Documente Academic
Documente Profesional
Documente Cultură
INDEX
Contents
EXECUTIVE SUMMARY
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
TABLE OF CONTENTS
LIST OF TABLES
Executive Summary E - ii
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
EXECUTIVE SUMMARY
1 GENARAL
Ministry of Road Transport and Highways, Government of India has decided to take up
the development of various National Highways Corridors where the intensity of traffic
has increased significantly and there is requirement of augmentation of capacity for safe
and efficient movement of traffic.
This project is a part of the above mentioned programme and the project awarded to
Consultant is Consultancy Services for rehabilitation and up-gradation of the existing 2-
lane National Highway71 to four lanes configuration in the State of Haryana. The
National Highways Authority of India (NHAI) has been entrusted with implementation
of the development of this corridor from Ministrys Plan Funds.
In order to fulfil the above task, The National Highways Authority of India has entrusted
the work of preparation of the feasibility study, Environmental and Social Impact
Assessment and Detailed Project Report for the above project to M/s Louis Berger
Group, Inc., vide contract agreement dated 30th March, 2010. The Letter of Acceptance
was communicated vide NHAIs letter No PB&HP/DPR/NHDP-IV/08/10794.
2 OBJECTIVES
The main objective of the consultancy service is to establish the technical, economic and
financial viability of the project and prepare detailed project reports for rehabilitation
and upgrading of the existing 2-lane National Highway (NH) sections to 4- lane divided
carriageway configuration taking into account the investment requirements and
financial return through toll and other revenues.
3 SCOPE OF SERVICES
The scope of consultancy services includes:
Engineering surveys and investigations
Highway design
Environmental Impact Assessment
Estimation of Project Cost
Economic Analysis
Preparation of Feasibility study report and Detailed project report
Submission of Deliverables
5 NHAI
The National Highways Authority (NHAI) of India was constituted by an act of
Parliament, the National Highways Authority of India Act, 1988. It is responsible for the
development, maintenance and management of National Highways entrusted to it and
for matters connected or incidental thereto. The Authority was operationalized in
February, 1995 with the appointment of full time Chairman and other Members.
7 TERRAIN
Most of the project road passes through plain terrain.
9 REFERENCING SYSTEM
Along the existing road, Kilometre stones are fixed in entire length of the project
highway. It is called as "Existing Chainage". During topography survey with Total
Station, observations made are referred to "Design Chainage". The relationship between
the "Existing Chainage and the Design Chainage" as per field surveys of the location of
existing km stones using the Total Station for the Project Highway, Design Chainage
corresponding to existing kilometre stone.
Design Chainage of New NH-352 Ch. corresponding to existing kilometre stone
Existing New Design Existing New Design
Chainage (i.e. NH-352 Chainage Chainage (i.e. NH-352 Chainage
Km stone) Chainage (Km) Km stone) Chainage (Km)
239+000 - 239+000 267+000 3+710 266+934
240+000 - 240+103 268+000 4+670 267+887
241+000 - 240+995 269+000 5+635 268+863
242+000 - 241+991 270+000 6+685 269+912
243+000 - 242+991 271+000 7+740 270+971
244+000 - 243+990 272+000 8+700 271+928
245+000 - 244+990 273+000 9+655 272+888
246+000 - 245+989 274+000 10+625 273+859
247+000 - 246+993 276+000 12+625 275+847
248+000 - 247+987 277+000 13+580 276+817
249+000 - 248+987 278+000 14+790 278+018
250+000 - 249+986 279+000 15+772 279+008
251+000 - 250+985 280+000 16+720 279+970
253+000 - 252+986 281+000 17+745 280+993
11 ROAD INVENTORY
The project corridor traverses mostly through plain terrain. The land use is
predominantly agricultural with intermittent built up areas. The two / four lane
carriageway is having a width of 7.0-14.0m. The earthen shoulder width generally varies
from 0.50-1.00 m on either side. The type of shoulder is earthen or hard excluding the
urban areas. The details of existing carriageway width are given in Table E-1.
Table E-1: Details of Existing Carriageway Width
Existing
Chainage (km) Length Width of
Lane Configuration Median
(km) Carriage way
From To (m)
239.000 247.160 8.160 2-Lane with PS 7+(2.0 to 3.0) -
247.160 247.460 0.300 2-Lane 6.00 -
247.460 258.650 11.190 2-Lane with PS 7+(2.0 to 3.0) -
258.650 262.000 3.350 4-Lane with raised median 2 x 7.50 1.2 to 1.5m
262.000 292.700 30.700 2-Lane with PS 7+(2.0 to 3.0) -
292.700 295.400 2.700 2-Lane with PS 7+(2.0 to 3.0) -
295.400 296.550 1.150 4-Lane with raised median 2 x 7.00 1.2 to 1.5m
296.550 307.000 10.450 2-Lane with PS 7+(2.0 to 3.0)
12 RIGHT OF WAY
The Right of Way (ROW) boundary stones are available only at few locations along the
project corridor. In most of the urban areas, properties exist adjacent to carriageway.
Information on available land-width has been collected from local highways department,
Govt. of Haryana. The details of ROW along the project corridor are given in Table E-2.
13 LAND ACQUISITION
The present status of land acquisition is given in below:
Table E-3: Status of Land Acquisition
Existing Chainage Design Proposed
Sl. (Km) Chainage (km) ROW Remarks
No.
From To From To (m)
1 239.000 239.400 239.000 239.400 60 Dhabian Gujron Village
2 239.400 240.697 239.400 240.800 43 Pipaithan / Pattawala Village
3 240.697 241.705 240.800 241.700 60
4 241.705 242.509 241.700 242.500 43 Garhi Village
5 242.509 252.615 242.500 252.600 60
6 252.615 253.414 252.600 253.400 43 Balarkha Village
7 253.414 257.648 253.400 257.600 60
8 257.648 258.828 257.600 258.700 60 ROB
9 258.828 260.051 258.700 259.850 43 Narwana Town
10 260.051 260.185 259.850 260.000 35 Narwana Town
11 260.185 262.788 260.000 262.600 34 Narwana Town
12 262.788 270.238 262.600 270.150 60
13 270.238 270.638 270.150 270.550 31 Khersafa Village
14 270.638 274.341 270.550 274.200 60
15 274.341 276.253 274.200 276.100 37.5 Uchana Town / Ghaso Bara
16 276.253 278.992 276.100 279.000 60
17 278.992 280.330 279.000 280.300 30 Baroda Village
18 280.330 284.548 280.300 284.500 60
19 284.548 285.242 284.500 285.200 30 Khatkad Village
20 285.242 285.762 285.200 285.720 60
21 285.762 286.168 285.720 286.120 130 Toll Plaza
22 286.168 288.817 286.120 288.800 60
23 288.817 289.464 288.800 289.450 30 Jhanj Kalan/Barsola
24 289.464 290.312 289.450 290.300 60
25 290.312 290.812 290.300 290.800 30 Khurkhru Village
26 290.812 292.712 290.800 292.700 60 Hirka Village
Proposed Jind Bypass
27 0.000 1.750 60 Jind Bypass
Flyover @Jind Bypass
28 1.750 2.350 110
( SH-12)
29 2.350 5.100 60 Jind Bypass
30 5.100 6.100 60 Flyover @ Jind Bypass (Cross Road)
31 Jind Bypass 6.100 7.050 60 Jind Bypass
32 7.050 7.650 110 Flyover @Jind Bypass ( SH-14)
33 7.650 9.210 60 Jind Bypass
34 9.210 9.810 110 Flyover @Jind Bypass (SH-10)
35 9.810 10.600 60 ROB at Jind Bypass (Near SH-10)
36 10.600 15.650 60 Jind Bypass
14 GEOMETRICS
The Project Corridor generally has a good geometry and has a design speed of 70-80
Kmph. The corridor has few substandard curves with a low radius that are of concern.
The vertical gradients are gentle for majority of its length except at very few locations,
which require modification. However, camber has worn out for most of the lengths and
requires correction for quick dispersal of surface water. The details of the locations
having poor geometric characteristics are given in Table E-4.
Table E-4: Locations of poor road geometry
S. No Existing Chainage Description
1 263+000to 263+200 Poor T-Junction between NH 71 &NH 65
The lists of junctions with secondary importance are presented in Table E-6.
Table E-6: List of Existing Junctions with Secondary Importance
SI Chainages Type of
Side Leading to Remarks
No (Km) Road
1 239+830 LHS To Village BT-3.5m Y Junction
2 239+860 LHS To Dhanauri Village CC-3.5m Y Junction
3 240+200 RHS To Village BT-3.5m T Junction
4 240+385 RHS To Village BT-3.5m T Junction
5 240+520 LHS To Dhanauri Village BT-5.0m T Junction
6 241+900 LHS To Dhanauri Village BT-4.0m T Junction
7 242+250 RHS Bebltha BT-5.5m T Junction
Ujhana Village (Left) Pipelsha
8 246+115 RHS BT-3.0m Staggered Junction
Village (Right)
9 246+970 LHS To Ujhana Village BT-3.5m T Junction
10 247+650 RHS To Hardar Village BT-3.5m T Junction
11 252+600 LHS To Belarkha Village BT-3.5m T Junction
12 252+760 RHS To Hamargarh Village BT-5.0m T Junction
13 252+940 RHS To Tharodi Village BT-3.5m T Junction
SI Chainages Type of
Side Leading to Remarks
No (Km) Road
14 253+290 RHS To Village BT-3.5m T Junction
15 253+400 LHS Surajakehda BT-5.0m T Junction
16 258+080 LHS To Golkehra Village BT-3.5m T Junction
17 258+780 RHS To Tohana Village BT-5.0m Y Junction
Tohana Village (Left) Govt.
18 259+450 RHS BT-5.0m Square Junction
College (Right)
19 259+500 LHS Narwana City BT-3.5m T Junction
20 259+660 RHS To Narwana Town BT-3.0m T Junction
21 259+800 LHS To Gurthari Village BT-5.0m T Junction
22 259+870 RHS To Railway Station,Narwana BT-5.0m T Junction
23 261+315 RHS To School BT-5.0m T Junction
Village (Left) Railway
24 261+390 RHS BT-5.0m Square Junction
Station (Right)
25 261+600 LHS Vasanth Vihar BT-16m T Junction
26 261+870 LHS Indian Oil Patrol Pump BT-3.0m T Junction
27 262+690 RHS To Uklana Village BT-10.0m T Junction
28 263+100 LHS Haryana Vidut Nigam BT-3.5m Y Junction
29 263+300 LHS To Dumerkha Village BT-5.5m Y Junction
30 264+605 RHS To Geel Village BT-5.0m T Junction
31 265+985 LHS To Dumerkha Village BT-5.0m T Junction
32 268+600 RHS To Ghaso Khurd BT-3.0m T Junction
33 270+455 LHS To Kheri Saffa Village BT-5.5m T Junction
Khark BhuraVillage (Left)
34 271+920 LHS BT-3.5m Square Junction
Kheri Mansaniya (Right)
35 273+875 RHS Uchana Bye-pass BT-6.5m Y Junction
36 274+293 LHS To Bara Sidu Village BT-5.5m T Junction
Bara SiduVillage (Left)
37 275+400 LHS BT-5.0m Square Junction
Uchana City (Right)
38 276+667 RHS Railway Station,Uchana BT-3.5m T Junction
39 279+490 LHS To Baroda Village BT-6.0m T Junction
40 279+940 RHS To Barsola Village BT-3.0m T Junction
41 284+535 LHS To Kasun Village BT-5.0m T Junction
42 284+890 RHS To Bhathoda Village BT-3.0m T Junction
43 285+100 LHS To Chapda Village BT-3.0m T Junction
44 285+175 RHS To Barsola Village BT-3.0m T Junction
45 289+040 LHS To Badothi Village BT-3.5m T Junction
46 291+010 LHS To Village BT-4.5m T Junction
47 292+130 LHS To Village BT-3.0m T Junction
16 RAILWAY CROSSINGS
There are two locations where railway line crosses the existing alignment. Presently all
are level crossings and RoBs are proposed at these locations. Out of two, one is at Jind
Bypass. The detail of the structures is given below in Table E-7.
There are 88 existing CD structures on the project road and 43 culverts along Jind
Bypass. There are four existing Minor Bridges, (6.0 m < Total Length < 60.0m) along
Existing road and one minor bridge along Jind Bypass.
The total number of structure on the site is given in Table E-8:
All of the minor bridges are to be reconstructed as they have been designed for 40R
loading.
The details of the existing Bridges are given in Table E-9 . All of the minor bridges are to
be reconstructed as they have been designed for 40R loading. The inventory and
conditional details of these minor bridges have been presented in Table E-9.
Table E-9: Details of Existing Bridges
Existing Span Total Type of Structure
S. Name of Width
Chainage Arrange- Length Sub Super
No Bridge (m) Foundation
(km) ment (m) (m) Structure Structure
Dhamtan Sahib Wall Type in
Open RCC Solid
1 Distributary 245.300 1 x 13.2 2 x 3.70 7.40 Brick
Foundation Slab
Masonry
Bhakra Main
Wall Type in
Line Barwala Open RCC Solid
2 247.400 1 x 7.5 3 x 10.5 31.50 Brick
Link Foundation Slab
Masonry
Sirsa Branch Open Wall Type in RCC Solid
3 262.950 1 x 7.6 4 x 8.3 33.20
(Western Foundation Brick Slab
The General condition of culverts in project corridor is not very satisfactory except that
some of these require repairs and are to be widened up to required width of four lanes.
Distresses in form of exposed reinforcement, corroded reinforcement, honey combing etc
in the slab portion and damaged pointing, exposed joints, cracks in PCC substructures/
head walls, parapets and PCC wing walls and chocked HP culvert with damaged head
wall are observed in some of the culverts which require repairs. All the Slab Culverts
were found made of either brick masonry or plain cement concrete but most of them are
in poor/ very poor condition. The details of culverts are given in Table E-10.
Table E-10: Details of Existing Culverts
A. Slab Culvert
S.No. Existing Chainage (km) Structure no. Span Arrangement (m)
1 239.241 - 1x2.9
2 242.158 - 1 X 1.50
3 247.806 - 1x1.2
4 251.345 252/2 1 X 3.7
5 254.460 - 1 X 0.7
6 261.395 - 1X4
7 262.761 - 1 X 0.8
8 262.817 - 1 X 2.1
9 262.880 - 1 X 2.3
10 265.189 266/1 1X3
11 265.212 266/2 1X3
12 265.231 266/3 2X3
13 265.254 266/4 1X3
14 265.268 266/5 1X3
15 273.155 - 1 X 1.50
16 273.816 274/2 1X3
17 274.282 - 1 X 1.20
18 275.940 - 1X3
19 277.737 - 1x1.2
20 279.497 - 1x1.2
B. Arch Culvert
S.No. Existing Chainage (km) Structure no. Span Arrangement (m)
1 278.073 - 1x1.50
C. Pipe Culvert
Span Arrangement
S.No. Existing Chainage (km) Structure no.
(m)
1 239.098 - 1 X 0.9
2 239.812 240/2 1 X 0.9
3 239.957 241/1 1X1
4 240.448 - 1 X 0.9
5 240.875 241/3 1 X 0.9
6 241.144 - 1 X 0.9
7 241.750 - 1 X 0.9
8 244.863 - 1 X 0.9
9 245.176 - 1 X 1.20
10 245.507 - 1 X 1.20
11 246.611 247/1 1 X 1.20
12 246.946 - 1 X 0.9
13 247.529 - 1 X 0.9
14 248.891 - 1 X 0.9
15 249.012 250/1 1 X 0.9
16 250.463 - 1 X 0.9
17 251.132 252/1 1 X 0.9
18 251.990 252/3 1 X 0.9
19 252.446 - 1 X 0.9
20 253.297 254/1 1 X 1.20
21 255.243 - 1 X 0.9
22 255.582 - 1 X 0.9
23 256.032 - 1 X 0.9
24 256.721 257/2 1 X 0.9
25 257.07 - 1 X 1.20
26 258.103 - 1 X 0.9
27 258.180 - 1 X 0.9
28 263.064 - 1 X 0.90
Executive Summary E - 10
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Span Arrangement
S.No. Existing Chainage (km) Structure no.
(m)
29 263.508 - 1 X 0.90
30 264.538 - 1 X 0.90
31 266.553 - 1 X 0.90
32 267.092 - 1 X 0.90
33 267.327 - 1 X 0.90
34 267.830 - 1 X 0.90
35 269.010 - 1 X 0.90
36 269.149 - 1 X 0.90
37 270.445 - 1 X 0.90
38 270.463 - 1 X 0.90
39 271.785 - 1 X 0.90
40 272.734 - 1 X 0.90
41 273.042 274/1 1x0.6
42 273.086 - 1x0.9
43 273.280 - 1x0.9
44 274.063 - 1x1.2
45 276.262 - 1x0.9
46 276.767 - 1x0.9
47 278.396 - 1 X 0.90
48 279.070 - 1 X 0.90
49 280.066 - 1 X 0.90
50 280.577 281/2 1 X .90
51 281.860 281/3 1 X .90
52 282.300 282/1 1 X .90
53 283.224 283/1 1 X .90
54 288.044 288/1 1 X 0.90
55 288.518 - 1 X 0.90
56 289.175 - 1 X 0.90
57 290.415 - 1 X 0.90
58 291.005 - 1 X 0.90
59 292.393 - 1 X 0.90
In Jind Bypass
Proposed Bypass Span Arrangement
Structure no.
Chainages (km) (m)
60 0.107 - 1 x 0.90
61 0.279 - 1 x 0.90
62 0.446 - 1 x 0.90
63 0.662 - 1 x 0.90
64 0.673 - 1 x 0.90
65 0.748 - 1 x 0.90
66 0.825 - 1 x 0.90
67 1.155 - 1 x 0.90
68 1.258 - 1 x 0.90
69 1.390 - 1 x 0.90
70 1.492 - 1 x 0.90
Executive Summary E - 11
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Span Arrangement
S.No. Existing Chainage (km) Structure no.
(m)
71 1.763 - 1 x 0.90
72 1.901 - 1 x 0.90
73 2.216 - 1 x 0.60
74 2.434 - 1 x 0.60
75 2.649 - 1 x 0.60
76 2.904 - 1 x 0.60
77 3.371 - 1 x 0.60
78 3.441 - 1 x 0.60
79 3.782 - 1 x 0.60
80 4.077 - 1 x 0.60
81 4.320 - 1 x 0.60
82 4.584 - 1 x 0.60
83 4.924 - 1 x 0.60
84 5.057 - 1 x 0.60
85 5.417 - 1 x 0.60
86 5.709 - 1 x 0.60
87 6.230 - 1 x 0.60
88 6.654 - 1 x 0.60
89 7.000 - 1 x 0.60
90 7.123 - 1 x 0.60
91 7.263 - 1 x 0.60
92 7.272 - 1 x 0.60
93 7.482 - 1 x 0.60
94 7.849 - 1 x 0.60
95 8.026 - 1 x 0.60
96 8.090 - 1 x 0.60
97 8.208 - 1 x 0.60
98 8.570 - 1 x 0.60
99 8.755 - 1 x 0.60
100 9.289 - 1 x 0.60
Executive Summary E - 12
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Maximum contribution to the traffic is of cars and two wheelers at both the location.
Heavy vehicles are more or less same in number at both the locations as shown in
the figure below.
The average composition of traffic shows passenger vehicle comprising maximum
traffic all along the corridor followed by Trucks. At Khanauri goods vehicle
comprise very high as compared to other location.
The average stream speed on the project corridor varies from 51 KMPH to 62
KMPH.
Major point of delay has been observed in the corridor are Narwana, Uchana and
village more than 500 m length section since it is due to very congested area.
As per the provision of New MCA, 5% growth rate has been adopted for the project
corridor.
Executive Summary E - 13
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Pavement condition survey has been carried out on the project corridor by visual
observation of basic pavement distress. Predominant distresses like cracking, raveling,
and extent of patching have been noted as percentage area for every 100m length of
road. Number of potholes for each 100m length has also been noted. Apart from these
distresses, Edge breaking as percentage length affected has also been noted for every
100m along the road. Condition of the unpaved shoulders was also assessed in terms of
shoulder drop-off and depressions on shoulder. Residual structural strength of the
existing pavement was separately assessed by Benkelman Beam deflection
measurements for the purpose of Design of Overlay.
The overall condition of the pavement varies from fair to good. The overall riding quality
is also fair except for a few stretches. Condition of the unpaved shoulders is fair.
Executive Summary E - 14
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
20 EXISTING FACILITIES
Various Way side Amenities have been observed at many places along the project
corridor. The list of bus stops is given in Table E-12.
Table E-12: Way Side Amenities
S. No. Name of Existing Amenity Total
1 School 11
2 College 3
3 Hospitals 6
4 Petrol pump 21
5 Bus-stop 11
6 Hotel 3
7 Dhabas 17
Executive Summary E - 15
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
The median shall be flared at the location of median opening to accommodate waiting
facility of vehicles for negotiation of right turn or U turn.
Table E-13: Cross Section Type along the Project Corridor
Existing Design Typical
Sl. Chainage (Km) Chainage (km) Length Proposed
X-Section Location
No. (m) Widening
From To From To Type
Dhabian Gujron
1 239.000 239.400 239.000 239.400 400 LHS Type-2A
Village
Pipaithan /
2 239.400 240.697 239.400 240.800 1400 Concentric Type-1D
Pattawala Village
3 240.697 241.705 240.800 241.700 900 RHS Type-2A
4 241.705 242.509 241.700 242.500 800 Concentric Type-1D Garhi Village
5 242.509 244.890 242.500 244.880 2380 RHS Type-2A
6 244.890 245.590 244.880 245.580 700 RHS Type-2B
7 245.590 247.007 245.580 247.000 1420 RHS Type-2A
8 247.007 247.587 247.000 247.580 580 LHS Type-2B
9 247.587 252.615 247.580 252.600 5020 RHS Type-2A
10 252.615 253.414 252.600 253.400 800 Concentric Type-1D Balarkha Village
11 253.414 258.668 253.400 258.540 5140 LHS Type-2A
12 258.668 259.851 258.540 259.650 1110 Concentric Type-1A Narwana Town
13 259.851 261.988 259.650 261.800 2150 Concentric Type-1C Narwana Town
14 261.988 263.888 261.800 263.700 1900 RHS Type-2B
15 263.888 268.813 263.700 268.700 5000 RHS Type-2A
16 268.813 270.238 268.700 270.150 1450 LHS Type-2B
17 270.238 270.638 270.150 270.550 400 Concentric Type-1D Khersafa Village
18 270.638 274.331 270.550 274.190 3640 LHS Type-2A
Uchana Town /
19 274.331 276.091 274.190 275.950 1760 Concentric Type-1B
Ghaso Bara
20 276.091 278.992 275.950 279.000 3050 LHS Type-2A
21 278.992 280.330 279.000 280.300 1300 Concentric Type-1D Baroda Village
22 280.330 284.548 280.300 284.500 4200 LHS Type-2A
23 284.548 285.242 284.500 285.200 700 Concentric Type-1D Khatkad Village
24 285.242 288.817 285.200 288.800 3600 RHS Type-2A
25 288.817 289.464 288.800 289.450 650 Concentric Type-1D Jhanj Kalan/Barsola
26 289.464 290.312 289.450 290.300 850 Concentric Type-2A
27 290.312 290.812 290.300 290.800 500 Concentric Type-1D Khurkhru Village
28 290.812 292.712 290.800 292.700 1900 LHS Type-2A Hirka Village
292.700/
29 1.700 1700 Concentric Type-3 Jind Bypass
0.000
30 1.700 2.400 700 Concentric Type-4 Jind Bypass
31 2.400 7.000 4600 Concentric Type-3 Jind Bypass
32 Jind Bypass 7.000 7.700 700 Concentric Type-4 Jind Bypass
33 7.700 9.160 1460 Concentric Type-3 Jind Bypass
34 9.160 9.500 340 Concentric Type-4 Jind Bypass
15.650/
35 9.500 6150 Concentric Type-3 Jind Bypass
307.000
Executive Summary E - 16
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
23 PROPOSED BYPASSES
Realignments and bypasses have been proposed where it is not feasible to improve the
existing alignment of 2-lane road to the desired design standards. The constraints at each
location have been described in the chapter 5. The details of stretches to be bypass are
given in Table E-14.
Table E-14: Details of Bypasses
Existing Chainage
(km) Length Width of
Lane Configuration Median
(km) Carriage way
From To (m)
239.000 247.160 8.160 2-Lane with PS 7+(2.0 to 3.0) -
247.160 247.460 0.300 2-Lane 6.00 -
247.460 258.650 11.190 2-Lane with PS 7+(2.0 to 3.0) -
4-Lane with raised
258.650 262.000 3.350 2 x 7.50 1.2 to 1.5m
median
262.000 292.700 30.700 2-Lane with PS 7+(2.0 to 3.0) -
292.700 295.400 2.700 2-Lane with PS 7+(2.0 to 3.0) -
4-Lane with raised
295.400 296.550 1.150 2 x 7.00 1.2 to 1.5m
median
296.550 307.000 10.450 2-Lane with PS 7+(2.0 to 3.0)
Slip Road:-
Existing Chainage Design Chainage Total
(km) (km) Length Width
S No Length( Side
(m) (m)
From To From To m)
1 Jind Bypass 1.700 2.400 2x700 1400 Both 2x7.00
2 Jind Bypass 7.000 7.700 2x700 1400 Both 2x7.00
3 Jind Bypass 9.160 9.500 2x340 680 Both 2x7.00
Total Length of Slip Road 3480
Executive Summary E - 17
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
The composition of pavement has been worked out on the basis of:
Extended thickness combination block has been used to determine the surfacing
course thickness;
Surfacing course is designed for 10-year design life while base and sub-base
courses are designed for the full 15-year design life; and, minimum compacted
layer thickness for surfacing and base courses.
26 DESIGN OVERLAY
From the BBD analysis strengthening of existing pavement is not required however, in
order to improve the riding quality of the existing surface after pre-treatment 40mm BC
is proposed.
27 SERVICE ROAD
Bituminous service road has been designed for 5 msa traffic and 8% sub-grade CBR.
Accordingly based on IRC guidelines, the composition will be as given in Table E-16
below.
Table E-16: Required Pavement Composition for Service Road (mm)
Semi Dense Bituminous Concrete
25
(SDBC)
Dense Bituminous Macadam (DBM) 50
Granular Base (WMM) 250
Granular Sub base (GSB) 150
Executive Summary E - 18
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
29 PROPOSED STRUCTURES
I. Cross-Drainage (Bridges & Culverts)
Following guidelines shall be followed in design and construction of cross drainage
structures:
i) All the cross drainage structures for the new carriageway shall be designed in such
way so that the outermost faces of the railing kerbs is equal to the roadway width of
the approaches.
ii) The existing structure, wherever possible, shall be widened i.e. extended to match
the new road cross sections.
iii) For bridges/ Grade separators covered median of the same width as of highway
shall be provided except in case of T-Beam type superstructure where open median
shall be provided with minimum 4.5 m gap including two parapet walls/crash
barrier of the bridges.
iv) The adequacy of the vent size for all culverts/bridges shall be ascertained through
detailed hydrological surveys. The Highest Flood Level / Maximum Supply Level
shall be properly assessed after collecting flood histories from local authorities /
local enquiries / Irrigation authorities.
v) Canal bridges shall be designed as per hydraulic requirements of irrigation
authorities. The construction plans shall be prepared as per closure schedule of
canals. Approval of GAD from irrigation department may be required. For smaller
canals, it may be preferred to plan single span canal bridges with foundations not
disturbing the canal bunds.
vi) The new bridge shall be so planned to not affect the foundations of existing bridge.
vii) The existing Pipe culverts in good conditions and adequate hydraulic capacity shall
be widened to new carriageway with NP-4 HP culverts. In case where the culverts
are structurally/ hydraulically inadequate shall be replaced by new culvert of
adequate size.
All the bridges for the new carriageway shall be designed for 70 R Loading. However
minor CD structures are proposed to be widened to four-lane highway configuration.
Improvement for the existing cross-drainage structures shall be made as summarized in
Table E-17.
Table E-17: Recommendations on Cross Drainage Structures of the Project
Repair & New Total no. of
Type of structures Reconstruction
Widening Construction Structures
Slab / Box Culvert 21 6 1 28
Hume Pipe Culvert 67 33 16 116
Minor Bridge 0 5 0 5
II. Culverts:
Table E-18 presents the details of Culverts proposed for the entire project.
Executive Summary E - 19
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Executive Summary E - 20
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Executive Summary E - 21
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
B. Reconstruction
(a) Slab/Arch culvert to Box culvert
Existing Chainage Design Chainage Span Arrangement
S.No Existing CD No.
(km) (km) (m)
1 - 254.460 254.443 1x2.0
2 - 262.761 263.062 1x2.0
3 - 274.282 274.138 1x2.0
4 - 278.073 278.091 1x2.0
5 279.497 279.506 1x2.0
Executive Summary E - 22
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
C. New Culvert
(a) Box Culvert in Jind Bypass
Existing Chainage Design Chainage Span Arrangement
Sl.No
(km) (km) (m)
1 Jind Bypass 9.800 1x2.0
Executive Summary E - 23
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
III. Bridges
Minor Bridges (5 Nos.)
Table E-19. presents the details of minor bridges.
Table E-19: Details of New Minor Bridges and Rehabilitation/Repair Scheme
for Existing Minor Bridges
Repair Scheme for Existing Minor Bridges
Reconstruction of Existing Bridges
Shudkain
RHS of Main
3 Distributary 268.950 268.819 1x12 1 x 10.0
Carriageway
New Construction
Existing Design Span
Sl.
Name of Bridge Chainage Chainage Width (m) Arrangement Side
No.
(Km) (Km) (m)
Dhamtan Sahib
RHS of Main
1 Distributary 245.300 245.187 1x12 1 x 10.0
Carriageway
Bhakra Main Line
RHS of Main
2 Barwala Link ** 247.400 247.304 1x12 1 x 31.5
Carriageway
Sirsa Branch
RHS of Main
3 (Western Yamuna 262.950 263.140 1x12 1 x 35.0
Carriageway
Canal)
Shudkain
LHS of Main
4 Distributary 268.950 268.819 1x12 1 x 10.0
Carriageway
Hansi Branch
5 (Western Yamuna Jind Bypass 3.668 2x12 1 x 58.4 Both sides
Canal)
Executive Summary E - 24
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
IV. Underpasses
Table E-20.presents the details of proposed underpasses. The existing carriageway under
the underpasses shall be constructed with rigid pavement. The crossing road under the
underpasses shall also be constructed with rigid pavement up to 30 m distance on either
side.
Table E-20: Details of Proposed Pedestrian/Cattle Underpasses
Proposed Total
Existing Design Name of Proposed Proposed Clear
S. clear Span Width of
Chainage Chainage Intersecting Structural Structure Height
no Arrangement Structure
(km) ** (km) Road Configuration Type (m)
(m) (m)
New 4 Lane
1 Bypass 13.980 Village Road R.C.C. Box 1X7 2 x 12 3.5
configuration
** Chainage along Jind bypass (Proposed Chainage)
Executive Summary E - 25
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Arrangement (m)
Chainage (km)
Total Width of
Configuration
Structure (m)
Structural
Locations
Proposed
Proposed
Structure
Crossing
Name of
Existing
Existing
Design
S.no
Steel plate
NR Narwana 4L girder
BG 1x30+1x2
1 Narwana 258.140 258.013 Kurukshetra configu &Precast 2x12 6.525
(Single) 5+1x30
Branch rations PSC
Girder
Steel plate
NR Jind 4L girder
On Jind BG 1x25+1x1
2 Bypass 10.000 Panipat configur &Precast 2x12 6.525
Bypass (Single) 9+1x25
Branch ations PSC
Girder
30 PROPOSED FACILITIES
I. Toll Plaza (1 Nos.)
The tentative locations are existing chainage Km. 286. Open System of toll collection
shall be provided on the Project Highway with collection of user fee from vehicles only
at the toll plaza. There shall be a total of maximum 8 (4+4)-lanes(land for 12 lane
acquired) having a semi-automatic system of toll collection comprising equipments for
registering of vehicle classification, ticket issuing, data processing and power supply.
One toll lane in each direction shall be provided for traffic not required to pay fees.
Appropriate technology shall be used in this regard so that not more than 6 vehicles per
lane queue up during the peak hours.
II. Bus Bays (14no)
A total of 14 nos. of Bus Bays have been proposed along the project highway. The
locations of these bus bays are given in Table E-23.
Table E-23: Bus Bays and Bus Stops Locations
S.No Existing Chainage (Km) Location Side
1 240+00 Pipaithan Village Both Side
2 253+00 Balarkha Village Both Side
3 260+00 Narwana Village Both Side
4 275+00 Uchana Village Both Side
5 279+50 Baroda Village Both Side
6 289+00 Jhanj Kalan / Barsola Both Side
7 291+00 Hirka Village Both Side
Executive Summary E - 26
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
31 ENVIRONMENTAL SCREENING
The following are the main findings of the environmental screening survey and has been
detailed out in this report.
The topography is plane and agricultural field.
The land use is mixed type of agricultural, industrial, residential and commercial.
Majority of land use is agriculture; the productivity of the land is very high. It is
found from the public consultation that the agricultural land produces Rice, wheet,
Pulses and Sugarcane etc.
The climate is extreme type.
The project area falls in the seismic zone IV.
No natural stream or river falling in the impact corridor. No natural water body like
lake or natural pond.
No archaeological structure found in the CoI. 22 number of religious structure
found in the CoI.
The alignment does not pass through any wildlife area or reserved forest.
The road side plantation is notified protected forest.
It is found that the project under reference can be categorized under Category-
A as per Environmental Guidelines for Selected Infrastructure Projects.
32 SOCIAL SCREENING
Social Impact Assessment of the project is an important component of project
preparation. GOI regulations (The Government of India has recently approved "The
National Policy on Resettlement and Rehabilitation for Project Affected Families, 2003"
and published in the Gazette of India, Extraordinary Part-I, Section I, dated 17th
February, 2004.),National Highway Authority of India(NHAI) require social impact
assessment during the design stage to avoid, reduce or mitigate potential negative
impacts of project action and enhance positive impacts, sustainability and development
benefits.
The land acquisition will affect the following category of loss.
Loss of Residential Property.
Loss of Commercial Properties.
Families losing Residential cum Commercial Structures.
Loss of Agricultural Land Other Properties.
The mitigation measures to minimise the impact will be detailed in Resettlement Action
Plan.
The available right of way according to the PWD records is 20-30m. Using available
records with the PWD, boundaries of legal right of way as well as boundaries of private
properties within ROW has been verified. The limit of displacement will be limited not
to the legal right of way but to the corridor of impact. The corridor of impact is the
corridor required for the actual construction of the road, including carriageway,
Executive Summary E - 27
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
shoulders, embankments and longitudinal drainage. Within this corridor there should be
no structures or hindrances.
33 COST ESTIMATE
The project cost is worked out according to the improvement proposal detailed under
chapter 5. Cost of civil works is calculated bill wise and other non civil items like R&R
cost, land acquisition cost, Utilities relocation cost, Environmental cost, contingencies etc
are added to arrive the total project cost. The summary of Total Project Cost is presented
under table E-24
Table E-24: Summary of Project Cost
S. Rate Amount
Items Unit Quantity
No. (lakhs) (Lakhs)
A ROAD WORKS
EACH INDIVIDUAL CROSS SECTION
1 km 69.328
(TCS1, TCS2, ETC)
TCS : 1A
TCS : 1B
TCS : 1C
TCS : 1D
TCS : 2A
TCS : 2B
TCS : 3
TCS : 4
2 MAJOR BRIDGES m -
Executive Summary E - 28
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
S. Rate Amount
Items Unit Quantity
No. (lakhs) (Lakhs)
5 FLYOVER m 120 11.52 1,382.00
9 SERVICE ROAD
Executive Summary E - 29
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Do Nothing Scenario
This scenario is the present state of the road which is no improvement has been
involved with the roads.
Sensitivity Analysis
Two critical factors could affect the viability of the project and these are the Capital Cost
and traffic level. The capital cost can increase or the expected traffic growth could not
materialise or both factors could occur simultaneously sensitivity check using the
following parameters has been carried out:
Sensitivity Option S1 Increase in base costs by 15%
Sensitivity Option S2 Decrease in base benefits by 15%
Sensitivity Option S3 Inc in base costs by 15% & decrease in base benefits by 15%
Cost benefit streams for each link and combined for individual NH Sections are
calculated. Decrease in MT time costs reported in these tables represents the cargo/
freight time costs. The EIRR and NPV (at 12%) for each link and section along with
sensitivity analysis have been presented as follows:
Executive Summary E - 30
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
35 PROJECT VIABILITY
Financial Internal Rate of Return (FIRR) has been worked out based on Discounted Net
Cash Flow technique by comparing both cost stream and revenue stream. FIRR (%) has
been worked out for with 25 years of concession period and the results are given below:
Financial Indicators
Concession Period 20 Years 25 Years 30 Years
Grant 40% 40% 35%
Equity IRR 13.0% 15.3% 15.5%
From the above table it can be interpreted that the project is viable for the concession
period of 25 Years with 40% VGF OR for a concession period of 30 years with 35% VGF.
However the project is not viable in 20 years concession period with maximum possible
40% grant.
Executive Summary E - 31
CHAPTER 1: PROJECT BACKGROUND
The Louis Berger Group, Inc. Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
TABLE OF CONTENTS
LIST OF TABLES
Table 1.1: Construction Packages ............................................................................................... 4
Table 1.2: Bypass Details .............................................................................................................. 4
LIST OF FIGURES
Fig. 1.1: Project Location Map ...................................................................................................................3
1.1 BACKGROUND
Ministry of Road Transport and Highways, Government of India has decided to take up
the development of various National Highways Corridors where the intensity of traffic
has increased significantly and there is requirement of augmentation of capacity for safe
and efficient movement of traffic.
This project is a part of the above mentioned programme and the project awarded to
Consultant is Consultancy Services for rehabilitation and up-gradation of the existing 2-
lane National Highway71 to four lanes configuration in the State of Haryana. The
National Highways Authority of India (NHAI) has been entrusted with implementation
of the development of this corridor from Ministrys Plan Funds.
In order to fulfil the above task, The National Highways Authority of India has entrusted
the work of preparation of the feasibility study, Environmental and Social Impact
Assessment and Detailed Project Report for the above project to M/s Louis Berger
Group, Inc., vide contract agreement dated 30th March, 2010. The Letter of Acceptance
was communicated vide NHAIs letter No PB&HP/DPR/NHDP-IV/08/10794.
The Consultant shall study the possible locations and design of toll plaza. Wayside
amenities required on tolled highway shall also be planned. The local and slow traffic
may need segregation from the main traffic and provision of service roads and fencing
may be considered, wherever necessary to improve efficiency and safety.
The general scope of services is given in the sections that follow. However, the entire
scope of services would, inter-alia, include the items mentioned in the Letter of
Invitation and the TOR. The Consultant will also make suitable proposals for
widening/improvement of the existing road to 4 lanes configuration and strengthening
of the carriageways, as required at the appropriate time to maintain the level of service
over the design period. The Consultants shall prepare documents for BOT contracts for
each DPR assignment all ready to implement good for construction drawings shall be
prepared.
Environmental Impact Assessment, Environmental Management Plan and Rehabilitation
and Resettlement Studies shall be carried out by the Consultant meeting the
requirements of the lending agencies like ADB/ World Bank/ JBIC etc.
Wherever required, consultant will liaise with concerned authorities and arrange all
clarifications. Approval of all drawings including GAD and detail engineering drawings
will be got done by the consultant from the Railways. However, if Railways require
proof checking of the drawings prepared by the consultants, the same will be got done
by NHAI and payment to the proof consultant shall be made by NHAI directly.
Consultant will also obtain NO Objection Certificate from Ministry of Environment and
Forest and also incorporate the estimates for shifting of utilities of all types involved
from concerned local authorities in the DPR. Consultant is also required to prepare all
Land Acquisition papers (i.e. all necessary schedules as per L.A. act) for acquisition of
land either under NH Act or State Act.
The DPR consultant shall prepare the Bid Documents, based on the feasibility report,
due to exigency of the project for execution.
Consultant shall obtain all types of necessary clearances required for implementation of
the project on the ground from the concerned agencies. The client shall provide the
necessary supporting letters and any official fees as per the demand note issued by such
concerned agencies from whom the clearances are being sought to enable
implementation. In case Consultant does not obtain all the necessary clearances up-to the
completion of the assignment, deduction up to 5% amount will be made from the final
payment. The amount thus deducted will be released after all necessary clearances have
been obtained.
Km 239+000
Km 307+000
1.6 BYPASSES/REALIGNMENTS
There is one bypass in the project highway. All the bypasses as well as the realignment
shall be of four lane configuration with paved shoulder. The details of stretches to be
bypass are given in Table 1.2.
Table 1.2: Bypass Details
Name of From Side of Length of
No. To (Ex.km)
Town/Village (Ex.km) Existing road Bypass(Km)
1 Jind Bypass 292+700 307+000 LHS 15.650
Total 15.650
All of the minor bridges are to be reconstructed as they have been designed for 40R
loading.
TABLE OF CONTENTS
LIST OF TABLES
Table 2.1: R&R Entitlement Framework ................................................................................................... 4
Table 2.2: Demographic Profile of the Project Area ................................................................................ 6
Table 2.3: Socio-Economic Profile of the Project Affected Settlement .................................................. 6
Table 2.4: Socio-economic Indicators of the Project Affected Districts................................................. 7
Table 2.5: The Project Road Characteristics .............................................................................................. 8
Table 2.6: Distribution of Entitled PAFs ................................................................................................... 9
Table 2.7: PAFs by Type of Families ........................................................................................................ 10
Table 2.8: Age-Sex Composition of PAPs ............................................................................................... 10
Table 2.9: Education Level of PAPs ......................................................................................................... 11
Table 2.10: Occupation Profile of PAPs................................................................................................... 11
Table 2.11: Average Sources of Income (Rs.) of Different Social Groups ........................................... 11
Table 2.12: Major Issues and Agreement Reached at village level consultation ............................... 12
Table 2.13: Role and Responsibilities Identified after Consultation ................................................... 13
Table 2.14: Village wise Acquisition of Land (in Sqm) ......................................................................... 15
Table 2.15: Cost Estimate for Land Acquisition and R&R.................................................................... 18
Table 2.16: Resettlement Action Plan (RAP) Implementation Schedule ............................................ 19
Table 2.17: Number of Properties Affected ............................................................................................ 20
LIST OF FIGURES
Figure 2.1: Methodology and Approach adopted for Resettlement Action Plan ............................... 3
Methodologies adopted for the preparation of RAP include collection of data from both
primary and secondary sources. Secondary data/information have been collected from
the project records, published reports, discussions with officials from NHAI and other
functionaries, stakeholders consultation, groups discussions, etc. The main sources of
primary data have been the local communities and census survey among the potential
PAPs. In addition, 25% of the PAPs surveyed formed the sample for collecting detailed
baseline socio-economic data. The methodology and approach adopted for the
preparation of Resettlement plan has been summarized in Figure 2.1.
In order to assess the extent of losses, measurement and survey of structures and other
assets were carried out after finalization of design. To quantify losses, designs were
superimposed on revenue maps. Basic schedule of rate (BSR) and market values were
collected and accounted in the valuation of assets and properties to finalize budgetary
requirement for compensation and implementing R&R activities.
Background information about the project highway Visually identify problematic locations.
area. Social, historical & cultural background of the
districts of the project.
Identification of problematic stretches with
respect to congestion and encroachments.
Study of demographic, social, economic & growth
patterns of population of the highway area.
Consultation process to obtain the views
and possible solutions from the local
Detailed study of demographic features of project people, NGOs and other Govt. officials.
district, villages and towns (Census of India
preparation of report
Figure 2.1: Methodology and Approach adopted for Resettlement Action Plan
In accordance with the provision of -NRRP 2007 and NH Act 1956, an R&R entitlement
framework for the different categories of entitled persons (EPs) has been prepared. As per
the framework, all the titleholders and project affected families who are affected will be
entitled to a combination of compensation measures and resettlement support,
depending on the nature of ownership of lost assets and the extent of the impact caused.
The entitlement framework for supporting the PAFs of this project is presented in the
Table 2.1, below.
Table 2.1: R&R Entitlement Framework
Unit of
Type of Loss R&R Entitlement Framework
Entitlement
Agricultural Titleholder (i) Compensation as per the NH LA Act 1956
land Family (ii) Compensation for full parcel of plot if land left
after acquisition is not viable.
(iii) compensation for lost irrigation
structure(including pump)
(iv) Ex-gratia of Rs 20,000 to each Khatedar as per
provision of NRRP 2007
(ix) Additional assistance to the farmers whose land is
divided because of acquisition equivalent to cost of
irrigation pipeline joining the two agricultural filed as
per NH Act 1956
Unit of
Type of Loss R&R Entitlement Framework
Entitlement
(x) Additional assistance for the loss of accessibility to
the farmer as per provision of NH-Act 1956.
Homestead Title holder (i) Compensation as per NH LA Act 1956 for the loss
(or non-agri. of homestead land and structure
land) (ii) Ex-gratia of Rs 20,000 to each Khatedar as per
provision of NRRP 2007
(iii) Those affected but not displaced will get
compensation for the portion of homestead land and
structure affected by the project and permission to
salvage construction material
(iv) Those displaced will get
Compensation for the structure affected (full)
computed at CSR without deducting depreciation
Permission to salvage construction material,
Other R&R assistance as per provision of NH Act
1956
Land under Titleholder (i) Compensation for the loss of land used for
commercial (Owner and commercial purpose.
use occupier) (ii) Ex-gratia of Rs 20,000 to each Khatedar as per
provision of NRRP 2007
(iii) For the structure affected (part or full), compensation
will be computed at BSR without deducting depreciation
(iv) Permission to salvage construction material
(v) If more than 25% of the structure is lost, the affected
business/work place will be categorized as displaced.
(vi) PAFs affected but not displaced will get
compensation for the portion of land lost and the
structure (at CSR without depreciation) affected by the
project.
(vii) Other assistance as per provision of NH Act 1956
Titleholder (i) He/she will receive only compensation for both land
(Absentee and structure (owned)
Land Lord) (ii) Permission to salvage materials from the demolished
structure.
Other assets Owner Loss of other assets (including wells, trees) will be
affected compensated equivalent to their replacement value.
family
Common Community Common properties will be replaced in consultation
infrastructur with the community
e and Civic infrastructure will be replaced in consultation
common with the affected community and the local
Property administration
Resources
Any Affected Any unforeseen impact would be mitigated/enhance as
Unforeseen community per the NH Act 1956 or through any additional measures
Impacts and/persons as may be required
Total % % Non-
NAME % Male % Female % SC % Literacy
Population Worker Workers
Jhanj Khurd 2203 55% 45% 16% 56% 35% 65%
Ahirka 3747 53% 47% 17% 58% 41% 59%
Kaer Kheri 1174 54% 46% 24% 51% 51% 49%
Amarheri 3722 53% 47% 15% 56% 39% 61%
Haibatpur 2498 55% 45% 30% 57% 29% 71%
Pindara 3141 55% 45% 26% 54% 32% 68%
Ashrafgarh 2374 55% 45% 34% 54% 46% 54%
Kishanpura 1284 53% 47% 3% 49% 36% 64%
Gobindpura 1683 54% 46% 48% 53% 38% 62%
Birbaraban 136 57% 43% 7% 49% 57% 43%
Ikas 2508 53% 47% 11% 61% 45% 55%
Ramrai 5861 55% 45% 17% 53% 55% 45%
Ramgarh 3035 53% 47% 28% 56% 49% 51%
Bishanpura 2274 53% 47% 20% 56% 38% 62%
Baroli 2319 55% 45% 25% 54% 38% 62%
Nirjan 3264 53% 47% 19% 58% 51% 49%
Anoopgarh 1878 55% 45% 10% 56% 54% 46%
Jind 1044 55% 45% 41% 55% 41% 59%
Naguran 11265 53% 47% 20% 46% 46% 54%
Table 2.4 explains about the socio-economic conditions of the project area. Where SC
population is 19.56% and workers are 24.04% in Jind District. Further, agricultural
workers are 19.93% to total population. Intensity of cropping of about 200 (more than two
season crop in one year) suggests higher agricultural development in the project area is
high. Other Social Indicators are also in favor of high development indices.
Table 2.4: Socio-economic Indicators of the Project Affected Districts
S.
Particulars Jind
No.
1 Density of population (per sq.km) 440
2 percentage of literates to total population 62.80
3 percentage of Schedule castes to total population 19.56
4 Percentage of Workers to total population 24.04
5 Percentage of Agriculture Workers to total workers 19.93
6 Percentage of Agriculture Workers to total population 4.79
7 Total Irrigated Area (, 000 Ha.) 429
8 Net Irrigated Area (, 000 Ha.) 220
9 Net Area Shown (, 000 Ha.) 236
Area under HYV of wheat to total cropped area of wheat (,000
10 203.1
Ha.)
Area under HYV of Paddy to total cropped area of paddy
11 116.5
(,000 Ha.)
Area under HYV of Bazar to total cropped area of maize (,000
12 34.4
Ha.)
S.
Particulars Jind
No.
13 Percentage of Net Irrigated area to Net shown Area 93.22
14 No of tractors registered 13205
15 livestock population per veterinary institutor (,00 Number) 1165
16 Population served per medical institution 482841
17 Number of Pre-Primary school 629
18 Number of Middle school 130
19 Number of High/ Higher Senior Sec. School 263
20 Length of Metaled Road (Km) 1149
21 Number of Commercial Bank 59
23 Number of Police Station 12
24 Number of Post Office 164
Table 2.5 presents occupational structure of the project affected area. Occupational
structure of the project area suggests high proportion of population engaged in
agricultural activities. About 21.90% of the populations have been engaged in cultivation.
About 7.2% of the total population of the area is agricultural labors. Total main and
marginal workers is about 43%.While female participation in agriculture labor similar to
male, the female participation has been less in cultivation and other works.
Table 2.5: The Project Road Characteristics
Post Graduate
Professional
Neo-literate
High School
Secondary
Graduate
Category
Illiterate
Children
Primary
Middle
Higher
Total
SC 26 19 5 12 6 0 0 0 0 0 68
OBC 112 126 140 127 125 120 45 65 38 4 902
OC 95 105 75 52 42 45 21 36 29 1 501
Total 233 250 220 191 173 165 66 101 67 5 1471
Source: Baseline Socio Economic/ Census Survey, 2010
(vi) Occupational Structure
Out of total 1471 PAPs, 3.9% of PAPs are engaged in service and 6.8% are in business.
About 14.27% are engaged in cultivation and 11.7% engaged as agriculture labour.
Another 161 PAPs are unemployed. About 14% of total population in OBC categories is
unemployed which is higher than OC (6.8%).
Table 2.10: Occupation Profile of PAPs
Occupation profile(PAPs)
Total PAPs
Package
Employed
cultivator
Students
Business
Workers
Service
Labour
House
others
Wife
SC 3 3 1 14 18 8 Un-
1 8 12 68
ST 0 0 0 0 0 0 0 0 0 0
OBC 25 56 155 78 255 110 125 64 34 902
OC 30 32 54 61 175 55 35 25 34 501
Total 58 91 210 153 448 173 161 97 80 1471
(vii) Income Level
As evident from the Table 2.11, average annual income of PAFs varies from Rs. 45339 for
SC to Rs. 68393 for OC. Among the sources of household income, the average income
from agriculture is generally less than income from service sector. People engaged in
tertiary sector (service and others) have higher average income as can be seen from the
data analyzed and presented in Table 2.7.
Table 2.11: Average Sources of Income (Rs.) of Different Social Groups
Major
Location Agreement reached Remarks
Issues/concern
about loss of structures and relocation
residence Plantation of fruit-bearing
Junction trees,
improvement and Junction improvement without
land acquisition LA,
Uchana LA from built-up Avoid/minimize LA in built- Compensation of
section up area by reducing RoW upto tube wells is
Acquisition of 45m , given only after
Water bodies like Compensation of tube wells, joint verification
pump house, Suitable traffic management with Revenue
Crossing of roads for road safety, officers
and need of
underpass
*DLPFC: District level Price Fixation Committee
(ii) Consultation at Official Level
The consultants team is in continuous touch with the officials from National Highways
Authority of India (NHAI) including Chief General Manager (CGM) and Project Director,
Rohtak and NHAI, HQ Office, Delhi. Various project related issues were discussed in the
meeting itself. Periodic presentations to Honble Minister (MoRT&H) were also held and
appraised progress of the work. Important agenda of discussion during these meetings
have been improvement proposal in built-up locations, community facilities in settlement
portion, cross drainage, traffic forecast, land acquisition and other regulatory clearances.
Consultation during Detailed Project Preparation Stage
Consultation during detailed project preparation stage is planned. These consultations
will be held soon after finalization of land plan.
(iii) Role and Responsibilities Identified during Consultation
The above-mentioned highlight of consultation suggests role and responsibility of
stakeholders in project planning. Table 2.13 envisaged responsibilities of officials and
expected benefits from the consultation. From the consultation, it was established that
implementation of the project could be better done in close coordination with regular
PWD engineers, forest officials, revenue officials and local representatives.
Table 2.13: Role and Responsibilities Identified after Consultation
Expected Benefit for the
Stakeholders Roles and Responsibility
Project
Potential Project Participate in formal and Easing implementation.
Affected Persons, informal public meeting, Raise Incorporation of good
Project affected critical issues relevant to the practices (From long term
groups, project, memories of the people) of
Project Affected Suggest alternative alignments, the past in project design.
Communities, Options of widening, Planning for road safety
Host population Methodologies for agreement on issues.
compensation and assistance Community Capacity
Suggest methodologies for building and sense of
continued participation in project ownership of the project.
cycle
1 The National Highways Act, 1956 with National Highways Authority of Indian Act, 1998 and Allied
Rules. Law Publishers (India) Private Ltd, undated. The LA Act of 1894 does not apply in
case of NHAI projects.
earlier.
The ESDU at apex level will have overall responsibility for policy guidance, coordination,
and contingency planning, monitoring and overall reporting during RP implementation.
The ESDU headed by Chief General Manager (Land and Environment), will have a
Manager R&R and Manager Environment. The PIU and field offices will coordinate with
the various Government Departments, like Revenue, Forest, other administrative units at
various levels, and other local NGOs for convergences of resources and to facilitate
smooth implementation of RP.
(ii) Roles and Responsibilities
The role and responsibilities of the various offices in R&R implementation is presented in
this section. The Chief General Manager (CGM) and Regional Officer (Technical) will be
in charge of the overall project activities and participate in the State level Committee to
facilitate land acquisition, pre-construction activities and implementation of R&R
activities. The Project Director PIU shall:
co-ordinate the implementation of R&R activities with corporate and field staff;
review the implementation of R&R;
review monthly progress;
Monitor the progress on R&R and land acquisition;
establish appropriate mechanism for monitoring and evaluation; and
plan and conduct training programs for staff capacity building
The Manger (Tech) will be responsible for acquisition of land, relocation of road side
properties, forest clearance. Specific roles are as follow
Co-ordinate with the District Administration, on LA R&R,
Make available the RAP at the project site office;
where required;
Liaison with the District Administration and DRDA for dovetailing government
developmental programs for the socio-economic benefit to the PAPs;
Develop and maintain a PAP level database including aspects related to losses,
compensation, R&R entitlement, release of funds and utilization
Ensure transfer of funds (including the R&R entitlement) in the account of PAFs;
Ensure release of amount as per the milestones indicated in RAP;
Monitor physical and financial progress on LA, R&R;
(iii) RAP Implementation Tasks
The PD-PIU will be responsible to carry the following task concerning resettlement of the
project:
Overall responsibility of implementation of R&R activities of RAP;
Responsible for land acquisition and R&R activities in the field;
Ensure availability of budget for R&R activities;
Liaison with district administration for support for land acquisition and
implementation of R&R ; and
Participate in the District Level Committees.
TABLE OF CONTENTS
LIST OF TABLES
Table 3.1: Urban & Built-up sections along the Project Road ...............................................................2
Table 3.2: Existing Carriageway width Schedule ...................................................................................3
Table 3.3: Carriageway Distribution along the Project Road ................................................................3
Table 3.4: Road Length and Height of Embankment .............................................................................3
Table 3.5: Road Condition distribution ....................................................................................................4
Table 3.6: Summary of Right of Way ........................................................................................................4
Table 3.7: Summary of Cross-Drainage Structures along Existing Road
(Km 239.000 to Km 292.700).......................................................................................................................5
Table 3.8: Embankment Raising Sections ................................................................................................6
Table 3.9: List of Road Junction .................................................................................................................6
Table 3.10: Way Side Amenities ................................................................................................................8
Table 3.11: Water Bodies along the Project Corridor .............................................................................8
Table 3.12: Homogeneous Section ..........................................................................................................10
Table 3.13: VDF Values.............................................................................................................................10
Table 3.14: Summary of Existing Structures..........................................................................................11
Table 3.15: Details of Existing Bridges ...................................................................................................12
Table 3.16: Details of Existing Culverts..................................................................................................12
Table 3.17: GPS Control Points ................................................................................................................18
Table 3.18: BM Pillars Details ..................................................................................................................21
LIST OF FIGURES
Land Use
The land use is principally of following categories: Built-Up and Agricultural.
Agriculture plays a predominant role in the economy of the region particularly with
respect to generation of employment and share in GDP.
Table 3.1: Urban & Built-up sections along the Project Road
Sl.
Village Name From To Length Remarks
No
Narwana Tahsil up to
1 Data Singhwala 238.750 241.200 2450
267+050
2 Garhi Village 241.200 243.250 2050
3 Chak Ujhana Village 243.250 244.000 750
4 Ujhana 244.000 251.350 7350
5 Belar Khan Village 251.350 256.250 4900
6 Mohal Khera Village 256.700 257.000 300
Railway Track at
258+300, Existing 4
7 Narwana 256.250 262.300 6050
Lane section along
Narwana Town
8 Dumar Khan Kalan 262.300 266.000 3700
9 Dumar Khan Khurd 266.000 267.050 1050
10 Ghaso Khurd 267.050 268.900 1850
11 Safa Kheri Village 268.900 271.600 2700
12 Kharakbura Village 271.600 272.900 1300
13 Palwa Village 272.900 275.000 2100
14 Uchana 275.000 277.700 2700
15 Barodha Village 277.700 281.950 4250
16 Khatkar Village 281.950 287.280 5330
17 Jhanjh Kalan 287.280 289.500 2220
18 Jhanjh Khurd 289.500 290.900 1400
19 Kehar khera 290.900 291.352 452
20 Hirka Village 291.325 292.700 1375
Based on extent of built-up, land use and availability of ROW road widening scheme
shall be provided for built-up areas. Built up sections with poor horizontal geometrics/
less ROW will be provided with bypass.
The roadside environment is variable from urbanized town developments to rural
agricultural areas, with intermediate semi-urban settlements and semi-rural open areas
with occasional roadside dwellings and small businesses scattered throughout the route.
Nearly 14.40% of land use is of urban type, 7.20%of built up area, 50.60% of the project
corridor has purely agricultural land and 27.90% is rural area.
Existing Cross Section
The project road section comprises 7.0m wide carriageway and 1.0m to 2.5m wide
shoulders on either side. There are isolated locations, especially village and built-up
sections and the some of the bridges approaches, where 1.5m wide pave shoulders are
provided.
Road elevations vary from ground level to typically 3m above ground for locations such
as waterlogged areas or major bridge crossings where embankment heights can be 8-10
meters above ground level. The following tables give the distribution of length of road in
terms of height of embankment based on reconnaissance.
Table 3.2: Existing Carriageway width Schedule
Chainage Length in Lane Width of Carriage
From To Km Configuration way
239.00 247.16 8.162-Lane with PS 7+(2.0 to 3.0)
247.16 247.46 0.30 2-Lane 6.00
247.46 258.65 11.902-Lane with PS 7+(2.0 to 3.0)
258.65 262.00 3.35 4-Lane 2 x 7.50
262.00 293.0 31.02-Lane with PS 7+(2.0 to 3.0)
2-Lane with PS/4- -
293.00 307.00 14.00
Lane
Total Length of Project = 68.0
The condition of the CW varies between good to poor.
Table 3.3: Carriageway Distribution along the Project Road
Length in Km and Percentage
Two Lane (7.0m Two Lane with paved Four Lane(dual
Total
Blacktop) shoulder(10.0m Blacktop) 7.0m carriageway)
0.3 57.35 10.35 68.0
0.6 % 84.4% 15.2% 100.00%
Shoulders: Mostly soft shoulders width varies from 0.5m to 3.0m. At few places hard
shoulders are also available with width varies from 1.5m to 2.4m. The condition of soft
shoulders varies from fair to very poor. The condition of hard shoulders varies from
Good to fair.
Almost of Project road is in embankment, there are some isolated low-lying sections of
the road that need to be raised.
Table 3.4: Road Length and Height of Embankment
Length of Project road with Height of Embankment Total
<0.5m 0.5-1.0m 1.0m to 2.0m 2.0m -4.0. > 4.0m
12 km 17.5 km 7 km 17.5 km 0 km 54 km
22.3 (%) 32.4(%) 12.9 (%) 32.40 (%) 0 (%) 100
* Rest of 15 Km is on Jind Bypass.
Road Condition
The project road section has riding quality varying from good to poor along its length.
Consultants have carried out a visual pavement surveys. At quite a few locations the
pavement has been failed. The observed pavement condition of the project road, based
on crack area, pot-hole area, and ravelling area, has been divided into three categories,
Good, Fair and Poor. The following table gives the distribution of length of road in terms
of road condition based on reconnaissance. Details of pavement condition are presented
in Annexure 3.2.
Existing Facilities
Various Way side Amenities have been observed at many places along the project
corridor. The list of bus stops is given in Table 3.10.
Table 3.10: Way Side Amenities
S. No. Name of Existing Amenity Total
1 School 11
2 College 3
3 Hospitals 6
4 Petrol pump 21
5 Bus-stop 11
6 Hotel 3
7 Dhabas 17
Location of Water bodies
Along the project corridor, minor irrigation channels and its distributaries are crossing
the road. Also localised ponds are seen. The list of local ponds is summarized here in
Table 3.11 below.
Table 3.11: Water Bodies along the Project Corridor
Distance
Location Water
Sl.No Side from Road
at km Resources
edge(m)
1 240+150 Pond LHS 2
2 253+000 Pond LHS 3
3 253+400 Pond LHS 1
4 264+450 Pond LHS 5
5 279+000 Pond RHS 5
6 284+500 Pond LHS 8
7 285+000 Pond RHS 10
8 289+150 Pond LHS 5
Visual inspection of survey reveals that the pavement condition varies for each Km
stretch.
Taking all the pavement distress into consideration, overall pavement condition is
shown in Table 3.5. The sections visualised have wide cracking at some locations as
well as hair cracks at few of the places. The sections show poor condition both in
structural failure and functional failure due to extensive cracking and ravelling.
Most sections passing through towns, villages, near level crossings and
intersections are damaged. Due to high water table along the road sections
pavement deterioration is faster. All variety of cracking pattern has been observed
mostly along wheel paths as detailed in pavement condition survey data.
Transverse cracks identified at bridge/ ROB entry and exit. Reflective cracking
observed at some locations even patched portion were also cracked. Road side
drains are weak at some sections which lead to rain water stagnation at shoulders.
Paved shoulders were covered with bushes and grass along some sections making
there use less effective. Pavement edge drop varies from 0 to 200 mm.
Pavement edge drop
Pavement edge drop (settlement/erosion of shoulder at the edge of pavement) has been
measured at every 100m interval. It was found that mostly the level of unpaved
shoulders does not match with the road profile and edge drop varies from 0 to 250 mm
on the project road.
Embankment Condition
Locations of high embankment have already been discussed in the above paragraphs.
The condition of embankment is fair throughout the project length.
Homogeneous Sections
As it is not practical to have different overlay
thickness from kilometre to kilometre, adjacent
lengths have been combined for treatment.
Using the method of cumulative differences to
the corrected deflection data, demarcation of
homogeneous sections has been done. The
characteristic deflections for the respective
homogeneous sections were calculated as the
mean plus 2 standard deviations are included
in Annexure 3.6.
The Project Road has been divided into 2 homogeneous segments based on cumulative
difference approach. Control test data on each homogeneous section has been corrected
for temperature and seasonal variation. The corrected data used to calculate mean,
standard deviation and characteristic deflection for each homogeneous section. List of
homogeneous sections are shown below in Table 3.12.
Table 3.12: Homogeneous Section
HOMOGENEOUS Location
SECTION From To Deflection
HS-1 239.000 264.000 0.72
HS-2 264.000 307.000 0.70
Maximum value of deflection = 1.25
3.4.2 Axle Load Survey
The Axle load survey in both the directions is
carried out at 259+000 near Narwana on the
project road stretch on a random sample basis for
trucks, LCVs (both empty and loaded) for 1 days
(24 hours). The axle load survey is carried out
using axle load pads. Axle load survey analysis
has been performed as per IRC standards for the
assessment of Vehicle Damage Factor (VDF). The
result of the axle load survey is presented in Table
3.13 below. The Axle load data and its analysis
are included in the Annexure 3.7.
Table 3.13: VDF Values
Sr. No. Type of Vehicle VDF
1 LCV 0.84
2 Bus 0.46
3 2 Axle 6.13
4 3 Axle 4.86
5 M-axle 3.59
Terms of Reference. The variation of measured IRI which has been converted to BI is
shown in the Figure 3.1. Details of Roughness Surveys are given in Annexure 3.8.
3/670
(Chainage RCC Slab Minor Poor
5 3 x 10.8m Reconstruction
along Jind Bridge Bridge Condition
Bypass)
** 3/670 is the design chainage along Jind Bypass
The General condition of culverts in project corridor is not very satisfactory except that
some of these require repairs and are to be widened up to required width of four lanes.
Distresses in form of exposed reinforcement, corroded reinforcement, honey combing etc
in the slab portion and damaged pointing, exposed joints, cracks in PCC substructures/
head walls, parapets and PCC wing walls and chocked HP culvert with damaged head
wall are observed in some of the culverts which require repairs. All the Slab Culverts
were found made of either brick masonry or plain cement concrete but most of them are
in poor/ very poor condition. The details of culverts are given in Table 3-16.
Table 3.16: Details of Existing Culverts
Existing Type of
S.No. Culvert No. Span Arrangement
Chainage Structure
1 239+098 - Pipe Culvert 1 X 0.9
2 239+241 - Slab Culvert 1x2.9
3 239+812 240/2 Pipe Culvert 1 X 0.9
4 239+957 241/1 Pipe Culvert 1X1
5 240+448 - Pipe Culvert 1 X 0.9
6 240+875 241/3 Pipe Culvert 1 X 0.9
7 241+144 - Pipe Culvert 1 X 0.9
8 241+750 - Pipe Culvert 1 X 0.9
9 242+158 - Slab Culvert 1 X 1.50
10 244+863 - Pipe Culvert 1 X 0.9
11 245+176 - Pipe Culvert 1 X 1.20
12 245+507 - Pipe Culvert 1 X 1.20
13 246+611 247/1 Pipe Culvert 1 X 1.20
14 246+946 - Pipe Culvert 1 X 0.9
15 247+529 - Pipe Culvert 1 X 0.9
16 247+806 - Slab Culvert 1x1.2
17 247+900 - Pipe Culvert 1 X 0.9
Existing Type of
S.No. Culvert No. Span Arrangement
Chainage Structure
18 249+012 250/1 Pipe Culvert 1 X 0.9
19 250+463 - Pipe Culvert 1 X 0.9
20 251+132 252/1 Pipe Culvert 1 X 0.9
21 251+345 252/2 Slab Culvert 1 X 3.7
22 251+990 252/3 Pipe Culvert 1 X 0.9
23 252+446 - Pipe Culvert 1 X 0.9
24 253+297 254/1 Pipe Culvert 1 X 1.20
25 254+500 - Slab Culvert 1 X 0.7
26 255+243 - Pipe Culvert 1 X 0.9
27 255+582 - Pipe Culvert 1 X 0.9
28 256+032 - Pipe Culvert 1 X 0.9
29 256+521 257/2 Pipe Culvert 1 X 0.9
30 257+070 - Pipe Culvert 1 X 1.20
31 258+102 - Pipe Culvert 1 X 0.9
32 258+100 - Pipe Culvert 1 X 0.9
33 261+395 - Slab Culvert 1X4
34 262+761 - Slab Culvert 1 X 0.8
35 262+817 - Slab Culvert 1 X 2.1
36 262+880 - Slab Culvert 1 X 2.3
37 263+064 - Pipe Culvert 1 X 0.90
38 263+508 - Pipe Culvert 1 X 0.90
39 264+538 - Pipe Culvert 1 X 0.90
40 265+189 266/1 Slab Culvert 1X3
41 265+212 266/2 Slab Culvert 1X3
42 265+231 266/3 Slab Culvert 2X3
43 265+254 266/4 Slab Culvert 1X3
44 265+268 266/5 Slab Culvert 1X3
45 266+553 - Pipe Culvert 1 X 0.90
46 267+092 - Pipe Culvert 1 X 0.90
47 267+327 - Pipe Culvert 1 X 0.90
48 267+830 - Pipe Culvert 1 X 0.90
49 269+010 - Pipe Culvert 1 X 0.90
50 269+149 - Pipe Culvert 1 X 0.90
51 270+445 - Pipe Culvert 1 X 0.90
52 270+463 - Pipe Culvert 1 X 0.90
53 271+785 - Pipe Culvert 1 X 0.90
54 272+734 - Pipe Culvert 1 X 0.90
55 273+042 274/1 Pipe Culvert 1x0.6
56 273+086 - Pipe Culvert 1x0.9
57 273+155 - Slab Culvert 1 X 1.50
58 273+280 - Pipe Culvert 1x0.9
59 273+816 274/2 Slab Culvert 1X3
60 274+063 - Pipe Culvert 1x1.2
61 274+282 - Slab Culvert 1 X 1.20
Existing Type of
S.No. Culvert No. Span Arrangement
Chainage Structure
62 275+940 - Slab Culvert 1X3
63 276+262 - Pipe Culvert 1x0.9
64 276+767 - Pipe Culvert 1x0.9
65 277+737 - Slab Culvert 1x1.2
66 278+073 - Arch 1x1.5
67 278+396 - Pipe Culvert 1 X 0.90
68 279+070 - Pipe Culvert 1 X 0.90
69 279+497 - Slab Culvert 1x1.2
70 280+066 - Pipe Culvert 1 X 0.90
71 280+479 - Slab Culvert 1 X 2.50
72 280+557 281/2 Pipe Culvert 1 X .90
73 281+860 281/3 Pipe Culvert 1 X .90
74 282+300 282/1 Pipe Culvert 1 X .90
75 283+224 283/1 Pipe Culvert 1 X .90
76 285+069 284/1 Slab Culvert 1X3
77 285+082 286/1 Slab Culvert 1X3
78 287+413 286/2 Slab Culvert 1 X 2.50
79 288+044 288/1 Pipe Culvert 1 X 0.90
80 288+518 - Pipe Culvert 1 X 0.90
81 289+175 - Pipe Culvert 1 X 0.90
82 290+415 - Pipe Culvert 1 X 0.90
83 291+005 - Pipe Culvert 1 X 0.90
84 292+393 - Pipe Culvert 1 X 0.90
Proposed
SI. Structure Type of
Bypass Span Arrangement
No. no. Structure
Chainages
17 2+434 - Pipe 1 x 0.60m
18 2+649 - Pipe 1 x 0.60m
19 2+904 - Pipe 1 x 0.60m
20 3+371 - Pipe 1 x 0.60m
21 3+441 - Pipe 1 x 0.60m
22 3+782 - Pipe 1 x 0.60m
23 4+077 - Pipe 1 x 0.60m
24 4+320 - Pipe 1 x 0.60m
25 4+584 - Pipe 1 x 0.60m
26 4+924 - Pipe 1 x 0.60m
27 5+057 - Pipe 1 x 0.60m
28 5+417 - Pipe 1 x 0.60m
29 5+709 - Pipe 1 x 0.60m
30 6+230 - Pipe 1 x 0.60m
31 6+654 - Pipe 1 x 0.60m
32 7+000 - Pipe 1 x 0.60m
33 7+123 - Pipe 1 x 0.60m
34 7+263 - Pipe 1 x 0.60m
35 7+272 - Pipe 1 x 0.60m
36 7+482 - Pipe 1 x 0.60m
37 7+849 - Pipe 1 x 0.60m
38 8+026 - Pipe 1 x 0.60m
39 8+090 - Pipe 1 x 0.60m
40 8+208 - Pipe 1 x 0.60m
41 8+570 - Pipe 1 x 0.60m
42 8+755 - Pipe 1 x 0.60m
43 9+289 - Pipe 1 x 0.60m
Structural condition
Durability aspects
The aim of condition survey is to assess the condition of existing bridges and structures
for their capacity to carry two lanes of traffic with or without widening. As a partial
component of condition survey visual observations were made keeping in view the
requirement of IRC SP-35 and IRC SP-40. According to IRC SP-40, the normally
observed signs of distresses are listed below. The common distress signals in RCC
bridges are as follows.
Cracking; cracks could be of different types and widths
Scaling
Spalling of concrete
Leaching
Rust stains
Delimitation
Deformation
Holes in Deck Slab
Visual observations carried out during the condition survey were mainly made to find
out the above listed distresses. In addition to the superstructure, the substructure also
were inspected to locate visual signs of settlement, tilting, cracking, decay, corrosion,
cavitations, abnormal scour and damage due to impact of floating bodies. Condition
survey of Bridges is given in Annexure 3.9.
TOR. The scope of Consultancy was to carry out the topographic survey to cover
following aspects:
Control Surveys
GPS Control
Total Station Traverse
Height Control
processed, verified for loop closure and networks adjusted at select locations.
Subsequent to differential post processing, loop closure was computed to identify
possible anomalies in the observed results. On satisfactory completion of loop
closure analysis, Net work adjustments were carried out to attain the final co-
ordinates for all the control pillars. The location of GPS pillars have been marked on
base map drawing and northing and easting values also shown at every control
point.
The geographic coordinates of all control points were determined on WGS84 datum.
The adjusted coordinates in WGS84 datum are presented in Table 3.17 below.
Table 3.17: GPS Control Points
Precision levelling has been carried out by two levelling teams in fore and back
direction and mean will be taken to establish the elevation of all cement concrete
pillars, and other control points, using auto-levels. This established control work of
plan and height would enable topographical survey on systematic accurate and
scientific basis.
Bench mark/ reference pillar of size 15cm x 15cm x 45cm casted in RCC of M15 grade
with a nail fixed in the centre of the top surface. These pillars are embedded in
concrete up-to a depth of 30cm with CC M10 (5 cm wide all around). The balance 15cm
above ground has been painted and BM numbers are given to each pillar. These
numbers along with RL value are shown in base map. The interval of these bench
marks pillars are 250m along the project road as per TOR. Final Data will be appended
to the preliminary Project report
The feature code is an alphanumeric code assigned to each topographical feature to
represent and communicate between surveyor and highway design engineer. Before
picking of any feature the surveyor will assign the feature code to that particular
feature and collect the x, y, z of that feature. Coding for feature shall comprise of four
characters, first two characters describing the feature and last two characters
mentioning the string number. All the surveyed points with same string name shall be
joined, (eg. road centreline, shoulder, building, etc.). All the features are not joined (e g.
Telephone poles, trees, spot levels, etc.) shall have their codes start with P. No feature
shall have its survey code starting with M, L or G. A predefined list of feature codes
have been prepared and handed to surveyors. An initial training to field surveyors has
been given by highway engineer to get acquaintance of these codes. The survey
procedure
Upon completion of horizontal and vertical control points along the project road on
permanent concrete pillars, the detailed topographical survey was carried out for the 60
to 70m corridor of the project road. Details of all physical and topographical features
within the survey corridor such as roads, rivers, streams, rail crossings, OFC / electric
/ telephone lines, high / low tension lines and their offsets from the road edge,
buildings, trees (girth more than 300mm), etc have been captured with predefined
feature codes. At locations of encroachments where ROW has been reduced or where
existing alignment can be improved upon through minor adjustments, the width of the
survey corridor is extended appropriately to accommodate the proposed alignment. At
road junction locations, survey was carried out for a length of 200 m along the cross
roads to accommodate improvements including at grade / grade separated
intersections to be designed. At interchange locations, survey covered the extent of the
structure as per GAD.
Cross sections were picked at every 50 m intervals, and at each cross-section the survey
normally extended beyond 30 m on each side of the existing road centre line with
survey points at 3-5 m apart and at all variations in the natural ground or breaks in
level.
Longitudinal levels and cross sections for major and minor rivers are taking as per
recommendations stipulated in IRC S.P.No.13 (Guidelines for the design of small
bridges and culverts) and IRC-5-2001 (Standard Specifications & Code of Practice for
Road Bridges Section I General Features of Design).
For bridges, apart from taking bridge centreline levels at regular interval of 25 m,
additional centreline levels at the start and end of the bridge has been taken. To define
channel, cross-section has been taken at proposed bridge location and in stream
direction on upstream and downstream.
For minor waterway less than 30 m length of existing bridge, only one such cross-
section has been taken each, on upstream and downstream side. For culverts, only one
reading is taken at the centre of the culvert. For pipe culvert, the invert level is taken.
The Bench Mark Pillars are presented in Table 3.18 below.
Table 3.18: BM Pillars Details
Sl
BM No. Easting Northing Level
No.
1 239/000 285270.668 345438.359 229.923
2 239/250 285305.680 345185.621 231.279
3 239/500 285341.958 344896.761 230.575
4 239/750 285369.547 344644.703 229.620
5 240/000 285405.018 344345.643 231.419
6 240/500 285445.776 343996.626 230.954
7 240/750 285512.604 343727.410 229.456
8 241/000 285510.829 343486.752 229.341
9 241/250 285551.307 343170.664 229.809
10 241/500 285581.420 342921.771 229.027
11 241/750 285600.695 342712.969 230.109
12 242/000 285589.113 342481.845 231.486
13 242/500 285572.937 341967.193 231.482
14 242/750 285557.328 341717.119 229.729
15 243/000 285575.021 341469.599 230.512
16 243/250 285535.870 341239.056 230.004
17 243/500 285549.282 340961.779 230.051
18 243/750 285508.853 340709.407 229.853
19 244/000 285494.764 340470.488 229.853
20 244/250 285515.993 340204.523 228.824
21 244/500 285473.198 339975.460 228.494
22 244/750 285490.102 339727.982 227.737
23 245/000 285448.246 339480.065 227.960
24 245/500 285414.742 338921.044 229.090
25 246/000 285418.437 338483.233 228.433
26 246/250 285382.689 338294.055 228.240
27 246/500 285371.686 338066.946 228.221
28 246/750 285352.669 337790.948 227.847
29 247/000 285336.709 337503.914 228.148
30 247/500 285313.895 336988.538 228.076
31 247/750 285323.198 336725.408 227.523
32 248/000 285280.452 336496.587 227.702
33 248/250 285262.441 336201.105 227.541
34 248/500 285280.618 335977.844 227.046
35 248/750 285260.921 335726.216 226.583
36 249/000 285217.809 335473.903 227.153
Sl
BM No. Easting Northing Level
No.
37 249/250 285208.275 335312.029 228.333
38 249/500 285229.554 335059.871 228.184
39 249/750 285201.533 334766.247 227.813
40 250/000 285155.533 334483.906 227.442
41 250/250 285165.788 334214.975 227.530
42 250/500 285124.164 333972.733 228.593
43 250/750 285100.083 333684.959 228.020
44 251/000 285124.070 333489.536 227.951
45 251/250 285074.951 333241.938 227.821
46 251/500 285057.193 333003.246 227.902
47 251/750 285070.764 332751.309 227.581
48 252/000 285050.847 332467.908 227.297
49 252/250 285028.067 332146.466 227.939
50 252/500 284980.657 331874.655 227.428
51 253/000 284976.746 331501.779 229.427
52 253/250 285032.817 331184.128 227.177
53 253/500 285051.896 330951.121 227.511
54 253/750 285036.353 330717.313 227.929
55 254/000 285083.188 330499.211 228.204
56 254/250 285095.853 330263.533 227.741
57 254/500 285112.115 330009.069 227.563
58 254/750 285100.947 329756.049 227.376
59 255/000 285150.845 329495.194 227.542
60 255/250 285134.889 329265.833 227.484
61 255/500 285174.958 329031.242 227.357
62 255/750 285165.196 328780.765 227.507
63 256/000 285180.128 328531.859 227.473
64 256/250 285226.356 328280.114 227.569
65 256/500 285245.966 328035.717 227.753
66 256/750 285231.021 327783.080 226.996
67 257/000 285244.448 327558.982 227.073
68 257/250 285258.214 327365.342 228.887
69 257/500 285271.264 327137.714 228.428
70 257/750 285282.730 326871.270 229.488
71 258/000 285328.738 326617.936 229.730
72 258/250 285306.366 326353.861 228.750
73 258/750 285360.807 326043.611 228.943
74 259/000 285333.122 325761.583 228.871
75 259/500 285356.624 325270.756 227.904
76 259/750 285380.797 324974.443 228.189
77 260/250 285398.918 324554.386 227.650
78 260/500 285412.118 324298.296 227.624
79 260/750 285461.762 324072.428 227.577
80 260/750 285675.137 323603.727 227.577
Sl
BM No. Easting Northing Level
No.
81 261/000 285775.683 323387.266 229.011
82 261/250 285878.106 323174.434 228.165
83 261/750 286122.657 322638.162 227.201
84 262/000 286239.170 322373.167 227.409
85 262/250 286373.206 322155.528 227.152
86 262/500 286446.103 321923.602 227.439
87 262/750 286559.420 321710.896 227.547
88 263/000 286763.464 321559.895 228.527
89 263/250 286875.123 321301.479 226.330
90 263/250A 286837.392 321331.629 227.011
91 263/500 286947.212 321099.005 226.538
92 263/750 287057.662 320873.959 226.477
93 264/00 287151.572 320681.146 226.984
94 264/250 287249.755 320481.120 226.896
95 264/500 287353.876 320281.161 227.026
96 264/750 287481.702 320036.469 226.230
97 265/000 287611.072 319790.494 225.594
98 265/250 287729.466 319625.198 227.860
99 265/750 287837.957 319363.068 225.859
100 266/250 288035.447 318990.951 227.450
101 266/500 288174.879 318790.925 227.519
102 266/750 288264.387 318561.297 227.693
103 267/000 288383.032 318336.481 227.741
104 267/250 288533.183 318108.032 227.360
105 267/500 288608.498 317965.429 227.321
106 267/750 288718.004 317703.786 226.863
107 268/000 288846.029 317516.746 226.641
108 268/250 288907.305 317347.524 226.750
109 268/750 289134.335 316914.470 226.863
110 269/000 289288.422 316625.224 228.802
111 269/250 289449.035 316344.218 227.208
112 269/500 289585.487 316152.094 227.274
113 269/750 289709.255 315929.708 226.860
114 270/000 289799.634 315712.036 226.804
115 270/250 289947.690 315408.533 226.135
116 270/500 290053.468 315188.749 226.089
117 270/750 290096.982 314972.506 225.656
118 271/000 290201.307 314741.055 225.591
119 271/250 290288.182 314485.197 226.426
120 271/500 290340.338 314251.811 225.946
121 271/750 290437.441 314036.183 225.774
122 272/000 290487.742 313813.261 226.276
123 272/250 290558.502 313589.594 226.142
124 272/500 290634.562 313367.217 225.976
Sl
BM No. Easting Northing Level
No.
125 272/750 290713.119 313133.329 225.586
126 273/000 290783.598 312925.015 225.891
127 273/250 290831.723 312774.423 224.941
128 273/500 290933.934 312560.899 226.031
129 273/750 290998.946 312282.895 225.810
130 274/000 291072.705 312064.514 226.885
131 274/250 291184.359 311803.396 224.878
132 274/500 291241.593 311555.492 225.399
133 274/750 291356.213 311295.714 225.756
134 275/000 291402.573 311072.746 225.508
135 275/250 291497.824 310860.055 226.746
136 275/750 291657.798 310315.355 225.916
137 276/000 291757.623 310097.417 226.336
138 276/250 291852.513 309730.619 226.692
139 276/750 291996.811 309362.420 227.245
140 277/000 292087.821 309016.553 227.040
141 277/250 292218.201 308702.348 227.064
142 277/500 292317.976 308500.992 228.144
143 277/750 292457.858 308356.613 227.356
144 278/000 292603.218 308127.891 226.638
145 278/250 292813.875 307884.969 226.290
146 278/500 292941.349 307679.382 226.366
147 279/000 293193.755 307339.823 226.812
148 279/250 293301.000 307203.502 225.592
149 279/500 293444.265 307047.713 226.521
150 279/750 293616.919 306780.371 226.060
151 280/000 293795.922 306579.284 226.165
152 280/250 293987.233 306292.524 226.989
153 280/500 294125.867 306146.013 225.513
154 280/750 294261.621 305926.577 225.605
155 281/000 294415.139 305764.298 225.025
156 281/750 294841.184 305159.202 225.027
157 282/250 294597.593 305520.465 225.194
158 282/250 295131.065 304777.198 224.440
159 282/500 294707.262 305335.266 224.668
160 282/500 295295.528 304595.878 224.287
161 282/750 295451.347 304390.564 224.429
162 283/000 295575.517 304182.076 223.888
163 283/250 295755.671 303986.221 223.811
164 283/500 295910.247 303779.446 223.540
165 283/750 296046.924 303558.949 223.164
166 284/000 296196.117 303400.938 222.912
167 284/250 296332.106 303181.304 222.371
168 284/500 296478.863 302985.710 222.097
Sl
BM No. Easting Northing Level
No.
169 284/750 296631.733 302780.560 221.862
170 285/000 296805.514 302609.466 222.050
171 285/250 297003.217 302436.321 222.486
172 285/500 297194.479 302296.843 223.155
173 285/750 297365.382 302117.638 223.641
174 286/000 297573.673 301966.696 223.534
175 286/250 297747.617 301784.338 223.373
176 286/750 298123.654 301454.888 223.068
177 287/000 298330.524 301310.614 223.490
178 287/250 298507.420 301125.175 224.202
179 287/500 298704.083 300987.419 224.181
180 288/000 299106.886 300637.340 222.955
181 288/250 299279.848 300455.707 223.374
182 288/500 299486.787 300308.884 223.019
183 289/000 299853.649 299969.622 223.988
184 289/250 299670.217 300118.386 223.139
185 289/250 299998.590 299759.888 223.833
186 289/500 300165.388 299579.471 223.102
187 289/750 300332.641 299395.879 223.537
188 290/000 300506.718 299204.772 223.853
189 GPS10A 285451.882 339980.568 228.493
TABLE OF CONTENTS
LIST OF TABLES
Table 4.1: Homogeneous sections for traffic survey ............................................................................ 3
Table 4.2: The traffic surveys conducted for this project includes: .................................................... 4
Table 4.3: Classified Traffic Volume Count Locations ......................................................................... 4
Table 4.4: PCU Adopted ........................................................................................................................... 5
LIST OF FIGURES
Fig 4.1: Vehiclewise variation in AADT along Jind to Haryana/Punjab Border ............................. 6
Fig. 4.2 a: Typical trend of hourly flow of passenger vehicles............................................................ 7
Fig. 4.2 b: Typical trend of hourly flow of goods vehicles .................................................................. 7
Fig. 4.2 c: Typical trend of hourly flow of all vehicles ......................................................................... 8
Fig. 4.3: Average Composition of Traffic ............................................................................................... 8
Fig. 4.4 a: Daily Variation of passenger traffic at Both Locations....................................................... 9
Fig. 4.4 b: Daily Variation of goods traffic at Both Locations ............................................................. 9
Fig. 4.4 c: Daily Variation of total traffic at Both Locations................................................................. 9
Fig. 4.5 a: Turning Moment flow Diagram at Narwana Hisar Intersection ................................. 14
Fig. 4.5 b: Turning Moment flow Diagram at Narwana Kaithal Intersection ............................. 15
Fig. 4.5 c: Turning Moment flow Diagram at Jind .............................................................................. 15
4.1 INTRODUCTION
Traffic surveys have been carried out on the project corridor in order to identify present
and likely future scenarios and to device suitable remedial measures and to evolve
appropriate design method.
The primary objectives of these traffic surveys are to determine the characteristics of
traffic movement on the project corridor, collect historical data on traffic growth, assess
the future traffic growth rate during the design life of the project, determine the travel
pattern as well as type and weight of commodity carried by trucks, determine the
spectrum of axle loads and vehicle damage factors for different types of commercial
vehicles, determine the turning movement pattern of traffic at road intersections and
determine traffic bottlenecks.
4.2 METHODOLOGY
All these traffic surveys have been carriedout in accordance with the guidelines
specified by IRC: 9-1972 and IRC: 102-1988. The methodology adopted for the traffic
study is detailed below.
The project road corridor is divided into traffic homogeneous sections based on
change in traffic flow pattern.
The traffic surveys including classified traffic volume count, Origin Destination
survey and Alxe load survey is carried out for each traffic homogeneous section.
Speed and delay survey is carried out along the complete project road corridor to
identify the bottlenecks and critical locations along the project road.
The turning Moment survey, pedestrian crossing survey and Truck terminal survey
are carried out at major crossings and as per the critical locations identified and
discussed with the client.
Table 4.2: The traffic surveys conducted for this project includes:
One Week Classified Traffic Km 267 (Near Narwana)
Volume count at 2 locations. Km 244 (Near Garhi)
Axle Load Survey at 1 location. Km 236 (Haryana Punjab Border)
Origin and Destination Survey Km 259 (Near Narwana)
at 1 locations.
Speed-Delay Surveys for the Entire Project Corridor
entire project road.
Turning Movement Surveys for Km 297 at Jind
8 hours at 2 intersections. Km 262 Intersections with NH-65 (Narwana)
The vehicle classification system as per IRC: SP- 19:2001 was followed. This study
would help in realistic forecast of traffic volume for lane configuration, pavement
design, to optimize the cost of improvement and realistic approach in assessing
economic and financial viability. Classified manual traffic counts have been recorded in
15 minutes intervals, using Tally marks on a standard format.
The survey data was analyzed to bring out the following traffic characteristics:
Daily variation of traffic volume
Average hourly variation of traffic volume
Average composition of traffic
Average Daily Traffic (ADT)
Annual Average Daily Traffic (AADT)
Directional distribution of traffic
Classified traffic volume count survey are enclosed in Annexure 4.1
Average Daily Traffic (ADT) has been converted into Annual Average Daily Traffic
(AADT) by using seasonal correction factor (SCF). SCF has been derived from fuel sale
data gathered from various petrol pumps along the corridor of the project. Table 4.6
gives the SCF used for various survey points.
Table 4.6: Seasonal Correction Factor at two Locations
Km 244 Km 267
The vehicle wise ADT (Average daily Traffic) for all the locations is summarised in Fig.
4.1. Maximum contribution to the traffic is of cars and two wheelers at both the
location. Heavy vehicles are more or less same in number at both the locations as shown
in the Figures below.
2500
2000
Km 244
1500
Km 267
1000
500
0
2 A x le T ru c k
4 -6 A x le
C a r/J e e p /
A m b u la n c e ,
F ire T e n d e r,
T o n g a /B u llo c
T ra c to r w ith
S td . B u s
O th e rs
R ic k s h a w
T ru c k s
T ra ile r
A u to
Van
C a rt
Type of Vehicles
250
Number of Vehicles
200
150 Km 244
100 Km 267
50
0
12
14
16
18
20
22
10
Time
140
N umber of Vehicles
120
100
80 Km 244
60 Km 267
40
20
0
2
8
12
14
16
18
20
22
10
Time
600
Number of Vehicles
500
400
Km 244
300
Km 267
200
100
0
12
14
16
18
20
22
10
2
8
Time
Daily Variation of Traffic: The daily traffic varies with total traffic being lowest on
Friday and highest on Thursday given in Fig. 4.4. The below figure shows passenger
vehicles prominency during weekends and goods vehicles are more prominent during
Tuesday and Wednesday.
4000
Number of Vehicles
3500
3000
2500
Narwana
2000
Khanauri
1500
1000
500
0
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7
Day
3000
Number of Vehicles
2500
2000
Narwana
1500
Khanauri
1000
500
0
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7
Day
16000
Number of Vehicles
14000
12000
10000
Narwana
8000
Khanauri
6000
4000
2000
0
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7
Day
This is a useful input for capacity analysis and pavement design. The directional split is
almost same i.e. near 50% each and is considered for traffic loading in pavement design.
It is one of the parameter to be considered while finalizing the growth rates for the
proposed Expressways.
India Punjab
Population Population Growth-rate
Year (Thosands) Growth-rate (%) (Millions) (%)
1971 548.16 9.62
1981 685.18 25 13.29 23.89
1991 846.42 23.87 16.96 20.81
2001 1028.74 21.54 21.08 20.1
As for the project 2010-2012 is taken as construction period and growth rate is
substracted by 2% for each vehicle kind for analysis. In this exercise wherever growth
rate is less than 5% it is assumed traffic will grow at 5% as per NHAI Manual for four
laning.
Figures 4.5 (a to c) and the observed traffic in terms of PCU/Hour (Peak Hour) is also
showon in the same figures.
1. Km 297 at Jind
2. Km 262 Intersections with NH-65 at Narwana with Kaithal
3. Km 262 Intersections with NH-65 at Narwana with Hisar
C Hisar
Year Total Veh PCU's
Veh
364
2010 933 1378
2020 1520 2244
365
2030 2476 3655
Peak Hour 6:15 Pm -7:15 Pm
257 107
195
389 132 327
N a rw a n a
J in d
170
242 72 179
A
B
Fig. 4.5 a: Turning Moment flow Diagram at Narwana Hisar Intersection
B Kaithal
Year Total Veh PCU's
Veh
443
2010 1213 1215
2020 1976 1978
702
2030 3218 3222
Peak Hour 6:15 Pm -7:15 Pm
205 238
352
219 14 366
N a rw a n a
J in d
350
399 49 287
C
A
Fig. 4.5 b: Turning Moment flow Diagram at Narwana Kaithal Intersection
C NH-71
864
499
476 334 54
117
B B u s S ta n d
A Narwana
Fig. 4.5 c: Turning Moment flow Diagram at Jind
The O-D survey was carried out on random sample basis and sample size obtained and
the expansion factor for each vehicle type is given in Table 4.16.
To have a complete traffic scenario and to work out the through traffic the consultant
prepared an O-D matrix which is presented in tables below.
Table 4.16: O & D Expansion Factor
Multi
2 Axle 3 Axle
Location Car Bus LCV Axle
Truck Truck
Turck
Km 259 (Near Narwana) 18.4 2.48 19.78 10.04 6.09 7.91
On an average 10% to 20% of each vehicle type has been stopped for O-D survey as the
expansion factor given above suggests.
The number of trips originating from and destined to any zone represents the influence
of that zone in traffic generation/attraction. As our project corridor is very vast, the O-D
Zoning has ben done location specific as shown below.
O-D Zoning Codes for Different Locations.
Narwana
1 Patran/Jakhal
2 Narwana
3 Jind
4 khanauri
5 Tohana
6 West Haryana
7 East Haryana
8 North Haryana
9 South Haryana
10 Punjab,Himachal,J&K
11 Delhi,U.P,Uttranchal
12 M.P,Chatrtisgarh and East India
13 Maharashtra,Goa,Gujarat,South India
speeds are noted and presented in table below. These data are used to suggest suitable
remedial measures so as to improve the over all travel speeds on the project corridor.
Speed and delay survey were carried out by moving car observer method during peak
hours and off peak hours on normal day. Journey speed is one of the parameters that
reveal the level of service (LOS) provided by the facility to the road users. The average
stream speed on the project corridor varies from 51 KMPH to 62 KMPH as shown in the
Table 4.20. The speed represents no significant traffic congestion along the project road
corridor.
Table 4.20: Speed and Delay Characteristics
Chainage Journey
Distanc Speed Delay
Section Time Remarks
Start End e (Km) (KMPH) (Sec)
(Sec)
Delay was caused due
to populated areas
Jind to
307.00 264.00 43.0 2976 52 459 along the stretch and
Narwana
tremendous amount of
local traffic at Jind.
Delay was caused due
to higher percentage of
Narwana goods vehicle plying
to on the road and poor
Haryana/ 264.00 239.00 25.00 1765 51 270 geometry of the road.
Punjab Also revenue collection
Border at Haryana Punjab
Border causes major
delay.
Design Service Volume of a 4 lane (as designed) is considered to be 27000 PCU per day
Table 4.23: Year Traffic reaching Design Service Volume
Homogenous Length Year for 4 Lane
From km to km
Section # (km) Construction
HS 1 Km 239+000 to km 260+000 21.0 2021
Total
Homogen Multi Total
2 Axle 3 Axle Number
ous Car Minibus Bus Axle Traffic
Truck Truck of
Section # Truck in
Vehicle
PCU
HS 1 1,488 685 116 671 872 289 4121 8794
Appropriate growth rates can be applied to this traffic to derive the toll-able traffic for
the subsequent years.
Traffic Homogenous Section and existing km MSA (10 Years) MSA (15 Years)
HS-01 (239.00 to 264.00) 40 65
HS-02 (264.00 to 307.00) 40 70
TABLE OF CONTENTS
LIST OF TABLES
Table 5.1: Categorization of elements for design standards ................................................................ 1
Table 5.2: Design service volumes for 2 lane/4 lane road in plain ..................................................... 2
Table 5.3: Widening Scheme ..................................................................................................................... 3
Table 5.4: Proposed Culverts ................................................................................................................. 11
Table 5.5: Details of New Minor Bridges and Rehabilitation ............................................................ 15
Table 5.6: Recommendations on Cross Drainage Structures of the Project ..................................... 17
Table 5.7: Details of Proposed Pedestrian/Cattle Underpasses ........................................................ 17
Table 5.8: Details of Proposed Grade Separator Intersections (Flyover) .......................................... 18
Table 5.9: Details of Proposed Railway Over Bridge .......................................................................... 18
Table 5.10: List of Existing Major Junctions ......................................................................................... 19
Table 5.11: List of Existing Junctions with Secondary Importance ................................................... 19
Table 5.12: Embankment Raising Sections ........................................................................................... 20
Table 5.13: Details of Service Roads/Slip Roads ................................................................................. 21
Table 5.14: Proposed Jind Bypass .......................................................................................................... 21
Table 5.15: Bus Bays and Bus Stops Locations ..................................................................................... 22
5.1 GENERAL
The existing NH-71 from Km 239.000 to Km 307.000 (from Haryana Punjab Border to
Jind in the State of Haryana) is two-lane National Highway with 7.0m to 7.5m wide
carriageway with paved shoulder and earthen shoulders varying from 1m to 2.5m on
either side. This Project corridor is considered as one package. Project road includes
Proposed Jind Bypass (Km. 0.000 to Km 15.650. The present submission of Final DPR
includes the strengthening and widening of existing two lane roads to Four Lane and
also construction of new Bypasses.
5.3 ALIGNMENT
The alignment of the existing two lanes National Highway has many substandard
curves. The existing alignment is being used with modifications to cater for the design
speed of 100 km per hour. The existing horizontal alignment is being followed for almost
entire road. The entire alignment has been improved to a designed speed of 100 Km per
hour.
Project road includes Proposed Jind Bypass (Km. 0.000 to Km 15.650.)
The bypass option study along with the realignments on both the sides of the road has
been submitted to the NHAI. The detailed topographical survey and other investigations
have been carried out on the finalised alignment.
Structures Flyover
Bridges
Culverts
ROBs
Intersections and Interchanges. At grade intersections
Grade separated intersections
Acceleration and deceleration lanes
Slope protection Side slopes
Slope protection
Drainage system Longitudinal, cross drainage
Safety Measures and Road Furniture Guard rails & safety barriers
Road signage & pavement markings
Footpaths and sidewalks
Wayside Amenities Bus laybys, rest areas, Bus stops, Bus Laybys
and Truck Parking Terminal (as the case may
be)
4-Lane 27,000
In the Draft & Final Feasibility report, options of widening were proposed. Their pros &
cons have been discussed and finalised widening scheme has been made based on the
principle of better geometry and least land acquisition. In the built up areas, concentric
widening with 1.50m median irrespective of the width of right way has been proposed.
Width of Service road is 5.50/3.75 meter with kerb shyness on each side of the proposed
four lane highway wherever applicable.
The widening scheme for the project corridor is given in below Table 5.3.
Table 5.3: Widening Scheme
Existing Design Typical
Sl. Chainage (Km) Chainage (km) Length Proposed
X-Section Location
No. (m) Widening
From To From To Type
Dhabian Gujron
1 239.000 239.400 239.000 239.400 400 LHS Type-2A
Village
Pipaithan /
2 239.400 240.697 239.400 240.800 1400 Concentric Type-1D
Pattawala Village
3 240.697 241.705 240.800 241.700 900 RHS Type-2A
4 241.705 242.509 241.700 242.500 800 Concentric Type-1D Garhi Village
5 242.509 244.890 242.500 244.880 2380 RHS Type-2A
6 244.890 245.590 244.880 245.580 700 RHS Type-2B
7 245.590 247.007 245.580 247.000 1420 RHS Type-2A
8 247.007 247.587 247.000 247.580 580 LHS Type-2B
9 247.587 252.615 247.580 252.600 5020 RHS Type-2A
10 252.615 253.414 252.600 253.400 800 Concentric Type-1D Balarkha Village
11 253.414 258.668 253.400 258.540 5140 LHS Type-2A
12 258.668 259.851 258.540 259.650 1110 Concentric Type-1A Narwana Town
13 259.851 261.988 259.650 261.800 2150 Concentric Type-1C Narwana Town
14 261.988 263.888 261.800 263.700 1900 RHS Type-2B
15 263.888 268.813 263.700 268.700 5000 RHS Type-2A
16 268.813 270.238 268.700 270.150 1450 LHS Type-2B
17 270.238 270.638 270.150 270.550 400 Concentric Type-1D Khersafa Village
18 270.638 274.331 270.550 274.190 3640 LHS Type-2A
Uchana Town /
19 274.331 276.091 274.190 275.950 1760 Concentric Type-1B
Ghaso Bara
20 276.091 278.992 275.950 279.000 3050 LHS Type-2A
21 278.992 280.330 279.000 280.300 1300 Concentric Type-1D Baroda Village
22 280.330 284.548 280.300 284.500 4200 LHS Type-2A
23 284.548 285.242 284.500 285.200 700 Concentric Type-1D Khatkad Village
24 285.242 288.817 285.200 288.800 3600 RHS Type-2A
25 288.817 289.464 288.800 289.450 650 Concentric Type-1D Jhanj Kalan/Barsola
26 289.464 290.312 289.450 290.300 850 Concentric Type-2A
27 290.312 290.812 290.300 290.800 500 Concentric Type-1D Khurkhru Village
28 290.812 292.712 290.800 292.700 1900 LHS Type-2A Hirka Village
292.700/
29 1.700 1700 Concentric Type-3 Jind Bypass
0.000
30 Jind Bypass 1.700 2.400 700 Concentric Type-4 Jind Bypass
31 2.400 7.000 4600 Concentric Type-3 Jind Bypass
32 7.000 7.700 700 Concentric Type-4 Jind Bypass
TYPE- 1A
CONCENTRIC WIDENING FROM EXISTING 4-LANE ROAD TO 4-LANE WITH PAVED SHOULDER AND
BOTH SIDE SERVICE ROAD (URBAN AREA)
TYPE- 1B
CONCENTRIC WIDENING FROM EXISTING ROAD TO 4-LANE WITH PAVED SHOULDER AND
BOTH SIDE SERVICE ROAD (URBAN AREA) : WITH LAND CONSTRAINT
TYPE- 3
NEW CONSTRUCTION 4-LANE ROAD AT BYPASS LOCATION
EXISTING GROUND
BC BC
DBM DBM
WMM WMM
GSB GSB
TYPE-4
MEDIAN WIDTH
CROSS SECTION AT STRUCTURE APPROACH
BUILT UP AREA = 1.5m
WITH SERVICE ROAD BOTH SIDE RURAL AREA = 4.5m
5.9 PAVEMENT
The pavement width on existing two lanes is 7.0m to 7.5m. The additional two lanes are
also proposed to have carriageway width of 7.0m and a kerb shyness of 250mm. The
provision of overlay is based on Benkelman Beam test being made on the existing
pavement. The design period has been taken as 15 years. The pavement has been
designed based on IRC37:2001 and IRC58:2002 in respect of flexible and rigid pavement.
The Flexible Pavement has been proposed on the additional carriageway through out.
5.10 SHOULDERS
It is proposed to have 1.5m paved shoulders and 2 m earthen shoulder at the two ends of
each carriageway. The paved shoulders are proposed to have the same pavement as that
of main carriageway. The earthen shoulders are proposed to be provided with selected
soil.
5.11 CULVERTS
The General condition of culverts in project corridor is not very satisfactory except that
some of these require repairs and are to be widened up to required width of four lanes.
Distresses in form of exposed reinforcement, corroded reinforcement, honey combing etc
in the slab portion and damaged pointing, exposed joints, cracks in PCC substructures/
head walls, parapets and PCC wing walls and chocked HP culvert with damaged head
wall are observed in some of the culverts which require repairs.
Table 5.4 shows the details of proposed culverts.
B. Reconstruction
(a) Slab/Arch culvert to Box culvert
Existing Chainage Design Chainage Span Arrangement
S.No Existing CD No.
(km) (km) (m)
1 - 254.460 254.443 1x2.0
2 - 262.761 263.062 1x2.0
3 - 274.282 274.138 1x2.0
4 - 278.073 278.091 1x2.0
5 279.497 279.506 1x2.0
5.12 BRIDGES
Major Bridges Inventory
Nil
Minor Bridges
There are 5 minor bridges along the total project corridor. Most of these bridges are RCC
Slab bridges. All of the minor bridges are made for irrigation purpose and proposed for
reconstruction.
Table 5.5: Details of New Minor Bridges and Rehabilitation
Repair Scheme for Existing Minor Bridges
Reconstruction of Existing Bridges
Shudkain
RHS of Main
3 Distributary 268.950 268.819 1x12 1 x 10.0
Carriageway
New Construction
Existing Design Span
Sl.
Name of Bridge Chainage Chainage Width (m) Arrangement Side
No.
(Km) (Km) (m)
Dhamtan Sahib
RHS of Main
1 Distributary 245.300 245.187 1x12 1 x 10.0
Carriageway
Bhakra Main Line
RHS of Main
2 Barwala Link ** 247.400 247.304 1x12 1 x 31.5
Carriageway
Shudkain
LHS of Main
4 Distributary 268.950 268.819 1x12 1 x 10.0
Carriageway
Hansi Branch
(Western Yamuna
5 Jind Bypass 3.668 2x12 1 x 58.4 Both sides
Canal)
Minor Bridge 0 5 0 5
5.14 DRAINAGE
Drainage, both surface and subsurface, is essential for efficient and healthy functioning
of a road. Broadly, drainage has two aspects, namely
I. Cross-drainage works to ensure free and smooth movement of surface run-off
through bridges and culverts, so that there is no overtopping of road
II. Road Drainage, which ensures quick and safe disposal of water from road
surface and embankments through roadside drains to their respective outfalls.
The Road is divided into 3 sections i.e., built-up area with service road, built-up area
without service road and rural area. Road drainage is essential in the residential areas,
namely villages and towns. Drains are provided either on left or on right side or on both
sides depending on country slope with respect to road. Different types of drains have
been provided for the different areas, based on physical inspection and profile of the
road.
5.15 UNDERPASSES
Table 5.7 presents the details of proposed underpasses. The existing carriageway under
the underpasses shall be constructed with rigid pavement. The crossing road under the
underpasses shall also be constructed with rigid pavement up to 30 m distance on either
side.
Arrangement (m)
Total Width of
Configuration
Structure (m)
Structural
Locations
Proposed
Proposed
Structure
Crossing
Name of
Existing
Existing
Design
S.no
Steel plate
NR Narwana 4L girder
BG 1x30+1x2
1 Narwana 258.140 258.013 Kurukshetra configu &Precast 2x12 6.525
(Single) 5+1x30
Branch rations PSC
Girder
Steel plate
NR Jind 4L girder
On Jind BG 1x25+1x1
2 Bypass 10.000 Panipat configur &Precast 2x12 6.525
Bypass (Single) 9+1x25
Branch ations PSC
Girder
The minor junctions of the project road are also designed depending upon the type of
road. The junction improvement for these is given in the Drawing Volume.
The lists of junctions with secondary importance are presented in Table 5-11.
Table 5.11: List of Existing Junctions with Secondary Importance
Existing Design
Type of
S.No Chainages Chainages Side Leading to Remarks
Road
(Km) (Km)
1 239.830 239.929 LHS To Village BT-3.5m Y Junction
2 239.860 239.960 LHS To Dhanauri Village CC-3.5m Y Junction
3 240.200 240.240 RHS To Village BT-3.5m T Junction
4 240.385 240.318 RHS To Village BT-3.5m T Junction
5 240.520 240.535 LHS To Dhanauri Village BT-5.0m T Junction
6 241.900 241.894 LHS To Dhanauri Village BT-4.0m T Junction
7 242.250 242.090 RHS Bebltha BT-5.5m T Junction
Ujhana Village (Left) Staggered
8 246.115 246.095 RHS BT-3.0m
Pipelsha Village (Right) Junction
9 246.970 246.958 LHS To Ujhana Village BT-3.5m T Junction
10 247.650 247.528 RHS To Hardar Village BT-3.5m T Junction
11 252.600 252.562 LHS To Belarkha Village BT-3.5m T Junction
12 252.760 252.741 RHS To Hamargarh Village BT-5.0m T Junction
13 252.940 252.928 RHS To Tharodi Village BT-3.5m T Junction
14 253.290 253.270 RHS To Village BT-3.5m T Junction
15 253.400 253.400 LHS Surajakehda BT-5.0m T Junction
16 258.080 257.953 LHS To Golkehra Village BT-3.5m T Junction
17 258.780 258.578 RHS To Tohana Village BT-5.0m Y Junction
Tohana Village (Left)
18 259.450 259.230 RHS BT-5.0m Cross Junction
Govt. College (Right)
19 259.500 259.276 LHS Narwana City BT-3.5m T Junction
20 259.660 259.382 RHS To Narwana Town BT-3.0m T Junction
21 259.800 259.610 LHS To Gurthari Village BT-5.0m T Junction
To Railway
22 259.870 259.680 RHS BT-5.0m T Junction
Station,Narwana
23 261.315 261.132 RHS To School BT-5.0m T Junction
Village (Left)
24 261.390 261.205 RHS BT-5.0m Cross Junction
Railway Station (Right)
Existing Design
Type of
S.No Chainages Chainages Side Leading to Remarks
Road
(Km) (Km)
25 261.600 261.420 LHS Vasanth Vihar BT-16m T Junction
26 261.870 261.685 LHS Indian Oil Patrol Pump BT-3.0m T Junction
27 262.690 262.497 RHS To Uklana Village BT-10.0m T Junction
28 263.100 263.402 LHS Haryana Vidut Nigam BT-3.5m Y Junction
29 263.300 263.605 LHS To Dumerkha Village BT-5.5m Y Junction
30 264.605 264.895 RHS To Geel Village BT-5.0m T Junction
31 265.985 265.455 LHS To Dumerkha Village BT-5.0m T Junction
32 268.600 268.450 RHS To Ghaso Khurd BT-3.0m T Junction
33 270.455 270.360 LHS To Kheri Saffa Village BT-5.5m T Junction
Khark BhuraVillage (Left)
34 271.920 271.846 LHS BT-3.5m Cross Junction
Kheri Mansaniya (Right)
35 273.875 273.740 RHS Uchana Bye-pass BT-6.5m Y Junction
36 274.293 274.150 LHS To Bara Sidu Village BT-5.5m T Junction
Bara SiduVillage (Left)
37 275.400 275.134 LHS BT-5.0m Cross Junction
Uchana City (Right)
38 276.667 276.518 RHS Railway Station,Uchana BT-3.5m T Junction
39 279.490 279.480 LHS To Baroda Village BT-6.0m T Junction
40 279.940 279.915 RHS To Barsola Village BT-3.0m T Junction
41 284.535 284.483 LHS To Kasun Village BT-5.0m T Junction
42 284.890 284.842 RHS To Bhathoda Village BT-3.0m T Junction
43 285.100 285.075 LHS To Chapda Village BT-3.0m T Junction
44 285.175 285.140 RHS To Barsola Village BT-3.0m T Junction
45 289.040 289.020 LHS To Badothi Village BT-3.5m T Junction
46 291.010 290.985 LHS To Village BT-4.5m T Junction
47 292.130 292.117 LHS To Village BT-3.0m T Junction
However the judicious location and sizing of all new (reconstruction and additional)
culverts and raising of embankment will be based on a full hydrological analysis of the
project area, would be carried out at forthcoming stage for Detailed Design.
Slip Road:-
Existing Chainage Design Chainage Total
(km) (km) Length Width
S No Length( Side
(m) (m)
From To From To m)
1 Jind Bypass 1.700 2.400 2x700 1400 Both 2x7.00
2 Jind Bypass 7.000 7.700 2x700 1400 Both 2x7.00
3 Jind Bypass 9.160 9.500 2x340 680 Both 2x7.00
Total Length of Slip Road 3480
5.23 RAILINGS
In built up areas, where service roads have been proposed, railings will be provided on
both edges of footpath cum drain.
TABLE OF CONTENTS
LIST OF TABLE
6.1 GENERAL
Cost estimate is an important component of the feasibility study as it provides vital input
to economic evaluation. The cost estimation have been prepared for the project corridor,
for widening of the existing 2-lane road to 4 lane configuration including strengthening
of the existing pavement, bypasses, reconstruction/ widening of road section at
Urban/Village area, reconstruction/ widening of cross drainage structures,
lined/unlined longitudinal drains, road furniture, bus bays, project facilities etc. Over
and above these construction costs, provision has been made for social and
environmental costs and land acquisition costs for road widening, bypasses, and truck
lay byes, bus bays, toll plazas etc.
6.3 QUANTIFICATION
The main construction items covered in costs estimating are; site clearance, earth work,
base and sub-base works, pavement in carriageway/service road and shoulders, bridges
and culverts, ROBs, underpasses and miscellaneous items such as side drains, road
furniture, retaining walls, intersections, bus bays, truck lay byes, toll plaza etc.
The quantification of the road items that are uniformly accruing is calculated as per
typical cross sections. The quantification of structures is based on actual quantities
worked from the general arrangement drawings (GAD) for each structure for widening
and reconstruction.
S. Rate Amount
Items Unit Quantity
No. (lakhs) (Lakhs)
A ROAD WORKS
EACH INDIVIDUAL CROSS SECTION
1 km 69.328
(TCS1, TCS2, ETC)
TCS : 1A
Concentric Widening km 1.110
167.77 186.22
TCS : 1B
Concentric Widening km 1.760
237.27 417.60
TCS : 1C
Concentric Widening km 2.150
237.27 510.13
TCS : 1D
Concentric Widening km 6.550
237.27 1,554.12
TCS : 2A
Eccentric Widening km 38.515
271.23 10,446.42
TCS : 2B
Eccentric Widening km 4.543
345.85 1,571.20
TCS : 3
New Construction. km 11.824 419.20 4,956.62
TCS : 4
New Construction. km 1.850
1,337.23 2,473.88
TCS : Toll Plaza km 0.600
B BRIDGES AND STRUCTURES
2 MAJOR BRIDGES m -
3 MINOR BRIDGES m 145
11.52 1,670.00
4 ROB/RUB m 154
12.65 1,948.00
5 FLYOVER m 120
11.52 1,382.00
6 UNDERPASSES m 7
10.45 73.00
7 CULVERTS (pipe/slab/box) No. 144
6.87 989.18
Sub total for length km* 0.426
S. Rate Amount
Items Unit Quantity
No. (lakhs) (Lakhs)
OTHER ROAD
C APPURTENENCE/MISCELLENEOUS
ITEMS
8 JUNCTIONS
MAJOR No. 5
11.50 57.50
MAJOR WITH ROUND ABOUT No. 1
45.00 45.00
MINOR No. 47
8.50 399.50
9 SERVICE ROAD
5.5m Width km 5.74
80.32 461.04
3.75m Width km 4.3
60.47 260.02
10 SLIP ROAD km 3.48
116.18 404.31
11 DRAIN (Type-I, Type-II etc)
RCC Cover Drain km 10.04
58.30 585.33
Stone Masonry Cover Drain km 13.1
31.90 417.89
Unlined Drain km 113.464
0.72 81.69
12 BUS BAYS
Laybyes & shelter No. 14
7.91 110.74
13 TOLL PLAZA (Km 287) No. 1
884.80 884.80
15 TRUCK LAY BYES No.
OTHER MISCELLENEOUS ITEMS
(sign boards, rest areas, medical/traffic
16 No.
aid post, HTMS, ambulances, cranes etc 3,228.96
to be listed out separately)
TOTAL AMOUNT In Lakhs 35,115.15
TABLE OF CONTENTS
LIST OF TABLE
SR. Applicable
Act / Rules Purpose Authority
No Yes/ No
Ancient Monuments
Conservation of cultural and
and Archaeological
14 historical remains found in Yes ASI, GoI
Sites and Remains
India
Act1958
Public Liability and Protection form hazardous
15 Yes
Insurance Act 1991 materials and accidents.
Safe transportation, storage Chief
16 Explosive Act 1984 and use of explosive Yes Controller of
material Explosives
Minor Mineral and District
17 For opening new quarry. Yes
concession Rules Collector
Central Motor Vehicle
Motor
Act 1988 and Central To check vehicular air and
18 Yes Vehicle
Motor Vehicle noise pollution.
Department
Rules1989
National Forest To maintain ecological Forest
Policy1952 stability through Department,
19 Yes
National Forest preservation and restoration Gol and
Policy(Revised) 1988 of biological diversity. (GOH)
The mining act has been
Department
20 The Mining Act notified for safe and sound Yes
of mining.
mining activity.
Widening Proposal
The proposed widening has been carried out considering social and environmental
aspects of the project. Concentric widening has been proposed in built-up portion to
save acquisition of road side residential and commercial structures. Likewise eccentric
widening (LHS or RHS) has been proposed in open areas to save tree from the other
side. In other words, only one side tree requires to be felled. Out of total 68 km length
concentric widening is proposed for about 14.30 km mainly in built-up locations, about
20.80 km LHS widening and at remaining length for RHS widening shown in Table 7.2.
Table 7.2: Widening Scheme
Existing Design Typical
Sl. Chainage (Km) Chainage (km) Length Proposed
X-Section Location
No. (m) Widening
From To From To Type
Dhabian Gujron
1 239.000 239.400 239.000 239.400 400 LHS Type-2A
Village
Pipaithan /
2 239.400 240.697 239.400 240.800 1400 Concentric Type-1D
Pattawala Village
3 240.697 241.705 240.800 241.700 900 RHS Type-2A
4 241.705 242.509 241.700 242.500 800 Concentric Type-1D Garhi Village
5 242.509 244.890 242.500 244.880 2380 RHS Type-2A
6 244.890 245.590 244.880 245.580 700 RHS Type-2B
7 245.590 247.007 245.580 247.000 1420 RHS Type-2A
8 247.007 247.587 247.000 247.580 580 LHS Type-2B
9 247.587 252.615 247.580 252.600 5020 RHS Type-2A
10 252.615 253.414 252.600 253.400 800 Concentric Type-1D Balarkha Village
TYPE- 1A
CONCENTRIC WIDENING FROM EXISTING 4-LANE ROAD TO 4-LANE WITH PAVED SHOULDER AND
BOTH SIDE SERVICE ROAD (URBAN AREA)
TYPE- 1B
CONCENTRIC WIDENING FROM EXISTING ROAD TO 4-LANE WITH PAVED SHOULDER AND
BOTH SIDE SERVICE ROAD (URBAN AREA) : WITH LAND CONSTRAINT
TYPE- 3
NEW CONSTRUCTION 4-LANE ROAD AT BYPASS LOCATION
EXISTING GROUND
BC BC
DBM DBM
WMM WMM
GSB GSB
TYPE-4
MEDIAN WIDTH
CROSS SECTION AT STRUCTURE APPROACH
BUILT UP AREA = 1.5m
WITH SERVICE ROAD BOTH SIDE RURAL AREA = 4.5m
Projected Traffic
The daily traffic volume count has been carried out at 2 locations (km 244 and km 267)
considering the traffic intensity and merging and diverging traffic on the project road
corridor. To convert the mixed traffic into common unit, passenger car unit factor is used
as given in IRC 102: 1988. Adopted equivalent passenger car units for the study have
been presented in Table 7.4 A summary of traffic data in terms of Annual Average Daily
Traffic (ADT) and Passenger Car Unit (PCU) has been presented in Table 7.4 to have
better appreciation.
Table 7.4: Classified Traffic Volume Count at two Locations
Traffic Growth: The growth rates estimates were subjected to scenario analysis and the
most likely case was adopted for the purpose of the present study. The traffic growth
estimates scenario is based on the likely growth of the Indian economy and its
relationship to the growth in the state economy. Information presented in Table 7.5
reveals that traffic growth is more than 7% in initial years of project.
Table 7.5 Projected Growth rates of Vehicles in Haryana
Table 7.7: Locations of Water Bodies and their Chainage along the Project Road
Ponds
S.No Hand pump Water Tap Tube wells Canal crossing
Educational
Sl. No Type Hospital Type
Institutes
1 239+800 School 247+000 Hospital
2 241+600 School 258+000 Hospital
3 252+900 School 279+200 Animal Husbandry
4 257+900 School 284+800 Animal Husbandry
5 259+600 ITI Narwana
6 259+950 School
7 260+000 Play Ground
8 260+400 Govt College
9 261+100 School
10 262+200 School
11 270+600 School
Shivania
274+600
12 Public School
Rajeev Gandhi
277+080
13 Govt. College
14 284+510 School
15 289+800 School
Religious & Cultural Properties along the Project Road
Besides above mentioned CPRs, there are about 22 religious structures which are near
the road. Out of 22 religious structures, 15 are temples, 2 are Radhaswami charcha, 3 are
mazars, one is Gurudwara and one other religious structure is also exists. They are
shown in table below:
Table 7.9: Religious and Cultural Properties along the Project Road
(57%), Tarkha (60%) and Ramarai village than District proportion. However, work
participation is lower in Padrath khera, Garhi Jhanjkaathan District average. Literacy in
project affected settlement is generally lower than the literacy of the District as whole.
Table 7.11: Socio-Economic Profile of the Project Affected Settlement
Total % % % % Non-
NAME % Male % SC
Population Female Literacy Worker Workers
Jind (District) 1189827 54% 46% 20% 52% 44% 56%
Total % % % % Non-
NAME % Male % SC
Population Female Literacy Worker Workers
Pindara 3141 55% 45% 26% 54% 32% 68%
dryness of the areas. PM2.5 values were ranging from 35-38. While comparing with the
NAAQ Standard of 60 the monitored PM2.5 values were found to be well within the limit.
Similarly monitored values for SO, NO and CO is also found within the limit.
Table 7.14: AAQ Monitoring Result of Project Road (NH-71)
Radha
Sl. swami
Parameters Unit Prescribed
No. ITI,Narwana, satsang. Protocol
Limits
259/600 292/300
Date of AAQ Monitoring 15.12.2010 15.12.2010
A01 PM10 110 112 100 IS: 5182 (Part
23), 2006
A02 PM2.5 35 38 60 CPCB
Guidelines
A03 SO2 17 17 80 IS: 5182 Part-
II, 2001
A04 NOx 19 25 80 IS: 5182 Part-
VI, 2007
A05 CO 840 1200 2000 IS: 5182 Part-
10
The maximum SO2 and NOx levels monitored were 23.41g/m3 and 35.15g/m3
respectively. While comparing with the NAAQ Standard (80 g/m3), the monitoring
results were found to be well within the limits. The maximum CO concentration
monitored was 1.8g/m3 and most of the CO levels were monitored below the
detectable limit of 2 g/m3. While comparing the NAAQ Standard, the monitored CO
levels were found to be well within the limit. All HC values were found to be below the
detectable limit of 65g/m3.
All Particulate Lead values were found to be below the detectable limit of 0.01g/m3
and within the NAAQ Standard of 1.0 g/m3 (24-hourly).
Noise Levels
Ambient Noise Standards
Ambient noise standards were established as per the CPCB/MOEF Gazette
Notification dated 26 th December 1989. It is based on the A weighted equivalent
noise level, Leq (Table 7.15).
Table 7.15: National Ambient Noise Standards
Day* limits of Night* Limits of Leq
Area Code Category of Zones
Leq (dB(A)) (dB(A))
A Industrial 75 70
B Commercial 65 55
C Residential 55 45
D Silence Zone ** 50 40
Source: GoI, CPCB, 1989
Monitoring locations & results
The noise measurement has been carried out continuously for a period of 24 hours. At
each site 2880 data were recorded, each taken at an interval of 30 seconds of which 1800
data recorded at day time (07:00 AM to 10:00 PM) and 1080 at night time (10:00 PM
07:00 AM).(Table 7.16)
Table 7.16: Equivalent Noise Level Data
Name of Date of Category of Leq dB(A), Leq dB(A),
Sl. No.
Locations Monitoring the Area Day Night
ITI, Narwana
1. 15.10.2010 Educational 65.2 51.4
KM 259+400
Radha Swami
2 15.10.2010 Religious 64.2 54.2
Satsang
The monitored noise levels were ranging from 65.2 dB(A) (Narwana) to 54.2 dB(A)
(Radha Swami Satsang) While comparing the MOEF Ambient Noise Norms for different
categories, Leq noise levels at all locations during day time & during night time], were
found to be exceeding their respective limits. This is because of regular movement of
diverse vehicles.
It may be noted that as the noise survey was carried out at sensitive receptors i.e. School
Zone and Hospital Zone respectively, noise standards is found above the limits at
almost all the location.
Water Quality
Water Quality Standard
The rivers, canal and ponds located along the proposed project road are a source of
water for the local inhabitants, for domestic as well as agricultural uses. An analysis of
their present status and the quality of the water has been done. They have been classified
as per the CPCB classification norms for best use as shown in Table 7.17.
Table 7.17: CPCB Best Use Classification for Surface Water Bodies
Parameters Class A Class B Class C Class D Class E
1. pH 6.58.5 6.58.5 6.0-9.0 6.58.5 6.58.5
2. Dissolved oxygen (as O2),
6 5 4 4 -
mg/l, min
3. BOD, 5 days at 20 C, max 2 3 3 - -
4. Total coliform organism,
50 500 5000 - -
MPN/100 ml, max
5. Free ammonia (as N), mg/l,
- - - 1.2 -
max
6. Electrical conductivity,
- - - - 2250
mhos/cm, max
7. Sodium absorption ratio, max. - - - - 26
8. Boron (as B), mg/l, max. - - - - 2
Class A: Drinking water source without conventional treatment but after
disinfection
Class B: Outdoor bathing (organized)
Class C: Drinking water source after conventional treatment and after
disinfections
Class D: Propagation of Wild life and Fisheries
Class E: Irrigation, Industrial Cooling, and Controlled Waste Disposal
Below E: Not meeting A, B, C, D & E Criteria
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Haryana Punjab Border (Km 239) to Jind (Km 307) Section of NH-71 in the State of Haryana
Fauna
The wild animals which are found in this area include the nilgai (Boselaphus
tragocamelus), antelok (Anelok cervicapra), pig (Sus scrofa), wolf (Canis lupus), jackal
(Conis aureus), fox (Vulpes bengalensis), hare (Lepus ruficandatus), monkey (Macaca
mulatta), wild cat (felis bengalensis) and the porcupine (Hystric leucura) .The game -
birds of the area include the usual varieties found through out the plains. Among them
mention may be made of the peafowl(pavo cristatus), the black partridge (frencolinus
francolinus) and the gray partridge (francalinus pondicervanus).The area is famous for
the number and variety of water fowls which visit it during the winter season. The goose
(Anser anser), comon teal (Anas crecca), red-cristed pochard duck(netta rufina), white-
eyed pochard (aythya rufa) and widgeon (mareca penelope) visit the area only in winter
and inhabit the fringes of rivers, lakes and swamps
Aquatic Life
Snakes are common in the area especially in the rural areas, the chief being the Cobra
(Naja Naja), karait (Bungarus caeruleus), and rat-snake (ptyas mucosus). Indian
crocodile or naka (Crocodilus pulustris), and the ghariyal (gavialis gangeticus) are also
found in the rivers. Fish of almost all the varieties that occur elsewhere in the state are
found in the rivers, lakes and ponds of this area, the common species being rohu (lebeo
rohita), bhakur (Catla catla), nain (Cirrhina mrigala), parhin (Wallagonia attu), krunch
(lebeo calbasu), tengan (Mystus seenghla) etc.
Archaeological and Historical sites:
There is no archeologically protected monument or historical sites along the project
route.
Environmental Impacts
Impact on Topography
During the construction of the proposed project, the topography will change due to
excavation of borrow areas, fills for project road, especially construction of project
related cross drainage structures etc. Provision of construction camp/yard for material
handling will also alter the existing topography. There will be change in topography at
realignments as these realignments have been proposed through agriculture fields. The
change in topography will also be due to the probable induced developments of the
project. With adequate planning, all topographical impacts could be made to enhance the
local aesthetics. Similarly, it will invite benefits in the form of land levelling and tree
plantations in the vicinity of the project road.
Impact on Climate
The widening and strengthening of project is not going to have impact on macro-climate
of the region.
Impact on Air Quality
There will be rise in SPM levels due to the construction activities because the project runs
entirely in plain areas. Since the emission will be fugitive in nature it is difficult to
quantify the SPM standards even expected to be violated, as the background values are
not alarming at many places. Even if it is exceeded it will be for very short period. There
will be some increase in levels of gaseous pollutant also.
The impact on ambient air quality has been assessed using CALINE-3 model. The air
quality predictions have been done for the horizon years 2010, 2020 and 2030. The results
of mathematical modelling show that CO, SO2, NOx, HC, RPM concentration will
remain within the limits of CPCB till the end of project life. SPM levels are well within
limit at present also. But significant contribution of SPM is expected from vehicular
emissions in future.
Impact on Noise Levels
The impact of noise levels from the proposed project on the neighbouring communities
is addressed by carrying out Noise modelling using FHWA model developed by Federal
Highway Administration (FHWA). It has been concluded after mathematical modelling
that both day time and night time equivalent noise levels are within the permissible
limits right from start of project life.
Noise sensitive receptors have been identified along the project road. The noise sensitive
receptors include school, hospitals, colleges, etc. The predicted levels indicate that the
noise levels in future years will not exceed permissible limits right from start of project
life. Hence there is no need to protect these noise sensitive receptors.
Impact on Water Resources and Quality
The construction and operation of the proposed project roads will not have any major
impacts on the surface water and the ground water quality in the area. Contamination to
water bodies may results due to spilling of construction materials, oil, grease, fuel and
paint in the equipment yards and asphalt plants. This will be more prominent in case of
locations where the project road crosses water streams, major canals distributaries, etc.
Mitigatory measures have been planned to avoid contamination of these water bodies.
Impact on Ecological Resources
There is no wildlife sanctuary in the close vicinity of the project road. The study area
passes primarily through agricultural land in plain areas. There will be temporary
impact on terrestrial ecology, as trees will be cut. But after construction no impact is
anticipated as compensatory afforestation is planned. There are no endangered species
or rare species of flora and fauna in the project area.
There is no major loss of vegetation hence adverse impact in terms of availability of
nesting sites for the bird doesnt arise. Furthermore, there is no sensitive ecological area
near the existing project roads, so the impact will be insignificant. Brief potential impact
is presented in matrix below.
Construction of bridges across water streams may result in siltation of water body,
which can affect aquatic fauna. Proper mitigatory measures have been recommended in
EMP.
Impact on Human Use Values
Impact on human use values include common property resources such as temples,
mosques, wells, hand pumps, tube well, etc. Impact on these has been minimized
through proper planning of the alignments. The environmental impacts have been
summarized and are given in Table- below:
Mitigation Avoidance and Enhancement Measures
The mitigation measures have been planned for identified adverse environmental
impacts. These mitigation measures have been identified as management plan during
planning, construction and operation phase.
Design Phase
Impacts during design phase is limited to removal of trees, acquisition of land and
structures, relocation of water ways, identification and management of borrow pits as
mentioned in Table 7.21
Table 7.21: Impacts during design phase
Impacts Mitigation Measures
Land Acquisition Alignment design to minimize the land acquisition
Major Bypasses and detours to be considered
Displacement
Removal of Trees Alignment design to reduce the number, widening on the side of
the road where less tree require be cut.
Compensatory plantation to be planned.
Impact on public Alignment design to consider. In case of removal alternate
utilities e.g. arrangement to be done before.
community wells
etc.
Impact on Cultural Alignment design to consider. Public consultation may be needed if
Sites impact cannot be avoided
Relocation of Hydrology to be considered. Public consultation will be needed
waterways
Access Restriction Required alternatives, underpasses, proper signposts for people
should be included in design
Congestion in Service road to be provided
Settlement Areas
Borrow pits Locations to be selected considering minimum loss of productive
land and redevelopment
Environmental Environmental qualifications specification should be included in
Specifications for pre-qualification packages for the contractors
Contractors
Construction Phase
Environmental management during construction phase is more crucial because major
impacts during construction like earthworks, movement of heavy machineries etc cause
lot of disturbance and management becomes essential at this stage. The construction
workers camp will be located at least 500m away from habitations. The construction
yard, hot mix plants, crushers etc. will be located at 500m away from habitations and in
downwind directions. The minimum distance of these will be kept 3.0 km from reserve
forest areas. Adequate cross drainage structures have been planned to maintain proper
cross drainage. In order to compensate negative impacts on flora due to cutting of trees
the project plans compensatory plantation in the ratio of 1:3 i.e. for every to be tree cut
three trees will be planted. The acquisition of forest area will be minimal and will be
compensated through compensatory afforestation. The noise barriers have been planned
closed to educational institute so that post project noise levels are within the specified
limits. The project will take an opportunity to provide environmental enhancement
measures to improve aesthetics in the project area. The planned environmental
enhancement measures include ponds enhancement, plantation in median and in
available clear space in ROW, seating arrangements around trees. The pond
enhancement measures will include such as stepped access, washing plat form, seating
arrangement etc. Some of ditches will be filled up due to embankment construction in
the ROW. In order to avoid contamination of water bodies during construction
sedimentation chambers, oils and grease separators, oil interceptors at storage areas and
at construction yard have been planned. The bill of quantities for mitigation and
enhancement measures has been given in respective EMPs of construction packages.
Table 7.22 below summarizes impacts and its management.
Table 7.22 Environmental Management Plan during construction period
Twice the number of trees cut will be planted. Besides there will be
more plantation on roadsides where there are no trees at present.
Total length of the road including bypasses will be about 321 km.
Considering 300 trees per kilometre altogether 96300 will be
required to be planted. To compensate the felling of trees and
improve environmental quality trees will be planted in nearby areas
beyond the project site. The species will be selected depending on
site, plantation design and in consultation with local community in
the plantation programme and forest department. Tree plantation
will continue as part of construction process and will be included in
Environmental Management Plan.
Operation Phase
Environmental issues change during operation phase and its mitigation plan also has
related with vehicular movement, road safety, management of ecological issues.
Environmental aspects are thus more or less related to vehicular emission. The
mitigation measures for different environmental aspects are discussed in Table 7.23
below.
enhancement of 36 water
bodies
Safety signs and provisions - Provided in civil works
at different locations contract
Cost to be included in
engineering
All underpasses Included in civil works
Dust suppression by Incidental to work with in
watering contractor
Environmental measures at Incidental to work with in
Workers camps contractor
Vegetation turf at slopes Civil works
Operation Phase
Based on the environmental assessment and surveys conducted for the project,
associated potential adverse environmental impacts can be mitigated to an acceptable
level by adequate implementation of the measures as stated in the EIA Report. Adequate
provisions have been made to cover the environmental mitigation and monitoring
requirements (including afforestation cost) which is about Rs. 4.25 crores.
TABLE OF CONTENTS
LIST OF TABLES
8.1 GENERAL
Any infrastructure project, which is in terms of improving the existing facility, is
subjected to economic and financial analysis to establish its viability and ensure that the
investment proposed would yield appropriate return either to the national economy of
the private/ public investor. The economic appraisal has been carried out for the each
National Highway sections separately, and also for the entire project.
different construction packages. Each of the packages has been dealt with for evaluation
purpose.
Although each of the packages is having uniform traffic in broader terms, major built-up
areas en-route have higher traffic volume specially, in terms of passenger vehicles and
slow moving traffic within the urban influence zones. Thus project road has been
divided into two homogenous sections.
A construction period of 3 years (2011, 12 and 13) has been envisaged with a phasing of
30%, 30% and 40% respectively.
Serial
Maintenance Standard Remarks
Nr.
Repair of Pavement Edges For existing road during
1 Repair of Surface distress and potholes construction
Routine Maintenance
Surface renewal, 40mm AC, once in 5 year For existing road Without
Repair of Pavement Edges project
2
Repair of Surface distress and potholes
Routine Maintenance
Surface renewal, 40mm AC at IRI> 4.5 For improved road, 4-lane
m/km divided carriageway
3 Repair of Pavement Edges
Repair of Surface distress and potholes
Routine Maintenance
Based on the market survey and inquiries from the various organisations in Punjab, the
maintenance labour cost/hr and wages/hour has been evaluated. The crew salary for
LCV (Driver and Conductor), Heavy Trucks (Driver and cleaner) and Passenger Bus
(Driver and Conductor) are found to be around `10000/-, `12000/- and `17000/- per
month respectively based on 300 hours of working per month. Keeping this in view the
cost `/hr. has been calculated for the different categories of crew. Rates have been
compared with that adopted for the recent studies before arriving at reasonable values.
Adopted values are given below:
Maintenance Labour and Crew Costs (Cost in ` per hour)
Two Small Medium Mini Light Medium Heavy Artic
Category Bus
Wheeler Car Car Bus Truck Truck Truck Truck
Maintane-
nce 12.00 13.50 15.00 17.40 19.30 17.40 19.30 24.10 24.10
Labour
Crew 0.00 0.00 0.00 37.50 50.00 26.67 33.33 40.00 40.00
Wage
Passenger Time-delay Costs
Value of travel time saving of passengers was first quantified in Road User cost Study
(RUCS) carried out in India in 1982 on the basis of wage rate approach. The results so
obtained were updated to 1990 values using wage index and subsequently validated by
limited primary survey carried out on various secondary and trunk routes in the Study
for Updating Road User Cost Data, 1992. Passenger time-delay cost for the project road
has been derived from the same corresponding to leisure trips @ 25% of the value of non-
leisure trips (recommended by RUCS, 1992) as given below:
Travel Time Value of Passengers (`/hour)
(Based on average wage/income for both work and non-work trips)
Travel time Value WPI Ratio Eq. Work- Eq. Non-work
Travel RUCS- RUCS- 1990/ 2002/ Time Value Time Value in
1980 1990 1980 1990 in 2007 2007
Car/ Taxi 10.0 24.3 1.96 2.30 61.22 15.33
Bus, Other routes 4.5 9.3 1.96 2.30 23.44 5.80
Bus, Trunk routes 7.0 19.7 1.96 2.30
Overhead
Annual overhead cost per vehicle is derived by the consultants as per the
recommendations of the Study for Updating Road User Cost Data, 1992 as given
below: (Cost in `.)
Two Small Medium Mini Light Medium Heavy Artic
Bus
Wheeler Car Car Bus Truck Truck Truck Truck
0 0 0 48195 107940 48195 102375 112665 112665
Interest
An economic interest rate of 11% has been adopted based on opportunity cost of capital.
Fuel and Lubricants
Market price of petrol, diesel and lubricants are found to be a little varying within the
project road corridor on account of varying cost of transportation. For the analysis
purpose, market price at Punjab has been considered for arriving at economic cost of fuel
and lubricants. Applicable taxes and duties on these items are:
Taxes and Duties
Item Rate
Excise Other Levy Sales Tax
Petrol `/litre 16% ` 7/litre 16.5%
Diesel `/litre 16% ` 1/litre 16.5%
Lubricants `/litre 16% Nil 16.5%
Based on above taxes and duties economic costs have been derived as:
Economic cost Without product price
Market Price `/litre
adjustment `/litre
Petrol 49.25 33.24
Diesel 34.25 23.11
Engine Oil 125 84.37
Lubricants 135 91.12
Grease 160 108.00
Cargo Time-delay Costs
Average value of commodity is based on the Study for Updating Road User Cost Data,
1992. A value of ` 20000/- per ton was worked out from a detailed survey carried out in
1990. Equivalent cost of commodity in 2007 is determined using the WPI ratio (2.30 over
1990) as ` 46,000/-. However, commodity survey on the project road corridor does not
justify such high value. For the present analysis, therefore, 50% cost is considered, i.e. `
23000 per tonne. Average payload for each category of freight vehicles is based on axle
load survey. Time-delay cost is estimated with an economic interest rate of 11% and
economic conversion factor of 0.85.
Mediu
Two Small Medium Mini Light Heavy Artic
Particulars Bus m
Wheeler Car Car Bus Truck Truck Truck
Truck
Km Driven 10000 33300 33300 40000 80000 40000 60000 60000 60000
Life, yr 12 16 16 12 12 12 12 12 12
Working h 400 925 925 1025 2010 1025 2155 2535 2535
Passenger 2 20 50
FINANCIAL ANALYSIS
8.5 INTRODUCTION
Financial viability analysis examines the possibilities of recovering the costs of
investment in improving the traffic facility keeping in view the requirements of the
future travel demand through the imposition of tolls for vehicles using the improved
facility. The basic inputs required for this analysis, in financial terms, are investment
costs (including O&M costs) and their phasing.
It is also assumed that the project concession period (25 years) includes the periods for
financial closure (6 months) and also construction (30 months). The project is expected to
commence on 2010 for this analysis. The project road, thus, is expected to open to traffic
on 1st April 2013 and is likely to have toll revenue-earnings.
8.8 PACKAGING
Based on the traffic flow pattern and road network in the project influence area, the
project road has been kept as single package/ homogeneous sections, as given below
8.9 TRAFFIC
Traffic survey has been carried out at one location at proposed toll plaza location to
finalise the traffic to be considered for revenue calculations. Traffic considered for the
calculation of revenue at proposed toll plaza location is presented below.
Traffic at Toll Plaza Locations
Mini- 2A 3 Axle 4-6 Axle >=7
Length Car Bus LCV
Bus Truck Truck Truck Axle
68 Km 2651 47 225 596 820 610 187 0
With this traffic (Tolled and Non-tolled) the current PCU on the project road is 12258
PCUs. Table below presents the projection of the traffic (total PCUs) in coming years.
As per traffic projection (considering 60K PCU as the capacity of the 4 Lane
configuration) the section is not reaching the capacity within 30 years.
From the above table it can be interpreted that the project is viable for the concession
period of 25 Years with 40% VGF OR for a concession period of 30 years with 35% VGF.
However the project is not viable in 20 years concession period with maximum possible
40% grant.
TABLE OF CONTENTS
The primary objective of Value Engineering is to analyze the engineering planning and
design with a view to identifying unnecessary costs to ensure that the proposed
solutions are technically and financially balanced.
The Value Engineer participates in the initial choice of technical solutions, to identify
contract provisions that may add costs to the project. Also, an analysis has been done to
find out technical solutions that are less costly but do not compromise the performance,
safety, appearance or maintenance of the finished road. An early analysis with
discussion during feasibility and preliminary engineering stage on the project
parameters was undertaken in house involving the various design experts who prepared
the design.
The Value Engineer worked first during the initial stage of feasibility and preliminary
engineering, during which the choice of the general lines of actions, construction
procedures and technical solutions was determined. Assessment of equivalent less
expensive solutions for the execution of the project was made. For example, at this stage
the choices for the type of bridge superstructure between normal reinforced concrete and
pre-stressed concrete structures or the choice for the pavement type being rigid or
flexible and other similar technically comparable alternatives was made. Alternate
alignments, design speed, widening side were examined in detail and changed to give
the most economical design.
The Value Engineer studied the solutions proposed for:
Type of cross-drainage structures
Type of Bridges/other structures
Type of Pavement
Vertical and horizontal alignments
Road construction materials for earthworks, concrete and pavement
Sequence of construction operations
Road safety
Road furniture, etc.
The involvement of the Value Engineer during the detailed engineering was to make the
fine tuning of the various solutions for the project components proposed in the
Preliminary Engineering, to further develop and include in the final design. The analysis
involved the study of the plans and the specifications and changes involving the
substitution of materials, modification of the design, reduction of quantities or
procedures other than those set forth and required by the standard contract documents
were made.
Maximum efforts were made to make the best use of the local resources, options and
procedures for eventually proposing innovations dictated by the local conditions.
Changes in plans or in specifications were proposed after a detailed analysis of the costs
involved in each of the technically equivalent solutions.
The main working tools for the Value Engineer were first his deep understanding of the
possible technical solutions for each project component, for which he held in depth
discussion with the experts to get details of possible alternatives, and second the costs to
be prepared by the Quantity Surveyor. The Quantity Surveyor made detailed cost
calculations for the various types of project elements and alternatives. A combination of
those two elements provided the basis for proposing changes and for evaluating the
adequacy of the final detailed design and specifications.
LIST OF ANNEXURES
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border
to Jind Section of NH-71 in the State of Haryana
Annexure 3.1
Road Inventory Data
Annexure 3.1
ROAD INVENTORY (NH-71)
THE Louis Berger Group, Inc.
Embankment/cut Carriageway
Earthen Shoulder
Median width(m)
Existing Road height(m)
Left Right
Terrain (P/R)
Land Use
Left Right
& con
Condition
Condition
Width (m)
Width (m)
From To
Condition
Condition
Width(m)
Width(m)
Type
Type
Left Right
km km Left Right
239+000 239+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.7 Poor 0.7 Poor -
239+500 240+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.7 Poor 0.7 Poor -
240+000 240+500 P BU BU 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.7 Poor 0.7 Fair -
240+500 241+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.7 Poor 0.7 Fair -
241+000 241+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.7 Poor 0.7 Poor -
241+500 242+000 P BU BU 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.7 Poor 0.7 Poor -
242+000 242+500 P Agri Agri 1.0-2.0 1.0-2.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.7 Poor 0.7 Poor -
242+500 243+000 P Agri Agri 1.0-2.0 1.0-2.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.7 Poor 0.7 Poor -
243+000 243+500 P Agri Agri 1.0-3.0 1.0-3.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.7 Poor 0.7 Fair -
243+500 244+000 P Agri Agri 1.0-3.0 1.0-3.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.7 Poor 0.7 Fair -
244+000 244+500 P Agri Agri 3.5 3.5 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Fair 1 Fair -
244+500 245+000 P Agri Agri 3.5 3.5 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Fair 1 Fair -
245+000 245+500 P Agri Agri 3.5 3.5 Bridge (1.5+3.5) to 4.0 Good CW+PS(3.5+1.5) to 4.0 Good - - - Fair -
245+500 246+000 P Agri Agri 3.5 3.5 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Fair 1 Fair -
246+000 246+500 P Agri Agri 3 3 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Fair 1 Fair -
246+500 247+000 P Agri Agri 3 3 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.5 Fair 0.5 Fair -
247+000 247+500 P Agri Agri 2.0-2.5 2.0-2.5 Bridge 3.5 Poor Bridge 3.5 Poor - Poor - Poor -
247+500 248+000 P Agri Agri 2.0-2.5 2.0-2.5 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
248+000 248+500 P Agri Agri 3 3 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.5 0.5 0.5 Poor -
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 1
Annexure 3.1
ROAD INVENTORY (NH-71)
THE Louis Berger Group, Inc.
Embankment/cut Carriageway
Earthen Shoulder
Median width(m)
Existing Road height(m)
Left Right
Terrain (P/R)
Land Use
Left Right
& con
Condition
Condition
Width (m)
Width (m)
From To
Condition
Condition
Width(m)
Width(m)
Type
Type
Left Right
km km Left Right
248+500 249+000 P Agri Agri 3 3 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.5 0.5 0.5 Poor -
249+000 249+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
249+500 250+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
250+000 250+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
250+500 251+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
251+000 251+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
251+500 252+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
252+000 252+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
252+500 253+000 P BU Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
253+000 253+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
253+500 254+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
254+000 254+500 P Agri Agri 0.5-1.0 0.5-1.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
254+500 255+000 P Agri Agri 0.5-1.0 0.5-1.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
255+000 255+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.7 0.7 0.7 Poor -
255+500 256+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.7 0.7 0.7 Poor -
256+000 256+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.7 0.7 0.7 Poor -
256+500 257+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.7 0.7 0.7 Poor -
257+000 257+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.7 0.7 0.7 Poor -
257+500 258+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.7 0.7 0.7 Poor -
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 2
Annexure 3.1
ROAD INVENTORY (NH-71)
THE Louis Berger Group, Inc.
Embankment/cut Carriageway
Earthen Shoulder
Median width(m)
Existing Road height(m)
Left Right
Terrain (P/R)
Land Use
Left Right
& con
Condition
Condition
Width (m)
Width (m)
From To
Condition
Condition
Width(m)
Width(m)
Type
Type
Left Right
km km Left Right
258+000 258+500 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair - - - Poor -
258+500 259+000 P BU Bu GL-1.0 GL-1.0 PS+CW 1.5+7.0 Poor CW+PS 7.0+1.5 Poor 1 Poor 1 Poor 1.25
259+000 259+500 P BU Bu GL-0.5 GL-0.5 PS+CW 1.5+7.0 Poor CW+PS 7.0+1.5 Poor 1 Poor 1 Poor 1.25
259+500 260+000 P BU Bu GL-0.5 GL-0.5 PS+CW 1.5+7.0 Poor CW+PS 7.0+1.5 Poor 1 Poor 1 Poor 1.25
260+000 260+500 P BU Bu GL GL PS+CW 1.5+7.0 Poor CW+PS 7.0+1.5 Poor 1 Poor 1 Poor 1.25
260+500 261+000 P BU Bu GL GL PS+CW 1.5+7.0 Poor CW+PS 7.0+1.5 Poor 1 Poor 1 Poor 1.25
261+000 261+500 P BU Bu GL GL PS+CW 1.5+7.0 Poor CW+PS 7.0+1.5 Poor 1 Poor 1 Poor 1.25
261+500 262+000 P BU Bu GL GL PS+CW 1.5+7.0 Poor CW+PS 7.0+1.5 Poor 1 Poor 1 Poor 1.25
262+000 262+500 P BU Bu 1 1 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 1 Poor 1 Poor -
263+000 263+500 P BU Bu 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.6 Poor 0.5 Poor -
263+500 264+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.6 Poor 0.5 Poor -
264+000 264+500 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.6 Poor 0.5 Poor -
264+500 265+000 P Agri Agri 3 3 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.6 Poor 0.5 Poor -
265+000 265+500 P Agri Agri 3 3 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.6 Poor 0.5 Poor -
265+500 266+000 P Agri Agri 3 3 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 0.6 Poor 0.5 Poor -
266+000 266+500 P Agri Agri 1.0-2.0 1.0-2.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.6 Poor 0.5 Poor -
266+500 267+000 P Agri Agri 1.0-2.0 1.0-2.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.6 Poor 0.5 Poor -
267+000 267+500 P Agri Agri GL-0.5 GL-0.5 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 3
Annexure 3.1
ROAD INVENTORY (NH-71)
THE Louis Berger Group, Inc.
Embankment/cut Carriageway
Earthen Shoulder
Median width(m)
Existing Road height(m)
Left Right
Terrain (P/R)
Land Use
Left Right
& con
Condition
Condition
Width (m)
Width (m)
From To
Condition
Condition
Width(m)
Width(m)
Type
Type
Left Right
km km Left Right
267+500 268+000 P Agri Agri GL-0.5 GL-0.5 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 1 Poor 1 Poor -
268+000 268+500 P Agri Agri GL-0.5 GL-0.5 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
268+500 269+000 P Agri Agri GL-3.0 GL-3.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 1 Poor 1 Poor -
269+000 269+500 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 1 Poor 1 Poor -
269+500 270+000 P Agri Agri GL-0.5 GL-0.5 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
270+000 270+500 P Bu BU 1.0-1.5 1.0-1.5 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.6 Poor 0.6 Poor -
270+500 271+000 P Agri Agri 0.5-1.0 0.5-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.6 Poor 0.6 Poor -
271+000 271+500 P Agri Agri GL-0.2 GL-0.2 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 1 Poor 1 Poor -
271+500 272+000 P Agri Agri 1 1 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
272+000 272+500 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
272+500 273+000 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 1 Poor 1 Poor -
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 4
Annexure 3.1
ROAD INVENTORY (NH-71)
THE Louis Berger Group, Inc.
Embankment/cut Carriageway
Earthen Shoulder
Median width(m)
Existing Road height(m)
Left Right
Terrain (P/R)
Land Use
Left Right
& con
Condition
Condition
Width (m)
Width (m)
From To
Condition
Condition
Width(m)
Width(m)
Type
Type
Left Right
km km Left Right
273+000 273+500 P Bu BU GL-1.0 GL-1.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Poor 1 Poor 1 Poor -
273+500 274+000 P Agri Agri 2.0-3.0 2.0-3.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 Poor 0.5 Poor -
274+000 274+500 P Bu Bu GL-1.0 GL-1.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
274+500 275+000 P Bu Bu GL-1.0 GL-1.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
276+000 276+500 P Agri Agri GL GL PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
276+500 277+000 P Agri Agri GL GL PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
277+000 277+500 P Bu Agri 1.0 - 2.0 1.0 - 2.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
277+500 278+000 P Agri Agri 1.0 - 2.0 1.0 - 2.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
278+000 278+500 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
278+500 279+000 P Agri Bu GL-1.0 GL-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
279+000 279+500 P Bu Bu GL-1.5 GL-1.5 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair - - - Poor -
279+500 280+000 P Bu Bu GL-1.5 GL-1.5 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair - - - Poor -
280+000 280+500 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
280+500 281+000 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
281+000 281+500 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 5
Annexure 3.1
ROAD INVENTORY (NH-71)
THE Louis Berger Group, Inc.
Embankment/cut Carriageway
Earthen Shoulder
Median width(m)
Existing Road height(m)
Left Right
Terrain (P/R)
Land Use
Left Right
& con
Condition
Condition
Width (m)
Width (m)
From To
Condition
Condition
Width(m)
Width(m)
Type
Type
Left Right
km km Left Right
281+500 282+000 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
282+000 282+500 P Agri Agri GL GL PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
282+500 283+000 P Agri Agri GL GL PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
283+000 283+500 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 0.5 0.5 0.5 Poor -
283+500 284+000 P Agri Agri GL-1.0 GL-1.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 0.5 0.5 0.5 Poor -
284+000 284+500 P Agri Agri 0.5 0.5 PS+CW 1.5+3.5 Poor CW+PS 3.5+1.5 Poor 1 Poor 1 Poor -
284+500 285+000 P Bu Bu 0.5 0.5 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Poor 1 Poor -
285+000 285+500 P Agri Agri GL-1.5 GL-1.5 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Poor 1 Poor -
285+500 286+000 P Agri Agri GL-1.5 GL-1.5 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Poor 1 Poor -
286+000 286+500 P Agri Agri GL-1.5 GL-1.5 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
286+500 287+000 P Agri Agri GL-1.5 GL-1.5 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
287+000 287+500 P Agri Agri 0.5 0.5 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Poor 1 Poor -
287+500 288+000 P Agri Agri 0.5 0.5 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Poor 1 Poor -
288+000 288+500 P Agri Agri 0.5 0.5 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
288+500 289+000 P Agri Agri 0.5 0.5 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Poor 1 Poor -
289+000 289+500 P Bu Bu 0.5 -1.0 0.5 -1.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Fair 1 Fair -
289+500 290+000 P Bu Bu 0.5 -1.0 0.5 -1.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Fair 1 Fair -
290+000 290+500 P Agri Agri 0.5 -1.0 0.5 -1.0 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
290+500 291+000 P Bu Bu 0.5 -1.0 0.5 -1.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Poor 1 Poor -
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 6
Annexure 3.1
ROAD INVENTORY (NH-71)
THE Louis Berger Group, Inc.
Embankment/cut Carriageway
Earthen Shoulder
Median width(m)
Existing Road height(m)
Left Right
Terrain (P/R)
Land Use
Left Right
& con
Condition
Condition
Width (m)
Width (m)
From To
Condition
Condition
Width(m)
Width(m)
Type
Type
Left Right
km km Left Right
291+000 291+500 P Agri Agri 0.5 -1.0 0.5 -1.0 PS+CW 1.5+3.5 Good CW+PS 3.5+1.5 Good 1 Poor 1 Poor -
291+500 292+000 P Agri Agri 0.5 0.5 PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
292+000 292+500 P Agri Agri GL GL PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
292+500 293+000 P Agri Agri GL GL PS+CW 1.5+3.5 Fair CW+PS 3.5+1.5 Fair 1 Poor 1 Poor -
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 7
Annexure 3.1
ROAD INVENTORY (NH-71)
THE Louis Berger Group, Inc.
Embankment/cut Carriageway
Earthen Shoulder
Median width(m)
Existing Road height(m)
Left Right
Terrain (P/R)
Land Use
Left Right
& con
Condition
Condition
Width (m)
Width (m)
From To
Condition
Condition
Width(m)
Width(m)
Type
Type
Left Right
km km Left Right
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 8
Annexure 3.2
Pavement Condition Survey
Annexure 3.2
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 1
Annexure 3.2
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 2
Annexure 3.2
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 3
Annexure 3.2
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 4
Annexure 3.2
Detailed Project Report for Rehabilitation and Upgrading to 4-lanes Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 5
Annexure 3.3
Details of Existing ROW
THE Louis Berger Group, Inc. Annexure-3.3
256+250 259+850 43
259+850 260+000 35
7 Narwana
260+000 261+300 33
261+300 262+300 30
262+3000 262+400 30
262+400 262+600 30
8 262+600 264+000 30 Dumar Khan Kalan
264+000 264+500 31.73
264+500 266+000 30
9 266+000 267+050 31.73 Dumar Khan Khurd
10 267+050 268+900 30 Ghaso Khurd
268+900 269+300 30
269+300 269+400 30
11 Safa Kheri
269+400 271+000 31
271+000 271+600 30
271+600 272+000 30
12 Kharakbura
272+000 272+900 31
13 272+900 275+000 31 Palwa
275+000 275+500 35
14 Uchana
275+500 277+700 29
15 277+700 281+950 30 Barodha
281+950 284+850 30
16 284+850 284+900 23 Khatkar
284+900 287+280 30
287+280 288+600 31
17 Jhanjh Kalan
288+600 289+500 28
289+500 289+900 28
18 Jhanjh Khurd
289+900 290+900 30
19 290+900 291+352 31.73 Kehar khera
20 291+325 292+700 32.69 Ahirka
Details of Existing Right of Way (ROW) along Jind Bypass
Proposed Bypass Chainages Total ROW(in
S.No. Remarks
From To m)
1 0+000 2+048 46 Ahirka
2 2+048 3+600 25 Amarheri
3 3+600 4+350 25 Jind
4 4+350 6+380 25 Haibat Pur
5 6+380 8+211 25 Nirjan
6 8+211 9+507 25 Pindari
Detailed Project Report for Rehabilitation and Upgrading to 4 Lane Configration of NH 71 from Haryana Punjab Border to Jind in the State of Haryana
Annexure 3.4
List of Existing Structures
Annexure 3.4
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 1
Annexure 3.4
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 2
Annexure 3.4
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 3
Annexure 3.4
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 4
Annexure 3.5
Road Junction
Annexure 3.5
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71 in the State of Haryana 1
Annexure 3.5
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71 in the State of Haryana 2
Annexure 3.6
BBD Survey
Annexure 3.6
Mean deflection
Deflection (mm)
Standard Dev
Temp
mm/km X
Temparature
Pavement Seasonal
Std. temp.
Corrected Corrected Characterisitic
Chainage Up/Dn Temperature FMC% Correction
Initial Intermediate Final Deflection Def, mm Deflection (mm)
(km) (C) Factor
(mm)
239.000 9.54 9.37 9.35 0.38 39 35.00 -0.04 0.340 10.900 1.210 0.41 0.42 0.12 0.65
239.200 9.02 8.89 8.87 0.29 28 35.00 0.07 0.360 0.44 0.68
239.400 8.49 8.4 8.39 0.20 39 35.00 -0.04 0.160 0.19 0.43
239.600 9.11 8.97 8.96 0.31 32 35.00 0.03 0.340 0.41 0.65
239.800 9.73 9.53 9.52 0.42 39 35.00 -0.04 0.380 0.46 0.70
240.000 8.43 8.26 8.25 0.36 39 35.00 -0.04 0.320 0.39 0.63
239.100 9.28 9.13 9.11 0.34 29 35.00 0.06 0.395 0.48 0.72
239.300 8.75 8.64 8.63 0.25 36 35.00 -0.01 0.235 0.28 0.52
239.500 9.12 8.94 8.91 0.59 39 35.00 -0.04 0.555 0.67 0.91
239.700 9.42 9.25 9.24 0.36 39 35.00 -0.04 0.325 0.39 0.63
239.900 9.37 9.15 9.15 0.44 39 35.00 -0.04 0.400 0.48 0.72
Dc 0.66
241.000 9.10 9.04 9.01 0.35 29 35.00 0.06 0.415 8.000 1.320 0.55 0.43 0.15 0.85
241.200 8.96 8.88 8.86 0.19 28 35.00 0.07 0.260 0.34 0.65
241.400 8.81 8.72 8.71 0.20 29 35.00 0.06 0.260 0.34 0.65
241.600 9.23 9.03 9.02 0.42 32 35.00 0.03 0.450 0.59 0.90
241.800 9.42 9.34 9.33 0.18 29 35.00 0.06 0.240 0.32 0.62
242.000 8.67 8.56 8.56 0.22 29 35.00 0.06 0.280 0.37 0.67
241.100 9.03 8.96 8.94 0.33 29 35.00 0.06 0.391 0.52 0.82
241.300 8.88 8.80 8.79 0.20 35 35.00 0 0.195 0.26 0.56
241.500 9.62 9.48 9.45 0.51 29 35.00 0.06 0.575 0.76 1.06
241.700 9.33 9.19 9.18 0.30 39 35.00 -0.04 0.260 0.34 0.65
241.900 9.78 9.68 9.68 0.20 29 35.00 0.06 0.260 0.34 0.65
Dc 0.73
243.000 9.07 8.87 8.84 0.63 40 35.00 -0.05 0.585 13.500 1.150 0.67 0.47 0.16 0.96
243.200 9.41 9.24 9.22 0.37 28 35.00 0.07 0.440 0.51 0.79
243.400 9.74 9.61 9.6 0.28 40 35.00 -0.05 0.230 0.26 0.55
243.600 9.65 9.48 9.47 0.37 32 35.00 0.03 0.400 0.46 0.75
243.800 9.56 9.35 9.33 0.46 40 35.00 -0.05 0.410 0.47 0.76
244.000 8.58 8.28 8.28 0.60 40 35.00 -0.05 0.550 0.63 0.92
243.100 9.24 9.06 9.03 0.56 29 35.00 0.06 0.621 0.71 1.00
243.300 9.57 9.43 9.41 0.33 36 35.00 -0.01 0.315 0.36 0.65
243.500 9.92 9.81 9.81 0.22 40 35.00 -0.05 0.170 0.20 0.48
243.700 9.61 9.42 9.40 0.41 39 35.00 -0.04 0.375 0.43 0.72
243.900 9.74 9.5 9.5 0.48 40 35.00 -0.05 0.430 0.49 0.78
Dc 0.76
245.000 8.49 8.37 8.33 0.55 27 35.00 0.08 0.633 8.000 1.320 0.84 0.46 0.21 1.26
245.200 8.49 8.39 8.36 0.41 28 35.00 0.07 0.476 0.63 1.05
245.400 8.49 8.4 8.39 0.20 29 35.00 0.06 0.260 0.34 0.77
245.600 8.56 8.48 8.47 0.18 32 35.00 0.03 0.210 0.28 0.70
245.800 8.63 8.56 8.55 0.16 28 35.00 0.07 0.230 0.30 0.73
246.000 9.35 9.25 9.22 0.43 29 35.00 0.06 0.495 0.65 1.08
245.100 8.49 8.38 8.35 0.48 29 35.00 0.06 0.539 0.71 1.14
245.300 8.49 8.39 8.38 0.23 35 35.00 0 0.230 0.30 0.73
245.500 9.2 9.13 9.1 0.37 38 35.00 -0.03 0.345 0.45 0.88
245.700 8.60 8.52 8.51 0.17 39 35.00 -0.04 0.130 0.17 0.60
245.900 9.03 8.9 8.9 0.26 29 35.00 0.06 0.320 0.42 0.85
Dc 0.89
247.000 9.10 9.04 9.01 0.35 29 35.00 0.06 0.415 8.000 1.320 0.55 0.43 0.15 0.85
247.200 8.96 8.88 8.86 0.19 28 35.00 0.07 0.260 0.34 0.65
247.400 8.81 8.72 8.71 0.20 29 35.00 0.06 0.260 0.34 0.65
247.600 9.23 9.03 9.02 0.42 32 35.00 0.03 0.450 0.59 0.90
247.800 9.42 9.34 9.33 0.18 29 35.00 0.06 0.240 0.32 0.62
248.000 8.67 8.56 8.56 0.22 29 35.00 0.06 0.280 0.37 0.67
247.100 9.03 8.96 8.94 0.33 29 35.00 0.06 0.391 0.52 0.82
247.300 8.88 8.80 8.79 0.20 35 35.00 0 0.195 0.26 0.56
247.500 9.62 9.48 9.45 0.51 29 35.00 0.06 0.575 0.76 1.06
247.700 9.33 9.19 9.18 0.30 39 35.00 -0.04 0.260 0.34 0.65
247.900 9.78 9.68 9.68 0.20 29 35.00 0.06 0.260 0.34 0.65
Dc 0.73
249.000 9.54 9.37 9.35 0.38 39 35.00 -0.04 0.340 10.900 1.210 0.41 0.42 0.12 0.65
249.200 9.02 8.89 8.87 0.29 28 35.00 0.07 0.360 0.44 0.68
249.400 8.49 8.4 8.39 0.20 39 35.00 -0.04 0.160 0.19 0.43
249.600 9.11 8.97 8.96 0.31 32 35.00 0.03 0.340 0.41 0.65
249.800 9.73 9.53 9.52 0.42 39 35.00 -0.04 0.380 0.46 0.70
250.000 8.43 8.26 8.25 0.36 39 35.00 -0.04 0.320 0.39 0.63
249.100 9.28 9.13 9.11 0.34 29 35.00 0.06 0.395 0.48 0.72
249.300 8.75 8.64 8.63 0.25 36 35.00 -0.01 0.235 0.28 0.52
249.500 9.12 8.94 8.91 0.59 39 35.00 -0.04 0.555 0.67 0.91
249.700 9.42 9.25 9.24 0.36 39 35.00 -0.04 0.325 0.39 0.63
249.900 9.37 9.15 9.15 0.44 39 35.00 -0.04 0.400 0.48 0.72
Dc 0.66
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from
Haryana Punjab Border to Jind in the State of Haryana 1
Annexure 3.6
Mean deflection
Deflection (mm)
Standard Dev
Temp
mm/km X
Temparature
Pavement Seasonal
Std. temp.
Corrected Corrected Characterisitic
Chainage Up/Dn Temperature FMC% Correction
Initial Intermediate Final Deflection Def, mm Deflection (mm)
(km) (C) Factor
(mm)
251.000 9.10 9.04 9.01 0.35 29 35.00 0.06 0.415 8.000 1.320 0.55 0.43 0.15 0.85
251.200 8.96 8.88 8.86 0.19 28 35.00 0.07 0.260 0.34 0.65
251.400 8.81 8.72 8.71 0.20 29 35.00 0.06 0.260 0.34 0.65
251.600 9.23 9.03 9.02 0.42 32 35.00 0.03 0.450 0.59 0.90
251.800 9.42 9.34 9.33 0.18 29 35.00 0.06 0.240 0.32 0.62
252.000 8.67 8.56 8.56 0.22 29 35.00 0.06 0.280 0.37 0.67
251.100 9.03 8.96 8.94 0.33 29 35.00 0.06 0.391 0.52 0.82
251.300 8.88 8.80 8.79 0.20 35 35.00 0 0.195 0.26 0.56
251.500 9.62 9.48 9.45 0.51 29 35.00 0.06 0.575 0.76 1.06
251.700 9.33 9.19 9.18 0.30 39 35.00 -0.04 0.260 0.34 0.65
251.900 9.78 9.68 9.68 0.20 29 35.00 0.06 0.260 0.34 0.65
Dc 0.73
253.000 9.07 8.87 8.84 0.63 40 35.00 -0.05 0.585 13.500 1.150 0.67 0.47 0.16 0.96
253.200 9.41 9.24 9.22 0.37 28 35.00 0.07 0.440 0.51 0.79
253.400 9.74 9.61 9.6 0.28 40 35.00 -0.05 0.230 0.26 0.55
253.600 9.65 9.48 9.47 0.37 32 35.00 0.03 0.400 0.46 0.75
253.800 9.56 9.35 9.33 0.46 40 35.00 -0.05 0.410 0.47 0.76
254.000 8.58 8.28 8.28 0.60 40 35.00 -0.05 0.550 0.63 0.92
253.100 9.24 9.06 9.03 0.56 29 35.00 0.06 0.621 0.71 1.00
253.300 9.57 9.43 9.41 0.33 36 35.00 -0.01 0.315 0.36 0.65
253.500 9.92 9.81 9.81 0.22 40 35.00 -0.05 0.170 0.20 0.48
253.700 9.61 9.42 9.40 0.41 39 35.00 -0.04 0.375 0.43 0.72
253.900 9.74 9.5 9.5 0.48 40 35.00 -0.05 0.430 0.49 0.78
Dc 0.76
255.000 9.54 9.37 9.35 0.38 39 35.00 -0.04 0.340 10.900 1.210 0.41 0.42 0.12 0.65
255.200 9.02 8.89 8.87 0.29 28 35.00 0.07 0.360 0.44 0.68
255.400 8.49 8.4 8.39 0.20 39 35.00 -0.04 0.160 0.19 0.43
255.600 9.11 8.97 8.96 0.31 32 35.00 0.03 0.340 0.41 0.65
255.800 9.73 9.53 9.52 0.42 39 35.00 -0.04 0.380 0.46 0.70
256.000 8.43 8.26 8.25 0.36 39 35.00 -0.04 0.320 0.39 0.63
255.100 9.28 9.13 9.11 0.34 29 35.00 0.06 0.395 0.48 0.72
255.300 8.75 8.64 8.63 0.25 36 35.00 -0.01 0.235 0.28 0.52
255.500 9.12 8.94 8.91 0.59 39 35.00 -0.04 0.555 0.67 0.91
255.700 9.42 9.25 9.24 0.36 39 35.00 -0.04 0.325 0.39 0.63
255.900 9.37 9.15 9.15 0.44 39 35.00 -0.04 0.400 0.48 0.72
Dc 0.66
257.000 8.49 8.37 8.33 0.55 27 35.00 0.08 0.633 8.000 1.320 0.84 0.46 0.21 1.26
257.200 8.49 8.39 8.36 0.41 28 35.00 0.07 0.476 0.63 1.05
257.400 8.49 8.4 8.39 0.20 29 35.00 0.06 0.260 0.34 0.77
257.600 8.56 8.48 8.47 0.18 32 35.00 0.03 0.210 0.28 0.70
257.800 8.63 8.56 8.55 0.16 28 35.00 0.07 0.230 0.30 0.73
258.000 9.35 9.25 9.22 0.43 29 35.00 0.06 0.495 0.65 1.08
257.100 8.49 8.38 8.35 0.48 29 35.00 0.06 0.539 0.71 1.14
257.300 8.49 8.39 8.38 0.23 35 35.00 0 0.230 0.30 0.73
257.500 9.2 9.13 9.1 0.37 38 35.00 -0.03 0.345 0.45 0.88
257.700 8.59 8.52 8.51 0.17 39 35.00 -0.04 0.130 0.17 0.60
257.900 9.03 8.9 8.9 0.26 29 35.00 0.06 0.320 0.42 0.85
Dc 0.89
259.000 9.54 9.37 9.35 0.38 39 35.00 -0.04 0.340 10.900 1.210 0.41 0.42 0.12 0.65
259.200 9.02 8.89 8.87 0.29 28 35.00 0.07 0.360 0.44 0.68
259.400 8.49 8.4 8.39 0.20 39 35.00 -0.04 0.160 0.19 0.43
259.600 9.11 8.97 8.96 0.31 32 35.00 0.03 0.340 0.41 0.65
259.800 9.73 9.53 9.52 0.42 39 35.00 -0.04 0.380 0.46 0.70
260.000 8.43 8.26 8.25 0.36 39 35.00 -0.04 0.320 0.39 0.63
259.100 9.28 9.13 9.11 0.34 29 35.00 0.06 0.395 0.48 0.72
259.300 8.75 8.64 8.63 0.25 36 35.00 -0.01 0.235 0.28 0.52
259.500 9.12 8.94 8.91 0.59 39 35.00 -0.04 0.555 0.67 0.91
259.700 9.42 9.25 9.24 0.36 39 35.00 -0.04 0.325 0.39 0.63
259.900 9.37 9.15 9.15 0.44 39 35.00 -0.04 0.400 0.48 0.72
Dc 0.66
261.000 8.49 8.37 8.33 0.55 27 35.00 0.08 0.633 8.000 1.320 0.84 0.46 0.21 1.26
261.200 8.49 8.39 8.36 0.41 28 35.00 0.07 0.476 0.63 1.05
261.400 8.49 8.4 8.39 0.20 29 35.00 0.06 0.260 0.34 0.77
261.600 8.56 8.48 8.47 0.18 32 35.00 0.03 0.210 0.28 0.70
261.800 8.63 8.56 8.55 0.16 28 35.00 0.07 0.230 0.30 0.73
262.000 9.35 9.25 9.22 0.43 29 35.00 0.06 0.495 0.65 1.08
261.100 8.49 8.38 8.35 0.48 29 35.00 0.06 0.539 0.71 1.14
261.300 8.49 8.39 8.38 0.23 35 35.00 0 0.230 0.30 0.73
261.500 9.2 9.13 9.1 0.37 38 35.00 -0.03 0.345 0.45 0.88
261.700 8.59 8.52 8.51 0.17 39 35.00 -0.04 0.130 0.17 0.60
261.900 9.03 8.9 8.9 0.26 29 35.00 0.06 0.320 0.42 0.85
Dc 0.89
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from
Haryana Punjab Border to Jind in the State of Haryana 2
Annexure 3.6
Mean deflection
Deflection (mm)
Standard Dev
Temp
mm/km X
Temparature
Pavement Seasonal
Std. temp.
Corrected Corrected Characterisitic
Chainage Up/Dn Temperature FMC% Correction
Initial Intermediate Final Deflection Def, mm Deflection (mm)
(km) (C) Factor
(mm)
263.000 9.54 9.37 9.35 0.38 39 35.00 -0.04 0.340 10.900 1.210 0.41 0.42 0.12 0.65
263.200 9.02 8.89 8.87 0.29 28 35.00 0.07 0.360 0.44 0.68
263.400 8.49 8.4 8.39 0.20 39 35.00 -0.04 0.160 0.19 0.43
263.600 9.11 8.97 8.96 0.31 32 35.00 0.03 0.340 0.41 0.65
263.800 9.73 9.53 9.52 0.42 39 35.00 -0.04 0.380 0.46 0.70
264.000 8.43 8.26 8.25 0.36 39 35.00 -0.04 0.320 0.39 0.63
263.100 9.28 9.13 9.11 0.34 29 35.00 0.06 0.395 0.48 0.72
263.300 8.75 8.64 8.63 0.25 36 35.00 -0.01 0.235 0.28 0.52
263.500 9.12 8.94 8.91 0.59 39 35.00 -0.04 0.555 0.67 0.91
263.700 9.42 9.25 9.24 0.36 39 35.00 -0.04 0.325 0.39 0.63
263.900 9.37 9.15 9.15 0.44 39 35.00 -0.04 0.400 0.48 0.72
Dc 0.66
265.000 9.07 8.87 8.84 0.63 40 35.00 -0.05 0.585 13.500 1.150 0.67 0.47 0.16 0.96
265.200 9.41 9.24 9.22 0.37 28 35.00 0.07 0.440 0.51 0.79
265.400 9.74 9.61 9.6 0.28 40 35.00 -0.05 0.230 0.26 0.55
265.600 9.65 9.48 9.47 0.37 32 35.00 0.03 0.400 0.46 0.75
265.800 9.56 9.35 9.33 0.46 40 35.00 -0.05 0.410 0.47 0.76
266.000 8.58 8.28 8.28 0.60 40 35.00 -0.05 0.550 0.63 0.92
265.100 9.24 9.05 9.03 0.56 29 35.00 0.06 0.621 0.71 1.00
265.300 9.57 9.42 9.41 0.33 36 35.00 -0.01 0.315 0.36 0.65
265.500 9.92 9.81 9.81 0.22 40 35.00 -0.05 0.170 0.20 0.48
265.700 9.61 9.42 9.40 0.41 39 35.00 -0.04 0.375 0.43 0.72
265.900 9.74 9.5 9.5 0.48 40 35.00 -0.05 0.430 0.49 0.78
Dc 0.76
267.000 9.54 9.37 9.35 0.38 39 35.00 -0.04 0.340 10.900 1.210 0.41 0.42 0.12 0.65
267.200 9.02 8.89 8.87 0.29 28 35.00 0.07 0.360 0.44 0.68
267.400 8.49 8.4 8.39 0.20 39 35.00 -0.04 0.160 0.19 0.43
267.600 9.11 8.97 8.96 0.31 32 35.00 0.03 0.340 0.41 0.65
267.800 9.73 9.53 9.52 0.42 39 35.00 -0.04 0.380 0.46 0.70
268.000 8.43 8.26 8.25 0.36 39 35.00 -0.04 0.320 0.39 0.63
267.100 9.28 9.13 9.11 0.34 29 35.00 0.06 0.395 0.48 0.72
267.300 8.75 8.64 8.63 0.25 36 35.00 -0.01 0.235 0.28 0.52
267.500 9.12 8.94 8.91 0.59 39 35.00 -0.04 0.555 0.67 0.91
267.700 9.42 9.25 9.24 0.36 39 35.00 -0.04 0.325 0.39 0.63
267.900 9.37 9.15 9.15 0.44 39 35.00 -0.04 0.400 0.48 0.72
Dc 0.66
269.000 9.54 9.37 9.35 0.38 39 35.00 -0.04 0.340 10.900 1.210 0.41 0.42 0.12 0.65
269.200 9.02 8.89 8.87 0.29 28 35.00 0.07 0.360 0.44 0.68
269.400 8.49 8.4 8.39 0.20 39 35.00 -0.04 0.160 0.19 0.43
269.600 9.11 8.97 8.96 0.31 32 35.00 0.03 0.340 0.41 0.65
269.800 9.73 9.53 9.52 0.42 39 35.00 -0.04 0.380 0.46 0.70
270.000 8.43 8.26 8.25 0.36 39 35.00 -0.04 0.320 0.39 0.63
269.100 9.28 9.13 9.11 0.34 29 35.00 0.06 0.395 0.48 0.72
269.300 8.75 8.64 8.63 0.25 36 35.00 -0.01 0.235 0.28 0.52
269.500 9.12 8.94 8.91 0.59 39 35.00 -0.04 0.555 0.67 0.91
269.700 9.42 9.25 9.24 0.36 39 35.00 -0.04 0.325 0.39 0.63
269.900 9.37 9.15 9.15 0.44 39 35.00 -0.04 0.400 0.48 0.72
Dc 0.66
271.000 8.49 8.37 8.33 0.55 27 35.00 0.08 0.633 8.000 1.320 0.84 0.46 0.21 1.26
271.200 8.49 8.39 8.36 0.41 28 35.00 0.07 0.476 0.63 1.05
271.400 8.49 8.4 8.39 0.20 29 35.00 0.06 0.260 0.34 0.77
271.600 8.56 8.48 8.47 0.18 32 35.00 0.03 0.210 0.28 0.70
271.800 8.63 8.56 8.55 0.16 28 35.00 0.07 0.230 0.30 0.73
272.000 9.35 9.25 9.22 0.43 29 35.00 0.06 0.495 0.65 1.08
271.100 8.49 8.38 8.35 0.48 29 35.00 0.06 0.539 0.71 1.14
271.300 8.49 8.39 8.38 0.23 35 35.00 0 0.230 0.30 0.73
271.500 9.2 9.13 9.1 0.37 38 35.00 -0.03 0.345 0.45 0.88
271.700 8.59 8.52 8.51 0.17 39 35.00 -0.04 0.130 0.17 0.60
271.900 9.03 8.9 8.9 0.26 29 35.00 0.06 0.320 0.42 0.85
Dc 0.89
273.000 9.12 9.08 9.08 0.08 40 35.00 -0.05 0.030 13.500 1.150 0.03 0.30 0.16 0.36
273.200 9.04 8.97 8.96 0.16 28 35.00 0.07 0.230 0.26 0.59
273.400 8.95 8.85 8.83 0.24 40 35.00 -0.05 0.190 0.22 0.54
273.600 9.37 9.20 9.18 0.39 32 35.00 0.03 0.420 0.48 0.81
273.800 9.79 9.54 9.52 0.54 40 35.00 -0.05 0.490 0.56 0.89
274.000 9.67 9.58 9.55 0.41 40 35.00 -0.05 0.365 0.42 0.75
273.100 9.08 9.02 9.02 0.12 29 35.00 0.06 0.180 0.21 0.53
273.300 8.99 8.91 8.89 0.20 36 35.00 -0.01 0.190 0.22 0.54
273.500 9.84 9.74 9.74 0.20 40 35.00 -0.05 0.150 0.17 0.50
273.700 9.58 9.37 9.35 0.46 39 35.00 -0.04 0.425 0.49 0.82
273.900 9.65 9.52 9.52 0.26 40 35.00 -0.05 0.210 0.24 0.57
Dc 0.63
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from
Haryana Punjab Border to Jind in the State of Haryana 3
Annexure 3.6
Mean deflection
Deflection (mm)
Standard Dev
Temp
mm/km X
Temparature
Pavement Seasonal
Std. temp.
Corrected Corrected Characterisitic
Chainage Up/Dn Temperature FMC% Correction
Initial Intermediate Final Deflection Def, mm Deflection (mm)
(km) (C) Factor
(mm)
275.000 9.55 9.53 9.49 0.35 40 35.00 -0.05 0.303 13.500 1.150 0.35 0.35 0.16 0.67
275.200 9.32 9.26 9.24 0.16 28 35.00 0.07 0.230 0.26 0.58
275.400 9.08 8.98 8.98 0.20 40 35.00 -0.05 0.150 0.17 0.49
275.600 8.93 8.82 8.82 0.23 32 35.00 0.03 0.260 0.30 0.62
275.800 8.78 8.66 8.65 0.26 40 35.00 -0.05 0.210 0.24 0.56
276.000 9.63 9.32 9.32 0.62 40 35.00 -0.05 0.570 0.66 0.97
275.100 9.43 9.39 9.36 0.31 29 35.00 0.06 0.375 0.43 0.75
275.300 9.20 9.12 9.11 0.18 36 35.00 -0.01 0.170 0.20 0.51
275.500 9.98 9.73 9.72 0.52 40 35.00 -0.05 0.470 0.54 0.86
275.700 8.86 8.74 8.73 0.24 39 35.00 -0.04 0.205 0.24 0.55
275.900 8.85 8.6 8.6 0.50 40 35.00 -0.05 0.450 0.52 0.84
Dc 0.67
277.000 9.42 9.26 9.25 0.34 40 35.00 -0.05 0.290 13.500 1.150 0.33 0.39 0.09 0.51
277.200 9.51 9.37 9.36 0.30 28 35.00 0.07 0.370 0.43 0.60
277.400 9.6 9.47 9.47 0.26 40 35.00 -0.05 0.210 0.24 0.42
277.600 9.25 9.07 9.07 0.36 32 35.00 0.03 0.390 0.45 0.63
277.800 8.89 8.67 8.66 0.46 40 35.00 -0.05 0.410 0.47 0.65
278.000 9.04 8.89 8.86 0.53 48 35.00 -0.13 0.405 0.47 0.64
277.100 9.46 9.31 9.30 0.32 29 35.00 0.06 0.380 0.44 0.62
277.300 9.55 9.42 9.41 0.28 36 35.00 -0.01 0.270 0.31 0.49
277.500 8.92 8.77 8.75 0.34 48 35.00 -0.13 0.210 0.24 0.42
277.700 9.07 8.87 8.86 0.41 39 35.00 -0.04 0.370 0.43 0.60
277.900 9.26 9.11 9.08 0.53 48 35.00 -0.13 0.405 0.47 0.64
Dc 0.57
279.000 8.59 8.48 8.46 0.26 48 35.00 -0.13 0.130 13.500 1.150 0.15 0.46 0.24 0.64
279.200 9.04 8.90 8.88 0.48 28 35.00 0.07 0.546 0.63 1.11
279.400 9.49 9.32 9.29 0.57 48 35.00 -0.13 0.445 0.51 1.00
279.600 9.23 9.03 9.00 0.63 32 35.00 0.03 0.665 0.76 1.25
279.800 8.96 8.73 8.7 0.69 48 35.00 -0.13 0.565 0.65 1.14
280.000 9.32 9.1 9.1 0.44 48 35.00 -0.13 0.310 0.36 0.84
279.100 8.81 8.69 8.67 0.29 29 35.00 0.06 0.355 0.41 0.89
279.300 9.26 9.11 9.08 0.53 36 35.00 -0.01 0.515 0.59 1.08
279.500 8.18 8.07 8.07 0.22 48 35.00 -0.13 0.090 0.10 0.59
279.700 9.09 8.88 8.85 0.66 39 35.00 -0.04 0.625 0.72 1.20
279.900 9.82 9.71 9.7 0.24 48 35.00 -0.13 0.110 0.13 0.61
Dc 0.94
281.000 8.75 8.52 8.49 0.69 48 35.00 -0.13 0.565 13.500 1.150 0.65 0.45 0.19 1.04
281.200 9.05 8.83 8.81 0.48 28 35.00 0.07 0.550 0.63 1.02
281.400 9.35 9.14 9.13 0.44 48 35.00 -0.13 0.310 0.36 0.74
281.600 9.33 9.15 9.14 0.38 32 35.00 0.03 0.410 0.47 0.86
281.800 9.31 9.15 9.15 0.32 48 35.00 -0.13 0.190 0.22 0.61
282.000 8.54 8.31 8.29 0.50 48 35.00 -0.13 0.370 0.43 0.81
281.100 8.90 8.67 8.65 0.65 29 35.00 0.06 0.706 0.81 1.20
281.300 9.20 8.98 8.97 0.46 36 35.00 -0.01 0.450 0.52 0.91
281.500 9.85 9.72 9.71 0.28 48 35.00 -0.13 0.150 0.17 0.56
281.700 9.32 9.15 9.15 0.35 39 35.00 -0.04 0.310 0.36 0.74
281.900 9.44 9.25 9.24 0.40 48 35.00 -0.13 0.270 0.31 0.70
Dc 0.84
283.000 9.75 9.51 9.49 0.52 48 35.00 -0.13 0.390 13.500 1.150 0.45 0.29 0.17 0.78
283.200 9.16 9.00 8.98 0.35 28 35.00 0.07 0.420 0.48 0.82
283.400 8.56 8.48 8.47 0.18 48 35.00 -0.13 0.050 0.06 0.39
283.600 9.03 8.95 8.94 0.19 32 35.00 0.03 0.220 0.25 0.59
283.800 9.5 9.41 9.4 0.20 48 35.00 -0.13 0.070 0.08 0.41
284.000 9.66 9.49 9.48 0.36 48 35.00 -0.13 0.230 0.26 0.60
283.100 9.45 9.25 9.24 0.44 29 35.00 0.06 0.495 0.57 0.90
283.300 8.86 8.74 8.73 0.27 36 35.00 -0.01 0.255 0.29 0.63
283.500 9.34 9.21 9.2 0.28 48 35.00 -0.13 0.150 0.17 0.51
283.700 9.26 9.18 9.17 0.19 39 35.00 -0.04 0.155 0.18 0.51
283.900 8.23 7.99 7.99 0.48 48 35.00 -0.13 0.350 0.40 0.74
Dc 0.63
285.000 8.48 8.28 8.26 0.44 48 35.00 -0.13 0.310 13.500 1.150 0.36 0.30 0.15 0.65
285.200 8.77 8.62 8.60 0.33 28 35.00 0.07 0.400 0.46 0.76
285.400 9.05 8.96 8.94 0.22 48 35.00 -0.13 0.090 0.10 0.40
285.600 8.94 8.82 8.81 0.25 32 35.00 0.03 0.280 0.32 0.62
285.800 8.82 8.68 8.68 0.28 48 35.00 -0.13 0.150 0.17 0.47
286.000 9.68 9.55 9.55 0.26 48 35.00 -0.13 0.130 0.15 0.45
285.100 8.62 8.45 8.43 0.39 29 35.00 0.06 0.445 0.51 0.81
285.300 8.91 8.79 8.77 0.28 36 35.00 -0.01 0.265 0.30 0.60
285.500 8.9 8.74 8.71 0.55 48 35.00 -0.13 0.425 0.49 0.78
285.700 8.88 8.75 8.75 0.27 39 35.00 -0.04 0.225 0.26 0.55
285.900 9.53 9.42 9.41 0.24 48 35.00 -0.13 0.110 0.13 0.42
Dc 0.59
287.000 9.04 8.79 8.79 0.50 40 35.00 -0.05 0.450 12.500 1.160 0.52 0.53 0.15 0.82
287.200 9.38 9.14 9.13 0.51 28 35.00 0.07 0.580 0.67 0.97
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from
Haryana Punjab Border to Jind in the State of Haryana 4
Annexure 3.6
Mean deflection
Deflection (mm)
Standard Dev
Temp
mm/km X
Temparature
Pavement Seasonal
Std. temp.
Corrected Corrected Characterisitic
Chainage Up/Dn Temperature FMC% Correction
Initial Intermediate Final Deflection Def, mm Deflection (mm)
(km) (C) Factor
(mm) 0.53 0.15
287.400 9.72 9.48 9.46 0.52 40 35.00 -0.05 0.470 0.55 0.84
287.600 9.58 9.36 9.35 0.45 32 35.00 0.03 0.480 0.56 0.85
287.800 9.43 9.24 9.24 0.38 40 35.00 -0.05 0.330 0.38 0.68
288.000 8.85 8.55 8.55 0.60 40 35.00 -0.05 0.550 0.64 0.93
287.100 9.21 8.96 8.96 0.50 29 35.00 0.06 0.565 0.66 0.95
287.300 9.55 9.31 9.29 0.51 36 35.00 -0.01 0.505 0.59 0.88
287.500 9.08 8.97 8.97 0.22 40 35.00 -0.05 0.170 0.20 0.49
287.700 9.50 9.30 9.30 0.42 39 35.00 -0.04 0.375 0.44 0.73
287.900 9.91 9.61 9.59 0.64 40 35.00 -0.05 0.590 0.68 0.98
Dc 0.83
289.000 9.74 9.65 9.62 0.41 40 35.00 -0.05 0.365 12.500 1.160 0.42 0.36 0.18 0.78
289.200 9.73 9.64 9.62 0.22 28 35.00 0.07 0.290 0.34 0.69
289.400 9.72 9.63 9.62 0.20 40 35.00 -0.05 0.150 0.17 0.53
289.600 9.53 9.42 9.41 0.23 32 35.00 0.03 0.260 0.30 0.65
289.800 9.33 9.21 9.2 0.26 40 35.00 -0.05 0.210 0.24 0.60
290.000 9.09 8.94 8.94 0.30 40 35.00 -0.05 0.250 0.29 0.64
289.100 9.74 9.65 9.62 0.38 29 35.00 0.06 0.436 0.51 0.86
289.300 9.73 9.64 9.62 0.21 36 35.00 -0.01 0.200 0.23 0.58
289.500 9.77 9.52 9.49 0.73 40 35.00 -0.05 0.685 0.79 1.15
289.700 9.43 9.32 9.31 0.24 39 35.00 -0.04 0.205 0.24 0.59
289.900 9.74 9.52 9.52 0.44 40 35.00 -0.05 0.390 0.45 0.80
Dc 0.72
291.000 9.52 9.4 9.39 0.26 38 35.00 -0.03 0.230 12.500 1.160 0.27 0.39 0.12 0.50
291.200 9.64 9.51 9.49 0.29 28 35.00 0.07 0.360 0.42 0.65
291.400 9.75 9.62 9.59 0.49 38 35.00 -0.03 0.465 0.54 0.78
291.600 9.32 9.13 9.11 0.41 32 35.00 0.03 0.440 0.51 0.75
291.800 8.88 8.64 8.63 0.50 38 35.00 -0.03 0.470 0.55 0.78
292.000 8.6 8.48 8.48 0.24 38 35.00 -0.03 0.210 0.24 0.48
291.100 9.58 9.45 9.44 0.27 29 35.00 0.06 0.335 0.39 0.63
291.300 9.69 9.56 9.54 0.30 36 35.00 -0.01 0.295 0.34 0.58
291.500 9.37 9.27 9.26 0.22 38 35.00 -0.03 0.190 0.22 0.46
291.700 9.10 8.89 8.87 0.45 39 35.00 -0.04 0.415 0.48 0.72
291.900 8.66 8.5 8.5 0.32 38 35.00 -0.03 0.290 0.34 0.57
Dc 0.63
293.000 9.36 9.15 9.15 0.42 38 35.00 -0.03 0.390 13.500 1.150 0.45 0.52 0.11 0.68
293.200 9.36 9.17 9.16 0.40 28 35.00 0.07 0.470 0.54 0.77
293.400 9.36 9.18 9.17 0.38 38 35.00 -0.03 0.350 0.40 0.63
293.600 9.58 9.38 9.38 0.40 32 35.00 0.03 0.430 0.49 0.72
293.800 9.79 9.58 9.58 0.42 38 35.00 -0.03 0.390 0.45 0.68
294.000 9.54 9.3 9.3 0.48 38 35.00 -0.03 0.450 0.52 0.74
293.100 9.36 9.16 9.16 0.41 29 35.00 0.06 0.470 0.54 0.77
293.300 9.36 9.17 9.17 0.39 36 35.00 -0.01 0.380 0.44 0.66
293.500 9.05 8.72 8.7 0.70 38 35.00 -0.03 0.670 0.77 1.00
293.700 9.68 9.48 9.48 0.41 39 35.00 -0.04 0.370 0.43 0.65
293.900 9.33 9.02 9.02 0.62 38 35.00 -0.03 0.590 0.68 0.91
Dc 0.75
294.000 9.12 9.02 8.98 0.51 39 35.00 -0.04 0.473 13.500 1.150 0.54 0.49 0.16 0.85
294.200 9.44 9.32 9.30 0.28 28 35.00 0.07 0.350 0.40 0.71
294.400 9.75 9.61 9.61 0.28 39 35.00 -0.04 0.240 0.28 0.59
294.600 9.50 9.30 9.28 0.44 32 35.00 0.03 0.470 0.54 0.85
294.800 9.25 8.98 8.95 0.77 39 35.00 -0.04 0.735 0.84 1.16
295.000 9.43 9.21 9.2 0.46 40 35.00 -0.05 0.410 0.47 0.78
294.100 9.28 9.17 9.14 0.45 29 35.00 0.06 0.515 0.59 0.90
294.300 9.59 9.46 9.45 0.28 36 35.00 -0.01 0.270 0.31 0.62
294.500 8.75 8.65 8.62 0.43 40 35.00 -0.05 0.385 0.44 0.75
294.700 9.38 9.14 9.12 0.52 39 35.00 -0.04 0.480 0.55 0.86
294.900 9.1 8.92 8.9 0.40 40 35.00 -0.05 0.350 0.40 0.71
Dc 0.80
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from
Haryana Punjab Border to Jind in the State of Haryana 5
Annexure 3.7
Axle Load Survey
Annexure 3.7
THE Louis Berger Group, Inc. AXLE LOAD SURVEY - Narwana Km 262+000
Axle Load (Tonnes)
Sl. Vehicle Commodity
Origin Destination
No. Type Type 1st Axle 2nd Axle 3rd Axle 4th Axle 5th Axle
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 1
Annexure 3.7
THE Louis Berger Group, Inc. AXLE LOAD SURVEY - Narwana Km 262+000
Axle Load (Tonnes)
Sl. Vehicle Commodity
Origin Destination
No. Type Type 1st Axle 2nd Axle 3rd Axle 4th Axle 5th Axle
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 2
Annexure 3.7
THE Louis Berger Group, Inc. AXLE LOAD SURVEY - Narwana Km 262+000
Axle Load (Tonnes)
Sl. Vehicle Commodity
Origin Destination
No. Type Type 1st Axle 2nd Axle 3rd Axle 4th Axle 5th Axle
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 3
Annexure 3.7
THE Louis Berger Group, Inc. AXLE LOAD SURVEY - Narwana Km 262+000
Axle Load (Tonnes)
Sl. Vehicle Commodity
Origin Destination
No. Type Type 1st Axle 2nd Axle 3rd Axle 4th Axle 5th Axle
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana 4
Annexure 3.8
Roughness Survey
Annexure 3.8
15 22
15 17
1 238.000 239.000 9 17 99.000 132.000 2642.9 3240.2 2941.55
26 32
34 44
49 65
40 47
2 239.000 240.000 24 45 181.000 210.000 4127.1 4652 4389.55
33 30
35 23
17 21
24 19
3 240.000 241.000 26 25 122 126 3059.2 3131.6 3095.4
23 18
32 43
24 27
32 28
4 241.000 242.000 28 26 119 125 3004.9 3113.5 3059.2
18 24
17 20
16 20
34 17
5 242.000 243.000 45 29 144 88 3457.4 2443.8 2950.6
20 11
29 11
22 20
39 35
6 243.000 244.000 18 22 121 151 3041.1 3584.1 3312.6
20 23
22 51
34 16
18 14
7 244.000 245.000 18 16 110 118 2842.0 2986.8 2914.4
12 18
20 11
21 20
22 12
8 245.000 246.000 14 15 125 130 3113.5 3204.0 3158.8
14 17
22 20
20 10
14 18
9 246.000 247.000 18 20 94 98 2552.4 2624.8 2588.6
13 18
76 97
85 94
45 47
10 247.000 248.000 14 12 179 177 4090.9 4054.7 4072.8
9 11
26 13
18 12
19 17
11 248.000 249.000 20 25 112 120 2878.2 3023.0 2950.6
22 24
33 42
15 19
41 26
12 249.000 250.000 21 28 118 167 2986.8 3873.7 3430.3
24 41
17 53
21 48
18 26
13 250.000 251.000 19 22 105 154 2751.5 3638.4 3195.0
19 23
28 35
20 26
21 23
14 251.000 252.000 18 17 99 109 2642.9 2823.9 2733.4
20 15
20 28
17 23
46 35
15 252.000 253.000 41 40 171 181 3946.1 4127.1 4036.6
42 54
25 29
18 30
17 21
16 253.000 254.000 14 18 85 113 2389.5 2896.3 2642.9
12 18
24 26
17 21
17 31
17 254.000 255.000 35 17 151 180 3584.1 4109.0 3846.6
41 45
41 66
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from
Haryana Punjab Border to Jind in the State of Haryana 1
Annexure 3.8
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from
Haryana Punjab Border to Jind in the State of Haryana 2
Annexure 3.8
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from
Haryana Punjab Border to Jind in the State of Haryana 3
Annexure 3.8
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from
Haryana Punjab Border to Jind in the State of Haryana 4
Annexure 3.9
Inventory & Condition Survey of Bridges
The Louis Berger Group, Inc Annexure 3.9
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 1
The Louis Berger Group, Inc Annexure 3.9
Ht of embankment in m A1 A2
Parapet top ht. From Road
0.5 0.5
in m
Parapet top ht. From G.L. in
2.5 2.5
m
Road ht. From min. G.L. in
2.0 2.0
m
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 2
The Louis Berger Group, Inc Annexure 3.9
Span No. 1 2
HC - -
Concrete Superstructure
Spalling - -
Corroded Reinforcement - -
Exposed Reinforcement - -
Crack - -
Leaching - -
Stains - -
P8-
Pier No. P1 P2 P3 P4 P5 P6 P7 P13
12
Honey Combing -
-
Substructure
Spalling
Concrete
Corroded Reinforcement -
Exposed Reinforcement -
Crack -
Leaching
Pier No. P1
Type of foundation Open
Condition Ok
Pier No. A1 A2
Type of foundation Open Open
Condition OK OK
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 3
The Louis Berger Group, Inc Annexure 3.9
a) Curvature of River No
b) Defined Channel yes
c) On Rivers Banks -
Recommendations
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 4
The Louis Berger Group, Inc Annexure 3.9
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 5
The Louis Berger Group, Inc Annexure 3.9
Ht of embankment in m A1 P1 P2 A2
Parapet top ht. From Road
0.5 0.5 0.5 0.5
in m
Parapet top ht. From G.L. in
5.7 5.7 5.7 5.7
m
Road ht. From min. G.L. in
5.2 5.2 5.2 5.2
m
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 6
The Louis Berger Group, Inc Annexure 3.9
Span No. 1 2 3
HC - - -
Concrete Superstructure
Spalling - - -
Corroded Reinforcement - - -
Exposed Reinforcement - - -
Crack - - -
Leaching - - -
Stains - - -
Pier No. P1 P2
Honey Combing - -
- -
Substructure
Spalling
Concrete
Corroded Reinforcement - -
Exposed Reinforcement - -
Crack - -
Leaching
Pier No. P1 P2
Type of foundation Open Open
Condition Ok Ok
Pier No. A1 A2
Type of foundation Open Open
Condition OK OK
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 7
The Louis Berger Group, Inc Annexure 3.9
a) Curvature of River No
b) Defined Channel yes
c) On Rivers Banks -
Recommendations
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 8
The Louis Berger Group, Inc Annexure 3.9
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 9
The Louis Berger Group, Inc Annexure 3.9
Ht of embankment in m A1 P1 P2 P3 A2
Parapet top ht. From Road
0.9 0.9 0.9 0.9 0.9
in m
Parapet top ht. From G.L.
4.4 4.4 4.4 4.4 4.4
in m
Road ht. From min. G.L. in
3.5 3.5 3.5 3.5 3.5
m
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 10
The Louis Berger Group, Inc Annexure 3.9
Span No. 1 2 3 4
HC - - - -
Concrete Superstructure
Spalling - - - -
Corroded Reinforcement - - - -
Exposed Reinforcement - - - -
Crack - - - -
Leaching - - - -
Stains - - - -
Pier No. P1 P2 P3
Honey Combing - - -
- - -
Substructure
Spalling
Concrete
Corroded Reinforcement - - -
Exposed Reinforcement - - -
Crack - - -
Leaching
Pier No. P1 P2 P3
Type of foundation Open Open Open
Condition Ok Ok Ok
Pier No. A1 A2
Type of foundation Open Open
Condition OK OK
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 11
The Louis Berger Group, Inc Annexure 3.9
a) Curvature of River No
b) Defined Channel yes
c) On Rivers Banks Buildings
Recommendations
1. Widening required.
2. Floor Protection damaged.
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 12
The Louis Berger Group, Inc Annexure 3.9
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 13
The Louis Berger Group, Inc Annexure 3.9
Ht of embankment in m A1 P1 A2
Parapet top ht. From Road
0.6 0.6 0.6
in m
Parapet top ht. From G.L.
2.25 2.25 2.25
in m
Road ht. From min. G.L. in
1.65 1.65 1.65
m
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 14
The Louis Berger Group, Inc Annexure 3.9
Span No. 1 2
HC Yes -
Concrete Superstructure
Spalling Yes -
Corroded Reinforcement Yes -
Exposed Reinforcement - -
Crack Yes Yes
Leaching - -
Stains - -
P8-
Pier No. P1 P2 P3 P4 P5 P6 P7 P13
12
Honey Combing -
-
Substructure
Spalling
Concrete
Corroded Reinforcement -
Exposed Reinforcement -
Crack -
Leaching
Pier No. A1 A2
Type of foundation Open Open
Condition OK OK
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 15
The Louis Berger Group, Inc Annexure 3.9
a) Curvature of River No
b) Defined Channel yes
c) On Rivers Banks -
Recommendations
1. Good Condition.
Detailed Project Report for Rehabilitation and Upgradig to 4-lane configuration of Haryana Punjab Border to Jind Section of NH-71
in the State of Haryana 16
Annexure 4.1
Classified Traffic Volume Count
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
Tonga/Bulloc Cart
Scooterr / Motor
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
3 AxleTrucks
2AxleTrucks
car/jeep/van
Tractor with
Other
Tempo/LCV
Std.Buses
Hand Cart
Mini bus
Tender
Trailor
Trailor
Cycle
Cycle
Time
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Haryana Punjab Border to Jind (Km 244 Near Border)
29/05/2010
0-1hr 11 12 30 0 5 7 9 13 5 0 3 6 1 46 1 6 0 0 0
1-2 hr 12 13 31 0 3 12 4 7 4 0 1 3 1 46 0 1 0 0 0
2-3hr 13 14 38 0 8 3 6 9 5 0 2 3 1 50 0 2 1 0 0
3-4 hr 14 15 40 0 6 3 6 3 1 0 3 8 0 38 0 4 0 0 0
4-5 hr 15 16 26 0 10 12 5 8 4 0 4 4 0 51 1 5 1 0 0
5-6 hr 16 17 50 0 2 8 3 20 5 0 0 5 0 31 1 2 0 0 0
6-7 hr 17 18 30 0 3 4 6 12 4 0 4 2 2 50 0 7 2 0 0
7-8 hr 18 19 31 0 2 6 5 12 6 0 1 1 1 46 1 1 3 0 0
8-9 hr 19 20 23 0 0 3 5 10 5 0 1 2 0 35 0 3 0 0 0
9-10 hr 20 21 26 0 0 7 6 12 3 0 0 2 0 21 0 0 0 0 1
10-11hr 21 22 19 0 0 10 3 12 6 0 0 1 1 9 0 0 0 0 0
11-12 hr 22 23 19 0 0 16 11 16 8 0 0 1 0 3 0 0 0 0 0
12-13 hr 23 17 0 0 7 13 8 0 0 0 0 0 3 0 0 0 0 0
13-14 hr 1 8 0 0 13 12 17 5 0 0 0 0 0 0 0 0 0 0
14-15 hr 1 2 5 0 0 11 13 16 5 0 0 0 0 0 0 0 0 0 0
15-16 hr 2 3 5 1 0 10 9 11 1 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 5 1 0 17 10 17 0 0 0 0 0 1 0 0 0 0 0
17-18 hr 4 5 11 0 0 6 4 15 3 0 0 0 0 2 0 0 0 0 0
18-19 hr 5 6 17 0 1 6 10 15 1 0 0 2 0 5 0 3 1 0 0
19-20 hr 6 7 32 0 2 7 8 14 3 0 2 1 0 29 1 1 2 0 0
20-21 hr 7 8 46 0 4 5 14 13 1 0 2 5 1 66 0 3 5 0 0
21-22 hr 8 9 37 1 1 5 10 10 9 0 3 4 2 60 1 4 1 0 0
22-23 hr 9 10 52 0 5 7 7 10 6 0 3 7 0 80 2 7 3 0 0
23-24 hr 10 11 54 0 1 5 3 5 5 0 6 7 0 74 3 5 1 0 0
Total 652 3 53 190 182 285 95 0 35 64 10 746 11 54 20 0 1
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Haryana Punjab Border to Jind (Km 244 Near Border)
30/05/2010
0-1hr 11 12 40 0 3 6 10 13 1 0 0 7 0 29 2 5 0 0 0
1-2 hr 12 13 39 0 3 5 9 11 4 0 2 3 0 29 2 4 0 0 0
2-3hr 13 14 31 0 5 6 2 9 5 0 0 4 3 36 1 3 2 0 0
3-4 hr 14 15 42 0 5 9 4 11 0 0 0 1 0 25 0 1 0 0 0
4-5 hr 15 16 45 0 6 7 4 10 3 0 5 2 0 42 0 8 0 0 0
5-6 hr 16 17 45 0 2 5 6 6 3 0 3 4 0 35 0 7 0 0 0
6-7 hr 17 18 42 0 2 5 2 6 5 0 6 3 3 39 0 2 3 0 0
7-8 hr 18 19 33 0 1 7 20 25 8 0 2 0 1 37 0 2 0 0 0
8-9 hr 19 20 43 0 1 9 18 16 3 0 1 1 0 36 1 6 0 0 0
9-10 hr 20 21 28 0 4 12 3 11 0 0 1 1 0 12 0 0 0 0 0
10-11hr 21 22 24 0 0 32 10 16 7 0 1 2 0 10 0 0 0 0 0
11-12 hr 22 23 14 0 0 20 18 14 5 0 0 0 0 1 0 0 0 0 0
12-13 hr 23 8 0 2 9 14 15 10 4 0 0 0 3 0 0 0 0 0
13-14 hr 1 13 0 0 20 19 23 5 1 0 0 0 0 0 0 0 0 0
14-15 hr 1 2 12 0 0 20 17 19 0 0 1 0 0 0 0 0 0 0 0
15-16 hr 2 3 11 0 0 21 12 17 8 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 22 0 0 21 14 23 12 0 0 0 0 0 1 0 0 0 0
17-18 hr 4 5 15 0 0 12 8 17 7 0 0 0 0 2 0 0 0 0 0
18-19 hr 5 6 22 0 1 4 8 9 7 0 1 1 0 6 0 6 0 0 0
19-20 hr 6 7 32 0 2 9 12 11 7 0 2 1 0 43 0 9 0 0 0
20-21 hr 7 8 47 0 6 18 16 10 7 0 4 0 0 54 0 19 2 0 0
21-22 hr 8 9 26 1 2 6 15 14 5 0 6 5 0 77 0 2 2 0 0
22-23 hr 9 10 31 0 3 4 9 10 4 0 2 8 0 84 1 2 1 0 0
23-24 hr 10 11 35 0 3 8 8 8 2 0 6 4 1 76 1 4 0 0 0
Total 700 1 51 275 258 324 118 5 43 47 8 676 9 80 10 0 0
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Haryana Punjab Border to Jind (Km 244 Near Border)
31/05/2010
0-1hr 11 12 37 1 5 11 6 7 2 0 1 6 2 68 0 3 0 0 0
1-2 hr 12 13 33 0 4 5 8 12 4 0 3 6 0 36 0 2 0 0 0
2-3hr 13 14 32 0 5 3 2 11 1 0 0 3 0 28 2 3 0 0 0
3-4 hr 14 15 28 0 4 4 8 6 0 0 4 3 0 35 4 1 0 0 0
4-5 hr 15 16 42 0 8 6 8 10 2 0 4 5 0 35 0 2 0 0 0
5-6 hr 16 17 36 0 2 3 7 6 3 0 4 1 0 41 2 0 0 0 0
6-7 hr 17 18 39 0 3 8 10 18 0 0 4 1 0 40 0 3 2 0 0
7-8 hr 18 19 40 0 1 6 10 5 1 0 6 3 2 47 1 4 1 0 1
8-9 hr 19 20 37 0 1 4 14 12 6 0 1 0 1 45 2 5 0 0 0
9-10 hr 20 21 32 1 0 18 13 9 4 0 1 2 0 33 0 0 0 0 0
10-11hr 21 22 21 0 0 29 26 36 15 1 0 1 0 31 0 1 0 0 0
11-12 hr 22 23 25 1 0 15 17 14 10 0 2 1 0 15 0 0 0 0 0
12-13 hr 23 18 0 0 16 21 24 12 0 0 0 0 14 1 0 0 0 0
13-14 hr 1 13 1 0 21 16 18 5 0 0 0 0 1 0 0 0 0 1
14-15 hr 1 2 20 0 1 17 13 15 7 0 0 0 0 0 0 0 0 0 0
15-16 hr 2 3 17 0 0 18 18 13 8 0 0 0 1 0 0 0 0 0 0
16-17 hr 3 4 14 0 0 19 13 13 4 0 0 0 0 1 0 2 0 0 0
17-18 hr 4 5 26 0 0 14 10 17 3 0 0 0 0 25 0 0 1 0 0
18-19 hr 5 6 26 0 1 12 12 9 5 0 1 0 0 29 0 5 1 0 0
19-20 hr 6 7 33 1 2 11 15 20 3 0 3 2 0 39 0 10 1 0 0
20-21 hr 7 8 41 1 6 16 15 14 3 0 3 3 0 56 0 15 1 0 0
21-22 hr 8 9 33 0 1 7 14 7 3 0 4 4 0 73 0 4 1 0 0
22-23 hr 9 10 38 0 4 9 13 11 5 0 4 6 0 106 0 4 0 0 0
23-24 hr 10 11 27 0 2 8 9 9 2 0 2 4 1 63 0 4 1 0 0
Total 708 6 50 280 298 316 108 1 47 51 7 861 12 68 9 0 2
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Haryana Punjab Border to Jind (Km 244 Near Border)
1/6/2010
0-1hr 11 12 31 0 5 5 9 2 4 0 2 3 0 45 0 4 0 0 0
1-2 hr 12 13 33 0 4 12 20 12 0 0 3 4 0 47 1 5 0 0 0
2-3hr 13 14 31 0 6 7 8 8 2 0 3 0 0 30 1 4 0 0 0
3-4 hr 14 15 39 0 3 8 2 10 1 0 0 1 0 31 1 3 0 0 1
4-5 hr 15 16 42 0 10 5 9 6 1 0 4 4 0 24 1 1 0 0 0
5-6 hr 16 17 41 0 3 7 7 14 4 0 5 9 0 58 1 3 2 0 0
6-7 hr 17 18 41 0 2 14 13 8 2 0 2 3 0 43 1 3 3 0 3
7-8 hr 18 19 39 0 1 4 10 17 5 0 4 2 0 35 0 5 0 0 0
8-9 hr 19 20 23 0 0 10 6 11 7 0 0 3 2 19 2 9 1 0 0
9-10 hr 20 21 34 0 0 12 21 26 3 0 2 3 0 37 1 0 0 0 0
10-11hr 21 22 33 0 0 34 29 31 0 0 0 0 1 23 0 0 0 0 0
11-12 hr 22 23 31 0 0 26 18 26 4 0 0 0 1 4 0 0 0 0 0
12-13 hr 23 21 1 0 19 11 13 5 0 0 0 1 1 0 0 0 0 0
13-14 hr 1 13 0 0 19 12 14 6 0 0 0 0 0 0 0 0 0 0
14-15 hr 1 2 16 0 0 26 9 23 9 0 0 0 1 0 0 0 0 0 0
15-16 hr 2 3 14 0 0 24 14 17 13 0 0 0 0 1 0 0 0 0 0
16-17 hr 3 4 15 0 0 16 17 16 9 0 0 0 0 2 0 0 0 0 0
17-18 hr 4 5 16 0 0 20 14 18 0 0 0 0 0 8 0 2 2 0 0
18-19 hr 5 6 26 0 1 13 13 15 8 0 1 1 0 13 0 0 0 0 0
19-20 hr 6 7 34 0 2 11 7 13 0 0 4 1 0 23 0 8 0 0 0
20-21 hr 7 8 40 1 5 19 16 24 6 0 5 2 0 47 3 6 3 0 0
21-22 hr 8 9 34 0 1 3 11 10 4 0 1 7 0 66 1 3 2 0 0
22-23 hr 9 10 30 1 3 7 7 11 1 0 2 8 0 75 2 4 0 0 0
23-24 hr 10 11 40 0 4 4 8 9 5 0 1 2 0 85 2 6 1 0 1
Total 717 3 50 325 291 354 99 0 39 53 6 717 17 66 14 0 5
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Haryana Punjab Border to Jind (Km 244 Near Border)
2/6/2010
0-1hr 11 12 34 0 3 6 8 7 2 0 4 7 0 58 0 1 0 0 0
1-2 hr 12 13 45 0 1 5 7 8 0 0 3 4 0 48 0 1 0 0 0
2-3hr 13 14 37 0 4 7 11 8 1 0 1 1 0 28 1 0 0 0 0
3-4 hr 14 15 43 0 4 6 10 14 2 0 1 2 0 29 1 1 0 0 0
4-5 hr 15 16 39 0 6 5 9 7 0 0 1 3 0 35 1 1 0 0 0
5-6 hr 16 17 30 0 1 7 3 5 6 0 3 1 0 50 2 3 1 0 0
6-7 hr 17 18 34 0 3 4 3 6 5 0 2 2 0 54 1 4 0 0 0
7-8 hr 18 19 36 0 3 7 6 2 0 1 4 5 0 38 1 1 0 0 0
8-9 hr 19 20 29 0 0 2 8 6 2 0 0 1 0 16 0 1 0 0 0
9-10 hr 20 21 31 0 0 13 12 22 8 0 1 1 0 21 0 0 0 0 0
10-11hr 21 22 27 0 0 13 10 19 3 0 1 3 0 10 1 0 0 0 0
11-12 hr 22 23 17 0 0 17 20 22 1 0 1 0 0 5 1 0 0 0 0
12-13 hr 23 8 0 1 19 10 18 5 0 1 0 0 2 0 0 0 0 0
13-14 hr 1 4 2 0 14 13 13 2 0 0 0 3 10 0 0 0 0 0
14-15 hr 1 2 13 0 0 16 19 19 0 0 0 0 2 0 0 0 0 0 0
15-16 hr 2 3 11 0 0 22 20 20 8 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 10 0 0 14 16 16 11 0 0 2 0 1 0 0 0 0 0
17-18 hr 4 5 13 0 0 18 18 10 4 0 0 0 0 4 0 3 1 0 0
18-19 hr 5 6 17 0 0 22 21 20 1 0 0 0 0 35 0 0 0 0 0
19-20 hr 6 7 32 1 3 17 24 22 9 0 3 0 2 50 0 7 0 0 0
20-21 hr 7 8 37 0 6 13 10 12 4 0 1 7 0 45 0 8 1 0 0
21-22 hr 8 9 27 1 1 10 10 9 2 0 3 0 0 59 3 4 1 0 0
22-23 hr 9 10 40 0 3 3 6 12 1 0 0 3 1 60 2 6 2 0 0
23-24 hr 10 11 30 1 2 2 4 12 4 0 0 11 0 45 1 9 1 0 0
Total 644 5 41 262 278 309 81 1 30 53 8 703 15 50 7 0 0
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Haryana Punjab Border to Jind (Km 244 Near Border)
3/6/2010
0-1hr 11 12 27 0 5 4 5 8 0 0 4 3 0 48 0 3 0 0 0
1-2 hr 12 13 21 1 1 4 4 14 1 0 3 5 0 37 0 0 0 0 0
2-3hr 13 14 23 0 4 2 9 4 3 0 0 3 0 18 1 0 0 0 0
3-4 hr 14 15 30 0 4 9 4 12 2 0 2 1 0 34 1 3 0 0 0
4-5 hr 15 16 27 1 2 2 8 11 1 0 2 2 1 29 0 0 0 0 0
5-6 hr 16 17 32 1 2 5 3 12 2 0 2 3 1 34 0 1 0 0 0
6-7 hr 17 18 32 0 2 7 10 7 2 0 1 3 0 39 0 4 1 0 0
7-8 hr 18 19 18 0 0 8 4 14 6 0 2 3 0 46 1 2 0 0 0
8-9 hr 19 20 29 0 0 10 12 20 3 0 0 1 0 22 1 4 0 0 0
9-10 hr 20 21 40 0 2 10 15 32 14 0 1 1 1 31 2 7 0 0 0
10-11hr 21 22 33 0 0 34 36 36 2 0 1 1 1 0 0 0 0 0 0
11-12 hr 22 23 18 0 0 21 16 16 16 0 0 0 0 0 0 0 0 0 0
12-13 hr 23 14 1 0 18 17 28 11 0 0 0 0 0 0 0 0 0 0
13-14 hr 1 10 0 0 15 14 16 9 1 0 0 1 0 0 0 0 0 0
14-15 hr 1 2 10 0 0 36 26 28 5 0 0 0 0 0 0 0 0 0 0
15-16 hr 2 3 11 0 0 15 13 6 5 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 12 0 0 17 15 13 9 0 0 1 0 1 0 0 0 0 0
17-18 hr 4 5 14 0 0 19 12 12 10 0 0 0 0 7 0 0 1 0 0
18-19 hr 5 6 14 0 1 11 8 13 5 1 1 1 0 5 0 0 3 0 0
19-20 hr 6 7 14 1 2 6 17 14 6 0 0 0 0 23 0 0 1 0 0
20-21 hr 7 8 46 0 5 13 22 27 2 0 2 3 0 46 2 14 0 0 0
21-22 hr 8 9 42 0 0 10 5 3 2 0 4 3 0 40 0 0 0 0 0
22-23 hr 9 10 42 0 4 6 8 18 1 0 3 3 0 68 2 11 0 0 0
23-24 hr 10 11 30 0 2 3 8 17 3 0 1 2 0 44 0 0 1 0 1
Total 589 5 36 285 291 381 120 2 29 39 5 572 10 49 7 0 1
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Haryana Punjab Border to Jind (Km 244 Near Border)
4/6/2010
0-1hr 11 12 52 0 5 9 5 8 4 0 0 3 0 21 3 2 0 0 0
1-2 hr 12 13 22 0 5 4 11 4 1 0 5 1 0 40 1 4 0 0 0
2-3hr 13 14 36 0 6 14 5 17 3 0 3 5 0 43 1 2 1 0 0
3-4 hr 14 15 30 0 4 10 4 13 4 0 2 5 0 26 3 1 0 0 1
4-5 hr 15 16 33 1 4 5 9 8 5 0 2 5 0 45 0 4 0 0 0
5-6 hr 16 17 33 0 3 6 3 9 2 0 2 3 0 45 1 2 1 4 0
6-7 hr 17 18 42 0 0 7 3 19 10 0 3 2 1 51 0 5 3 0 0
7-8 hr 18 19 25 0 1 2 13 12 2 0 0 1 0 30 0 2 0 0 0
8-9 hr 19 20 20 0 0 12 6 7 1 0 1 0 0 28 1 6 0 0 1
9-10 hr 20 21 26 0 0 9 17 15 6 0 1 1 1 22 2 6 0 0 0
10-11hr 21 22 20 0 0 14 18 19 6 0 3 2 1 13 0 0 0 0 0
11-12 hr 22 23 30 0 0 26 34 25 6 0 0 0 0 12 0 0 0 0 0
12-13 hr 23 20 3 0 22 15 13 9 0 0 0 0 4 0 0 0 0 0
13-14 hr 1 18 0 1 15 17 13 12 0 0 0 0 0 0 0 0 0 0
14-15 hr 1 2 14 3 0 17 15 19 7 0 0 0 0 0 0 0 0 0 0
15-16 hr 2 3 17 1 1 16 11 11 7 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 15 0 0 15 14 13 8 0 0 0 1 0 0 0 0 0 0
17-18 hr 4 5 26 2 0 28 34 25 8 0 0 0 0 0 0 0 0 0 0
18-19 hr 5 6 24 0 0 13 4 19 1 0 1 0 1 13 0 2 4 0 0
19-20 hr 6 7 24 2 2 9 12 19 7 0 0 2 0 38 0 0 2 0 0
20-21 hr 7 8 34 0 4 16 24 27 6 0 6 0 0 65 0 13 0 0 0
21-22 hr 8 9 29 0 2 11 5 4 3 0 1 0 0 46 0 1 0 0 0
22-23 hr 9 10 36 0 3 7 8 13 3 0 1 3 0 57 0 2 0 0 0
23-24 hr 10 11 40 0 4 1 11 11 1 0 4 1 1 51 2 4 1 0 0
Total 666 12 45 288 298 343 122 0 35 34 6 650 14 56 12 4 2
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Jind to Haryana Punjab Border (Km 244 Near Border)
29/05/2010
0-1hr 11 12 47 1 7 11 8 15 3 0 3 10 0 68 0 5 3 0 0
1-2 hr 12 13 43 2 2 7 9 10 2 0 2 6 1 43 0 1 0 0 0
2-3hr 13 14 36 1 6 8 2 7 3 0 3 3 3 33 1 1 1 0 0
3-4 hr 14 15 18 0 4 2 9 19 5 0 0 3 1 29 1 3 1 0 0
4-5 hr 15 16 51 0 3 10 5 19 6 0 4 5 1 24 0 0 0 0 1
5-6 hr 16 17 24 0 1 4 7 9 2 0 1 4 0 17 1 1 1 0 0
6-7 hr 17 18 58 0 5 16 9 17 7 0 1 6 3 41 2 10 2 0 0
7-8 hr 18 19 32 0 2 7 5 32 6 0 3 0 0 39 0 10 2 0 0
8-9 hr 19 20 30 1 0 10 1 12 4 0 2 1 3 27 0 1 0 0 0
9-10 hr 20 21 23 0 0 4 3 14 4 0 0 0 0 37 1 2 1 0 0
10-11hr 21 22 26 0 0 16 11 18 3 0 0 2 1 15 1 0 0 0 0
11-12 hr 22 23 13 0 0 10 6 18 4 0 0 0 0 5 0 0 0 0 0
12-13 hr 23 13 0 1 6 8 13 5 0 0 0 0 3 0 0 0 0 3
13-14 hr 1 9 0 7 7 9 5 0 0 0 0 3 0 0 0 0 0 0
14-15 hr 1 2 6 1 0 10 9 12 0 0 0 0 0 0 0 0 0 0 0
15-16 hr 2 3 9 1 2 23 18 8 2 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 8 0 0 11 6 16 3 0 0 0 0 0 0 0 0 0 0
17-18 hr 4 5 11 0 0 11 10 13 3 0 0 0 0 0 0 0 0 0 0
18-19 hr 5 6 19 1 3 10 12 15 2 0 2 0 0 7 0 4 1 0 0
19-20 hr 6 7 41 0 5 9 20 19 9 0 0 0 1 30 0 8 1 0 0
20-21 hr 7 8 39 0 4 12 11 22 2 0 4 3 1 71 0 16 3 0 1
21-22 hr 8 9 38 0 2 4 7 9 0 0 2 5 8 34 1 6 1 0 0
22-23 hr 9 10 55 0 7 12 0 13 2 0 3 5 0 47 1 5 2 0 0
23-24 hr 10 11 51 0 3 8 5 22 1 0 3 3 0 42 1 4 1 0 0
Total 700 8 64 228 190 357 78 0 33 56 26 612 10 77 20 0 5
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Jind to Haryana Punjab Border (Km 244 Near Border)
30/05/2010
0-1hr 11 12 58 0 5 4 6 11 1 0 0 4 0 43 0 3 2 0 0
1-2 hr 12 13 53 0 5 6 7 8 0 0 1 5 0 30 2 7 0 0 0
2-3hr 13 14 40 1 3 7 12 9 2 0 2 2 0 30 0 2 0 0 1
3-4 hr 14 15 43 0 3 7 9 9 4 0 0 3 3 13 1 2 4 0 0
4-5 hr 15 16 39 0 3 4 9 12 7 0 2 2 0 22 3 2 0 0 0
5-6 hr 16 17 48 0 3 10 9 19 4 0 2 5 0 27 2 1 3 0 0
6-7 hr 17 18 55 0 2 11 14 20 4 0 3 3 0 33 0 0 1 0 0
7-8 hr 18 19 23 0 1 16 14 16 9 0 2 2 0 25 0 0 2 0 0
8-9 hr 19 20 44 0 2 15 14 23 4 0 1 6 0 37 2 11 1 0 0
9-10 hr 20 21 34 0 1 9 12 10 4 0 0 4 0 37 3 2 0 0 0
10-11hr 21 22 16 0 0 12 9 16 5 0 1 1 0 16 1 0 0 0 0
11-12 hr 22 23 16 2 0 9 13 18 8 0 0 0 0 5 1 0 0 0 0
12-13 hr 23 9 1 0 13 15 19 2 0 0 0 0 3 0 0 0 0 0
13-14 hr 1 16 0 0 11 8 17 2 0 0 0 0 0 0 0 0 0 0
14-15 hr 1 2 14 0 1 12 15 26 4 0 0 0 1 0 0 0 0 0 0
15-16 hr 2 3 12 0 3 13 8 17 5 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 14 0 1 12 11 14 10 0 0 0 0 0 0 0 0 0 0
17-18 hr 4 5 14 0 0 13 11 20 8 0 0 0 0 1 1 0 0 0 0
18-19 hr 5 6 22 0 1 11 9 17 1 0 0 1 0 20 0 1 1 0 0
19-20 hr 6 7 29 2 3 10 14 17 12 0 1 9 1 42 1 6 2 0 0
20-21 hr 7 8 42 2 2 15 16 18 8 0 6 6 0 80 3 19 4 0 0
21-22 hr 8 9 47 0 3 10 4 13 5 0 3 5 0 32 0 4 0 0 0
22-23 hr 9 10 33 1 6 17 7 13 11 0 5 4 0 53 0 5 0 0 0
23-24 hr 10 11 36 0 3 6 4 10 3 0 2 5 1 38 1 2 1 0 0
Total 757 9 51 253 250 372 123 0 31 67 6 587 21 67 21 0 1
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Jind to Haryana Punjab Border (Km 244 Near Border)
31/05/2010
0-1hr 11 12 29 0 7 4 5 5 3 0 3 3 2 55 4 4 0 0 0
1-2 hr 12 13 30 0 3 5 1 9 1 0 3 6 0 31 0 2 1 0 0
2-3hr 13 14 37 0 1 5 7 16 1 0 3 3 1 43 0 1 0 0 0
3-4 hr 14 15 36 1 4 2 8 7 2 0 2 5 0 25 0 2 0 0 0
4-5 hr 15 16 26 0 2 3 4 3 1 0 0 4 0 24 0 2 0 0 1
5-6 hr 16 17 43 0 3 5 15 13 4 0 1 9 0 45 0 8 0 0 0
6-7 hr 17 18 34 0 3 1 6 19 1 0 1 5 0 34 0 6 0 0 0
7-8 hr 18 19 38 1 1 2 9 14 1 0 5 3 2 38 2 8 2 0 0
8-9 hr 19 20 30 1 1 10 11 22 1 0 2 2 1 52 0 12 1 0 0
9-10 hr 20 21 32 0 0 15 16 15 3 0 0 6 0 50 0 6 0 0 0
10-11hr 21 22 22 0 0 19 18 21 8 0 2 0 0 26 0 0 0 0 0
11-12 hr 22 23 19 0 0 16 16 22 10 0 0 2 0 10 3 0 0 0 0
12-13 hr 23 19 2 0 17 16 20 13 0 0 0 0 4 0 0 0 0 0
13-14 hr 1 15 1 0 16 15 25 16 0 0 0 0 0 0 0 0 0 0
14-15 hr 1 2 14 0 2 15 12 23 12 0 0 0 0 1 0 0 0 0 0
15-16 hr 2 3 15 0 0 28 30 24 15 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 5 1 0 18 28 34 6 0 0 0 1 0 0 0 0 0 0
17-18 hr 4 5 24 0 0 16 15 18 19 0 0 0 0 14 0 3 0 0 0
18-19 hr 5 6 22 2 1 21 17 20 5 0 0 0 0 23 1 10 0 0 0
19-20 hr 6 7 45 3 3 13 17 23 7 0 2 2 1 39 0 11 3 0 0
20-21 hr 7 8 49 1 3 14 16 18 9 0 3 1 0 79 0 11 4 0 1
21-22 hr 8 9 31 0 2 9 15 16 1 0 2 3 0 33 0 4 0 0 0
22-23 hr 9 10 36 0 5 10 4 5 5 0 4 3 0 42 1 1 0 0 0
23-24 hr 10 11 41 0 4 5 7 11 0 0 4 2 0 34 2 3 2 0 0
Total 692 13 45 269 308 403 144 0 37 59 8 702 13 94 13 0 2
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Jind to Haryana Punjab Border (Km 244 Near Border)
1/6/2010
0-1hr 11 12 31 0 5 9 5 8 0 0 1 2 0 42 0 1 0 0 0
1-2 hr 12 13 32 2 2 6 4 11 4 0 2 2 1 41 2 3 2 0 0
2-3hr 13 14 38 0 5 11 2 9 6 0 3 2 0 33 0 1 1 0 0
3-4 hr 14 15 19 0 4 11 6 6 4 0 0 1 0 23 1 1 0 0 0
4-5 hr 15 16 47 0 2 11 21 9 7 0 1 1 1 21 1 1 1 0 0
5-6 hr 16 17 32 0 3 9 13 5 1 0 5 2 0 29 1 1 0 0 0
6-7 hr 17 18 38 0 0 7 7 16 5 0 3 3 0 33 1 2 4 0 0
7-8 hr 18 19 36 0 3 4 1 31 4 0 4 5 0 35 0 11 3 0 0
8-9 hr 19 20 35 0 1 4 11 18 1 0 0 1 0 31 0 4 1 0 0
9-10 hr 20 21 30 0 0 19 19 26 15 0 0 4 0 55 1 6 0 0 0
10-11hr 21 22 21 0 0 19 15 30 7 0 2 2 2 19 0 0 0 0 0
11-12 hr 22 23 23 0 0 27 12 22 4 0 0 1 6 20 0 0 0 0 0
12-13 hr 23 23 0 0 17 18 29 1 0 1 0 1 0 0 0 0 0 0
13-14 hr 1 15 0 0 21 30 28 6 0 0 0 0 2 0 0 0 0 0
14-15 hr 1 2 15 0 0 21 14 18 1 0 1 0 0 0 0 0 0 0 0
15-16 hr 2 3 19 1 2 22 11 17 7 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 13 0 0 17 11 14 10 0 0 0 0 1 0 0 0 0 0
17-18 hr 4 5 17 2 0 22 27 24 6 0 0 0 0 6 1 0 1 0 0
18-19 hr 5 6 20 0 1 11 18 15 6 0 0 4 0 12 0 3 2 0 0
19-20 hr 6 7 28 2 4 11 23 16 14 0 5 3 0 43 0 5 1 0 0
20-21 hr 7 8 64 2 2 18 18 22 4 0 2 2 0 70 1 14 2 0 0
21-22 hr 8 9 37 0 1 6 9 8 5 0 9 0 23 31 0 4 1 0 0
22-23 hr 9 10 42 0 7 4 7 6 7 0 1 6 0 45 0 0 0 0 0
23-24 hr 10 11 48 0 5 4 5 8 5 0 2 3 0 52 2 2 1 0 1
Total 723 9 47 311 307 396 130 0 42 44 34 644 11 59 20 0 1
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Jind to Haryana Punjab Border (Km 244 Near Border)
2/6/2010
0-1hr 11 12 35 1 2 22 20 10 3 0 6 3 0 27 1 4 1 0 0
1-2 hr 12 13 34 0 4 7 5 12 2 0 2 5 1 32 0 0 2 0 0
2-3hr 13 14 38 1 4 4 9 14 2 0 1 3 0 28 0 3 0 0 0
3-4 hr 14 15 29 0 4 4 5 13 4 0 0 2 0 29 2 2 1 0 0
4-5 hr 15 16 24 0 2 2 9 19 5 0 0 2 0 20 1 2 1 0 0
5-6 hr 16 17 23 2 1 5 6 21 1 0 0 5 0 39 1 4 1 0 0
6-7 hr 17 18 36 0 3 16 12 16 3 0 3 4 1 37 0 5 4 0 0
7-8 hr 18 19 36 0 1 13 17 30 6 0 2 1 0 32 0 10 4 0 0
8-9 hr 19 20 28 1 1 12 8 19 3 0 3 2 0 28 0 4 1 0 1
9-10 hr 20 21 30 1 0 13 14 16 10 0 0 4 1 38 1 4 0 0 0
10-11hr 21 22 17 0 0 15 12 18 13 0 0 0 0 7 0 0 0 0 0
11-12 hr 22 23 14 0 0 12 14 22 9 0 0 0 0 4 0 0 0 0 0
12-13 hr 23 15 0 0 16 22 18 2 0 1 0 0 4 0 0 0 0 0
13-14 hr 1 15 0 0 15 12 15 7 0 0 0 0 2 0 0 0 0 0
14-15 hr 1 2 12 0 2 14 10 17 8 0 0 0 0 1 0 0 0 0 0
15-16 hr 2 3 19 0 2 20 18 21 10 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 17 2 0 23 12 21 10 0 0 0 1 0 0 1 0 0 0
17-18 hr 4 5 16 1 0 20 18 25 21 0 0 0 0 2 0 0 0 0 0
18-19 hr 5 6 24 1 1 19 14 13 8 0 2 0 1 32 0 4 0 0 0
19-20 hr 6 7 42 1 3 16 19 18 8 0 1 4 2 45 0 14 1 0 0
20-21 hr 7 8 34 3 3 14 9 11 2 0 2 4 0 43 0 14 1 0 0
21-22 hr 8 9 34 0 2 10 14 15 3 0 0 2 0 42 0 4 2 0 0
22-23 hr 9 10 45 0 4 2 4 11 2 0 4 3 2 28 4 4 0 0 0
23-24 hr 10 11 34 0 4 6 10 19 6 0 4 1 0 37 0 4 3 0 0
Total 651 14 43 300 293 414 148 0 31 45 9 557 10 83 22 0 1
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Jind to Haryana Punjab Border (Km 244 Near Border)
3/6/2010
0-1hr 11 12 37 0 4 6 5 13 2 0 2 4 0 55 2 1 0 0 0
1-2 hr 12 13 38 1 6 6 8 21 2 0 0 4 0 32 1 1 2 0 0
2-3hr 13 14 24 2 1 12 8 17 5 0 1 2 1 39 1 1 0 0 1
3-4 hr 14 15 17 0 2 3 2 12 0 0 0 3 0 25 0 0 0 0 0
4-5 hr 15 16 33 0 3 9 16 33 9 0 3 2 0 25 2 0 0 0 0
5-6 hr 16 17 34 1 1 3 10 18 4 0 1 7 2 31 2 1 0 0 0
6-7 hr 17 18 43 0 4 6 15 19 5 0 2 2 1 40 0 2 1 0 1
7-8 hr 18 19 50 1 0 7 12 16 2 0 4 4 0 31 3 7 4 0 0
8-9 hr 19 20 25 0 2 6 17 23 6 0 3 1 1 25 1 5 2 0 0
9-10 hr 20 21 22 0 0 13 9 24 14 0 1 1 0 37 0 0 0 0 0
10-11hr 21 22 20 0 0 14 13 13 9 0 0 1 0 19 0 0 0 0 0
11-12 hr 22 23 22 0 0 13 14 19 7 0 2 8 0 8 0 0 0 0 0
12-13 hr 23 24 0 0 15 17 22 10 0 0 0 0 0 0 0 0 0 0
13-14 hr 1 17 0 0 23 18 20 7 0 0 0 2 0 0 0 0 0 0
14-15 hr 1 2 14 0 0 42 36 31 10 0 0 0 0 0 0 0 0 0 0
15-16 hr 2 3 8 1 2 10 12 14 2 0 0 0 0 0 1 0 0 0 0
16-17 hr 3 4 14 2 0 18 14 20 11 0 0 0 0 0 0 0 0 0 0
17-18 hr 4 5 13 2 1 13 14 17 8 0 0 1 0 6 0 2 1 0 0
18-19 hr 5 6 11 0 1 15 12 13 9 0 0 2 0 15 0 0 0 0 0
19-20 hr 6 7 24 3 3 11 10 15 8 0 1 0 0 25 1 12 1 0 0
20-21 hr 7 8 53 6 3 16 16 13 9 0 3 3 0 58 0 13 4 0 0
21-22 hr 8 9 29 0 3 10 11 8 5 0 4 2 0 27 1 3 0 0 0
22-23 hr 9 10 47 0 5 9 10 15 1 0 3 5 0 32 1 3 0 0 0
23-24 hr 10 11 36 0 1 7 7 20 2 0 1 1 0 40 0 2 2 0 1
Total 655 19 42 287 306 436 147 0 31 53 7 570 16 53 17 0 3
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Appendix 4.1
3 - 6 AxleTrucks
Ambulance, fire
>=6 AxleTrucks
Tractor without
Auto Rickshaw
Other
Tonga/Bulloc
3 AxleTrucks
2AxleTrucks
car/jeep/van
Motor Cycle
Tractor with
Tempo/LCV
Std.Buses
Hand Cart
Scooterr /
Mini bus
Tender
Trailor
Trailor
Cycle
Time
Cart
Jind to Haryana Punjab Border (Km 244 Near Border)
4/6/2010
0-1hr 11 12 41 2 4 2 3 11 3 0 3 3 0 43 0 2 2 0 0
1-2 hr 12 13 35 0 3 5 9 15 1 0 1 3 0 45 0 2 0 0 0
2-3hr 13 14 34 0 0 5 4 13 1 0 7 4 0 14 0 0 1 0 0
3-4 hr 14 15 34 0 5 7 4 12 2 0 0 1 0 27 3 0 0 0 0
4-5 hr 15 16 23 0 2 4 11 6 2 0 3 0 0 28 0 2 0 0 0
5-6 hr 16 17 33 0 3 11 12 12 4 0 3 3 0 33 1 4 1 0 0
6-7 hr 17 18 31 0 4 9 12 12 3 0 1 2 0 43 0 10 1 0 0
7-8 hr 18 19 53 0 0 7 17 10 4 0 0 4 0 31 0 4 4 0 0
8-9 hr 19 20 27 0 2 4 15 17 4 0 2 1 0 23 0 5 0 0 0
9-10 hr 20 21 36 1 0 11 13 15 13 0 1 1 1 42 0 4 1 0 0
10-11hr 21 22 22 0 0 11 21 16 8 0 0 0 0 21 0 0 0 0 0
11-12 hr 22 23 22 0 0 15 23 20 9 0 0 4 0 25 0 0 0 0 0
12-13 hr 23 18 0 0 14 20 17 9 0 0 0 0 2 0 0 0 0 0
13-14 hr 1 15 0 0 17 14 15 9 0 0 0 0 0 0 0 0 0 0
14-15 hr 1 2 14 0 0 19 13 15 9 0 0 0 0 0 0 0 0 0 0
15-16 hr 2 3 12 0 2 13 14 12 8 0 0 0 0 0 0 0 0 0 0
16-17 hr 3 4 16 0 0 14 11 11 8 0 0 0 1 0 0 0 0 0 0
17-18 hr 4 5 15 2 0 14 14 15 6 0 0 0 0 0 1 0 1 0 0
18-19 hr 5 6 13 0 1 21 11 14 8 0 0 0 0 14 0 3 1 0 0
19-20 hr 6 7 31 2 4 14 15 15 4 0 0 1 0 34 0 14 3 0 0
20-21 hr 7 8 40 3 3 16 17 16 10 0 1 2 1 95 1 11 1 0 0
21-22 hr 8 9 44 0 4 16 11 11 2 0 2 3 2 47 0 6 2 0 0
22-23 hr 9 10 32 0 7 6 9 10 8 0 4 3 0 66 2 7 0 0 0
23-24 hr 10 11 43 0 3 9 11 9 4 0 0 4 0 79 2 4 0 0 0
Total 684 10 47 264 304 319 139 0 28 39 5 712 10 78 18 0 0
Detailed Project Report for Rehabilitation and Upgrading to 4-lane Configuration of NH-71, from Haryana Punjab Border to Jind in the State of Haryana
Annexure 4.2
MSA Calculation
Annexure 4.2
2-Axle 3-Axle
S. No. Year Mini Bus Bus LCV MAV
Truck Truck
Growth Rate
7.2 8.3 10.4 8.6 8.6 8.6
(%)(2010-12)
Growth Rate
6.50 7.40 9.10 7.60 7.60 7.60
(%)(2013-17)
Growth Rate Yearwise Cumulative
5.70 6.60 8.00 6.60 6.60 6.60
(%)(2018-22) CSA in CSA in
Growth Rate million million
5.10 5.90 7.10 5.90 5.90 5.90
(%)(2023-27)
Growth Rate
4.70 5.40 6.40 5.30 5.30 5.30
(%)(2028-32)
Growth Rate
4.40 5.10 6.10 5.00 5.00 5.00
(%)(>2032)
VDF 0.46 0.46 0.56 4.90 4.10 3.10
1 2011 79 223 144 992 1618 323
2 2012 85 242 159 1077 1757 351
3 2013 90 259 173 1159 1891 377
4 2014 96 279 189 1247 2034 406
5 2015 102 299 206 1342 2189 437
6 2016 109 321 225 1444 2355 470 2.53 2.53
7 2017 116 345 246 1554 2534 506 2.73 5.26
8 2018 123 368 265 1656 2702 539 2.91 8.17
9 2019 130 392 287 1766 2880 575 3.10 11.27
10 2020 137 418 310 1882 3070 613 3.30 14.57
11 2021 145 446 334 2006 3273 653 3.52 18.09
12 2022 153 475 361 2139 3489 696 3.76 21.85
13 2023 161 503 387 2265 3694 738 3.98 25.83
14 2024 169 533 414 2399 3912 781 4.21 30.04
15 2025 178 564 444 2540 4143 827 4.46 34.50
16 2026 187 597 475 2690 4388 876 4.72 39.22
17 2027 196 633 509 2849 4647 928 5.00 44.22
18 2028 206 667 541 3000 4893 977 5.27 49.49
19 2029 215 703 576 3159 5152 1029 5.55 55.04
20 2030 225 741 613 3326 5425 1083 5.84 60.88
21 2031 236 781 652 3503 5713 1140 6.15 67.03
22 2032 247 823 694 3688 6016 1201 6.48 73.51
23 2033 258 865 736 3873 6316 1261 6.80 80.31
24 2034 269 909 781 4066 6632 1324 7.14 87.45
25 2035 281 956 829 4270 6964 1390 7.50 94.95
26 2036 293 1004 879 4483 7312 1460 7.88 102.83
27 2037 306 1055 933 4707 7678 1533 8.27 111.10
28 2038 320 1109 990 4942 8061 1609 8.69 119.79
29 2039 334 1166 1050 5190 8465 1690 9.12 128.91
30 2040 349 1225 1114 5449 8888 1774 9.58 138.49
Sheet 1 of 2
Annexure 4.2
2-Axle 3-Axle
S. No. Year Mini Bus Bus LCV MAV
Truck Truck
Growth Rate
7.2 8.3 10.4 8.6 8.6 8.6
(%)(2010-12)
Growth Rate
6.50 7.40 9.10 7.60 7.60 7.60
(%)(2013-17)
Growth Rate Yearwise Cumulative
5.70 6.60 8.00 6.60 6.60 6.60
(%)(2018-22) CSA in CSA in
Growth Rate million million
5.10 5.90 7.10 5.90 5.90 5.90
(%)(2023-27)
Growth Rate
4.70 5.40 6.40 5.30 5.30 5.30
(%)(2028-32)
Growth Rate
4.40 5.10 6.10 5.00 5.00 5.00
(%)(>2032)
VDF 0.46 0.46 0.56 4.90 4.10 3.10
1 2011 111 247 877 1283 902 336
2 2012 119 268 968 1393 980 365
3 2013 127 287 1056 1499 1054 393
4 2014 135 309 1152 1613 1134 422
5 2015 144 331 1257 1736 1220 455
6 2016 153 356 1372 1868 1313 489 2.33 2.33
7 2017 163 382 1497 2010 1413 526 2.51 4.84
8 2018 172 407 1616 2142 1506 561 2.68 7.52
9 2019 182 434 1746 2284 1606 598 2.86 10.38
10 2020 193 463 1885 2434 1711 638 3.05 13.43
11 2021 204 494 2036 2595 1824 680 3.25 16.68
12 2022 215 526 2199 2766 1945 724 3.47 20.15
13 2023 226 557 2355 2930 2060 767 3.68 23.83
14 2024 238 590 2522 3102 2181 812 3.89 27.72
15 2025 250 625 2701 3285 2310 860 4.13 31.85
16 2026 262 662 2893 3479 2446 911 4.37 36.22
17 2027 276 701 3099 3685 2590 965 4.63 40.85
18 2028 289 739 3297 3880 2728 1016 4.88 45.73
19 2029 302 779 3508 4085 2872 1070 5.14 50.87
20 2030 317 821 3732 4302 3024 1127 5.42 56.29
21 2031 331 865 3971 4530 3185 1186 5.71 62.00
22 2032 347 912 4225 4770 3354 1249 6.01 68.01
23 2033 362 958 4483 5009 3521 1312 6.32 74.33
24 2034 378 1007 4757 5259 3697 1377 6.64 80.97
25 2035 395 1058 5047 5522 3882 1446 6.97 87.94
26 2036 412 1112 5355 5798 4076 1518 7.33 95.27
27 2037 430 1169 5681 6088 4280 1594 7.70 102.97
28 2038 449 1229 6028 6392 4494 1674 8.09 111.06
29 2039 469 1291 6395 6712 4719 1758 8.50 119.56
30 2040 490 1357 6786 7048 4955 1846 8.93 128.49
Sheet 2 of 2