Documente Academic
Documente Profesional
Documente Cultură
Introduction
The process of calculation for drain and sewers pipes involves the
determination of fixture units, and the developed length of piping, using
specific tables. Paying attention to details is an important element in
designing any type of system, and this certainly holds true when sizing
drains and sewers. Moving too quickly and using the wrong sizing table can
cause you a lot of error. If you read the tables carefully and apply them
properly, sizing is not difficult. Some engineers get so accustomed to using
sizing tables that they fail to think of code requirements that may make
the tables inaccurate if all notes are not observed and followed.
Accuracy in sizing pipes is essential to a job in more than one way. First,
you have to draw riser diagrams and size the pipes for code approval. On
the other hand all types of drains and sewers can be calculated with a
method that depends on the ratings of drainage fixture units. Fixture-unit
ratings are established by local codes. A probability factor is built into the
system. While a direct flow rate or discharge rate cannot be determined
from the rating of fixture units, the fixture units are accurate enough to
2
allow a sensible system to be designed, in compliance with the plumbing
code.
DRAINAGE AND SEWERAGE SYSTEM
a- Safe Drainage System
All sanitary drainage systems should be connected to the public
sewer system (wherever available) at the nearest possible
point. In case the public sewer system is not available, a safe
and non-polluting drainage system must be ensured. The
drainage system should be so designed as to guard against
fouling, deposit of solids and clogging.
b- Vent Pipes
The drainage system should be designed to allow for adequate
circulation of air within the system, thereby preventing the
danger of siphonage or unsealing of trap seals under normal
3
working conditions. The system should have access to
atmospheric pressure and venting of foul gases by vent pipes.
4
c- Exclusion of Foreign Substances from the System
d- Ground and Surface Water Protection
e- Prevention of Contamination
f- Prevention of Sewage Flooding
5
Vent Pipe
Junction Box
Floor drain
6
Sanitary
Drainage
Vent drain
7
W.C. Pipe Vent pipe
Bidet drain Sanitary
pipe
Floor
drain
Bath tube
drain Lavatory
drain
8
Ac drain Lavatory
WC drain
Drain
Bidet
Drain
F.D.1 F.D.2
9
DWV Systems
D = drain tubs & sinks
W = waste from water closets
V = vent air into / out of the system.
11
Fixture Unit Tables
The information in Table 1[a-b & c] representative of what you might
find in your local code book. This is the type of table that assigns
specific ratings for fixture units on given fixtures. In cases where a
known fixture is not listed, another type of table, like the one in figure
[1-d] is used to assign ratings for fixture units.
Before we get too many tables in front of us, let's go over the three
tables that you've just been introduced to.
Dont make mistakes by not paying attention to footnotes and exclusions when
10 you use sizing table
Table 1-a
11
Table 1-b
12
Ref [2]
Table 1-c
13
Ref [2]
Is used for fixture not listed in the previous table. For example the
Table 1-d
By Size of trap
floor drain with 2 pipe diameter, the corresponding DFU is 3 14Ref [1]
15
Number Fixtures DFU Diameter
1 Lavatory 1 1.1/2- 2
1 Bidet 1 1.1/2- 2
1 Floor drain * 2x 3 3
1 Bathtub 2 1.1/2- 2
1 W.C.s (flash Tank), 4 4
Total 8 F.U
DFU
1 Lavatory 1 1.1/2-
2
1.1/2- 2
1 Bidet 1
1 Floor drain * 3
1.1/2- 2
2 Bathtub 2*2
1 W.C.s (flash 4 4
Tank),
Total 10
DFU F.U
18
Sizing Horizontal Branches
Let's talk about how you can size a horizontal branch. We're going to
use a sizing table because they're easy, fast, and accurate. Look at Fig
below (2). This table shows you the maximum number of fixture units
that may be placed on a single horizontal branch of a given size.
Stack Sizing
Stack sizing requires you to know the number of fixture units that will
discharge into the stack from a single branch and the total number of
fixture units that will be allowed on the stack. So, let's say that you
have a stack with two branches. There is a bathroom group on each
branch, and those two bathroom groups are all that will discharge into
the stack. What size pipe is the smallest allowable for use as the stack?
25
To figure this, use the table in Fig. 2
26
Table 2
27
Table 2 is used for sizing drainage stacks provides different
permissible loading for stack of 3 stories or less in height and
for stacks more than 3 stories in height. Included in the table
are the maximum loads permitted on any horizontal fixture
Branch.
Horizontal fixture branch
28
Example 1
29
Solution:
30
Example :
32
Figure below illustrates an example of sizing the main branch which connected to the
basement floor where a flow from a sump pump is also connected to the same pipe.
The building has four soil stacks. The total fixture units for each stack are given.
1- Size each stack using Table 2.
2- Size the horizontal branches from the base of a stack to the building drain according
to its fall per foot (1/8) and (1/4) using (Table 3 next page).
N.B. The discharge from the sump is converted into fixture-unit values by
multiplying the number of gallons flow by 2. That is 100 gpm x 2 = 200 FUs
33
1.04%
Solution
1.04% 2.1%
34
Table 2
Vertical for
Horizontal per
each floor
floor
35
Riser Offsets on drainage piping
An offset in a vertical
stack, with a change of
direction of 45 degrees
or less from the vertical,
may be sized as a straight
vertical stack.
36
Example :
32
Ref [6]
Step 4:
Size the lower portion of the stack from the fifth floor down
through the street floor. The lower portion of the stack must
be large enough to serve all the fixture units connected to it,
from the top floor down, in this case, 1200 fixture units.
According to Table 2, 1,200 fixture units require a 6-inch
stack.
Step 5: Size the offset below the street floor the same as
for a building drain. The lower offset also has to be large
enough to serve all fixture units from the top floor down, in
this case, 1200 fixture units. According to Table 3, 1200
fixture units require an 8-inch offset. This 8-inch line is run
full size to the building drain.
41
The offset on the fifth floor should be provided with a relief
vent. Sizing the offset larger than the stack and providing a
relief vent will prevent pressures from building up at the point
of offset and possibly siphoning or blowing nearby trap seals.
The critical point of a soil stack is at the base and where
an offset occurs.
Review the sizing of sewage network
44
Size the following restaurant toilet
45
46
Table 3-b
For 4 pipe diameter, having a slope of 1.04%, the Max. DFU is 180 , However
if the slope is 4.2%, the DFU becomes 250
47
48
Two pipe system S.S. Vent pipe Vent pipe
49
One pipe system
S.S.
( Most popular )
Vent pipe
50
43
Ref [2]
Sanitary Drainage
Similar to loading or demand units in water Materials
for sanitary pipework
Cast iron 50 mm and above vent and discharge Lead caulking with molten or fibrous
stacks lead; cold compound caulking
Polypropylene
Up to 50 mm waste and ventilating pipes Push-fit ring seal and compression
and traps couplings
Modified PVC Up to 50 mm waste and vent pipes Solvent cement and push-fit ring seal
Pitch fibre Over 50 mm discharge and vent stacks Driven taper or polypropylene fitting
45
with a push-fit ring seal
52
Drainage for Basement
53
Drainage for grease/ oil generating area car park and
grease trap Petrol Interceptor
56
what your drawings
might look like.
Drains are drawn
with solid lines,
while vents are
indicated by broken
lines.
Drainage
Riser diagram
57
58