Work Method Statement for 132kV Cable pulling

1) Permit shall be obtained for confined space suitable shoring and shuttering shall be provided for
weak soils.
2) Cable drums shall be there on the excavated area.
3) Suitable safety barriers shall be provided.
4) Walky tallies or suitable communication systems shall be arranged.
5) Cable rollers shall be placed on 10 meter intervals
6) Pulling eye has to be fixed on the cable.
7) Carefull attention have to be made to fix the supports of cable hinges.
8) Winching machine has to set to as per the manufacturers requirement.