Documente Academic
Documente Profesional
Documente Cultură
A1050 Develop procurement and supply plan 3 0% 09-Sep-17 11-Sep-17 Develop procurement and supply plan
A1060 Conduct supplier analysis 3 0% 07-Sep-17 10-Sep-17 Conduct supplier analysis
A1070 Develop all other project plans 5 0% 10-Sep-17 14-Sep-17 Develop all other project plans
A1080 Submit plans to UNDP for approval 1 0% 16-Sep-17 16-Sep-17 Submit plans to UNDP for approval
A1090 UNDP review time for documents 15 0% 17-Sep-17 03-Oct-17 UNDP review time for documents
A1140 Get approval from UNDP 0 0% 03-Oct-17 Get approval from UNDP
MPD.3 Permitting and Zoning 26 0% 04-Oct-17 02-Nov-17 02-Nov-17, MPD.3 Permitting and Zoning
A1100 Contact provincial officials and introduce them to teams 6 0% 04-Oct-17 10-Oct-17 Contact provincial officials and introduce them to teams
A1110 Apply for required permissions and site access 6 0% 07-Oct-17 12-Oct-17 Apply for required permissions and site access
A1120 Submit construction, supply and storage plans to each area 5 0% 14-Oct-17 18-Oct-17 Submit construction, supply and storage plans to each area
A1130 Finalize site access and security 15 0% 17-Oct-17 02-Nov-17 Finalize site access and security
MPD.5 Construction Preparation and Mobilization 25 0% 21-Oct-17 18-Nov-17 18-Nov-17, MPD.5 Construction Preparation and Mobilization
A1190 Provide the technical team and resources 3 0% 04-Nov-17 06-Nov-17 Provide the technical team and resources
A1200 Mobilize site offices at each province 15 0% 21-Oct-17 06-Nov-17 Mobilize site offices at each province
A1210 Mobilize construction machinery and storage spaces 18 0% 26-Oct-17 15-Nov-17 Mobilize construction machinery and storage spaces
A1220 Transport material to site 17 0% 30-Oct-17 18-Nov-17 Transport material to site
A1230 Start execution 0 0% 05-Nov-17 Start execution
MPD.6 Construction Phase 138 0% 02-Sep-17 08-Feb-18 08-Feb-18, MPD.6 Construction Phase
A1240 Site preparation for construction work 10 0% 05-Nov-17 15-Nov-17 Site preparation for construction work
A1250 Put a layer of aggregate for RCC foundations 7 0% 15-Nov-17 22-Nov-17 Put a layer of aggregate for RCC foundations
A1260 RCC for foundations 12 0% 19-Nov-17 02-Dec-17 RCC for foundations
A1270 PCC below stone masonry walls 6 0% 27-Nov-17 03-Dec-17 PCC below stone masonry walls
A1280 Construct stone masonry with 35% mortar 12 0% 04-Dec-17 17-Dec-17 Construct stone masonry with 35% mortar
A1290 Construct brick masonry with 20% mortar 9 0% 19-Dec-17 28-Dec-17 Construct brick masonry with 20% mortar
A1300 Construct RCC stairs with marble stone 11 0% 20-Dec-17 01-Jan-18 Construct RCC stairs with marble stone
A1310 Remaining floor work 5 0% 02-Jan-18 07-Jan-18 Remaining floor work
A1320 Perform tile work 6 0% 08-Jan-18 14-Jan-18 Perform tile work
A1321 Install doors and windows 5 0% 15-Jan-18 20-Jan-18 Install doors and windows
A1322 Perform roof work 3 0% 15-Jan-18 17-Jan-18 Perform roof work
A1330 Furnish remaining works 2 0% 21-Jan-18 22-Jan-18 Furnish remaining works
A1380 Construct brick masonry for water reservoir 5 0% 23-Jan-18 28-Jan-18 Construct brick masonry for water reservoir
A1390 Complete outdoor work 5 0% 29-Jan-18 03-Feb-18 Complete outdoor work
A1400 Complete electrical works 3 0% 23-Jan-18 25-Jan-18 Complete electrical works
A1410 Complete plumbing works 5 0% 29-Jan-18 03-Feb-18 Complete plumbing works
A1420 Construction of setic tank (optional) 5 0% 04-Feb-18 08-Feb-18 Construction of setic tank (optional)
A1440 Drilling of water well for some of the project sites 50 0% 02-Sep-17 29-Oct-17 Drilling of water well for some of the project sites