Documente Academic
Documente Profesional
Documente Cultură
PREPARED BY:
Matric No :2015886518
Programme :EE112
Supervisor
By:
2015886518
June 2017
ACKNOWLEDGEMENT
First of all,I would like to express my highest gratitude to Allah S.W.T for His
guidance,bless and for giving me the strength to perform my responsibilities as a trainee
and complete this industrial training report within the stipulated time.
My grateful thanks goes to the Puan Salina binti Ahmad for giving me the opportunity
to carry out my industrial training in this agency for 8 weeks period. A big contribution
and hard worked fro staff during practical period is very great indeed.
The special thank goes to my helpful supervisor,Ahmad Aminuddin bin Basar.The
supervision and support that he gave truly help the progression and smoothness of the
internship programme.Not forget, great appreciation go to the rest of Mohd.Azhar bin
Mohd.Khairi, staff that help me from time to time during the project.The whole program
really brought us to appreciate the true value of friendship and respect of each other.
Lastly, to my family and friends that also give me strength and guide to continue my
journey as a trainee and complete my internship. Thank you to all of you that involve as
direct or indirect to make sure this programme smooth and clear.
ABSTRACT
This report is explain about my activities that I have done during industrial training
for 8 week in Politeknik Banting Selangor. Politeknik Banting Selangor (PBS) were the
places for student to get a diploma or degree certificate. It also explain about
development and maintenance unit that which I doing industrial training with monitored
by supervisor to make our job more safety and can be done smoothly.
Inside this report it will explain more detail about background of the company,
history of the company, overview of industrial training at Politeknik Banting Selangor,
and my activities during industrial training, problems encountered with comment, and
how to solve the problems with my supervisor. Beside that,every safety, component and
equipment will be explain to make more clearly know how to use and to be more aware
on surrounding.
This report were making with my full hardworking and struggle to finish it because
Im narrowness of time between my part time job and doing report. Hopefully, every
information that will be explain can satisfying the reader at once can give benefits to
myself and the organization itself. Other than that, it can give me the direction and
strong to face every problems in my future life at work environment.
TABLE OF CONTENT
Acknowledgment I
TABLE OF CONTENTS II
LIST OF TABLE IV
LIST OF APPENDICES V
ABSTRACT VI
CHAPTER 1 INTRODUCTION 2
1.1)INTRODUCTION OF FIRM 2
1.2)COMPANY BACKGROUND 3
1.3)ORGANIZATION CHART 5
2.3)JOB RESPONSIBILITIES 9
2.4)OVERVIEW OF TRAINING 10
3.1)INTRODUCTION 18
3.2)FEEDER PILLAR 19
3.3)SUBSTATION 23
1
3.5)FIRE PROTECTION SYSTEM 27
3.7)PANEL BOARD 33
3.10)AIR COMPRESSOR 45
4.2)REFERENCE 50
4.3)APPENDIX 51
CHAPTER 1: INTRODUCTION
2
Organization names : Politeknik Banting Selangor
Telephone No :03-31201625
Fax No :03-31201706
E-mail :admin@polibanting.edu.my
Website :http://www.polibanting.edu.my
3
1.2 Company Background
1.2.1 HISTORY
PBS has always given priority to the sharing of knowledge and industry relationships in
which teachers are encouraged to participate in industrial projects, research and
development. This effort is open to the exchange of ideas and expertise with institutions
and industry to produce graduates skilled, competent, ready to work and have the nature
for marketability. Hence, the PBS intends to develop the network and collaborative
relationships with the industry on an ongoing basis. In addition, students will be able to
equip themselves for more industry savvy, resilient with the right mind set towards
achieving high-income nation's workforce. This initiative will continue to be a priority
to strengthen the resilience and competitiveness of students.
In realizing this mission, PBS has appointed 10 members of the Advisory Board of the
caliber to join together in achieving the organization's direction and advise on the
management and improve the quality of graduates PBS. Party PBS feel proud and lucky
and thank the contributions made by members of the Advisory Board in reinforcing and
improving the programs offered at the university in line with the rapid technological
advancements.
4
1.2.2 MISION
1.2.3 VISION
PBS was determined to develop the excellence of students to ensure that students
acquire the marketability and career readiness as well as meeting the needs of customers
through the process of continuous improvements
Product
Service
5
6
1.3 Organization chart.
7
1.3.2 Organization chart Development and Maintenance Unit.
PENOLONG JURUTERA
8
AHMAD AMINUDDIN BIN BASAR
JURUTEKNIK
9
CHAPTER 2: JOB OVERVIEW
2.1.1 Purpose
The purpose of industrial training is to produce graduates who are ready and capable
to face their profession academically or non-academically with a high professionalism
appearance. Other than that, the industrial training exposes the students about the real
situation of the working class citizen. The industrial training also helps in developing
social skills in the students.
To expose the students to the real life working experience and expanding the knowledge
in their specific field.
i. Students will further learn about their real life profession. They will also learn
what they need to do in order to finish their works. This will prepare the students
so that they will easily fit in and fulfill the demands of their profession after they
10
ii. Students are only exposed to the basic theory and needed in the fields of their own.
These theory and were mainly according to the books. With the industrial training in
place, students will experience real life situation in the field. This will make the students
use their knowledge in order to get their works done.
To produce trustworthy workers with high responsibility and able to cooperate with
other staffs.
i. All tasks given by the supervisor must be completed with a sense of trustworthy and
full responsibility. This attitude very important to ensure all business entrusted to
students were carried out flawlessly. Also, it train the students to be honest not only to
themselves but others as well.
ii. When the industrial training students are exposed to a variety of problems and had to
face it. With the experience learned through industrial training, the students will be
more confidence both in learning and working. High spirit and skills to overcome the
problems faced certainly create a strong confidence in the students.
i. In this training, students get the opportunity to interact with upper management such
as engineer,director and consultant and others. With this opportunity , student will be
able to associate and discuss with them in a closer way. This opportunity will not come
without the implication of industrial training. This opportunity should be used well by
the students to learn more.
11
i. There will be many things that students will face during the period of the industrial
training. These events will enhance the curiosity in the students. Other than that,the real
life exposure given to the students will also increase the interest of the students towards
their fields of studies.
12
2.2 Scope Of Work
Unit pembangunan dan penyenggaraan (UPP) is a unit that manages the development,
13
Maintenance should be emphasized especially important assets involved in the learning
process of polytechnics Malaysia disturbed and avoid long term loss.
Objective
Ensure that all buildings and infrastructure facilities in good condition and safe to
support the process of semi-professional training and running perfectly smoothly.
Function
-Compare the cost for fix damaged occured to get the low budget.
14
OVERVIEW OF TRAINING
WEEK 1
15
21 April 2017 Wiring the plug.
WEEK 2
Collaborative activities.
16
26 April 2017 Repair a whiteboard.
17
WEEK 3
18
WEEK 4
19
11 May 2017 Filing
WEEK 5
20
15 May 2017 Mailing the letter of air conditioning
problems to other company.
21
WEEK 6
22
26 May 2017 Learning the location address at
distribution board.
WEEK 7
23
30 May 2017 Troubleshoot the trip at Kooperasi.
WEEK 8
24
5 June 2017 Learn how to write quotation mail.
25
CHAPTER 3: TECHNICAL REPORT
3.1 Introduction
This chapter is explain about the whole weekend activities that have been done
during practical. Based on activities that have been record on log book with briefly will
be explain in this chapter was task from my supervisor to be done. Every activities or
task that have been done must record at log book. Thats why this part will be explain
more detail about activities that have been done during industrial training at Politeknik
Banting for 2 month.
All activities will be explain for week by week , so that can concluded the works in
a week ,other than that it can easier the process of review. Work day in a week not
always same each week because the company have a public holiday or holiday that will
be announcement from company.
26
During undergoing the industrial training,I have been exposed with more new things.
Besides that,I had been introduced with the rules and company ethics where Im doing
the industrial training. During my industrial training I have been places to the
development and maintenance unit department that more to repair and maintenance
works. My supervisor is mechanical engineer but in their he must learn electrical and
civil engineering to do the job as technician.
Each work task had been scheduled by maintenance engineer for easier our job
maintenance. After that every week we do prevention maintenance thats mean routine
check around the Politeknik Banting by followed the scheduled. In undergo industrial
training, I have gave time for 8 hour per day,start from 8.00 a.m until 5.00 p.m every
day for Monday until Friday. Thats was my weekly summary when Im doing the
industrial training.
27
Definition
28
Figure 1.2: Compound Lighting Feeder Pillar Schematic Image
29
3.2.2 The time switch.
-To eliminate the need for human actions to turn ON and OFF the lighting at the
intended operation hours.
-It simply bypass the time switch to turn ON or OFF the external lighting or street
lighting.
-The load currents to the lighting cables are usually higher than the current that the
timer contacts can handle.
-Another coil with heavy current contacts needs to provided to switch the heavy
currents.
30
3.2.5 Safety step before troubleshooting:
3.2.6 Troubleshooting
31
i) Look for the trip at feeder pillar.
ii)Turn OFF all circuit breaker and set the time at time switch.
iii)Turn ON from main switch and turn ON one by one the circuit breaker with bypass
at timer to ON the light.
iv)If found the trip at circuit breaker,thats mean one of the lamp have the problem.
32
3.3 Substation
Definition
33
Substations may be owned and operated by an electrical utility, or may be owned
by a large industrial or commercial customer. Generally substations are unattended,
relying on SCADA for remote supervision and control.
The word substation comes from the days before the distribution system became
a grid. As central generation stations became larger, smaller generating plants were
converted to distribution stations, receiving their energy supply from a larger plant
instead of using their own generators. The first substations were connected to only
one power station, where the generators were housed, and were subsidiaries of that
power station
3.4.1Transformer.
34
This transformer can steps down the high voltage electricity to the low voltage
electricity
35
Figure 1.7: Power factor correction board.
Power factor is the ratio between the KW and the KVA drawn by an electrical load
where the KW is the actual load power and the KVA is the apparent load power. It is a
measure of how effectively the current is being converted into useful work output and
more particularly is a good indicator of the effect of the load current on the efficiency of
the supply system.
2.Check the type of capacitor installed is suitable for application or the capacitor are
derated.
3.Check if the capacitors are permanently ON. The Capacitor are not switched off.
4.When the load is not working, under such condition the average power factor is found
to be lower side.
36
5.Check whether all the capacitors are operated in APFC depending upon the load
operation.
Definition
Earthing system connects specific parts of that installation with the Earths conductive
surface for safety and functional purposes.
-To protect a single-wire earth return power and signal lines, such as were used for low
wattage power delivery.
-As ancillary voltage balance for other kinds of radio antennas, such as dipoles.
-As the feed-point of a ground dipole antenna for VLF and ELF radio.
37
3.5 Fire protection system
Politeknik banting is equipped with hose reel system, fire alarm system,heat and smoke
detectors,portable fire extinguishers and other passive fire systems.The walls are
protected with Fire Rated Walls to ensure the building is able to withstand the fire for a
certain of time to allow occupants to escape.
38
Every fire exit and escape staircase is equipped with a Keluar sign to guide the
building occupants to the exit path. Besides, a simplified floor plan with indications on
the emergency exit is located next to the lift on every level of the building. Emergency
light are also installed at each areas of the building to ensure illumination for the
building occupants to the nearest exits in thick smokes or sudden blackout.
Passive system does not require external power or any activation and can be grouped
into three categories according to its purposes:
Passive system slows down fire with fire-resistant walls, floors, doors or spray-on
fireproofing mixture on critical members such as beams and columns. This protects the
building from collapsing due to the weaken building parts in high temperature condition
and provides building occupants with more time to evacuate.
39
3.5.3 Active Fire Protection
3.5.5 Pumps.
40
-Can automatic OFF when the water have reach limit to pump.
-Manual OFF.
41
Figure 2.2: Pressure gauge and pressure switches
Figure 2 is the adjusted pressure field setting of the pressure switch. This triggers the
automatic operation of the pump to supply water for the hose. On the other hand,the
pump will shut OFF when the pressure is higher than the pre-set range.
42
3.5.7 Hose Reel
-Wet riser,dry riser,sprinkler and other fire installation pipes and fittings shall be painted
red.
-All cabinets and areas of recessed in walls for location of fire installations and
extinguishers shall be clearly identified to the satisfaction of the Fire Authority or
otherwise clearly identified.
43
Figure 2.4:Flow for fire alarm system.
The Fire alarm system are alerts the building occupants when there is a fire outbreak so
that immediate safety measure and fire fighting action can be taken. This system can be
operated either automatically through the detectors or manually by breaking the glass of
the break glass unit to activate the fire alarm.
44
Figure 2.6: Manual key switch boxes located outside of TNB switch room and
transformer room.
Individual manual key switch boxes are installed outside of each switch room and
transformer room. This enables quick activation of fire alarm and release of carbon
dioxide gas when the room is on fire by turning the key of the key switch box. Key
switch boxes are used here instead of manual breakglass unit is to prevent anyone to
intentionally activate the carbon dioxide system without emergency as only
permissioned individuals and the Fire Authority have the key.
45
Portable extinguisher shall be provided in accordance with the relevant codes of practice
and shall be sited in prominent positions on exit routes to be visible from all directions
and similar extinguishers in a building shall be of the same method of operation.
46
Figure2.9: Circuit breaker (CB).
Definition
47
Figure 3 : Miniature circuit breaker.
48
Figure 3.1: Moulded case circuit breaker.
49
RCCB/RCD(Residual Current Circuit Breaker).
50
3.8.2 Vacuum CB(Vacuum circuit breaker).
-The fixed and moving contact is enclosed in a permanently sealed vacuum interrupter.
51
-In comparison to various other insulating media used in VCB is a superior dielectric
medium.
3.8.4 Relays.
Definition Relays are switches that open and close circuits electromechanically or
electronically.
52
Have 2 types:-
Electric
loop.
3 phase - 415V
53
Frequency-50Hz
Number of wire Require two wires for Requires four wires for
L(life),N(neutral) to R(red),Y(yellow),B(blue),
completing the circuit. and N(neutral) to
completing the circuit.
54
3.8.7 Problems during industrial training.
-Our panel board for air condition in Hanger have been entered by water because the
water come from the leaking gutter. All the circuit breaker has been moistened with
water, and the short circuit occur in there. Small blast happen when turn on the main
circuit breaker, it happen because water at circuit breaker has make the electric from
any wire to combine together.
55
Figure 4.1:Damaged area in circuit breaker. Figure 4.2:Damaged circuit breaker.
3.8.9 Troubleshooting.
i)Make sure the main electric for the damaged panel board has been turned off at
substation TNB and turned off all circuit breaker in panel board.
ii)Always use the test pen to check the supply at main circuit breaker.
iii)Open the main circuit breaker and elcb circuit breaker and the damaged component.
iv)Use the blow gun air compressor to blow the wet circuit breaker until it dry and blow
component inside panel board until dry.
v)Fix the leaking gutter and install back the circuit breaker to the palace of origin.
56
vii)Turned on the main supply for panel board from substation TNB, turned on all
circuit breaker and test the supply at main circuit breaker.
57
3.9 Telephone plug
Definition
A telephone plug is a type of connector used to connect a telephone set to the telephone
wiring inside a building, establishing a connection to a telephone network. It is inserted
into its counterpart, a telephone jack, commonly affixed to a wall or baseboard.
58
Socket
Figure4.4:Socket
Definition
59
A junction box is a connection point used in supplying telephone service to various
points in a building. Providing an interface between exterior and interior wiring,
junction boxes contain terminals for each of the four colored phone wires and allow for
expansion of a phone system.
Crimping tool
60
Figure4.6:Crimping tool
-It have a two hole (RJ45 & RJ11) to easier for crimp with wire.
Multimeter
-To check the same value voltage at telephone juction box for connect with the correctly
line.
61
3.10 Air compressor
Definition
62
Figure 5: pump flywheel Figure 5.1: air filter
Gauge Tank
63
Figure 5.4: gauge Figur 5.5 : tank
-It has one power stroke for every two -It has one power stroke for each
revolutions of the crankshaft revolution of the crankshaft
64
-Engine design is complicated due to -Engine design is simple due to absence
valve mechanism. of valve mechanism.
-Less mechanical efficiency due to more -More mechanical efficiency due to less
friction on many parts. friction on few parts.
-Air compressor use Four stroke engine application to compress the air and use the AC
motor to move the rotor.
65
3.10.3 Problems during industrial training.
Air compressor in store have been damaged because it run non stop. It cause the
capacitor damage, it run non stop because one of the gasket has loose and the gauge
cant reach the limit to turn off the air compressor.
66
3.10.4 Troubleshooting
Iii)Change the pressure switch with new one and set the pressure limit.
v)Turn on the supply and test the compressor if it can stop at the limit set of the
pressure.
CHAPTER 4
Industrial training is very much essential for Electrical Students. It is also a great
opportunity to acquire practical knowledge. During my training period, in the industry I
acquired lots of experiences in Politeknik Banting Selangor. This will help me to clarify
my theory knowledge. I hope and pray this experience during industrial training will
help me much in my future profession.
During our training period, we had seen the various instruments and apparatus in
the industry. The important thing that instruments usually use for troubleshooting the
electrical problems is test pen and multimeter. Our development and maintenance unit
will analysis the complaint letter and go to the location for maintenance the damage
items.
67
This training have taught me to learn more than 1 basic course other than electrical
course such as mechanical or civil because in real job, we will be instructed by
employer to do work other than our course to look at skills in various jobs. My
supervisor is technician in mechanical engineering but he learn all about electrical and
civil to make sure more understanding when dealing with contractor.
I had been monitored by supervisor for safety in doing many jobs. Safety first
always will be our first rule before doing anything maintenance to make sure the job can
smoothly done. Sometimes the job was difficult to finish it and the technician will make
a report to buy a contractor to solve the problems.
Overall, This development and maintenance unit need more worker to handle the
difficult job for give more efficiency. Need a worker in various field that can help other
worker to know better in troubleshooting and gained more knowledge. This unit need a
lot of budget for maintenance job to give a good condition in surrounding Politeknik
Banting Selangor.
4.2 Reference
Internet
[Online].Available.www.polibanting.edu.my.
[Online].Available.www.switchbuild.co.nz.
68
[Acessed: September 6,2017].
[Online].Available.www.slideshare.net.
[Online].Available.www.airtoolresource.com.
[Acessed:August 18,2017].
Book
U.S.A,Park Publishing,Inc,2005.
69
4.3 Appendix
4.https://en.wikipedia.org/wiki/Distribution_board.
5.https://en.wikipedia.org/wiki/air_compressor.
6.https://en.wikipedia.org/wiki/2_stroke_engine.
7.https://en.wikipedia.org/wiki/4_stroke engine.
8.https://en.wikipedia.org/wiki/circuit_breaker.
9.http://www.engineering.com/AskForum/aft/1012.aspx
10.https://www.edgefx.in/electrical-engineering-substation-components-and-their-worki
ngs/
70