HIRARC FORM

Company : VC Constructions Sdn Bhd Conducted by: Mr. Ismail (Supervisor)


Process: Roofwork (Name, designation) (5 April 2017 to 15 May 2017)
Approved by: Mr. Afwan bin Ismail Date: (from..to)
(Name/ Designation) (Manager)
Date: 25 April 2017

1. Hazard Identification 2. Risk Analysis 3. Risk Control

No Work Activity Hazard Which can Existing Likelihood Severity Risk Recommended PIC
. cause/effect Risk Control control Due date
(if any) measure /status
1 Install the drip edge Falls from Death or injury Guardrails, 5 4 20 Set up an Chia (23
height. safety nets intermediate April
guardrail 2017) /
completed
2 Transfer and Falling Being hit by Set up of 4 4 18 Tool belts to be Amber(26
placement of work object falling objects. scaffolding, used to prevent April
materials safety nets fall of 2017)/
tools/materials completed
from pockets.
3 Install slates and UV Dehydration, Personal 3 3 9 Use wide brim Ali (10
roof tiles exposure, Muscle cramp, Protective hat April
heat Heat stroke Equipment 2017) /
(PPE) completed
4 Getting on and off Falls from Death or injury Properly 5 4 20 Personal Fall Ahmad
the roof heights secured Arrest System (15 April
ladder 2017) /
completed
5 Transfer and Falling Being hit by 5 3 15 Use lifting Thomas (8
placement of work object falling objects. equipment April
materials 2017) /
completed
6 Installation of roof Awkward Back pain, 3 3 9 Job rotation and Thomas (8
tiles posture Musculoskeletal reassignment April
disorders (MSD) 2017) /
completed
7 Installation of roof Loud noise Hearing loss Hearing 3 3 9 Use of less Ahmad
tiles protection sound produce (10 April
tools 2017) /
completed
8 Installation of slates Slippery Death or injury 4 3 12 Complete Alia (9
and tiles roof Personal April
Protective 2017) /
Equipment completed
(PPE)
9 Roof installation on Fall or slip Death or injury 4 3 12 Signage such as Said (9
fragile roof surface from high warning sign April
2017) /
completed