Sunteți pe pagina 1din 10

EUROPEAn

OFFSHORE
SPE 8120 PETROLEum
conFEREnCE
THE DEVELOPMENT HISTORY a EXHIBITion
OF GREATER EKOFISK
by W. L. Heidbreder,
Phillips Petroleum Co.

Copyright 1978, European Offshore Petroleum Conference and Exhibition on behalf of the Society of Petroleum Engineers (U.K.) Limited

This paper was presented at the European Offshore Petroleum Conference and Exhibition in London 24-27, October, 1978. The material is subject to correction by the author. Permission to
copy is restricted to an abstract of not more than 300 words.

ABSTRACT West Germany was the first to grant petroleum


rights followed by the United Kingdom in 1964.
The Ekofisk Field, discovered in 1969, at a Interest at that time was concentrated in the
time when exploratory interest in the hostile southern region as water depths were less and the
North Sea vas beginning to wane, marked the begin- weather less hostile. Drilling in the U.K. began
ning of a new era in the oil industry. This was in December that year and discoveries followed
an era of remarkable technological advancement, quickly; West Sole gas field in 1965, Leman in
one in which man's ingenuity was pitted against early 1966, Indefatigable in mid 1966, Hewett in
the elements of nature at their worst. With the late 1966 and Viking in 1968.
further discovery of West Ekofisk, Tor and Eldfisk
fields in 1970, Edda and Albuskjell fields in 1972 Most of this production was from the Rotlie-
and the decision to develop Cod field discovered gendes formation of Permian age. Phillips Petroleum
in 1968, a comprehensive three phase development Company's seismic work, however, indicated a thick
plan, one of the largest in petroleum history, was Tertiary basin along the median line between
under way - The Development of Gre~ter Ekofisk. Norway and the United Kingdom. This basin of
younger age was of much interest since historically
Based on nine years of completed development much of the world's production was from basins of
and seven years of Ekofisk production history, this nature.
this paper reviews the history of development,
highlights technological advancements and discusses The Phillips Norway Group, consisting of
the problems incurred at Greater Ekofisk. Although Phillips Petroleum Company Norway (Operator),
certain revisions in design and slippages in Norske Fina A/S and Norske AGIP A/S, therefore,
schedule have occurred, the original concepts applied for and was subsequently awarded Norwegian
remain valid after nine years. production licenses 016, 017 and 018 in 1965.
These licenses covered blocks 7/8, 8/1, 16/11 and
INTRODUCTION 17/12; 8/8, 8/10 and 8/11; and 1/5, 2/4, 2/7 and
7/11 respectively. In 1967 the A/S Petronord
Prior to 1959 the North Sea area had attracted Group acquired 20% interest in the Phillips Norway
little worldwide exploration attention. Although Group resulting In the present international
offshore areas were beginning to be widely consi- composition:
dered for exploration, none of the onshore oil
fields discovered in the previous 40 years around Phillips Petroleum Company
the North Sea would have been commercial if located Norway (USA) 36.960%
offshore. However, with the discovery of the American Petrofina Exploration
giant Groningen gas field in the Netherlands in Company Norway (USA) 30.000%
1959, exploratory interest in the North Sea began
to build. Although the Geneva Convention of 1958 Norske AGIP A/S (Italy) 13.040%
had laid out the basic rules for dividing conti-
A/S Petronord Group
nental shelf areas, the ratification of 22 nations
was needed before the convention became effective. Elf Aquitaine Norge A/S (France) 8.094%
This was not accomplished until 1964 and even then
Norsk Hydro a.s. (Norway) 6.700%
there were disputes between West Germany, Denmark
and the Netherlands that were not settled until Total Marine Norsk A/S (France) 4.047%
1970. In the meantime companies were busy shooting Eurafrep Norge A/S (France) 0.456%
seismic lines and trading data. In this way many
companies were ready for selecting promising Coparex Norge A/S (France) 0.399%
acreage when made available. Cofranord A/s (France) o ,'l04%
299
DISCOVERY environments is clearly indicated by the sub-
sequent discoveries and pipelines indicated in
Drilling began on the Norwegian continental Figure 1. The development of none of these areas,
shelf in 1966 and between July of that year and however, can compare in scope with that of the
August 1969, Phillips, Esso, Amoco, Petronord, Greater Ekofisk area. With the subsequent disco-
Texaco, Shell, Gulf, Murphy and Syracuse had very of five additional fields located at distances
drilled some 32 wells without a commercial dis- of up to 23 kID (14 mil from Ekofisk (Fig. 2) and
covery. The Phillips Norway Group had been en- the decisions to develop Cod field some 80 kID (50
couraged by their condensate discovery in Block mil away and to tie all these into a central
7/11, Cod field, in mid 1968 but after subsequent processing facility, the Development of Greater
dry holes in other blocks, Phillips like most Ekofisk was under way.
operators was ready to shut down.
DEVELOPMENT HISTORY
Only the contract obligation on the semi-sub-
mersible drilling rig "Ocean Viking" resulted in Once the appraisal of Ekofisk was complete,
the drilling of the well 2/4-1X in August 1969. the planning of one of the biggest offshore de-
This hole was plugged after encountering drilling velopments ever attempted in such adverse environ-
problems at 1,675 m (5,500 ft). Oil shows had mental conditions was undertaken. A three phase
been recorded, so a replacement well, 2/4-1AX, was development plan was devised to insure development
drilled. This well did not encounter the upper and production with maximum efficiency. Each
interval oil shows but at approximately 3,050 m phase was to be a continuation of the previous and
(10,000 ft) oil shows were encountered and contin- with a definitive purpose.
ued for 215 m (700 ft) through the Danian and into
the upper Cretaceous limestones. This was December Phase I was designed to obtain lengthy pro-
1969 and weather was extremely bad. Logs were duction history, additional reservoir information,
run, short drill stem tests conducted and the well early operational experience and to generate early
temporarily abandoned. The results were suffi- income. To accomplish this the four subsea explo-
ciently encouraging to cause the Phillips Norway ration wells were tied into a temporary production
Group to continue their exploration effort. platform with oil loaded onto tankers through two
single point monomooring buoys (SBM's).
Three months later, the 2/4-2X well was
drilled 3.2 kID (2 mil east of the discovery and Phase II, devised to complete the early and
confirmed the discovery of hydrocarbons by testing rapid development of Ekofisk field to its potential
at oil rates in excess of 600 m3 /d (3,800 BOPD). of 56,000 m3 /d (350,000 BOPD) , called for the re-
This flow rate was equipment limited and indica- placement of the temporary platform with permanent
tions were that flow capacities were in excess of production facilities and the erection of three
1,600 m3 /d (10,000 BOPD). Well 2/4-3X was drilled drilling platforms, a flare platform, a quarters
3.2 km (2 mil south of the discovery and as geo- platform and an underwater storage tank. Offshore
logically anticipated, since it was drilled down loading was to continue during this phase.
dip to establish an oil-water contact, encountered
about one half as much pay as the first two Ekofisk The magnitUde of Phase III, the development
wells. The fourth well, drilled 5 kID (3 mil north of outlying fields, was not realized at the onset.
of the discovery, confirmed the largest oil field The connection of outlying fields to a central
In Western Europe. system was planned along with the laying of a gas
pipeline. A possible oil line was planned contin-
After the discovery, further seismic was run gent upon proving sufficient reserves for justifi-
and drilling continued elsewhere in the area. cation. As the seven fields were proven, Phase
Three additional fields, Tor, which extended into III took on its current scope calling for connect-
Amoco's Block 2/5, West Ekofisk and Eldfisk were ing the seven fields to a central system, laying
discovered in 1970. Albuskjell, which extended an oil line to a newly constructed onshore crude
into Shell's Block 1/6, and Edda were discovered stabilization and NGL processing facility and
in 1972. laying a gas line to a newly constructed gas
treatment plant.
LOCATION
PHASE I
The Ekofisk field is located in the central
North Sea on the Norwegian continental shelf near The Phillips Norway Group had commenced
the United Kingdom boundary (Fig. 1). It is prac- pushing the limits of technology in 1967 with the
tically equidistant from the major oil consuming contracting of a new breed of drilling vessel, a
nations of Europe, being 290 kID (180 mil from semi-submersible, for their exploration drilling
Norway and 320 kID (200 mil from Denmark, Scotland program to be conducted year round in the North
and England. The size of the hydrocarbon accu- Sea. In order to accomplish the objectives of
mulations located at this remote, hostile location Phase I, several more innovative steps 'had to be
was to provide the incentive for stepping beyond taken. First, the four subsea exploration wells
the bounds of previous oil industry experience. were re-entered and completed using 114 mm (4~ in)
This area became a proving ground for many ideas tubing and subsea wellhead equipment. Second, the
and techniques to be used by the industry in jack-up drilling rig "Gulftide" became the first
subsequent hydrocarbon discoveries at locations mobile rig used for offshore production facilities
where environmental conditions were even more and finally, SBM's were installed in 70 m (230 ft)
adverse. The steady progress of the industry in water depths and tanker loading undertaken in open
moving northward into more hostile North Sea seas.

300
The "Gulftide" was thoroughly inspected and producing wells completed by November 1975.
repairs made before its conversion to a production Platform B, a 12 leg, 24 slot, 2 rig unit was
platform. Pipe racks were removed for installation completed in October 1973. Its 16 wells were
of production equipment, supports added to the completed by April 1976. Finally, Platform C, a
derrick to brace the gas flare stack, supports 12 leg, 16 slot combination drilling and compres-
added to accommodate survival capsules and the sion platform was installed by October 1973.
helideck enlarged and strengthened. Production Drilling commenced in January 1974 and the 4
equipment to handle 6,400 m3 (40,000 bbls) of oil producing wells and 8 injection wells were com-
and 1.4 million m3 (50 MMCF) of gas per day was pleted by December 1975. The compression equip-
installed. ment became operable in February 1975.

Oil from the first stage separator operating Platform A and B were located in the south
at 3,500 kPa (500 psia) was heated to 66c (150 0 F) central and north central part of the field res-
and flashed into the second stage separator at 41 pectively. Platform C was in the line of inter-
kPa (6 psia). The gas was flared through a 508 mm connected structures making up the Ekofisk Complex.
(20 in) line in the "Gulftide's" derrick. The oil From south to north these Phase II facilities
was metered and pumped through two 273 mm (lOa in) consist of FL-l, followed by two bridge support
loading lines to two SBM's anchored 2.4 and 2.8 km tripods, 2/4-FTP, 2/4-Q, 2/4-c, another bridge
(1; and ld mil from the "Gulftide". Although support tripod, platform 2/4-p and finally the
SBM's had been utilized elsewhere in the world, underwater storage tank (Fig. 3).
none were located in waters in excess of 27 m (90
ft) and all were located in sheltered water close Platform Q is a 4 leg structure providing 34
to shore with mooring gear and loading hoses rooms for permanent quarters with temporary quar-
handled by launches. The location of SBM's in ters for 115 men. Platform P, a 4 leg structure,
water 70 m (230 ft) deep, the development of was installed for future pump equipment.
mooring line capable of securing 60,000 dwt tankers
in 93 km/h (50 knot) winds and 5 m (16 ft) signi- The production facilities located on 2/4-FTP
ficant waves and the development of a self mooring were designed to handle 56,000 m3 /d (350,000 BOPD)
system for these tankers were all innovations of and associated gas expected to range from 13 - 28
Phase I. Performance figures indicate that an million m3 /d (450-1,000 MMCFD) which was to be
average downtime of 22.2 per cent was experienced produced from 2/4-A, Band C. The oil and gas
with successful moorings regularly made in 4.6 m separation facilities on 2/4-FTP consist of two
(15 ft) seas with 56 km/h (30 knot) winds and trains of heat exchangers with three stages of
ships remaining at berth in 7.6 m (25 ft) seas and separation operating at 7,000 kPa (1,015 psia),
93 km/h (50 knot) winds. The final innovative 1,830 kPa (265 psia) and 138 kPa (20 psia) res-
design of Phase I was the 1,070 mm (42 in) x 91 m pectively (Fig. 4). Gas from the low stage sepa-
(300 ft) caisson to conduct and support all the rator is compressed and joined with the gas from
lines from the sea floor to the platform. This the second stage. This gas is then recompressed,
caisson held fourteen lines; two 114 mm (4; in) joined with the gas from the first stage and piped
flowlines to each well, four specially designed to 2/4-c for re-injection into the reservo~r.
hydraulic control lines, one to each well, and two
273 mm (lOa in) tanker loading lines along with Phase II production commenced at 3,200 m3 /d
two electric cables. (20,000 BOPD) in April 1974 with production from
2/4-A through 2/4-FTP and onto tankers through the
Phase I production commenced from one well on SBM's used in Phase I. New 760 mm (30 in) subsea
July 7,1971 setting another landmark as the first lines from 2/4-FTP to these buoys were installed.
commercial oil production from the North Sea. All Original plans called for the continued production
four wells were completed and on stream by January of the four subsea 1-Tells by tieing them into 2/4-
1972. Phase I ended in April 1974 after a total FTP. All four wells required workovers. Problems
production of 4.5 million m3 (28 million bbls) at on the first workover resulted in the decision to
maximum rates in excess of 7,200 m3 /d (45,000 abandon these wells. The last well 2/4-2X was
BOPD). Production had commenced only 18 months abandoned in 1976.
after the discovery and continued for over two
years before permanent facilities were available. The plans for Phase II again called for a
This period provided valuable North Sea opera- series of innovations, the most outstanding being
tional experience and allowed refinements in the 160,000 m3 (one million bbl) storage tank.
reservoir parameters. These, together with the The tank is a prestressed concrete structure
early income, made the $28,000,000 Phase I a weighing 115,000 tonnes (125,000 tons). The
success. storage reservoir made of nine separate inter-
connected cells is 50 m (165 ft) in diameter and
PHASE II 82 m (270 ft) in height. The reservoir is sur-
rounded by a breakwater wall about 92 m (302 ft)
Completing the development of Ekofisk field in diameter. The breakwater wall is perforated
called for the installation of three drilling and is designed to dissipate 70% of the total wave
platforms, 2/4-A, Band C, a field terminal plat- energy between it and the inner wall. The base of
form, 2/4-FTP, a quarters platform, 2-4/Q, an the tank was constructed in dry dock at Jattavagen,
emergency gas flare, FL-l and an underwater near Stavanger, and towed to deep inland water in
concrete storage tank, 2/4-T. Hillevagen Bay for construction of the walls and
roof. The tank was completed on June 21, 1973 and
Platform A, an 8 leg, 16 slot unit was set on location by June 29. The tank is to be
completely installed by August 1973 and its 11 full of liquid at all times, normally both crude

301
and water. Four 38,000 m3 /d (240,000 BPD) pumps, offshore construction equipment in the world. The
one as standby, are used for transferring crude to decision to begin using modular construction to
tankers and three 57,000 m3 /d (360,000 BPD) sea- reduce expensive offshore construction time by
water pumps, one as standby, replace seawater as assembling entire packages of equipment onshore in
oil is discharged. Transfer of water in and out modules weighing hundreds of tonnes necessitated
of the tank is through two 760 mm (30 in) risers this. In 1973, the largest derrick barge in tile
and a skimming tank where oil is removed before world, the 1,090 tonne (1,200 ton) "Champion" was
discharging water into the sea. being used at Ekofisk. In the summer of that year
a 1,045 tonne (1,150 ton) lift, the largest in the
Actual operation of the tank commenced in world at that time, was made.
December 1974. From this time until oil pipeline
start up, October 1975, offshore loading downtime Phase II production was originally planned to
averaged 40% but the storage provided by the tank commence in May 1972 but actual production did not
limited actual production downtime to less than begin until April 1974. Complete redesign of all
1%. Production during this period averaged the platforms due to re-evaluation of wave height
26,000 m3 /d (165,000 BOPD). data was a major factor in this slippage. Project
slippage was also attributable to industry in-
The second major technological aavancement of experience in the North Sea, weather downtime and
Phase II was the design and operation of the other major design changes such as those encoun-
world's highest pressure gas injection centrifugal tered with the compressors. These problems result-
compressors. These compressors were designed to ed in a final cost for Phase II of $477,000,000
take 6,720 kPa (975 psia) gas from the second compared to an early anticipated cost of
stage recompressor and the first stage separator $175,000,000.
and compress it in two stages, first to 24,000 kPa
(3,500 psia) and then to pressures as high as Drilling of the 40 Phase II wells was rela-
63,000 kPa (9,200 psia) depending on the number of tively trouble free with an average time of 60
injection wells and the formation pressure. The days/well including driving the 760 mm (30 in)
installation of these compressors was completed in conductor, completing and testing the well. Wells
June 1974. Original attempts at operation, how- with deviation angles in excess of 55 degrees were
ever, were met with excessive vibration problems. drilled sucessfully.
Analysis of the situation resulted in an inter-
mediate redesign of the compressor rotor and Although full of accomplishments, Phase II
seals. The new equipment was installed in Decem- was not without its problems. The original Phase
ber 1974 and after testing was put into operation II risers were protected in the splash zone by a
in February 1975 although full design discharge 4 mm (5/32 in) coating of coal tar, fiberglass and
pressures could not be reached. Well injectivity felt wrapping and a 38 mm (l~ in) coating of
response, however, was better than previously concrete. A riser failure causing a fire and
anticipated and it was possible to inject the platform damage on 2/4-A resulted in a redesign of
required volumes of gas at lesser pressures than splash zone riser protection. The redesign was a
originally anticipated. With the two trains Monel sheathed steel jacket with the annulus
operating, injection of 13.6 million m3 /d (480 between the jacket and the riser filled with
MMCFD) of gas corresponding to an oil production cement. In addition to the problem with the high
of 51,000 m3 /d (320,000 BOPD) was possible. The stage compressors, a failure occurred in the fresh
final redesign of the compressor rotor and seals water chilled, high stage compressor gas inter-
was completed and the equipment manufactured and cooler. This was caused by corrosion attributable
installed by September 1975. This unit has been to installation and testing technique and prolonged
operating since then with no major problems. atmospheric exposure before putting into service.
Minor problems with downhole safety valves, chokes
Finally, the method of installing platform and wellheads were also encountered.
foundations at Ekofisk was another technological
achievement. Pile driving experience in strong PHASE III
foundation soils such as those found at Ekofisk,
precluded the driving of piles as a means of Phase III as originally planned called for
providing the necessary structural support for connecting outlying fields, laying a submarine gas
anticipated platform and wave loads. While con- line and possibly laying an oil line. With the
sidering the uncertainties and problems of using size of the first five fields confirmed and the
grouted insert piles in this environment, the idea discovery of Albuskjell and Edda fields in 1972
of using an underreamed footing, bell foundation, (Fig. 2), this Phase took on a new dimension. The
was studied. Apparently, this had never been decision was made to tie the six outlying fields
attempted in an offshore environment but appeared into a central processing facility at Ekofisk
entirely feasible. The techniques and equipment Center. This facility, located on top of the
were developed and used on the first platform underwater storage tank, would produce a 100 Reid
installed in 1971. Of the 248 foundations at vapor pressure NGL-crude oil mixture for delivery
Ekofisk, 84% utilized bell foundations ranging In by pipeline to a crude stabilizing, loading and
diameter from 2.7 to 6.1 m (9 to 20 ft). Contin- NGL fractionation plant at Teesside, England. The
ued refinements in technique have resulted in low hydrocarbon dew point residue gas from Ekofisk
continued reductions in the time needed to install Center would be piped to a treating plant at
bell foundations. Emden, Germany. Pipelines to Norway were evaluated
and determined not feasible because of the depth
Installation of the Phase II platforms and of the Norwegian trench located between Ekofisk
equipment called for the use of some of the largest and Norway.

302
After the decision to construct oil and gas Ekofisk Center capable of delivering 41 million
pipelines, approval was requested of the Norwegian m3 /d (1,440 MMCFD) to Emden. At that time, how-
Government for laying a 58 million t/a (1 MMBOPD) ever, the trenching of the line, which had been a
oil line and a 56 million m3 /d (2,100 MMCFD) gas continuous problem on both the oil and gas lines
line. The Norwegian Ministry decided that the and had caused significant delays, became a serious
State Oil Company, now Statoil, should take a 50% obstacle to start up of the gas line. The Danish
interest in each line. Consequently, Norpipe authorities would not issue a start up permit
a.s., a 50/50 joint stock company between the unless the 48 km (30 mil of line in their waters
Phillips Norway Group and Statoil, was formed. met their criteria for a 2 m (7 ft) trench and 1
The Phillips Norway Group constructed and is m (3 ft) of cover. Continued attempts to meet
operator of the two lines on behalf of Norpipe. these criteria had been made from 1974 to 1977.
In the meantime plans were developed for the During trenching operations, as many as five
laying of two of the largest and longest submarine passes were made in the Danish sector. It was
pipelines ever built. Although the Norwegians had finally agreed that if critical areas, those with
not given approval for the landfall sites, plans less than a 50 cm (20 in) trench and less than 10
went ahead assuming Teesside and Emden would cm (4 in) of cover, were covered, a pipeline start
eventually be approved. The designs called for an up permit would be issued. The critical areas
864 mm (34 in), 354 km (220 mil oil line and a 914 amounting to about 5 km (3 mil of pipe were covered
mm (36 in), 443 km (274 mil gas line. Each of the using over 625,000 sandbags and the start up
lines was to have two intermediate booster plat- permit was issued September 14, 1977. Drying of
forms which were necessitated by the large volumes the gas line then commenced. This permit was
involved. This was the first time that boosters issued contingent upon the pipeline in the Danish
had been utilized offshore. With the booster sector being covered to 50 cm (20 in) by June 1,
platforms in operation, nominal capacities are 1980. A year of development went into the design
160,000 m3 /d (1 MMBOPD) for the oil line and 56 and construction of new equipment technically
million m3 /d (2,100 MMCFD) for the gas line. capable of pipeline backfilling. These vessels
are now working on the line.
THE OIL PIPELINE
During the construction of the oil and gas
Approval for the Teesside location was finally lines, industry firsts were again recorded. At
given on May 4, 1973 and the first lay barge times, one half of the world's offshore pipelaying
commenced work on May 5. Laying of the line was capacity was in use on the two lines. In one day
divided into three segments with one contractor in mid-September 1974, a total of 189 joints,
selected for each. Two contractors completed 2,300 m (7,547 ft) of 914 mm (36 in) line were
their sections in 1973 and moved over to assist hand welded on one barge. The preceding August,
the third. Bad weather, however, forced a shut- 155,436 m (509,959 ft), 40%, of the gas pipeline
down in November. Work was resumed in February offshore portion was laid by the four barges.
1974 and laying was completed May 23. In May and
September 1974 booster platforms 37/4-A and 36/22- TEESSIDE FACILITIES
A were installed. The subsea connections of the
line and platform risers were made using HydroBall/ Facilities at Teesside actually make up two
HydroCouples. The crude reception facilities, plants. The first, owned by Norpipe Petroleum
tank farm and one loading jetty were ready at U.K. Ltd., a 50/50 joint stock company between the
Teesside in 1975 and delivery of low vapor pres- Phillips Norway Group and Statoil, includes four
sure crude (9 RVP) began flowing to Teesside on 7,200 m3 (45,000 bbl) receiving surge tanks and 7
October 19, 1975. The booster pump packages were desalter and crude stabilizing trains. The 5-7
not scheduled for completion at the intermediate RVP crude from these units is pumped to the 1.2
pump platforms until September 1977 but the ini- million m3 (7.5 million bbl) capacity tank farm at
tiating pump equipment had already been installed Greatham, 5 km (3 mil away. From here it can be
on the Phase II platform, 2/4-p, at Ekofisk Complex loaded into tankers as large as 150,000 dwt through
(Fig. 3 and 4). With its three centrifugal pumps, any of four jetties. Normally, tankers in the
2/4-p was capable of delivering 86,200 m3 /d 80,000 dwt range are utilized as they can operate
(542,400 BOPD) to Teesside. Therefore, as early at the terminal in all tides and they are the most
as October 1975, part of Phase III went into economical for the majority of the runs which are
operation. Considerable work remained before all to northern European ports.
of Phase III was operational. In fact, drilling
of some Phase III wells is not expected to be The NGL's from the stabilizers pass to the
complete until 1983 or thirteen years after the second facility owned by Norsea Pipeline Ltd., a
discovery of Ekofisk. 100% Phillips Norway Group company. These faci-
lities include 2 de-ethanizers, 1 demethanizer, 2
THE GAS PIPELINE depropanizers, 1 butane splitter, 1 isobutane
depropanizer and over 240,000 m3 (1.5 million
As with the oil line, laying of the gas line bbls) of refrigerated storage. These facilities
commenced within hours after the final notification can process 11,000 m3 /d (70,000 BPD) of NGL's.
from the Norwegian and German governments that There will be two berths for handling refrigerated
pipeline permits had been issued. This was April LPG and three berths for loading pressurized
5, 1974 and by 4 November, 424 km (262 mil of pipe NGL's.
had been laid and only a 3.2 km (2 mil portion
near the Ekofisk Complex and a 16 km (10 mil land As mentioned, oil deliveries began October
portion remained. Hook up of the gas line was 19, 1975 and at that time Jetty No. 1 was complete
completed in August 1977 with the compressors at and eight storage tanks installed. To date all

303
crude storage is complete as well as all jetties. a 406 mm (16 in), 76 km (47 mil two phase pipeline
Teesside stabilization and NGL processing facili- to Ekofisk Center. Drilling commenced on Cod in
ties were originally forecast to be completed by August 1976 and all 8 wells were completed by
October 1975. However, continued delays have been October 1977 for an average of 50 days/ well.
experienced due to various problems including Production from six Cod wells began December 28,
labor difficulties, late delivery of materials, 1977. Production from Cod is varied with gas
and receipt of off-spec material from suppliers. sales demand and is therefore cyclical. Antici-
NGL facilities and four of the stabilizers are now pated maximum rate is 2.6 million m3 /d (90 MMCFD).
expected to be operational the second quarter of
1979. At that time 100 RVP crude can be delivered Tor Field - This is a unitized field between
from the offshore facilities and the final opera- the Phillips Norway Group owning 74.5% and the
tional mode at Ekofisk achieved. Amoco/Noco Group owning 25.5%. The platform, 2/4-
E, is an 8 leg combination drilling and production
EMDEN PLANT platform installed in June 1976. Separation
initially operates at 8,790 kPa (1,275 psia). The
In contrast to the Teesside facilities, cons- oil stream then flows to Ekofisk Center through a
truction at Emden has progressed relatively close 305 mm (12 in), 12 km (7.5 mil line and the gas,
to schedule. The facilities at Emden are owned by after dehydration, is piped through a 356 mm (14
Norsea Gas A/S, a 100% Phillips Norway Group in) line. The lines are owned 100% by the Phillips
company. Facilities include 9 molecular sieve Norway Group. Again, provisions have been made to
treating trains and facilities for the sale of 56 install future compression at Tor. Tor drilling
million m3 /d (2,100 MMCFD). This represents one commenced in February 1977 and its 12 wells should
of the largest facilities of its kind in the be completed the fourth quarter of 1979. Pro-
world. The installation of six of the mole sieve duction to Ekofisk Center commenced on June 28,
units was complete in July 1976. At that time the 1978. Permission has been given to simultaneously
plant was ready to receive gas but the pipeline drill and produce on Tor, however, regulations
was not operational. With the completion of a concerning simultaneous drilling and production
further three units in June 1977 this facility will make drilling of these wells slower than
took on a new distinction as one of the few plants originally anticipated.
to be expanded before operations began. Gas sales
began September 17,1977 after approval by Denmark Early operation at Tor was complicated by
of pipeline start up. Distribution is to Ruhrgas problems in hydrotesting the oil pipeline. To
AG, West Germany, Gasunie NV, Netherlands, facilitate start up, gas and oil production were
Distrigaz SA, Belgium and Gaz de France. An recombined at Tor and flowed to Ekofisk Center
average of 20 million m3 /d (735 MMCFD) has been through the gas line until the oil line was suc-
handled by the plant since start up with a single cessfully tested. This was just one of the several
daily maximum sales of 30.6 million m3 (1,143 improvizations that had to be made in order to
MMCF). To date, there has been no downtime due minimize slippages in schedules and maximize
to operational problems. production.

FIELD FACILITIES Edda Field - Platform 2/7-C is a 12 leg


drilling and production platform. The platform
As work progressed on the oil and gas pipe- was installed and all packages set by April 1978.
lines and at Teesside and Emden, field construction Separation at Edda will operate at 3,550 kPa (515
was in full swing. The major additional facilities psia). The oil will flow to Ekofisk Center via a
of Phase III and their current status are as 254 mm (10 in), 13 km (8 mil line. The gas will
follows (Figs. 3 and 4): be compressed, dehydrated and piped to Ekofisk
Center via a 305 mm (12 in) line. These lines
West Ekofisk Field - The 8 leg drilling should be laid and riser tie-ins completed in
platform, 2/4-D, was installed in April 1974. All April 1979. Drilling should commence in December
equipment was installed and drilling commenced by 1978 with production start up anticipated for July
January 1975. All 12 wells were completed by 1979 assuming approval for simultaneous drilling
September 1977 for an average drilling and comple- and production is given. Drilling of the 13 wells
tion time of 71 days/well. Drilling was suspended should be completed by November 1981.
from December 1975 through May 1976 while this
platform was used as quarters for the personnel Albuskjell Field - This field is a 50/50 unit
needed for repairs of platform 2/4-A after the between the Phillips Norway Group and Norske
riser failure and fire. The 610 mm (24 in), 8 km Shell. Development calls for two 12 leg drilling
(5 mil oil and gas line was completed in 1976. and production platforms, 2/4-F and 1/6-A. These
Production commenced from West Ekofisk on May 31, will be jointly owned by the Phillips Norway Group
1977 and current production is 11,000 m3 /d (70,000 and Shell. Phillips will be the operator for the
BOPD) . field. Both platforms were installed and all
drilling and production packages set by November
Cod Field - Platform 7/11-A, an 8 leg drill- 1977. Fifteen wells will be drilled from each
ing and production platform, was installed by platform by mid 1981. Drilling commenced on both
August 1975. Production equipment consists of a platforms the first quarter of 1978. Separation
first stage separator initially operating at on each platform will operate at 8,830 kPa (1,280
11,000 kPa (1,385 psia) and dehydration facilities. psia) and the gas will be dehydrated on the indi-
An allowance has been made for future compression vidual platforms. Compressor facilities will be
when reservoir pressure declines. The dehydrated added at a later date. pipelay and tie-in of the
oil and gas streams are recombined and flow through 457 mm (18 in) oil line and 610 mm (24 in) gas

304
line between 1/6-A and 2/4-F, 7.6 km (4.7 mil, and Ekofisk Center - With the start up of the oil
2/4-F and Ekofisk Center, 13 km (8 mil, should be line, the underwater storage tank had fulfilled
completed the first quarter of 1979. As with Tor, its initial purpose. Provisions had been made,
the pipelines are owned by the Phillips Norway however, for a steel deck completely covering the
Group. Start up of all facilities should be in tank at the 20 m (66 ft) level and for a concrete
the second quarter of 1979. deck covering 65% of that deck at the 30 m (98 ft)
level. These two decks provided over 10,700 m2
Eldfisk Field - Eldfisk development will (115,000 ft2) of space for all central processing
consist of three major platforms. Platform 2/7-A equipment. The 20 m (66 ft) deck was completed
is a 12 leg, 2 rig drilling platform connected to before towing the tank to location and the 30 m
an 8 leg production platform, 2/7-FTP. All pack- (98 ft) deck constructed offshore. In order to
ages were set on these two platforms by November process the 160,000 m3 /d (1 MMBOPD) and 56 million
1977. Drilling of the first well from both rigs m3 /d (2,100 MMCFD), Ekofisk Center has three 7,000
commenced in May 1978. Drilling of all 30 wells kPa (1,015 psia) separators, one 1,830 kPa (265
is scheduled to be completed the second quarter of psia) separator, two 690 kPa (100 psia) separators,
1981. Separation on 2/7-FTP will be operated at various miscellaneous separators, 3 glycol dehy-
3,550 kPa (515 psia). The gas will be compressed dration units, 3 gas processing (dew point) units,
and dehydrated. Both streams will be piped the gas pipeline compressors, heat exchangers, coolers,
5.6 km (3.5 mil to platform 2/7-B via a 610 mm (24 hot oil furnaces, communications and a computer
in) oil line and a 760 mm (30 in) gas line. controlled/satellite telemetry system.

Platform 2/7-B is a 12 leg drilling and Ekofisk Center began operation in February
production platform. All 2/7-B packages were set 1977. However, due to the incompletion of Tees-
by May 1978. Drilling of 19 wells is scheduled to side, 100 RVP crude could not be delivered.
commence in January 1979. Separation at 2/7-B Again, major improvizations were necessary in
will also operate at 3,550 kPa (515 psia) and the order to limit vapor pressure to 10 RVP. With gas
oil will join that from 2/7-FTP and be piped to delivery to Emden possible, dew point processing
Ekofisk Center via a 610 mm (24 in), 18 km (11 mil began through the facilities on the Center. The
line. The gas will be compressed, dehydrated and decision was made to temporarily change the in-
then joined with the gas from 2/7-FTP for transfer tended functions of Ekofisk Center and 2/4-FTP to
to Ekofisk Center Vla a 760 mm (30 in) pipeline. allow all crude production, even from outlying
fields, to be processed on 2/4-FTP. This allowed
The drilling and production schedule for second and third stage separators at the Center to
those fields in which drilling is not yet complete be used strictly for NGL handling. All gas vapors
is dependent upon Norwegian regulations concerning were routed to Ekofisk Center dew point facilities
simultaneous drilling and production. As men- and pumps were installed on 2/4-c in order to re-
tioned, permission has been given to drill and inject the NGL's into the formation, another
produce on Tor. As a result drilling will be industry first, while maximizing oil and gas
slower than anticipated and certain production production. Capabilities for spiking NGL's into
shut downs will be necessary. By maintaining a the crude line were also made. Utilizing this
safe operation at Tor it is believed that simul- system allows production of 80,000 m3 /d (500,000
taneous drilling and production will be allowed on BOPD), 34 million m3 /d (1,200 MMCFD) with 6,400
other platforms. If not allowed, production from m3 /d (40,000 BPD) NGL re-injected.
Eldfisk, Albuskjell and Edda could be delayed.
As 2/4-FTP facilities had not been designed
Each of the production platforms of Phase III for these high rates, it was apparent that as
will be connected to an emergency flare tripod. additional production came on stream, the first
These flares, including bridge support tripods, stage operating pressure of 7,000 kPa (1,015 psia)
will total 10 structures. These, in conjunction would result in overloading of the second and
with the drilling and production platforms for third stage gas recompressors. Original plans
outlying fields, the booster platforms on the oil called for a reduction of the first stage pressure
and gas lines and the interconnected structures at to 3,500 kPa (500 psia) and the installation of
Ekofisk Complex result in a total of 38 structures first stage compressors. To alleviate second and
necessary for Greater Ekofisk development. third stage overload this step was expedited and
the 3,500 kPa (500 psia) compressors began opera-
EKOFISK COMPLEX tion on March 15, 1978.

The facilities and platforms in the line of Oil production at Greater Ekofisk is related
interconnected structures making up Ekofisk Complex to gas demand which results in producing rates
were expanded during Phase III. The pump packages being cyclical. Peak production to date occurred
for initial operation of the oil line were in- last winter when oil production from Ekofisk, West
stalled on platform 2/4-p. A 12 leg riser plat- Ekofisk and Cod reached a maximum of 66,000 m3 /d
form, 2/4-R, was installed north of the tank for (415,000 BOPD) with gas sales of 30.6 million m3 /d
tie-in of all the oil and gas lines from outlying (1,143 MMCFD). Current forecasts call for a peak
platforms. Also located on 2/4-R are additional average annual production for the Phillips Norway
gas compression and separation equipment to Group of 100,000 m3 /d (650,000 BPD) of oil and 45
complement Ekofisk Center. North of 2/4-R, a million m3 /d (1,600 MMCFD) of gas and 8,000 m3 /d
second emergency flare platform was installed (50,000 BPD) of NGL's.
along with a final bridge support tripod. Total
length of the interconnected structures now The number of personnel involved in the
exceeds 1,200 m (4,000 ft). construction of Phase III has been phenomenal. In

305
late 1976 and early 1977 when offshore hook up and cafeteria, sauna and exerClse room.
construction as well as construction at Teesside
were at a peak, total manpower was as high as To complement all facilities in the Greater
13,500 people. Ekofisk Area, the world's first specially cons-
tructed semi-submersible utility and emergency
Present offshore personnel total 2,000. vessel, the Sedco/Phillips SS was built. This
These people are housed in permanent offshore vessel took up station in November 1977 and will
quarters capable of accommodating 802 people under serve as a floating workshop, diving base, fire
new Norwegian regulations for two men per room and station, hospital and hotel during its initial
in four offshore drilling rigs converted to float- five year tenure at Greater Ekofisk.
ing hotels, "flotels". Transportation of these
personnel is by helicopter. Fourteen flights per CONCLUSION
day transport a total of 213 people between
Stavanger and Greater Ekofisk. Including shuttling Development of Greater Ekofisk is close to
between platforms, a total of 180,000 personnel completion. Construction should be finalized in
were transported last year. 1979. Development drilling in all fields should
be completed by 1983. Total estimated development
Of the 802 permanent quarters, 280 are located cost to the Phillips Norway Group is $5.2 billion.
at the Ekofisk Complex. These accommodations Four fields are currently on production. The long
include the 212 man, 106 room hotel platform, 2/4- awaited revenue to repay the risks and efforts
H, (Fig. 3). This 4 leg platform with modules, undertaken by the Phillips Norway Group is being
connected by a bridge to 2/4-c, was installed in realized. These past nine years of development
1977. At a cost of $1,000,000 per room it must be have resulted in many technological advancements
one of the most expensive hotels in the world. It for the industry. Additional technological
is 5 stories high with 9,600 m2 (103,000 ft2) of advances should continue to be realized as the
floor space including the utility deck. Facilities project moves into its final phase - The Operation
will include a 186 seat cinema, 8 bed hospital, of Greater Ekofisk.

Fig. 1 North Sea development.

306
1,--~c------------:;;
M iM ..'"

I i

u..1
WEKOJSK~
'-I~
I
!

~,.~---~----~~-i---t.~"'~

EL~SK
)J ber
1970 I

--
o ,
'';,,,,.,

i
"00

Fig. 2 Greater Ekofisk fields.

7/11A
,/aA
COD
IS" OIL &
24" GAS
~~2/4F
ALBUSKJELL jj'4E:-:-
4.7 MI.
7-6 Km.)
,
----X'_
B /~~
-
TOR 0

/
16" 0 & G \ ,S"OIL & /
46.8 MI. 24" GAS
(76 Km.) ~ MI.
13 Km.b- 12" OIL &
14" GAS
7.5 MI.
R 112 Km.)
WEST 2/4D

EKOFISK~b --=. \\~""!'<IJ_--3


= 24" 0 & G
5 MI.

7
7/4~ (SKm.)
GNSC/S-l1

2/4A \ A --:... 36"


GAS
.I' \ __ 274 MI.
=
~
::3'i!r ':' 11 MI. 24"OIL & 443Km.)

;V E~~;--==-llf
36/22A 0
= .
.
10"OIL &
12"GAS 8 MI.
(13 Km.)
-=J=

--= /S.6KJ1'
{1SKm.)30"GAS-
'--
2/7S

EL~~7~K
-=

/OOIC/H-7
/1
4" OIL
220 MI.
~_ _ _ _"'-:--r_-",/3~S4,,-,K"'im.)
3.5
24"OIL & co
Mi~ 0
_
2/7FTP
"
n--,...-....;,---:7===,
30" GAS.-=.

TEESSIDE. ENGLAND EMDEN, GERMANY VIII

Fig. 3 Greater Ekofisk development plan.


NORWEGIAN NORTH SEA COMPLEX

==,-----i---~,.'~.~,.~-- '\', "-----

VOlin OI'VI.-f''''

::~:~
JlZlZ<D
:~~~ ~

....... "'
'"

!to . . ..,
tl_ ..e ,

'.-""

0'.'
'\.121)

-------'~ """ -~

~ ON PLANT
TUE~E~SI~DE~C.~U~D~E~O~IL~ST~A~.~IL~IZ~AT~I~~~

Fig. 4 Greater Ekofisk flow schematic.

S-ar putea să vă placă și