Sunteți pe pagina 1din 28

Republic of the Philippines defendant alleged that he suffered damages in the sum of P1,000 on account of the

SUPREME COURT filing of this action against him by the plaintiff with full knowledge that the said
Manila defendant had nothing to do whatever with any and all of the transactions mentioned
in the complaint in his own individual and personal capacity.
EN BANC
The trial court rendered judgment ordering the defendant Antonio Vazquez to pay to
G.R. No. L-48930 February 23, 1944 the plaintiff the sum of P3,175.20 plus the sum of P377.50, with legal interest on both
sums, and absolving the defendant Fernando Busuego (treasurer of the corporation)
from the complaint and the plaintiff from the defendant Antonio Vazquez'
ANTONIO VAZQUEZ, petitioner, counterclaim. Upon appeal to the Court of Appeals, the latter modified that judgment
vs. by reducing it to the total sum of P3,314.78, with legal interest thereon and the costs.
FRANCISCO DE BORJA, respondent. But by a subsequent resolution upon the defendant's motion for reconsideration, the
Court of Appeals set aside its judgment and ordered that the case be remanded to the
x---------------------------------------------------------x court of origin for further proceedings. The defendant Vazquez, not being agreeable
to that result, filed the present petition for certiorari (G.R. No. 48930) to review and
G.R. No. L-48931 February 23, 1944 reverse the judgment of the Court of Appeals; and the plaintiff Francisco de Borja,
excepting to the resolution of the Court of Appeals whereby its original judgment was
set aside and the case was ordered remanded to the court of origin for further
FRANCISCO DE BORJA, petitioner, proceedings, filed a cross-petition for certiorari (G.R. No. 48931) to maintain the
vs. original judgment of the Court of Appeals.
ANTONIO VAZQUEZ, respondent.
The original decision of the Court of Appeals and its subsequent resolutions on
OZAETA, J.: reconsideration read as follows:

This action was commenced in the Court of First Instance of Manila by Francisco de Es hecho no controvertido que el 25 de Febrero de 1932, el demandado-
Borja against Antonio Vazquez and Fernando Busuego to recover from them jointly apelante vendio al demandante 4,000 cavanes de palay al precio de P2.10
and severally the total sum of P4,702.70 upon three alleged causes of action, to wit: el cavan, de los cuales, dicho demandante solamente recibio 2,583
First, that in or about the month of January, 1932, the defendants jointly and severally cavanes; y que asimismo recibio para su envase 4,000 sacos vacios. Esta
obligated themselves to sell to the plaintiff 4,000 cavans of palay at P2.10 per cavan, provbado que de dichos 4,000 sacos vacios solamente se entregaron, 2,583
to be delivered during the month of February, 1932, the said defendants having quedando en poder del demandado el resto, y cuyo valor es el de P0.24
subsequently received from the plaintiff in virtue of said agreement the sum of cada uno. Presentada la demanda contra los demandados Antonio Vazquez
P8,400; that the defendants delivered to the plaintiff during the months of February, y Fernando Busuego para el pago de la cantidad de P4,702.70, con sus
March, and April, 1932, only 2,488 cavans of palay of the value of P5,224.80 and intereses legales desde el 1.o de marzo de 1932 hasta su completo pago y
refused to deliver the balance of 1,512 cavans of the value of P3,175.20 las costas, el Juzgado de Primera Instancia de Manila el asunto condenando
notwithstanding repeated demands. Second, that because of defendants' refusal to a Antonio Vazquez a pagar al demandante la cantidad de P3,175.20, mas la
deliver to the plaintiff the said 1,512 cavans of palay within the period above cantidad de P377.50, con sus intereses legales, absolviendo al demandado
mentioned, the plaintiff suffered damages in the sum of P1,000. And, third, that on Fernando Busuego de la demanda y al demandante de la reconvencion de
account of the agreement above mentioned the plaintiff delivered to the defendants los demandados, sin especial pronunciamiento en cuanto a las costas. De
4,000 empty sacks, of which they returned to the plaintiff only 2,490 and refused to dicha decision apelo el demandado Antonio Vazquez, apuntado como
deliver to the plaintiff the balance of 1,510 sacks or to pay their value amounting to principal error el de que el habia sido condenado personalmente, y no la
P377.50; and that on account of such refusal the plaintiff suffered damages in the corporacion por el representada.
sum of P150.
Segun la preponderancia de las pruebas, la venta hecha por Antonio
The defendant Antonio Vazquez answered the complaint, denying having entered into Vazquez a favor de Francisco de Borja de los 4,000 cavanes de palay fue
the contract mentioned in the first cause of action in his own individual and personal en su capacidad de Presidente interino y Manager de la corporacion
capacity, either solely or together with his codefendant Fernando Busuego, and Natividad-Vazquez Sabani Development Co., Inc. Asi resulta del Exh. 1, que
alleging that the agreement for the purchase of 4,000 cavans of palay and the es la copia al carbon del recibo otorgado por el demandado Vazquez, y cuyo
payment of the price of P8,400 were made by the plaintiff with and to the Natividad- original lo habia perdido el demandante, segun el. Asi tambien consta en los
Vasquez Sabani Development Co., Inc., a corporation organized and existing under libros de la corporacion arriba mencionada, puesto que en los mismos se ha
the laws of the Philippines, of which the defendant Antonio Vazquez was the acting asentado tanto la entrada de los P8,400, precio del palay, como su envio al
manager at the time the transaction took place. By way of counterclaim, the said
gobierno en pago de los alquileres de la Hacienda Sabani. Asi mismo lo The action is on a contract, and the only issue pleaded and tried is whether the
admitio Francisco de Borja al abogado Sr. Jacinto Tomacruz, posterior plaintiff entered into the contract with the defendant Antonio Vazquez in his personal
presidente de la corporacion sucesora en el arrendamiento de la Sabani capacity or as manager of the Natividad-Vazquez Sabani Development Co., Inc. The
Estate, cuando el solicito sus buenos oficios para el cobro del precio del Court of Appeals found that according to the preponderance of the evidence "the sale
palay no entregado. Asi igualmente lo declaro el que hizo entrega de parte made by Antonio Vazquez in favor of Francisco de Borja of 4,000 cavans of palay
del palay a Borja, Felipe Veneracion, cuyo testimonio no ha sido refutado. Y was in his capacity as acting president and manager of the corporation Natividad-
asi se deduce de la misma demanda, cuando se incluyo en ella a Fernando Vazquez Sabani Development Co., Inc." That finding of fact is final and, it resolving
Busuego, tesorero de la Natividad-Vazquez Sabani Development Co., Inc. the only issue involved, should be determinative of the result.

Siendo esto asi, la principal responsable debe ser la Natividad-Vazquez The Court of Appeals doubly erred in ordering that the cause be remanded to the
Sabani Development Co., Inc., que quedo insolvente y dejo de existir. El court of origin for further trial to determine whether the corporation had sufficient stock
Juez sentenciador declaro, sin embargo, al demandado Vazquez of palay at the time appellant sold, 1500 cavans of palay to Kwong Ah Phoy. First, if
responsable del pago de la cantidad reclamada por su negligencia al vender that point was material to the issue, it should have been proven during the trial; and
los referidos 4,000 cavanes de palay sin averiguar antes si o no dicha the statement of the court that it had not been sufficiently discussed and proven was
cantidad existia en las bodegas de la corporacion. no justification for ordering a new trial, which, by the way, neither party had solicited
but against which, on the contrary, both parties now vehemently protest. Second, the
Resulta del Exh. 8 que despues de la venta de los 4,000 cavanes de palay a point is, in any event, beside the issue, and this we shall now discuss in connection
Francisco de Borja, el mismo demandado vendio a Kwong Ah Phoy 1,500 with the original judgment of the Court of Appeals which the plaintiff cross-petitioner
cavanes al precio de P2.00 el cavan, y decimos 'despues' porque esta seeks to maintain.
ultima venta aparece asentada despues de la primera. Segun esto, el
apelante no solamente obro con negligencia, sino interviniendo culpa de su The action being on a contract, and it appearing from the preponderance of the
parte, por lo que de acuerdo con los arts. 1102, 1103 y 1902 del Codigo evidence that the party liable on the contract is the Natividad-Vazquez Sabani
Civil, el debe ser responsable subsidiariamente del pago de la cantidad Development Co., Inc. which is not a party herein, the complaint should have been
objecto de la demanda. dismissed. Counsel for the plaintiff, in his brief as respondent, argues that altho by the
preponderance of the evidence the trial court and the Court of Appeals found that
En meritos de todo lo expuesto, se confirma la decision apelada con la Vazquez celebrated the contract in his capacity as acting president of the corporation
modificacion de que el apelante debe pagar al apelado la suma de and altho it was the latter, thru Vazquez, with which the plaintiff had contracted and
P2,295.70 como valor de los 1,417 cavanes de palay que dejo de entregar which, thru Vazquez, had received the sum of P8,400 from Borja, and altho that was
al demandante, mas la suma de P339.08 como importe de los 1,417 sacos true from the point of view of a legal fiction, "ello no impede que tambien sea verdad
vacios, que dejo de devolver, a razon de P0.24 el saco, total P3,314.78, con lo alegado en la demanda de que la misma persona de Vasquez fue la que contrato
sus intereses legales desde la interposicion de la demanda y las costas de con Borja y que la misma persona de Vasquez fue quien recibio la suma de P8,400."
ambas instancias. But such argument is invalid and insufficient to show that the president of the
corporation is personally liable on the contract duly and lawfully entered into by him in
its behalf.
Vista la mocion de reconsideracion de nuestra decision de fecha 13 de
Octubre de 1942, y alegandose en la misma que cuando el apelante vendio
los 1,500 cavanes de palay a Ah Phoy, la corporacion todavia tenia bastante It is well known that a corporation is an artificial being invested by law with a
existencia de dicho grano, y no estando dicho extremo suficientemente personality of its own, separate and distinct from that of its stockholders and from that
discutido y probado, y pudiendo variar el resultado del asunto, dejamos sin of its officers who manage and run its affairs. The mere fact that its personality is
efecto nuestra citada decision, y ordenamos la devolucion de la causa al owing to a legal fiction and that it necessarily has to act thru its agents, does not
Juzgado de origen para que reciba pruebas al efecto y dicte despues la make the latter personally liable on a contract duly entered into, or for an act lawfully
decision correspondiente. performed, by them for an in its behalf. The legal fiction by which the personality of a
corporation is created is a practical reality and necessity. Without it no corporate
entities may exists and no corporate business may be transacted. Such legal fiction
Upon consideration of the motion of the attorney for the plaintiff-appellee in may be disregarded only when an attempt is made to use it as a cloak to hide an
case CA-G.R. No. 8676, Francisco de Borja vs. Antonio Vasquez et al., unlawful or fraudulent purpose. No such thing has been alleged or proven in this
praying, for the reasons therein given, that the resolution of December 22, case. It has not been alleged nor even intimated that Vazquez personally benefited by
1942, be reconsidered: Considering that said resolution remanding the case the contract of sale in question and that he is merely invoking the legal fiction to avoid
to the lower court is for the benefit of the plaintiff-appellee to afford him personal liability. Neither is it contended that he entered into said contract for the
opportunity to refute the contention of the defendant-appellant Antonio corporation in bad faith and with intent to defraud the plaintiff. We find no legal and
Vazquez, motion denied. factual basis upon which to hold him liable on the contract either principally or
subsidiarily.
The trial court found him guilty of negligence in the performance of the contract and The judgment of the Court of Appeals is reversed, and the complaint is hereby
held him personally liable on that account. On the other hand, the Court of Appeals dismissed, without any finding as to costs.
found that he "no solamente obro con negligencia, sino interveniendo culpa de su
parte, por lo que de acuerdo con los arts. 1102, 1103 y 1902 del Codigo Civil, el debe Yulo, C.J., Moran, Horrilleno and Bocobo, JJ., concur.
ser responsable subsidiariamente del pago de la cantidad objeto de la demanda." We
think both the trial court and the Court of Appeals erred in law in so holding. They
have manifestly failed to distinguish a contractual from an extracontractual obligation,
or an obligation arising from contract from an obligation arising from culpa aquiliana.
The fault and negligence referred to in articles 1101-1104 of the Civil Code are those
incidental to the fulfillment or nonfullfillment of a contractual obligation; while the fault Separate Opinions
or negligence referred to in article 1902 is the culpa aquiliana of the civil law,
homologous but not identical to tort of the common law, which gives rise to an PARAS, J., dissenting:
obligation independently of any contract. (Cf. Manila R.R. Co. vs. Cia. Trasatlantica,
38 Phil., 875, 887-890; Cangco vs. Manila R.R. Co., 38 Phil. 768.) The fact that the
corporation, acting thru Vazquez as its manager, was guilty of negligence in the Upon the facts of this case as expressly or impliedly admitted in the majority opinion,
fulfillment of the contract, did not make Vazquez principally or even subsidiarily liable the plaintiff is entitled to a judgment against the defendant. The latter, as acting
for such negligence. Since it was the corporation's contract, its nonfulfillment, whether president and manager of Natividad-Vazquez Sabani Development Co., Inc., and with
due to negligence or fault or to any other cause, made the corporation and not its full knowledge of the then insolvent status of his company, agreed to sell to the
agent liable. plaintiff 4,000 cavans of palay. Notwithstanding the receipt from the plaintiff of the full
purchase price, the defendant delivered only 2,488 cavans and failed and refused to
deliver the remaining 1,512 cavans and failed and refused to deliver the remaining
On the other hand if independently of the contract Vazquez by his fault or negligence 1,512 cavans and a quantity of empty sacks, or their value. Such failure resulted,
cause damaged to the plaintiff, he would be liable to the latter under article 1902 of according to the Court of First Instance of Manila and the Court of Appeals, from his
the Civil Code. But then the plaintiff's cause of action should be based on culpa fault or negligence.
aquiliana and not on the contract alleged in his complaint herein; and Vazquez'
liability would be principal and not merely subsidiary, as the Court of Appeals has
erroneously held. No such cause of action was alleged in the complaint or tried by It is true that the cause of action made out by the complaint is technically based on a
express or implied consent of the parties by virtue of section 4 of Rule 17. Hence the contract between the plaintiff and Natividad-Vazquez Sabani Development Co., Inc.
trial court had no jurisdiction over the issue and could not adjudicate upon it which is not a party to this case. Nevertheless, inasmuch as it was proven at the trial
(Reyes vs. Diaz, G.R. No. 48754.) Consequently it was error for the Court of Appeals that the defendant was guilty of fault in that he prevented the performance of the
to remand the case to the trial court to try and decide such issue. plaintiff's contract and also of negligence bordering on fraud which cause damage to
the plaintiff, the error of procedure should not be a hindrance to the rendition of a
decision in accordance with the evidence actually introduced by the parties, especially
It only remains for us to consider petitioner's second assignment of error referring to when in such a situation we may order the necessary amendment of the pleadings, or
the lower courts' refusal to entertain his counterclaim for damages against the even consider them correspondingly amended.
respondent Borja arising from the bringing of this action. The lower courts having
sustained plaintiff's action. The finding of the Court of Appeals that according to the
preponderance of the evidence the defendant Vazquez celebrated the contract not in As already stated, the corporation of which the defendant was acting president and
his personal capacity but as acting president and manager of the corporation, does manager was, at the time he made the sale of the plaintiff, known to him to be
not warrant his contention that the suit against him is malicious and tortious; and insolvent. As a matter of fact, said corporation was soon thereafter dissolved. There is
since we have to decide defendant's counterclaim upon the facts found by the Court admitted damage on the part of the plaintiff, proven to have been inflicted by reason
of Appeals, we find no sufficient basis upon which to sustain said counterclaim. of the fault or negligence of the defendant. In the interest of simple justice and to
Indeed, we feel that a a matter of moral justice we ought to state here that the avoid multiplicity of suits I am therefore impelled to consider the present action as one
indignant attitude adopted by the defendant towards the plaintiff for having brought based on fault or negligence and to sentence the defendant accordingly. Otherwise,
this action against him is in our estimation not wholly right. Altho from the legal point he would be allowed to profit by his own wrong under the protective cover of the
of view he was not personally liable for the fulfillment of the contract entered into by corporate existence of the company he represented. It cannot be pretended that any
him on behalf of the corporation of which he was the acting president and manager, advantage under the sale inured to the benefit of Natividad-Vazquez Sabani
we think it was his moral duty towards the party with whom he contracted in said Development Co., Inc. and not of the defendant personally, since the latter
capacity to see to it that the corporation represented by him fulfilled the contract by undoubtedly owned a considerable part of its capital.
delivering the palay it had sold, the price of which it had already received. Recreant to
such duty as a moral person, he has no legitimate cause for indignation. We feel that
under the circumstances he not only has no cause of action against the plaintiff for
damages but is not even entitled to costs.
On January 9, 1992, FSI filed a complaint for Sum of Money against FBI before the
Republic of the Philippines RTC of Makati City seeking to collect the amount of One Million Six Hundred Thirty-
SUPREME COURT Five Thousand Two Hundred Seventy-Eight Pesos and Ninety-One Centavos
Manila (1,635,278.91), representing Billings No. 3 and 4, with accrued interest from August
1, 1991 plus moral and exemplary damages with attorneys fees. 9 In its complaint,FSI
alleged that FBI refused to pay said amount despite demand and itscompletion of
THIRD DIVISION ninety-seven percent (97%) of the contracted works.

G.R. No. 194507 September 8, 2014 In its Answer with Counterclaim, FBI claimed that FSI completed only eighty-five
percent (85%) of the contracted works, failing to finish the diaphragm wall and
FEDERAL BUILDERS, INC., Petitioner, component works in accordance with the plans and specifications and abandoning
vs. the jobsite. FBI maintains that because of FSIs inadequacy, its schedule in finishing
FOUNDATION SPECIALISTS, INC., Respondent, the Project has been delayed resulting in the Project owners deferment of its own
progress billings.10 It further interposed counterclaims for amounts it spent for the
x-----------------------x remedial works on the alleged defects in FSIs work.

G.R. No. 194621 On May 3, 2001, after evaluating the evidence of both parties, the RTC ruled in favor
of FSI, the dispositive portion of its Decision reads:

FOUNDATION SPECIALISTS, INC., Petitioner,


vs. WHEREFORE, on the basis of the foregoing, judgment is rendered ordering
FEDERAL BUILDERS, INC., Respondent. defendant to pay plaintiff the following:

DECISION 1. The sum of 1,024,600.00 representing billings 3 and 4, less the amount
of 33,354.40 plus 12% legal interest from August 30, 1991;

PERALTA, J.:
2. The sum of 279,585.00 representing the cost of undelivered cement;

Before the Court are two consolidated cases, namely: (1) Petition for review on
certiorari under Rule 45 of the Rules of Court, docketed as G.R. No. 194507, filed by 3. The sum of 200,000.00 as attorneys fees; and
Federal Builders, Inc., assailing the Decision1 and Resolution,2dated July 15, 2010
and November 23, 2010, respectively, of the Court of Appeals (CA) in CA-G.R. CV 4. The cost of suit.
No. 70849, which affirmed with modification the Decision 3 dated May 3, 2001 of the
Regional Trial Court (RTC) in Civil Case No. 92-075; and (2) Petition for review on Defendants counterclaim is deniedfor lack of factual and legal basis.
certiorari under Rule 45 of the Rules of Court,docketed as G.R. No. 194621, filed by
Foundation Specialists, Inc., assailing the same Decision 4 and Resolution,5 dated July
15, 2010 and November 23, 2010,respectively, of the CA in CA- G.R. CV No. 70849, SO ORDERED.11
which affirmed with modification the Decision6 dated May 3, 2001 of the RTC in Civil
Case No. 92-075. On appeal, the CA affirmed the Decision of the lower court, but deleted the sum of
279,585.00 representing the cost of undelivered cement and reduced the award of
The antecedent facts are as follows: attorneys fees to 50,000.00. In its Decision12 dated July 15, 2010, the CA explained
that FSI failed to substantiate how and in what manner it incurred the cost of cement
by stressing that its claim was not supported by actual receipts. Also, it found that
On August 20, 1990, Federal Builders, Inc. (FBI) entered into an agreement with while the trial court did not err in awarding attorneys fees, the same should be
Foundation Specialists, Inc. (FSI) whereby the latter, as subcontractor, undertook the reduced for being unconscionable and excessive. On FBIs rejection of the 12%
construction of the diaphragm wall, capping beam, and guide walls of the Trafalgar annual interest rate on the amount of Billings 3 and 4, the CA ruled that the lower
Plaza located at Salcedo Village, Makati City (the Project), for a total contract price of court did not err in imposing the same in the following wise:
Seven Million Four Hundred Thousand Pesos (7,400,000.00). 7 Under the
agreement,8 FBI was to pay a downpayment equivalent to twenty percent (20%) of
the contract price and the balance, through a progress billing every fifteen (15) days, x x x The rule is well-settled that when an obligation is breached, and it consists in the
payable not later than one (1) week from presentation of the billing. payment of a sum of money, the interest due shall itself earn legal interest from the
time it is judicially demanded (BPI Family Savings Bank, Inc. vs. First Metro
Investment Corporation, 429 SCRA 30). When there is no rate of interest stipulated, The petition is partly meritorious.
such as in the present case, the legal rate of interest shall be imposed, pursuant to
Article 2209 of the New Civil Code. In the absence of a stipulated interest rate on a We agree with the courts below and reject FBIs first and third arguments. Well-
loan due, the legal rate of interest shall be 12% per annum.13 entrenched in jurisprudence is the rule that factual findings of the trial court, especially
when affirmed by the appellate court, are accorded the highest degree of respectand
Both parties filed separate Motions for Reconsideration assailing different portions of considered conclusive between the parties, save for the following exceptional and
the CADecision, but to no avail.14 Undaunted, they subsequently elevated their claims meritorious circumstances: (1) when the factual findings of the appellate court and the
withthis Court via petitions for review on certiorari. trial court are contradictory; (2) whenthe findings of the trial court are grounded
entirely on speculation, surmises or conjectures; (3) when the lower courts inference
On the one hand, FSI asserted that the CA should not have deleted the sum of from its factual findings is manifestly mistaken, absurd or impossible; (4) when there
279,585.00 representing the cost of undelivered cement and reduced the award of is grave abuse of discretion in the appreciation of facts; (5) when the findings of the
attorneys fees to 50,000.00, since it was an undisputed fact that FBI failed to deliver appellate court go beyond the issues of the case, or fail to notice certain relevant facts
the agreed quantity of cement. On the other hand, FBI faulted the CA for affirming the which, if properly considered, will justify a different conclusion; (6) when there is a
decision of the lower court insofar as the award of the sum representing Billings 3 and misappreciation of facts; (7) when the findings of fact are themselves conflicting; and
4, the interest imposed thereon, and the rejection of his counterclaim were concerned. (8) when the findings of fact are conclusions without mention of the specific evidence
In a Resolution15 dated February 21, 2011, however, this Court denied, with finality, on which they are based, are premised on the absence of evidence, or are
the petition filed by FSI in G.R. No. 194621 for having been filed late. contradicted by evidence on record.16

Hence, the present petition filed byFBI in G.R. No. 194507 invoking the following None of the aforementioned exceptions are present herein. In the assailed Decision,
arguments: the RTC meticulouslydiscussed the obligations of each party, the degree of their
compliance therewith, as well as their respective shortcomings, all of which were
properly substantiated with the corresponding documentary and testimonial evidence.
I.
Under the construction agreement, FSIs scope of workconsisted in (1) the
THE COURT OF APPEALS COMMITTED A CLEAR, REVERSABLE construction of the guide walls, diaphragm walls, and capping beam; and (2) the
ERROR WHEN IT AFFIRMED THE TRIAL COURTS JUDGMENT THAT installation of steel props.17 As the lower courts aptly observed from the records at
FEDERAL BUILDERS, INC. WAS LIABLE TO PAY THE BALANCE OF hand, FSI had, indeed, completed ninety-seven percent (97%) of its contracted works
1,024,600.00 LESS THE AMOUNT OF 33,354.40 NOTWITHSTANDING and the non-completion of the remaining three percent (3%), as well as the alleged
THAT THE DIAPHRAGM WALL CONSTRUCTED BY FOUNDATION defects in the said works, are actually attributable to FBIs own fault such as, but not
SPECIALIST, INC. WAS CONCEDEDLY DEFECTIVE AND OUT-OF- limited to, the failure to deliver the needed cement as agreed upon in the contract, to
SPECIFICATIONS AND THAT PETITIONER HAD TO REDO IT AT ITS wit:
OWN EXPENSE.
On March 8, 1991, plaintiff had finished the construction of the guide wall and
II. diaphragm wall (Exh. "R") but had not yet constructed the capping beam as of April
22, 1991 for defendants failure to deliver the needed cement in accordance with their
THE COURT OF APPEALS COMMITTED SERIOUS, REVERSABLE agreement(Exhibit "I"). The diaphragm wall had likewise been concrete tested and
ERROR WHEN IT IMPOSED THE 12% LEGAL INTEREST FROM AUGUST was found to have conformed with the required design strength (Exh. "R").
30, 1991 ON THE DISPUTED CLAIM OF 1,024,600.00 LESS THE
AMOUNT OF 33,354.40 DESPITE THE FACT THAT THERE WAS NO Subsequently, plaintiff was paid the aggregate amount of 5,814,000.00. But as of
STIPULATION IN THE AGREEMENT OF THE PARTIES WITH REGARD May 30, 1991, plaintiffs billings numbers 3 and 4 had remained unpaid (Exhs. "L",
TO INTEREST AND DESPITE THE FACT THAT THEIR AGREEMENT "M", and "M-1").
WAS NOT A "LOAN OR FORBEARANCE OF MONEY."
xxxx
III.
On the misaligned diaphragm wall from top to bottom and inbetween panels, plaintiff
THE COURT OF APPEALS COMMITTED GRAVE AND SERIOUS explained thatin the excavation of the soil where the rebar cages are lowered and
REVERSABLE ERROR WHEN IT DISMISSED THE COUNTERCLAIM OF later poured with concrete cement, the characteristics of the soil is not the same or
PETITIONER NOTWITHSTANDING OVERWHELMING EVIDENCE homogenous all throughout. Because of this property of the soil,in the process of
SUPPORTING ITS CLAIM OF 8,582,756.29 AS ACTUAL DAMAGES. excavation, it may erode in some places that may cause spaces that the cement may
fill or occupy which would naturally cause bulges, protrusions and misalignment in the objection on plaintiffs works, the majority of which were for the accomplishments in
concrete cast into the excavated ground(tsn., June 1, 2000, pp 14-18). This, in fact the construction of the diaphragm wall (tsn., ibid, p. 70).
was anticipated when the agreement was executed and included as provision 6.4
thereof. xxxx

The construction of the diaphragm wall panel by panel caused misalignment and the While there is no evidence to show the scope of work for these billings, it is safe to
chipping off of the portions misaligned is considered a matter of course. Defendant, assume that these were also works in the construction of the diaphragm wall
as the main contractor of the project, has the responsibility of chopping or chipping off considering that as of May 16, 1991, plaintiff had only the installation of the steel
of bulges(tsn., ibid, pp 20-21). Wrong location of rebar dowels was anticipated by both props and welding works to complete (Exh. "H"). If defendant was able to evaluate the
contractor and subcontractor as the latter submitted a plan called "Detail of Sheer work finished by plaintiff the majority of which was the construction of the diaphragm
Connectors" (Exh "T") which was approved.The plan provided two alternatives by wall and paid it about 6 million as accomplishment, there was no reason why it could
which the wrong location of rebar dowels may be remedied. Hence, defendant, aware not evaluate plaintiffs works covered by billings 3 and 4.In other words, defendants
of the possibility of inaccurate location of these bars, cannot therefore ascribe the did nothave to excavate in order to determine and evaluate plaintiffs works. Hence,
same to the plaintiff as defective work. defendants refusal to pay was not justified and the alleged defects of the diaphragm
wall (tsn, Sept. 28, 2000, p. 17) which it claims to have discovered only after January
Construction of the capping beam required the use of cement. Records, however, 1992 were mere afterthoughts.19
show that from September 14, 1990 up to May 30, 1991 (Exhs. "B" to "L"), plaintiff
had repeatedly requested defendant to deliver cement. Finally, on April 22, 1991, Thus, in the absence of any record to otherwise prove FSIs neglect in the fulfilment of
plaintiff notified defendant of its inability to construct the capping beam for the latters its obligations under the contract, this Court shall refrain from reversing the findings of
failure to deliver the cement as provided in their agreement(Exh. "I"). Although the courts below, which are fully supported by and deducible from, the evidence on
records show that there was mention of revision of design, there was no evidence record. Indeed, FBI failed to present any evidence to justify its refusal to pay FSI for
presented to show such revision required less amount of cement than what was the works it was contracted to perform. As such, We do not see any reason to deviate
agreed on by plaintiff and defendant. from the assailed rulings.

The seventh phase of the construction of the diaphragm wall is the construction of the Anent FBIs second assignment of error, however, We find merit in the argument that
steel props which could be installed only after the soil has been excavated by the the 12% interest rateis inapplicable, since this case does not involve a loan or
main contractor. When defendant directed plaintiff to install the props, the latter forbearance ofmoney. In the landmark case of Eastern Shipping Lines, Inc. v. Court of
requested for a site inspection to determine if the excavation of the soil was finished Appeals,20 We laid down the following guidelines in computing legal interest:
up to the 4th level basement. Plaintiff, however, did not receive any response.It later
learned that defendant had contracted out that portion of work to another sub-
contractor (Exhs. "O" and "P"). Nevertheless, plaintiff informed defendant of its II. With regard particularly to an award of interest in the concept of actual and
willingness to execute that portion of its work.18 compensatory damages, the rate of interest, as well as the accrual thereof, is
imposed, as follows:
It is clear from the foregoing that contrary to the allegations of FBI, FSI had indeed
completed its assigned obligations, with the exception of certain assigned tasks, 1. When the obligation is breached, and it consists in the payment of a sum
which was due to the failure of FBI to fulfil its end of the bargain. of money, i.e., a loan or forbearance of money, the interest due should be
that which may have been stipulated in writing. Furthermore, the interest due
shall itself earn legal interest from the time it is judicially demanded. In the
It can similarly be deduced that the defects FBI complained of, such as the misaligned absence of stipulation, the rate of interest shall be 12% per annum to be
diaphragm wall and the erroneous location of the rebar dowels, were not only computed from default, i.e., from judicial or extrajudicial demand under and
anticipated by the parties, having stipulated alternative plans to remedy the same, but subject to the provisions of Article1169 of the Civil Code.
more importantly, are also attributable to the very actions of FBI. Accordingly,
considering that the alleged defects in FSIs contracted works were not so much due
to the fault or negligence of the FSI, but were satisfactorily proven to be caused by 2. When an obligation, not constituting a loan or forbearance of money, is
FBIs own acts, FBIs claim of 8,582,756.29 representing the cost of the measures it breached, an interest on the amount of damages awarded may be imposed
undertook to rectify the alleged defects must necessarily fail. In fact, as the lower at the discretion of the court at the rate of 6% per annum. No interest,
court noted, at the time when FBI had evaluated FSIs works, it did not categorically however, shall be adjudged on unliquidated claims or damages except when
pose any objection thereto, viz: or until the demand can be established with reasonable certainty.
Accordingly, where the demand is established with reasonable certainty, the
interest shall begin to run from the time the claim is made judicially or
Defendant admitted that it had paid 6 million based on its evaluation of plaintiffs extrajudicially (Art. 1169, Civil Code) but when such certainty cannot be so
accomplishments (tsn., Sept. 28, 2000, p. 17) and its payment was made without
reasonably established at the time the demand is made, the interest shall the rate of legal interest, whether the case falls under paragraph 1
begin to run only from the date the judgment of the court is made (at which or paragraph 2, above, shall be 6% per annumfrom such finality
time the quantification of damages may be deemed to have been reasonably until its satisfaction, this interim period being deemed to be by then
ascertained). The actual base for the computation of legal interest shall, in an equivalent to a forbearance of credit.
any case, be on the amount finally adjudged.
And, in addition to the above, judgments that have become final and executory prior
3. When the judgment of the court awarding a sum of money becomes final to July 1, 2013, shall not be disturbed and shall continue to be implemented applying
and executory, the rate of legal interest, whether the case falls under the rate of interest fixed therein.23
paragraph 1 or paragraph 2, above, shall be 12% per annum from such
finality until its satisfaction, this interim period being deemed to be by then an It should be noted, however, that the new rate could only be applied prospectively and
equivalent to a forbearance of credit.21 not retroactively. Consequently, the twelve percent (12%) per annum legal interest
shall apply only until June 30, 2013. Come July 1, 2013, the new rate of six percent
In line, however, with the recent circular of the Monetary Board of the Bangko Sentral (6%) per annum shall be the prevailing rate of interest when applicable. Thus, the
ng Pilipinas (BSP-MB) No. 799, we have modified the guidelines in Nacar v. Gallery need to determine whether the obligation involved herein is a loanand forbearance of
Frames,22 as follows: money nonetheless exists.

I. When an obligation, regardless of itssource, i.e., law, contracts, In S.C. Megaworld Construction and Development Corporation v. Engr. Parada,24 We
quasicontracts, delicts or quasi-delicts is breached, the contravenor can be clarified the meaning of obligations constituting loans or forbearance of money in the
held liable for damages. The provisions under Title XVIII on "Damages" of following wise:
the Civil Code govern in determining the measure of recoverable damages.
As further clarified in the case of Sunga-Chan v. CA, a loan or forbearance of money,
II. With regard particularly to an award of interest in the concept of actual goods or credit describes a contractual obligation whereby a lender or creditor has
and compensatory damages, the rate of interest, as well as the accrual refrained during a given period from requiring the borrower or debtor to repay the loan
thereof, is imposed, as follows: or debt then due and payable. Thus:

1. When the obligation is breached, and it consists in the payment In Reformina v. Tomol, Jr., the Court held that the legal interest at 12% per annum
of a sum of money, i.e., a loan or forbearance of money, the under Central Bank (CB) Circular No. 416 shall be adjudged only in cases involving
interest due should be that which may have been stipulated in the loan or forbearance of money. And for transactions involving payment of
writing. Furthermore, the interest due shall itself earn legal interest indemnities in the concept of damages arising from default in the performance of
from the time it is judicially demanded. In the absence of stipulation, obligations in general and/or for money judgment not involving a loan or forbearance
the rate of interest shall be 6% per annumto be computed from of money, goods, or credit, the governing provision is Art. 2209 of the Civil Code
default, i.e., from judicial or extrajudicial demand under and subject prescribing a yearly 6% interest. Art. 2209 pertinently provides:
to the provisions of Article 1169 of the Civil Code.
Art. 2209. If the obligation consists in the payment of a sum of money, and the debtor
2. When an obligation, not constituting a loan or forbearance of incurs in delay, the indemnity for damages, there being no stipulation to the contrary,
money, is breached, an interest on the amount of damages shall be the payment of the interest agreed upon, and in the absence of stipulation,
awarded may be imposed at the discretion of the court at the rate of the legal interest, which is six per cent per annum.
6% per annum. No interest, however, shall be adjudged on
unliquidated claims or damages, except when or until the demand The term "forbearance," within the context of usury law, has been described as a
can be established with reasonable certainty. Accordingly, where contractual obligation ofa lender or creditor to refrain, during a given period of time,
the demand is established with reasonable certainty, the interest from requiring the borrower or debtor to repay the loan or debt then due and
shall begin to run from the time the claim is made judicially or payable.25
extrajudicially(Art. 1169, Civil Code), but when such certainty
cannot be so reasonably established at the time the demand is
made, the interest shall begin to run only from the date the Forbearance of money, goods or credits, therefore, refers to arrangements other than
judgment of the court is made (at which time the quantification of loan agreements, where a person acquiesces to the temporary use of his money,
damages may be deemed to have been reasonably ascertained). goods orcredits pending the happening of certain events or fulfilment of certain
The actual base for the computation of legal interest shall, in any conditions.26 Consequently, if those conditions are breached, said person is entitled
case, be on the amount finally adjudged. 3. When the judgment of not only to the return of the principal amount paid, but also to compensation for the
the court awarding a sum of money becomes final and executory,
use of his money which would be the same rateof legal interest applicable to a loan
since the use or deprivation of funds therein is similar to a loan.27

This case, however, does not involve an acquiescence to the temporary use of a
partys money but a performance of a particular service, specifically the construction
of the diaphragm wall, capping beam, and guide walls of the Trafalgar Plaza.

A review of similar jurisprudence would tell us that this Court had repeatedly
recognized this distinction and awarded interest at a rate of 6% on actual or
compensatory damages arising from a breach not only of construction
contracts,28 such as the one subject ofthis case, but also of contracts wherein one of
the parties reneged on its obligation to perform messengerial services, 29 deliver
certain quantities of molasses,30 undertake the reforestation of a denuded forest
land,31 as well as breaches of contracts of carriage,32 and trucking agreements.33 We
have explained therein that the reason behind such is that said contracts do not
partake of loans or forbearance of money but are more in the nature of contracts of
service.

Thus, in the absence of any stipulation as to interest in the agreement between the
parties herein, the matter of interest award arising from the dispute in this case would
actually fall under the second paragraph of the above-quoted guidelines inthe
landmark case of Eastern Shipping Lines, which necessitates the imposition of
interestat the rate of 6%, instead of the 12% imposed by the courts below.

The 6% interest rate shall further be imposed from the finality of the judgment herein
until satisfaction thereof, in light of our recent ruling in Nacar v. Gallery Frames. 34

Note, however, that contrary to FBIsassertion, We find no error in the RTCs ruling
that the interest shall begin to run from August 30, 1991 as this is the date when FSI
extrajudicially made its claim against FBI through a letter demanding payment for its
services.35

In view of the foregoing, therefore, We find no compelling reason to disturb the factual
findings of the RTC and the CA, which are fully supported by and deducible from, the
evidence on record, insofar as the sum representing Billings 3 and 4 is concerned. As
to the rate of interest due thereon, however, We note that the same should be
reduced to 6% per annum considering the fact that the obligation involved herein
does not partake of a loan or forbearance of money.

WHEREFORE, premises considered, the instant petition is DENIED. The Decision


and Resolution, dated July 15, 2010 and November 23, 2010, respectively, of the
Court of Appeals in CA-G.R. CV No. 70849 are hereby AFFIRMED with
MODIFICATION. Federal Builders, Inc. is ORDERED to pay Foundation Specialists,
Inc. the sum of Pl ,024,600.00 representing billings 3 and 4, less the amount of
33,354.40, plus interest at six percent (6%) per annum reckoned from August 30,
1991 until full payment thereof.

SO ORDERED.
one month at 6% per month. Servado and Leticia executed a promissory note
THIRD DIVISION for P50,000.00, to evidence the loan, payable on January 7, 1986.
On November 19, 1985, Servando and Leticia obtained from Veronica another
loan in the amount of P90,000.00, payable in two months, at 6% interest per
month.They executed a promissory note to evidence the loan, maturing on January 19,
[G.R. No. 131622. November 27, 1998]
1986. They received only P84,000.00, out of the proceeds of the loan.
On maturity of the two promissory notes, the borrowers failed to pay the
indebtedness.
LETICIA Y. MEDEL DR. RAFAEL MEDEL and SERVANDO FRANCO, petitioners,
On June 11, 1986, Servando and Leticia secured from Veronica still another loan
vs. COURT OF APPEALS, SPOUSES VERONICA R. GONZALES and
in the amount of P300,000.00, maturing in one month, secured by a real estate
DANILO G. GONZALES, JR., doing lending business under the trade
mortgage over a property belonging to Leticia Makalintal Yaptinchay, who issued a
name and style "GONZALES CREDIT ENTERPRISES", respondents.
special power of attorney in favor of Leticia Medel, authorizing her to execute the
mortgage. Servando and Leticia executed a promissory note in favor of Veronica to pay
DECISION the sum of P300,000.00, after a month, or on July 11, 1986. However, only the sum
of P275,000.00, was given to them out of the proceeds of the loan.
PARDO, J.:
Like the previous loans, Servando and Medel failed to pay the third loan on
The case before the Court is a petition for review on certiorari, under Rule 45 of maturity.
the Revised Rules of Court, seeking to set aside the decision of the Court of On July 23, 1986, Servando and Leticia with the latter's husband, Dr. Rafael
Appeals,[1] and its resolution denying reconsideration,[2] the dispositive portion of which Medel, consolidated all their previous unpaid loans totaling P440,000.00, and sought
decision reads as follows: from Veronica another loan in the amount of P60,000.00, bringing their indebtedness
"WHEREFORE, the appealed judgment is hereby to a total of P500,000.00, payable on August 23, 1986. The executed a promissory
MODIFIED such that defendants are hereby ordered to pay the note, reading as follows:
plaintiff: the sum of P500,000.00, plus 5.5% per month interest
and 2% service charge per annum effective July 23, 1986, plus "Baliwag, Bulacan July 23, 1986
1% per month of the total amount due and demandable as penalty "Maturity Date August 23, 1986
charges effective August 23, 1986, until the entire amount is fully
paid. "P500,000.00
"The award to the plaintiff of P50,000.00 as attorney's "FOR VALUE RECEIVED, I/WE jointly and severally promise to pay to the
fees is affirmed. And so is the imposition of costs against the order of VERONICA R. GONZALES doing business in the business style
defendants. of GONZALES CREDIT ENTERPRISES, Filipino, of legal age, married to
Danilo G. Gonzales, Jr., of Baliwag Bulacan, the sum of PESOS ........
SO ORDERED."[3] FIVE HUNDRED THOUSAND ..... (P500,000.00) Philippine
Currency with interest thereon at the rate of 5.5 PER CENT per month plus
The Court required the respondents to comment on the petition, [4] which was filed 2% service charge per annum from datehereof until fully paid according to
on April 3, 1998,[5] and the petitioners to reply thereto, which was filed on May 29, the amortization schedule contained herein. (Underscoring supplied)
1998.[6] We now resolve to give due course to the petition and decide the case. "Payment will be made in full at the maturity date.
The facts of the case, as found by the Court of Appeals in its decision, which are "Should I/WE fail to pay any amortization or portion hereof when due, all
considered binding and conclusive on the parties herein, as the appeal is limited to the other installments together with all interest accrued shall immediately
questions of law, are as follows: be due and payable and I/WE hereby agree to pay
On November 7, 1985, Servando Franco and Leticia Medel (hereafter Servando an additional amount equivalent to one per cent (1%) per month of the amo
and Leticia) obtained a loan from Veronica R. Gonzales (hereafter Veronica), who was unt due and demandable as penalty charges inthe form of liquidated dama
engaged in the money lending business under the name "Gonzales Credit Enterprises", ges until fully paid; and the
in the amount of P50,000.00, payable in two months. Veronica gave only the amount further sum of TWENTY FIVE PER CENT (25%) thereon in full, without
of P47,000.00, to the borrowers, as she retained P3,000.00, as advance interest for deductions as Attorney's Feewhether actually incurred or not, of the total
amount due and demandable, exclusive of costs and judicial or extra provision of the New [Civil] Code" that the "legal rate of interest for loan or forbearance
judicial expenses. (Underscoring supplied) of money, goods or credit is 12% per annum." [7]
"I, WE further agree that in the event the present rate of interest on loan is Accordingly, on December 9, 1991, the trial court rendered judgment, the
increased by law or the Central Bank of the Philippines, the holder shall dispositive portion of which reads as follows:
have the option to apply and collect the increased interest charges without
notice although the original interest have already been collected wholly or "WHEREFORE, premises considered, judgment is hereby rendered, as follows:
partially unless the contrary is required by law.
"It is also a special condition of this contract that the parties herein agree "1. Ordering the defendants Servando Franco and Leticia Medel, jointly and severally,
that the amount of peso-obligation under this agreement is based on the to pay plaintiffs the amount of P47,000.00 plus 12% interest per annum from
present value of peso, and if there be any change in the value thereof, due November 7, 1985 and 1% per month as penalty, until the entire amount is paid in full.
to extraordinary inflation or deflation, or any other cause or reason, then
the peso-obligation herein contracted shall be adjusted in accordance with "2. Ordering the defendants Servando Franco and Leticia Y. Medel to plaintiffs, jointly
the value of the peso then prevailing at the time of the complete fulfillment and severally the amount of P84,000.00 with 12% interest per annum and 1% per
of obligation. cent per month as penalty from November 19,1985 until the whole amount is fully
"Demand and notice of dishonor waived. Holder may accept partial paid;
payments and grant renewals of this note or extension of payments,
reserving rights against each and all indorsers and all parties to this note. "3. Ordering the defendants to pay the plaintiffs, jointly and severally, the amount
of P285,000.00 plus 12% interest per annum and 1% per month as penalty from July
"IN CASE OF JUDICIAL Execution of this obligation, or any part of it, the 11, 1986, until the whole amount is fully paid;
debtors waive all his/their rights under the provisions of Section 12, Rule
39, of the Revised Rules of Court."
"4. Ordering the defendants to pay plaintiffs, jointly and severally, the amount
On maturity of the loan, the borrowers failed to pay the indebtedness of P50,000.00 as attorney's fees;
of P500,000.00, plus interests and penalties, evidenced by the above-quoted
promissory note. "5. All counterclaims are hereby dismissed.
On February 20, 1990, Veronica R. Gonzales, joined by her husband Danilo G.
Gonzales, filed with the Regional Trial Court of Bulacan, Branch 16, at Malolos, "With costs against the defendants."[8]
Bulacan, a complaint for collection of the full amount of the loan including interests and
other charges. In due time, both plaintiffs and defendants appealed to the Court of Appeals.
In his answer to the complaint filed with the trial court on April 5, 1990, defendant In their appeal, plaintiffs-appellants argued that the promissory note, which
Servando alleged that he did not obtain any loan from the plaintiffs; that it was consolidated all the unpaid loans of the defendants, is the law that governs the
defendants Leticia and Dr. Rafael Medel who borrowed from the plaintiffs the sum parties. They further argued that Circular No. 416 of the Central Bank prescribing the
of P500,000.00, and actually received the amount and benefited therefrom; that the rate of interest for loans or forbearance of money, goods or credit at 12% per annum,
loan was secured by a real estate mortgage executed in favor of the plaintiffs, and that applies only in the absence of a stipulation on interest rate, but not when the parties
he (Servando Franco) signed the promissory note only as a witness. agreed thereon.
In their separate answer filed on April 10,1990, defendants Leticia and Rafael The Court of Appeals sustained the plaintiffs-appellants' contention. It ruled that
Medel alleged that the loan was the transaction of Leticia Yaptinchay, who executed a "the Usury Law having become 'legally inexistent' with the promulgation by the Central
mortgage in favor of the plaintiffs over a parcel of real estate situated in San Juan, Bank in 1982 of Circular No. 905, the lender and borrower could agree on any interest
Batangas; that the interest rate is excessive at 5.5% per month with additional service that may be charged on the loan".[9] The Court of Appeals further held that "the
charge of 2% per annum, and penalty charge of 1% per month; that the stipulation for imposition of 'an additional amount equivalent to 1% per month of the amount due and
attorney's fees of 25% ofthe amount due is unconscionable, illegal and excessive, and demandable as penalty charges in the form of liquidated damages until fully paid' was
that substantial payments made were applied to interest, penalties and other charges. allowed by law".[10]
After due trial, the lower court declared that the due execution and genuineness Accordingly, on March 21, 1997, the Court of Appeals promulgated it decision
of the four promissory notes had been duly proved, and ruled that although the Usury reversing that of the Regional Trial Court, disposing as follows:
Law had been repealed, the interest charged by the plaintiffs on the loans was
unconscionable and "revolting to the conscience". Hence, the trial court applied "the "WHEREFORE, the appealed judgment is hereby
MODIFIED such that defendants are hereby ordered to pay the
plaintiffs the sum of P500,000.00, plus 5.5% per month interest WHEREFORE, the Court hereby REVERSES and SETS ASIDE the decision of
and 2% service charge per annum effective July 23, 1986, plus the Court of Appeals promulgated on March 21, 1997, and its resolution dated
1% per month of the total amount due and demandable as November 25, 1997. Instead, we render judgment REVIVING and AFFIRMING the
penalty charges effective August 24, 1986, until the entire decision dated December 9, 1991, of the Regional Trial Court of Bulacan, Branch 16,
amount is fully paid. Malolos, Bulacan, in Civil Case No. 134-M-90, involving the same parties.
"The award to the plaintiffs of P50,000.00 as attorney's No pronouncement as to costs in this instance
fees is affirmed. And so is the imposition of costs against the
defendants. SO ORDERED.

"SO OREDERED."[11]
On April 15, 1997, defendants-appellants filed a motion for reconsideration of the
said decision. By resolution dated November 25, 1997, the Court of Appeals denied the
motion.[12]
Hence, defendants interposed the present recourse via petition for review
on certiorari.[13]
We find the petition meritorious.
Basically, the issue revolves on the validity of the interest rate stipulated
upon. Thus, the question presented is whether or not the stipulated rate of interest at
5.5% per month on the loan in the sum of P500,000.00, that plaintiffs extended to the
defendants is usurious. In other words, is the Usury Law still effective, or has it been
repealed by Central Bank Circular No. 905, adopted on December 22, 1982, pursuant
to its powers under P.D. No. 116, as amended by P.D. No. 1684?
We agree with petitioners that the stipulated rate of interest at 5.5% per month on
the P500,000.00 loan is excessive, iniquitous, unconscionable and
exorbitant.13However, we can not consider the rate "usurious" because this Court has
consistently held that Circulr No. 905 of the Central Bank, adopted on December 22,
1982, has expressly removed the interest ceilings prescribed by the Usury Law[14] and
that the Usury Law is now "legally inexistent".[15]
In Security Bank and Trust Company vs. Regional Trial Court of Makati, Branch
61[16] the Court held that CB Circular No. 905 "did not repeal nor in anyway amend the
Usury Law but simply suspended the latter's effectivity." Indeed, we have held that "a
Central Bank Circular can not repeal a law. Only a law can repeal another law."[17] In
the recent case of Florendo vs. Court of Appeals[18], the Court reiterated the ruling that
"by virtue of CB Circular 905, the Usury Law has been rendered ineffective"."Usury has
been legally non-existent in our jurisdiction. Interest can now be charged as lender and
borrower may agree upon."[19]
Nevertheless, we find the interest at 5.5% per month, or 66% per annum,
stipulated upon by the parties in the promissory note iniquitous or unconscionable, and,
hence, contrary to morals ("contra bonos mores"), if not against the law.[20] The
stipulation is void.[21] The courts shall reduce equitably liquidated damages, whether
intended as an indemnity or a penalty if they are iniquitous or unconscionable. [22]
Consequently, the Court of Appeals erred in upholding the stipulation of the
parties. Rather, we agree with the trial court that, under the circumstances, interest at
12% per annum, and an additional 1% a month penalty charge as liquidated damages
may be more reasonable.
Petitioners filed a motion to lift order of default and attached their position paper
Republic of the Philippines attributing the delay in construction to the 1997 Asian financial crisis. Petitioners
SUPREME COURT denied committing fraud or misrepresentation which could entitle respondents to an
Manila award of moral damages.

SECOND DIVISION On 13 June 2002, the HLURB, through Arbiter Atty. Joselito F. Melchor, rendered
judgment ordering petitioners to jointly and severally pay respondents the following
amount:
G.R. No. 185798 January 13, 2014
a) The amount of TWO MILLION ONE HUNDRED NINETY-EIGHT
FIL-ESTATE PROPERTIES, INC. AND FIL-ESTATE NETWORK INC., Petitioners, THOUSAND NINE HUNDRED FORTY NINE PESOS & 96/100
vs. (2,198,949.96) with interest thereon at twelve percent (12%) per annum to
SPOUSES CONRADO AND MARIA VICTORIA RONQUILLO, Respondents. be computed from the time of the complainants demand for refund on
October 08, 1998 until fully paid,
DECISION
b) ONE HUNDRED THOUSAND PESOS (100,000.00) as moral damages,
PEREZ, J.:
c) FIFTY THOUSAND PESOS (50,000.00) as attorneys fees,
Before the Court is a petition for review on certiorari under Rule 45 of the 1997 Rules
.of Civil Procedure assailing the Decision1 of the Court of Appeals in CA-G.R. SP No. d) The costs of suit, and
100450 which affirmed the Decision of the Office of the President in O.P. Case No.
06-F-216.
e) An administrative fine of TEN THOUSAND PESOS (10,000.00) payable
to this Office fifteen (15) days upon receipt of this decision, for violation of
As culled from the records, the facts are as follow: Section 20 in relation to Section 38 of PD 957.3

Petitioner Fil-Estate Properties, Inc. is the owner and developer of the Central Park The Arbiter considered petitioners failure to develop the condominium project as a
Place Tower while co-petitioner Fil-Estate Network, Inc. is its authorized marketing substantial breach of their obligation which entitles respondents to seek for rescission
agent. Respondent Spouses Conrado and Maria Victoria Ronquillo purchased from with payment of damages. The Arbiter also stated that mere economic hardship is not
petitioners an 82-square meter condominium unit at Central Park Place Tower in an excuse for contractual and legal delay.
Mandaluyong City for a pre-selling contract price of FIVE MILLION ONE HUNDRED
SEVENTY-FOUR THOUSAND ONLY (5,174,000.00). On 29 August 1997,
respondents executed and signed a Reservation Application Agreement wherein they Petitioners appealed the Arbiters Decision through a petition for review pursuant to
deposited 200,000.00 as reservation fee. As agreed upon, respondents paid the full Rule XII of the 1996 Rules of Procedure of HLURB. On 17 February 2005, the Board
downpayment of 1,552,200.00 and had been paying the 63,363.33 monthly of Commissioners of the HLURB denied4 the petition and affirmed the Arbiters
amortizations until September 1998. Decision. The HLURB reiterated that the depreciation of the peso as a result of the
Asian financial crisis is not a fortuitous event which will exempt petitioners from the
performance of their contractual obligation.
Upon learning that construction works had stopped, respondents likewise stopped
paying their monthly amortization. Claiming to have paid a total of 2,198,949.96 to
petitioners, respondents through two (2) successive letters, demanded a full refund of Petitioners filed a motion for reconsideration but it was denied 5 on 8 May 2006.
their payment with interest. When their demands went unheeded, respondents were Thereafter, petitioners filed a Notice of Appeal with the Office of the President. On 18
constrained to file a Complaint for Refund and Damages before the Housing and April 2007, petitioners appeal was dismissed6 by the Office of the President for lack
Land Use Regulatory Board (HLURB). Respondents prayed for reimbursement/refund of merit. Petitioners moved for a reconsideration but their motion was denied7 on 26
of 2,198,949.96 representing the total amortization payments, 200,000.00 as and July 2007.
by way of moral damages, attorneys fees and other litigation expenses.
Petitioners sought relief from the Court of Appeals through a petition for review under
On 21 October 2000, the HLURB issued an Order of Default against petitioners for Rule 43 containing the same arguments they raised before the HLURB and the Office
failing to file their Answer within the reglementary period despite service of of the President:
summons.2
I.
THE HONORABLE OFFICE OF THE PRESIDENT ERRED IN AFFIRMING THE THE HONORABLE COURT OF APPEALS ERRED WHEN IT AFFIRMED IN TOTO
DECISION OF THE HONORABLE HOUSING AND LAND USE REGULATORY THE DECISION OF THE OFFICE OF THE PRESIDENT WHICH SUSTAINED
BOARD AND ORDERING PETITIONERS-APPELLANTS TO REFUND RESCISSION AND REFUND IN FAVOR OF THE RESPONDENTS DESPITE LACK
RESPONDENTS-APPELLEES THE SUM OF 2,198,949.96 WITH 12% INTEREST OF CAUSE OF ACTION.
FROM 8 OCTOBER 1998 UNTIL FULLY PAID, CONSIDERING THAT THE
COMPLAINT STATES NO CAUSE OF ACTION AGAINST PETITIONERS- B.
APPELLANTS.
GRANTING FOR THE SAKE OF ARGUMENT THAT THE PETITIONERS ARE
II. LIABLE UNDER THE PREMISES, THE HONORABLE COURT OF APPEALS
ERRED WHEN IT AFFIRMED THE HUGE AMOUNT OF INTEREST OF TWELVE
THE HONORABLE OFFICE OF THE PRESIDENT ERRED IN AFFIRMING THE PERCENT (12%).
DECISION OF THE OFFICE BELOW ORDERING PETITIONERS-APPELLANTS TO
PAY RESPONDENTS-APPELLEES THE SUM OF 100,000.00 AS MORAL C.
DAMAGES AND 50,000.00 AS ATTORNEYS FEES CONSIDERING THE
ABSENCE OF ANY FACTUAL OR LEGAL BASIS THEREFOR.
THE HONORABLE COURT OF APPEALS LIKEWISE ERRED WHEN IT AFFIRMED
IN TOTO THE DECISION OF THE OFFICE OF THE PRESIDENT INCLUDING THE
III. PAYMENT OF 100,000.00 AS MORAL DAMAGES, 50,000.00 AS ATTORNEYS
FEES AND 10,000.00 AS ADMINISTRATIVE FINE IN THE ABSENCE OF ANY
THE HONORABLE OFFICE OF THE PRESIDENT ERRED IN AFFIRMING THE FACTUAL OR LEGAL BASIS TO SUPPORT SUCH CONCLUSIONS.11
DECISION OF THE HOUSING AND LAND USE REGULATORY BOARD
ORDERING PETITIONERS-APPELLANTS TO PAY 10,000.00 AS Petitioners insist that the complaint states no cause of action because they allegedly
ADMINISTRATIVE FINE IN THE ABSENCE OF ANY FACTUAL OR LEGAL BASIS have not committed any act of misrepresentation amounting to bad faith which could
TO SUPPORT SUCH FINDING.8 entitle respondents to a refund. Petitioners claim that there was a mere delay in the
completion of the project and that they only resorted to "suspension and reformatting
On 30 July 2008, the Court of Appeals denied the petition for review for lack of merit. as a testament to their commitment to their buyers." Petitioners attribute the delay to
The appellate court echoed the HLURB Arbiters ruling that "a buyer for a the 1997 Asian financial crisis that befell the real estate industry. Invoking Article 1174
condominium/subdivision unit/lot unit which has not been developed in accordance of the New Civil Code, petitioners maintain that they cannot be held liable for a
with the approved condominium/subdivision plan within the time limit for complying fortuitous event.
with said developmental requirement may opt for reimbursement under Section 20 in
relation to Section 23 of Presidential Decree (P.D.) 957 x x x."9 The appellate court Petitioners contest the payment of a huge amount of interest on account of
supported the HLURB Arbiters conclusion, which was affirmed by the HLURB Board suspension of development on a project. They liken their situation to a bank which
of Commission and the Office of the President, that petitioners failure to develop the this Court, in Overseas Bank v. Court of Appeals,12 adjudged as not liable to pay
condominium project is tantamount to a substantial breach which warrants a refund of interest on deposits during the period that its operations are ordered suspended by
the total amount paid, including interest. The appellate court pointed out that the Monetary Board of the Central Bank.
petitioners failed to prove that the Asian financial crisis constitutes a fortuitous event
which could excuse them from the performance of their contractual and statutory
obligations. The appellate court also affirmed the award of moral damages in light of Lastly, petitioners aver that they should not be ordered to pay moral damages
petitioners unjustified refusal to satisfy respondents claim and the legality of the because they never intended to cause delay, and again blamed the Asian economic
administrative fine, as provided in Section 20 of Presidential Decree No. 957. crisis as the direct, proximate and only cause of their failure to complete the project.
Petitioners submit that moral damages should not be awarded unless so stipulated
except under the instances enumerated in Article 2208 of the New Civil Code. Lastly,
Petitioners sought reconsideration but it was denied in a Resolution 10 dated 11 petitioners refuse to pay the administrative fine because the delay in the project was
December 2008 by the Court of Appeals. caused not by their own deceptive intent to defraud their buyers, but due to
unforeseen circumstances beyond their control.
Aggrieved, petitioners filed the instant petition advancing substantially the same
grounds for review: Three issues are presented for our resolution: 1) whether or not the Asian financial
crisis constitute a fortuitous event which would justify delay by petitioners in the
A. performance of their contractual obligation; 2) assuming that petitioners are liable,
whether or not 12% interest was correctly imposed on the judgment award, and 3)
whether the award of moral damages, attorneys fees and administrative fine was issue as a question of fact which may not be raised in a petition for review considering
proper. that there was no variance in the factual findings of the HLURB, the Office of the
President and the Court of Appeals. Second, the Court cited the previous rulings of
It is apparent that these issues were repeatedly raised by petitioners in all the legal Asian Construction and Development Corporation v. Philippine Commercial
fora. The rulings were consistent that first, the Asian financial crisis is not a fortuitous International Bank14 and Mondragon Leisure and Resorts Corporation v. Court of
event that would excuse petitioners from performing their contractual obligation; Appeals15 holding that the 1997 Asian financial crisis did not constitute a valid
second, as a result of the breach committed by petitioners, respondents are entitled to justification to renege on obligations. The Court expounded:
rescind the contract and to be refunded the amount of amortizations paid including
interest and damages; and third, petitioners are likewise obligated to pay attorneys Also, we cannot generalize that the Asian financial crisis in 1997 was unforeseeable
fees and the administrative fine. and beyond the control of a business corporation. It is unfortunate that petitioner
apparently met with considerable difficulty e.g. increase cost of materials and labor,
This petition did not present any justification for us to deviate from the rulings of the even before the scheduled commencement of its real estate project as early as 1995.
HLURB, the Office of the President and the Court of Appeals. However, a real estate enterprise engaged in the pre-selling of condominium units is
concededly a master in projections on commodities and currency movements and
business risks. The fluctuating movement of the Philippine peso in the foreign
Indeed, the non-performance of petitioners obligation entitles respondents to exchange market is an everyday occurrence, and fluctuations in currency exchange
rescission under Article 1191 of the New Civil Code which states: rates happen everyday, thus, not an instance of caso fortuito.16

Article 1191. The power to rescind obligations is implied in reciprocal ones, in case The aforementioned decision becomes a precedent to future cases in which the facts
one of the obligors should not comply with what is incumbent upon him. are substantially the same, as in this case. The principle of stare decisis, which
means adherence to judicial precedents, applies.
The injured party may choose between the fulfillment and the rescission of the
obligation, with payment of damages in either case. He may also seek rescission, In said case, the Court ordered the refund of the total amortizations paid by
even after he has chosen fulfillment, if the latter should become impossible. respondents plus 6% legal interest computed from the date of demand. The Court
also awarded attorneys fees. We follow that ruling in the case before us.
More in point is Section 23 of Presidential Decree No. 957, the rule governing the sale
of condominiums, which provides: The resulting modification of the award of legal interest is, also, in line with our recent
ruling in Nacar v. Gallery Frames,17 embodying the amendment introduced by the
Section 23. Non-Forfeiture of Payments.1wphi1 No installment payment made by a Bangko Sentral ng Pilipinas Monetary Board in BSP-MB Circular No. 799 which
buyer in a subdivision or condominium project for the lot or unit he contracted to buy pegged the interest rate at 6% regardless of the source of obligation.
shall be forfeited in favor of the owner or developer when the buyer, after due notice
to the owner or developer, desists from further payment due to the failure of the We likewise affirm the award of attorneys fees because respondents were forced to
owner or developer to develop the subdivision or condominium project according to litigate for 14 years and incur expenses to protect their rights and interest by reason
the approved plans and within the time limit for complying with the same. Such buyer of the unjustified act on the part of petitioners.18 The imposition of 10,000.00
may, at his option, be reimbursed the total amount paid including amortization administrative fine is correct pursuant to Section 38 of Presidential Decree No. 957
interests but excluding delinquency interests, with interest thereon at the legal rate. which reads:
(Emphasis supplied).
Section 38. Administrative Fines. The Authority may prescribe and impose fines not
Conformably with these provisions of law, respondents are entitled to rescind the exceeding ten thousand pesos for violations of the provisions of this Decree or of any
contract and demand reimbursement for the payments they had made to petitioners. rule or regulation thereunder. Fines shall be payable to the Authority and enforceable
through writs of execution in accordance with the provisions of the Rules of Court.
Notably, the issues had already been settled by the Court in the case of Fil-Estate
Properties, Inc. v. Spouses Go13promulgated on 17 August 2007, where the Court Finally, we sustain the award of moral damages. In order that moral damages may be
stated that the Asian financial crisis is not an instance of caso fortuito. Bearing the awarded in breach of contract cases, the defendant must have acted in bad faith,
same factual milieu as the instant case, G.R. No. 165164 involves the same must be found guilty of gross negligence amounting to bad faith, or must have acted
company, Fil-Estate, albeit about a different condominium property. The company in wanton disregard of contractual obligations.19 The Arbiter found petitioners to have
likewise reneged on its obligation to respondents therein by failing to develop the acted in bad faith when they breached their contract, when they failed to address
condominium project despite substantial payment of the contract price. Fil-Estate respondents grievances and when they adamantly refused to refund respondents'
advanced the same argument that the 1997 Asian financial crisis is a fortuitous event payment.
which justifies the delay of the construction project. First off, the Court classified the
In fine, we find no reversible error on the merits in the impugned Court of Appeals'
Decision and Resolution.

WHEREFORE, the petition is PARTLY GRANTED. The appealed Decision is


AFFIRMED with the MODIFICATION that the legal interest to be paid is SIX
PERCENT (6%) on the amount due computed from the time of respondents' demand
for refund on 8 October 1998.

SO ORDERED.
4) LIQUIDATED DAMAGES of Ten (10%) per cent of the total amount
THIRD DIVISION due;cralawlibrary

G.R. NO. 191178 : March 13, 2013 5) One Hundred Thousand pesos as reasonable ATTORNEY'S FEES;cralawlibrary

ANCHOR SAVINGS BANK (FORMERLY ANCHOR FINANCE AND INVESTMENT 6) Costs of suit.
CORPORATION), Petitioner, v. HENRY H. FURIGAY, GELINDA C. FURIGAY,
HERRIETTE C. FURIGAY and HEGEM C. FURIGAY, Respondents. SO ORDERED.6chanroblesvirtualawlibrary

DECISION While Civil Case No. 99-865 was pending, respondent spouses donated their
registered properties in Alaminos, Pangasinan, to their minor children, respondents
MENDOZA, J.: Hegem G. Furigay and Herriette C. Furigay. As a result, Transfer Certificate of Title
(TCT) Nos. 21743,7 21742,8 21741,9 and 2174010 were issued in the names of
Hegem and Herriette Furigay.
This concerns a petition for review_ on certiorari filed by petitioner Anchor Savings
Bank (ASB) under Rule 45 of the 1997 Rules of Civil Procedure, assailing the May 28,
2009 Decision1 and the January 22, 2010 Resolution2 of the Court of Appeals (CA), in Claiming that the donation of these properties was made in fraud of creditors, ASB
CA-G.R. CV No. 90123, dismissing the appeal.3chanroblesvirtualawlibrary filed a Complaint for Rescission of Deed of Donation, Title and Damages11 against
the respondent spouses and their children. The case was docketed as Civil Case No.
A-3040 and raffled to Branch 55 of the RTC of Alaminos, Pangasinan. In its
The assailed resolution denied the separate motions for reconsideration of both Complaint, ASB made the following allegations:chanroblesvirtualawlibrary
parties.
xxx
The Facts
4. That Ciudad Transport Services, Inc., Henry H. Furigay and Gelinda C. Furigay
On April 21, 1999, ASB filed a verified complaint for sum of money and damages with obtained a loan from Anchor Savings Bank and subsequently the former defaulted
application for replevin against Ciudad Transport Services, Inc. (CTS), its president, from their loan obligation which prompted Anchor Savings Bank to file the case
respondent Henry H. Furigay; his wife, respondent Gelinda C. Furigay; and a "John entitled "Anchor Savings Bank vs. Ciudad Transport Services, Inc., Henry H. Furigay
Doe." The case was docketed as Civil Case No. 99-865 and raffled to Branch 143 of and Gelinda C. Furigay" lodged before Makati City Regional Trial Court Branch 143
the Regional Trial Court of Makati City (RTC).4chanroblesvirtualawlibrary and docketed as Civil Case No. 99-865. On 7 November 2003 the Honorable Court in
the aforesaid case issued a Decision the dispositive portion of which reads as
On November 7, 2003, the RTC rendered its Decision5 in favor of ASB, the dispositive follows:chanroblesvirtualawlibrary
portion of which reads:chanroblesvirtualawlibrary
xxx
WHEREFORE, judgment is hereby rendered in favor of plaintiff Anchor Savings Bank
ordering defendants Ciudad Transport Services, Inc., Henry H. Furigay and Genilda 5. That defendants Sps. Henry H. Furigay and Gelinda C. Furigay are the registered
C. Furigay to pay the following:chanroblesvirtualawlibrary owners of various real properties located at the Province of Pangasinan covered by
Transfer Certificate of Title Nos. 19721, 21678, 21679, and 21682. x x x
1) The amount of Eight Million Six Hundred Ninety Five Thousand Two Hundred Two
pesos and Fifty Nine centavos (Php8,695,202.59) as PRINCIPAL OBLIGATION as of 6. That on 8 March 2001 defendants Sps. Henry H. Furigay and Gelinda C. Furigay
12 April 1999;cralawlibrary executed a Deed of Donation in favor of their children herein defendants Hegem C.
Furigay and Herriette C. Furigay donating to them all of the above-mentioned
2) An INTEREST of Twelve per cent (12%) per annum until fully paid;cralawlibrary properties. Hence, the following titles were issued under their names to wit: Transfer
Certificate of Title Nos. 21743, 21742, 21741, and 21740. x x x
3) PENALTY CHARGE of Twelve per cent (12%) per annum until fully
paid;cralawlibrary 7. That the donation made by defendants Sps. Henry H. Furigay and Gelinda C.
Furigay were done with the intention to defraud its creditors particularly Anchor
Savings Bank. Said transfer or conveyance is the one contemplated by Article 1387 of
the New Civil Code, which reads:chanroblesvirtualawlibrary
xxx as over the subject matter in view of the failure of the ASB to serve the summons
properly and to pay the necessary legal fees.
8. x x x In the instant case, Sps. Furigay donated the properties at the time there was
a pending case against them. x x x. In the instant case, the Sps. Furigay donated the RTC Resolutions
properties to their son and daughter. Moreover, the transfer or donation was executed
in 2001 when both donees Hegem C. Furigay and Herriette C. Furigay are minors. On September 29, 2006, the RTC issued an Order13 denying the motion to dismiss.
Respondents sought reconsideration of the Order adding that the ASB's action for
9. Clearly, the Donation made by defendants Sps. Furigay was intended to deprive rescission had already prescribed.
plaintiff Anchor Savings Bank from going after the subject properties to answer for
their due and demandable obligation with the Bank. The donation being undertaken in Upon filing of ASB's opposition to the motion for reconsideration, on February 27,
fraud of creditors then the same may be rescinded pursuant to Article 1381 of the 2007, the RTC reconsidered its earlier pronouncement and dismissed the complaint
New Civil Code. The said provision provides that: x x x for failure of ASB to pay the correct docket fees and for
prescription.14chanroblesvirtualawlibrary
Consequently, Transfer Certificate of Title Nos. 21743, 21742, 21741, and 21740
issued under the names of defendants Herriette C. Furigay and Hegem C. Furigay RTC explained that the service of summons by publication made by ASB was valid
should likewise be cancelled and reverted to the names of co-defendants Henry and because respondents' whereabouts could not have been ascertained with exactitude
Gelinda Furigay. and because Section 14, Rule 14 of the Rules of Court did not distinguish what kind
of action it would apply.
10. That because of the fraud perpetrated by defendants, plaintiff suffered the
following damages. On the issue of lack of jurisdiction over the subject matter of the case, the RTC ruled
that the complaint was actually a real action as it affected title to or possession of real
11. Plaintiff suffered actual and compensatory damages as a result of the filing of the property. Accordingly, the basis for determining the correct docket fees was the fair
case the bank has spent a lot of man-hours of its employees and officers re- market value of the real property under litigation as stated in its current tax declaration
evaluating the account of defendant Sps. Furigay. Such man-hour when converted or its current zonal valuation, whichever was higher. Considering that ASB did not
into monetary consideration represents the salaries and per diems of its employees state the current tax declaration or current zonal valuation of the real properties
particularly the CI/Appraiser, Head Office Lawyer and Bank Auditor;cralawlibrary involved, as well as the amount of actual damages and attorney's fees it prayed for,
the trial court was of the view that ASB purposely evaded the payment of the correct
12. Said claim likewise represents administrative expenses such as transportation filing fees.
expenses, reproduction of documents, and courier expenses among
others;cralawlibrary On the issue of prescription, the RTC ruled that the action for rescission had already
prescribed. It stated that an action for rescission grounded on fraud should be filed
13. Defendants should be made to pay plaintiff Anchor Savings Bank the amount of within four (4) years from the discovery of fraud. ASB filed the action for rescission
PESOS: ONE MILLION (P1,000,000.00) as moral damages for the damage it caused only on October 14, 2005 or after four (4) years from the time the Deed of Donation
to the latter's business goodwill and reputation;cralawlibrary was registered in the Register of Deeds of Alaminos, Pangasinan, on April 4, 2001.
The four-year prescriptive period should be reckoned from the date of registration of
the deed of donation and not from the date of the actual discovery of the registration
14. By way of example for the public and to deter others from the malicious filing of of the deeds of donation because registration is considered notice to the whole world.
baseless (sic) suit, defendants should be ordered to pay [plaintiff] the amount of Thus, the RTC disposed:chanroblesvirtualawlibrary
PESOS: TWO HUNDRED THOUSAND (P200,000.00) as exemplary damages.
WHEREFORE, premises considered, the Order dated September 29, 2006 is hereby
15. Attorneys fees equivalent to twenty-five percent (25%) of the total amount that can reconsidered and set aside, in lieu thereof, the instant complaint is hereby ordered
be collected from defendant;cralawlibrary dismissed on the account of lack of jurisdiction over the subject matter of the case for
failure of the plaintiff to pay the correct docket fees upon its institution attended by
16. Defendants should also be held liable to pay for the cost of bad faith and on the ground of prescription.
suit.12chanroblesvirtualawlibrary
SO ORDERED.15chanroblesvirtualawlibrary
Instead of filing an answer, respondents sought the dismissal of the complaint,
principally arguing that the RTC failed to acquire jurisdiction over their persons as well ASB sought reconsideration, but to no avail.16chanroblesvirtualawlibrary
Ruling of the CA As stated at the outset, both parties sought reconsideration but were rebuffed.

On appeal, the CA agreed with ASB that its complaint should not have been Issue
dismissed on the ground that it failed to pay the correct docket fees. It stated that the
lack of specific amount of actual damages and attorney's fees in ASB's complaint did Hence, this recourse of ASB to the Court, presenting the lone issue
not, by itself, amount to evident bad faith. The CA noted that ASB had previously of:chanroblesvirtualawlibrary
manifested before the trial court that it was willing to pay additional docket fees should
the same be found insufficient.
WHETHER OR NOT THE COURT OF APPEALS, IN CA G.R. CV NO 90123, HAS
DECIDED A QUESTION OF SUBSTANCE, NOT HERETOFORE DETERMINED BY
On the issue of prescription, however, the CA saw things differently. Considering the THE SUPREME COURT, OR HAS DECIDED IT IN A WAY PROBABLY NOT IN
subsidiary nature of an action for rescission, the CA found that the action of ASB had ACCORDANCE WITH LAW OR THE APPLICABLE DECISIONS OF THE SUPREME
not yet prescribed, but was premature. The CA noted that ASB failed to allege in its COURT, WHEN IT RENDERED THE DECISION DATED 28 MAY 2009, AND
complaint that it had resorted to all legal remedies to obtain satisfaction of its claim. RESOLUTION DATED 22 JANUARY 2010, IN FINDING THAT PETITIONER FAILED
The CA wrote:chanroblesvirtualawlibrary TO PROVE THAT IT HAS RESORTED TO ALL LEGAL REMEDIES TO OBTAIN
SATISFACTION OF ITS CLAIM, WITHOUT GIVING PETITIONER THE
After a thorough examination of the foregoing precepts and the facts engirding this OPPORTUNITY TO BE HEARD OR THE CHANCE TO PRESENT EVIDENCE TO
case, this court opines that plaintiff-appellant's action for rescission has not yet SUPPORT ITS ACTION, THEREBY DEPRIVING THE LATTER OF THE RIGHT TO
prescribed for it must be emphasized that it has not even accrued in the first place. To DUE PROCESS.18chanroblesvirtualawlibrary
stress, an action for rescission or accion pauliana accrues only if all five requisites are
present, to wit:chanroblesvirtualawlibrary ASB argues that, considering that its action was still in its preliminary stages, the CA
erred in dismissing its action on the ground that it failed to allege in its complaint the
1) That the plaintiff asking for rescission, has a credit prior to the alienation, although fact that it had resorted to all other legal remedies to satisfy its claim, because it is a
demandable later;cralawlibrary matter that need not be alleged in its complaint, but, rather, to be proved during trial. It
asserts that its action is not yet barred by prescription, insisting that the reckoning
2) That the debtor has made a subsequent contract conveying a patrimonial benefit to point of the four
a third person;cralawlibrary
(4)-year prescriptive period should be counted from September 2005, when it
3) That the creditor has no other legal remedy to satisfy his claim, but would benefit discovered the fraudulent donation made by respondent spouses.
by rescission of the conveyance to the third person;cralawlibrary
The basic issue in this case is whether the CA was correct in dismissing ASB's
4) That the act being impugned is fraudulent; and complaint on the ground that the action against respondents was premature.

5) That the third person who received the property conveyed, if by onerous title, has Ruling of the Court
been an accomplice in the fraud.
The Court finds the petition bereft of merit.
In the instant case, the plaintiff-appellant failed to satisfy the third requirement
considering that it did not allege in its complaint that it has resorted to all legal Section 1 of Rule 2 of the Revised Rules of Court requires that every ordinary civil
remedies to obtain satisfaction of his claim. It did not even point out in its complaint if action must be based on a cause of action. Section 2 of the same rule defines a
the decision in Civil Case No. 99-865 has already become final and executory and cause of action as an act or omission by which a party violates the right of another. In
whether the execution thereof yielded negative result in satisfying its claims. Even the order that one may claim to have a cause of action, the following elements must
skip tracing allegedly done by the plaintiff-appellant to locate the properties of the concur: (1) a right in favor of the plaintiff by whatever means and under whatever law
defendant-appellees was not mentioned. And although the skip tracing reports were it arises or is created; (2) an obligation on the part of the named defendant to respect
subsequently presented by the plaintiff-appellant, such reports are not sufficient to or not to violate such right; and (3) an act or omission on the part of such defendant in
satisfy the third requirement. First, they are not prepared and executed by the sheriff, violation of the right of the plaintiff or constituting a breach of the obligation of the
and second, they do not demonstrate that the sheriff failed to enforce and satisfy the defendant to the plaintiff for which the latter may maintain an action for recovery of
judgment of the court and that the plaintiff-appellant has exhausted the property of the damages or other appropriate relief.19 In other words, "a cause of action arises when
defendant-appellees. Perforce, the action for rescission filed by the plaintiff-appellant that should have been done is not done, or that which should not have been done is
is dismissible.17chanroblesvirtualawlibrary done."20chanroblesvirtualawlibrary
In Philippine American General Insurance Co., Inc. v. Sweet Lines, Inc.,21 it was held 3) That the creditor has no other legal remedy to satisfy his claim, but would benefit
that "before an action can properly be commenced, all the essential elements of the by rescission of the conveyance to the third person;cralawlibrary
cause of action must be in existence, that is, the cause of action must be complete.
All valid conditions precedent to the institution of the particular action, whether 4) That act being impugned is fraudulent; and
prescribed by statute, fixed by agreement of the parties or implied by law must be
performed or complied with before commencing the action, unless the conduct of the
adverse party has been such as to prevent or waive performance or excuse non- 5) That the third person who received the property conveyed, if by onerous title, has
performance of the condition." been an accomplice in the fraud.26chanroblesvirtualawlibrary

Moreover, it is not enough that a party has, in effect, a cause of action. A cursory reading of the allegations of ASB's complaint would show that it failed to
allege the ultimate facts constituting its cause of action and the prerequisites that
must be complied before the same may be instituted. ASB, without availing of the first
The rules of procedure require that the complaint must contain a concise statement of and second remedies, that is, exhausting the properties of CTS, Henry H. Furigay and
the ultimate or essential facts constituting the plaintiff's cause of action. "The test of Genilda C. Furigay or their transmissible rights and actions, simply undertook the third
the sufficiency of the facts alleged in the complaint is whether or not, admitting the measure and filed an action for annulment of the donation. This cannot be done. The
facts alleged, the court can render a valid judgment upon the same in accordance Court hereby quotes with approval the thorough discourse of the CA on this
with the prayer of plaintiff."22 The focus is on the sufficiency, not the veracity, of the score:27chanroblesvirtualawlibrary
material allegations. Failure to make a sufficient allegation of a cause of action in the
complaint warrants its dismissal.23chanroblesvirtualawlibrary
To answer the issue of prescription, the case of Khe Hong Cheng vs. Court of
Appeals (G.R. NO. 144169, March 28, 2001) is pertinent. In said case, Philam filed an
In relation to an action for rescission, it should be noted that the remedy of rescission action for collection against Khe Hong Cheng. While the case was still pending, or on
is subsidiary in nature; it cannot be instituted except when the party suffering damage December 20, 1989, Khe Hong Cheng, executed deeds of donations over parcels of
has no other legal means to obtain reparation for the same. 24 Article 1177 of the New land in favor of his children, and on December 27, 1989, said deeds were registered.
Civil Code provides:chanroblesvirtualawlibrary Thereafter, new titles were issued in the names of Khe Hong Cheng's children. Then,
the decision became final and executory. But upon enforcement of writ of execution,
The creditors, after having pursued the property in possession of the debtor to satisfy Philam found out that Khe Hong Cheng no longer had any property in his name.
their claims, may exercise all the rights and bring all the actions of the latter for the Thus, on February 25, 1997, Philam filed an action for rescission of the deeds of
same purpose, save those which are inherent in his person; they may also impugn donation against Khe Hong Cheng alleging that such was made in fraud of creditors.
the actions which the debtor may have done to defraud them. (Emphasis added) However, Khe Hong Cheng moved for the dismissal of the action averring that it has
already prescribed since the four-year prescriptive period for filing an action for
Consequently, following the subsidiary nature of the remedy of rescission, a creditor rescission pursuant to Article 1389 of the Civil Code commenced to run from the time
would have a cause of action to bring an action for rescission, if it is alleged that the the deeds of donation were registered on December 27, 1989. Khe Hong Cheng
following successive measures have already been taken: (1) exhaust the properties of averred that registration amounts to constructive notice and since the complaint was
the debtor through levying by attachment and execution upon all the property of the filed only on February 25, 1997, or more than four (4) years after said registration, the
debtor, except such as are exempt by law from execution; (2) exercise all the rights action was already barred by prescription. The trial court ruled that the complaint had
and actions of the debtor, save those personal to him (accion subrogatoria); and (3) not yet prescribed since the prescriptive period began to run only from December 29,
seek rescission of the contracts executed by the debtor in fraud of their rights (accion 1993, the date of the decision of the trial court. Such decision was affirmed by this
pauliana).25chanroblesvirtualawlibrary court but reckoned the accrual of Philam's cause of action in January 1997, the time
when it first learned that the judgment award could not be satisfied because the
judgment creditor, Khe Hong Cheng, had no more properties in his name. Hence, the
With respect to an accion pauliana, it is required that the ultimate facts constituting case reached the Supreme Court which ruled that the action for rescission has not yet
the following requisites must all be alleged in the complaint, prescribed, ratiocinating as follows:chanroblesvirtualawlibrary
viz.:chanroblesvirtualawlibrary
"Essentially, the issue for resolution posed by petitioners is this: When did the four (4)
1) That the plaintiff asking for rescission, has credit prior to the alienation, although year prescriptive period as provided for in Article 1389 of the Civil Code for
demandable later;cralawlibrary respondent Philam to file its action for rescission of the subject deeds of donation
commence to run?
2) That the debtor has made a subsequent contract conveying a patrimonial benefit to
a third person;cralawlibrary The petition is without merit.
Article 1389 of the Civil Code simply provides that, The action to claim rescission Petitioners, however, maintain that the cause of action of respondent Philam against
must be commenced within four years. Since this provision of law is silent as to when them for the rescission of the deeds of donation accrued as early as December 27,
the prescriptive period would commence, the general rule, i.e, from the moment the 1989, when petitioner Khe Hong Cheng registered the subject conveyances with the
cause of action accrues, therefore, applies. Article 1150 of the Civil Code is Register of Deeds. Respondent Philam allegedly had constructive knowledge of the
particularly instructive:chanroblesvirtualawlibrary execution of said deeds under Section 52 of Presidential Decree No. 1529, quoted
infra, as follows:chanroblesvirtualawlibrary
ARTICLE 1150. The time for prescription for all kinds of actions, when there is no
special provision which ordains otherwise, shall be counted from the day they may be SECTION 52. Constructive knowledge upon registration. Every conveyance,
brought. mortgage, lease, lien, attachment, order, judgment, instrument or entry affecting
registered land shall, if registered, filed or entered in the Office of the Register of
Indeed, this Court enunciated the principle that it is the legal possibility of bringing the Deeds for the province or city where the land to which it relates lies, be constructive
action which determines the starting point for the computation of the prescriptive notice to all persons from the time of such registering, filing, or entering.
period for the action. Article 1383 of the Civil Code provides as
follows:chanroblesvirtualawlibrary Petitioners argument that the Civil Code must yield to the Mortgage and Registration
Laws is misplaced, for in no way does this imply that the specific provisions of the
ARTICLE 1383. An action for rescission is subsidiary; it cannot be instituted except former may be all together ignored. To count the four year prescriptive period to
when the party suffering damage has no other legal means to obtain reparation for rescind an allegedly fraudulent contract from the date of registration of the
the same. conveyance with the Register of Deeds, as alleged by the petitioners, would run
counter to Article 1383 of the Civil Code as well as settled jurisprudence. It would
likewise violate the third requisite to file an action for rescission of an allegedly
It is thus apparent that an action to rescind or an accion pauliana must be of last fraudulent conveyance of property, i.e., the creditor has no other legal remedy to
resort, availed of only after all other legal remedies have been exhausted and have satisfy his claim.
been proven futile. For an accion pauliana to accrue, the following requisites must
concur:chanroblesvirtualawlibrary
An accion pauliana thus presupposes the following: 1) A judgment; 2) the issuance by
the trial court of a writ of execution for the satisfaction of the judgment, and 3) the
1) That the plaintiff asking for rescission, has a credit prior to the alienation, although failure of the sheriff to enforce and satisfy the judgment of the court. It requires that
demandable later; 2) That the debtor has made a subsequent contract conveying a the creditor has exhausted the property of the debtor. The date of the decision of the
patrimonial benefit to a third person; 3) That the creditor has no other legal remedy to trial court is immaterial. What is important is that the credit of the plaintiff antedates
satisfy his claim, but would benefit by rescission of the conveyance to the third that of the fraudulent alienation by the debtor of his property. After all, the decision of
person; 4) That the act being impugned is fraudulent; 5) That the third person who the trial court against the debtor will retroact to the time when the debtor became
received the property conveyed, if by onerous title, has been an accomplice in the indebted to the creditor.
fraud.
xxx
We quote with approval the following disquisition of the CA on the
matter:chanroblesvirtualawlibrary
Even if respondent Philam was aware, as of December 27, 1989, that petitioner Khe
Hong Cheng had executed the deeds of donation in favor of his children, the
An accion pauliana accrues only when the creditor discovers that he has no other complaint against Butuan Shipping Lines and/or petitioner Khe Hong Cheng was still
legal remedy for the satisfaction of his claim against the debtor other than an accion pending before the trial court. Respondent Philam had no inkling, at the time, that the
pauliana. The accion pauliana is an action of a last resort. For as long as the creditor trial court's judgment would be in its favor and further, that such judgment would not
still has a remedy at law for the enforcement of his claim against the debtor, the be satisfied due to the deeds of donation executed by petitioner Khe Hong Cheng
creditor will not have any cause of action against the creditor for rescission of the during the pendency of the case. Had respondent Philam filed his complaint on
contracts entered into by and between the debtor and another person or persons. December 27, 1989, such complaint would have been dismissed for being premature.
Indeed, an accion pauliana presupposes a judgment and the issuance by the trial Not only were all other legal remedies for the enforcement of respondent Philam's
court of a writ of execution for the satisfaction of the judgment and the failure of the claims not yet exhausted at the time the deeds of donation were executed and
Sheriff to enforce and satisfy the judgment of the court. It presupposes that the registered. Respondent Philam would also not have been able to prove then that
creditor has exhausted the property of the debtor. The date of the decision of the trial petitioner Khe Hong Cheng had no more property other than those covered by the
court against the debtor is immaterial. What is important is that the credit of the subject deeds to satisfy a favorable judgment by the trial court.
plaintiff antedates that of the fraudulent alienation by the debtor of his property. After
all, the decision of the trial court against the debtor will retroact to the time when the
debtor became indebted to the creditor. xxx
As mentioned earlier, respondent Philam only learned about the unlawful
conveyances made by petitioner Khe Hong Cheng in January 1997 when its counsel
accompanied the sheriff to Butuan City to attach the properties of petitioner Khe Hong
Cheng. There they found that he no longer had any properties in his name. It was
only then that respondent

Philam's action for rescission of the deeds of donation accrued because then it could
be said that respondent Philam had exhausted all legal means to satisfy the trial
court's judgment in its favor. Since respondent Philam filed its complaint for accion
pauliana against petitioners on February 25, 1997, barely a month from its discovery
that petitioner Khe Hong Cheng had no other property to satisfy the judgment award
against him, its action for rescission of the subject deeds clearly had not yet
prescribed."

From the foregoing, it is clear that the four-year prescriptive period commences to run
neither from the date of the registration of the deed sought to be rescinded nor from
the date the trial court rendered its decision but from the day it has become clear that
there are no other legal remedies by which the creditor can satisfy his claims.
[Emphases in the original]

In all, it is incorrect for ASB to argue that a complaint need not allege all the elements
constituting its cause of action since it would simply adduce proof of the same during
trial. "Nothing is more settled than the rule that in a motion to dismiss for failure to
state a cause of action, the inquiry is "into the sufficiency, not the veracity, of the
material allegations."28 The inquiry is confined to the four comers of the complaint,
and no other.29 Unfortunately for ASB, the Court finds the allegations of its complaint
insufficient in establishing its cause of action and in apprising the respondents of the
same so that they could defend themselves intelligently and effectively pursuant to
their right to due process. It is a rule of universal application that courts of justice are
constituted to adjudicate substantive rights. While courts should consider public policy
and necessity in putting an end to litigations speedily they must nevertheless
harmonize such necessity with the fundamental right of litigants to due process.

WHEREFORE, the petition is DENIED.

SO ORDERED.
157 in LRC Case No. R-5475 in a petition for the issuance of writ of possession
FIRST DIVISION thereof way back on October 23, 1997 (Rollo, p. 22). Despite the lawful order of a
coordinate and co-equal court, the respondent Judge, presiding Regional Trial Court
of Pasig, Branch 71, issued the questioned orders to restore possession to private
respondent Chan, alleging an obviously grave abuse of discretion, tantamount to lack
[G. R. No. 141851. January 16, 2002] of jurisdiction (Rollo, p. 38).

On the same date on December 8, 1997, the temporary restraining order (TRO) was
issued, the Court Sheriff IV Cresencio Rabello, Jr. implemented the TRO and
DIRECT FUNDERS HOLDINGS CORPORATION, petitioner, vs. JUDGE CELSO D. submitted the Return on December 9, 1997 (Rollo, p. 39).
LAVIA, PRESIDING JUDGE OF RTC- PasigCity, Branch 71 and KAMBIAK
Y. CHAN, JR., respondents. Then, on January 21, 1998, the respondent Judge issued the questioned order
granting the issuance of a writ of preliminary injunction (Rollo, p. 14) who
DECISION subsequently denied the petitioners motion to dismiss and supplemental motion to
dismiss and the very urgent motion for reconsideration on February 16, 1998.
PARDO, J.:
On May 29, 1998, the motion for inhibition and the motion to dissolve the writ of
preliminary injunction were also denied (Rollo, p. 18).[5]
The Case
On August 5, 1998, petitioner filed with the Court of Appeals a petition for certiorari
and prohibition assailing the trial courts issuance of a writ of preliminary injunction. [6]
The petition at bar[1] seeks to review the decision[2] of the Court of
On September 28, 1999, the Court of Appeals promulgated a decision dismissing
Appeals[3] dismissing the petition assailing the ruling of the trial court issuing a writ of
the petition ruling that the trial court had jurisdiction to issue the injunction that did not
preliminary injunction that restrained a writ of possession issued by a coordinate
interfere with the writ of possession of a coordinate court.[7]
court.[4]
On October 19, 1999, petitioner filed with the Court of Appeals a motion for
reconsideration of the decision.[8]
The Facts On February 2, 2000, the Court of Appeals denied petitioners motion stating that
the arguments advanced were mere reiteration and restatements of those contained in
their pleadings x x x.[9]
The facts, as found by the Court of Appeals, are as follows:
Hence, this appeal.[10]
It is alleged by the petitioner that the respondent Judge issued the writ of preliminary
injunction, despite clear and express prayer in the Amended Complaint (Rollo, p. 23)
that private respondent Kambiak Y. Chan, Jr. sought the issuance of a writ of The Issue
preliminary mandatory injunction. This is again despite the fact this error was brought
to respondent Judges attention denied the Motion for Reconsideration on May 29,
1998 justifying the issuance thereof due to petitioners alleged misappreciation of facts The issue raised is whether the Court of Appeals erred in affirming the trial courts
and reliefs sought for. ruling issuing a writ of injunction restraining a writ of possession in another case to
place respondent back in possession of the subject property.
Culled from the records of the case, the action a quo is for annulment of
documents, reconveyance, recovery of possession, damages with application for the In other words, the issue is who between petitioner and respondent Kambiak Y.
issuance of a writ of preliminary mandatory injunction and temporary restraining Chan, Jr. has a better right to the possession of the subject property?
order.

During the hearing for the issuance of temporary restraining order, it was made clear The Courts Ruling
to the respondent Judge that the property in question was occupied by the petitioner
by virtue of a writ of possession issued by the Regional Trial Court of Pasig, Branch
We resolve the issue in favor of petitioner. 2. The Deed of Assignment dated 15 January 1997 executed by UCPB
Savings Bank (formerly United Savings Bank) whereby it conveyed its
The conditional sale agreement was the only document that the respondent rights as mortgagee in favor of the petitioner.
presented during the summary hearing of the application for a temporary restraining
order before the Regional Trial Court, Branch 71, Pasig City.[11] 3. The Deed of Assignment of Right of Redemption dated 15 January 1997,
executed by the Sps. Espino wherein they assigned their right of
We find that the conditional sale agreement is officious and ineffectual. First, it redemption over the subject property to UCPB Savings Bank and the
was not consummated. Second, it was not registered and duly annotated on the latters successors-in-interest.
Transfer Certificate of Title (No. 12357) covering the subject property. Third, it was
executed about eight (8) years after the execution of the real estate mortgage over the 4. The Certificate of Sale dated 29 May 1997 executed by the sheriff, the
subject property. affidavit of consolidation of ownership dated July 1997 (denominated as
Doc. No. 490; Page No. 99. Book No. CLVII, Series of 1997 in
To emphasize, the mortgagee (United Savings Bank) did not give its consent to the Notarial Books of Erlinda B. Espejo, Notary Public for Quezon City)
the change of debtor. It is a fundamental axiom in the law on contracts that a person and TCT No. 8559-R subsequently issued to Petitioner.
not a party to an agreement cannot be affected thereby. Worse, not only was the
conditional sale agreement executed without the consent of the mortgagee-creditor, 5. The Order dated 23 October 1997 of Branch 157, RTC, Pasig City (LRC
United Savings Bank, the same was also a material breach of the stipulations of the No. R-5475) and the Turn-over/Delivery of Possession of the sheriff in
real estate mortgage over the subject property.The real estate mortgage, in part, the said LRC case.
provides:
In Soriano v. Bautista,[13] the Deed of Real Estate Mortgage dated May 30,
1956 executed by the mortgagors contained a stipulation giving the mortgagee the
(j) The MORTGAGOR shall neither lease the mortgaged property/ies, nor sell or option to purchase the land subject of the mortgage on any date within the 2-year period
dispose of the same in any manner, without the written consent of the of the mortgage. The mortgagee subsequently decided to buy the land pursuant to this
MORTGAGEE.However, if notwithstanding this stipulation and during the existence of stipulation. We ruled:
this mortgage, the property/ies herein mortgaged, or any portion thereof, is/are leased
or sold, x x x.It shall also be incumbent upon the MORTGAGOR to make it a condition
of the sale or alienation that the vendee, or any other party in whose favor the Appellants contend that, being mortgagors, they cannot be deprived of the right to
alienation is made, shall recognize as first lien the existing mortgage or encumbrance redeem the mortgaged property, because such right is inherent in and inseparable
in favor of the MORTGAGEE, as well as any new modified mortgage covering the from this kind of contract. The premise of the contention is not entirely accurate. While
same properties to be executed by said MORTGAGOR in favor of the MORTGAGEE, the transaction is undoubtedly a mortgage and contains the customary stipulation
and shall thereafter agree, promise and bind himself to recognize and respect any concerning redemption, it carries the added special provision aforequoted, which
extension of the terms of the original mortgage granted by the MORTGAGEE in favor renders the mortgagors right to redeem defeasible at the election of the
of the MORTGAGOR and such extended mortgage shall be considered as prior to mortgages. There is nothing illegal or immoral in this. It is simply an option to buy,
such encumbrance as the original mortgage. It is also further understood that should sanctioned by Article 1479 of the Civil Code, which states: A promise to buy and sell a
the MORTGAGOR sell, transfer or in any manner alienate or encumber the determinate thing for a price certain is binding upon the promisor if the promise is
mortgaged property/ies in violation of this agreement, he/she shall be liable for supported by a consideration distinct from the price. [14]
damages to the MORTGAGEE.[12]
In view of all of the foregoing, it is inexorable to conclude that petitioner, not the
The conditions of the conditional sale agreement were not fulfilled, hence, respondent, has a better right to the possession of subject property.
respondents claim to the subject property was as heretofore stated ineffectual. Article
1181 of the Civil Code reads:
The Judgment
Art. 1181. In conditional obligations, the acquisition of rights, as well as the
extinguishments or loss of those already acquired, shall depend upon the happening
of the event which constitutes the condition. WHEREFORE, the Court hereby REVERSES the decision of the Court of
Appeals[15] and the order denying reconsideration.
On the other hand, petitioners right to the subject property is based on the
In lieu thereof, the Court renders judgment dismissing the case below, Civil Case
following:
No. 66554 of the Regional Trial Court, Branch 71, Pasig City, including the
1. The real estate mortgage constituted by the Sps. Espino duly registered counterclaims.
and annotated on TCT No. 12357 covering the subject property.
No costs. SO ORDERED.
their properties were washed away in the evening of 26 October and the early hours
Republic of the Philippines of 27 October 1978.3
SUPREME COURT
Manila
In their Answers, the defendants, now petitioners, alleged that: 1) the NPC exercised
due care, diligence and prudence in the operation and maintenance of the
THIRD DIVISION hydroelectric plant; 2) the NPC exercised the diligence of a good father in the
selection of its employees; 3) written notices were sent to the different municipalities
of Bulacan warning the residents therein about the impending release of a large
volume of water with the onset of typhoon "Kading" and advise them to take the
G.R. Nos. 103442-45 May 21, 1993 necessary precautions; 4) the water released during the typhoon was needed to
prevent the collapse of the dam and avoid greater damage to people and property; 5)
in spite of the precautions undertaken and the diligence exercised, they could still not
NATIONAL POWER CORPORATION, ET AL., petitioners, contain or control the flood that resulted and; 6) the damages incurred by the private
vs. respondents were caused by a fortuitous event or force majeure and are in the nature
THE COURT OF APPEALS, GAUDENCIO C. RAYO, ET AL., respondents. and character of damnum absque injuria. By way of special affirmative defense, the
defendants averred that the NPC cannot be sued because it performs a purely
The Solicitor General for plaintiff-appellee. governmental function.4

Ponciano G. Hernandez for private respondents. Upon motion of the defendants, a preliminary hearing on the special defense was
conducted. As a result thereof, the trial court dismissed the complaints as against the
NPC on the ground that the provision of its charter allowing it to sue and be sued
does not contemplate actions based on tort. The parties do not, however, dispute the
fact that this Court overruled the trial court and ordered the reinstatement of the
DAVIDE, JR., J.: complaints as against the NPC.5

This is a petition for review on certiorari under Rule 45 of the Revised Rules of Court Being closely interrelated, the cases were consolidated and trial thereafter ensued.
urging this Court to set aside the 19 August 1991 consolidated Decision of the Court
of Appeals in CA.-G.R. CV Nos. 27290-931 which reversed the Decision of Branch 5
of the then Court of First Instance (now Regional Trial Court) of Bulacan, and held The lower court rendered its decision on 30 April 1990 dismissing the complaints "for
petitioners National Power Corporation (NPC) and Benjamin Chavez jointly and lack of sufficient and credible evidence."6 Consequently, the private respondents
severally liable to the private respondents for actual and moral damages, litigation seasonably appealed therefrom to the respondent Court which then docketed the
expenses and attorney's fees. cases as CA-G.R. CV Nos. 27290-93.

This present controversy traces its beginnings to four (4) separate complaints 2 for In its joint decision promulgated on 19 August 1991, the Court of Appeals reversed
damages filed against the NPC and Benjamin Chavez before the trial court. The the appealed decision and awarded damages in favor of the private respondents. The
dispositive portion of the decision reads:
plaintiffs therein, now private respondents, sought to recover actual and other
damages for the loss of lives and the destruction to property caused by the inundation
of the town of Norzagaray, Bulacan on 26-27 October 1978. The flooding was CONFORMABLY TO THE FOREGOING, the joint decision
purportedly caused by the negligent release by the defendants of water through the appealed from is hereby REVERSED and SET ASIDE, and a new
spillways of the Angat Dam (Hydroelectric Plant). In said complaints, the plaintiffs one is hereby rendered:
alleged, inter alia, that: 1) defendant NPC operated and maintained a multi-purpose
hydroelectric plant in the Angat River at Hilltop, Norzagaray, Bulacan; 2) defendant 1. In Civil Case No. SM-950, ordering defendants-appellees to pay,
Benjamin Chavez was the plant supervisor at the time of the incident in question; 3) jointly and severally, plaintiffs-appellants, with legal interest from
despite the defendants' knowledge, as early as 24 October 1978, of the impending the date when this decision shall become final and executory, the
entry of typhoon "Kading," they failed to exercise due diligence in monitoring the following:
water level at the dam; 4) when the said water level went beyond the maximum
allowable limit at the height of the typhoon, the defendants suddenly, negligently and
recklessly opened three (3) of the dam's spillways, thereby releasing a large amount A. Actual damages, to wit:
of water which inundated the banks of the Angat River; and 5) as a consequence,
members of the household of the plaintiffs, together with their animals, drowned, and
1) Gaudencio C. Rayo, Two Hundred Thirty One 1) Actual damages of One Hundred Ninety Nine Thousand One
Thousand Two Hundred Sixty Pesos Hundred Twenty Pesos (P199,120.00);
(P231,260.00);
2) Moral Damages of One Hundred Fifty Thousand Pesos
2) Bienvenido P. Pascual, Two Hundred Four (P150,000.00);
Thousand Five Hundred Pesos (P204.500.00);
B. Plaintiff-appellant Norberto Torres:
3) Tomas Manuel, One Hundred Fifty Five
Thousand Pesos (P155,000.00); 1) Actual damages of Fifty Thousand Pesos (P50,000.00);

4) Pedro C. Bartolome, One Hundred Forty 2) Moral damages of Fifty Thousand Pesos (P50,000.00);
Seven Thousand Pesos (P147,000.00);.
C. Plaintiff-appellant Rodelio Joaquin:
5) Bernardino Cruz, One Hundred Forty Three
Thousand Five Hundred Fifty Two Pesos and
Fifty Centavos (P143,552.50); 1) Actual damages of One Hundred Thousand
Pesos (P100,000.00);
6) Jose Palad, Fifty Seven Thousand Five
Hundred Pesos (P57,500.00); 2) Moral damages of One Hundred Thousand
Pesos (P100,000.00); and
7) Mariano S. Cruz, Forty Thousand Pesos
(P40,000.00); D. Plaintifsf-appellants litigation expenses of Ten Thousand Pesos
(P10,000.00);
8) Lucio Fajardo, Twenty nine Thousand Eighty
Pesos (P29,080.00); and 4. In Civil case No. SM-1247, ordering defendants-appellees to pay,
jointly and severally, with legal interest from the date when this
decision shall have become final and executory :
B. Litigation expenses of Ten Thousand Pesos (P10,000.00);
A. Plaintiffs-appellants Presentacion Lorenzo and Clodualdo
2. In Civil case No. SM-951, ordering defendants-appellees to pay Lorenzo:
jointly and severally, plaintiff-appellant, with legal interest from the
date when this decision shall have become final and executory, the
following : 1) Actual damages of Two Hundred Fifty Six
Thousand Six Hundred Pesos (P256,600.00);
A. Actual damages of Five Hundred Twenty
Thousand Pesos (P520,000.00);. 2) Moral damages of Fifty Thousand Pesos
(P50,000.00);
B. Moral damages of five hundred Thousand
Pesos (P500,000.00); and. B. Plaintiff-appellant Consolacion Guzman :

C. Litigation expenses of Ten Thousand Pesos 1) Actual damages of One Hundred forty
(P10,000.00);. Thousand Pesos (P140,000.00);

3. In Civil Case No. SM-953, ordering defendants-appellees to pay, 2) Moral damages of Fifty Thousand Pesos
jointly and severally, with legal interest from the date when this (P50,000.00);
decision shall have become final and executory;
C. Plaintiff-appellant Virginia Guzman :
A. Plaintiff-appellant Angel C. Torres:
1) Actual damages of Two Hundred Five Hundred thereby giving no sufficient allowance for the reservoir to contain
Twenty Pesos (205,520.00); and the rain water that will inevitably be brought by the coming typhoon.

D. Plaintiffs-appellants litigation expenses of Ten Thousand Pesos On October 24, 1978, before typhoon "Kading" entered the
(10,000.00). Philippine area of responsibility, water elevation ranged from
217.61 to 217.53, with very little opening of the spillways, ranging
In addition, in all the four (4) instant cases, ordering defendants- from 1/2 to 1 meter. On October 25, 1978, when typhoon "Kading"
appellees to pay, jointly and severally, plaintiffs-appellants attorney entered the Philippine area of responsibility, and public storm signal
fees in an amount equivalent to 15% of the total amount awarded. number one was hoisted over Bulacan at 10:45 a.m., later raised to
number two at 4:45 p.m., and then to number three at 10:45 p.m.,
water elevation ranged from 217.47 to 217.57, with very little
No pronouncement as to costs.7 opening of the spillways, ranging from 1/2 to 1 meter. On October
26, 1978, when public storm signal number three remained hoisted
The foregoing judgment is based on the public respondent's conclusion that the over Bulacan, the water elevation still remained at its maximum
petitioners were guilty of: level of 217.00 to 218.00 with very little opening of the spillways
ranging from 1/2 to 2 meters, until at or about midnight, the
. . . a patent gross and evident lack of foresight, imprudence and spillways were suddenly opened at 5 meters, then increasing swiftly
negligence . . . in the management and operation of Angat Dam. to 8, 10, 12, 12.5, 13, 13.5, 14, 14.5 in the early morning hours of
The unholiness of the hour, the extent of the opening of the October 27, 1978, releasing water at the rate of 4,500 cubic meters
spillways, And the magnitude of the water released, are all but per second, more or less. On October 27, 1978, water elevation
products of defendants-appellees' headlessness, slovenliness, and remained at a range of 218.30 to 217.05 (Civil Case No. SM-950,
carelessness. The resulting flash flood and inundation of even Exhibits "D" and series, "L", "M", "N", and "O" and Exhibits "3" and
areas (sic) one (1) kilometer away from the Angat River bank would "4"; Civil Case No. SM-951, Exhibits "H" and "H-1"; Civil Case No.
have been avoided had defendants-appellees prepared the Angat SM-953, Exhibits "I" and "I-1"; Civil Case No. SM 1247, Exhibits "F"
Dam by maintaining in the first place, a water elevation which would and "F-1").
allow room for the expected torrential rains.8
xxx xxx xxx
This conclusion, in turn, is anchored on its findings of fact, to wit:
From the mass of evidence extant in the record, We are convinced,
As early as October 21, 1978, defendants-appellees knew of the and so hold that the flash flood on October 27, 1978, was caused
impending onslaught of and imminent danger posed by typhoon not by rain waters (sic), but by stored waters (sic) suddenly and
"Kading". For as alleged by defendants-appellees themselves, the simultaneously released from the Angat Dam by defendants-
coming of said super typhoon was bannered by Bulletin Today, a appellees, particularly from midnight of October 26, 1978 up to the
newspaper of national circulation, on October 25, 1978, as "Super morning hours of October 27,
Howler to hit R.P." The next day, October 26, 1978, said typhoon 1978.9
once again merited a headline in said newspaper as "Kading's Big
Blow expected this afternoon" (Appellee's Brief, p. 6). Apart from The appellate court rejected the petitioners' defense that they had sent "early warning
the newspapers, defendants-appellees learned of typhoon "Kading' written notices" to the towns of Norzagaray, Angat, Bustos, Plaridel, Baliwag and
through radio announcements (Civil Case No. SM-950, TSN, Calumpit dated 24 October 1978 which read:
Benjamin Chavez, December 4, 1984, pp. 7-9).
TO ALL CONCERN (sic):
Defendants-appellees doubly knew that the Angat Dam can safely
hold a normal maximum headwater elevation of 217 meters Please be informed that at present our reservoir (dam) is full and
(Appellee's brief, p. 12; Civil Case No. SM-951, Exhibit "I-6"; Civil that we have been releasing water intermittently for the past several
Case No. SM-953, Exhibit "J-6"; Civil Case No. SM-1247, Exhibit days.
"G-6").
With the coming of typhoon "Rita" (Kading) we expect to release
Yet, despite such knowledge, defendants-appellees maintained a greater (sic) volume of water, if it pass (sic) over our place.
reservoir water elevation even beyond its maximum and safe level,
In view of this kindly advise people residing along Angat River to Case No. SM-950, TSN, Benjamin Chavez, December 4, 1984, pp.
keep alert and stay in safe places. 7-11 and TSN, Leonardo Nepomuceno, March 7, 1985, pp. 10-12).

Said notice is Bineffectual, insufficient and inadequate for purposes


of the openingEof the spillway gates at midnight of October 26, 1978
and on October N 27, 1978. It did not prepare or warn the persons so
served, for theJ volume of water to be released, which turned out to
be of such magnitude,
A that residents near or along the Angat River,
even those one M (1) kilometer away, should have been advised to
evacuate. Said I notice, addressed "TO ALL CONCERN (sic)," was
delivered to a Npoliceman (Civil Case No. SM-950, pp. 10-12 and
Exhibit "2-A") Lfor the municipality of Norzagaray. Said notice was
not thus addressed
. and delivered to the proper and responsible
officials who could
C have disseminated the warning to the residents
directly affected.
H As for the municipality of Sta. Maria, where
plaintiffs-appellants
A in Civil Case No. SM-1246 reside, said notice
does not appearV to have been served.11
E
Relying on Juan F. Nakpil & Sons Z vs. Court of Appeals,12 public respondent rejected
P
the petitioners' plea that the incident in question was caused by force majeure and
o to the private respondents for any kind of damage
that they are, therefore, not liable
such damage being in the nature w of damnum absque injuria.
e
r
The motion for reconsideration filed
P by the13petitioners, as well as the motion to modify
judgment filed by the public respondents,
l were denied by the public respondent in
14
its Resolution of 27 December 1991.a
n
Petitioners thus filed the instant tpetition on 21 February 1992.
S
After the Comment to the petition u was filed by the private respondents and the Reply
p We gave due course to the petition on 17 June
thereto was filed by the petitioners,
1992 and directed the parties toesubmit their respective Memoranda, 15 which they
subsequently complied with. r
i
n
The petitioners raised the following
t errors allegedly committed by the respondent
Court : e
n
I. THE COURT d OF APPEALS ERRED IN APPLYING THE RULING
OF NAKPIL &eSONS V. COURT OF APPEALS AND HOLDING
n
THAT PETITIONERS WERE GUILTY OF NEGLIGENCE.
t
1
II. THE COURT
0 OF APPEALS ERRED IN HOLDING THAT THE
WRITTEN NOTICES OF WARNING ISSUED BY PETITIONERS
WERE INSUFFICIENT.
because:
III. THE COURT OF APPEALS ERRED IN HOLDING THAT THE
Said notice was delivered to the "towns of Bulacan" on October 26, DAMAGE SUFFERED BY PRIVATE RESPONDENTS WAS
1978 by defendants-appellees driver, Leonardo Nepomuceno (Civil NOT DAMNUM ABSQUE INJURIA.
IV. THE COURT OF APPEALS ERRED IN NOT AWARDING THE The principle embodied in the act of God doctrine strictly requires
COUNTERCLAIM OF PETITIONERS FOR ATTORNEY'S FEES that the act must be one occasioned exclusively by the violence of
AND EXPENSES OF LITIGATION.16 nature and all human agencies are to be excluded from creating or
entering into the cause of the mischief. When the effect, the cause
These same errors were raised by herein petitioners in G.R. No. 96410, of which is to be considered, is found to be in part the result of the
entitled National Power Corporation, et al., vs. Court of Appeals, et al.,17 which this participation of man, whether it be from active intervention or
Court decided on 3 July 1992. The said case involved the very same incident subject neglect, or failure to act, the whole occurrence is thereby
of the instant petition. In no uncertain terms, We declared therein that the proximate humanized, as it were, and removed from the rules applicable to
cause of the loss and damage sustained by the plaintiffs therein who were similarly the acts of God. (1 Corpus Juris, pp. 1174-1175).
situated as the private respondents herein was the negligence of the petitioners,
and that the 24 October 1978 "early warning notice" supposedly sent to the affected Thus it has been held that when the negligence of a person concurs
municipalities, the same notice involved in the case at bar, was insufficient. We thus with an act of God in producing a loss, such person is not exempt
cannot now rule otherwise not only because such a decision binds this Court with from liability by showing that the immediate cause of the damage
respect to the cause of the inundation of the town of Norzagaray, Bulacan on 26-27 was the act of God. To be exempt from liability for loss because of
October 1978 which resulted in the loss of lives and the destruction to property in both an act of God, he must be free from any previous negligence or
cases, but also because of the fact that on the basis of its meticulous analysis and misconduct by which that loss or damage may have been
evaluation of the evidence adduced by the parties in the cases subject of CA-G.R. CV occasioned. (Fish & Elective Co. v. Phil. Motors, 55 Phil. 129;
Nos. 27290-93, public respondent found as conclusively established that indeed, the Tucker v. Milan, 49 O.G. 4379; Limpangco & Sons v. Yangco
petitioners were guilty of "patent gross and evident lack of foresight, imprudence and Steamship Co., 34 Phil. 594, 604; Lasam v. Smith, 45 Phil. 657). 21
negligence in the management and operation of Angat Dam," and that "the extent of
the opening of the spillways, and the magnitude of the water released, are all but Accordingly, petitioners cannot be heard to invoke the act of God or force majeure to
products of defendants-appellees' headlessness, slovenliness, and escape liability for the loss or damage sustained by private respondents since they,
carelessness."18 Its findings and conclusions are biding upon Us, there being no the petitioners, were guilty of negligence. The event then was not occasioned
showing of the existence of any of the exceptions to the general rule that findings of exclusively by an act of God or force majeure; a human factor negligence or
fact of the Court of Appeals are conclusive upon this Court. 19 Elsewise stated, the imprudence had intervened. The effect then of the force majeure in question may
challenged decision can stand on its own merits independently of Our decision in be deemed to have, even if only partly, resulted from the participation of man. Thus,
G.R. No. 96410. In any event, We reiterate here in Our pronouncement in the latter the whole occurrence was thereby humanized, as it were, and removed from the laws
case that Juan F. Nakpil & Sons vs. Court of Appeals20 is still good law as far as the applicable to acts of God.
concurrent liability of an obligor in the case of force majeure is concerned. In
the Nakpil case, We held:
WHEREFORE, for want of merit, the instant petition is hereby DISMISSED and the
Consolidated Decision of the Court of Appeals in CA-G.R. CV Nos. 27290-93 is
To exempt the obligor from liability under Article 1174 of the Civil AFFIRMED, with costs against the petitioners.
Code, for a breach of an obligation due to an "act of God," the
following must concur: (a) the cause of the breach of the obligation
must be independent of the will of the debtor; (b) the event must be SO ORDERED.
either unforseeable or unavoidable; (c) the event must be such as
to render it impossible for the debtor to fulfill his obligation in a
moral manner; and (d) the debtor must be free from any
participation in, or aggravation of the injury to the creditor. (Vasquez
v. Court of Appeals, 138 SCRA 553; Estrada v. Consolacion, 71
SCRA 423; Austria v. Court of Appeals, 39 SCRA 527; Republic of
the Phil. v. Luzon Stevedoring Corp., 21 SCRA 279; Lasam v.
Smith, 45 Phil. 657).

Thus, if upon the happening of a fortuitous event or an act of God,


there concurs a corresponding fraud, negligence, delay or violation
or contravention in any manner of the tenor of the obligation as
provided for in Article 1170 of the Civil Code, which results in loss
or damage, the obligor cannot escape liability.

S-ar putea să vă placă și