PROJECT PRGRESSIVE REVIEW MEETING

REHABILITATION & IMPROVEMENT OF 67KM LENGTH OF NAVATKULI


Project
KARATIVE-MANNAR ROAD (A032)

Subject MINUTES OF THE MONTHLY PROJECT PROGRESS REVIEW MEETING

Meeting date 05/10/2010 Time: 10.00 am

Venue Contractor Auditorium (CHEC), Mannar.

Meeting No. M-02

CONTRACT DATA

The Donor Chinese Government Funded.

The Client Road Development Authority.(RDA)


The Consultant Central Engineering Consultancy Bureau (CECB)
The Contractor China Harbour Engineering Co. Ltd. (CHEC)

Contract Amount LKR 6,532.5 M

Contract No RDA/NRRP/CGF/C2
Commencement Date

Contract Period 30 Months.

Date of completion

ATTENDANCE

NAME POSITION Contract Number / Email Address


1.Client
1.1 Eng. R.K. Abekoon Project Director/RDA 0773208540/ ranjanaka@gmail.com

2.Consultant
2.1 Eng.W.A.Ariyathilaka AGM/(EPC-R) /CECB 0712628628 / aricecb@yahoo.com
2.2 Eng.M.M.Joseph RE/CECB 0712204878/josephcecb@yahoo.com
2.3 Eng. C.N. Thilakasiri DE/CECB 0714488245/namal69@gmail.com
2.4 Eng.H.M.G. Jayasundara ME/CECB 0716824965/ hmgjayasundara@yahoo.com
2.5 Eng. M.U.C.P. Jayasekara CE/CECB 0714180328/ jayasekaramucp@yahoo.com
2.6 Eng.A.H. Dissanayaka CE/CECB 0718418014/ hansike039@yahoo.com
3.Contractor
3.1 Mr. Nanhai Zeng PM / CHEC 0777588718/ nanhaihainan@yahoo.com.cn
3.2 Mr.Zang Lingiu DPM/(CHEC) 0772069818
3.3 Eng. W.W. Bandara DE/ CHEC* 0812232501/ wwbandara@gmail.com
3.4 Eng H.M. Hemantha DE/ CHEC* 0773788535/ghbherath@yahoo.com
3.5 Mr.M.I.P. Mahagamage S.QS/ CHEC 0772674306/ manoj.savinda@gmail.com
3.6 Eng. Thayaparan PM/ CHEC* 0777711449/ thaya@access.com
3.7 Mr.Nadula Abeysinghe E & S Manager/CHEC 071141116753/ nadula2008@gmail.com
3.8 Eng. L.D.A.S. Rupasinghe QAM/CHEC 0773771861/aruna19692004@yahoo.co.uk

Page 1 of 4
PROJECT PRGRESSIVE REVIEW MEETING

NOTE: Any correction(s) or addition to Minutes of Meeting must be addressed during next meeting

Discussion No1 Acceptance of Previous Minutes of Meeting Action By


Conclusion &
Accepted by all parties
Action items

Discussion No 2 Review of Progress Action By

CHEC failed to submit the work programme in MS project as agreed in CHEC


progress meeting no. 01 and reminded to provide the same soon.

Progress
Conclusion & Construction of contractors office - 100%
Action items Investigation of quarry and soil pits - 70 %
Cross section survey -90 %
DCP Testing - 0%
Hydrological study and investigation - 50 %

Discussion No 3 Finance Action By


Conclusion &
No discussion
Action items

Discussion No 04 Design & Survey Action By

Surveying Works
The Engineer(CECB) mentioned to finalize the followings,
-Hydrological survey report and CHEC
-Traffic data to complete the pavement design. RDA

Employer (RDA) informed that Traffic data have already been requested
Conclusion & from RDA Head Office. RDA
Action items
CHEC informed their inability to start CS survey from 14+390 to 20+400
as the horizontal alignment had not been finalized. CECB

Design Engineer (CECB) agreed to complete the design review and


finalize the matter within one week. CECB

Page 2 of 4
PROJECT PRGRESSIVE REVIEW MEETING

Discussion No 04 Quality Assurance & Quality Control and Safety Action By

QA & QC
CECB questioned about the investigation of quarries and borrow pits
and CHEC agreed to provide an investigation report soon. CHEC
CECB requested to provide 03 quotations for different brands for the
purchase of Laboratory and Survey Equipment.
CECB question about the DCP tests and contractors design engineer
informed that presently available data of soil investigations were not
CHEC
adequate to do the design. He further suggested to do DCP tests in
Conclusion &
250m intervals (03 tests at one location) in zigzag manner and test pits
Action items
in 1Km intervals.
CECB requested to submit method statements and design criteria
before starting the tests. CHEC

Safety

Employer (RDA) informed that they had attempted to get the demining
report and agreed to expedite getting the same. RDA

Discussion No 05 Other Matters Action By


CHEC informed that prefab materials had been ordered and material
would be received by the end of October. CHEC

Contractor informed that he had submitted subcontractors quotations


to Engineer for the construction of PDs and Engineers quarters.
CECB informed to CHEC that necessity is to provide only one
reasonable estimate for the approval. CHEC

CECB requested to submit estimate for laying asphalt concrete instead


of DBST for the cost comparison. CHEC

Conclusion & CHEC requested written request for the above matter and CECB
Action items agreed to make a written request. CECB

CHEC agreed to provide a hired vehicle for the use of RE within a


week. CHEC

CECB requested to make arrangements to construct site office at


Mulankavil. CHEC

PD requested copies of Safety Plan, Quality Plan, Test report formats


and Hydrological study report. He further requested to send him copies
of future correspondence. CECB/CHEC

Page 3 of 4
PROJECT PRGRESSIVE REVIEW MEETING

CECB mentioned the requirement to available an inception report in


video form. ALL

CECB requested to expedite the purchase of computers and software


packages. CHEC

NEXT MEETING:
Next monthly meeting will be on 2nd November 2010 at 10.00 hrs at contractors office (CHEC)
- Mannar

Page 4 of 4