Project Name : CONSTRUCTION OF TWO-STOREY RESIDENTIAL BUILDING

Location : P-14 ERICSON SUBDIVISION, MANGKAROGO, POBLACION


BISLIG CITY, SURIGAO DEL SUR
Date of Completion: June 1, 2017 - August 31, 2017

# DESCRIPTION OF WORKS JUNE 1-30, 2017 JULY 1-31, 2017 A


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9
GENERAL REQUIREMENTS
1 Temporary Structure, Utilities, Service and Local Permits
Locational Clearance
2 Mobilization
3 Demobilization
4 Personal Protective Equipment(PPE)
5 Safety and Health
6 Project Billboard
7 Signage and Barricades
EARTHWORKS
8 Clearing and Grubbing
9 Excavation of Footing, Wall Footing, Tie Beam and Septic Tank
10 Embankment
11 Backfillingof Excavated Materials and Compaction
12 Gravel Bedding
13 Soil Poisoning
14 REINFORCED STEEL
15 Footings
16 Tie Beams
17 Column
18 Girders & Beams
19 Slab on Fill
20 Stairs
21 FORMWORKS & SCAFOLDINGS
22 Footings
23 Tie Beams
Column
24 Girders & Beams
25 Slab on Fill
26 Stairs
27 REINFORCED CONCRETE
28 Footings
29 Tie Beams
Column
30 Girders & Beams
31 Slab on Fill
32 Stairs
33 MASONRY WORKS
34 CHB Laying
35 Ceiling Works
36 Door & Windows
37 Water Proofing
Painting
38 Ceramic Tiles
39 ROOFING WORKS
40 Steel Trusses
41 Corrugated Metal Roofing

Prepared by: Check & Approved by:


Christian S. Consigna Engr. Jennifer Pagalan