Documente Academic
Documente Profesional
Documente Cultură
AND
DECISION
1. Business Day (appellant) lodged an appeal in this matter, and Trillian Capital
2. The respondent had filed a complaint against the appellant in respect of a story
which appeared in the appellants edition of 26 April 2017, with the headline
company; Politically connected Trillian supported bid. The story also appeared
company and politically connected Trillian supported bid. Actually, there was
an earlier online headline which was removed by the appellant within a few
hours of its appearance, and replaced by the one stated above. That headline
is not in issue. Part of the story was about the role the respondent played in the
the validity of which was being challenged by one of the failed bidders, namely,
1|Page
General Electrict (GE). Murray & Roberts (M&R) was the other failed
competitor. In his Ruling dated 24 June 2017, which is being appealed against,
Complaint
The company also complains that the reporter did not adequately
apology. The Ombud dismissed all the complaints except one, namely, that the
certain allegations respondent felt had been levelled against it. In this respect,
the Ombud held that the appellant breached articles 1.1, 1.2 and 3.3 of the
Press Code. The sanction imposed was an apology. Appellant felt the sanction
was too severe, and sought leave to appeal against it; however, leave was
denied.
Respondents Counter-appeal
Central to the dispute between the parties is a report known as a High Level
Review which was prepared by the respondent at the request of Eskom. Eskom
had to consider tenders from the above mentioned 3 companies, and the report
was to assist it in deciding on these bids, which were for the replacement of a
2|Page
boiler at one of Eskoms power stations. The report dealt with a very crucial
element of the tender, namely, the cost element. The bid by Dongfang differed
with those of its competitors in that, although higher, it was at a fixed amount
and therefore did not have an escalation element. Regarding the other two
competing bids, the report showed that there was a risk that costs could
subsequently turn out to be much more because of the escalation factor built
into them. It also indicated that with the Dongfang bid, Eskom would find it
5. The respondent complained that the story falsely implied that respondent
also that appellant falsely said that respondent favoured Dongfang. These
complaints can conveniently be dealt with together. It was argued for the
respondent that the headline and the first three consecutive paragraphs cast
the respondent as corrupt. That cannot be so, for the reason given below.
6. The headlines and sub-heads: The print headline and its sub-heads read: GE
Trillian
The appellant argues that the main headline is borne out by the story, the first
sentence thereof, and by other paragraphs further into the story; and that the
3|Page
factual accuracy of the headline was never challenged by the respondent. The
Electric on the part of Eskom. The appellant points out that the politically
connected allegation was never complained of, and says its assertion that it is
common cause was not challenged by the respondent. That the respondents
denied.
All the arguments in relation to the print headline and its sub-headlines hold
Eskom which is being accused of rigging the tender. The rigging could have
been in tandem with Dongfang, and not necessarily with the respondent.
Respondent also questions any reference to it in the headlines and the story,
on the basis that respondent was not part of the court case between General
Electric and Eskom. But the truth of the matter is that the story could not have
made sense without reference to the respondents report; there had to be some
background or context to the court case reported on. In any case, the story was
not exclusively about the court case; reference had to be made to the role
7. That the content of the story suggested corruption on the part of the respondent;
that is, that respondent improperly influenced Eskom and favoured Dongfang:
4|Page
7.1. It must be accepted, for a start, that the report was meant to influence
Eskoms decision; that must have been why Eskom commissioned it in the first
place, and for which it surely must have paid. That does not, however, amount
itself as provisional, and has some caveats, it is very emphatic about the fact
that the bids of other companies (GE and M&R) were more risky because of the
cost escalation factor and that, with Dongfangs bid, it would be easier for
Eskom to raise funds. On the face of it, the report was objective and not meant
7.2 The respondent argues that the Ombud erred in his Ruling that breach of
the Code is demonstrated only if the reportage was devised to impel readers to
assisting Eskom to rig the outcome of the tender. Respondent argues that the
Ombud set the bar too high. We do not agree. While the Ombud might indeed
have used the clause devised to impel readers, it is clear that he was not
setting the bar higher than usual. He was applying the usual standard by asking
the usual question: how would an average reader understand the story? This is
the question we need to ask, and answer, in the present case. In doing so, we
need not again define what is understood to be a reasonable reader; the test
is well known. It is our view that no inference contended for by the respondent
can be drawn by an average reader from the story, let alone that such an
inference would be the only reasonable one to be made. The contents state the
truth, and state in so many words that the respondent did not take part in the
5|Page
adjudication. For the same reason there was no need for a disclaimer against
heavy weather of the statement in the story that respondent gave the thumbs
than that the report, objectively looked at, speaks in favour of Dongfang. The
article went into details explaining, if not justifying, why the report favoured that
company.
8. We are of the view that the Ombud dealt well with the above complaints, and
find no justification to overturn his Ruling. For the reasons given by the Ombud,
Appellants Appeal
9. Prior to the publication of the story, the journalist sent a number of questions to
the respondent. The latter gave certain responses. It later complained that the
constituted denials of certain allegations against it. The Press Ombud found,
The journalist neglected report to Trillians denial [in response to what the Mail
any prior knowledge of or relationship with Dongfang and therefore did not
6|Page
been involved in a conflict of interest (for evaluating a sort-listed [sic]
He found that these omissions were in breach of articles 1.1, 1.2 and 3.3 of the
10. The respondent submitted that the Ombuds factual findings on the
materiality of the omitted response were correct and should not be lightly
disturbed on appeal.
11. The appellant points out that the part of the story on which the respondent relies
In 2016, the Mail & Guardian reported Trillian had helped Eskom in
talks to settle its insurance claim for the boiler after it exploded in
replace it.
Appellant says it is true the story said as stated above; but it says it was entitled
to so report and that it sought comment from the respondent, and the response,
Trillian said this week it had planned to submit a proposal with another
Chinese firm, HYPEC, during a previous bidding round that was cancelled. It
context, the statement and response do not convey that Trillian has a previous
7|Page
relationship with Dongfang; sourced it for the job; and then assessed its bid in
be added the fact that the story specifically mentioned that respondent did not
take part in the adjudication of the bids: This week, Trillian said it had merely
produced a cost-benefit analysis over a two day period for the Duvha bids and
12. From the portions of the story we reproduce above, as well as the appellants
were omitted, was not justified; we therefore disagree with the Ombud that the
appellant breached articles 1.1, 1.2 and 3.3 of the Code. Appellants appeal
therefore succeeds.
13.2 The finding made by the Press Ombud in his Ruling of 24 June 2017 that
the appellant breached articles 1.1, 1.2 and 3.3 of the Code of Ethics and
MINORITY DECISION
1. I concur with the Orders made in the Majority Decision. However, regarding the
though with the same results. In dismissing respondents complaint that the
8|Page
report transgressed article 3.3 of the Press Code, I have a different motivation
these [the first three] paragraphs or the article as a whole, that Trillian was
our view that no inference contended for by the respondent can be drawn by an
average reader from the story, let alone that such an inference would be the
only reasonable one to be made. The contents state the truth, and state in so
many words that the respondent did not take part in the adjudication.
Having taken all of the above facts and argument into account, I do not believe
that the article(s) impelled readers to wrongly conclude that Trillian was involved
correct.
4. The appellant also relied on the precedent set by the Appeals Panel in ANC v
Daily Dispatch, dated 3 November 2015, par. 25 and applied in Mail &
Guardian v Jesse Duarte, Press Appeals Panel, 21 Jun 2016, par. 7-8:
[N]either the Press Code nor South African law hold the author of a factual
article liable for any adverse inferences that are drawn by the reader. Critical to
this defence is that the facts (not the inferences) must be verified.
5. I respectfully submit that this precedent does not fully reflect the correct legal
9|Page
rebut wrongfulness. According to the Press Code the dignity or reputation of an
articles 3.3.1 to 3.3.5 which mirror the common law defences in defamation
cases.
6. Contrary to the Majority Decision (and also the Press Ombud) I, however,
reading the article and especially taking into consideration the juxtapositioning
that the respondent was in some way implicated with the alleged tender
rigging. This would then certainly have a negative impact on the respondents
reputation.
7. But this does not necessarily mean that the appellant was in breach of article
3.3 of the Press Code it could have a defence to override the reputation of the
respondent.
had adversely been involved in the alleged tender rigging, the appropriate
defence for the appellant would be as stated in article 3.3.4 of the Press Code:
9. Contrary to what the respondent argued, I find that the appellants report met
the requirements set in articles 3.3 and 3.3.4. It was reasonable to publish the
particular facts in the particular way at the particular time. The appellant based
10 | P a g e
reasonably; the respondent was given an opportunity to comment; and these
11 | P a g e