ELECTRICAL COMPLETE START-UP

1. 69kV Substation Energization

a. Reference Documents (SLDs, Vendor Prints, Schematic Diagrams etc.)


b. Pre-requisites (List of Equipment pre-com tests/activities that have been completed, etc.)
c. 69kV Energization Detailed Procedure (Includes log sheets for parameters such as voltages,
current, etc.)
d. Precautions during Energization (Includes safety of personnel and equipment, trouble
handling during system abnormalities)

2. Auxiliary Power System Energization


a. Reference Documents (SLDs, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been completed, etc.)
c. 13.8kV Section Energization Procedure (Includes log, check sheets for parameters such as
voltages, current, etc.)
d. 4.16kV Section Energization Procedure (Includes log, check sheets for parameters such as
voltages, current, etc.)
e. 440V Section A & B Energization Procedure (Includes log, check sheets for parameters such
as voltages, current, etc.)
f. Precautions during Energization (Includes safety of personnel and equipment, trouble
handling during system abnormalities)

3. Plant DC System Commissioning


a. Reference Documents (SLDs, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been completed, etc.)
c. DC Distribution Panels Energization Procedure (Includes log, check sheets for parameters
such as voltages, current, etc.)
Test of Un-interrupt capability of DC System
d. Precautions during Energization (Includes safety of personnel and equipment, trouble
handling during system abnormalities)

4. UPS System Commissioning


a. Reference Documents (SLDs, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (includes system upstream source energization, list of Equipment pre-com
tests/activities that have been completed, etc.)
c. UPS Distribution Cabinet Energization Procedure (Includes log, check sheets for parameters
such as voltages, current, etc.)
Test of Un-interrupt Capability of UPS System
d. Precautions during Energization (Includes safety of personnel and equipment, trouble
handling during system abnormalities)
5. Commissioning of Diesel Generator and Emergency Supply System
a. Reference Documents (SLDs, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (includes system upstream source energization, list of Equipment pre-com
tests/activities that have been completed, etc.)
c. EDG Energization Procedure (Includes log, check sheets for parameters such as voltages,
current, etc.)
EDG start/stop at Local
EDG start/stop by DCS
EDG Synchronize Loading
Emergency Power Supply Switchover
d. Precautions during Energization (Includes safety of personnel and equipment, trouble
handling during system abnormalities)
CONTROL and INSTRUMENTATION COMPLETE START-UP

DCS

1. Furnace Purging
a. Reference Documents (P&IDs, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been completed, etc.)
c. Furnace Purging Procedure (Includes log sheets for parameters such as Air flow, furnace
pressure, sequence control etc.)
d. Precautions during Furnace Purging (Includes safety of personnel and equipment, trouble
handling during system abnormalities)
2. Oil Leak Test
a. Reference Documents (P&IDs, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been completed, etc.)
c. Oil Leak Test Procedure (Includes log sheets for parameters such as oil flow, oil pressure,
sequence control etc.)
d. Precautions during Oil Leak Test (Includes safety of personnel and equipment, trouble
handling during system abnormalities)
3. Oil Ignition Sequence Control
a. Reference Documents (P&IDs, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been completed, etc.)
c. Oil Ignition Sequence Procedure (Includes log sheets for parameters such as air flow, oil, air
pressure, sequence control etc.)
d. Precautions during Oil Ignition Sequence Control Test (Includes safety of personnel and
equipment, trouble handling during system abnormalities)
4. Soot Blowing Sequence Control
a. Reference Documents (P&IDs, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been completed, etc.)
c. Soot Blowing Sequence Control Procedure (Includes log sheets for parameters such as air
flow, temperature, damper position, oil, air pressure, sequence control etc.)
d. Precautions during Oil Ignition Sequence Control Test (Includes safety of personnel and
equipment, trouble handling during system abnormalities)
5. Primary Air Fan, Induced Draft Fan, Secondary Air Fan Sequence Control
a. Reference Documents (P&IDs, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been completed, etc.)
c. Air Fans Sequence Control Procedure (Includes log sheets for parameters such as air flow,
temperature, damper position, oil, air pressure, sequence control etc.)
d. Precautions during Oil Ignition Sequence Control Test (Includes safety of personnel and
equipment, trouble handling during system abnormalities)
DAS Routine Operation

1. Charts and Printing


a. Reference Documents (P&IDs, I/O Lists, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been
completed, etc.)
c. Report Sheet Forms Test
d. Printing Capability Test

2. Sequence of Event
a. Reference Documents (P&IDs, I/O Lists, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been
completed, etc.)
c. Sequence of Event Operation Test Procedure
3. Alarms Operation
a. Reference Documents (P&IDs, I/O Lists, Vendor Prints, Schematic Diagrams etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been
completed, etc.)
c. Alarms Operation Test Procedure
4. Trending Operation
a. Reference Documents (P&IDs, I/O Lists, Vendor Prints, Schematic Diagrams
etc.)
b. Pre-requisites (List of Equipment pre-com tests/activities that have been
completed, etc.)
c. Trending Operation Test Procedure

Turbine ESD

1. Unit Vibration Monitoring (TSI)


2. DEH Operation
3. Thermal Expansion Instrumentation
4. Governor Control Modes

PLC Control System Commissioning

1. DM Water Treatment Control System


2. Fuel Handling Control System
3. Ash Handling Control System