UNDP- MOIA and Police Development (MPD) Jahan Design Construction Company 07-Aug-17

Activity ID Activity Name Original Schedule % Start August


Finish
2017 September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018
Duration Complete
27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 0411
MPD UNDP- MOIA and Police Development (MPD) 148 0% 02-Sep-17 20-Feb-18 20-Feb-18, MPD UNDP- MOIA and Police

MPD.1 Project Development 6 0% 02-Sep-17 09-Sep-17 09-Sep-17, MPD.1 Project Development


A1000 ContractAward 0 0% 02-Sep-17 ContractAward
A1010 Meet with client and stakeholders in Kabul 1 0% 02-Sep-17 02-Sep-17 Meet with client and stakeholders in Kabul
A1020 Finalize the contract documentation 5 0% 03-Sep-17 07-Sep-17 Finalize the contract documentation
A1040 Start actual work 0 0% 09-Sep-17 Start actual work
MPD.2 Site Assesment 23 0% 07-Sep-17 03-Oct-17 03-Oct-17, MPD.2 Site Assesment

A1050 Develop procurement and supply plan 3 0% 09-Sep-17 11-Sep-17 Develop procurement and supply plan
A1060 Conduct supplier analysis 3 0% 07-Sep-17 10-Sep-17 Conduct supplier analysis
A1070 Develop all other project plans 5 0% 10-Sep-17 14-Sep-17 Develop all other project plans
A1080 Submit plans to UNDP for approval 1 0% 16-Sep-17 16-Sep-17 Submit plans to UNDP for approval
A1090 UNDP review time for documents 15 0% 17-Sep-17 03-Oct-17 UNDP review time for documents
A1140 Get approval from UNDP 0 0% 03-Oct-17 Get approval from UNDP
MPD.3 Permitting and Zoning 26 0% 04-Oct-17 02-Nov-17 02-Nov-17, MPD.3 Permitting and Zoning
A1100 Contact provincial officials and introduce them to teams 6 0% 04-Oct-17 10-Oct-17 Contact provincial officials and introduce them to teams
A1110 Apply for required permissions and site access 6 0% 07-Oct-17 12-Oct-17 Apply for required permissions and site access
A1120 Submit construction, supply and storage plans to each area 5 0% 14-Oct-17 18-Oct-17 Submit construction, supply and storage plans to each area
A1130 Finalize site access and security 15 0% 17-Oct-17 02-Nov-17 Finalize site access and security
MPD.5 Construction Preparation and Mobilization 25 0% 21-Oct-17 18-Nov-17 18-Nov-17, MPD.5 Construction Preparation and Mobilization
A1190 Provide the technical team and resources 3 0% 04-Nov-17 06-Nov-17 Provide the technical team and resources
A1200 Mobilize site offices at each province 15 0% 21-Oct-17 06-Nov-17 Mobilize site offices at each province
A1210 Mobilize construction machinery and storage spaces 18 0% 26-Oct-17 15-Nov-17 Mobilize construction machinery and storage spaces
A1220 Transport material to site 17 0% 30-Oct-17 18-Nov-17 Transport material to site
A1230 Start execution 0 0% 05-Nov-17 Start execution
MPD.6 Construction Phase 138 0% 02-Sep-17 08-Feb-18 08-Feb-18, MPD.6 Construction Phase
A1240 Site preparation for construction work 10 0% 05-Nov-17 15-Nov-17 Site preparation for construction work
A1250 Put a layer of aggregate for RCC foundations 7 0% 15-Nov-17 22-Nov-17 Put a layer of aggregate for RCC foundations
A1260 RCC for foundations 12 0% 19-Nov-17 02-Dec-17 RCC for foundations
A1270 PCC below stone masonry walls 6 0% 27-Nov-17 03-Dec-17 PCC below stone masonry walls
A1280 Construct stone masonry with 35% mortar 12 0% 04-Dec-17 17-Dec-17 Construct stone masonry with 35% mortar
A1290 Construct brick masonry with 20% mortar 9 0% 19-Dec-17 28-Dec-17 Construct brick masonry with 20% mortar
A1300 Construct RCC stairs with marble stone 11 0% 20-Dec-17 01-Jan-18 Construct RCC stairs with marble stone
A1310 Remaining floor work 5 0% 02-Jan-18 07-Jan-18 Remaining floor work
A1320 Perform tile work 6 0% 08-Jan-18 14-Jan-18 Perform tile work
A1321 Install doors and windows 5 0% 15-Jan-18 20-Jan-18 Install doors and windows
A1322 Perform roof work 3 0% 15-Jan-18 17-Jan-18 Perform roof work
A1330 Furnish remaining works 2 0% 21-Jan-18 22-Jan-18 Furnish remaining works
A1380 Construct brick masonry for water reservoir 5 0% 23-Jan-18 28-Jan-18 Construct brick masonry for water reservoir
A1390 Complete outdoor work 5 0% 29-Jan-18 03-Feb-18 Complete outdoor work
A1400 Complete electrical works 3 0% 23-Jan-18 25-Jan-18 Complete electrical works
A1410 Complete plumbing works 5 0% 29-Jan-18 03-Feb-18 Complete plumbing works
A1420 Construction of setic tank (optional) 5 0% 04-Feb-18 08-Feb-18 Construction of setic tank (optional)
A1440 Drilling of water well for some of the project sites 50 0% 02-Sep-17 29-Oct-17 Drilling of water well for some of the project sites

MPD.7 Hand Over 10 0% 10-Feb-18 20-Feb-18 20-Feb-18, MPD.7 Hand Over


A1340 Prepare punch list 2 0% 10-Feb-18 11-Feb-18 Prepare punch list
A1350 Complete remaining defects 3 0% 12-Feb-18 14-Feb-18 Complete remaining defects
A1360 Demobilize from site 1 0% 15-Feb-18 15-Feb-18 Demobilize from site
A1370 Complete commissioning 4 0% 17-Feb-18 20-Feb-18 Complete commissioning
A1430 Project hand-over 0 0% 20-Feb-18 Project hand-over