Alvaro Solano Milln Segundo examen parcial Diseo Vial

Clculo de Volumen #1

Vrtice Y (m) X (m) Vrtice Y (m) X (m)


0 0 0 0 0 0
1 0 5 1 0 5
2 -5 15 2 -2.5 10
3 -5 0 3 -4 0
4 -5 -15 4 -5 -15
5 0 -5 5 0 -5
0 0 0 0 0 0

Suma Y*X Continuas: Suma Y*X Continuas:


(0*5+0*15+-5*0+-5*-15+-5*-5+0*0)= 100 (0*5+0*10+-2.5*0+-4*-15+-5*-5+0*0)= 85

Suma Y*X discontinuas: Suma Y*X discontinuas:


(0*-5+0*-15+-5*0+-5*15+-5*5+0*0)= -100 (0*-5+0*-15+-5*0+-4*10+-2.5*5+0*0)= -52.5

2A= 200 2A= 137.5


A= 100 m2 A= 68.75 m2

Volumen 1: Relleno + Relleno

Volumen 1: 843.75 m3 (relleno)


18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

Clculo de Volumen # 2

0.0

-500.0

Vol umenes tota les a cumul ados (M3)


-1000.0

-1500.0

-2000.0

-2500.0

Vrtice Y (m) X (m) Vrtice Y (m) X (m) -3000.0


0 0 0 0 0 0
-3500.0
1 0 5 1 0 5
2 -2.5 10 2 -2.5 10 -4000.0
3 -4 0 3 -3 0
-4500.0
4 -5 -15 4 -2.5 -10
5 0 -5 5 0 -5
0 0 0 0 0 0

Suma Y*X Continuas: Suma Y*X Continuas:


(0*5+0*10+-2.5*0+-4*-15+-5*-5+0*0)= 85 (0*5+0*10+-2.5*0+-3*-10+-2.5*-5+0*0)= 42.5

Suma Y*X discontinuas: Suma Y*X discontinuas:


(0*-5+0*-15+-5*0+-4*10+-2.5*5+0*0)= -52.5 (0*-5+0*-10+-2.5*0+-3*10+-2.5*5+0*0)= -42.

2A= 137.5 2A= 85


A= 68.75 m 2
A= 42.5 m2

Volumen 2: Relleno + Relleno

Volumen 2: 556.25 m3 (relleno)


18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

Clculo de Volumen # 3

Vrtice Y (m) X (m) Vrtice Y (m) X (m)


0 0 0 0 0 0
1 0 5 1 0 5
2 -2.5 10 2 -2 0
3 -3 0 3 -2.5 -10
4 -2.5 -10 4 0 -5
5 0 -5 0 0 0
0 0 0

Suma Y*X Continuas: Suma Y*X Continuas:


(0*5+0*10+-2.5*0+-3*-10+-2.5*-5+0*0)= 42.5 (0*5+0*0+-2*-10+-2.5*-5+0*0)= 32.5

Suma Y*X discontinuas: Suma Y*X discontinuas:


(0*-5+0*-10+-2.5*0+-3*10+-2.5*5+0*0)= -42. (0*-5+0*-10+-2.5*0+-2*5+0*0)= -10

2A= 85 2A= 42.5


A= 42.5 m 2
A= 21.25 m2

Volumen 3: Relleno + Relleno


18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

Volumen 3: 318.75 m3 (relleno)

Clculo de Volumen # 4

Vrtice Y (m) X (m) Vrtice Y (m) X (m)


0 0 0 0 0 0
1 0 5 1 0 5
2 -2 0 2 -2.5 10
3 -2.5 -10 3 -4 0
4 0 -5 4 -5 -15
0 0 0 5 0 -5
0 0 0

Suma Y*X Continuas: Suma Y*X Continuas:


(0*5+0*0+-2*-10+-2.5*-5+0*0)= 32.5 (0*5+0*10+-2.5*0+-4*-15+-5*-5+0*0)= 85

Suma Y*X discontinuas: Suma Y*X discontinuas:


(0*-5+0*-10+-2.5*0+-2*5+0*0)= -10 (0*-5+0*-15+-5*0+-4*10+-2.5*5+0*0)= -52.5

2A= 42.5 2A= 137.5


A= 21.25 m 2
A= 68.75 m2

Volumen 4: Relleno + Relleno


18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

Volumen 4: 450 m3 (relleno)

Clculo de Volumen # 5

Vrtice Y (m) X (m) Vrtice Y (m) X (m)


0 0 0 0 0 0
1 0 5 1 0 5
2 -2.5 10 2 -2.5 10
3 -4 0 3 -3 0
4 -5 -15 4 -5 -15
5 0 -5 5 0 -5
0 0 0 0 0 0

Suma Y*X Continuas: Suma Y*X Continuas:


(0*5+0*10+-2.5*0+-4*-15+-5*-5+0*0)= 85 (0*5+0*10+-2.5*0+-3*-15+-5*-5+0*0)= 70

Suma Y*X discontinuas: Suma Y*X discontinuas:


(0*-5+0*-15+-5*0+-4*10+-2.5*5+0*0)= -52.5 (0*-5+0*-15+-5*0+-3*10+-2.5*5+0*0)= -42.5

2A= 137.5 2A= 112.5


A= 68.75 m2 A= 56.25

Volumen 5: Relleno + Relleno


18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

Volumen 5: 625 m3 (relleno)

Clculo de Volumen # 6

Vrtice Y (m) X (m) Vrtice Y (m) X (m)


0 0 0 0 0 0
1 0 5 1 0 5
2 -2.5 10 2 -2 0
3 -3 0 3 -2.5 -10
4 -5 -15 4 0 -5
5 0 -5 0 0 0
0 0 0

Suma Y*X Continuas: Suma Y*X Continuas:


(0*5+0*10+-2.5*0+-3*-15+-5*-5+0*0)= 70 (0*5+0*0+-2*-15+-2.5*-5+0*0)= 32.5

Suma Y*X discontinuas: Suma Y*X discontinuas:


(0*-5+0*-15+-5*0+-3*10+-2.5*5+0*0)= -42.5 (0*-5+0*-15+-2.5*0+-2*5+0*0)= -10

2A= 112.5 2A= 42.5


A= 56.25 A= 21.25 m2
18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

Volumen 6: Relleno + Relleno

Volumen 6: 387.5 m3 (relleno)

Clculo de Volumen # 7

Vrtice Y (m) X (m) Vrtice Y (m) X (m)


0 0 0 0 0 0
1 0 5 1 0 5
2 -2 0 2 2.5 10
3 -2.5 -10 3 1 0
4 0 -5 4 0 -5
0 0 0 0 0 0

Suma Y*X Continuas: Suma Y*X Continuas:


(0*5+0*0+-2*-15+-2.5*-5+0*0)= 32.5 (0*5+0*10+-2.5*0+1*-5+0*0)= -5

Suma Y*X discontinuas: Suma Y*X discontinuas:


(0*-5+0*-15+-2.5*0+-2*5+0*0)= -10 (0*-5+0*0+1*10+2.5*5+0*0)= 22.5

2A= 42.5 2A= -27.5


A= 21.25 m2 A= -13.75 m2
18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

Volumen en Relleno: Volumen en Corte:


1/3*(21.25)*10 1/3*(-13.75)*10

Vrelleno: 70.83 m3 Vcorte: -45.83 m3

Clculo de Volumen # 8

Vrtice Y (m) X (m) Vrtice Y (m) X (m)


0 0 0 0 0 0
1 0 5 1 0 5
2 2.5 10 2 5 15
3 1 0 3 3 0
4 0 -5 4 2.5 -10
0 0 0 5 0 -5
0 0 0

Suma Y*X Continuas: Suma Y*X Continuas:


(0*5+0*10+-2.5*0+1*-5+0*0)= -5 (0*5+0*15+-5*0+-3*-10+2.5*-5+0*0)= -42.5

Suma Y*X discontinuas: Suma Y*X discontinuas:


(0*-5+0*0+1*10+2.5*5+0*0)= 22.5 (0*-5+0*-10+2.5*0+-3*15+5*5+0*0)= 70
18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

2A= -27.5 2A= -112.5


A= -13.75 m 2
A= -56.25

Volumen 8: Corte + Corte

Volumen 8: -350 m3 (Corte)

Clculo de Volumen # 9

Vrtice Y (m) X (m) Vrtice Y (m) X (m)


0 0 0 0 0 0
1 0 5 1 0 5
2 5 15 2 5 15
3 3 0 3 4 0
4 2.5 -10 4 2.5 -10
5 0 -5 5 0 -5
0 0 0 0 0 0

Suma Y*X Continuas: Suma Y*X Continuas:


(0*5+0*15+-5*0+-3*-10+2.5*-5+0*0)= -42.5 (0*5+0*15+-5*0+4*10+2.5*-5+0*0)= -52.5

Suma Y*X discontinuas: Suma Y*X discontinuas:


(0*-5+0*-10+2.5*0+-3*15+5*5+0*0)= 70 (0*-5+0*-10+2.5*0+4*15+5*5+0*0)= 85
18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

2A= -112.5 2A= -137.5


A= -56.25 A= -68.75

Volumen 9: Corte + Corte

Volumen 9: -625 m3 (Corte)

Clculo de Volumen # 10

Vrtice Y (m) X (m) Vrtice Y (m) X (m)


0 0 0 0 0 0
1 0 5 1 0 5
2 5 15 2 5 15
3 4 0 3 5 0
4 2.5 -10 4 5 -15
5 0 -5 5 0 -5
0 0 0 0 0 0

Suma Y*X Continuas: Suma Y*X Continuas:


18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

(0*5+0*15+-5*0+4*10+2.5*-5+0*0)= -52.5 (0*5+0*15+5*0+5*15+5*-5+0*0)= -100

Suma Y*X discontinuas: Suma Y*X discontinuas:


(0*-5+0*-10+2.5*0+4*15+5*5+0*0)= 85 (0*-5+0*-15+5*0+5*15+5*5+0*0)= 100

2A= -137.5 2A= -200


A= -68.75 A= -100

Volumen 10: Corte + Corte

Volumen 10: -843.75 m3 (Corte)


18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

Volumetra Calle 5+000 a 5+100

Volmenes Relleno (m3) Corte (m3)


Volumen # 1 843.75 -
Volumen # 2 556.25 -
Volumen # 3 318.75 -
Volumen # 4 450 -
Volumen # 5 625 -
Volumen # 6 387.5 -
Volumen # 7 70.83 -45.83
Volumen # 8 - -350
Volumen # 9 - -625
Volumen # 10 - -843.75

V total: 3252.0833333333 -1864.58

Volmenes (m3)
Abscisas Cortes Terrapn suelto Terrapln compacto Corte + Terrapln V tot Acum

k 5+000 0.000
-843.750 -1124.997 -1124.997
k 5+010 -1124.997
-556.250 -741.665 -741.665
k 5+020 -1866.662
-318.750 -424.999 -424.999
k 5+030 -2291.661
-450.000 -599.999 -599.999
k 5+040 -2891.659
-625.000 -833.333 -833.333
k 5+050 -3724.993
-387.500 -516.665 -516.665
k 5+060 -4241.658
45.833 -70.833 -94.444 -48.611
k 5+070 -4290.269
350.000 350.000
k 5+080 -3940.269
625.000 625
k 5+090 -3315.269
843.750 843.75
k 5+100 -2471.519

Material de corte 1719 m3


18 Julio 2017
Alvaro Solano Milln Segundo examen parcial Diseo Vial

Material faltante 2571 m3

Grfico de la Curva Masa y Comentario

CURVA MASA
k 5+000

k 5+010

k 5+020

k 5+030

k 5+040

k 5+050

k 5+060

k 5+070

k 5+080

k 5+090

k 5+100
0.000

-500.000
Vol umenes tota les a cumul ados (M3)

-1000.000

-1500.000

-2000.000

-2500.000

-3000.000

-3500.000

-4000.000

-4500.000

aBSCISAS (M)

Comentario:

Como se muestra en el grfico, se puede apreciar y concluir que hizo falta material de corte,
por lo tanto, se tendr que buscar alrededor de 2570 m3 de material para la necesidad de
relleno a lo largo de la obra. El material total aproximado que se necesita para relleno son
4290 m3, contra 1720 m3 aproximadamente de material extrado que puede brindar el
segmento de la carretera por corte, por ende, la notable necesidad de obtener material para el
relleno faltante.