Documente Academic
Documente Profesional
Documente Cultură
CONTRACT DATA
Contract No RDA/NRRP/CGF/C2
Commencement Date
Date of completion
ATTENDANCE
2.Consultant
2.1 Eng.W.A.Ariyathilaka AGM/(EPC-R) /CECB 0712628628 / aricecb@yahoo.com
2.2 Eng.M.M.Joseph RE/CECB 0712204878/josephcecb@yahoo.com
2.3 Eng. C.N. Thilakasiri DE/CECB 0714488245/namal69@gmail.com
2.4 Eng.H.M.G. Jayasundara ME/CECB 0716824965/ hmgjayasundara@yahoo.com
2.5 Eng. M.U.C.P. Jayasekara CE/CECB 0714180328/ jayasekaramucp@yahoo.com
2.6 Eng.A.H. Dissanayaka CE/CECB 0718418014/ hansike039@yahoo.com
3.Contractor
3.1 Mr. Nanhai Zeng PM / CHEC 0777588718/ nanhaihainan@yahoo.com.cn
3.2 Mr.Zang Lingiu DPM/(CHEC) 0772069818
3.3 Eng. W.W. Bandara DE/ CHEC* 0812232501/ wwbandara@gmail.com
3.4 Eng H.M. Hemantha DE/ CHEC* 0773788535/ghbherath@yahoo.com
3.5 Mr.M.I.P. Mahagamage S.QS/ CHEC 0772674306/ manoj.savinda@gmail.com
3.6 Eng. Thayaparan PM/ CHEC* 0777711449/ thaya@access.com
3.7 Mr.Nadula Abeysinghe E & S Manager/CHEC 071141116753/ nadula2008@gmail.com
3.8 Eng. L.D.A.S. Rupasinghe QAM/CHEC 0773771861/aruna19692004@yahoo.co.uk
Page 1 of 4
PROJECT PRGRESSIVE REVIEW MEETING
NOTE: Any correction(s) or addition to Minutes of Meeting must be addressed during next meeting
Progress
Conclusion & Construction of contractors office - 100%
Action items Investigation of quarry and soil pits - 70 %
Cross section survey -90 %
DCP Testing - 0%
Hydrological study and investigation - 50 %
Surveying Works
The Engineer(CECB) mentioned to finalize the followings,
-Hydrological survey report and CHEC
-Traffic data to complete the pavement design. RDA
Employer (RDA) informed that Traffic data have already been requested
Conclusion & from RDA Head Office. RDA
Action items
CHEC informed their inability to start CS survey from 14+390 to 20+400
as the horizontal alignment had not been finalized. CECB
Page 2 of 4
PROJECT PRGRESSIVE REVIEW MEETING
QA & QC
CECB questioned about the investigation of quarries and borrow pits
and CHEC agreed to provide an investigation report soon. CHEC
CECB requested to provide 03 quotations for different brands for the
purchase of Laboratory and Survey Equipment.
CECB question about the DCP tests and contractors design engineer
informed that presently available data of soil investigations were not
CHEC
adequate to do the design. He further suggested to do DCP tests in
Conclusion &
250m intervals (03 tests at one location) in zigzag manner and test pits
Action items
in 1Km intervals.
CECB requested to submit method statements and design criteria
before starting the tests. CHEC
Safety
Employer (RDA) informed that they had attempted to get the demining
report and agreed to expedite getting the same. RDA
Conclusion & CHEC requested written request for the above matter and CECB
Action items agreed to make a written request. CECB
Page 3 of 4
PROJECT PRGRESSIVE REVIEW MEETING
NEXT MEETING:
Next monthly meeting will be on 2nd November 2010 at 10.00 hrs at contractors office (CHEC)
- Mannar
Page 4 of 4