Documente Academic
Documente Profesional
Documente Cultură
COMPUTER TECHNIQUES
4.1Introduction]4[
A number of different procedures have been developed to aid the facilities planner in
designing layouts. These procedures can be classified into two main categories:
construction type and improvement type. Construction type layout methods
basically involve developing a new layout from scratch.
Improvement procedures generate layout alternatives based on an existing
layout. Based on the above two procedures, many algorithmic approaches
have been developed.
Construction algorithm
Input requirements are as follows:
Relationship chart
Department areas
Sweep width
Arbitrarily selects first department
Allows fixed departments
First department selected randomly
Next department selected based on relationship with placed departments
If more than one with same relationship, choice is random
If no departments with minimally acceptable relationship exist, choice is
random
Place first department in the upper left corner and extend downward
Additional departments begin where the previous one ended
Sweep width < area of smallest department
1
Why?
1 grid = 5 m2
Sweep width = 3
Start laying out departments top-down and left to right, when you came to border
continue laying out bottom-up and left to right...
2
Dept. 3 (conf. room) is selected due to E rating with 1
3
Dept. 6 (general storage) is selected due to A rating with 5
Total score of the final layout is computed using the following values: A= 64, E=16,
I=4, O=1, U=0, X=-1024, and only fully adjacent departments take points
4
4.1.2 CORELAP(3)
1. The first department placed in the layout is the one with the greatest TCR
value. If a tie exists, choose the one with more As.
2. If a department has an X relationship with he first one, it is placed last in the
layout. If a tie exists, choose the one with the smallest TCR value.
5
3. The second department is the one with an A relationship with the first one. If
a tie exists, choose the one with the greatest TCR value.
4. If a department has an X relationship with he second one, it is placed next-to-
the-last or last in the layout. If a tie exists, choose the one with the smallest
TCR value.
5. The third department is the one with an A relationship with one of the placed
departments. If a tie exists, choose the one with the greatest TCR value.
6. The procedure continues until all departments have been placed.
Consider the figure on the right. Assume that a department is placed in the
middle (position 0). Then, if another department is placed in position 1, 3, 5
or 7, it is fully adjacent with the first one. It is placed in position 2, 4, 6 or
8, it is partially adjacent.
For each position, Weighted Placement (WP) is the sum of the numerical
values for all pairs of adjacent departments.
The placement of departments is based on the following steps:
1. The first department selected is placed in the middle.
2. The placement of a department is determined by evaluating all possible
locations around the current layout in counterclockwise order
beginning at the western edge.
3. The new department is located based on the greatest WP value.
6
4.2.4 Example
7
8
4.5 CRAFT (Computerized Relative Allocation of Facilities
Technique)(2)
First computer-aided layout algorithm (1963)
The input data is represented in the form of a From-To chart, or qualitative
data.
The main objective behind CRAFT is to minimize total transportation cost:
9
Find the cost of the initial layout by multiplying the
From-To (flow) chart,
Unit cost matrix, and
From-To (distance) matrix
Improve the layout by performing all-possible two or three-way exchanges
At each iteration, CRAFT selects the interchange that results in the
maximum reduction in transportation costs
These interchanges are continued until no further reduction is possible
Total movement cost = (20 x 15) + (20 x 10) + (40 x 50) + (20 x 20) + (20 x 5)
+ (20 x 10) = 3200
Solution :
10
The possible interchanges for the initial layout are:
1. A B interchanging
Movement Cost = (20 x 15) + (30 x 10) + (10 x 50) + (10 x 20) + (30 x 5)
+ (20 x 10) = 1650
The reduction in movement cost = 3200 1650 = 1550
2. A C interchanging
11
gxC = [ (100)5 + (200)10 ] /300 = 8.33
Movement Cost = (10 x 15) + (20 x 10) + (10 x 50) + (23.34 x 20) + (20 x 5)
+ (30 x 10) = 1716.8
The reduction in movement cost = 3200 1716.8 = 1483.2
With this layout new pair wise interchanges are attempted as follows :
12
A D, B C, C D
A B not considered since it will result no savings
A C not considered since they dont have common borders
B D not considered since they dont have common borders
So, the current layout is the best layout that CRAFT can find
Improvement type
13
From-To chart as input
Distance based objective function (rectilinear distances between centroids).
Improvements: Two way exchanges and steepest descent
MULTIPLE can exchange departments that are not adjacent to each other.
The layout is divided into grids
Space Filling Curves are generated so that the curve touches each grid in the
layout.
A layout vector (DEO) is specified and the departments are added to the
layout using the layout vector.
To exchange departments, the positions of the departments in the layout vector
are exchanged.
Solution :
Cost = 100*20*0.1 + 10*10*0.1 + 5*10*0.1 + 25*10*0.1 + 25*10*0.1 + 10*10*0.1
+100*20*0.1 = 475
15
1. First Iteration
2. First Iteration
16
406. MULTIPLE vs. CRAFT
Multi-floor capabilities
17