Workers on contaminated sites can be subject to unusual stresses, for example, manual
work while wearing dust masks or respirators, or exposure to elevated concentrations of
contaminants. It would be prudent to check that personnel working under the requirements of
this SMP do not have any pre-existing condition which might place them at risk as a result of such
stresses.
Contaminated Land Specialist input if necessary. The contractor shall then instruct all staff on the
health and safety procedures associated with the new hazard.
10 Contingency measures
The following actions are proposed in the event that unexpected conditions are encountered,
discharges occur and/or complaints are received in relation to the works.
11 Validation
Validation will have been undertaken following the removal of contaminated materials during the
enabling works package as per the T+T RAP and reported in the iSVR.
Further validation, post construction activities, is only required if unexpected contamination is
encountered. The objective of such validation is to confirm that actions in respect of the unexpected
contamination means residual soils meet a commercial land use criteria, or have alternatively been
contained such that contact by future users of the site is prevented.
Further validation (if any) shall be undertaken and reported by the Contaminated Land Specialist.
11.4 Reporting
On completion of the construction activities a final site validation report (SVR) shall be prepared by
the Contaminated Land Specialist and provided to CCC and ECan. The report shall update the
interim SVRs produced following completion of the enabling/early works contamination
remediation:
Confirmation that soil disturbance works were completed according to this SMP and that
there were no variations during the works (or details of the variations and approval by Council
if required);
Volumes of soil removed from or replaced on the site, associated chemical test results (if any),
disposal destination of surplus soils and waste disposal acceptance receipts; and
Confirmation that there were no environmental incidents during the works. If there was an
environmental incident then the report shall detail the nature of the incident and the
measures taken to mitigate effects.
The final validation report shall comply with the MfEs CLMG No. 1.
Leighs Cockram JVs contractors shall undertake the following during construction of the MSF
During the works General SMP Compliance g Maintain earthworks (dust, erosion, sediment, stormwater, odour)
controls as per SMP Sections 7;
h Implement health and safety procedures in Section 9;
i Retain all weighbridge and disposal dockets;
j Ensure imported material meets requirements in Section 7.5;
k Implement dewatering procedures if surface/groundwater dewatering
required refer Section 7.2;
Alert the Project Manager l Ensure compliance with any other procedures outlined by the
and Contaminated Land Contaminated Land Specialist,
Specialist
If any of the following situations arise:
m Contaminated soil is encountered that includes:
- Odours (petroleum, oil);
- Discolouration (black, green/blue staining most common);
- Inclusions of non-cleanfill allowable (refer MfE Cleanfill Guidelines)
deleterious materials (i.e. plastic, rubber, metal);
- Asbestos containing materials (ACM).
n Groundwater with an oil sheen, odour or discolouration is encountered;
o If soil is to be disposed offsite, additional soil samples may need to be
collected and tested. Refer to Section 7.9;
Within one Provide contaminated p Details of any complaints relating to odour or dust made during the
month of land-related information works;
completion of the to the Project Manager
q Details of unexpected encounters/events and the action taken;
relevant works
r Details of visits made by Council representatives;
s Summary of weighbridge information for disposal verification;
t Details of correspondence and visits by Worksafe.
REPORT
1 Introduction 1
1.1 Site identification 1
1.2 Objective and scope of this report 1
1.3 Regulatory compliance 3
2 Roles and responsibilities 4
2.1 General 4
2.2 Distribution and implementation 5
2.3 Review and update 5
2.4 Licensed Asbestos Removal Supervisor 5
2.5 Contaminated land specialist 5
2.6 Communication with Worksafe 5
3 Site history and condition 7
3.1 Site history 7
3.2 Soil contamination 7
3.2.1 Asbestos contamination 8
3.2.2 Other soil contamination 8
3.3 Groundwater contamination 9
4 Proposed works 12
4.1 Conceptual design 12
4.2 Works overview 12
4.3 Proposed works timing and sequencing 13
4.4 Detailed design 15
5 Remediation plan 17
5.1 Remediation objectives 17
5.2 Remediation strategies 17
5.3 Remediation criteria 18
5.3.1 Soils 18
5.3.2 Groundwater and surface water 19
6 Site establishment 21
6.1 General site management 21
6.2 Site establishment Class A works 21
6.3 Notifications and approval process 22
6.4 Induction and training 23
6.5 Vehicle wash facilities 23
6.6 Health and safety facilities 23
7 Class A removal works controls and procedures 24
7.1 Dust 24
7.2 Decontamination procedures 24
7.2.1 Personnel decontamination 24
7.2.2 Vehicle decontamination procedures 25
7.3 Asbestos-containing demolition material disposal 26
7.4 Containment 26
7.4.1 Burial pits 26
7.4.2 Retention in-place 27
7.5 Clearance 27
8 Site preparation works controls and procedures 29
8.1 Earthworks controls 29
Title:
Metro Sports Facility
Date Issue No Description Initials
August 2016 1 Remediation Action Plan for consultation wmw
September 2 Remediation Action Plan to support resource consent wmw
2016 applications
October 3 Remediation Action Plan to support resource consent wmw
2016 applications
This report has been prepared for the exclusive use of our client tkaro Limited , with respect to
the particular brief given to us and it may not be relied upon in other contexts or for any other
purpose, or by any person other than our client, without our prior written agreement.
Authorised by:
.................................................
Peter Cochrane
Project Director
Technical review and certification by a suitably qualified and experienced practitioner as prescribed
under the NES Soil:
..........................................................
Wendi Williamson
Senior Contaminated Land Specialist
\\ttgroup.local\corporate\christchurch\tt projects\53556\53556.0020\issueddocuments\rap\wmw071016.rap.v3.docx
1 Introduction
Tonkin & Taylor Ltd (T+T) has been commissioned by karo Limited to prepare this Remediation
Action Plan (RAP) for ground contamination to be implemented during development works within
the Metro Sports Facility (herein referred to as the site or MSF). The location of the site is shown in
Figure 1.1.
This RAP has been prepared on the basis of conceptual development plans for the MSF available at
the time of its preparation and information obtained during a detailed site investigation (Asbestos)
(DSI) by T+T reported in July 20151 and a DSI by Beca Ltd dated June 20162 along with a
supplementary more detailed grid based investigation by T+T in September 2016 3.
The RAP has been prepared to support application for resource consent for enabling and site
preparation works associated with the MSF. This document provides a proposed programme of
works, sequencing of enabling and site preparation works and sets out the remedial strategies and
the basis on which they have been selected for the MSF. It is possible remediation strategies may
change during the design process thus the RAP includes procedures for implementation of several
remedial methods, some or all of which may be confirmed by the design phase works.
An Interim Site Management Plan (ISMP), prepared by T+T in January 2016 4, is being implemented in
the intervening period until ground works for the MSF development commence.
1 Tonkin & Taylor Ltd, July 2016. Metro Sports Facility Detailed Site Investigation (Asbestos). Prepared for karo
Limited. T+T Reference 53556.v2
2 Beca, 2016: Detailed Site Investigation (Contamination), Metro Sports Facility, Prepared for karo Limited, 30/6/2016
3 Tonkin & Taylor Ltd, Letter dated 26 September 2016. Metro Sports Facility Supplementary asbestos investigation,
- Unsuitable materials removal to assist the future construction process. This will involve
removals of materials containing asbestos below the risk based criteria from the
construction zones.
- Works to reduce or remove materials containing metals and or polycyclic aromatic
hydrocarbons from several localised areas across the MSF will also occur during the
enabling works;
2 Site preparation works procedures Including remedial strategies that could be employed
during preparation works in the event that unexpected contamination is encountered, such as
USTs, or to enable decisions over materials reuse or disposal during foundation installation.
The foundation solution is for installation of stone columns coupled with some screw piles
within the dive pool;
3 General earthworks procedures and controls for managing ground contamination-related
effects on human health and the environment during and following enabling and site
preparation-related earthworks; and
4 Health and safety procedures for both enabling and site preparation works, timing and
requirements for Class A works supervision and controls as per the Health and safety at Work
(Asbestos) Regulations 2016 (Asbestos Regulations) and procedures for worker protection
should unexpected contamination be encountered.
2.1 General
This RAP has been prepared to provide procedures for undertaking enabling remedial, unsuitables
removal and site preparation works at the MSF, Christchurch. A summary of the organisations
involved in the proposed works and their roles and responsibilities under the RAP is provided in
Table 2.1.
Confirmation of contractor organisations and individual contact details will be provided to Council
and the Contractor prior to works commencement.
7 A supervisor must hold a current asbestos removal license for Class A works. An up to date list is held by Worksafe NZ
http://www.business.govt.nz/worksafe/information-guidance/all-guidance-items/certified-asbestos-
contractors.pdf/view
8 Various tasks require different levels of experience. The person undertaking the task should be suitably qualified and
experienced to the level required for the task they are undertaking out as specified in the Users Guide
Worksafe liaison Lyn Osmers; 03 966 7697 / 0272 550 079 / lyn.osmers@worksafe.govt.nz
officer(s): Assistant; TBA
(All communication shall be directed through the officers)
Communication Responsibility: Requirements:
milestones:
Enabling works package Contaminated materials removal
Pre-works/ site Licensed Asbestos Confirm works commencement dates and duration
establishment Removal Supervisor Confirm reporting lines
(Contractor)
Provide Contractor contact details
Confirm works i.e. Class A Asbestos Removal
Confirm health and safety measures
Confirm monitoring frequency and reporting as per
Section 9.3
During remediation Licensed Asbestos Daily air monitoring reports as per Section 9.3
works Removal Supervisor Report any incidents
(Contractor)
Report and agree on any variations to:
- controls in Section 7
- the Contractors Method Statement
- monitoring requirements in Section 9.3
Post remediation Licensed Asbestos Report on clearance process as per Section 7.5
works Assessor/
Contaminated Land
Specialist
Site preparation works packages Foundation installation and bulk earthworks
Pre-works site Contaminated land Weekly air monitoring reports as per Section 9.3
preparation (prior to Specialist Confirm works commencement dates and duration
each soil disturbance
Confirm reporting lines and Contractor contact details
activity)
Confirm works class: Asbestos Related Works
Agree health and safety requirements as set out in
Section 10
Confirm monitoring frequency and reporting as per
Section 9.3
During the works Contaminated land Report any incidents
Specialist Report and agree on any proposed variations to:
- controls in Section 7
- monitoring in Section 9.3
Post each soil Contaminated land Provide works completion information and any validation
disturbance activity Specialist data that may impact on controls set out Section 7 for any
subsequent site preparation works
Ground works completion
Post completion of Contaminated land Provide final site validation report
all earthworks Specialist
9 Beca, 2014: Metro Sports Facility Taiwhanga Rehia - Preliminary Site Investigation (Contamination), Prepared for
Canterbury Earthquake Recovery Authority, 12 June 2014.
Soil data obtained from the above units and evaluated against acceptance criteria applicable to
assessment of potential human health and environmental effects in a commercial land use scenario.
The data findings are described in the sections below.
10Western Australian Department of Health, May 2009: Guidelines for the Assessment, Remediation and Management of
Asbestos-Contaminated Sites in Western Australia. All uses criterion of 0.001% weigh by weight
commercial/ industrial use. The four locations where contaminants exceeded the
commercial/industrial criteria are in underlying historic fill within the Phases 1 and 3 areas, shown as
blue hashed circles on Figure 4. At these locations contaminants included arsenic, lead or
benzo(a)pyrene equivalent all present within the historic fill layer. Granular near surface materials
tested within the Phase 1 area during the supplementary T+T investigation (September 2016)
contain metals and PAH levels generally above background, but below commercial industrial
acceptance criteria.
Beca commented in their DSI report that based on previous commercial activities on the site there
remains the possibility for in-ground fuel tanks to still remain on the site.
A4 B4 C4 D4 E4 F4 G4 H4
Asbestos detected
BH340 TP107
PHASE 3 A6 B6 C6 D6 E6 F6 G6 H6
PHASE 1
BH339
STEWART STREET
A7 B7 C7 D7 E7 F7 G7 H7
TP112
TP111
A8 TP113 E8 TP114 G8 TP115
A9 B9 C9 D9 E9 F9 G9 H9
TP119 TP120
D10 TP118
TP116 B10 G10
TP117
TP226 TP227
ANTIGUA STREE
TP121 TP122 TP124 TP225 TP228
TP123 TP125
TP126
A13 B13 D13 E13
PHASE 4
C13
PHASE 2
TP224
A14 B14 C14 D14 E14 F14
BALFOUR STREET
T
TP216
TP306
TP215
TP308 TP312 TP318 TP320
TP220 TP223
PHASE 2 TP305
TP307 PHASE 3
TP214 PHASE 2
TP311 TP319
TP316
TP213
TP212 TP304
TP302 TP313 TP317 TP221 TP222
TP321
TP309
Concentration of
HORATIO STREET
ACM fragments TP408 TP406
TP411 TP409
TP325
TP404
TP208 TP414 TP405
TP326
TP202 TP410 TP324 TP407 PHASE 4
TP203
TP401
TP332
PHASE 4 TP323 TP329
TP207 TP402
TP415 TP403
TP413
TP327
PHASE 2 TP206 PHASE 3 TP336
TP333
TP412
TP328 TP335
TP201 TP204 TP416 TP331
TP205
TP337
TP322 TP330 TP334
L:\53556\CAD\FIGS\53556-RAP-F3.dwg F3 30/09/2016 2:41:27 p.m.
MOORHOUSE AVENUE
LEGEND
PHASE 3
Separable portion 1
PHASE 1
Seperable portion 2
BH339
TP112
TP111
TP113 TP114 TP115
STEWART STREET
TP119 TP120
TP116 TP118
TP117
BH341
TP226 TP227
TP121 TP124
ANTIGUA STREE
TP122 TP225 TP228
TP125
PHASE 4
TP123
TP126 PHASE 2
TP224
BALFOUR STREET
T
TP216
TP306
TP215
TP308 TP312 TP318 TP320
TP220 TP223
PHASE 2 TP305
TP307 PHASE 3
TP214 PHASE 2
TP311 TP319
TP316
TP213
TP212 TP304 TP313 TP222
TP302 TP317 TP321 TP221
TP309
Concentration of
HORATIO STREET
ACM fragments TP409 TP408 TP406
TP411 TP325
TP208 TP404
TP414 TP405
TP326
TP410 TP324 TP407
TP202 TP203 PHASE 4
TP401
TP332
PHASE 4 TP323 TP329
TP207 TP402
TP415 TP413 TP403
TP327
PHASE 2 TP206 PHASE 3 TP336
TP333
TP412
TP201 TP328 TP335
TP204 TP416 TP331
TP205
TP337
TP322 TP330 TP334
L:\53556\CAD\FIGS\53556-RAP-F4.dwg F4 5/10/2016 3:18:51 p.m.
MOORHOUSE AVENUE
4 Proposed works
materials excavated during site preparation and construction works, if this strategy is required.
A number of areas have been identified for possible use as burial areas should onsite
containment be required (refer Figure 6 for location of proposed burial areas);
Excavations for services removal including disused ACM services;
Levelling (cut and fill) earthworks;
Geotechnical and structural testing of existing piles cut below surface within the former
Canterbury Brewery site in the Phase 1 area (refer areas outlined in blue on Figure 4);
Excavations required during installation of stone columns for ground improvement purposes;
Excavations for services installation, carpark formation and landscaping;
Formation of the landscaped mound in the southeast corner (refer Figure 5 for location);
Discharge of stormwater (construction phase); and
Dewatering, treatment and disposal of dewatering discharges during construction and
installation of the in-ground pools.
LEGEND
Proposed asbestos-containing
demolition materials burial areas.
Landscape mound
PHASE 3
PHASE 1
Proposed Building
Footprint
ANTIGUA STREE
PHASE 4
PHASE 2
STEWART STREET
Carparking
BALFOUR STREET
T
Carparking
PHASE 2
PHASE 3
PHASE 2
Carparking
HORATIO STREET
Carparking
PHASE 4
Carparking
PHASE 4
PHASE 2 PHASE 3
L:\53556\CAD\FIGS\53556-RAP-F6.dwg F2 28/09/2016 7:30:35 a.m.
MOORHOUSE AVENUE
5 Remediation plan
The following remediation plan sets out the rationale behind the enabling works remediation and
procedures developed for ground contamination management during site preparation works. The
plan also provides the remediation criteria for evaluation of soil and groundwater conditions during
the MSF development.
Revisions to the remediation plan are possible following detailed design process.
5.3.1 Soils
The following are the target remediation criteria for human health and environmental protection on
the basis of the sites future use for commercial activities. At a minimum, soils accessible by future
site users (i.e. surface soils in landscaping areas) must meet the human health standards. The
location of soils exceeding these criteria will need to be provided on final as-built plans and provided
as part of the site validation so they can be managed appropriately during any future land
disturbance activities.
Table 5.1: Remediation criteria for soils (mg/kg unless stated otherwise)
Contaminant 80% level of fresh water 95% level of fresh water Proposed Performance
aquatic protection1 aquatic protection1 Standards2
TDS - - 50
Arsenic 0.36 0.024 -
Cadmium 0.0008 0.0002 -
Chromium 0.04 0.001 -
Copper 0.0025 0.0014 0.014
Lead 0.0094 0.0034 0.034
Nickel 0.017 0.011 -
Zinc 0.031 0.008 0.08
Naphthalene 0.085 0.0016 0.016
Contaminant 80% level of fresh water 95% level of fresh water Proposed Performance
aquatic protection1 aquatic protection1 Standards2
Benzene 2 0.95 9.5
o-xylene 0.64 0.35 3.5
p-xylene 0.34 0.2 2
Notes:
1. Australian and New Zealand Environment and Conservation Council Guidelines for Fresh and Marine Waters (2000)
fresh water values.
2. Derived from ANZECC 95% protection levels applying a dilution factor of 10 x upon mixing with stormwater within the
network
6 Site establishment
Figure 7: Example site establishment showing asbestos management area and general works areas
ECan/ CCC
Contaminated land
Project Manager Otakaro specialist
Contractor
Licensed asbestos
removal supervisor
Worksafe NZ
7.1 Dust
Dust controls as set out in Section 8.1.1 shall be adhered to during enabling works. In addition
during disturbance and removal of demolition materials within the AMA, where asbestos levels
exceed the risk based threshold of 0.001% w/w, the following additional procedures are to be
implemented:
Continual review of dust control measures by the Licensed Asbestos Removal Supervisor;
Added vigilance by the Contractors site manager on maintenance of equipment to support
dust control;
Use of polymer dust suppressant, water and covers to ensure no stockpiled materials are left
in a situation where they may dry out and generate dust;
Daily air monitoring as per Section 9.3; and
Evaluation of wind conditions (strength and direction) and directive by the Licensed Asbestos
Removal Supervisor.
The Contractor and Class A asbestos removal licence holder shall ensure dust controls comply with
relevant local regulations.
washing boots and an area for washing skin. An example is provided in Figure 10. Portable
decontamination units can also be hired.
The Licensed Asbestos Removal Supervisor shall determine the extent of decontamination
required based on the contamination present and tasks being undertaken. All workers shall
be inducted on decontamination methods prior to works commencing as per Section 6.4.
13 New Zealand Demolition and Asbestos Association, March 2011: New Zealand Guidelines for the Management and
Removal of Asbestos
7.4 Containment
Full Class A asbestos controls outlined in Sections 7.1 7.3 shall be implemented within the
burial pit area;
Fill shall be placed in layers and compacted. Geotechnical specification (if any) shall be
followed for the compaction;
Only onsite sourced materials shall be placed in the pit. Unexpected material encounters shall
be cleared by the Contaminated land Specialist prior to disposal.
Fill shall be placed to a maximum of 300 mm below the finished subgrade level;
A marker layer of geotextile shall be laid over the completed surface. The geotextile
specification will be determined in part by geotechnical requirements, but is expected to be a
minimum of Bidim A14 or similar non-woven material;
Subgrade materials shall be placed over the geotextile a minimum of 300 mm thick. A thinner
layer may be placed where the contained materials are to be overlain by concrete building
floor or foundation slabs (subject to geotechnical requirements); and
The burial pit locations shall be surveyed and provided on as-built drawings and those
drawings included in the validation report and future long term management plans.
7.5 Clearance
On completion of removal or containment works an independent licensed asbestos assessor shall
issue a clearance certificate that confirms:
The AMAs are free from visible asbestos at surface;
Final monitoring data shows that the respirable asbestos fibre level does not exceed trace
level (i.e. 0.01 f/ml) at all monitored locations (around and within the AMA/ burial pit area);
Containment measures in Section 7.4 have been placed over residual ACM; and
The AMAs do not pose a risk to health and safety from exposure to asbestos.
The clearance certificate shall be provided in writing to the Licenced Asbestos Removal Supervisor,
Contractor and karo. The clearance certificate shall comply with the requirements of the
Asbestos Regulations 2016 requirements and shall document the date of the clearance, the assessor
providing the clearance and data, including photographic evidence to support the conclusions made
in the clearance.
A stockpiling area shall be established where runoff from the stockpile can be controlled,
including a sump for collection of water and diversion bunds to collect runoff and divert clean
water away from the stockpile; and
Erosion and sediment control measures shall be upgraded/ modified where necessary.
Erosion and sediment control measures shall remain in place until the site surfaces are returned to a
stabilised condition, including sealing with impermeable surfaces (e.g. concrete floor slabs).
Table 8.1: Water collection and treatment procedures for short term discharges
Particular attention shall be taken to demolition fill materials, those in situ, ex situ (excavated
and stockpiled) and during replacement, to ensure they are kept damp to prevent the
generation of dust and airborne asbestos fibres;
Excavated soil/fill to be disposed offsite shall, where possible, be placed directly on a truck;
Trucks shall be loaded within the site where runoff and possible spills during loading shall be
controlled and contained;
Trucks shall have their loads covered during transport of contaminated soil to the designated
offsite disposal site;
Appropriate permits to dispose of low level (at or below 0.001%) asbestos wastes and
notifications must be made prior to works commencing;
Trucks shall have their wheels washed down before they leave the site; and
Any truck that is transporting excavated soil from the works area shall have a tracking
document signed out onsite and collected at the landfill to track each load of material.
Be derived from a source which has been previously verified in accordance with the
methods described in the NES Soil regulations as being a piece of land to which the NES
Soil regulations do not apply; or
Be sampled by a suitably qualified Contaminated Land Specialist at a rate of 1
composite sample (made up of no less than 3 and no more than 4 subsamples) for every
1,000 m3 (from each source location) and tested to confirm that contamination
concentrations are suitable for the proposed use. A higher sampling density will be
required for smaller imported materials volumes. It is preferable if the soil is tested at
its source prior to its disposal at the site. However, if not, the materials shall be
stockpiled on site until test results are available.
analysis; or entire fraction double bagged for identification and analysis at the laboratory;
and
- The fines fraction shall be collected, a minimum of 2 cups of fines (500 ml), labelled and
double-bagged for analysis; or
- A 500 ml sample collected from representative soils (a separate 1 x 1 m area to the 10 L
bucket, but within the same 15x15 m grid) and submitted to the laboratory for analysis in
accordance with the AS4964-2004 Method for the qualitative identification of asbestos in
bulk samples.
Action shall be taken as required to notify the relevant parties and rectify any controls if monitoring
identifies that it is needed. Contingency measures are defined in Section 11.
9.3.3 Reporting
Air monitoring results shall be evaluated on receipt. If asbestos fibres are detected (> 0.01
fibres/mL) works shall cease until dust and other earthworks controls are reviewed and modified
where necessary. Amendments to the earthworks procedures shall be reported to the Project
Manager, CCC, ECan and Worksafe (if at or above 0.02 fibres/mL as this level is a notifiable incident).
All air monitoring results shall be reported daily to the Contractors site manager and the project
manager as well as in the site validation report (SVR) (refer Section 12).
carry out all maintenance requirements to ensure the effectiveness of the control measures if the
inspections show that this is required.
Odour Action
(at nominated downwind station) (if exceeded for more than 30 seconds)
No Odour Works continue without modification
Slight Odour Works may continue however modification of odour abatement
measures should be implemented (refer Section 8.9). Consider
vapour monitoring as per Section 9.77.
Strong Odour Works MUST CEASE until additional odour abatement measures
have been implemented (refer below)
It should be noted that after periods longer than around 30 seconds, even strong odours may no
longer seem detectable. This is due to a condition known as odour fatigue which is often noted
during long periods of odour detection. This condition is not indicating adverse health effects from
detection of the odour (unless the odour is very strong which is only likely if the assessor is very
close to heavily contaminated material) but is simply caused by a prolonged olfactory sense
stimulation. A simple means of relieving odour fatigue is to leave the area where the odour is noted
for a period of at least 10 minutes.
The controls for vapour and odour are described in Section 8.9.
HALT OPERATIONS: Switch off all mechanical and electrical equipment. Evacuate the immediate area
and, assuming discharges are not that extending beyond the site boundary, allow the area to ventilate
for at least 15 minutes, then resample. If conditions fall and remain below the required level works can
be recommenced, otherwise additional mitigation measures shall be implemented. If discharges are
impinging on the site boundary additional control measures, as described in the following sections, shall
be implemented immediately.
In some circumstances, hot works activities, (such as the use of, oxy-acetylene equipment, or use of
steel cutting or grinding equipment) may be required. In these situations Lower Explosive Limit (LEL)
readings of less than 0.1% should be achieved prior to undertaking the tasks.
10.1 General
It is recommended that the person(s) responsible for undertaking the ground disturbance activity
(the Contractor) prepare and implement a health and safety plan in compliance with the Health and
safety at Work Act (2015), associated regulations, and other applicable legislation, regulations, codes
and guidelines. The health and safety plan should cover hazards associated with the work (e.g.
equipment) and working practises/activities.
General protocols relating to the presence of contaminated material including asbestos are
described in this section and should be included or referenced in the project-specific health and
safety plan(s). The relevance of these protocols and level of protection required should be reviewed
during the preparation of project specific health and safety plan. As noted in Section 1.4, these
protocols are not intended to relieve the controller of the place or work of either their responsibility
for the health and safety of their workers, contractors and the public, or their responsibility for
protection of the environment.
As described in Section 3.2.1, contamination in the AMAs exceeds the risk based acceptance criteria
for the protection of human health. Excavation of asbestos containing demolition fill in these areas,
and potentially in other areas of site presents a risk to site workers. The following procedures reflect
this risk and are provided to minimise contact with contaminants during the proposed work and for
controlling and manage the risk from airborne contaminants.
Note: Workers on contaminated sites can be subject to unusual stresses, for example, manual
work while wearing dust masks or respirators, or exposure to elevated concentrations of
contaminants. It would be prudent to check that personnel working under the requirements of
this RAP do not have any pre-existing condition which might place them at risk as a result of such
stresses.
separated from the remainder of the earthworks and a decontamination area made available to the
persons working in this area (refer Section 7.2 for decontamination procedures):
Respiratory protection shall be worn at all times during disturbance of demolition fill in AMAs
and burial pit footprints because of the presence of asbestos fibres. The minimum
requirement of respiratory protection will be determined by the Licensed Asbestos Removal
Supervisor as required by the Asbestos Regulations 2016. This will comprise a P3 half face
respirator as a minimum;
Disposable coverall suits (e.g. Tyvek) shall be worn to prevent contaminated material
contacting other parts of the body, i.e. legs and arms, and preventing asbestos fibres
collecting within the folds of clothing;
Disposable impermeable gloves shall be worn by workers who may have contact with
contaminated material during their work, including accidental contact. Gloves shall be
replaced regularly, if ripped or holed;
Boot covers shall be used to prevent asbestos fibres being tracked offsite on the soles of
workers/visitors boots, or alternatively a boot wash shall be established at the entrance to the
contaminated area from the loading area;
Disposable coverall suits, boot covers and dust filter worn within AMAs shall be removed in
the decontamination area and disposed of. Tyvek shall not be reused; and
No eating, drinking or smoking on any part of the site during enabling and site preparation
works to prevent contaminated material contacting food or being ingested directly via soiled
hands.
green/blue staining most common), and/or inclusions of deleterious materials (e.g. plastic, rubber,
metal). Further hazards may also be identified during the course of the works.
The Contractor is responsible for reviewing any new work element and assessing whether there are
any new associated hazards, and whether these can be addressed through the Hierarchy of Controls
for Hazard Management (eliminate or minimise [substitute, engineer, isolate, administer, personal
protective equipment]). The Contractor shall seek review by the Project Manager, who will seek
Contaminated Land Specialist input if necessary. The Contractor shall then instruct all staff on the
health and safety procedures associated with the new hazard.
11 Contingency measures
The following actions are proposed in the event that unexpected conditions are encountered,
discharges occur and/or complaints are received in relation to the works.
Green/yellow discoloured soil may indicate high levels of copper and chromium;
Black gravel/sand may be boiler ash materials that could be high in metals and PAHs; and
Inclusions of deleterious materials such as timber, brick, concrete, clinker, metal.
Table 11.1 is a first response checklist for the sites nominated contractor(s) to follow should visual
or olfactory evidence of contamination be encountered during the works onsite, including
encountering asbestos outside of the AMAs.
The presence of other contaminants in high levels may dictate further controls be implemented and
additional or different containment/disposal be required. The first response procedures are to
ensure contamination is appropriately contained while decisions about its management are being
undertaken.
12 Validation
12.1 General
Validation is the process of confirming the objectives of the works have been achieved, and showing
works were undertaken according to agreed procedures and reporting on any incidents.
Validation of the site shall be conducted by the Contaminated Land Specialist. The validation
programme recommended includes observation of the ground works and appropriate encapsulation
and/or removal of contaminated materials.
Both validation sampling and reporting may need to be undertaken in a staged manner to reflect the
staged nature of the development if necessary.
Details of any health and safety incidents related to the contamination and how they were
resolved.
The Contractor shall provide the required information within one month of completion of each stage
of works.
12.5 Reporting
On completion of the soil disturbance works a site validation report (SVR) shall be prepared and
provided to CCC and ECan. The report shall include, as a minimum:
Confirmation that soil disturbance works were completed according to this RAP and that there
were no variations during the works (or details of the variations and approval by Council if
required);
Volumes of soil removed from or replaced on the site, associated chemical test results (if any),
disposal destination of surplus soils and waste disposal acceptance receipts; and
Confirmation that there were no environmental incidents during the works. If there was an
environmental incident then the report shall detail the nature of the incident and the
measures taken to mitigate effects.
This report shall be provided to CCC and ECan within 3 months of completion of the soil disturbance
works. Multiple stages of reporting may be required at the discretion of the Contaminated Land
Specialist.
The validation report shall comply with the MfEs CLMG No. 1.
Asbestos
General soil contamination
Table A1: Semi-quantitative asbestos data evaluation
Concentration (w/w) %
During the works General SMP Compliance i Maintain earthworks ((dust, erosion, sediment, stormwater, odour)
controls as per SMP Sections 7 and 8;
j Implement health and safety procedures in Section 10;
k Retain all weighbridge and disposal dockets and provide to Contractor;
l Ensure imported material meets requirements in Section 8.6;
m Implement dewatering procedures if surface/groundwater dewatering
required (refer Section 8.2;
Alert the Project Manager n Ensure compliance with any other procedures outlined by the
and Contaminated Land Contaminated Land Specialist,
Specialist
If any of the following situations arise:
o Contaminated soil is encountered that includes:
- Odours (petroleum, oil);
- Discolouration (black, green/blue staining most common);
- Inclusions of non-cleanfill allowable (refer Appendix F MfE Cleanfill
Guidelines) deleterious materials (i.e. plastic, rubber, metal);
- Asbestos containing materials (ACM).
p Groundwater with an oil sheen, odour or discolouration is encountered;
q If soil is to be disposed offsite, additional soil samples may need to be
collected and tested. Refer to Section 8.5 and 8.10;
Within one Provide contaminated r Details of any complaints relating to odour or dust made during the
month of land-related information works;
completion of the to the Project Manager
s Details of unexpected encounters/events and the action taken;
relevant works
t Details of visits made by Council representatives;
u Summary of weighbridge information for disposal verification;
v Complete works verification form.
/641 521465 (#%+.+6; 6#+9#0)# 4+#
%4+56%74%
57
%1
57 %1
.%,8 %
064
%#4064#%61
10
2#4 4
#4# #%614
.%,8 1((+%5
%#4 2#547.6#06
521465 %1746
&4; #4
7 #4#
211. #..
96 #4
#4#
.#;&190 561
)#61
4#)
75
5+6 064; 9+6
64#((+% %10641.
57
%1
57 %1
.%,8 %
064
%#4064#%61
10
2#4 4
#4# #%614
.%,8 1((+%5
%#4 2#547.6#06
%1//70+6; %1746 (42 (170+105 56 2+. &+8+0) 211. 7 #4# (170+105 56 2+. &2 5%6+105 +0
(14 5647%674 %1//0%& :%#8#6 %1//0%& .+574 211. +( 437+4&
#4#
.#;&190 561
)#61
4#)
75
&+4%6+10 1( 5610 %1.7/05 &+4%6+10 1( 5610 %1.7/05
+056#..#6+10 %1/26+6+10 211. +056#..#6+10 .+574 211.
57
%1
57 %1
519 %1746 5%6+10
.%,8 %
064
5647%674#. 56. %1//0%&
%#4064#%61
10
2#4 4
#4# #%614
.%,8 1((+%5
%#4 2#547.6#06
521465 %1746 411(
5647%674 %1//0%&
#4#
.#;&190 561
)#61
4#)
75
211. #.. 411( 211. #.. 24+/#4; 5647%674
5647%674 241)455+0) 0#4+0) %1/2.6+10
57
%1
57 %1
%1//70+6; %17465 411( 411( 5647%674 61 52%6#614
.%,8 %
064
5647%674 %1/2.6 %17465 %1//0%&
%#4064#%61
10
2#4 4
#4# #%614
.%,8 1((+%5
%#4 2#547.6#06
#4#
.#;&190 561
)#61
4#)
75
211. #.. (42 .8. 211. #.. 411( ;&41 5.+& 5647%674
5.# 70&49#; 5647%674 %1/2.6 (170+10 +056#..&
57
%1
57 %1
7 #4# 521465 %1746 (4#/+0)
.%,8 %
064
08.12 %1/2.6 %.#&&+0) %1/2.6
%#4064#%61
10
2#4 4
#4# #%614
.%,8 1((+%5
%#4 2#547.6#06
#4#
.#;&190 561
)#61
4#)
75
%1/26+6+10 211. .+574 211. ;&41 5.+&
+056#..#6+10 %1/2.6 +056#..#6+10 %1/2.6 5647%674 %1//0%&
57
%1
57 %1
521465 %1746 08.12 7 #4#
.%,8 %
064
%1/2.6 %1/2.6
%#4064#%61
10
2#4 4
#4# #%614
.%,8 1((+%5
%#4 2#547.6#06
#4#
.#;&190 561
)#61
4#)
75
211. #.. 08.12 ;&41 5.+&
%1/2.6 +056#..#6+10 %1/2.6
.%,8 1((+%5
,7.;
.%,8 %
10
%#4 2#547.6#06
57 %1 .#;&190 561
064
#4# #%614 4#)
#4#
57
%1
%#4064#%61
2#4 4
)#61
75
+052%6+105
%1//+55+10+0)
%4+56%74%
/641 521465 (#%+.+6; 6#+9#0)# 4+#
%4+56%74%
Hi Luke
We are pleased to provide our response to the balance of the rfi matters. Sorry for the delay in the response the
contractor has been a bit slow.
2. By virtue of the design, machinery and installation methods associated with both the stone column ground
remediation system and also vibro-compaction of hardfill on the MSF Project, vibration will be caused in
order to achieve soil compaction. The attached management plan outlines how the contractor will comply
with DIN 4150 1999 02 Effects of vibration on structures as per the attached Aurecon Construction Noise
and Vibration Management Plan (CNVMP) prepared specifically for Leighs Cockram for the MSF Project.
I trust this information satisfies the RFI request. If you have any further questions or require any further information
please come back to me asap.
Regards
Melanie
Melanie Foote
Consultant Planner
Resource Management Group
Level 4, 69 Cambridge Terrace
PO Box 908
Christchurch Box Lobby
Christchurch 8140
P 03 943 4112
M 021 959 295
D 03 962 1738
E melanie@rmgroup.co.nz
Disclaimer: This email and any files transmitted with it are confidential and intended solely for the use of the individual or
entity to which they are addressed. You must not present this message to another party without gaining permission from
the sender. If you have received this email in error please notify the sender immediately. Any views expressed in this
message are those of the individual sender, except where the sender specifically states them to be the views of Resource
Management Group Ltd. Finally, the recipient should check this email and any attachments for the presence of viruses.
Resource Management Group Ltd accepts no liability for any damage caused by any virus transmitted by this email.
Before printing think about your responsibility and commitment to the environment. Print double-sided and two pages per
sheet whenever possible
1
File Ref: C15129_MSF_Landscape_for_Outline_Plan.indd
ST ASAPH STREET
(AAC ENTRANCE DESIGN TBC) +15.4
CYCLES
CE PU BLIC
SECURE O
UTDOOR SPACE CYCLES
AREA
FENCE
LANDSCAPE SITE PLAN OUTDOOR LEISURE
CANOPY
FOR OUTLINE PLAN SECURE OUTDOOR AREA
OLS
CAFE CAFE +17.7
ACCESSIBLE
+17.7
Date: 25th January 2017
DROP OFF
Plan prepared for Warren and Mahoney Architects
by Boffa Miskell Limited
Project Manager: nik.kneale@boffamiskell.co.nz
This plan has been prepared by Boffa Miskell Limited on the SHOW COURT LEISURE POOL
specific instructions of our Client. It is solely for our Clients use
+17.7
DROP OFF
NORTHWESTERN +17.7
in accordance with the agreed scope of work. Any use or reliance
by a third party is at that partys own risk. Where information CAR PARK
has been supplied by the Client or obtained from other external
sources, it has been assumed that it is accurate. No liability
or responsibility is accepted by Boffa Miskell Limited for any
errors or omissions to the extent that they arise from inaccurate
METRO SPORTS FACILITY
information provided by the Client or any external source.
DROP OFF
0 15m DN
+15.4
1:500 @ A1
+17.7 +17.7
ACCESSIBLE
DROP OFF
DROP OFF
PLANTING
ANTIGUA STR
(INDICATIVE)
GRASS +16.7 +16.7 COMPETITION POOL
STONE PAVING
EE
CONCRETE FOOTPATH
T
ASPHALT
SOFTFALL/SPORT SURFACE
FURNITURE
+17.7
WESTERN CAR
PARK
CANOPY
INTERNAL AVENUE
COMMUNITY COURTS
CYCLES
+16.7
SECURE SERVICE AREA +15.4
COACH
+16.2
SOUTHERN CIVIC SPCAE
ACCESSIBLE
SUBSTATION
SUBSTATION
DROP OFF
EASTERN
CANOPY
+16.0
SIGN
AGE
+15.4
COACH
CYCLES CYCLES
RAINGARDEN
STEWART ST
INTERNAL AVENUE
SOUTHERN
CL
DEVELOPMENT LOT
CY
RECREATION AREA
2500M2
E
SIGN N AG
AGE SIG
MOORHOUSE AVE
15.38
ST ASAPH STREET
15.55 15.67 15.47 15.76
15.60 15.71
1:54
1:85
1:45 1:120
00
RETAINING WALL A 1:50 16.
REFER TO DWG CI-0-14-21 FOR DETAILS
CH:0.00 15.78 15.85 15.85
LEGEND: 15.84 16.45
1:85
1:50
AREAS BEING DETAILED BY BOFFA MISKELL LANDSCAPE ARCHITECTS.
CH:10.00
15.95 16.03
16.12
PROPOSED RETAINING WALL
CH:20.00 16.18 16.56
0
16.5
MAJOR CONTOUR 16.26
DROP OFF
1:33
1:50 16.75
A 1:76
1:48
CH:30.00 1:59
11-21 16.75
16.67
MINOR CONTOUR
00
CH:40.00
16.57 16.74 17.
1:33
NOTE:
17.47 HIGH POINT
DROP OFF
CH:50.00 1:83
16.78
1. TIE-IN LEVELS AT ACCESS ROADS AND BOUNDARIES TO BE CONIRMED TO TIE INTO FUTURE CCC WORKS. 1:50 1:47
2. CONTOURS SHOWN IN AREAS BEING DETAILED BY BOFFA MISKELL FOR DETAILED LEVELS.
3. FOOTPATHS TO HAVE A 1:50 CROSSFALL UNLESS NOTED OTHERWISE TO MEET ACCESSIBILITY REQUIREMENTS. 17.70
16.92
CH:60.00
16.69
17.15 17.47
DROP OFF
1:69 17.0
0
1:27
CH:70.00
1:127
1:58
CH:80.00 16.40 16.49 16.58 16.71
DROP 1:187
1:247
PRIORITY
OFF
DROP OFF
CH:100.00 16.38
CH:110.00 16.33
1:51 16.19 1:77 16.38 16.34 1:43 16.62
ANTIGUA STREET
16.60 16.70
CH:120.00
1:320
1:314
CH:130.00 1:46 1:64 1:59
CH:140.00
1:320
1:314
COACH
CH:160.00 1:37 1:46
16.08 16.33
16.20 16.47
CH:170.00
15.5
COACH
16.04 16.32 16.13
0
1:40 1:35
16.00
CH:180.00
COACH
1:103
CH:190.00
50 16.14 16
16. 16.43
.00
1:30 16.07
1:35 1:30
16.30 16.06 16.47
1:320
16.13
1:258
CH:200.00
COACH
1:140 16.02 15.98
16.
CH:208.89
16.20
16.22
50
1:27
COACH
1:104 1:94 16.18 .00
1:258
16.82 16.50 15.90 16
STEWART STREET
16.08
1:29
1:101
1:104
1:320
1:97
16.00 15.92
1:50
1:50
1:59
16.05 15.93
1:50
16.22
1:63
16.18
1:50
1:50
1:50
1:50
1:131 1:148 1:148
16.24 16.28 16.41 1:429 15.53
1:50
1:50
1:50
1:429 1:429
16.18 16.34 16.09 15.79 15.70 15.66 15.63
1:50
1:50
1:50
1:50
1:50
1:50
1:200 1:200
16.40 16.28 16.16 16.06 16.06
1:27
HIGH POINT
1:36
1:50
1:76
1:50
16.45 1:50
14.68
16.47 16.46 15.97 15.97 16.22 16.22
1:50 1:50
1:49
1:49
1:50
1:50
16.47
16.06
16.43 16.17 16.08 16.18 16.18 16.08 16.17 16.16 15.96 15.90 15.96 15.96 15.90 15.96
16.30 16.30 16.30 16.03 16.03 16.06 16.06
1:50
1:50
1:49
1:49
1:193
D
Filename: P:\250518\CADD\DRGS\CIV\250518-0000-DRG-CI-0-10-21.DWG
1:50
1:50
1:49
1:49
1:50
1:50
16.11
1:49
MSF CLIENT GROUP AND OTHER KEY STAKEHOLDERS WHICH MAY CONTAIN CONFLICTING DATA, 16.47
OMISSIONS AND ERRORS AND ON REFERENCE ARCHITECTURAL DRAWINGS DATED 22ND 16.47 16.47 16.23 16.23 16.30
DECEMBER 2016. IN READING THIS DOCUMENT THE CONTRACTOR SHALL REFER TO ALL PROJECT 16.47
1:50
1:50
1:49
1:49
DESIGN FEATURES REPORTS, SPECIFICATIONS AND CROSS REFERENCE WITH ALL OTHER 16.15
ENGINEERING DISCIPLINE DOCUMENTATION AND THE PRINCIPALS PROJECT REQUIREMENTS. TO 16.06 16.06
1:193
COMPLETE THE DESIGN THE CONTRACTOR WILL BE REQUIRED TO WORK WITH THE CONSULTANT 16.17 16.08 16.18 16.18 16.08 16.17 15.96 15.90 15.96 15.96 15.90 15.96 16.32
16.30 16.30 16.30 16.06
TEAM, AUTHORITIES, STAKEHOLDERS AND CLIENT GROUPS THROUGH TO ISSUE FOR
1:50
1:50
1:49
DEVELOPMENT OF THE ENTIRE PROJECT WILL OCCUR, THE CONTRACTOR IS ADVISED TO MAKE AN 16.47 16.35
ASSESSMENT, BASED ON THEIR OWN EXPERIENCE OF PROJECTS OF THIS NATURE, OF RISKS 16.47 16.47 16.29 16.23 16.23
1:50
1:50
INCLUDING CHANGES TO SCOPE, DESIGN DEVELOPMENT, COMPLETION OF DETAILED DESIGN AND 16.32 16.16 16.36
1:50
16.19
1:50
16.50
1:80
COORDINATION AND MAKE ADEQUATE ALLOWANCES AND CONTINGENCIES FOR ITEMS IDENTIFIED IN
16.07
Plot Date: 31/1/2017 9:22:27 AM
'GAP ANALYSIS' DOCUMENTATION LOCATED IN THE DESIGN FEATURES REPORTS. 16.31 16.31 16.31 16.07 16.07
16.31 16.10
16.10
HIGH POINT
5 0
SCALE 1:500
10 20m
MOORHOUSE AVENUE
IN PARTNERSHIP WITH CLIENT REV DATE REVISION DETAILS APPROVED SCALE SIZE METRO SPORTS FACILITY - TAIWHANAGA REHIA
DEVELOPED DESIGN PROJECT
A 01/07/16 PRELIMINARY DESIGN ISSUE D ARMSTRONG 1:500 A0 NOT FOR CONSTRUCTION BALFOUR TERRACE CHRISTCHURCH
B 31/01/17 DEVELOPED DESIGN ISSUE D ARMSTRONG
DRAWN APPROVED
R SIMPSON . DATE
DESIGNED 01/07/16
TITLE SITE CONTOUR PLAN
C MERCER
R DAVIES
CHECKED PROJECT No. WBS TYPE DISC NUMBER REV
DRAWING No.
R SMITH D ARMSTRONG 250518 0000 DRG CI 0-10-21 B
Metro Sport Early
Works
Construction Noise and Vibration
Management Plan
Leighs Cockram JV Ltd
250518
10 August 2017
Document control record
Document prepared by:
Aurecon New Zealand Limited
Level 2, Iwikau Building
93 Cambridge Terrace
Christchurch 8013
New Zealand
Document control
Current revision 1
Approval
Project 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx 10 August 2017 Revision 1
Contents
1 Introduction.................................................................. 1
1.1 Scope 1
1.2 Project overview 1
1.3 Site description 1
1.4 Key contacts 3
1.5 Ongoing Noise and Vibration Effects 4
Appendices
Appendix A
Affected Receivers
Distance to Work Site
Appendix B
Predicted vibration levels
General vibratory works
Appendix C
Predicted noise levels
Figures
Figure 1 Metro Sport site overview ............................... 2
Figure 2 Layout of Canterbury Health Laboratories ....... 3
Figure 3 Potentially affected receivers around Metro
Sport construction site ...................................................... 11
Tables
Table 1 Metro Sport Early Works Key contacts.......... 3
Table 2 Operational Noise limits in Updated
Christchurch District Plan ................................................... 5
Table 3 NZS6803-1999 Noise Guidelines for residential
receivers (values taken from Table 2 in NZS6803-1999)... 5
Table 4 NZS6803-1999 Noise Guidelines for
commercial receivers (copied from Table 3 in NZS6803-
1999) 6
Table 5 Vibration guidelines for short-term vibration on
structures (replicated from Table 1 from DIN4150-3: 1992-
02) 6
Table 6 Transient vibration guidelines for cosmetic
damage (replicated from Table B.2 from BS 5228-2:2009) 7
Table 7 Subjective evaluation of vibration (replicated
from Table B.1 from BS 5228-2:2009) ............................... 7
Table 8 Relevant noise criteria for Metro Sport Early
Works level at affected receivers .................................... 8
Table 9 Selected vibration criteria for Metro Sport Early
Works level at affected receiver ...................................... 8
Table 10 Indicative programme for Metro Sport Early
Works 9
Table 11 Equipment used in for noise assessment ......... 9
Table 12 Noise levels due to construction activities ...... 10
Table 13 Typical high risk activities used in construction
and demolition works ........................................................ 12
Table 14 Hierarchy of controls for Metro Sport early
works 13
Table 15 Notification list for high noise and vibration
activities 14
Table 16 Notification list for stone column insertion ...... 15
Table 17 Notification list for residential receivers to be
notified if any night or Sunday works are undertaken ...... 17
Table 18 Information reporting requirements ................ 17
Table 19 Noise and vibration receivers around Metro
Sport site 20
Table 20 Predicted vibration level for potentially affected
receivers around Metro Sport site .................................... 25
Table 21 Predicted vibration level for potentially affected
receivers around Metro Sport site .................................... 29
Table 22 Noise and vibration receivers around Metro
Sport site 33
1 Introduction
1.1 Scope
This Construction Noise and Vibration Management Plan (CNVMP) has been developed to assist Leighs
Cockram JV (LCJV) in managing the noise and vibration emissions from the Metro Sport Early Works. This
document contains the following:
An overview of the project;
An assessment of relevant noise and vibration criteria, District Plan Rules, and Consent Conditions;
Specification of guideline noise and vibration limits for the construction activities;
An assessment of the noise and vibration risks for different project stages;
Predicted noise and vibration levels at nearby receivers around the site;
Management, monitoring and mitigation methodologies for noise and vibration emissions;
Detailed noise and vibration emission maps for communication purposes.
A separate Site Specific Noise and Vibration Management Plan (SSNVMP) will be issued for the Canterbury
Health Laboratories Site, as this has been identified as a highly sensitive receiver.
The early works have commenced in late July/early August and are predicted to be completed by the end of
October (total duration of approximately 10 - 12 weeks). Throughout this period various ground improvement
and site establishment activities will be undertaken. Initially several sheet piles, screw piles, and stone
columns will be installed in two test areas.
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 1
Figure 1 Metro Sport site overview
To the south of the site Moorhouse Ave. is a significant noise source, with three lanes of busy traffic an
Annual Average Daily Traffic (AADT) count of approximately 35,000/day1. South of Moorhouse Ave. is
predominantly light industrial and commercial sites, the nearest of which are approximately 50 m from the
carpark site and approximately 200 m from the Metro Sport building footprint.
To the east of the site Antigua St. is a moderate noise source, with two lanes of traffic and an AADT count of
approximately 7,500/day1. On the eastern side of Antigua St. are predominantly commercial sites and the
Christchurch Central Police Station. The nearest buildings are approximately 20 m from the Metro Sport
building footprint.
To the north, St. Asaph St. is a moderate noise source, with two lanes of traffic (1-way) and an AADT count
of approximately 10,000/day1. The Canterbury Health Laboratories occupy much of the site to the north.
These laboratories house vibration sensitive equipment, and have been identified as a vibration sensitive
receiver. The Endolab is approximately 50 m from the building footprint and the Canterbury Health Lab is
approximately 80 m from the building footprint. The location of the Canterbury Health Laboratories is shown
in the following figure, a detailed assessment of this site will be presented in a supplementary Site Specific
Management Plan.
1 mobileroad.org
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 2
Figure 2 Layout of Canterbury Health Laboratories
To the west, Stewart St. is a quiet, urban, two lane road, with an AADT of approximately 1000/day2. This
area is a mixture of light commercial sites, Hagley Community College, and some residential properties. The
nearest commercial sites are approximately 40 m from the Metro Sport building footprint. Due to the lower
existing noise and vibration environment properties on the western side are likely to be more sensitive to
noise and vibration emissions from the Metro Sport site.
The primary haul route is entry and exit via Balfour Terrace onto Antigua St. There are no specified haul
routes on the Metro Sport site and heavy vehicles are free to move anywhere on the existing site.
2 mobileroad.org
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 3
1.5 Ongoing Noise and Vibration Effects
This document is focused on managing the noise and vibration effects from the Metro Sports early works.
Effective management of noise and vibration effects on adjacent properties will have ongoing impacts on the
longer-term project. As such it is important that the management methodology described in this document is
followed and good communication is established with all affected stakeholders. Good co-ordination between
phases will be important to ensure that noise and vibration emissions from the ongoing Metro Sport
construction works are adequately managed.
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 4
2 Relevant noise and vibration criteria
2.1 Specification/Contract requirements
There are no specific consent conditions related to noise and vibration activities for the Metro Sport early
works.
These limits do not apply to construction activities, but they provide guidance on the existing noise
environment. Based on observations of the existing environment the noise level is significantly higher than
the daytime operational limit specified in Table 2.
Construction activities are listed as Permitted Activities in relation to noise and vibration emissions (Section
6.1.6.1.1 of the Christchurch District Plan) should meet the noise limits presented in Tables 2 and 3 of NZS
6803:19993 (see Section 6.1.6.1.1 of the Christchurch District Plan). The criteria specified in NZS6803-1999
are described in the following section.
All construction activities should manage vibration emissions and should meet the vibration limits specified in
DIN 4150-3 (1999-02) 4. The criteria specified in DIN 4150:1999 are described in the following section.
2.3.1 Noise
NZS6803-1999 provides guidance on construction noise criteria at both commercial and residential
receivers. The noise criteria are dependent on the duration of the works and the corresponding duration of
exposure. These criteria are presented in Table 3 and Table 4. The typical duration criteria are appropriate
for the management of noise emissions from construction activities.
In addition, the British Standard BS 5228-1 provides useful guidance for evaluating and the management of
noise from a wide range of construction sites and will be referenced throughout this document. The levels
and methodology specified in NZS 6803-1999 are based on BS 5228-1.
Table 3 NZS6803-1999 Noise Guidelines for residential receivers (values taken from Table 2 in NZS6803-1999)
Time period Typical duration (more Short-term duration (up to Long-term duration (more
than 14 days but less than 14 days), dBA than 20 weeks), dBA
20 weeks)
dB LAeq dB LAFmax dB LAeq dB LAFmax dB LAeq dB LAFmax
Weekdays
0630-0730 60 75 65 75 55 75
0730-1800 75 90 80 95 70 85
1800-2000 70 85 75 90 65 80
Table 4 NZS6803-1999 Noise Guidelines for commercial receivers (copied from Table 3 in NZS6803-1999)
Time period Short-term duration (up Typical duration (more Long-term duration
to 14 days), than 14 days but less (more than 20 weeks),
dB LAeq than 20 weeks), dB LAeq dB LAeq
0730-1800 75 80 70
1800-0730 80 85 75
2.3.2 Vibration
New Zealand does not have a standard that provides guidance on controlling vibration from construction
activities. The German standard DIN 4510:1999 is referenced in the Christchurch District Plan for the control
of vibration from earthworks activities. The British standard BS 5228-2:20095 is often used to provide
guidance on suitable vibration criteria for construction vibration levels received at buildings. Both these
standards utilise the measurement Peak Particle Velocity (PPV), which is the maximum absolute velocity for
the three horizontal and vertical direction.
DIN 4510:1999 specifies the following criteria for ground vibration levels measured or predicted at different
types of buildings. The maximum permissible vibration levels for various frequency ranges at the foundations
of a building are presented in Table 5
Table 5 Vibration guidelines for short-term vibration on structures (replicated from Table 1 from DIN4150-3:
1992-02)
5 BNS5228-2:2009 Code of practice for noise and vibration control on construction and open sites. Vibration.
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 6
BS 5228-2:2009 specifies alternative criteria for assessing the impact of ground vibration on structures. The
criteria provided in this standard are presented in Table 6. The effect of these vibration levels on the
occupants of the buildings is presented in Table 7
Table 6 Transient vibration guidelines for cosmetic damage (replicated from Table B.2 from BS 5228-2:2009)
Table 7 Subjective evaluation of vibration (replicated from Table B.1 from BS 5228-2:2009)
In addition to these standards, the NZTA provides guidance on construction noise and vibration in the State
highway construction and maintenance noise and vibration guide6. Whilst this guide is directed at road
construction, it addresses many common causes of construction noise and vibration. This guideline
replicates the levels presented in Table 7.
In our experience the low frequency DIN4150 criteria (Table 6) criteria are suitable for evaluating the impact
of ground vibration on structures, and the BS5228-2 subjective criteria (Table 6) are suitable for evaluating
the impact of vibration on the occupants of buildings. These criteria should be applied to all construction
activities, and should be utilised to inform neighbouring properties of the potential vibration impacts of these
works.
The vibration limits specified in Table 9 are based on the DIN4150, BS5228-2, and previous experience. The
notification limit of 1 mm/s ppv has been found to be effective at mitigating adverse community effects.
6 State highway construction and maintenance noise and vibration guide NZTA, August 2013, Version 1.0
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 7
The duration of the early works is approximately 10 weeks, as such the relevant NZS 6803:1999 noise limits
are the Typical Duration criteria. The anticipated project duration is based on the project programme
supplied by LCJV on 4/8/2017.
Table 8 Relevant noise criteria for Metro Sport Early Works level at affected receivers
Table 9 Selected vibration criteria for Metro Sport Early Works level at affected receiver
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 8
3 Assessment of noise and vibration impacts
3.1 Timeline
Currently the following schedules apply to the main activities, this schedule will be updated as the project
progresses. The duration of each activity is based on the project programme supplied by LCJV on 4/8/2017.
3.2 Equipment
The equipment listed in Table 11 have been produced based on our current understanding of the activities
on site. Currently the number of pieces of equipment and the duty cycle of this equipment has been
assumed based on similar project experience. The noise levels have been taken from BS 5228-1 and NZS
6803:1999. If noise measurements are performed as part of the ongoing management works this table will
be updated accordingly.
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 9
Equipment Number Operational duty Sound Pressure Reference
on site cycle Level at 10m,
dB LAeq
CPT rig 1 Intermittent (25%) 73 Estimate
(generator/hydraulic
pump)
3.3 Activities
The cumulative noise levels from each individual activity have been assessed using the methodology
specified in BS 5228-1. The noise levels at 10 m from these activities are presented in Table 12.
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 10
Figure 3 Potentially affected receivers around Metro Sport construction site
The vibration levels at all the potentially affected receivers have been predicted using the methodology
described in BS 5228-2. The predicted levels apply to the nearest edge of the affected structure. The
predicted vibration levels at the potentially affected receivers are presented in Appendix C.
As the location, duration and extent of all activities develop the predicted noise and vibration levels will be
updated appropriately. The current predicted levels should be viewed as a worst case scenario and actual
onsite construction noise levels are likely to be lower than this.
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 11
4 Risk Assessment
4.1 Noise and vibration risk levels
The noise and vibration risks of the activities proposed for the Metro Sport early works have been assessed,
and are presented in Table 13. High risk activities have a significant chance of causing adverse effects on
adjacent receivers and resulting in annoyance or complaints. The vibration risk is based on predicted
emissions and previous project experience with similar equipment. The noise risk due to various site
activities categorised as follows:
Low Less than 80 dBA at 10m
Medium 80 dBA to 85 dBA at 10m
High Greater than 85 dBA at 10m
Where practical the noise emissions from these works should be managed using the strategies presented in
Section 5.
Table 13 Typical high risk activities used in construction and demolition works
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 12
5 Management and mitigation
5.1 Management strategies
Noise and vibration effects should be managed using a standard hierarchy of controls as described in Table
14. Due to the project schedule and the activities being undertaken on site the most practical control strategy
is likely to be notification of affected receivers.
Noise monitoring is not suggested on the site due to the high background noise level from nearby industrial
sites and busy roads. If any high noise risk activities are to be undertaken at night this requirement should
be reassessed.
Noise and/or vibration monitoring should be implemented in response to any complaints received. The
details of this monitoring should be developed on receipt of the complaint. This monitoring may require the
installation of additional equipment, or may be sufficiently managed by the ongoing vibration monitoring.
If dynamic compaction is required on site this may have significant vibration effects and this will require a
more detailed assessment. A separate notification list will be prepared if dynamic compaction is to be
undertaken.
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 13
Details of a contact person on site;
Details of complaints procedure;
Works that will be undertaken that may cause disturbance;
Likely duration and times of day when high noise and/or vibration activities will be undertaken;
Predicted noise and/or vibration impacts;
Updates to duration and times of day if activities are delayed or prolonged.
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 14
The receivers identified in the following table should be notified if stone column activities are undertaken
within the noted areas. Due to the extent of the notification list for site wide stone columns it is advised that
this is updated when the location of all stone column activities are confirmed.
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 15
Address Stone columns Stone columns
limited to test anywhere within
sites only the building
footprint
235 Antigua Street No Yes
128 Moorhouse Avenue No Yes
140 Moorhouse Avenue No Yes
16 Waller Terrace No Yes
14 Waller Terrace No Yes
18 Waller Terrace No Yes
144 Moorhouse Avenue No Yes
10 Waller Terrace No Yes
144 Moorhouse Avenue No Yes
19 St. Asaph Street No Yes
104 Moorhouse Avenue No Yes
132 Moorhouse Avenue No Yes
130 Moorhouse Avenue No Yes
100 Moorhouse Avenue No Yes
550 Hagley Avenue No Yes
239 Antigua Street No Yes
98 Moorhouse Avenue No Yes
27 Waller Terrace No Yes
81 Moorhouse Avenue No Yes
7 Waller Terrace No Yes
136 Moorhouse Avenue No Yes
73 Moorhouse Avenue No Yes
21 Waller Terrace No Yes
16 Tuam Street No Yes
166 Moorhouse Avenue No Yes
264 Antigua Street No Yes
69 St. Asaph Street No Yes
77 Moorhouse Avenue No Yes
86 Moorhouse Avenue No Yes
19 Waller Terrace No Yes
31 Waller Terrace No Yes
71 St. Asaph Street No Yes
199 Hazeldean Road No Yes
33 Waller Terrace No Yes
17 Waller Terrace No Yes
76 Moorhouse Avenue No Yes
40 Tuam Street No Yes
15 Waller Terrace No Yes
35 Waller Terrace No Yes
11 Waller Terrace No Yes
1 12 / 41 Waller Terrace No Yes
69 Moorhouse Avenue No Yes
9 Waller Terrace No Yes
77 St. Asaph Street No Yes
77 St. Asaph Street No Yes
175 Moorhouse Avenue No Yes
74 Moorhouse Avenue No Yes
63 Moorhouse Avenue No Yes
48 Tuam Street No Yes
154 Hazeldean Road No Yes
156 Hazeldean Road No Yes
180 Hazeldean Road No Yes
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 16
All residential receivers should receive notification of any proposed night or Sunday works. The following
table provided a list of the identified residential receivers. Where possible night and Sunday works should be
avoided. If night or Sunday works are required they should meet the relevant district plan noise criteria; the
residential criteria should not be exceeded at night or on Sunday.
Table 17 Notification list for residential receivers to be notified if any night or Sunday works are undertaken
Address
34 Stewart St
33 Waller Terrace
35 Waller Terrace
1 12 / 41 Waller Terrace
8/488 Selwyn Street
7/488 Selwyn Street
3/492 Selwyn Street
2/492 Selwyn Street
2/492 Selwyn Street
6/488 Selwyn Street
5.5 Reporting
The following information will be compiled by the project acoustic engineer, within the time frames identified
in Table 18.
Information Timeframe
Noise/vibration Within one week of monitoring
survey reports
Noise/vibration Within 48 hours
complaint initial
report
Noise/vibration Within one week of closing complaint
complaint report
Updated CNVMP Within one week of significant changes
and SSEMP in project methodology
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 17
The initial response to any complaints should consist of acknowledgement of the complaint, and the
immediate actions that will be taken (e.g. monitoring, scheduling). This response should be documented in
complaints register.
The complaint report will assess the cause of the complaint, present monitoring results, and provide
information on the remedial action to be taken to prevent ongoing complaints.
Place stationary equipment (generators, pumps etc.) as practicable far from sensitive receivers;
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 18
Affected
Receivers
Appendix A
Affected Receivers
Distance to Work Site
The following table provides all receivers within 200 m of the Metro Sport construction site. The distance
between each receiver and the construction site, and the building footprint are also provided. These
distances are measured using GIS mapping software and are based on the nearest edge of the building.
Distance to
Building Distance to
Address Type Description Footprint Overall Site
1 - 12 / 212 Antigua Street Commercial - 26 m 29 m
1 12 / 41 Waller Terrace Residential - 140 m 251 m
1 & 2 / 40 Stewart Street Commercial Don Beaven Medical 13 m 55 m
Research Centre
1 Balfour Terrace Commercial Melray Electric 33 m 75 m
10 Halkett Street Commercial - 59 m 61 m
10 Halkett Street Commercial - 60 m 61 m
10 Waller Terrace Commercial The Auto Shop 40 m 163 m
100 Moorhouse Avenue Commercial Sugarhorse Bar & Eatery 61 m 202 m
104 Moorhouse Avenue Commercial Meridian 44 m 172 m
11 - 20 /212 Antigua Street Commercial - 25 m 24 m
11 Waller Terrace Commercial - 135 m 250 m
12 Acton Street Commercial - 88 m 92 m
12 Halkett Street Commercial - 70 m 71 m
122 Hazeldean Road Commercial - 203 m 358 m
126 Hazeldean Road Commercial - 187 m 341 m
128 Hazeldean Road Commercial - 187 m 338 m
128 Moorhouse Avenue Commercial Brownies Mattress 37 m 149 m
130 Hazeldean Road Commercial - 179 m 330 m
130 Moorhouse Avenue Commercial Vast Christchurch 60 m 169 m
132 Hazeldean Road Commercial - 189 m 336 m
132 Moorhouse Avenue Commercial - 58 m 165 m
134 Hazeldean Road Commercial - 185 m 330 m
136 Moorhouse Avenue Commercial - 86 m 193 m
137 Antigua Street Commercial - 185 m 298 m
14 Halkett Street Commercial - 80 m 81 m
14 Waller Terrace Commercial Hagley Motors 39 m 158 m
140 Hazeldean Road Commercial - 169 m 312 m
140 Moorhouse Avenue Commercial - 38 m 145 m
144 Hazeldean Road Commercial - 167 m 298 m
144 Moorhouse Avenue Commercial - 40 m 162 m
144 Moorhouse Avenue Commercial - 42 m 163 m
146 Hazeldean Road Commercial - 173 m 299 m
15 Halkett Street Commercial - 79 m 78 m
15 Stewart Street Commercial Paul Kelly Motor 22 m 137 m
Company
15 Waller Terrace Commercial - 127 m 242 m
152 Hazeldean Road Commercial - 174 m 291 m
154 Hazeldean Road Commercial - 166 m 280 m
156 Hazeldean Road Commercial - 166 m 278 m
157 Moorhouse Avenue Commercial Chevron Motors 50 m 122 m
16 Halkett Street Commercial - 93 m 96 m
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 20
Distance to
Building Distance to
Address Type Description Footprint Overall Site
16 St. Asaph Street Commercial - 35 m 75 m
16 Tuam Street Commercial - 89 m 115 m
16 Waller Terrace Commercial - 39 m 156 m
160 Antigua Street Commercial - 181 m 305 m
162 Hazeldean Road Commercial - 167 m 276 m
164 Hazeldean Road Commercial - 167 m 275 m
166 Hazeldean Road Commercial - 173 m 281 m
166 Moorhouse Avenue Commercial - 90 m 216 m
168 Hazeldean Road Commercial - 168 m 275 m
17 St. David Street Commercial - 71 m 97 m
17 Waller Terrace Commercial - 118 m 233 m
170 Hazeldean Road Commercial - 168 m 275 m
171 Moorhouse Avenue Commercial - 126 m 177 m
175 Montreal Street Commercial - 189 m 189 m
175 Moorhouse Avenue Commercial - 161 m 204 m
176 Hazeldean Road Commercial - 222 m 329 m
177 Montreal Street Commercial - 128 m 128 m
178 Hazeldean Road Commercial - 174 m 281 m
179 Moorhouse Avenue Commercial - 196 m 235 m
18 St. Asaph Street Commercial - 26 m 67 m
18 Waller Terrace Commercial - 39 m 155 m
180 Hazeldean Road Commercial - 167 m 275 m
183 Montreal Street Commercial - 158 m 157 m
184 Hazeldean Road Commercial - 173 m 283 m
186 Hazeldean Road Commercial - 169 m 286 m
19 St. Asaph Street Commercail - 43 m 87 m
19 St. David Street Commercial - 73 m 87 m
19 Stewart Street Commercial Unicool Automotive 24 m 136 m
Airconditioning
19 Waller Terrace Commercial - 109 m 224 m
190 Moorhouse Avenue Commercial - 171 m 263 m
192 Hazeldean Road Commercial - 171 m 297 m
198 Antigua Street Commercial TCS 30 m 69 m
198 Hazeldean Road Commercial - 186 m 315 m
199 Hazeldean Road Commercial - 111 m 244 m
2/492 Selwyn Street Residential - 198 m 311 m
2/492 Selwyn Street Residential - 198 m 311 m
20 Halkett Street Commercial - 102 m 104 m
200 Antigua Street Commercial Skylab 31 m 47 m
200 Hazeldean Road Commercial - 203 m 334 m
208 Antigua Street Commercial Electrolux 22 m 24 m
21 St. Asaph Street Commercial EndoLab 28 m 51 m
21 Waller Terrace Commercial - 87 m 203 m
210 Antigua Street Commercial Seatbelt sales 22 m 22 m
210 Hazeldean Road Commercial - 195 m 330 m
22 St. Asaph Street Commercial - 14 m 58 m
22 Waller Terrace Commercial Campervan Hire 39 m 154 m
220 Antigua Street Commercial - 22 m 26 m
226 Antigua Street Commercial - 57 m 61 m
230 Antigua Street Commercial CAnterbury Medical 26 m 31 m
Research Foundation
235 Antigua Street Commercial - 34 m 66 m
239 Antigua Street Commercial - 70 m 100 m
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 21
Distance to
Building Distance to
Address Type Description Footprint Overall Site
24 St. Asaph Street Commercial - 4m 44 m
264 Antigua Street Commercial - 90 m 123 m
27 Waller Terrace Commercial Holyoake Air 82 m 196 m
Management Solutions
3 Balfour Terrace Commercial - 1m 43 m
3/492 Selwyn Street Residential - 194 m 308 m
30 Stewart Street Commercial - 26 m 94 m
31 Waller Terrace Commercial MecServe 109 m 224 m
33 St. Asaph Street Commercial CDHB Emergency 29 m 51 m
Operations Centre
33 Waller Terrace Residential - 116 m 230 m
34 Stewart Street Residential - 53 m 94 m
35 Waller Terrace Residential - 129 m 241 m
38 Stewart Street Commercial Melray Electric 44 m 93 m
4 Acton Street Commercial - 187 m 189 m
40 Tuam Street Commercial - 122 m 150 m
42 Stewart Street Commercial Child and Family Safety 4m 46 m
Services
46 Braddon Street Commercial - 202 m 311 m
48 Braddon Street Commercial - 192 m 301 m
48 Tuam Street Commercial - 162 m 190 m
49 Braddon Street Commercial - 191 m 304 m
510 Hagley Ave Education Hagley Collge 73 m 110 m
52 Stewart Street Commercial Auto Restorations Ltd 3m 44 m
52 Stewart Street Commercial Auto Restorations Ltd 5m 46 m
550 Hagley Avenue Commercial Canterbury Health Labs 61 m 84 m
6/488 Selwyn Street Residential - 206 m 321 m
61 Moorhouse Avenue Commercial Bridgestone Select 185 m 304 m
63 Moorhouse Avenue Commercial - 161 m 283 m
64 Stewart Street Commercial Auto Restorations 25 m 66 m
Limited
66 Stewart Street Commercial NZ Brain Research 24 m 64 m
Institute
68 St. Asaph Street Commercial Christchurch Central 56 m 63 m
Police Station
68 Tuam Street Commercial - 188 m 211 m
69 Moorhouse Avenue Commercial - 140 m 266 m
69 St. Asaph Street Commercial Betamorphis Lt 94 m 114 m
7 Waller Terrace Commercial - 85 m 208 m
7/488 Selwyn Street Residential - 193 m 307 m
70 Moorhouse Avenue Commercial - 180 m 331 m
71 St. Asaph Street Commercial - 110 m 137 m
73 Moorhouse Avenue Commercial Zip Plumbing Plus 86 m 206 m
74 Moorhouse Avenue Commercial - 161 m 314 m
76 Moorhouse Avenue Commercial Luciano Espresso 121 m 278 m
Bar/Lighting Direct
77 Moorhouse Avenue Commercial - 97 m 225 m
77 St. Asaph Street Commercial - 149 m 168 m
77 St. Asaph Street Commercial - 150 m 169 m
8/488 Selwyn Street Residential - 178 m 293 m
81 Moorhouse Avenue Commercial Fast Autoglass 82 m 210 m
85 Moorhouse Avenue Public Majestic Church 33 m 166 m
86 Moorhouse Avenue Commercial - 106 m 264 m
87 St. Asaph Street Commercial - 191 m 210 m
9 Waller Terrace Commercial - 144 m 259 m
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 22
Distance to
Building Distance to
Address Type Description Footprint Overall Site
98 Moorhouse Avenue Commercial - 81 m 239 m
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 23
Predicted
vibration levels
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 24
Appendix B
Predicted vibration levels
General vibratory works
The following table presents the predicted vibration level at the identified potentially affected receivers
around the Metro Sport site. These levels were calculated using the standard methodology specified in
BS5228-2. The vibration emissions from the following activities were based on the assumption these
activities would only occur within the building footprint:
Stone column installation;
Sheet pile installation.
The vibration emissions from dynamic compaction are based on the assumption that this activity could occur
anywhere on the Metro Sport site.
Table 20 Predicted vibration level for potentially affected receivers around Metro Sport site
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 25
Predicted vibration Level, ppv mm/s
Address Sheet pile installation Screw pile installation Dynamic compaction
19 St. Asaph Street 0.8 0.8 3.9
12 Acton Street 0.7 0.7 1.6
38 Stewart Street 0.7 0.7 3.8
34 Stewart Street 0.7 0.7 3.4
30 Stewart Street 0.7 0.7 7.4
16 Halkett Street 0.7 0.7 1.5
17 St. David Street 0.7 0.7 2.1
239 Antigua Street 0.7 0.7 2.2
20 Halkett Street 0.6 0.6 1.3
510 Hagley Ave 0.6 0.6 2.1
69 St. Asaph Street 0.6 0.6 1.5
16 Tuam Street 0.6 0.6 1.6
157 Moorhouse Avenue 0.5 0.5 3.3
264 Antigua Street 0.5 0.5 1.6
177 Montreal Street 0.5 0.5 1.0
19 Stewart Street 0.4 0.4 8.0
71 St. Asaph Street 0.4 0.4 1.2
15 Stewart Street 0.4 0.4 8.8
140 Moorhouse Avenue 0.4 0.4 4.6
128 Moorhouse Avenue 0.4 0.4 4.7
40 Tuam Street 0.4 0.4 1.1
22 Waller Terrace 0.4 0.4 4.4
18 Waller Terrace 0.4 0.4 4.4
16 Waller Terrace 0.4 0.4 4.4
183 Montreal Street 0.4 0.4 0.8
14 Waller Terrace 0.4 0.4 4.4
144 Moorhouse Avenue 0.4 0.4 4.4
10 Waller Terrace 0.4 0.4 4.3
144 Moorhouse Avenue 0.4 0.4 4.2
132 Moorhouse Avenue 0.3 0.3 2.7
85 Moorhouse Avenue 0.3 0.3 5.5
77 St. Asaph Street 0.3 0.3 0.8
130 Moorhouse Avenue 0.3 0.3 2.6
77 St. Asaph Street 0.3 0.3 0.8
104 Moorhouse Avenue 0.3 0.3 3.9
171 Moorhouse Avenue 0.3 0.3 1.0
4 Acton Street 0.3 0.3 0.6
175 Montreal Street 0.3 0.3 0.6
48 Tuam Street 0.3 0.3 0.7
136 Moorhouse Avenue 0.3 0.3 1.7
27 Waller Terrace 0.3 0.3 1.8
100 Moorhouse Avenue 0.3 0.3 2.6
21 Waller Terrace 0.3 0.3 1.6
175 Moorhouse Avenue 0.3 0.3 0.8
73 Moorhouse Avenue 0.3 0.3 1.7
7 Waller Terrace 0.3 0.3 1.7
81 Moorhouse Avenue 0.3 0.3 1.8
87 St. Asaph Street 0.3 0.3 0.6
68 Tuam Street 0.3 0.3 0.6
166 Moorhouse Avenue 0.2 0.2 1.6
31 Waller Terrace 0.2 0.2 1.2
19 Waller Terrace 0.2 0.2 1.2
77 Moorhouse Avenue 0.2 0.2 1.4
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 26
Predicted vibration Level, ppv mm/s
Address Sheet pile installation Screw pile installation Dynamic compaction
33 Waller Terrace 0.2 0.2 1.1
17 Waller Terrace 0.2 0.2 1.1
179 Moorhouse Avenue 0.2 0.2 0.6
98 Moorhouse Avenue 0.2 0.2 1.8
35 Waller Terrace 0.2 0.2 1.0
15 Waller Terrace 0.2 0.2 1.0
199 Hazeldean Road 0.2 0.2 1.2
11 Waller Terrace 0.2 0.2 0.9
1 12 / 41 Waller Terrace 0.2 0.2 0.9
9 Waller Terrace 0.2 0.2 0.9
190 Moorhouse Avenue 0.2 0.2 0.7
86 Moorhouse Avenue 0.2 0.2 1.3
69 Moorhouse Avenue 0.2 0.2 0.9
170 Hazeldean Road 0.2 0.2 0.7
180 Hazeldean Road 0.2 0.2 0.7
168 Hazeldean Road 0.2 0.2 0.7
164 Hazeldean Road 0.2 0.2 0.7
162 Hazeldean Road 0.2 0.2 0.7
76 Moorhouse Avenue 0.2 0.2 1.1
156 Hazeldean Road 0.2 0.2 0.7
154 Hazeldean Road 0.2 0.2 0.7
166 Hazeldean Road 0.2 0.2 0.7
178 Hazeldean Road 0.2 0.2 0.7
63 Moorhouse Avenue 0.2 0.2 0.7
184 Hazeldean Road 0.2 0.2 0.7
186 Hazeldean Road 0.2 0.2 0.7
152 Hazeldean Road 0.2 0.2 0.7
8/488 Selwyn Street 0.2 0.2 0.7
192 Hazeldean Road 0.2 0.2 0.7
137 Antigua Street 0.2 0.2 0.6
144 Hazeldean Road 0.2 0.2 0.7
146 Hazeldean Road 0.2 0.2 0.7
48 Braddon Street 0.2 0.2 0.6
49 Braddon Street 0.2 0.2 0.6
61 Moorhouse Avenue 0.2 0.2 0.6
160 Antigua Street 0.2 0.2 0.6
7/488 Selwyn Street 0.2 0.2 0.6
3/492 Selwyn Street 0.2 0.2 0.6
2/492 Selwyn Street 0.2 0.2 0.6
2/492 Selwyn Street 0.2 0.2 0.6
46 Braddon Street 0.2 0.2 0.6
140 Hazeldean Road 0.2 0.2 0.7
74 Moorhouse Avenue 0.2 0.2 0.8
198 Hazeldean Road 0.2 0.2 0.6
6/488 Selwyn Street 0.1 0.1 0.5
176 Hazeldean Road 0.1 0.1 0.5
130 Hazeldean Road 0.1 0.1 0.7
134 Hazeldean Road 0.1 0.1 0.6
210 Hazeldean Road 0.1 0.1 0.6
70 Moorhouse Avenue 0.1 0.1 0.7
200 Hazeldean Road 0.1 0.1 0.6
132 Hazeldean Road 0.1 0.1 0.6
128 Hazeldean Road 0.1 0.1 0.6
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 27
Predicted vibration Level, ppv mm/s
Address Sheet pile installation Screw pile installation Dynamic compaction
126 Hazeldean Road 0.1 0.1 0.6
122 Hazeldean Road 0.1 0.1 0.6
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 28
Stone column insertion
The following table presents the vibration level at all potentially affected receivers due to stone columns
within the building footprint and within the test sites. These levels are based on measured data and an
empirical correction factor.
Table 21 Predicted vibration level for potentially affected receivers around Metro Sport site
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 29
Predicted vibration Level, ppv mm/s
Stone columns anywhere in Stone columns within specified test
Address building footprint sites
33 St. Asaph Street 2.6 1.0
22 Waller Terrace 2.2 1.0
4 Acton Street 1.0 1.0
21 St. Asaph Street 2.7 1.0
175 Montreal Street 1.0 0.9
18 Waller Terrace 2.2 0.9
144 Moorhouse Avenue 2.2 0.9
144 Moorhouse Avenue 2.2 0.9
140 Moorhouse Avenue 2.3 0.9
16 Waller Terrace 2.2 0.9
235 Antigua Street 2.4 0.9
14 Waller Terrace 2.2 0.9
19 St. Asaph Street 2.1 0.9
175 Moorhouse Avenue 1.1 0.9
10 Waller Terrace 2.2 0.9
69 St. Asaph Street 1.4 0.9
128 Moorhouse Avenue 2.3 0.9
85 Moorhouse Avenue 2.5 0.9
166 Moorhouse Avenue 1.5 0.9
550 Hagley Avenue 1.8 0.9
132 Moorhouse Avenue 1.8 0.9
27 Waller Terrace 1.5 0.9
239 Antigua Street 1.7 0.9
130 Moorhouse Avenue 1.8 0.8
21 Waller Terrace 1.5 0.8
104 Moorhouse Avenue 2.1 0.8
179 Moorhouse Avenue 1.0 0.8
136 Moorhouse Avenue 1.5 0.8
73 Moorhouse Avenue 1.5 0.8
16 Tuam Street 1.5 0.8
71 St. Asaph Street 1.3 0.8
7 Waller Terrace 1.5 0.8
31 Waller Terrace 1.3 0.8
33 Waller Terrace 1.3 0.8
77 St. Asaph Street 1.1 0.8
77 St. Asaph Street 1.1 0.8
19 Waller Terrace 1.3 0.8
264 Antigua Street 1.5 0.8
81 Moorhouse Avenue 1.5 0.8
199 Hazeldean Road 1.3 0.8
17 Waller Terrace 1.3 0.8
35 Waller Terrace 1.2 0.8
40 Tuam Street 1.2 0.8
190 Moorhouse Avenue 1.0 0.8
100 Moorhouse Avenue 1.8 0.8
1 12 / 41 Waller Terrace 1.2 0.8
15 Waller Terrace 1.2 0.8
77 Moorhouse Avenue 1.4 0.8
11 Waller Terrace 1.2 0.8
9 Waller Terrace 1.1 0.8
87 St. Asaph Street 1.0 0.8
98 Moorhouse Avenue 1.5 0.7
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 30
Predicted vibration Level, ppv mm/s
Stone columns anywhere in Stone columns within specified test
Address building footprint sites
68 Tuam Street 1.0 0.7
48 Tuam Street 1.1 0.7
69 Moorhouse Avenue 1.2 0.7
61 Moorhouse Avenue 1.0 0.7
8/488 Selwyn Street 1.0 0.7
180 Hazeldean Road 1.1 0.7
63 Moorhouse Avenue 1.1 0.7
186 Hazeldean Road 1.0 0.7
86 Moorhouse Avenue 1.3 0.7
170 Hazeldean Road 1.0 0.7
184 Hazeldean Road 1.0 0.7
192 Hazeldean Road 1.0 0.7
2/492 Selwyn Street 1.0 0.7
178 Hazeldean Road 1.0 0.7
168 Hazeldean Road 1.0 0.7
2/492 Selwyn Street 1.0 0.7
3/492 Selwyn Street 1.0 0.7
7/488 Selwyn Street 1.0 0.7
160 Antigua Street 1.0 0.7
164 Hazeldean Road 1.0 0.7
76 Moorhouse Avenue 1.3 0.7
137 Antigua Street 1.0 0.7
166 Hazeldean Road 1.0 0.7
162 Hazeldean Road 1.0 0.7
198 Hazeldean Road 1.0 0.7
210 Hazeldean Road 1.0 0.7
156 Hazeldean Road 1.1 0.7
154 Hazeldean Road 1.1 0.7
6/488 Selwyn Street 0.9 0.7
200 Hazeldean Road 0.9 0.7
152 Hazeldean Road 1.0 0.7
48 Braddon Street 1.0 0.7
144 Hazeldean Road 1.0 0.7
146 Hazeldean Road 1.0 0.7
74 Moorhouse Avenue 1.1 0.7
49 Braddon Street 1.0 0.7
46 Braddon Street 0.9 0.7
176 Hazeldean Road 0.9 0.6
140 Hazeldean Road 1.0 0.6
70 Moorhouse Avenue 1.0 0.6
130 Hazeldean Road 1.0 0.6
134 Hazeldean Road 1.0 0.6
132 Hazeldean Road 1.0 0.6
128 Hazeldean Road 1.0 0.6
126 Hazeldean Road 1.0 0.6
122 Hazeldean Road 0.9 0.6
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 31
Predicted
noise levels
Appendix C
Predicted noise levels
The following table presents the predicted noise level at the identified potentially affected receivers around
the Metro Sport site. These levels were calculated using the standard methodology specified in BS5228-1
and NZS 6803. It was assumed that the following activities would only occur within the existing building
footprint:
Stone Columns;
Sheet Piling;
Screw Piling.
The noise emissions from the following activities were assessed for the overall construction site:
General Earthworks;
Dynamic Compaction.
Please note that the levels from the following activities are not included as the predicted levels are below 75
dBA for all locations on the Metro Sport site:
Hydro-bore installation;
Water flow testing;
CPT test rig.
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 33
Predicted external, free-field noise levels, dB L Aeq
Stone Sheet Piling Screw Piling General Dynamic
Address Columns Earthworks Compaction
1 Balfour Terrace 64 69 65 71 74
15 Halkett Street 64 69 65 63 66
14 Halkett Street 64 69 65 63 66
550 Hagley Avenue 64 69 65 65 68
19 St. David Street 63 68 64 64 67
19 St. Asaph Street 63 68 64 68 71
12 Acton Street 63 68 64 62 65
38 Stewart Street 63 68 64 65 68
34 Stewart Street 63 68 64 68 71
30 Stewart Street 63 68 64 73 76
16 Halkett Street 62 67 63 62 65
17 St. David Street 62 67 63 64 67
239 Antigua Street 62 67 63 64 67
20 Halkett Street 62 67 63 61 64
510 Hagley Ave 61 66 62 64 67
69 St. Asaph Street 61 66 62 62 65
16 Tuam Street 61 66 62 62 65
157 Moorhouse Avenue 60 65 61 67 70
264 Antigua Street 60 65 61 62 65
177 Montreal Street 60 65 61 59 62
19 Stewart Street 59 64 60 73 76
71 St. Asaph Street 59 64 60 60 63
15 Stewart Street 59 64 60 74 77
140 Moorhouse Avenue 59 64 60 69 72
128 Moorhouse Avenue 59 64 60 70 73
40 Tuam Street 58 63 59 59 62
22 Waller Terrace 58 63 59 69 72
18 Waller Terrace 58 63 59 69 72
16 Waller Terrace 58 63 59 69 72
183 Montreal Street 58 63 59 57 60
14 Waller Terrace 58 63 59 69 72
144 Moorhouse Avenue 58 63 59 69 72
10 Waller Terrace 58 63 59 69 72
144 Moorhouse Avenue 58 63 59 69 72
132 Moorhouse Avenue 58 63 59 66 69
85 Moorhouse Avenue 58 63 59 71 74
77 St. Asaph Street 57 62 58 58 61
130 Moorhouse Avenue 57 62 58 65 68
77 St. Asaph Street 57 62 58 57 60
104 Moorhouse Avenue 57 62 58 68 71
171 Moorhouse Avenue 57 62 58 59 62
4 Acton Street 56 61 57 56 59
175 Montreal Street 56 61 57 55 58
48 Tuam Street 56 61 57 57 60
136 Moorhouse Avenue 56 61 57 62 65
27 Waller Terrace 56 61 57 63 66
100 Moorhouse Avenue 56 61 57 65 68
21 Waller Terrace 56 61 57 62 65
175 Moorhouse Avenue 56 61 57 57 60
73 Moorhouse Avenue 56 61 57 62 65
7 Waller Terrace 56 61 57 62 65
81 Moorhouse Avenue 56 61 57 63 66
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 34
Predicted external, free-field noise levels, dB L Aeq
Stone Sheet Piling Screw Piling General Dynamic
Address Columns Earthworks Compaction
87 St. Asaph Street 56 61 57 55 58
68 Tuam Street 56 61 57 56 59
166 Moorhouse Avenue 55 60 56 62 65
31 Waller Terrace 55 60 56 60 63
19 Waller Terrace 55 60 56 60 63
77 Moorhouse Avenue 55 60 56 61 64
33 Waller Terrace 55 60 56 60 63
17 Waller Terrace 55 60 56 60 63
179 Moorhouse Avenue 55 60 56 55 58
98 Moorhouse Avenue 54 59 55 63 66
35 Waller Terrace 54 59 55 59 62
15 Waller Terrace 54 59 55 59 62
199 Hazeldean Road 54 59 55 60 63
11 Waller Terrace 54 59 55 58 61
1 12 / 41 Waller Terrace 54 59 55 58 61
9 Waller Terrace 54 59 55 58 61
190 Moorhouse Avenue 54 59 55 56 59
86 Moorhouse Avenue 54 59 55 60 63
69 Moorhouse Avenue 53 58 54 58 61
170 Hazeldean Road 53 58 54 56 59
180 Hazeldean Road 53 58 54 57 60
168 Hazeldean Road 53 58 54 57 60
164 Hazeldean Road 53 58 54 57 60
162 Hazeldean Road 53 58 54 57 60
76 Moorhouse Avenue 53 58 54 59 62
156 Hazeldean Road 53 58 54 57 60
154 Hazeldean Road 53 58 54 57 60
166 Hazeldean Road 53 58 54 56 59
178 Hazeldean Road 53 58 54 56 59
63 Moorhouse Avenue 53 58 54 57 60
184 Hazeldean Road 53 58 54 56 59
186 Hazeldean Road 53 58 54 56 59
152 Hazeldean Road 53 58 54 56 59
8/488 Selwyn Street 53 58 54 56 59
192 Hazeldean Road 53 58 54 56 59
137 Antigua Street 53 58 54 56 59
144 Hazeldean Road 53 58 54 57 60
146 Hazeldean Road 52 57 53 56 59
48 Braddon Street 52 57 53 55 58
49 Braddon Street 52 57 53 55 58
61 Moorhouse Avenue 52 57 53 56 59
160 Antigua Street 52 57 53 56 59
7/488 Selwyn Street 52 57 53 55 58
3/492 Selwyn Street 52 57 53 55 58
2/492 Selwyn Street 52 57 53 55 58
2/492 Selwyn Street 52 57 53 55 58
46 Braddon Street 52 57 53 55 58
140 Hazeldean Road 52 57 53 56 59
74 Moorhouse Avenue 52 57 53 57 60
198 Hazeldean Road 52 57 53 56 59
6/488 Selwyn Street 52 57 53 55 58
176 Hazeldean Road 52 57 53 54 57
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 35
Predicted external, free-field noise levels, dB L Aeq
Stone Sheet Piling Screw Piling General Dynamic
Address Columns Earthworks Compaction
130 Hazeldean Road 52 57 53 56 59
134 Hazeldean Road 52 57 53 56 59
210 Hazeldean Road 52 57 53 55 58
70 Moorhouse Avenue 52 57 53 56 59
200 Hazeldean Road 52 57 53 55 58
132 Hazeldean Road 51 56 52 55 58
128 Hazeldean Road 51 56 52 56 59
126 Hazeldean Road 51 56 52 56 59
122 Hazeldean Road 51 56 52 55 58
Project number 250518 File 250518-R01-AC-R1[1.0] MetroSport Construction Noise and Vibration Management Plan.docx, 10 August 2017 Revision 1 36
Document prepared by