REMARKS
ESTIMATE ON RE-ROUTING OF STRUCTURE FROM KK-203 TO 207
Unit Cost Original Scheme New Scheme
(Supply of Tower & associated
accessories/hardwares & Civil
QTY Cost QTY Cost
Works /Erection/Installation)
No. Of Structures 5 11
Steel Pole 7,701,285.84 - 1 7,701,286
60 long span tower 6,417,738.20 - -
60 compact tower 6,017,724.94 - -
45 long span tower 5,900,258.92 - 1 5,900,259
45 compact tower 4,721,574.96 1 4,721,575 1 4,721,575
15 long span tower 3,029,351.74 - 1 3,029,352
15 compact tower 3,102,070.92 1 3,102,071 -
5 long span tower 2,532,380.26 1 2,532,380 -
5 compact tower 2,722,495.52 - 2 5,444,991
2 compact tower 1,597,832.26 - 5 7,989,161
2 long span tower 1,597,832.26 2 3,195,665 -
TOTAL 13,551,691 34,786,624
Total Length (km) 1.34 1.57
ACSR 491,420.96 8.45 4,151,672 9.88 4,854,453
OPGW 380,542.12 1.41 535,822 1.65 626,525
OHGW 380,542.12 1.41 535,822 1.65 626,525
TOTAL 5,223,316 6,107,502
Additional Cost
Survey Works
Geotech. Works
Hardwares
REMARKS