Sunteți pe pagina 1din 3

Insulation Procedure

1.0 Scope
1.1 This procedure covers the installation of insulation on piping, vessels, and equipment operating in hot
service or cold service. Underground piping is not covered by this procedure.

2.0 Codes and Standards


2.1 Contract documents
2.2 General specification provided by Owner.
PDOC-SP-MEC-014 - Specification for Insulation
ASME C533 Calcium Silicate Block and Pipe Thermal Insulation
ASME C547 Mineral Fibre Performed Pipe Insulation
ASME C612 Mineral Fibre Block and Board Thermal Insulation
Occupational Health and Safety Act

3.0 Material Control


3.1 All the material shall be verified as per material certification. Tag and nameplate being as per data
sheet.
3.2 Items quantity and size of the material shall be as per P.O. and drawings.
3.3 All materials supplied shall be new and undamaged.
3.4 All insulation material shall be properly stored and protected from moisture in accordance with
CONTRACTORS procedure PDOC-587B-PR-GEN-001 (Material, Handling Delivery And Storage
Procedure) for material's loading, unloading, storage and distribution.
3.5 Use of materials other than those specified requires OWNER'S approval.
3.6 Insulation materials containing asbestos or polyurethane shall not be used.

4.0 Insulation Preparation


4.1 Check the materials as 3.1~3.5 to ensure that the type of the material and thickness are in
accordance with relevant specification and drawings.
4.2 Insulation supervisor shall receive a copy of the pipe test acceptance to confirm that all the testing
such as hydrostatic, X-ray , etc. have been completed and released on all piping and equipment involved
4.3 All surfaces to be insulated shall be cleaned and primed, and remained dry before insulation to be
applied.
4.4 Inspect weather condition. Insulation shall not be installed during weather which might cause the pipe
or insulation to become wet when the surfaces are less than 5C above dew point. Insulation to be
installed over an extended period must be protected to ensure it remains dry until it has been properly
sealed.
4.5 Heating tracing shall be installed, tested and tagged in accordance with relevant specification and
drawings before insulation.
4.6 Insulation support installation shall be finished as required before insulation
4.7 Make sure that Insulation will not cover the face of gauge glasses, equipment name or data plates or
tags, nor be applied so as to interfere with dynamic parts of instruments or equipment.

5.0 Piping Insulation


5.1 Insulation Construction shall be performed after all the insulation preparation have been finished and
released.
5.2 Factory fabricated sectional pipe insulation shall be applied in staggered joint construction and
secured with wire loops or bands on 225 mm centers. On multiple layer construction, all joints shall be
lapped one-half of each section between layers. Each layer shall be secured separately. All joints shall be
securely butted and all cracks, joints, etc. shall be filled with insulating sealant as appropriate.
5.3 Mastic sealer shall be used around pipe supports where the insulation is punctured by the support.
5.4 Heat traced lines shall be insulated to completely cover both line and tracing.
5.5 Where insulation is required on the outside of piping, vessels or equipment that extends through an
exterior building wall or roof, the insulation shall not stop at the exterior of the building but shall be
extended for 300 mm inside the building.
5.6 Any cracks or openings that occur in the insulation or weather-proofing are to be filled in with
additional insulation or weather-proofing to provide a smooth sealed surface
5.7 At all flanges, unions, and pipe terminations, the pipe insulation shall be bevelled at a 45angle to
facilitate remove of flange bolts and union collars without damage to the main pipe insulation and metal
jacketing. A screwed and sealed metal cover shall be installed.
5.8 All openings in metal jacketing for nipples, pipe supports, etc. are to be neatly cut to provide a tight fit
and shall be thoroughly sealed and weather-proofed to prevent moisture from penetrating under the
jacket. Openings shall be fitted with a metal collar or suitable flashing embedded in sealant and screwed
firmly on place.
5.9 Insulation shall be covered with metal jacketing lapped a minimum of 50 mm on all seams and
secured with screws and bands, locating one band at each lap joint and spaced a maximum of 450 mm
on centre. Vertical jacketing shall be supported with S clips.
5.10 All insulation shall be clad with metal jacketing. Jacketing shall be installed so as to shed water and
protect against wind and blowing rain.

6.0 Insulation on Fittings, Flanges and Valves


6.1 Fittings shall be insulated with standard factory formed insulation and secured with wire loops or
bands, minimum two per section. All joints shall be filled with insulating sealant as appropriate. Insulation
shall be covered with pre-formed metal jacketing.
6.2 Insulation and jacketing on valves, flanges and unions shall be installed so as to be removable
without damage to the main pipe insulation.
6.3 Unless the piping is heat/electrical traced, valves, flanges and unions shall not normally be insulated
unless specified by OWNER. All other fittings are to be insulated.

7.0 Insulation On Vessels and Equipment


Make sure that all the insulation preparation have been finished and released.
7.1 Vessels Insulation
7.1.1 Vessels shells shall be insulated with factory fabricated insulation curved or grooved to fit the vessel
shell contour. If additional layers are required, insulation shall be installed with staggered joints.
7.1.2 Each layer shall be secured with bands; machine stretched, and fastened on 300 mm centres.
7.1.3 Insulation shall be clad with metal jacketing lapped a minimum 75 mm on all seams. Jacketing shall
be installed so as to shed water and protect against wind and blowing rain.
7.1.4 All openings in metal jacketing for man-ways nozzles, nipples, pipe supports, etc. are to be neatly
cut to provide a tight fit and shall be thoroughly sealed and weather-proofed to prevent moisture from
penetrating under the jacket. Openings shall be fitted with a metal collar or suitable flashing embedded in
sealant and firmly screwed place.
7.1.5 Jacketing shall be secured with metal screws on 150 mm centres on longitudinal seams and with
bands, located at lap and spaced on a maximum of 450 mm on centre.
7.1.6 Vessel heads shall be insulated in the same manner as the shell. Insulation shall be covered with
metal jacketing in a pie shaped or segmented arrangement.
7.1.7 Corrugated jacketing on vertical vessels shall be installed using the S clip method and lapped a
minimum of two (2) corrugations on vertical seams.
7.1.8 A band shall be placed adjacent to heads of horizontal vessels and at the top sheet on vertical
vessels to secure flashing between head and shell jackets.
7.1.9 Where insulation is required on the outside of piping, vessels or equipment that extends through an
exterior building wall or roof, the insulation shall not stop at the exterior of the building but shall be
extended for 300 mm inside the building.
7.1.10 Insulation and jacketing on exchanger flanges and heads shall be installed so as to be removable
without damage to the main shell insulation.
7.2 Equipment
7.2.1 For equipment of irregular shape, insulation shall be of the same type and thickness as specified for
vessels. Insulation and metal jacketing shall be installed so as to be removable.
7.2.2 Insulation cement, where required shall be applied in layers 20 to 25 mm thick. Every layer shall be
reinforced with steel mesh. The outer surface of the insulation cement shall be finished with a smooth
layer of finish cement.

8.0 The Detailed Insulation System


The detailed insulation system for hot service, cold service and personal protection and detailed material
status shall conform to the MR & Manual that shall be reviewed and approved by OWNER.

9.0 Quality Record And Inspection Report


9.1 All quality records and report shall be accepted by CONTRACTOR. QC engineer and the OWNERs
representative.
9.2 All quality inspection records shall be coincident with the insulation construction. The recorded
information shall be real and reliable.

10.0 Revision Note


This procedure shall be revised if it is found to be inadequate for purposed work upon completion of
engineering/new construction practice / new site information or as requested by OWNER.

S-ar putea să vă placă și