Tender Ref No.

NEA000ETT16000148

14 December 2016

CORRIGENDUM NO. 1 TO TENDER REF NO. NEA000ETT16000148 FOR THE LEASE OF FOOD
WASTE RECYCLING MACHINES AND TRAINING SERVICES IN SCHOOLS

Dear Sir / Madam,

1. We refer to the above mentioned Invitation to Tender dated 2 December 2016. This
Corrigendum consists of 4 pages including this letter and its attachments.

2. Our replies to queries received are as follows:

S/N Question(s) Answer(s)


1 Do we have to submit both hard-copy and Please refer to Part 1 Section A: Instructions to
soft-copy documents? Tenderers. All documents shall be submitted to the
Agency using GeBIZ.

2 Is this an NEA or MOE initiated project? This pilot project is initiated by NEA.

3 What is the reason behind providing 10 This is a pilot project by the Agency. The Agency will
schools with the machine when it will be consider leasing up to 5 existing Machine(s) for
removed after 2 years? another 2 years after conducting a review of the pilot
(under Option to Extend).
Will NEA continue with the other 5
schools?
4 After the 2 years, what happens to the The contractor would have to retrieve the machines
machines? from the schools. Schools which are interested in
owning the machines may consider purchasing them
from the Contractor.

5 Will this tender be awarded to 1 contractor It will be awarded to 1 contractor.


or 10 contractors?

6 Are we required to supply the bins The Contractor is required to supply the bins upon
throughout the 2 years? What if the bins delivery of the Machines. The bins should be used by
become damaged within the first year due the schools during the 2 year lease.
to vandalism or misuse, are we expected
to replace them? Should the bins become damaged solely due to
improper use or mishandling by the Agency, the
Contractor would not be liable to replace the bins.
Please refer to Part 1 Section B: Conditions of
Contract, Clause 28 Warranty. The Contractor
should also work closely with the school to educate
the students on the proper usage of the bins.

1
7 Are these bins the same as recycling bins The design of the bins proposed by the tenderer is
(paper, plastic, metal)? dependent on the technology of the Machines. Please
refer to Part 2: Requirement Specifications, Part IV
Would there be a need for a separate bin Sufficient bins to segregate food waste.
to collect the liquids from the food waste?

8 Is the Contractor expected to provide the No, please refer to Part 2: Requirement
bins to collect the metal cans, plastic Specifications, Part IV Sufficient bins to segregate
bottles as well? food waste.

9 What happens to the compost from the The school will use the compost for their schools
food waste? activities. Please refer to Part 2: Requirement
Specifications, Clause 4a.

10 With regards to certifying that the compost Tenderers may test the compost against local (e.g.
is safe, who issues this certification? Is Centre for Urban Greenery & Ecology - CUGE) or
there a specific authority that can certify? other international standards and ensure that the
compost is safe and suitable for general landscaping
If the compost has been certified by use.
international standards, would that be
sufficient?

11 How dry should the compost be? The compost is acceptable as long as it is certified
safe and suitable for general landscaping use.

12 Does it matter if the system is in batches The machine must be able to convert between 5 to 20
or continuous process? kilograms of food waste into compost within 24 hours
daily. Please refer to Part 2: Requirement
Specifications, Clause 4a.

13 Who will be operating the machines? The respective schools will operate the Machines .
Please refer to Part 2: Requirement Specifications,
Clause 4a.

14 Will there be a mock-up test or evaluation The Agency will evaluate the Machines based on the
on the machines? technical specifications of the Machine proposed by
the tenderer.

The Agency will not do any mock-up tests on the


proposed Machine.

15 If the machine is sold internationally but The proposed Machine should comply with the
not in Singapore, would this machine be specifications stated under Part 2: Requirement
locally acceptable / approved by Agency? Specifications, Clause 4 and Clause 30.

The Agency will review the technical specifications


according to the above mentioned clauses.

2
16 Is the power for the machine provided? The proposed location(s) to place the Machines will
have the following pre-requisites:

- 2m by 2m space
- Sheltered area
- 1 power point (3 Phase, 415V, 63A)

Any additional electrical fittings will be setup by the


Contractor. Please refer to Part 2: Requirement
Specifications, Clause 4e.

17 How do you measure and track the The Machine should be able to measure and track the
electricity consumption of the machine? electricity usage. Please refer to Part 2: Requirement
Specifications, Clause 4e.

18 Is there an acceptable odour or smell The proposed Machines should be able to


threshold? mitigate/reduce any smell that might arise due to the
food waste processing. Please refer to Part 2:
Requirement Specifications, Clause 4c.

19 Is there any drainage area/water point? There is no drainage area or water point nearby. The
only output for this Machine should be compost.

20 Could the machines and bins be placed in The placement of the Machines may be decided after
a secured area to prevent vandalism from discussion with the schools. However, it is not
students? advisable to place the machines in a location that is
out of sight from the students as it does not resonate
with the objective of demonstrating the benefits of a
closed-loop system of managing food waste in
schools.

21 During the 2 months acceptance period, There is no line item in the Price Schedule for the
will NEA be paying the contractors for the work done during the first 2 months, prior to the
work done? delivery and installation of the Machines. Tenderers
may factor the costs under Leasing of 10 Food Waste
Recycling Machines. Please refer to Part 4: Price
Schedule, item 1.1 and 2.

22 During the school holidays when the Yes. The Contractor will continue to bill the Agency
machine is not in use, will the contractor every 3 months. Please refer to Annex D Payment
be paid? Schedule.

23 Under the service and maintenance Yes, the repair cost will be covered under warranty by
package, the repair cost will be under the contractors.
contractors? How about vandalism?
Please refer to Part 1 Section B: Conditions of
Contract, Clause 28, Warranty. Should the Machines
become damaged solely due to improper use or
mishandling by the Agency, the Contractor would not
be liable to replace the Machines.

The Contractor should also work closely with the


school to educate the students on the proper
operation and usage of the Machines.

3
24 Are the Machine(s) still under warranty Under the base contract, the length of the Warranty
upon extension of the Contract? Period shall be 24 months. Upon extension of the
Contract, the Warranty Period shall be further
extended for another 24 months.

25 How long is the maintenance down time? Please refer to Part 2: Requirement Specifications,
Clause 15 19.
If the machine is badly damaged and
requires some time to repair, what
happens to the food waste collected?

26 Is there a need to purchase Public Liability The Contractor shall be liable for and shall indemnify
Insurance? and keep the Agency fully indemnified against any
claims. Please refer to Part 1 Section B: Conditions of
Contract, Clause 31 Agency to Be Indemnified
Against Claims.

The Contractor may also decide to purchase a


suitable Public Liability Insurance Policy to cover the
amount of compensation for any personal injury or
death and/or damage or loss.

27 Based on your cost versus quality ratio, if Evaluation will be done based on the Evaluation
the cost is higher due to the thorough Criteria stated under Part 5: Evaluation Criteria.
proposal as compared to a cheaper one,
will you choose the cheaper one? Tenderers are to note that a minimum of 50 quality
points is required to qualify for further evaluation.

28 Under Annex A Schedule of Contracts Yes, tenderers may include relevant overseas projects
Currently Executed by Tenderer, can we from 2013 till present in Annex A.
put in relevant overseas projects?

3. This Corrigendum shall be read in conjunction with the tender documents and shall form part of
the tender documents. All other terms and conditions of this tender shall remain unaffected.

<<signature is not required for electronic copy>>


PAULA KESAVAN
DEPUTY DIRECTOR
SCHOOLS & YOUTH DEPT, 3P NETWORK DIVISION