DAILY PROGRESS REPORT NO:

CONTRACT NO: CHO/2012/DFHD/193


PROVISION FOR HOO
CONTRACT TITLE:
2018
WO No: DFHD/2016/75A WO TITLE:
DAILY PROGR
Leena Yeewae
PCSB HUC / Faten Adawiyah
Copy To Attn
SBO Nur Abcida Ahmad
Mareney Bt Yahaya
M Kamal Yosof
M Zaid Siwok
Copy To PRSB Attn
Mayassin
Amirul Fariz
1
Start Date 30-Nov-16
Estimate Completion Date 5-Dec-16
PLANNED PROGRESS % 33.33%
2
DAILY HSE HIGHLIGHTS DAILY T
N/A

NON-LOST TIME INCIDENTS


Incidents Case Previous Today Cumulative Incidents
Near Miss 0 0 0 Fatality
Property Damage 0 0 0 Permanent Total Disabi
Damage to Enviroment 0 0 0 Permanent Partial Disa
Fire / Explosion 0 0 0 Lost Workday Case
First Aid Case 0 0 0 Total
Restricted Work Case 0 0 0 Remarks:
Medical Treatment Case 0 0 0 Lost Time Incident (LT
Total 0 0 0 Lost Time Incident (LT

UC/UA (KPI, 1 : 150 MHRS)


Submission
Company Manhours Today Cumm.
PCSB Staff 24 0 0
PRSB 144 0 0
3rd Party/Vendor/Sub-Contractor 0 0 0
Total 168 0 0

Project HSE Plan % (Weekly Update) 80.00% M


PTW Verification 0 Man-Hours Expenditu
PTW Submission 0 PCSB Personnel
PTW Verification : PTW Submission (KPI, 1 : 5 PTW) 1:4 PRSB Direct
PRSB Indirect
3rd Party
Total Expended Manh

3
Total PRSB Indirect 6
No Trade Pax
1 Fabrication Superintendent 0
2 Project Manager 1
3 Project Engineer 0
4 Construction Superintendent 1
5 Planning Engineer 0
6 Structural Engineer 0
7 HSE Engineer 1
8 QA/QC Engineer 0
9 Commissioning Engineer 1
10 HSE/Safety Promoter** 0
11 QA/QC Inspector 1
12 Matco 0
13 Safety Officer 1
14 General Supervisor 0
15 Fabrication Foreman 0
16 Admin 0
17 Painting Inspector 0
18 Document Controller 0
19 Materials Inspector 0
Total PCSB 3
No Trade Pax
1 PCSB PMT** 0
2 PCSB Material Controller** 0
3 PCSB HUC Engineer 3

4
No Equipment/ Capacity Qty
1 Fitter - Tools of Trade 1
2 Welder - Tools of Trade 0
3 Rigger - Tools of Trade 7
4 Blaster/ Painter - Tools of Trade 0
5 Instrument Fitter - Tools of Trade 2
6 Generator - 150 kVA 0
7 Generator - 250 kVA 0
8 Welding Machine - Diesel (Portable) 0
9 Welding Machine - Elec. Rectifier 0
10 LP Gas Heater 0
11 Ventilator/Blower 12" 0
12 Ventilator/Blower 16" 0
13 Mobile Crane 0
14 Forklift 0
5 INST

Previous Cumulative
Platform
Planned Actual

SOGT (Installation) 33.33% 16.67%

Overall Progress 33.33% 16.67%

6
Hours Previous Today
Weather 0 0
Gen Set 0 0
Welding Machine 0 0
Accessories 0 0
Compressor 0 0
Concurrent Activities 0 0
Unavailability of Personnel 0 0
To

No. Highlights Description


1
2
3
4

AOC NO AOC TYPE DATE RAISED

Package Description P.O. / S.O. Referen


9
SOGT

- Safety Induction of SOGT


- Safety Handling Of Chemical (SHOC) training
- e-PTW training for PTW applicant.

10

Ref. NO Date Sent Descri

11
1
2
3
4
5
6

12
1
2
3
SIGNATURE REPORT PREPARED BY

Name IN'AMULHASSAN BIN JAMALUDIN

Designation Commissioning Engineer, PRSB Cons


Signature

Date 2-Dec-16
PRSB-SOGT-ONS-DPR- 2 DATE: 1-Dec-16
HO/2012/DFHD/193
ROVISION FOR HOOK-UP, COMMISSIONNING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR 201
018
PROVISION FOR HOOK-UP AND COMMISSIONING FOR KEBABANGAN OIL PIPELINE (POP)
PROJECT
DAILY PROGRESS REPORT CUT-OFF TIME: 1400 HRS
eena Yeewae Rudzuan B Awang Teh Nur Atika A Latif Zaaba B Ali
aten Adawiyah M Zhafri B Nasarudin Siti Nadiah Bt Jamaludin Faizal Rosdi
ur Abcida Ahmad Puteri Mira Dayana M Syahrul Ridhwan Reynilda Bt Sius
areney Bt Yahaya Ammar Cendric-Alexander Masuil
Kamal Yosof Safwan
Zaid Siwok In'amulhassan
ayassin Mohd Nashar
mirul Fariz Mohd Hanif
GENERAL INFO & OVERALL PROGRESS
-16 Location Sabah Oil Gas Te
16 Days On Site 2 Days
% ACTUAL PROGRESS % 16.6
HEALTH, SAFETY AND ENVIRONMENT (HSE)
DAILY TOOL BOX MEETING HSE TOPICS DESCRIPTION OF IN
N/A N/A

LOST TIME INCIDENTS HSE ACTIVITY


Incidents Previous Today Cumulative Toolbox Meeting
atality 0 0 0 HSE Committee Meeting
ermanent Total Disability 0 0 0 HSE Walkabout
ermanent Partial Disability 0 0 0 Hygiene Inspection
ost Workday Case 0 0 0 Fire/Emergency Drill
otal 0 0 0 Drug & Alcohol Test
emarks: 0 0 0 Health Talk
Equipment/Machine
ost Time Incident (LTI) Frequency Rate 0
Inspection
ost Time Incident (LTI) Severity Rate 0 Touch The Heart Session

KPI, 1 : 150 MHRS) BOT (KPI, 1 : 2000 MHRS) ZETO RULES AUDIT (KPI, 1 : 5000 M
Ratio Submission Ratio Submission
Cummulative Today Cumm. Cummulative Today Cumm.
1 : 38 0 0 1 : 2712 0 0
1 : 111 0 0 1: 803 0 0
1 : 112 0 0 1 : 1784 0 0
1 : 101 0 0 1 : 878 0 0

MAN-HOURS EXPENDITURE
an-Hours Expenditure Previous Today Cumulative
CSB Personnel 0 24 24
RSB Direct 0 96 96
RSB Indirect 0 48 48
d Party 0 0 0
Total Expended Manhours 0 168 168

MANPOWER LOADING
48 Total PRSB Direct
Hours No Trade
0 1 Welder
8 2 Fitter
0 3 Instrument Fitter
8 4 Milwright
0 5 Painter / Blaster
0 6 Rigger
8 7 Firewatcher
0 8 Scaffolder
8 9 Forklift Operator
0 10 Helper
8 11 Mechanic
0 12 Welder Foreman
8 13 Fitter Foreman
0 14 Rigger Foreman
0 15 Painting Foreman
0 16 Scaffolder Foreman
0 17 Crane Operator
0 18 UT Technician
0 MPI Technician
24 Total PCSB
Hours No Trade
0 4 PCSB HSE
0 5 PCSB Inspector
24

EQUIPMENT LOADING
Hours No Equipment/ Capacity
8 15 Semi Auto Pipe Cutter
0 16 Semi Auto Plate Cutter
56 17 Hydrotest Pump @ 6,000psi
0 18 Hydrotest Pump @ 10,000psi
16 19 Radial Drilling Machine
0 20 Electric Compressor - 375 cfm @ 120psi
0 21 Air Compressor - 375 cfm @ 120psi
0 22 Air Compressor - 830 cfm @ 125psi
0 23 Pressure Feed
0 24 Sand Blasting Set
0 25 After Cooler
0 26 Spray Eq. Airless Set
0 27 Extractor
0
INSTALLATION PROGRESS

SUMMARY OF PROGRESS

ous Cumulative Cumulative To Date Completion REMAR


Variance Planned Actual Variance Date

-16.66% 33.33% 16.67% -16.66% 5-Dec Ongoi

-16.66% 33.33% 16.67% -16.66%

DOWNTIME SUMMARY
Cummulative Hours Previous Today
0 OIC Constraint / Mopu Contraint 0 0
0 Drilling Constraint 0 0
0 Marine Spread 0 0
0 Interrigging 0 0
0 Work Stoppages 0 0
0 Permit to Work (PTW) 0 0
0 Others 0 0
Total Downtime
Downtime Highlights

AREA OF CONCERN

AOC DESCRIPTION

MATERIAL STATUS

P.O. / S.O. Reference ETSD RECEIVED Status


WORK DONE TODAY

SITE TECHNICAL QUERY (STQ) STATUS

Description

AOB - ANY OTHER BUSINESS

ATTACHMENTS

REPORT VERIFIED BY REPORT ACKNO

MAYASSIN JININ

Construction Superintendant, PRSB Company Site Repr


2-Dec-16 2-Dec
1-Dec-16

JOR MAINTENANCE SERVICES FOR 2013-


OR KEBABANGAN OIL PIPELINE (POP)

Zaaba B Ali
Faizal Rosdi
Reynilda Bt Sius

ESS
Sabah Oil Gas Terminal (SOGT)
Days
16.67%
(HSE)
DESCRIPTION OF INCIDENT (IF ANY)
N/A

Previous Today Cumulative


1 0 1
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0

ZETO RULES AUDIT (KPI, 1 : 5000 MHRS)


Ratio
Cummulative
1 : 2712
1 : 909
1 : 1784
1 : 994
PRSB Direct 12 96
Trade Pax Hours
0 0
1 8
2 16
0 0
7 56
0 0
0 0
0 0
0 0
0 0
0 0
0 0
1 8
0 0
1 8
0 0
0 0
0 0

PCSB 0 0
Trade Pax Hours
0 0
0 0

Equipment/ Capacity Qty Hours


0 0
0 0
psi 0 0
0psi 0 0
0 0
5 cfm @ 120psi 0 0
@ 120psi 0 0
@ 125psi 0 0
0 0
0 0
0 0
0 0
0 0
REMARKS

Ongoing

Cummulative
0
0
0
0
0
0
0
0

DATE
ACTION BY STATUS
RESOLVED

Remarks
TUS

Remarks

REPORT ACKNOWLEDGED BY

Company Site Representative, PCSB


2-Dec-16
DAILY PROGRESS REPORT NO:
CONTRACT NO: CHO/2012/DFHD/193
PROVISION FOR HOO
CONTRACT TITLE:
2018
WO No: DFHD/2016/75A WO TITLE:
DAILY PROGR
Leena Yeewae
PCSB HUC / Faten Adawiyah
Copy To Attn
SBO Nur Abcida Ahmad
Mareney Bt Yahaya
M Kamal Yosof
M Zaid Siwok
Copy To PRSB Attn
Mayassin
Amirul Fariz
1
Start Date 30-Nov-16
Estimate Completion Date 5-Dec-16
PLANNED PROGRESS % 16.67%
2
DAILY HSE HIGHLIGHTS DAILY T
N/A

NON-LOST TIME INCIDENTS


Incidents Case Previous Today Cumulative Incidents
Near Miss 0 0 0 Fatality
Property Damage 0 0 0 Permanent Total Disabi
Damage to Enviroment 0 0 0 Permanent Partial Disa
Fire / Explosion 0 0 0 Lost Workday Case
First Aid Case 0 0 0 Total
Restricted Work Case 0 0 0 Remarks:
Medical Treatment Case 0 0 0 Lost Time Incident (LT
Total 0 0 0 Lost Time Incident (LT

UC/UA (KPI, 1 : 150 MHRS)


Submission
Company Manhours Today Cumm.
PCSB Staff 24 0 0
PRSB 144 0 0
3rd Party/Vendor/Sub-Contractor 0 0 0
Total 168 0 0

Project HSE Plan % (Weekly Update) 0.00% M


PTW Verification 0 Man-Hours Expenditu
PTW Submission 0 PCSB Personnel
PTW Verification : PTW Submission (KPI, 1 : 5 PTW) 0:00 PRSB Direct
PRSB Indirect
3rd Party
Total Expended Manh

3
Total PRSB Indirect 6
No Trade Pax
1 Fabrication Superintendent 0
2 Project Manager 1
3 Project Engineer 0
4 Construction Superintendent 1
5 Planning Engineer 0
6 Structural Engineer 0
7 HSE Engineer 1
8 QA/QC Engineer 0
9 Commissioning Engineer 1
10 HSE/Safety Promoter** 0
11 QA/QC Inspector 1
12 Matco 0
13 Safety Officer 1
14 General Supervisor 0
15 Fabrication Foreman 0
16 Admin 0
17 Painting Inspector 0
18 Document Controller 0
19 Materials Inspector 0
Total PCSB 3
No Trade Pax
1 PCSB PMT** 0
2 PCSB Material Controller** 0
3 PCSB HUC Engineer 3

4
No Equipment/ Capacity Qty
1 Fitter - Tools of Trade 1
2 Welder - Tools of Trade 0
3 Rigger - Tools of Trade 7
4 Blaster/ Painter - Tools of Trade 0
5 Instrument Fitter - Tools of Trade 2
6 Generator - 150 kVA 0
7 Generator - 250 kVA 0
8 Welding Machine - Diesel (Portable) 0
9 Welding Machine - Elec. Rectifier 0
10 LP Gas Heater 0
11 Ventilator/Blower 12" 0
12 Ventilator/Blower 16" 0
13 Mobile Crane 0
14 Forklift 0
5 INST

Previous Cumulative
Platform
Planned Actual

SOGT (Installation) 16.67% 16.67%

Overall Progress 16.67% 16.67%

6
Hours Previous Today
Weather 0 0
Gen Set 0 0
Welding Machine 0 0
Accessories 0 0
Compressor 0 0
Concurrent Activities 0 0
Unavailability of Personnel 0 0
To

No. Highlights Description


1
2
3
4

AOC NO AOC TYPE DATE RAISED

Package Description P.O. / S.O. Referen


9
SOGT

- Safety Induction of SOGT


- Safety Induction by Petra HSE
- Safety Handling Of Chemical (SHOC) training
- e-PTW training for PTW applicant.

10

Ref. NO Date Sent Descri

11
1
2
3
4
5
6

12
1
2
3
SIGNATURE REPORT PREPARED BY

Name IN'AMULHASSAN BIN JAMALUDIN

Designation Commissioning Engineer, PRSB Cons


Signature

Date 1-Dec-16
PRSB-SOGT-ONS-DPR- 1 DATE: 30-Nov-16
HO/2012/DFHD/193
ROVISION FOR HOOK-UP, COMMISSIONNING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR 201
018
PROVISION FOR HOOK-UP AND COMMISSIONING FOR KEBABANGAN OIL PIPELINE (POP)
PROJECT
DAILY PROGRESS REPORT CUT-OFF TIME: 1400 HRS
eena Yeewae Rudzuan B Awang Teh Nur Atika A Latif Zaaba B Ali
aten Adawiyah M Zhafri B Nasarudin Siti Nadiah Bt Jamaludin Faizal Rosdi
ur Abcida Ahmad Puteri Mira Dayana M Syahrul Ridhwan Reynilda Bt Sius
areney Bt Yahaya Ammar Cendric-Alexander Masuil
Kamal Yosof Safwan
Zaid Siwok In'amulhassan
ayassin Mohd Nashar
mirul Fariz Mohd Hanif
GENERAL INFO & OVERALL PROGRESS
-16 Location Sabah Oil Gas Te
16 Days On Site 1 Days
% ACTUAL PROGRESS % 16.6
HEALTH, SAFETY AND ENVIRONMENT (HSE)
DAILY TOOL BOX MEETING HSE TOPICS DESCRIPTION OF IN
N/A N/A

LOST TIME INCIDENTS HSE ACTIVITY


Incidents Previous Today Cumulative Toolbox Meeting
atality 0 0 0 HSE Walkabout
ermanent Total Disability 0 0 0 Touch The Heart Session
ermanent Partial Disability 0 0 0 Inspection
ost Workday Case 0 0 0 Fire/Emergency Drill
otal 0 0 0
emarks: 0 0 0
ost Time Incident (LTI) Frequency Rate 0
ost Time Incident (LTI) Severity Rate 0

KPI, 1 : 150 MHRS) BOT (KPI, 1 : 2000 MHRS) ZETO RULES AUDIT (KPI, 1 : 5000 M
Ratio Submission Ratio Submission
Cummulative Today Cumm. Cummulative Today Cumm.
0 0 0
0 0 0
Not Applicable at SOGT
0 0 0
0 0 0

MAN-HOURS EXPENDITURE HSE TOPICS &


an-Hours Expenditure Previous Today Cumulative 1. Safety induction/Briefing on SOGT House
CSB Personnel 0 24 24 2. Training of Safe handling of Chemical for
RSB Direct 0 96 96 3. Training & familiarization with e-PTW
RSB Indirect 0 48 48 4
d Party 0 0 0 5
Total Expended Manhours 0 168 168 6

MANPOWER LOADING
48 Total PRSB Direct
Hours No Trade
0 1 Welder
8 2 Fitter
0 3 Instrument Fitter
8 4 Milwright
0 5 Painter / Blaster
0 6 Rigger
8 7 Firewatcher
0 8 Scaffolder
8 9 Forklift Operator
0 10 Helper
8 11 Mechanic
0 12 Welder Foreman
8 13 Fitter Foreman
0 14 Rigger Foreman
0 15 Painting Foreman
0 16 Scaffolder Foreman
0 17 Crane Operator
0 18 UT Technician
0 MPI Technician
24 Total PCSB
Hours No Trade
0 4 PCSB HSE
0 5 PCSB Inspector
24

EQUIPMENT LOADING
Hours No Equipment/ Capacity
8 15 Semi Auto Pipe Cutter
0 16 Semi Auto Plate Cutter
56 17 Hydrotest Pump @ 6,000psi
0 18 Hydrotest Pump @ 10,000psi
16 19 Radial Drilling Machine
0 20 Electric Compressor - 375 cfm @ 120psi
0 21 Air Compressor - 375 cfm @ 120psi
0 22 Air Compressor - 830 cfm @ 125psi
0 23 Pressure Feed
0 24 Sand Blasting Set
0 25 After Cooler
0 26 Spray Eq. Airless Set
0 27 Extractor
0
INSTALLATION PROGRESS

SUMMARY OF PROGRESS

ous Cumulative Cumulative To Date Completion REMAR


Variance Planned Actual Variance Date

0.00% 16.67% 16.67% 0.00% 5-Dec Ongoi

0.00% 16.67% 16.67% 0.00%

DOWNTIME SUMMARY
Cummulative Hours Previous Today
0 OIC Constraint / Mopu Contraint 0 0
0 Drilling Constraint 0 0
0 Marine Spread 0 0
0 Interrigging 0 0
0 Work Stoppages 0 0
0 Permit to Work (PTW) 0 0
0 Others 0 0
Total Downtime
Downtime Highlights

AREA OF CONCERN

AOC DESCRIPTION

MATERIAL STATUS

P.O. / S.O. Reference ETSD RECEIVED Status


WORK DONE TODAY

SITE TECHNICAL QUERY (STQ) STATUS

Description

AOB - ANY OTHER BUSINESS

ATTACHMENTS

REPORT VERIFIED BY REPORT ACKNO

MAYASSIN JININ

Construction Superintendant, PRSB Company Site Repr


1-Dec-16 1-Dec
30-Nov-16

JOR MAINTENANCE SERVICES FOR 2013-


OR KEBABANGAN OIL PIPELINE (POP)

Zaaba B Ali
Faizal Rosdi
Reynilda Bt Sius

ESS
Sabah Oil Gas Terminal (SOGT)
Days
16.67%
(HSE)
DESCRIPTION OF INCIDENT (IF ANY)
N/A

Previous Today Cumulative


0 0 0
0 0 0
0 0 0
0 0 0
0 0 0

ZETO RULES AUDIT (KPI, 1 : 5000 MHRS)


Ratio
Cummulative
0
0
0
0

HSE TOPICS & HIGHLIGHTS


1. Safety induction/Briefing on SOGT House rules, policies and target
2. Training of Safe handling of Chemical for handling with waste.
3. Training & familiarization with e-PTW
4
5
6

PRSB Direct 12 96
Trade Pax Hours
0 0
1 8
2 16
0 0
7 56
0 0
0 0
0 0
0 0
0 0
0 0
0 0
1 8
0 0
1 8
0 0
0 0
0 0

PCSB 0 0
Trade Pax Hours
0 0
0 0

Equipment/ Capacity Qty Hours


0 0
0 0
psi 0 0
0psi 0 0
0 0
5 cfm @ 120psi 0 0
@ 120psi 0 0
@ 125psi 0 0
0 0
0 0
0 0
0 0
0 0
REMARKS

Ongoing

Cummulative
0
0
0
0
0
0
0
0

DATE
ACTION BY STATUS
RESOLVED

Remarks
TUS

Remarks

REPORT ACKNOWLEDGED BY

Company Site Representative, PCSB


1-Dec-16
Percentage
Original Duration (Planned)
OVERALL PROJECT PROGRESS (Installation)
MOBILISATION (Installation) 1.00 16.67%
PREPARATORY WORK 3.50 58.33%
.1 GENERAL 1.00 16.67%
To carry out preparation work ie. Scaffolding erection 1.00 16.67%
.2 PIPING 2.5 41.67%
.2.1 INSTALLATION
.2.1.1 Line No 200-PL-13163-151041X-N 0.30 5.00%
Remove Blind Flange 0.05 0.83%
Install DN25 SPW Gasket & Gate valve DN25 RF 1500# A105N 0.10 1.67%
Install flange 1500# with quick coupling to the valve 0.10 1.67%
Connect the hose 150# to the quick coupling 0.05 0.83%
.2.1.2 Line No: 200-PL-13163-151XXX-N 0.30 5.00%
Remove Blind Flange 0.05 0.83%
Install DN20 SPW Gasket & Gate valve DN20 RF 1500# A105N 0.10 1.67%
Install flange 1500# with quick coupling to the valve 0.10 1.67%
Connect the hose 150# to the quick coupling 0.05 0.83%
.2.1.3 Line No 350-PL-13021-31001-20X-N 0.30 5.00%
Remove Blind Flange 0.05 0.83%
Install DN20 SPW Gasket & Ball valve DN20 RF 300# A105N 0.10 1.67%
Install flange 300# with quick coupling to the valve 0.10 1.67%
Connect the hose 150# to the quick coupling 0.05 0.83%
.2.1.4 Line No: 350-PL-13015-151041X-N 0.30 5.00%
Remove Blind Flange 0.05 0.83%
Install DN20 SPW Gasket & Gate valve DN20 RF 1500# A105N 0.10 1.67%
Install flange 1500# with quick coupling to the valve 0.10 1.67%
Connect the hose to the quick coupling 0.05 0.83%
.2.1.5 Line No: 300-PL-13024-31001-20X 0.20 3.33%
Remove Blind flange at valve VX13172 0.05 0.83%
Install flange 300# with quick coupling to the valve 0.10 1.67%
Connect the hose 150# to the quick coupling 0.05 0.83%
.2.1.6 Line No: 300-PL-15002-11001X-N 0.30 5.00%
Remove Blind Flange 0.05 0.83%
Install DN20 SPW Gasket & Gatel Valve 150# A105N 0.10 1.67%
Install flange 150# with quick coupling to the valve 0.10 1.67%
Connect the hose 150# to the quick coupling 0.05 0.83%
.2.1.7 Line No: 350-PL-13009-15104X-N 0.80 13.33%
Remove PG 13144 0.05 0.83%
Install flanged hose DN50 150# 0.10 1.67%
Install Transition Spool 1500# to 150# DN50 0.15 2.50%
Remove DN40 Blind flange 0.05 0.83%
Install sampling connection 1500# A105N 0.10 1.67%
Remove PG 13141 0.05 0.83%
Install Transition Spool 1500# to 150# DN50 0.15 2.50%
Install flanged hose DN50 150# 0.15 2.50%

Internal
BACKLOADING 0.50 8.33%
DEMOBILISATION 1.00 16.67%

Prepared By

.
In'amulhassan bin Jamaludin
PRSB COMMISSIONING ENGINEER

Internal
Planned Start Planned Finish Overall Progress

30 November, 2016 5 December, 2016 16.67%


30 November, 2016 30 November, 2016 16.67%
1 December, 2016 4 December, 2016 0.00%
1 December, 2016 1 December, 2016 0.00%
1 December, 2016 1 December, 2016
2 December, 2016 4 December, 2016 0.00%

2 December, 2016 2 December, 2016 0.00


2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016 0.00
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016 0.00
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016
2 December, 2016 2 December, 2016 0.00
2 December, 2016 2 December, 2016
2 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016 0.00
3 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016 0.00
3 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016
4 December, 2016 5 December, 2016 0.00
3 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016
3 December, 2016 3 December, 2016
4 December, 2016 4 December, 2016
4 December, 2016 4 December, 2016
4 December, 2016 4 December, 2016
4 December, 2016 4 December, 2016
4 December, 2016 4 December, 2016

Internal
4 December, 2016 4 December, 2016 0.00%
5 December, 2016 5 December, 2016 0.00%

Verify & Acknowledged By

PETRONAS CSR

Internal
PROJECT PROGRESS (Commissioning & Removal)
1.0 MOBILISATION (Commissioning & Removal)
2.0 COMMISSIONING
2.1 SYSTEM PREPARATION
KBB Oil Pipeline N2 displacement via 2' vent line at R-1310
Crude receiving system
Offspec receiving system
2.2 SCENARIO EVALUATION
Start-up mode and KOP Nitrogen displacement
Prolong offspec crude
Confirm crude onspec and handover
2.3 NITROGEN DISPLACEMENT AND SOGT START UP
KBB readiness for crude export and PIG launch
Vent Nitrogen at R-1310 using 2' flexible hose
Vent nitrogen using 1 inch vent (V1) line 200-PL-13163-151041XX
Vent nitrogen using 1 inch vent (V2) line 200-PL-13163-151041XX
Vent nitrogen using 1 inch vent (V3) line 350-PL-13015-151041XX
Vent nitrogen using 1 inch vent (V4) line 300-PL-13024-31001-20X via VX 13172 (inlet pipe PSV-13168A)
Vent nitrogen using 1 inch vent (V5) line (after FT-13120)
Vent nitrogen using 1 inch vent (V6) line 350-PL-15002-11001X
Confirm crude arrival to T-1510 and Crude sampling frequency for BS&W
Line up valve from offspec crude receiving to onspec crude receiving header
PIG arrival and retrieval
Prolong offspec crude from KBB
Stabilization of crude to on-spec tank for 6 hours
ESD Test
3. REMOVAL
3.1 Line No 200-PL-13163-151041X-N
Remove flange 1500# with quick coupling
Re-install Blind Flange 1500# DN25 (Existing)
3.2 Line No: 200-PL-13163-151XXX-N
Remove flange 1500# with quick coupling
Re-install Blind Flange 1500# DN20 (Existing)
3.3 Line No 350-PL-13021-31001-20X-N
Remove flange 300# with quick coupling
Re-install Blind Flange 300# DN20 (Existing)
3.4 Line No: 350-PL-13015-151041X-N
Remove flange 1500# with quick coupling
Re-install Blind Flange 1500# DN20 (Existing)
3.5 Line No: 300-PL-13024-31001-20X
Remove flange 300# with quick coupling
Re-install back Blind flange at valve VX13172 (Existing)
3.6 Line No: 300-PL-15002-11001X-N
Remove flange 150# with quick coupling
Re-install Blind Flange 150# DN20 (Existing)

Internal
3.7 Line No: 350-PL-13009-15104X-N
Remove DN50 150# flanged hose
Remove DN40 sampling connection 1500# A105N
Remove transition spool 1500# to 150# DN50
Reinstate back PG 13144 (Existing)
Re-install Blind flange DN40 (Existing)
Remove DN50 150# flanged hose
Remove transition spool 1500# to 150# DN50
Reinstate back PG 13141 (Existing)
BACKLOADING & HOUSEKEEPING
DEMOBILISATION

Prepared By

.
In'amulhassan bin Jamaludin
PRSB COMMISSIONING ENGINEER

Internal
Percentage
Original Duration Planned Start Planned Finish Overall Progress
(Planned)
23 December, 2016 31 December, 2016 0.00%
1.00 11.11% 23-Dec-16 23-Dec-16 0.00%
5.00 55.56% 24-Dec-16 28-Dec-16 0.00%
0.9 10.00% 24-Dec-16 24-Dec-16 0.00%
0.5 5.56% 24-Dec-16 24-Dec-16
0.2 2.22% 24-Dec-16 24-Dec-16
0.2 2.22% 24-Dec-16 24-Dec-16
0.6 6.67% 24-Dec-16 25-Dec-16 0.00%
0.2 2.22% 24-Dec-16 24-Dec-16
0.2 2.22% 25-Dec-16 25-Dec-16
0.2 2.22% 25-Dec-16 25-Dec-16
3.5 38.89% 25-Dec-16 29-Dec-16 0.00%
0.5 5.56% 25-Dec-16 25-Dec-16
0.1 1.11% 25-Dec-16 25-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.1 1.11% 26-Dec-16 26-Dec-16
0.2 2.22% 26-Dec-16 26-Dec-16
0.3 3.33% 26-Dec-16 27-Dec-16
0.5 5.56% 27-Dec-16 27-Dec-16
0.3 3.33% 27-Dec-16 27-Dec-16
0.5 5.56% 28-Dec-16 28-Dec-16
0.5 5.56% 28-Dec-16 28-Dec-16
2 22.22% 29-Dec-16 30-Dec-16 0.00%
0.2 2.22% 29-Dec-16 29-Dec-16 0.00%
0.1 1.11% 29-Dec-16 29-Dec-16
0.1 1.11% 29-Dec-16 29-Dec-16
0.2 2.22% 29-Dec-16 29-Dec-16 0.00%
0.1 1.11% 29-Dec-16 29-Dec-16
0.1 1.11% 29-Dec-16 29-Dec-16
0.2 2.22% 29-Dec-16 29-Dec-16 0.00%
0.1 1.11% 29-Dec-16 29-Dec-16
0.1 1.11% 29-Dec-16 29-Dec-16
0.2 2.22% 29-Dec-16 29-Dec-16 0.00%
0.1 1.11% 29-Dec-16 29-Dec-16
0.1 1.11% 29-Dec-16 29-Dec-16
0.2 2.22% 29-Dec-16 29-Dec-16 0.00%
0.1 1.11% 29-Dec-16 29-Dec-16
0.1 1.11% 29-Dec-16 29-Dec-16
0.2 2.22% 30-Dec-16 30-Dec-16 0.00%
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16

Internal
0.8 8.89% 30-Dec-16 30-Dec-16 0.00%
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.1 1.11% 30-Dec-16 30-Dec-16
0.50 5.56% 31-Dec-16 31-Dec-16 0.00%
0.50 5.56% 31-Dec-16 31-Dec-16 0.00%