ITP Reference

Number:AFISR/MEP/E/022

Project Title AL FORSAN HOTEL


Agreement No: Rev: 00
Inspection and Test Plan for: Installation of 11KV HV Switchgear Panel
GP-213 Date: 23-MAR- 13
Location:
Legends: ITL= Independent Testing Laboratory, SUB-CON= Sub-Contractor, CONT= Contractor, Inspection Points: H= Hold Point, W= Witness Point, R= Review
ITP= Inspection and Test Plan, CI= Comments Incorporated Point, S= Surveillance, A=Approval

Inspection Points
Inspection and Test Specification
Item No. Activity Description Frequency Acceptance Criteria Verifying Document / Report
Activity Reference SUB-CON CONT ITL ENGINEER

1 Material Approval

A33 Quality
Before site Standards and
Approved Material Submittal
1.1 11KV MV SWITCHGEAR PANEL Submit to the Engineer execution of the ENGINEER Approval Control,170.005 R R - R/A
Form
activity Standard and
Regulation

2 Drawing Submittal

Part A, A31
Before site
Provision,Content Approved Shop Drawings
2.1 H.V. Schematic Diagram Submit to the Engineer execution of the Workmanlike. ENGINEER Approval R R -- R/A
and use of Submittal Form
activity
Documents

3 Method Statement

Part B, Section V11,


Clauses
Before site
Method Statement for Installation 310.005,310.010,31
3.1 Submit to the Engineer execution of the Workmanlike. ENGINEER Approval R R -- R/A Approved Method Statement
11KV HV Switchgear Panel 0.015,310.020,310.
activity
025&310.0245

4 Delivery & Storage

Part B, Section V11,


Clauses
Visual Inspection for damages Every Delivery Proper identification, same as specification,
310.005,310.010,31 Material Inspection Check
4.1 11KV MV SWITCHGEAR PANEL and appearance. Inspection and movement of finish and packing. Storage and protection as H S -- S
0.015,310.020,310. sheet
for dimensions' verification material per manufacturers recommendation
025&310.0245

Page 1 of 2
ITP Reference
Number:AFISR/MEP/E/022

Project Title AL FORSAN HOTEL


Agreement No: Rev: 00
Inspection and Test Plan for: Installation of 11KV HV Switchgear Panel
GP-213 Date: 23-MAR- 13
Location:
Legends: ITL= Independent Testing Laboratory, SUB-CON= Sub-Contractor, CONT= Contractor, Inspection Points: H= Hold Point, W= Witness Point, R= Review
ITP= Inspection and Test Plan, CI= Comments Incorporated Point, S= Surveillance, A=Approval

Inspection Points
Inspection and Test Specification
Item No. Activity Description Frequency Acceptance Criteria Verifying Document / Report
Activity Reference SUB-CON CONT ITL ENGINEER

5 Installation

Part B, Section V11,


Clauses
Inspection for the proper For each floor Installation is as per the approved method 310.005,310.010,31
5.1 11KV MV SWITCHGEAR PANEL H H - A Quality Check Sheet
installation of Earthing system level statement 0.015,310.020,310.
025&310.0245

Comments if any:

MEP CONTRACTOR CONTRACTOR ENGINEER

SIGN: SIGN: SIGN:

NAME: NAME: NAME:

DATE: DATE: DATE:

Page 2 of 2