Documente Cultură
3
Total PRSB Indirect 6
No Trade Pax
1 Fabrication Superintendent 0
2 Project Manager 1
3 Project Engineer 0
4 Construction Superintendent 1
5 Planning Engineer 0
6 Structural Engineer 0
7 HSE Engineer 1
8 QA/QC Engineer 0
9 Commissioning Engineer 1
10 HSE/Safety Promoter** 0
11 QA/QC Inspector 1
12 Matco 0
13 Safety Officer 1
14 General Supervisor 0
15 Fabrication Foreman 0
16 Admin 0
17 Painting Inspector 0
18 Document Controller 0
19 Materials Inspector 0
Total PCSB 3
No Trade Pax
1 PCSB PMT** 0
2 PCSB Material Controller** 0
3 PCSB HUC Engineer 3
4
No Equipment/ Capacity Qty
1 Fitter - Tools of Trade 1
2 Welder - Tools of Trade 0
3 Rigger - Tools of Trade 7
4 Blaster/ Painter - Tools of Trade 0
5 Instrument Fitter - Tools of Trade 2
6 Generator - 150 kVA 0
7 Generator - 250 kVA 0
8 Welding Machine - Diesel (Portable) 0
9 Welding Machine - Elec. Rectifier 0
10 LP Gas Heater 0
11 Ventilator/Blower 12" 0
12 Ventilator/Blower 16" 0
13 Mobile Crane 0
14 Forklift 0
5 INST
Previous Cumulative
Platform
Planned Actual
6
Hours Previous Today
Weather 0 0
Gen Set 0 0
Welding Machine 0 0
Accessories 0 0
Compressor 0 0
Concurrent Activities 0 0
Unavailability of Personnel 0 0
To
10
11
1
2
3
4
5
6
12
1
2
3
SIGNATURE REPORT PREPARED BY
Date 2-Dec-16
PRSB-SOGT-ONS-DPR- 2 DATE: 1-Dec-16
HO/2012/DFHD/193
ROVISION FOR HOOK-UP, COMMISSIONNING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR 201
018
PROVISION FOR HOOK-UP AND COMMISSIONING FOR KEBABANGAN OIL PIPELINE (POP)
PROJECT
DAILY PROGRESS REPORT CUT-OFF TIME: 1400 HRS
eena Yeewae Rudzuan B Awang Teh Nur Atika A Latif Zaaba B Ali
aten Adawiyah M Zhafri B Nasarudin Siti Nadiah Bt Jamaludin Faizal Rosdi
ur Abcida Ahmad Puteri Mira Dayana M Syahrul Ridhwan Reynilda Bt Sius
areney Bt Yahaya Ammar Cendric-Alexander Masuil
Kamal Yosof Safwan
Zaid Siwok In'amulhassan
ayassin Mohd Nashar
mirul Fariz Mohd Hanif
GENERAL INFO & OVERALL PROGRESS
-16 Location Sabah Oil Gas Te
16 Days On Site 2 Days
% ACTUAL PROGRESS % 16.6
HEALTH, SAFETY AND ENVIRONMENT (HSE)
DAILY TOOL BOX MEETING HSE TOPICS DESCRIPTION OF IN
N/A N/A
KPI, 1 : 150 MHRS) BOT (KPI, 1 : 2000 MHRS) ZETO RULES AUDIT (KPI, 1 : 5000 M
Ratio Submission Ratio Submission
Cummulative Today Cumm. Cummulative Today Cumm.
1 : 38 0 0 1 : 2712 0 0
1 : 111 0 0 1: 803 0 0
1 : 112 0 0 1 : 1784 0 0
1 : 101 0 0 1 : 878 0 0
MAN-HOURS EXPENDITURE
an-Hours Expenditure Previous Today Cumulative
CSB Personnel 0 24 24
RSB Direct 0 96 96
RSB Indirect 0 48 48
d Party 0 0 0
Total Expended Manhours 0 168 168
MANPOWER LOADING
48 Total PRSB Direct
Hours No Trade
0 1 Welder
8 2 Fitter
0 3 Instrument Fitter
8 4 Milwright
0 5 Painter / Blaster
0 6 Rigger
8 7 Firewatcher
0 8 Scaffolder
8 9 Forklift Operator
0 10 Helper
8 11 Mechanic
0 12 Welder Foreman
8 13 Fitter Foreman
0 14 Rigger Foreman
0 15 Painting Foreman
0 16 Scaffolder Foreman
0 17 Crane Operator
0 18 UT Technician
0 MPI Technician
24 Total PCSB
Hours No Trade
0 4 PCSB HSE
0 5 PCSB Inspector
24
EQUIPMENT LOADING
Hours No Equipment/ Capacity
8 15 Semi Auto Pipe Cutter
0 16 Semi Auto Plate Cutter
56 17 Hydrotest Pump @ 6,000psi
0 18 Hydrotest Pump @ 10,000psi
16 19 Radial Drilling Machine
0 20 Electric Compressor - 375 cfm @ 120psi
0 21 Air Compressor - 375 cfm @ 120psi
0 22 Air Compressor - 830 cfm @ 125psi
0 23 Pressure Feed
0 24 Sand Blasting Set
0 25 After Cooler
0 26 Spray Eq. Airless Set
0 27 Extractor
0
INSTALLATION PROGRESS
SUMMARY OF PROGRESS
DOWNTIME SUMMARY
Cummulative Hours Previous Today
0 OIC Constraint / Mopu Contraint 0 0
0 Drilling Constraint 0 0
0 Marine Spread 0 0
0 Interrigging 0 0
0 Work Stoppages 0 0
0 Permit to Work (PTW) 0 0
0 Others 0 0
Total Downtime
Downtime Highlights
AREA OF CONCERN
AOC DESCRIPTION
MATERIAL STATUS
Description
ATTACHMENTS
MAYASSIN JININ
Zaaba B Ali
Faizal Rosdi
Reynilda Bt Sius
ESS
Sabah Oil Gas Terminal (SOGT)
Days
16.67%
(HSE)
DESCRIPTION OF INCIDENT (IF ANY)
N/A
PCSB 0 0
Trade Pax Hours
0 0
0 0
Ongoing
Cummulative
0
0
0
0
0
0
0
0
DATE
ACTION BY STATUS
RESOLVED
Remarks
TUS
Remarks
REPORT ACKNOWLEDGED BY
3
Total PRSB Indirect 6
No Trade Pax
1 Fabrication Superintendent 0
2 Project Manager 1
3 Project Engineer 0
4 Construction Superintendent 1
5 Planning Engineer 0
6 Structural Engineer 0
7 HSE Engineer 1
8 QA/QC Engineer 0
9 Commissioning Engineer 1
10 HSE/Safety Promoter** 0
11 QA/QC Inspector 1
12 Matco 0
13 Safety Officer 1
14 General Supervisor 0
15 Fabrication Foreman 0
16 Admin 0
17 Painting Inspector 0
18 Document Controller 0
19 Materials Inspector 0
Total PCSB 3
No Trade Pax
1 PCSB PMT** 0
2 PCSB Material Controller** 0
3 PCSB HUC Engineer 3
4
No Equipment/ Capacity Qty
1 Fitter - Tools of Trade 1
2 Welder - Tools of Trade 0
3 Rigger - Tools of Trade 7
4 Blaster/ Painter - Tools of Trade 0
5 Instrument Fitter - Tools of Trade 2
6 Generator - 150 kVA 0
7 Generator - 250 kVA 0
8 Welding Machine - Diesel (Portable) 0
9 Welding Machine - Elec. Rectifier 0
10 LP Gas Heater 0
11 Ventilator/Blower 12" 0
12 Ventilator/Blower 16" 0
13 Mobile Crane 0
14 Forklift 0
5 INST
Previous Cumulative
Platform
Planned Actual
6
Hours Previous Today
Weather 0 0
Gen Set 0 0
Welding Machine 0 0
Accessories 0 0
Compressor 0 0
Concurrent Activities 0 0
Unavailability of Personnel 0 0
To
10
11
1
2
3
4
5
6
12
1
2
3
SIGNATURE REPORT PREPARED BY
Date 1-Dec-16
PRSB-SOGT-ONS-DPR- 1 DATE: 30-Nov-16
HO/2012/DFHD/193
ROVISION FOR HOOK-UP, COMMISSIONNING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR 201
018
PROVISION FOR HOOK-UP AND COMMISSIONING FOR KEBABANGAN OIL PIPELINE (POP)
PROJECT
DAILY PROGRESS REPORT CUT-OFF TIME: 1400 HRS
eena Yeewae Rudzuan B Awang Teh Nur Atika A Latif Zaaba B Ali
aten Adawiyah M Zhafri B Nasarudin Siti Nadiah Bt Jamaludin Faizal Rosdi
ur Abcida Ahmad Puteri Mira Dayana M Syahrul Ridhwan Reynilda Bt Sius
areney Bt Yahaya Ammar Cendric-Alexander Masuil
Kamal Yosof Safwan
Zaid Siwok In'amulhassan
ayassin Mohd Nashar
mirul Fariz Mohd Hanif
GENERAL INFO & OVERALL PROGRESS
-16 Location Sabah Oil Gas Te
16 Days On Site 1 Days
% ACTUAL PROGRESS % 16.6
HEALTH, SAFETY AND ENVIRONMENT (HSE)
DAILY TOOL BOX MEETING HSE TOPICS DESCRIPTION OF IN
N/A N/A
KPI, 1 : 150 MHRS) BOT (KPI, 1 : 2000 MHRS) ZETO RULES AUDIT (KPI, 1 : 5000 M
Ratio Submission Ratio Submission
Cummulative Today Cumm. Cummulative Today Cumm.
0 0 0
0 0 0
Not Applicable at SOGT
0 0 0
0 0 0
MANPOWER LOADING
48 Total PRSB Direct
Hours No Trade
0 1 Welder
8 2 Fitter
0 3 Instrument Fitter
8 4 Milwright
0 5 Painter / Blaster
0 6 Rigger
8 7 Firewatcher
0 8 Scaffolder
8 9 Forklift Operator
0 10 Helper
8 11 Mechanic
0 12 Welder Foreman
8 13 Fitter Foreman
0 14 Rigger Foreman
0 15 Painting Foreman
0 16 Scaffolder Foreman
0 17 Crane Operator
0 18 UT Technician
0 MPI Technician
24 Total PCSB
Hours No Trade
0 4 PCSB HSE
0 5 PCSB Inspector
24
EQUIPMENT LOADING
Hours No Equipment/ Capacity
8 15 Semi Auto Pipe Cutter
0 16 Semi Auto Plate Cutter
56 17 Hydrotest Pump @ 6,000psi
0 18 Hydrotest Pump @ 10,000psi
16 19 Radial Drilling Machine
0 20 Electric Compressor - 375 cfm @ 120psi
0 21 Air Compressor - 375 cfm @ 120psi
0 22 Air Compressor - 830 cfm @ 125psi
0 23 Pressure Feed
0 24 Sand Blasting Set
0 25 After Cooler
0 26 Spray Eq. Airless Set
0 27 Extractor
0
INSTALLATION PROGRESS
SUMMARY OF PROGRESS
DOWNTIME SUMMARY
Cummulative Hours Previous Today
0 OIC Constraint / Mopu Contraint 0 0
0 Drilling Constraint 0 0
0 Marine Spread 0 0
0 Interrigging 0 0
0 Work Stoppages 0 0
0 Permit to Work (PTW) 0 0
0 Others 0 0
Total Downtime
Downtime Highlights
AREA OF CONCERN
AOC DESCRIPTION
MATERIAL STATUS
Description
ATTACHMENTS
MAYASSIN JININ
Zaaba B Ali
Faizal Rosdi
Reynilda Bt Sius
ESS
Sabah Oil Gas Terminal (SOGT)
Days
16.67%
(HSE)
DESCRIPTION OF INCIDENT (IF ANY)
N/A
PRSB Direct 12 96
Trade Pax Hours
0 0
1 8
2 16
0 0
7 56
0 0
0 0
0 0
0 0
0 0
0 0
0 0
1 8
0 0
1 8
0 0
0 0
0 0
PCSB 0 0
Trade Pax Hours
0 0
0 0
Ongoing
Cummulative
0
0
0
0
0
0
0
0
DATE
ACTION BY STATUS
RESOLVED
Remarks
TUS
Remarks
REPORT ACKNOWLEDGED BY
Internal
BACKLOADING 0.50 8.33%
DEMOBILISATION 1.00 16.67%
Prepared By
.
In'amulhassan bin Jamaludin
PRSB COMMISSIONING ENGINEER
Internal
Planned Start Planned Finish Overall Progress
Internal
4 December, 2016 4 December, 2016 0.00%
5 December, 2016 5 December, 2016 0.00%
PETRONAS CSR
Internal
PROJECT PROGRESS (Commissioning & Removal)
1.0 MOBILISATION (Commissioning & Removal)
2.0 COMMISSIONING
2.1 SYSTEM PREPARATION
KBB Oil Pipeline N2 displacement via 2' vent line at R-1310
Crude receiving system
Offspec receiving system
2.2 SCENARIO EVALUATION
Start-up mode and KOP Nitrogen displacement
Prolong offspec crude
Confirm crude onspec and handover
2.3 NITROGEN DISPLACEMENT AND SOGT START UP
KBB readiness for crude export and PIG launch
Vent Nitrogen at R-1310 using 2' flexible hose
Vent nitrogen using 1 inch vent (V1) line 200-PL-13163-151041XX
Vent nitrogen using 1 inch vent (V2) line 200-PL-13163-151041XX
Vent nitrogen using 1 inch vent (V3) line 350-PL-13015-151041XX
Vent nitrogen using 1 inch vent (V4) line 300-PL-13024-31001-20X via VX 13172 (inlet pipe PSV-13168A)
Vent nitrogen using 1 inch vent (V5) line (after FT-13120)
Vent nitrogen using 1 inch vent (V6) line 350-PL-15002-11001X
Confirm crude arrival to T-1510 and Crude sampling frequency for BS&W
Line up valve from offspec crude receiving to onspec crude receiving header
PIG arrival and retrieval
Prolong offspec crude from KBB
Stabilization of crude to on-spec tank for 6 hours
ESD Test
3. REMOVAL
3.1 Line No 200-PL-13163-151041X-N
Remove flange 1500# with quick coupling
Re-install Blind Flange 1500# DN25 (Existing)
3.2 Line No: 200-PL-13163-151XXX-N
Remove flange 1500# with quick coupling
Re-install Blind Flange 1500# DN20 (Existing)
3.3 Line No 350-PL-13021-31001-20X-N
Remove flange 300# with quick coupling
Re-install Blind Flange 300# DN20 (Existing)
3.4 Line No: 350-PL-13015-151041X-N
Remove flange 1500# with quick coupling
Re-install Blind Flange 1500# DN20 (Existing)
3.5 Line No: 300-PL-13024-31001-20X
Remove flange 300# with quick coupling
Re-install back Blind flange at valve VX13172 (Existing)
3.6 Line No: 300-PL-15002-11001X-N
Remove flange 150# with quick coupling
Re-install Blind Flange 150# DN20 (Existing)
Internal
3.7 Line No: 350-PL-13009-15104X-N
Remove DN50 150# flanged hose
Remove DN40 sampling connection 1500# A105N
Remove transition spool 1500# to 150# DN50
Reinstate back PG 13144 (Existing)
Re-install Blind flange DN40 (Existing)
Remove DN50 150# flanged hose
Remove transition spool 1500# to 150# DN50
Reinstate back PG 13141 (Existing)
BACKLOADING & HOUSEKEEPING
DEMOBILISATION
Prepared By
.
In'amulhassan bin Jamaludin
PRSB COMMISSIONING ENGINEER
Internal
Percentage
Original Duration Planned Start Planned Finish Overall Progress
(Planned)
23 December, 2016 31 December, 2016 0.00%
1.00 11.11% 23-Dec-16 23-Dec-16 0.00%
5.00 55.56% 24-Dec-16 28-Dec-16 0.00%
0.9 10.00% 24-Dec-16 24-Dec-16 0.00%
0.5 5.56% 24-Dec-16 24-Dec-16
0.2 2.22% 24-Dec-16 24-Dec-16
0.2 2.22% 24-Dec-16 24-Dec-16
0.6 6.67% 24-Dec-16 25-Dec-16 0.00%
0.2 2.22% 24-Dec-16 24-Dec-16
0.2 2.22% 25-Dec-16 25-Dec-16
0.2 2.22% 25-Dec-16 25-Dec-16
3.5 38.89% 25-Dec-16 29-Dec-16 0.00%
0.5 5.56% 25-Dec-16 25-Dec-16
0.1 1.11% 25-Dec-16 25-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.2 2.22% 26-Dec-16 26-Dec-16
0.3 3.33% 26-Dec-16 27-Dec-16
0.5 5.56% 27-Dec-16 27-Dec-16
0.3 3.33% 27-Dec-16 27-Dec-16
0.5 5.56% 28-Dec-16 28-Dec-16
0.5 5.56% 28-Dec-16 28-Dec-16
2 22.22% 29-Dec-16 30-Dec-16 0.00%
0.2 2.22% 29-Dec-16 29-Dec-16 0.00%
0.1 1.11% 29-Dec-16 29-Dec-16
0.1 1.11% 29-Dec-16 29-Dec-16
0.2 2.22% 29-Dec-16 29-Dec-16 0.00%
0.1 1.11% 29-Dec-16 29-Dec-16
0.1 1.11% 29-Dec-16 29-Dec-16
0.2 2.22% 29-Dec-16 29-Dec-16 0.00%
0.1 1.11% 29-Dec-16 29-Dec-16
0.1 1.11% 29-Dec-16 29-Dec-16
0.2 2.22% 29-Dec-16 29-Dec-16 0.00%
0.1 1.11% 29-Dec-16 29-Dec-16
0.1 1.11% 29-Dec-16 29-Dec-16
0.2 2.22% 29-Dec-16 29-Dec-16 0.00%
0.1 1.11% 29-Dec-16 29-Dec-16
0.1 1.11% 29-Dec-16 29-Dec-16
0.2 2.22% 30-Dec-16 30-Dec-16 0.00%
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
Internal
0.8 8.89% 30-Dec-16 30-Dec-16 0.00%
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.50 5.56% 31-Dec-16 31-Dec-16 0.00%
0.50 5.56% 31-Dec-16 31-Dec-16 0.00%