Documente Academic
Documente Profesional
Documente Cultură
4. Contract Administration (refer Private Standard Form with Quantities for HK)
Contd
K. Determination by Employer ()
This is difficult for the Employer to establish and the Contractor could argue,
depending on the circumstances, that he had reasonable cause for the alleged (
) failure.
For example, if the Employer were persistently late in honoring Interim Certificates
or under valuation in Interim Certificates this could well be reasonable cause for
slowing down the progress of the Works by the Contractor.
(d) Failure to comply with Clause 19.1 Assignment. The Contractor must not
assign any part of the works without the appropriate written consent from the
Employer.
(e) Failure to comply with Clause 19.2 Sub-letting. The Contractor must not
sub-let the whole or substantially the whole of the Works to the same person.
@VTC2013 1 of 5
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
@VTC2013 2 of 5
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
(1) The Architect must serve notice on the Contractor specifying the default, so as
to provide the opportunity of remedying the default by the Contractor.
(2) On receipt of the notice the Contractor has three courses of action available to
him:
The Employer may employ others to complete the Works, who for this purpose,
may enter the Site, use all temporary buildings, plant, tools, goods and materials
intended for them; and purchase all materials and goods required for completion.
The Contractor shall not remove any materials, goods, temporary buildings,
plant or equipment from the Site until instructed by the Architect;
The Contractor shall if so required, assign to the Employer the benefit of any
agreement for the supply of materials or goods and/or the execution of any work
under the Contract.
The Contractor shall, when required by the Architect, remove from the works
any temporary buildings, plants, tools, equipment, materials and goods belonging to
or hired by him. If within a reasonable time after such a requirement, the Contractor
has not complied, then the Employer may remove and sell any such property. The
proceeds, less all cost included, will be held by the Employer to the credit of the
Contractor.
The Employer is not bound to make any further payment to the Contractor until
the completion of the Works. The balance between the value of the work completed
and the value of the work certified, less the amount of the direct loss or damage
@VTC2013 3 of 5
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
caused by the determination will be computed in the final account and handle
accordingly.
L. Determination by Contractor ()
(a) Fail to make payment of certificates. If the Employer does not pay amounts
properly due on certificates within the period for payment of certificates (say
14 days), the Contractor may exercise his right to determine his own
employment under the Contract.
(b) Interference with or obstructing the issue of a certificate to the detriment of the
Contractor. Such interference by the Employer would include any attempt to
prevent the Architect issuing a certificate of any kind to the Contractor.
(c) Failure to comply with Clause 19.1(1) Assignment. The Employer must not
assign any part of the works without the appropriate written consent from the
Contractor.
(d) Postponing the date for commencement of the whole of the Works or
substantially the whole of the Works for a period of 120 days or more due to
Architects Instruction under clause 23.3.
(e) Suspension of the Works or substantially the whole of the Works for a period
of 120 days or more due to Architects Instructions under clause 23.3.
The Contractor may give a notice of determination of his own employment if the
Employer insolvent which includes:
@VTC2013 4 of 5
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
The obligation of the Contractor to carry out and to complete the Works shall be
suspended immediately if the Employer is insolvents and before any notice of
determination of his own employment takes effect.
The Contractor serves a notice of default to the Employer specify the default and
state that notice of determination may be served if the default continues for a further
14 days.
If the Employer continues with the default after 14 days of receipt of such notice of
default, the Contractor may determine his own employment by serving a notice of
determination to the Employer within a further 14 days.
The Contractor must forthwith remove all his temporary buildings, plant, tools,
equipment, materials and goods.
The Contractor is entitled to receive payment from the Employer for the total
value of work completed or partially completed up to the date of determination.
Direct loss/ and or damage, loss of profit etc. caused to the Contractor due to
the determination.
@VTC2013 5 of 5