Sunteți pe pagina 1din 15

Stress Ribbon and Cable-supported Pedestrian Bridges

ISBN 978-0-7277-4146-2

ICE Publishing: All rights reserved


doi: 10.1680/srcspb.41462.155

Chapter 9
Cable-stayed structures

Cable-stayed structures have been described in several excellent vertical or inclined. Multi-span cable-stayed structures have
books (Gimsing, 1998; Mathivat, 1983; Menn, 1990; Podolny also been built. Special attention has to be paid to the deection
and Scalzi, 1976; Walther et al., 1998); only additional informa- of the deck and to the analysis of the dynamic response.
tion about structures formed by a slender deck is presented in
this chapter. It is possible to suspend only the main span and anchor the back
stays at short side spans or anchor blocks (Figure 9.3(a)). The
9.1. Structural arrangement optimum span length of the side spans is from 0.40 to 0.45 of
As described in Chapter 2, a cable-stayed structure is formed by a the length of the main span. The length depends on the arrange-
slender deck that is suspended on stay cables anchored in the ment of the stay cables and side supports. If the deck has an
tower and deck (Figures 2.6(b) and 2.6(d)). The elevation of the expansion joint between the side and approach spans, the struc-
deck can therefore have an optimum arrangement corresponding ture requires a shorter side span and that backstays be anchored
to local conditions. The structures can have one or more spans. (Figure 9.3(b)).

It is possible to anchor back stays in the soil and create a totally If the structure is continuous, the side spans can be longer and
or partially earth-cable-stayed structure. For economical stay cables symmetrical to the tower can be extended into the
reasons, this solution makes sense only in special cases or for approach spans (Figure 9.3(c)). The cable-stayed structure can
structures of long spans. The prevailing portion of cable- be signicantly stiffened by supports situated in side spans
stayed structures is formed by self-anchored systems that (Figure 9.3(d)).
stress the footings by vertical reactions only (Figure 9.1).
Stay cables can have different arrangements as shown in Figure
Classic cable-stayed structures have two or three spans that are 9.4. While a statically superior radial arrangement (Figure
suspended on one or two towers (Figure 9.2). The towers can be 9.4(a)) brings structural difculties in relation to the anchoring

Figure 9.1 Neckar River Bridge, Germany

155

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Stress Ribbon and Cable-supported Pedestrian Bridges

Figure 9.2 Arrangement of the cable-stayed structure Figure 9.4 Arrangement of the stay cables

(a)

(b)

>0.6L
arrangements can be combined to create the most suitable
(c) (d) solution (Figure 9.6).

To reduce the bending moments in the deck it is necessary to


anchor stay cables at a relatively short distance (36 m). The
bending moments due to dead load are then very low and the
of all stays at one point (Figure 2.39), a statically less advanta- deck can be very slender (from 0.30 m).
geous parallel arrangement (Figure 9.4(b)) simplies structural
details. A semi-radial arrangement (Figure 9.4(c)) represents a If the towers have sufcient height (0.2L), the stiffness of the
reasonable compromise both from a static and structural cable-stayed structure is given by the stiffness of the system
point of view. formed by compressed masts and deck and by a tension
stiffness of the stay cables (Figure 9.7). If low towers are
The relatively light load of pedestrian bridges justies the designed, the structure requires sufcient bending stiffness of
solution presented in Figures 9.4(d) and 9.5. The basic the deck.

Figure 9.3 Cable-stayed structure length of the side spans Cable-stayed structures do not usually utilise increasing stiff-
ness of the structural system by anchoring the deck at the abut-
(a) ments (Figure 2.20). However, the advantage of restricting the
0.20L horizontal movement at the abutments was demonstrated by
Menn in the design of the Sunniberg Bridge. The bridge,
which has ve spans of length from 59 to 134 m, is curved in
Lk L Lk plan with a curvature radius R 503 m. The slender deck
running at 60 m above grade is suspended on pylons protruding
(b) 15 m above the deck.
0.20L

Figure 9.5 Badhomburg Bridge, Germany (courtesy of Schlaich,


Bergermann and Partners)
0.40L L 0.40L

(c)
0.20L

0.45L L 0.45L

(d)
0.20L

Ls Ls L Ls Ls

156

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Cable-stayed structures

Figure 9.6 Zidlochovice Bridge, Czech Republic Figure 9.8 Sunniberg Bridge, Switzerland, tower: (a) cross-section,
(b) longitudinal section, (c) transverse bending moments and (d)
longitudinal bending moments

The deck can be totally suspended on the stay cables or can be


The stiffness of the structure comes from the plan curvature of
supported at towers. The deck can be also frame connected with
the deck, which is xed at the abutments (Figure 9.9(a)). While
tower legs. At the towers, the cables can be deviated at the
vertical deection of the deck of traditional multi-span cable-
saddles (Figure 2.37(a)), anchored at anchor plates (Figure
supported structures has to be controlled by intermediate
2.37(b)) or they can overlap and be anchored at blocks
anchor piers or by bending stiffness of the deck; in this bridge
(Figures 2.37(c) and 9.10).
the vertical deformation of the deck is controlled by the trans-
verse stiffness of the curved deck. Any vertical load causes the
The deck is usually suspended on two planes of cables: vertical
horizontal movement of the deck that acts in the horizontal
or inclined. Suspension in the bridge axis requires a torsionally
plane as an arch (Figure 9.9). The transverse movement of the
stiff girder. Suspension in two inclined planes creates a feeling of
deck creates transverse moments in the piers forming transverse
safety (Figure 9.11), while suspension in one central plane can
frames (Figure 9.8(c)).
naturally divide cyclists from pedestrians (Figure 9.12).
A similar increase in the stiffness is used in the authors design
of the Bohumin Pedestrian Bridge (Section 11.3). Figure 9.9 Sunniberg Bridge, Switzerland: (a) calculation model
and (b) cross-section of the deck
The towers can be made from concrete or steel. They can be
formed by individual columns, or they can be H-, V- or A-
shaped. The possible arrangement of the cable-supported struc-
tures in the transverse direction is discussed in Section 2.2
(Figures 2.24 and 2.25).

Figure 9.7 Cable-stayed structure: (a) classical and (b) extradosed

157

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Stress Ribbon and Cable-supported Pedestrian Bridges

Figure 9.10 Zidlochovice Bridge, Czech Republic Figure 9.12 Bohumin Bridge, Czech Republic: suspension on one
central plane of stay cables

In cable-stayed structures of common spans, the concrete deck Figure 9.13 Cable-stayed structure supported by stay cables: (a)
guarantees the transverse stiffness. Although the outward one stay and (b) multiple stays
inclination of the stay cables increases the transverse stiffness
and inward inclination increases the torsion stiffness of the
system, the increase is not signicant. However, these structures
do not vibrate in pure transverse modes; all transverse modes
are accompanied with distortion of the deck that contributes
to the stiffness of the system.

The possible arrangements of the structure supported by stay cables


is presented in Figure 9.13. However, an elegant solution with one
upright (Figure 9.14) requires a relatively stiff deck. A slender
deck with several uprights shown in Figure 9.13(b) is, compared
with self-anchored suspension structures, too complicated.

Figure 9.11 Bohumin Bridge, Czech Republic: suspension on two


inclined planes of stay cables Figure 9.14 Osormort Bridge, Catalonia, Spain (courtesy of Carlos
Fernandez Casado, SL, Madrid)

158

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Cable-stayed structures

Figure 9.15 Pin connection of the stay cable The stay cables developed from the prestressing tendons are
formed by individual bars, parallel bars, parallel wires or prestres-
sing strands (Figure 2.31(b)). They can easily be assembled on the
site. Typical arrangement of the cable is shown in Figure 9.16.
Q

Due to large fatigue stresses that originate in stay cables, all


details are designed in such a way that the forces in the cables
can be adjusted and it is possible to progressively exchange
M the cables (AASHTO, 1997).

Due to the deformation of the deck and towers, relatively large


bending moments originate at the anchors of the stay. It is
Q reasonable to reduce these local moments and transfer the
critical moment from anchors.

Many designers assume that the pin connection of the stay cable
The stay cables situated above the deck are usually suspended eliminates bending stresses in the stay cable. Pin connection can
on cables developed by steel or prestressed concrete industry eliminate local bending caused by an erection misalignment, but
(Figure 2.31). In the rst application, the stay cables were also cannot eliminate bending stresses caused by service load. The
formed by prestressed concrete ties or walls (Figure 2.40). A rotation of the pin is caused by a shear force and corresponding
similar arrangement can be used for cables situated under the bending moment that stresses the cable. Rotation occurs only
deck. when rotation overcomes pin friction. The shear force that
rotates the pin stresses the cable. It is therefore necessary to
The stay cables can be formed by spiral strands, locked coil design the cable for corresponding local moment and/or
strands or parallel wires (Figure 2.31(a)). They are factory design a measure that reduces the bending.
tted with a combination of socket types to enable load trans-
mittal between the structure and the cable (Figure 2.32) and 9.2. Erection of the structures
are delivered on site in design length. The socket also enables The process of cable-stayed structure erection has to guarantee
a pin connection of the stays with the deck and tower (Figure that the forces in the stay cables, together with post-tensioning
9.15). of the deck, balance the effects of the dead load.

Figure 9.16 Typical arrangement of the stay cable

dead end anchorage

guide pipe
transition pipe

neoprene boot

adjustable stressing anchorage with


threaded anchor head and ring nut

159

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Stress Ribbon and Cable-supported Pedestrian Bridges

Figure 9.17 Erection of the deck on a falsework Figure 9.18 Erection of the deck in a cantilever

tensioned and in a design shape. The bars were anchored in


temporary erection struts that also guarantee the design sag
(Section 11.3). This procedure guarantees that the stays were
stressed by design forces.

The main advantage of cable-stayed structures is that they can


be progressively erected in self-anchored cantilevers indepen-
Cable-supported structures can be assembled from precast dently of the terrain under the bridge (Figure 9.18). They can
members or can be cast-in-place on the falsework. However, be assembled from precast segments or cast in movable travel-
the structural arrangement of a cable-stayed structure calls for lers. Precast segments can be lifted by a winch supported by a
the erection in free cantilevers in which the effects of the dead beam anchored to the deck. However, the beam or traveller
load are resisted by stay cables (Mathivat, 1983; Podolny and can cause relatively large bending moments in a slender deck.
Scalzi, 1976; Podolny and Muller, 1982). It is therefore suitable to suspend the beam or traveller on an
erection stay cable and transfer the load directly to the tower
If the structure is cast in place, the cables are usually installed (Figure 9.18). The connection between the traveller and
after the deck is completed. Since the tensioning of one cable already cast deck has to transfer the horizontal component of
(Figure 9.17) inuences the tension in all other cables which the cable force.
have already been tensioned, it is necessary to design an adjust-
ment of their tension. In the construction of Hungerford Bridge Figure 9.19 shows a traveller that was used in the construction
(London, UK) the stay cables, formed from bars, were installed of Diepoldsau Bridge, built across the Rhone River in

Figure 9.19 Erection of the Diepoldsau Bridge, Switzerland: (a) elevation, (b) partial elevation and (c) cross-section

(a)

(b) (c)
A erection B
load

Section BB A Section AA B

160

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Cable-stayed structures

Figure 9.20 Zidlochovice Bridge, Czech Republic: (a) elevation, (b) connection of the longitudinal and transverse members and
(c) longitudinal normal stresses in the deck

(a)

(b) MH (c)

H
PH

LG TM LG TM LG TM
Pv WTM
longitudinal girder (LG)
transverse member (TM)

Mv

Switzerland (Walther et al., 1998). The bridge of maximum span Erection eccentric transverse post-tensioning of the joints
97.00 m was formed by a solid slab of an average thickness of between longitudinal and transverse members solved the rst
0.45 m; the deck was cast in segments of length 6.00 m. The problem (Figure 9.20(b)). The transverse members were
traveller was suspended on the nal stay cables that also provided with steel brackets with nuts and screws situated on
served as erection cables. The horizontal component of the the surface close to their ends. After a transverse member was
cable force was resisted by precast edge girders in which the erected, the screws were drawn until their heads touched the
stay cables were also anchored. To guarantee the linear behav- longitudinal girders. The post-tensioning bars were then
iour of the cable, it was necessary to load the traveller by a partially tensioned. The couple of the forces acting on the
temporary load that was progressively unloaded during the girder (under the screw head and bar anchor) created a
casting of the segment. moment that balanced the torsion.

The deck can also be erected from two longitudinal precast edge The second problem was solved by the design process of
girders and transverse solid slab members connected by longitu- erection of the deck that was designed in such a way that the
dinal and transverse post-tensioning. Figure 9.20 shows a prestress of the longitudinal girders is larger then the prestress
bridge built across the Svratka River in the Czech Republic of the transverse members. Since the joints between the trans-
which is suspended on an inclined tower. verse members were cast after the erection of the deck, the
main compression caused by stay cables loads only the edge
The design of the bridge has addressed two special problems: girders. The deck was successively erected in 5 m long parts.
elimination of torsion of the longitudinal girders during the The process of the assembly was as follows (Figure 9.21).
erection of the structure and determination of the level of the
post-tensioning of the longitudinal girders and transverse 1. The edge longitudinal girders were erected; each new
members in such a way that the redistribution of stresses girder was post-tensioned to the same value as the pre-
between them is a minimum (Strasky et al., 2002). viously erected girders (Figure 9.21(a)).

161

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Stress Ribbon and Cable-supported Pedestrian Bridges

Figure 9.21 Zidlochovice Bridge, Czech Republic: progressive erection of the deck

2. Stay cables were installed and tensioned to the prescribed resisted by a couple of forces originating in tubes and anchor
level (Figure 9.21(b)). plates.
3. Transverse members were erected and the joints between
the transverse members and the longitudinal girders were The precast deck of the I-5 Gateway Pedestrian Bridge was
post-tensioned (Figure 9.21(c)). erected in balanced cantilevers from the central tower (Figures
4. The forces in the stay cables were adjusted (Figure 9.22 and 9.25(a)). The closures and composite slab was also
9.21(d)). placed in balanced cantilevers directed away from the tower
(Figure 9.25(c)). After that, the suspended spans together with
For small pedestrian bridges, progressive casting of the deck in
movable travellers or erecting deck from precast match-cast
segments is too expensive. To simplify construction, a very
Figure 9.22 I-5 Gateway Bridge, Oregon, USA: segment erection
simple technology has recently been developed. This technology
was utilised in the construction of two pedestrian bridges built
in Eugene, Oregon (see Chapter 11). The deck of both bridges
was erected in cantilevers above busy highways (Figure 9.22).

To simplify production, the segments were not match-cast. To


allow cantilever erection, the segments were cast with
projecting structural tubes that mated with adjacent segments
(Figures 9.23 and 9.24). During the erection, the anchor plates
of the stays were bolted to erected segments. To guarantee the
stability of the erected cantilever, the anchor plates of the
stays are also bolted to the adjacent, previously erected
segments. To allow adjustment of the erected structure and
allow erection tolerances, there are elliptical slots in the plates
above adjacent segments. These bolts were tightened after
adjustment of the geometry. The bending moments were then

162

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Cable-stayed structures

Figure 9.23 I-5 Gateway Bridge, Oregon, USA: segment connection: (a) bridge elevation, (b) connection detail and (c) section AA

(a)

(b) (c)

curved spans were post-tensioned. The precast deck of the Delta Figure 9.25 I-5 Gateway Bridge, Oregon, USA: construction
Ponds Bridge was erected similarly; the precast segments were sequences: (a) erection of segments, (b) suspension of the closure
erected in the cantilever that was directed from the already- formwork and (c) casting of the joints, closures, composite deck slab
and subsequent deck prestressing
cast backspans.
(a)
Figure 9.24 Delta Ponds Bridge, Oregon, USA: connection detail

(b)

(c)

163

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Stress Ribbon and Cable-supported Pedestrian Bridges

Since the erected cantilevers form a stable system the individual Figure 9.27 Static function of the stay cable
cantilevers can also be cast on the falsework, subsequently
suspended on the towers and then rotated into the design pi
position. DaH

9.3. Static and dynamic analysis


Cable-stayed structures can be analysed similarly to suspension
DbV
structures as geometrically non-linear structures. The stay
cables can be modelled as suspension cables and the towers and g c0
deck by 3D bars or shell elements (Figure 9.26). However, the
gic = g c0 Ii / I0
larger stiffness of cable-stayed structures given by the height of
Ni
the towers and by an initial tension in the stay cables allows the ai
stay cables to be substituted by bars. If the tension stiffness of N0
a x
the deck is not utilised (Figure 2.20) the cable-stayed structure
can be analysed linearly and it is possible to use a superposition h0
of the static effects. The structure can then be analysed in two y
hi
steps. In the rst step, the stresses due to the dead load and b
prestress are determined. In the second step, the structure is
N0
analysed as common structures by linear programs. Since the DbV
cable-stayed structures form progressively erected hybrid bi
systems, the time-dependent analysis is mandatory.
Ni
DaH Ii
9.3.1 Stay cables I0
The stay cables that are anchored at towers and the deck behave
as cables that are loaded by their own weight and by deection
of their supports. Figure 9.27 shows deformation of anchor
points of the longest stay cable of the Elbe River Bridge Figure 9.28 Normal stresses in stay cables
(Figure 2.10). It is evident that the new position of the cable
(a) N
is inuenced mainly by a horizontal deformation of the tower
f
and vertical deection of the deck. Due to these deformations N cos f I0 /c
os b
the length of the cable, and consequently the stress in the
cable, have changed. f0
f
h0 = I0tgb D
To understand the function of the cable the following study was
done. Figure 9.28(a) depicts cables of length l0/cos  where l0 is b = 2253' f
N
60, 120 and 180 m. The cable was assembled of 0.600 strands of I0 = 60 m, 120 m, 180 m D H

N cos f
Figure 9.26 Modelling of the cable-stayed structure: (a) deck (b) fs f (m)
modelled by 3D bars and (b) deck modelled by shell elements
0.5fs,u 5.00
60
I0

0
0
=1

18
12

(a)
I0 =

=
80

0.4fs,u 4.00
I0
I0

N
0.3fs,u 3.00
I0 =

0.2fs,u 2.00
120

(b) 0.1fs,u 1.00


I0

f
=6
0

0.0 0.00
N
N 0.0 0.5 1.00 1.50 D (m)

stress fs fs,u = 1860 MPa


sag f

164

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Cable-stayed structures

modulus of elasticity Es 190 GPa. The cables were stressed by where Es is the modulus of elasticity of steel, fs is the stress in the
an initial stress: cable,  is the density of the cable and l is the horizontal span of
the cable.
fs,i 0.005fs,u 0.005  1860 93.0 MPa.
The forces in the stay cables vary according to the position and
The cables were then loaded by deection  that was increased intensity of the load. Figure 9.30 shows the two positions of the
in stepped increments of 0.05 m. The results of the analyses are live load which cause maximum stresses in the longest back stay
presented in Figure 9.28(b) where stresses in the cables fs and cable of the Elbe River Bridge. By linear analysis we can observe
corresponding sags f are plotted. that, due to the load situated in the main span, the cable is
stressed by tension due to the load situated in side spans by
It is evident that the studied cables behave almost linearly (the compression.
change of stress is linearly proportional to the change of the
deection) for the stresses fs > 0.1fs,u. This means that for It is evident that the initial cable tension has to be designed in
these stresses the stays can be modelled as pin-connected bars such a way that the maximum tension stresses are less than
(Figure 9.30). The common structures can be solved by linear permissible stresses and minimum tension has to be greater
programs. However, it is necessary to check that the stresses than the tension that guarantees the linear behaviour. The
in the cables lie within the range that guarantees their linear design of the initial tension is also inuenced by the redistribu-
behaviour. The same is true for structures in which the stay tion of stresses due to the creep and shrinkage of concrete. This
cables are situated under the deck. will be discussed further in Section 9.3.2.

For longer stay cables, the initial stresses have to be higher. The
non-linear behaviour is usually taken into account by using the
Figure 9.30 Stresses in stay cables: (a) dead load, (b) max tension,
so-called Ernst modulus Ei (Figure 9.29) (Ernst, 1965). (c) min tension and (d) allowable range of stresses
Es
Ei gc
l2 Es (a)
1 f
12fs3

Figure 9.29 Ernst modulus Ng

Ei /Es
(b) p
1.0
fs = 0.50fs,u
fs = 0.40fs,u p
xN
fs = 0.30fs,u ma
0.8

fs = 0.20fs,u
(c) p p
0.6
Np
fs = 0.15fs,u min

0.4
N
(d) fs
f max fs 0.45fs,u
fs = 0.10fs,u linear
0.2 fs,f behaviour
I
N
min fs

0.0
0 100 200 300 400 I (m) time

165

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Stress Ribbon and Cable-supported Pedestrian Bridges

Figure 9.31 Bending moments and shear forces in stay cables

Ng , N

Hg , H g = 0.0543 kN/m

26.00
Hg = 1336 kN Ng = 1450 kN
H = 1043 kN N = 2000 kN
Hg , H
61.60
Ng , N
26.00

61.60 u = 0.0452 m w = 0.1073 m f = 0.002 rad

M 5 10 kNm
Q kN

Stay cables are usually xed to the pylons and deck. Due to their This is the reason why modern stay cables have the arrangement
deformations, signicant bending and shear stresses originate at shown in Figure 9.16. The cables are usually strengthened at the
the stay anchors. Figure 9.31 shows the deformations and corre- anchor area and are guided by strong pipe which ends with a
sponding shear forces and bending moments that originate due neoprene ring. The neoprene ring, together with the pipe,
to the design live load in the longest stay cable of the Elbe creates a exible support (a spring) which reduces the local
Bridge (Figures 2.10, 4.11 and 4.12). Since corresponding bending moments.
stresses signicantly inuence the design of stay cables, it is
necessary to develop details that reduce them. As already discussed, the bending moments also originate at the
anchors that are pin connected (Figure 9.15).
Figure 9.32(a) shows a course of the bending moment and
bending stresses that originates in the vicinity of their anchors From the above it is evident that the maximum stresses that
in the stays that were loaded by rotation of the deck  0.002 originate in the cable are substantially inuenced by the
radians (Figure 9.31). The gure shows the bending moments bending of the cable. The designer should also check the
and stresses for (1) the stay cables of the constant cross- fatigue stresses that can originate in the stays (Figure 9.30(d)).
section and (2) the stay cable that is strengthened at anchors Although the national standards do not usually specify the
(Figure 4.12). It is evident that local strengthening causes the fatigue load, the designer should use an engineering judgement
bending moment to increase. The resultant bending stresses and consider a reasonable value of fatigue stresses when
are smaller, however. designing exible structures.

Figure 9.32(b) shows courses of the bending moment in the stay 9.3.2 Redistribution of stresses due to creep and
of the constant section (1) that is loaded by the same rotation. In shrinkage
this case, the stay is supported by a spring at a distance of 1.7 m The importance of the accurate determination of the stay force
from the anchor. The spring has a different stiffness that varies was discussed in Chapter 6. The redistribution of the stresses
from 0 to 500 MPa. It is evident that the bending moment can be was demonstrated on the example of a simple beam that, after
signicantly reduced and the peak of bending moment can be 14 days of curing, was suspended at mid-span on a vertical
transferred from the anchor to the spring. cable (Figure 6.8). It was shown that the initial force in the

166

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Cable-stayed structures

Figure 9.32 Bending of the cable: (a) influence of local cable (EsAs 1). Before suspending, a force
strengthening and (b) influence of support by a spring
N R/cos 
(a)
was created at the cable. R is a reaction at the inter-
M (kNm) fs (MPa) mediate support of a continuous beam of two spans of length
0 0 2  6 m.

1 10 A time-dependent analysis was performed using the CEB-FIP


2
(MC 90) creep function. In time, the bending moments are
2 20 redistributed from the anchor point to the span; at time
1
1 t1 100 years the moment at the anchor point is approxi-
1
3 2 30 mately 60% of the initial moment.
M
4 2 fs 40
Another analysis was also performed on the assumption that
there is no shrinkage in the beam. In this case, the redistribution
is very small (Figure 9.33(b)).
5 50
0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
x (m) A time-dependent analysis was also completed for the structure
(b)
in which the initial force was increased by 10% (Figure 9.33(c)).
M (kNm) k (MPa) The value of the redistribution of bending moments was similar
1
to the redistribution of moments shown in Figure 9.33(a), but
k = 500 the nal value was closer to the bending moment that
0
corresponds to the force N R/cos .
k = 100
1 Figure 9.33(d) presents the results of the analysis in which the
k = 50 force in the stay cable was adjusted after one year. The redistri-
2 = 10
k bution of moments was signicantly reduced; at time t1 100
x years the moment at the anchor point is approximately 80% of
3 k=0 the initial moment.
f = 0.002 rad

4 It is evident that the redistribution of moments can reach sig-


0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 nicant values. However, note that in the structures with a
x (m) slender deck which is suspended on multiple stay cables, the
bending moments due to the dead load are (compared to the
bending moment due to the live load and temperature
changes) very small.
stay cable has to correspond to the reaction of a two-span
continuous beam and there is no redistribution of forces in To quantify the inuence of the redistribution of stresses in
time. However, the cable was vertical and therefore the beam actual cable-supported structures, a cable-stayed structure as
was not compressed. depicted in Figure 9.34 was studied. The goal of the study was
to determine optimum forces in the stay cables of progressively
Since the stay cables are inclined, they stress the beam by erected cable-stayed structures. Analyses were completed for a
normal forces. The normal stresses create horizontal deforma- non-composite and a composite deck of a different stiffness.
tions that, due to the creep of concrete, increase in time. Only the results of the analysis carried out for a slender deck
Shrinkage of concrete also causes horizontal deformations of are presented here.
the deck. The stay anchor horizontally moves and its initial
force is reduced. The change of the stay force causes a re- A parametric study was completed for a symmetrical cable-
distribution of stresses in the structure. stayed structure with radial arrangement of the stay cables.
To eliminate the inuence of the towers stiffness, the towers
To quantify this phenomenon, extensive studies were were modelled as movable bearings that can rotate and move
completed; only a few results are presented here. Figure in the horizontal direction of the bridge. Since the stay cables
9.33(a) depicts the same beam that was, after 14 days of have a symmetrical arrangement, the side spans are stiffened
curing, suspended at mid-span on a very stiff inclined stay by additional supports.

167

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Stress Ribbon and Cable-supported Pedestrian Bridges

Figure 9.33 Redistribution of bending moments in a two-span beam

(a) N = R/cos b (b) N = R/cos b


b b

M (MN m) M (MN m) ecs = 0


1.2 1.2

14 days
10 years 14 days
0.0 0.0

100 years 10 100 years


1.2 1.2
0 6 12 m 0 6 12 m

(c) N = 1.1R/cos b (d) N = 1.1R/cos b 14 days


b b 1 year

M (MN m) M (MN m)
1.2 1.2
14 days
14 days
10 years 1 year
0.0 0.0

100 years 10 100 years


1.2 1.2
0 6 12 m 0 6 12 m

Figure 9.34 Redistribution of bending moments in a cable-stayed structure

(a) (b)

0.60

24.00 36.00 126.00 36.00 24.00 15.00

(c)
M (MNm)
6.00
g + p + Dt end of the erection
g+p 100 years
4.00

2.00

0.00

2.00

4.00

g+p
6.00
g + p + Dt

8.00

126.00/2

168

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.


Cable-stayed structures

The structure was analysed for the effects of the dead and live engineering point of view) critical and can be accepted. The
loads given by the Czech standards and for temperature redistribution can also be notably reduced if the forces are
changes t 208C. The area of the cables was determined adjusted after one year.
from the conditions of max fs 4 0.45fs,u.
REFERENCES
The deck was progressively cast in 6 m long sections. It was AASHTO (1997) Guide specication for design of pedestrian
assumed that the traveller has a similar arrangement and bridges. AASHTO.
weight as the traveller used in the construction of the Ernst HJ (1965) Der E-Modul von Seilen unter Berucksichti-
Diepoldsau Bridge (Figure 9.19). The time-dependent analysis gung des Durchhanges. Bauingenieur, No. 2.
was done for a progressive erection in which one segment was Gimsing NJ (1998) Cable Supported Bridges: Concept &
completed (moving of the traveller, placing of the reinforce- Design. John Wiley & Sons, Chichester.
ment, casting of the segment and post-tensioning of the stay Mathivat J (1983) The Cantilever Construction of Prestressed
cable) within seven days. Concrete Bridges. John Wiley & Sons, New York.
Menn C (1990) Prestressed Concrete Bridges. Birkhauser
The forces in the stay cables were determined from several itera- Verlag, Basel.
tions. In the analysis, the structure was several times progres- Podolny W Jr and Scalzi JB (1976) Construction and Design of
sively demounted and erected in such a way that in the nal Cable Stayed Bridges. John Wiley & Sons, New York.
stage shown in Figure 9.34 (after the erection of the symmetric Podolny W and Muller J (1982) Construction and Design of
cantilevers) the forces in all stay cables were Ni Ri/cos  i. It is Prestressed Concrete Bridges. John Wiley & Sons, New
evident that after 100 years a signicant redistribution of the York.
bending moments has occurred. To quantify the value of the Strasky J, Navratil J and Susky S (2001) Applications of time-
redistribution, bending moment envelopes determined for live dependent analysis in the design of hybrid bridge struc-
load and temperature changes of t 208C are also shown. tures. PCI Journal 46(4): 5674.
It is evident that the dead load moments are (compared to Walther R, Houriet B, Walmar I and Moa P (1998) Cable
moments due to the live load) very small. It is therefore Stayed Bridges. Thomas Telford Publishing, London.
evident that the value of the redistribution is not (from the

169

Downloaded by [] on [25/09/17]. Copyright ICE Publishing, all rights reserved.

S-ar putea să vă placă și