In Assignment 2, the advance work and completion works are to be undertaken during a normal 38 hours a
week. Therefore a standard MS project calendar for these tasks can be used.
However, for weekend occupation and major shutdown tasks a customized calendar should be created in MS
Project. The following example shows how to create a new calendar in MS Project and assign it to a task.
Open MS Project. On the project tab, click on Change working time. Then click on Create a new
calendar:
Here we instruct you how to create an exception for Saturday and nonworking days (Tue, Wed,
Thurs, Fri). You can create exception for Sunday and Monday similarly.
In the Gantt chart/Task name, type Weekend occupations and set the total duration of weekend
occupation task in hours.
Double click on the Weekend occupation task and select Advance tab. Select the Weekend
occupation calendar as shown below:
Now your start and finish time for the Weekend occupations is calculated based on the new
calendar.