Republic of Iraq
Ministry of Electricity
CHAPTER 3
SCOPE OF WORK
TOTAL PAGES: 40
Including this page
Page 1 of 39
Table of Contents
3.1 General.........................................................................................................................................................2
3.1.1 Plants terminal points............................................................................................................3
3.1.2 Fuels supplies.........................................................................................................................3
3.1.3 Water supplies........................................................................................................................4
3.1.4 Electrical connections.............................................................................................................4
3.1.5 Communications.....................................................................................................................4
3.1.6 Drainage..................................................................................................................................4
3.1.7 Project systems and conceptual design...........................................................................5
Page 2 of 39
3.Scope of Work
General
The project will be constructed on a full design and build, turnkey basis, and it will be the
responsibility of the Contractor to ensure that all equipment, scope of work and services are
provided in order to render the power plant fully complete and functional for safe, reliable and
commercial operation under all conditions and respects.
Summary scope of work comprises from the following:
Externals Works outside the plant fence which will be the scope of work of others and the
Contractor have no responsibility upon.
Equipment supplied by Siemens under Siemens contract with MOE (The Contractor shall be
responsible for installation, commissioning and put into operation as per Siemens drawings &
vendors erection instructions)
All items specifically excluded from Siemens scope of supply and necessary for a correct operation
of the plant, should be assessed fully & carefully by the contractor and included in its scope of
works, all systems inside the plant fence shall be installed by the Contractor.
Balance of Plant (BOP) Systems necessary to complete Siemens scope of supply and all Civil Works.
The Contractor shall be responsible for the design, manufacture, testing in workshops, packaging
for export, shipping, transport, delivery to Site, unloading at Site, install, commissioning, putting
into operation and testing these systems as well as design all Civil Works and construct of these Civil
Works of the plant .The installation works of the Contractor cover all plant items up to the terminal
points indicated here in 3.1.1, including Siemens furnished equipment.
Technical field assistant and supervision for equipment furnished by Siemens will be provided by
contractor and approved by Siemens.
The warranty obligations of the Supplier (Siemens) which will be the responsibility of
contractor to maintain are conditioned upon:
All of the TFA (Technical field assistant) as recommended by the Supplier for the erection and
commissioning performed by contractor(s) should be approved by Supplier (Siemens).
Proper storage, erection, installation, commissioning, operation, use and maintenance of the Scope
of Work in conformance with the Erection/commissioning and operation manuals and operating
criteria and procedures provided by the Supplier, and Documentation of all installation and
commissioning check/test steps on quality plans and/or commissioning programs provided with the
erection/commissioning manuals by the Supplier, and submittal of these compiled on site quality
assurance documentation to the Supplier by the Purchaser .
Timely repair or modification pursuant to the Supplier's instructions and approval.
Page 3 of 39
The Contractor shall be also responsible for health and safety management during the
erection and commissioning period, final paintings and touch-up painting of items
supplied by others, instructions to Employers personnel and obligations for the defects
liability period.
All material, plant and equipment supplied by the Contractor shall be new and of a class
suitable for the purposes specified. Equipment shall be selected to ensure high reliability
and availability of the complete plant with low forced outage rates and minimal
maintenance. Permanent, safe access to all items of plant designed by the Contractor shall
be provided for inspection, operation and maintenance. The Contractor shall be responsible
to check and propose modifications, if necessary, of the proposed general arrangement
with the exception of the power island.
The Contractor shall assess the proposed termination points for all services and shall agree with the
Employer an appropriate tie-in point and tie-in schedule. The location and schedule shall, where
applicable, be designed to minimize inconvenience to other users of the systems. The Contractor
shall clearly identify in the contract program the date it requires the terminal points to be available.
Fuels supplies
The Contractor shall be responsible for the connection of the fuels supplies to an agreed
termination point located adjacent to the site boundary. The exact location of the termination point
will be finalized during Contract negotiations.
The expected analysis of the fuels is annexed to these specifications. The Contractor shall be
responsible, as soon as the external connections will be available, to check, with measurements and
analysis, if fuels satisfies the expected characteristics and, in case discrepancies are found, he shall
immediately inform the Employer of such discrepancies.
The supplier of the fuel forwarding systems has to ensure, that the fuels fulfill all the attached
requirements (chemical properties, temperatures, pressures in forward and also in return flow,
mass flow, maximum allowable speed of changes in pressure etc). It has also to be considered, that
in return flow mixtures of water and fuel are to be expected in DENOx operation and that in case of
fuel oil dosing the return flow oil will contain the dosing chemicals .Regarding the ignition gas
supply we want to highlight that it must be ensured that the pressure range is kept within allowable
range during the full ignition process (tank quantity needs to be large enough and tank heating
system is recommended, quality of ignition gas must meet spec., piping to turbine must be of
sufficient size and maybe trace heated etc.).
Page 4 of 39
Again: it is of the essence, that all requirements are completely fulfilled. Therefore it is import that
whoever designs these pre-systems for the supply of fuel, and ignition gas studies the enclosed
documents carefully and contacts SIEMENS in case of questions to make a hundred percent sure
that no details are overlooked or misunderstood.
ATTACHED SIEMENS REQUIREMENT (ANNEX TO CHAPTER 3)
Water supplies
The Contractor shall be responsible for the connection of the water supply to an agreed termination
point located adjacent to the site boundary. The exact location of the termination point will be
finalized during Contract negotiations.
The Contractor shall be responsible, as soon as the external connections will be available, to check,
with measurements and analysis if the water satisfies the expected characteristics and in case
discrepancies are found, it shall immediately inform the Employer of such discrepancies.
The supplier of the WATER TREATMENT systems has to ensure, that the TREATED WATER fulfill all the
attached SIEMENS requirements (ANNEX TO CHAPTER 3).
Electrical connections
Electrical power from the gas turbine generator packages shall be exported to, and be compatible
with, the electrical connection provided by the Employer. The HV switchyard outlet gantry structure
will be the terminal point of its supply.
The Contractor shall establish communication protocols and liaise with the Ministry of Electricity to
ensure that all appropriate safety requirements are fulfilled.
Communications
All connections to the public telephone network shall be the responsibility of the Contractor. The
Contractor shall ensure that all communication systems used during construction and operation of
the Site meet appropriate regulations and do not cause interference with any communication or
electrical equipment on the surrounding site.
Drainage
The termination points for the drainage systems shall be sub-divided into surface water, sewage
water, chemical and oily water systems as per the paragraphs here below.
Surface water
The surface water system should collect rainfalls on the whole station into a system of
underground pipes, manholes and discharge it into an existing system if available, providing
sufficient capacity is available. If no existing surface water system is available, the discharge
shall be arranged to a soak away to be agreed with the Employer.
Page 5 of 39
Sewage water
Sewerage treatment plant shall be provided to process the sewage drainage on site. Where
there is an existing public sewage drainage system available, the treated fluid shall be
discharged into the public system, otherwise the treated effluent shall be pumped to an
evaporation pond which supply shall be agreed during the Contract negotiations.
Systems
The systems of project plant are listed in the following table.
Page 6 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
THE CONTRACTOR SHALL COMPLETE ALL THE SHORTAGES OF THE SUPPLIED MATERIAL & EQUIPMENT BY SIEMENS
MENTIONED IN APPENDIXES( APPENDIX 1 ,APPENDIX 2,APPENDIX 3 ).(EXCLUSION,TERMINAL POINTS,CLARIFICATION)
WHICH ARE NECESSARY TO RENDER THE POWER PLANT FULLY COMPLETE &RELIABLE FOR COMMERCIAL OPERATION.
ATTACHED APPENDIXES
Page 7 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 8 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Oil / air cooler (fin-fan type) with spray water system Siemens
Air intake systems per gas turbine Siemens
1. Pulse filters system.
2. Inlet air filter house including weather hood, bird screen,
internal.
3. Support structure, instrumentation, lighting, power sockets,
and manhole.
4. Access ladders, staircase, platforms and doors
5. Interconnecting duct work with expansion joint, damper and
silencer
6. Electrical hoist for maintenance (250kg)
7. Pulse compressor 1 ~100%
8. Anti-icing
9. Dehumidifier for gas turbine standstill
10. Nozzle system for compressor cleaning inside air inlet duct
Exhaust gas systems per gas turbine Siemens
1. Diffuser
2. Exhaust stack (32 m height)
3. Silencer
4. Support frame
5. Expansion joints
6. Aircraft warning lights
Noise control installations at gas turbine: Scope per gas siemens
turbine
comprises
1. Structural steel with corrosion protection
2. Noise hoods for combustion chambers with silencers on top
and with doors to the gangways
3. Mobile sound barrier walls enclosing the combustion
chamber elbows
4. Sound barrier panels alongside the gas turbine and at
Page 9 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 10 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 11 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Base frame
Stator core; made up of dynamo sheet segments,
stacked and pressed together with insulated non-
magnetic through bolts
Stator winding; three-phase, double layer type made up
from transposed
solid strands with MICALASTIC@ post impregnation
Rotor, consisting of:
Shaft from one piece forging; rotor winding made up of
silver alloyed low oxygen copper conductors with radial
cooling
Rotor retaining rings; one piece construction, made up of
non-magnetic steel, which is not susceptible to stress
corrosion cracking and is shrunk onto the rotor body
Single-flow axial fans arranged on the rotor shaft for
circulation of the cooling medium
Steel slip rings arranged on generator shaft
Bearings
Sliding contact bearings with jacking oil device; insulated
towards ground; designed for external bearing lube and jacking
oil supply
(turbine scope)
Auxiliaries and further equipment siemens
All instruments wired to plugs or junction boxes
Provisions for vibration monitoring at bearings Cover
Bushings suitable for mounting current transformers
Cooler cover, consisting of:
-Cover, attached to generator cover
-Air-to-Water cooler elements (25% each)
Rotor grounding brushes
Space heater
Anchor bolts and nuts
Page 13 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 14 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 15 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 16 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 17 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 19 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 20 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 21 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
two (2) Sets Tee off to the GT auxiliary transformers (10 m. for Siemens
each phase1 unit)
Generator Circuit Breakers Siemens
two (2) pieces SF6 generator circuit breakers for GT generators Siemens
comprising the
necessary control, monitoring and protection facilities
Page 22 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 23 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Bus couplers & High Speed Busbar Transfer System scope of Siemens
supply:
One (1) cubicle ;Bus couplers with 1250 A vacuum circuit
breaker
one (1) cubicle; Bus coupler return
One (1) cubicle; 1 set of High Speed Busbar Transfer Systems
Page 27 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Additional (switchgears,
transformers,protective, high speed
14. transfer ,devices,cables,trays.etc)
for BoP supply(which supply by the
contractor)
Additional CONTRACTOR
equipments(motors,valves,Actuator
s .etc)
All type of cables,cable
trays,ladders to interconnection the
systems & equipments (Siemens
supply & EPC contractor) of plant.
15. I & C for BoP supply by Contractor
instruments & equipments
Black boxes with it
accessories,control panels ,PLC& CONTRACTOR
MMI.
Recorder,analyzer,control desk &
conventional control equipment,
local announciators,Push buttons
Page 28 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Page 30 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
2) Flushing fluids, possible chemical consumables for gas turbine and generator. Contractor
consumables necessary for commissioning works of other plant systems and
consumables (oil and chemicals) for the first six months.
3) Fuel gas station, Pressure Reducing station, heating station, with gas pipe & Contractor
supports required to deliver gas to the gas turbines at the required
conditions according to (SIEMENS GAS TURBINE REQUIREMENT) . (for 4
Units including the two units of Power machine).
4) Sound wall, or enclosures, expansion joint with flanges and counter flanges) Contractor
exhaust system.
7) Aux. tanks for false start oil and wash-water receiver Contractor
9) LFO tanks
Page 31 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
11) HEAVY FUEL OIL (HFO) FORWARDING AND TREATMENT SYSTEM contractor
COMPLETE TO MEET SIEMENS GAS TURBINE REQUIREMENT
COMPRISE OF:
8.1. HFO transfer
12) Heavy fuel oil (HFO) unloading and metering system Not Required
Page 32 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
21) Pumps, Valves & Various piping ( inter connection piping from fin fan coolers
to turbo set , piping between lube oil skids and heat exchange, vent pipes ,
drainage pipes , demin water pipes to coolers , turbine and water injection
pump , Piping from and to tanks, piping for fire fighting, piping to gas turbine Contractor
package inlet flanges, Instrument pipes etc) ) piping for interconnection all
systems of plant(Siemens supply & BOP supply) ,(including support system,
trace heating ,insulation etc )
22) Various lifting equipment & crane in these building ( main turbine hall Contractor See annex to chapter 6
Page 33 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
crane ,above Gen cooler ,Above Gen exciter & bearing ,above lube oil, above
Gen bearing,fire fighting pump house ,Emergency Gen,gas reducing station ,
400kv GIS ,auxiliary hoists,Crane above intermediate shaft, ,IPE
(450x190x9.4) 71 m long,with all accessories required for installationfor
work shop crane.
23) HVAC split units for offices and BoP control and battery room, central HVAC Contractor
system for control & switchgear building, water buffered cooling and
heating system for gas turbine halls, ventilation air inlet filters with first fill of
HVAC system with cooling agent.
24) Fire alarm, Fire fighting system & pump, for complete plant including Contractor Except where provided by SIEMENS
underground piping, hydrants, Foaming etc for fuel tanks , fuel
conditioning and forwarding system,CO2 system package area for all
equipments in gas turbine hall with under ground ,diesel generators
building, etc. (except substation which are included in main contract),with
first fill of foaming agent of the fire extinguishing system ( Should cover &
Include equipment & systems for existing buildings )& connection with the
main system. Administration,canteen,workshop,warerhouses,fire brigade,
Gate house & security, Truck gate,Chimecal Lab.
25) Cathodic protection Contractor
26) Material for blower door test and one full discharge test of CO2 fire fighting Contractor
system of the GT enclosure. Portable fire extinguishers.
27) Auxiliary boilers for fuel heating of unloading station, distribution piping, Contractor
storage tank, fuel oil treatment plant,. etc.
28) Compressed air system with filter, driers, coolers, receiver, and distribution Contractor
pipe work.
Page 34 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
29) Discharge pumps/pipes and tank trailers for discharge of waste oil and Contractor
chemical water
30) Sewage pre -treatment system and bio-sewage treatment .with basic tank Contractor
31) Painting and protection against corrosion for all plant equipment,with final Contractor
paint ,Touch up painting.
32) Steel works including racks, chequered plates, gratings,.... etc Contractor
Contractor
21. Spares parts for two years.
22. TESTING AND COMMISIONING OF ALL EQUIPMENT. Contractor
2. All provisional buildings and services, including electric feeding with diesel contractor
generators, needed during construction until the permanent works will be
available
4. Demolition of existing structures inside the fence, if any, zero level works up Contractor
to the existing one (FFL = 236.1 = 0.00) NGL= 235 above mean sea level .
5. All plant roads, paved areas, parking, paths and landscaping within the Contractor
fence for the whole site (2 unit (Siemens) + 2 units Power Machines
(Russian)).
Page 35 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
6. (Cables &pipes) concrete trenches with cover for the whole site (2 unit Contractor
(Siemens) + 2 units Power Machines).
7. Covering shelter for HFO treatment system complete with overhead Contractor
travelling crane
8. Structure for Gen. transformer, Aux. Power Transformers,LV transformer & Contractor
Fire wall
9. Compressed air building Contractor
10. GTG Area Foundation including all other associated off base skid Foundation Contractor
for GT Exhaust Stacks & Fuels..etc, Non-shrinking grout for all anchors
related Siemens equipments
11. Turbine Hall with steel structure & for columns & roofs. Contractor
12. Boundary fence (precast concrete) with whole power plant and guard Contractor
towers.
13. Internal fence / partition for fuel gas station, HV switchyard etc Contractor
14. Drainage water system including; surface water system, sewage water Contractor
treatment plant, chemical & oily water treatment,Buried concrete tanks,
drainage and water treatment pits ..etc for the whole site (2 unit
(Siemens) + 2 units Power Machines).
15. Utility pipe and other underground works for the whole site (2 unit Contractor
(Siemens) + 2 units Power Machines).
16. Acoustic attenuation where required to meet noise limits Contractor
Page 36 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
19. Rain system with pump set for the whole site (2 unit (Siemens) + 2 Contractor
units Power Machines).
20. Civil Work for Fuel Oil System (Unloading Station, foundation for storage Contractor
tanks with dyke wall, Fuel Flow, Pump House, Gas Pressure Reduction
Station, Oil Treatment, Etc.)
21. Buildings including earthworks, excavation and filling works, foundation Contractor
works including piling and complete with internal services such as air
conditioning, ventilation, lighting and sockets water distribution, potable
water skids, black water system
22. Water treatment building with all related system for the whole site (2 unit Contractor
(Siemens) + 2 units Power Machines).
23. Air-conditioned chemical store Not Required
30. Mechanical and Electrical Workshop including overhead travelling crane Not Required
Page 37 of 39
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
24. Security
Security services during construction and commissioning as per CHAPTER 11 CONTRACTOR.
of Specifications
Page 38 of 39
1.1.1.1. Conceptual Design
The basic drawings for the conceptual design of the plant are the following:
- Plant layout
- General single line diagram (SLD)
The drawings are herewith annexed in the revision available at the date of issue of these specifications.
Additional separate notes, which shall be considered as a revision, are listed here below
Notes on Plant Conceptual Layout
The shape, position and dimensions of buildings are approximate. The Contractor shall verify them
in order to fulfil all design requirements. Pathways shall be provided all around buildings and
equipments. Access entrances and escape doors are not indicated. Roads and accesses for suitable
vehicles to buildings and equipments are not indicated in the lay-out and shall allow safe
manoeuvrability and hard standing for all necessary deliveries, transporting and positioning plant
equipment.
The Contractor shall consider the number and position of main doors of store and workshop
buildings in order to provide the most suitable road arrangement as described above.
The conceptual layout indicates the site boundary fence and main entrances to the Power Station.
The Contractor shall provide other necessary access points around the perimeter as required for
normal operation and maintenance and for emergency vehicle access.
The conceptual layout doesnt show all the buildings listed in the table above. The Contractor is
aware that these buildings are to be located within the plant area.
Page 39 of 39