Royal Enterprises

Tank Summery Sheet


Fabrication /
SL NO DESCRIPTION Rolling Erection Welding NDT
Completed
1 Annular Plate Fabrication 7 Days 7 Day
2 Bottom Fabrication 15 Day Continue on Process
3 SC-5 5 Day 5 to 7 Day
4 SC-6 5 Day 5 to 7 Day
5 Curbe Angle 2 Day 5 to7 Day
6 Foam Deflector Plate 2 Day 2 day
7 Top Landing Platform/Handrailing Post 1 Day 2 Day
8 Primary Wind guider 10 Day 5 to 7 Day
9 Stair Case and Mid landing Platform 2 day Continue on Process
10 Colling Ring Support / Foam Riser Support 2 day As Rqd
11 SC-4 5 Day 5 to 7 Day
12 Secondary Wind Guider 5 Day 5 Day
13 SC-3 5 Day 7 to 9 Day
14 Bottom Sump Fabrication 3 Day 2 Day
15 Bottom Deck Fabrication Continue on Process
5 day
16 Deck Ring/ Bulk head Fabrication Continue on Process
17 SC-2 5 Day 7 to 9 Day
18 SC-1 5 Day 7 to 9 Day
19 Top Deck Fabrication Continue on Process
20 Deck Structure / Deck Rim Angle 5 Day Continue on Process
21 Foam Dam Plate Fabrication Continue on Process
22 Leg Support Fabrication 1 Day Continue on Process
23 Deck Box Man hole with Cover Fabrication 2 Day Continue on Process
24 Tank Manhole /COD /All Nozzle Fabrication 3 Day Continue on Process
25 Gauge well pipe with Sleeve Fabrication 2 Day 2Day
26 Rolling Ladder fabrication 5 Day 3 Day
27 Riser pipe Fabrication
10 Day
28 Colling Ring pipe Rolling and Fabrication 15 Day