Documente Academic
Documente Profesional
Documente Cultură
JACEK M. CZAPLICKI*
Introduction
The purpose of this paper is to present the procedure of analysis and calculation of the S-T-C-C
system in the light of the new method described comprehensively in the 2008 monograph.
Let us presume that there is an open pit mine in which a machinery system of the
shovel-truck type is in operation. Therefore we know the number of working machines and
their main operation/exploitation parameters. The mine has decided to change the system of
ore hauling, applying an in-pit crusher and a system of belt conveyors to deliver crushed rock
to a peripheral dressing plant unit. The problem is how to design this new component of the
machinery system and to indicate what kind of changes should be made in the old system.
We can describe this problem in mathematical form.
We have the system:
in turn, is divided into two subsystems but in a stochastic way. It is not strictly ascribed that
a given truck is only connected with haulage of a given type of material. Sometimes the truck
will transport waste, and sometime ore. Nevertheless, we presume that the system of haulers
is divided into two subsystems numerically a certain number of trucks will on average serve
the ore loading machines and a certain number on average will serve machines loading the
waste. Because the whole truck system was designed for longer distances and has m units,
we in fact have to recalculate this system from the beginning. It will be mw trucks hauling
the waste and mo units hauling the ore to the crusher. We obviously expect that mw + mo < m.
A new size of the reserve of the power rn = rw + ro, will be forecast: rn < r. Therefore the
repair shop should not be heavily loaded as before.
To design, analyse and calculate the new system we need information on the following six
parameters: < Ttc, y, Acr, Bcr, Ac, u > where: Ttc is the mean time of truck travel serving the
crusher, y is the number of trucks that can be unloaded simultaneously to the crusher, Acr is
the steady-state availability of the crusher, Bcr is the accessibility coefficient, Ac is the
steady-state availability of the conveyor and u is the number of conveyors required to connect
the outlet crusher with the peripheral dressing plant unit. Notice that the information on the
value of y means that y truck payloads can be given in time Td to the crusher without any
choke. Thus, the relationship between the truck payload, dump time and crusher capacity
should be rationally matched.
The procedure of analysis and calculation of the system can be made according to the
following scheme:
1. Recalculation of the whole system S-T-C-C considering the trucks.
Further part of considerations concerns the ore system alone.
2. Construction of the probability distribution of the number of loading machines able to
load with information as to how many power shovels are up.
3. Construction of the probability distribution of the number of trucks in work state for all
power shovels up.
4. Construction of the probability distribution of the number of trucks at shovels
assumption: no queue at the crusher.
5. Calculation of conditional system parameters.
6. Calculation of unconditional system parameters.
7. Evaluation of system productivities.
Points 1 7 can be calculated using the procedure presented in the 2008 monograph.
8. Calculation of the potential stream of ore that can be delivered to the crusher:
Spcr = 60yQ/Td
This output could be obtained if there will always be trucks to dump and the whole
continuous subsystem is totally reliable.
9. The steady-state availability Acon calculation of the continuous subsystem: crusher and
conveyors.
120
10. Calculation of the stream of ore that can be delivered to the crusher taking into account
the accessibility of the crusher Bcr (maintenance required)
11. Construction of the probability distribution of the number of trucks at the crusher.
12. Calculation of the whole system parameters.
13. Conclusions, recommendations and remarks.
2. Case of study
for which
P(S,D) : < Bk = 0.830, Z = 1.7 min, Tt = 26.0 min, Td = 0.9 min; t = 2.9; Bw = 0.880 >
< Ttc = 9.0 min, y = 2, Acr = 0.820, Bcr = 0.900, Ac = 0.998, u = 3 >
Pk((zd )
d = 0. 3 )
= 0.023 Pk((zd )
d =1. 2 )
= 0.172 Pk((zd )
d = 2.1)
= 0.436 Pk((zd )
d = 3. 0 )
= 0.369
where Pk((zd )
d = i ,n - i )
is the probability that i power shovels are able to load and ni spare
loaders, i = 0, 1, , n.
( p)
3. The probability distribution of the number of trucks in work state Pwj for the ore
system obtained from the Maryanovitch model is given in Table 1.
TABLE 1
The probability distribution of the number of trucks in work state for <18, 2>
TABELA 1
Rozkad prawdopodobiestwa liczby ciarwek w stanie gotowoci do pracy dla <18, 2>
j 9 10 11 12 13 14 15 16 17 18
( p)
Pwj 0.002 0.007 0.022 0.051 0.100 0.159 0.201 0.199 0.148 0.111
47. Employing the Sivazlian and Wang model with two randomisations (the number of
trucks in work state and the number of power shovels able to load) the probability
distribution of the number of haulers at loading machines can be obtained. Based on this
characteristic, further interesting probability measures can be determined. The outcomes of
these calculations are given in Table 2 with a list of keynotes.
8. The potential stream of ore that can be delivered to the crusher Spcr = 28533 t/h.
9. The steady-state availability calculation of the continuous subsystem. Knowing the
relationship between the steady-state availability and the failure rate k that is k = (1 A)/A we
can calculate the steady-state availability Acon of the continuous subsystem according to the
second principle of reduction of series systems of Markov type systems:
122
10. The stream of ore that can be delivered to the crusher is:
TABLE 2
Parameters of the ore system S
TABELA 2
Parametry systemu rud S
shovels trucks/lo
able to min trucks ading min
load machine
3 0.369 1.70 2.6 0.9 0.002 0.098 0.411 0.325 0.164 0.1
truck
loaded
min trucks trucks trucks work
trucks/h
cycles/h
13.41 2.85 15.2 1.7 65.5 68.0 0.000 0.038 0.174 0.174 0.614
11. Construction of the probability distribution of the number of trucks at the crusher can
be made by applying the Sivazlian and Wang model. Compared to the previous case of
application of this model it is significantly simplified, giving following results:
The subscript indicates how many trucks are at the crusher, whereas subscript p
means >2.
The average number of trucks at the crusher X = 1.04 and the time lost in the truck work
cycle due to standing in a queue for loading D = 0.0 min.
12. Let us now calculate the basic measures of system efficiency. We have three
subsystems and we are able to evaluate their productivity.
The shovel productivity is estimated at:
Obviously, we intuitively expect that all figures will be approximately the same, taking
only into account differences in numbers due to inevitable rounding up during calculations.
This is not right, however. In Sivazlian and Wangs original paper it is clearly stated that the
method of calculation presented only gives approximate solutions. It is also necessary to take
into consideration the fact that the heavy traffic condition must be fulfilled (see for instance
Czaplicki 2008a). Following short simple calculations it is easy to perceive that in all cases
this condition is fulfilled, but with different power. It generates varying accuracy in the
outcomes obtained. We may circumspectly assume that the ore system productivity will be
approximately 14000 t/h.
13. This productivity result must be compared with the ore productivity of the old
system. It is also important to evaluate the size of savings due to the fact that instead of 97
trucks that should fulfil the hauling task and 20 trucks in the reserve we now have 24 trucks
less that will be directed to the pit and 6 units less in the reserve. This is quite a high number.
However, the operation costs of the continuous subsystem must be estimated and taken into
account in the general economic considerations.
124
REFERENCES
Sowa kluczowe
Streszczenie
Niedawno opracowano metod analizy i obliczania systemw koparek czerpakowych, pozwalajc na wszech-
stronne uwzgldnienie prawie wszystkich gwnych problemw zwizanych z tego rodzaju systemami maszyn.
Moliw modyfikacj systemu jest zastosowanie mobilnej lub ruchomej kruszarki i przenonikw, ktra zapewni
dalszy przepyw pokruszonej rudy. Taki system jest poczeniem systemu cyklicznego i cigego. Opracowanie
przedstawia procedur modelowania, analizy i obliczania tego rodzaju systemw, wraz z rozleg orientacj
problemw stochastycznych zwizanych z procesem eksploatacji systemu. Biorc to pod uwag, wycignito
pewne wnioski i poczyniono uwagi o decydujcym znaczeniu.
THE ANALYSIS AND CALCULATION PROCEDURE FOR SHOVEL-TRUCK SYSTEMS WITH A CRUSHER AND CONVEYORS
Key words
Abstract
The method of analysis and calculation of shovel-truck systems was recently developed, allowing for
comprehensive considerations of almost all major problems connected with this type of machinery system.
One possible modification to the system is the application of an in-pit mobile or movable crusher and conveyors
ensuring further broken ore flow. Such a system is a combined cyclic and continuous one. In this paper the
procedure of modelling, analysis and calculation of this type of system is presented together with the vast
orientation of stochastic problems associated with the system exploitation process. Following the considerations,
some conclusions are drawn and some vital remarks made.