Documente Academic
Documente Profesional
Documente Cultură
Installation instruction
Installation procedures
Confirm project Check drawing
Install ducts
3. Piping installation
4. Electrical wiring
5. Commission
6. Main tools
VRF system installation
Plummet
Plumb bob
Indoor unit 2.Hoisting
Use level meter to keep the indoor unit horizontally .
Reduce the running noise
Avoid the condensate water spill from the water collector
Level meter
Indoor unit 2.Hoisting
1000mm
1000mm 1000mm
150-500mm 150-500mm
Outdoor unit 1.Location
If 2 rows of ODUs:
We recommend all the outdoor units installed on the same level if the project
site conditions permit.
Outdoor unit 2.Foundation making
The foundation can be made of channel steel or concrete.
Reserve the space for discharging condensate water from outdoor units.
Outdoor unit 2.Foundation making
Rubber anti-vibration pads are necessary to avoid vibration.
Rubber Pads
VRF system installation
Piping installation
Piping 0.Pipe storing
For storing the copper pipes:
1. If pipes will be used soon, nozzle should be sealed by plastic bag or tape.
2. If pipes will be stored for a long time, the pipes should be charged into
0.2~0.5MPa Nitrogen and the nozzle should be sealed by welding.
Piping 1.Procedures
Piping check
Pipes connection
Flushing
Gas-tightness test
Insulation
Vacuum dry
La Lb Lc Ld
LA LB
L1
L8 L9
L6 L7
f g h i j
L2
L4 L5
L3
a b c d e
Ld+LA+LB+L1+L2+L3+L4+L5+e 190 m
Piping 2.Piping check
The longest pipe length from 1st branch to farthest indoor unit 40 m
La Lb Lc Ld
LA LB
L1
L8 L9
L6 L7
f g h i j
L2
L4 L5
L3
a b c d e
L2+L3+L4+L5+e 40 m
Piping 2.Piping check
Height difference between outdoor unit and indoor unit 90 m
Height difference between indoor units 15 m
La Lb Lc Ld
LA LB
L1
L8 L9
L6 L7
f g h i j
L2
90m 15m
L4 L5
L3
a b c d e
Piping 2.Piping check
Select the correct branch joints according to the installation requirement.
Piping 3.Pipe hanging
The distance between the supports of the copper pipes.
Diameter (mm) 20 20 ~ 40 40
When the liquid pipe and gas pipe are hung up together, it is determined by
the diameter of liquid pipe.
Record the actual liquid pipe length for future reference when charging
additional refrigerant.
Piping 3.Pipe connection
The branch joint of outdoor side must be installed horizontally.
The branch joint of indoor side can be installed horizontally or vertically.
Horizontally Horizontally
Vertically Vertically
Piping 3.Pipe connection
When install the branch joint horizontally
A direction
Wrong
Correct
Avoid refrigerant distribution
15
unbalance.
15
Horizontal
Piping 3.Pipe connection
Keep enough distance:
1. Between two branch joints 1m
2. Between branch joints and indoor unit 0.5m
3. From the inlet or outlet of branch joint, there should be straight pipe
with length at least 0.5m
0.5m
Piping 3.Pipe connection
Why?
Do not replace branch joint with T pipe or use the branch joint from other suppliers
->DEKON branch joint is necessary
Piping 3.Pipe connection
Requirement of welding:
When welding the copper pipe, nitrogen is necessary to protect the copper pipe.
The pressure of the nitrogen is 0.02 MPa
Charge the nitrogen to the copper pipe at the beginning of welding and only
when the copper is fully cooled down, the nitrogen can be removed
Piping 3.Pipe connection
Why the Nitrogen is necessary?
High temp.
2Cu + O2 CuO
Piping 3.Pipe connection
How to charge Nitrogen.
Note
1. When flushing one pipe, the other pipes need to be sealed.
2. After flushing, remember to seal all the pipes.
Piping 5.Gas-tightness test
Purpose: check the gas leakage of the system
Procedures:
Caution: the gas used must be Nitrogen, but Nitrogen is forbidden to charge
to the outdoor units stop valve directly.
Piping 5.Gas-tightness test
Sequence of pressure test:
Purpose:
Prevent condensate
Protect people from
water adhere to the Avoid energy loss.
hurt of high temp.
gas pipe
Caution: After finish the gastight test, we go on the insulation work of the
refrigerant pipe.
Piping 6.Insulation
Insulation material
6.4~15.9mm 15mm
15.9~38.1mm 20mm
38.1~54.1mm 25mm
The insulation work must be done to every part of the refrigerant pipes
Piping 6.Insulation
Block the nozzle of the pipe when crossing the insulation material.
Wrong
Copper pipe
Insulation
Piping 7.Vacuum
Purposeremove the air and water in the system.
Necessary toolsvacuum pump (displacement: 4L/s or more)
Vacuum degree: less than -755mmHg(-0.1MPa)
With check
valve
Piping 7.Vacuum
Vacuum steps:
Liquid side
Make sure the gastight test, vacuum dry, pipe installation has
2 been finished
UP
R410A
Note:
1. Charging excessive refrigerant will cause liquid harmer.
2. Record the actual amount of additional refrigerant for further reference.
Piping 8.Charge refrigerant
Additional refrigerant charged volume:
R410A
Liquid pipe Size
kg/m
6.4 0.022
9.5 0.059
12.7 0.120
15.9 0.180
19.1 0.260
22.2 0.370
25.4 0.450
Calculate the additional refrigerant according to the diameter and the length
of all liquid pipes connecting to outdoor and indoor units.
Piping 9.Drainage pipe
Selection steps:
V 14 25 3.0
14 V 88 30 3.5
88 V 175 40 4.0
334 V 80 6.0
Piping 9.Drainage pipe
Cautionthe lean of main drainage pipe must be bigger than 1%
Exhaust outlet
1%
Condensate pipe
Note
1. If the lean 1%then select drainage pipe with bigger diameter
2. The drainage pipe should be independent with other water pipe
3. Never put the drainage pipe together with dirty water pipe
Piping 9.Drainage pipe
Discharge drainage water naturally (without drainage pump):
50mm
50mm
plug
Main drainage pipe
Electrical wiring
Wiring 0.Procedures
SW01
1 2 Description
OFF OFF Master unit
OFF ON Slave 1
ON OFF Slave 2
ON ON Slave 3
SW02
1 2 Definition
OFF OFF Dual DC Fan
OFF ON DC fan left, AC fan right
ON OFF AC fan right, DC fan left
ON ON Dual AC Fan
Wiring 1.DIP switch setting
Outdoor unit capacity setting
Check the unit capacity setting match the nameplate through DIP switch SW03
SW03
1 2 3 Capacity
OFF OFF OFF 8HP
OFF OFF ON 10HP
OFF ON OFF 12HP
OFF ON ON 14HP
ON OFF OFF 16HP
ON OFF ON 18HP
ON ON OFF 20HP
Wiring 1.DIP switch setting
Outdoor unit type setting
SW04
1 2 3 Definition
OFF OFF OFF DRV
(Factory default)
Wiring 1.DIP switch setting
the quantity of outdoor and indoor unit lock setting
Lock the quantity of outdoor and indoor unit through DIP switch SW05
SW05
1 2 3 Definition
OFF OFF OFF Unlock
(Factory default)
ON OFF ON Lock
Wiring 1.Address setting
Indoor address setting by Remote controller
Methold
Press [Sleep] button 8 times within 5
seconds to enter into the interface of
Indoor unit address remote parameter change;
NO.
All wires, and electric devices must All wiring work must be done by
be conformed to local standards qualified person
Basic requirement
Creepage breaker
/Manual switch
3-Phase
380/400/415V
Notice:
All the indoor units which connected to one outdoor system must be connected to
the same power supply
Wiring 2.Power supply
Why should all the indoor units which combined in one system have same power
supply?
System is normally running.
Some indoor units lose power (plug out or power supply failure) .
These indoor units stop, but built-in expansion valves still keep former
opening degree, they cant close.
The outdoor units and other indoor units are still running.
The liquid refrigerant flow into the stopped indoor units.
This units evaporator will freeze, because their fans are stopped .
And the other indoor units can not get enough refrigerant distribution, so the
cooling performance drop down.
Even worse, the liquid refrigerant will directly suck back the compressor, which
cause liquid hammer, damage the compressor.
Wiring 2.Power supply
Creepage breaker selection
According to 1.5-2 times of the total rated current.
Manual switch selection
As the power is supplied independently, selecting the manual switch and
fuse capacity according to the total capacity.
Total capacity of outdoor units (HP) Manual switch (A) Fuse (A)
10~14 100 75
15~18 100 100
19~28 150 150
29~36 200 200
37~47 300 250
48~50 300 300
5264 400 400
Wiring 2.Power supply
L N
Indoor unit
Controller
Wiring 3.Signal wire
Between outdoor units in one combination
Between outdoor unit and indoor unit
3. Non-polar communication
4. Series connection
Wiring 3.Signal wire
Key points
Commission
Commission 1.Check before start
Check valves
Commission 1.Check before start
Check valves
Commission 1.Check before start
Check valves
Commission 1.Check before start
Check valves
Commission 1.Check before start
Error check
Trial operation
Operation test
Hand to user
Commission 2.Check Operation
Preheat
Trial operation
Operation test
Hand to user
Commission 2.Check Operation
Preheat
Error check
Operation test
Hand to user
Commission 2.Check Operation
Preheat
Hand to user
Commission 2.Check Operation
Preheat
R410A
OD35/-,ID27/19 OD43/-,ID32/23
High pressure (MPa) 2.8~3.0 3.4~3.8
Low pressure (MPa) 0.85~1.0 1.0~1.45
Discharge temp.() 7080 /
Suction temp.() 1114 /
Indoor air outlet () 12~15 degree (T1 is around 21~27)
temp. difference 8~12
between return and
outlet (T)
Commission 2.Check Operation
Preheat
Error check
Trial operation
Operation test
Main tools
Main tools
Outlook Name Scope
5/16
Pressure gauge R410A
Check
valve
Vacuum pump R410A
Main tools
Outlook Name
Anemometer
acoustic meter
Main tools
Outlook Name
Infrared thermometer
Clamp meter
Main tools
Outlook Name
Torque spanner
Cutter
Main tools
Outlook Name
Electrodrill
Manual hydraulic
crimper
Thank you!