Sunteți pe pagina 1din 16

Pergamon Internattonal Journal of Project Management Vol. 15, No. 5, pp.

297-312, 1997
1997 Published by Elsevier Science Ltd. All rights reserved
Printed in Great Britain
0263-7863/97 $17.00+0.00

PII: S0263-7863(96)00082-8

Practices, barriers and benefits of


using risk management approaches
in selected Hong Kong industries

V M Rao Tummala*, H M Leung, C K Mokt, J F Burchett~ and


Y H Leung
Department of Manufacturing Engineering, City University of Hong Kong, Kowloon, Hong Kong

This paper summarizes and compares the current practices, the benefits realized and the barriers
faced in using risk management approaches based on the results obtained by conducting surveys
in building services cost estimation, public transportation and electricity supply industries in
Hong Kong. A few recommendations of overcoming the barriers in successfully implementing
and using risk management techniques are also suggested. 1997 Elsevier Science Ltd and
IPMA
Keywords: risk management,practices, barriers, benefits, selected industries, Hong Kong

1. Introduction assess the risks involved and risk adjustment is sometimes


Project management operates in a complex and dynamic made without real understanding of the inherent risks. Also,
environment that is constantly confronted with various as stated by Ho and Pike, the simple risk adjustment
risks and uncertainties. It is therefore imperative that methods could lead decision makers to accept decisions
project managers should identify all potential risk factors against their original attentions if the assumptions are not
affecting a given project, enumerate the consequences and clearly understood. 9 Furthermore, they rely heavily on
their severity, and assess their probabilities in order to single point estimates; consequently it is difficult to capture
develop response actions to control and manage the large uncertainties surrounding the project by using these
identified risks. The risk management approaches devel- single point estimates.
oped by Hertz and Thomas, and Hayes et al., provide In contrast, the probabilistic risk analysis techniques
effective frameworks to achieve this purpose.l'2 A number require rigorous analysis and are based on comprehensive
of successful studies reported in the literature support that awareness of the risks associated with critical variables and
risk management can increase quantitative information and their probabilities, and provide more quantitative informa-
knowledge on the risks inherent in a project and would lead tion about the risks inherent in a project. Some authors
to better decision outcomes. 3-8 assert that the greater the understanding of the precise
In practice, risk handling methods can be considered to nature and level of the risk, the better the decision and
fall into two categories: simple risk adjustment and ultimately, the firm's performance. 1"8 In-depth studies of
probabilistic risk analysis techniques. The simple risk firms using these methods suggest that management relies
adjustment techniques are based on intuitive and subjective heavily on risk analysis techniques for evaluating complex
adjustments to either the underlying cash flows or the strategic projects, and that corporate success can be partly
evaluation models, e.g. increasing the discount rate or attributed to the use of such approaches. Probabilistic
reducing the playback period for higher-risk projects. They analysis techniques include sensitivity analysis, basic
are easy to understand and apply, but they usually do not probability analysis, decision-tree analysis, Monte Carlo
simulation, and capital asset pricing method.
However, some of the literature studies and surveys
*On leave from the College of Business, Eastern Michigan University, reported indicate that probabilistic risk analysis is not
Ypsilanti, MI, USA. widely accepted in capital investment projects. As pointed
~'Currently employed as Budding Services Engineer m Architectural out by Hall, many managers refuse to use risk analysis
Services Department,Hong Kong Government,Hong Kong. because there is little evidence that use of risk analysis can
:~Currently employed as Semor Transmission Contracts Engineer, China
Light and Power CompanyLimited (CLP), Hong Kong. improve corporate profitability. 1 In a survey of financial
Currently employed as Mechanical Engineer, Mass Transit Railway modeling users in the UK, McGregor found that only about
Corporation (MTRC), Hong Kong. 10% of the firms used probabilistic risk analysis in making

297
Practices, barriers and benefits of risk management: V M Rao Tummala et al.

investment decisions. He further pointed out that the major Kong industries. ~6 Also, this would enable us to develop a
problems in building risk-analysis models were lack of comparative analysis of the three industries. Before we
sufficient data, difficulties in obtaining probability esti- develop a comparative analysis, we shall first summarize
mates and understanding probability concepts, correlation the survey results of each industry with respect to current
assumptions between variables and across time, and practices and their reasons, barriers faced and benefits
understanding of the output information. 11 realized of using risk management approaches.
Another survey of large-sized firms in UK was
conducted in 1989 by Ho and Pike to determine the extent
and variety of techniques used in risk analysis for capital 2. Risk management practices for cost estimation
budgeting. 12 The results of this survey show no evidence in building services
that the adoption of probabilistic risk analysis can lead to a In order to examine the current practices adopted, and to
significant change in relative capital expenditure and obtain an insight into the understanding, use and applica-
profitability within firms. Ho and Pike further pointed out tion of risk management process in preparing building cost
that the major reason for the lack of acceptance of risk estimates, Mok conducted a survey involving 120 building
analysis is that it is marred by some inherent and service engineers who are responsible for cost estimation in
implementation problems still to be resolved. Indeed, the the Building Service Branch of Architectural Services
findings revealed that the limitations frequently found in Department, Hong Kong Government, and eleven private
the application of risk analysis are obtaining input consulting firms who are known to do the work for Building
estimates, and managers' inadequate understanding of the Services Branch. 13 Of these, 52 completed questionnaires
risk analysis approach. The major problem is that managers were returned with a response rate of 43.3%. In fact, 48% of
simply lack the required knowledge to apply formal the respondents are from Building Service Branch and the
technique, or are unable to find an approach which is other 52% are from private firms. 13 The job titles of the
systematic, easy to apply and cost effective. 12 respondents covered a wide range and varied from assistant
More recently in 1994, three surveys were conducted in engineer to director, even though the majority of the
Hong Kong industries to examine the local practices of risk respondents were project engineers or engineers. Over 57%
management. The industries include building services, of them have more than 5 years' experience in preparing
electricity supply, and public transportation. 13-15 The cost estimates which indicates that the respondents are very
survey in building services industry was conducted by experienced in preparing building services cost estimates.
Mok to examine the current practices in preparing building About 22.4% of the respondents worked for small finns
services cost estimates. 13 Similarly, the survey in the with less than 100 employees and 61.2% were from medium
electricity supply industry was conducted by Burchett to firms with 100-5000 employees. The remaining 16.3%
examine the risk management practices in capital budget- worked for large firms with 5000 or more employees. From
ing. 14 The survey in the public transportation industry is these characteristics of the respondents and their firms, it
related to using risk management approaches in project can be assumed that the sample provides a realistic profile to
appraisal and selection which was conducted by Leung. 15 represent the general practices of cost estimation currently
The electricity supply industry survey was conducted used as well as the general views on the use of risk man-
worldwide including Hong Kong while the other two agement process within the Hong Kong building services
surveys were conducted with respect to Hong Kong industry.
companies. The reason for the worldwide survey is due
to the fact that there are only two utility companies in Hong 2.1. Current practices of building services cost estimation
Kong and one of them did not participate in the survey for Figures 1-3 summarize the current building services cost
confidentiality reasons. estimation practices adopted by the respondents. The
The purpose of this paper is to provide a comparative respondents were asked on a six-point scale (Never= '1',
analysis of the three surveys findings to obtain an insight R a r e l y = ' 2 ', L i t t l e = ' 3 ' , Sometimes='4', O f t e n = ' 5 ' and
into the understanding of the current risk handling Very Often = '6'), the extent to which the responding firms
practices, and find out the difficulties and problems to use each of the risk analysis techniques. With respect to
successful implementation of risk management approaches deterministic vs. probabilistic techniques used, the respon-
in the selected Hong Kong industries. In addition, some dents in the building services industry indicated that 53%
possible suggestions to bridge the gap between theory and use deterministic methods often or very often (see Figure
practice are also discussed. Since Hong Kong is one of the 1). The probabilistic techniques are used by about 19% of
dominant global competitive partners, the results of the
analysis would be beneficial to Hong Kong and to its global %
partners in terms of understanding the practices, the 20 40 60 80 100
benefits realized and the barriers faced in using risk
management approaches, and developing strategies to Deterministic
overcome the identified barriers. The words risk analysis, Methods
probability risk analysis, risk management and risk
management process are used interchangeably in this paper
to mean the same approach. Probabilistic
Since the three surveys were conducted at the same time, Methods
Burchett, Leung and Mok used a survey instrument which
is similar to the one used by Ho and Pike, but tailored to
satisfy their survey purposes so that a broader under- I Sometimes [ ] Often [ ] Very Often ]
standing of risk management practices, and the problems
and difficulties faced in applying risk management
approaches can be obtained among the selected Hong Figure 1 Cost estimation methods used

298
Practices, barriers and benefits of risk management." V M Rao Tummala et al.

0 20 40 60 80 1 O0

Single-figure (most likely)


estimates

Three-point estimates

Range of estimates with


the probabilities

Figure 2
I 1 Sometimes [ ]

Presentation of cost estimates


Often [] VeryOften I

the respondents often or very often. Thus the deterministic p o r t a n t = ' 5 ' ) . The respondents indicated that both
techniques are found to be the most popular techniques that government and commercial projects as important reasons
are used by building services engineers in preparing for using risk management approaches with 82% and 66%
building services cost estimates. of the respondents, respectively, indicating somewhat
As shown in Figure 2, the use of single-figure (most important to very important. Of these two, they felt
likely) estimates is found to be the most popular method government projects as the more compelling reason for
relative to the use of three-figure or range of estimates as using risk management approaches.
the respondents indicated their use often or very often with Over 96% of the respondents agreed that risk manage-
75%, 6% and 9%, respectively. Similarly, the use of ment is somewhat important to very important for projects
subjective or intuitive assessment (with 47% indicating its of costs above HK$100 million. Also, it is interesting to
use often or very often) is found to be more popular than observe that the perception of using risk management is
the use of sensitivity analysis (with 8%) or risk manage- increasing with the size of the projects. About 94% of the
ment process 9with 2%). Thus the sensitivity analysis and respondents believed that risk management is somewhat
risk management process are rarely used in assessing risks important to very important for 'very complex' projects.
and uncertainties in building services cost estimation. Similarly about 88% indicated the use of risk management
for 'complex' projects. As for contract types, about 76%,
2.2. Reasons for using risk management 65% and 68,5 of the respondents viewed that using risk
Four major categories of projects like government vs. management as justified for "Cost Reimbursement",
commercial, size, technical complexity and contract types "Schedule of Rates" and "Approximate quantities" types
are considered in examining the reasons for using risk of contracts, respectively. As in the case of size of projects,
management approaches. Within each of these categories, the use of risk management approaches is perceived to be
several subcategories are considered as shown in Figure 4. more important as the technical complexity of projects is
Respondents were asked to indicate how much they agreed increasing. The same is true for contract types in terms of
or disagreed with each item (Very Unimportant='l', complexity.
Somewhat Unimportant = '2', Neither Important Not Un- Simple correlation analysis was conducted to assess the
important= '3', Somewhat Important='4' and Very Im- relationship between the characteristics of a project and

0 10 20 30 40 50 60 70 80

No explicit allowance

Subjective or Intuitive
assessment

Sensitivity analysis

Risk Management Process

I t Sometimes [ ] Often [ ] Very Often

Figure 3 Methods used to assess risks and uncertainties in cost estimation

299
Practices, barriers and benefits of risk management." V M Rao Tummala et al.

Tvpe of Proiect
l [~ SomewhatImportant [ ] Very Important

Government project ,~,~\\.\\\\\\\\\\\"


\\~. ~'%\\\\\\\'%\\\~ ~\\\~%.\\XXX\'\\'~.,%X\\\\\.\\\\",.\\\'~~\~\\NN\~\\NX%~ I
1 I
Commercml project x~N~\~\\\\\\\\\~ x%.\\\\~\\\\\\\~ ~\\\\\\\\\\\\\\\"~ ~\\\\\\\\\\\\\\'~ ~\'~1 ]

SiZe of Project
Below HK$10 mdhon ~\\\\\~\\\\'\\~.

HK$10 - 50 mdhon ~\~\\\\N~\\N~\\~


i

HK$ 50 - 100 mdhon ~\\\\\N~\\\~\\'~

Above HK$100 million ~\\\\\\\.\~\~ t


Technical C o m p l e x i t y
Very complex ~.\~\\\\\\\\\\~
1 I I
I
Complex ~\\\\\N\\N\\\\'N ~,,NN\N~\~\\"N~ N~\~NNN
Average
Simple ~\\\\\\N.\\\\\\\\~, ~\\\~\XXNNN\\\\\~~\\\%.X~ I

Very simple ~\~\\\\~ ~\\%,\%.\\\\\\"~1 I

Contract Tvnes
I
Type B ,,%,\\\\\'%\\\\\\'~
1
Type C ~.\-~,,\\\~.\\\\\'~ ~\\\\\\XX~\\\~\'~~\X\\\X\\\\\\\\~ ~\\\\\~\\\%,X\\~~\\\\\\\\\\~ ]
I I
Type D ~\\~\\~\~\\"~
I I
Type E .~\\\\~N,\\\\\\\\\~

10 20 30 40 50 60 70 80 90 100
%

T y p e A : Lump sum contract based on drawings and specification


T y p e B : Lump sum contract based on bill of quantities
Type C : Measurement contract based on bill of approximate quantities
Type D : Measurement contract based on schedule of rates
Type E : Cost reimbursement contracts

Figure 4 Reasons for using risk m a n a g e m e n t (budding services)

different risk management methods used. We expect that asked the extent to which "inherent problems" and "bar-
the characteristics of the project are major factors that riers to implementation problems" were encountered on a
would affect what type of risk management method should five-point scale (Strongly D i s a g r e e = ' l ' , Disagree='2',
be chosen. However, the results of the correlation analysis Neutral = '3', Agree = '4' and Strongly Agree = '5'). The
indicated that there is no strong relationship between inherent problems include: 13
different risk management techniques and characteristics of AI: Difficulty in obtaining input estimates and
a project. ~3 In the current practices, the risk management is assessment of their probabilities;
not significantly employed in large projects. On the A2: Time involvement;
contrary, the risk management (Sensitivity Analysis and A3: Difficulty in understanding and interpreting out-
Risk Management Process) is significantly employed in the comes of risk management process;
projects for which the technical complexity is very simple. A4: Managers cannot agree on quantification of
This is somewhat surprising as we expect the contrary. This uncertainty/subjective probability assessment;
indicates that risk management is not well understood by A5: Cost-justification of risk management process
the respondents in Hong Kong. It can also explain why the techniques.
risk management is not widely accepted in the current
practice. We believe that there are some barriers existing in As shown in Figure 5, about 78% of the respondents
the current practices. These barriers can occur both in the agreed or strongly agreed that 'time involvemnet' and
organization itself and in its management. They are also difficulty in obtaining input estimates and assessment of
related to the questions of resources, knowledge and tools their probabilities will affect successful application of risk
used as discussed in the next section. management. Similarly, about 62% of the respondents
agreed or strongly agreed that there will be difficulty in
2.3. Barriers to successful implementation of risk management understanding and interpreting outcomes of risk manage-
From the literature review, a number of barriers in using ment process and 58% of them questioned about cost-
risk management were found. 7'1'12 The respondents were justification of risk analysis techniques. In addition, 46% of

300
Practices, barriers and benefits of risk management: V M Rao Tummala et al.
%
10 20 30 40 50 60 70 80
' I

A1

A2 m I

A3 M I

A4

A5 ............................. .....................................................

[[m Agree [--]StronglyAgree I


Figure 5 Inherent problems encountered (building services)

the respondents felt that managers cannot agree on quan- 2.4. Factor analysis of barriers to successful implementation
tification of uncertainty/subjective probability assessment. of risk management
Similarly, the "barriers to implementation problems" The barriers to successful implementation of risk manage-
include: 13 ment can be further analysed through factor analysis by
identifying a relatively small number of factors that can be
B 1: Lack of middle managers/supervisors support; used to represent relationships among sets of many inter-
B2: Managers' understanding of risk management related variables. ~7 Table 1 shows the rotated factor matrix
process techniques; for the inherent problems encountered. The first factor
B3: Lack of top management support; shows positive correlation with problems A1, A2 and A3.
B4: Human/organizational resistance to change; These inherent problems include "difficulty in obtaining
B5: Lack of computing resources and assistance. input estimates and assessment of their probabilities",
"time involvement" and "difficulty in understanding and
For implementation problems encountered, Figure 6 interpreting outcomes of risk management process". The
shows that about 56% and 60% of the respondents, second factor is positively correlated with problems A4,
respectively, agreed or strongly agreed that managers' and A5 which include "managers cannot agree on
understanding of risk management techniques and human/ quantification of uncertainty/subjective probability assess-
organizational resistance to change are the problems that ment" and "cost-justification of risk management process
need to be overcome. Similarly, about 53% of respondents techniques".
agreed or strongly agreed that lack of computing resources Similar analysis was repeated for the implementation
and assistance will affect the implementation of risk problems encountered. Table 2 shows the corresponding
management. Only 37% and 41% of the respondents, rotated factor matrix. The first factor shows positive
respectively, felt that lack of top management support and correlation with the questions B1, B3, B4 and B5,
lack of middle managers/supervisors support will be respectively. These implementation problems include
problems in implementing risk management. "lack of middle managers/supervisors support", "lack of
%
0 10 20 30 40 50 60 70

B1 'i
B2

B3 ~\",~ I
B4

B5 J,
I

[ ] Agree [ ] Strongly Agree

Figure 6 Implementation problems encountered (building services)

301
Practices, barriers and benefits of risk management." V M Rao Tummala et al.

Table 1 Rotated factor matrix (inherent problems encountered) Table 2 Rotated factor matrix 0mplementation problem encountered)

Factor 1 Factor 2 Factor 1 Factor 2


AI 0.83528 -0.04610 BI 0.84122 0.22976
A2 0.73453 0.11718 B3 0.76646 -0.09304
A3 0.54072 0.42286 B4 0.71714 -0.20559
A4 -0.02818 0.83884 B5 0.66722 0.10699
A5 0.18848 0.80701 B2 0.00827 0.97917

top management support", "human/organization resistance risks inherent in a project in order to develop response
to change" and "lack of computing resources and assis- actions, and that it would lead to increase the confidence in
tance". The second factor is only positively correlated with decision making.
question B2, which includes "managers' understanding of
risk management process techniques".
3. Risk management practices in public
2.5. Perception of benefits of using risk management transportation industry
The respondents were asked to indicate their perception of A survey involving Hong Kong public transportation com-
benefits of using risk management on a five-point scale (To panies was conducted by Leung. is He has selected and
a very lettle extent= '1', To a little extent = ' 2 ' , To some mailed 50 questionnaires to engineers and managers of
extent = ' 3 ' , To a great e x t e n t = ' 4 ' and To a very great major transportation companies in Hong Kong including
extent = '5'). The results are summarized in Figure 7. Mass Transit Railway Corporation (MTRC), Kowloon
The major benefits perceived by the respondents are Canton Railway Corporation (KCRC)--Heavy Rail Divi-
summarized as follows: sion, KCRC--Light Rail Division, Kowloon Motor Bus,
China Motor Bus and Hong Kong Tramway. These 50
allows judgement and intuition in decision making to be individuals were selected mainly on the basis of their
presented in a meaningful way; experiences and accessibility of project managers and pro-
provides a systematic and logical approach to decision ject engineers as a representative sample of the transporta-
making; tion industry in Hong Kong. Of these, 36 completed
makes it easier in interpreting the cost estimates; questionnaires, representing a return rate of 72%, were
enables the decision maker to confront risk and returned.
uncertainty in a realistic manner;
provides a few guidelines to aid problem formulation; 3.1. Current practices of assessing risks
is useful for complex decision problem; Figure 8 summarizes the risk analysis techniques used by
permits a thorough analysis of alternative options. the practicing managers in project appraisal and selection.
The respondents were asked on a six-point scale
From these findings, we find that most of respondents ( N e v e r = ' l ' , R a r e l y = ' 2 ' , L i t t l e = ' 3 ', S o m e t i m e s = ' 4 ' ,
believe that risk management can provide a realistic and O f t e n = ' 5 ' and Very Often = '6'), the extent to which the
systematic approach to obtain more information on the responding finns use each of the risk analysis techniques.

1 Provides a systematic and logical approach to


decision making
Permits a thorough analysis of altematMve
2
options
3 Enables the decision-maker to confront risk m
a realistic manner

4 Helps communication within the organization

Allows decision-maker to judge how much


5
information to gather in a decision problem
6 Allows judgment and intuition in decision
making to be presented in a meaning way

7 Provides a few guldehnes to aid problem


formulation

8 Is useful for complexdecis=on problem

9 Is accepted by members of orgamzation

10 Is easy in obtaining probability assessments

11 Makes it easier in interpreting the output of the


risk analysis process

0 10 20 30 40 50 60 70 80 9
%

I t To a some extent [ ] To a great extent [ ] To a very great extent

Figure 7 Perceived impact of risk management (building services)

302
Practices, barriers and benefits of risk management: V M Rao Tummala et al.
%
10 20 30 40 50 60 70 80 90 100

No explicitassessment

Subjectiveor Intuitive
assessment

Sensitivityanalysis

Risk discounted cash flows

Hertz type simulation

Risk ManagementProcess

I BB Sometimes [] Often [ ] Very Often I

Figure 8 Use of risk assessment techniques(public transportation)

Among the various techniques listed, sensitivity analysis agement approaches. Respondents were asked to indicate
and risk discounted cash flow analysis are found to be the how much they agreed or disagreed with each item as in the
most commonly used techniques. The subjective or case of building services cost estimation. Analysis of these
intuitive assessment (analyzed by assessing project risk as results indicate that the size of a project (89%) and
low, medium or high level etc.) is the next most commonly complexity of projects (75%) are the most important
used technique with about 72% using them often to very factors in the utilization of risk analysis (somewhat
often. The least popular techniques are found to be Hertz- important to very important). Introducing new product
type risk simulation (about 43%, followed by the risk (41%), avoiding delay (33%) and initiating long payback
management process (about 33%). period (34%) are also found to be the next important
reasons in preferring risk analysis. However, new market
3.2. Reasons for using risk management (23%) and client's requirements (28%) are identified as
Figure 9 summarizes the main reasons for using risk man- least popular reasons for using risk analysis techniques) 5

%
0 10 20 30 40 50 60 70 80 90
I I I
Size of project ~ / ~ ~ ~
I
Complexity of [
,,,-oje=
,,,ew,.o.uc.

Newmarket ~ ~ I

period
Client's "
requirement J'~J ~ i

I [ ] Somewhat Important [] Very Important

Figure 9 Reasonsfor using risk management(public transportation)

303
Practices, barriers and benefits of risk management." V M Rao Tummala et al.

0 10 20 30 40 50 6O 7O 80
i t I

A1 ~ ~ ~ I

A2 ~ ~ ~ ~ I

A4 ~%.~.~ ~ ~ ~ ~ ~.~

A5 I
I~-~ Agree [] Strongly Agree

Figure10 Inherentproblemsencountered (public transportation)

In order to assess the relationship between the risk lems" and "barriers to implementation problems" were
analysis methods used and the reaons of using risk encountered on a five-point scale ranging from "strongly
management, a number of simple correlation coefficients disagree to strongly agree". Figures 10 and 11 summarize
were found. Based on this information, we concude that the respondents' views on the barriers to successful im-
sensitivity analysis is positively correlated with the size of plementation of risk management. The "inherent problems"
project. On the contrary, Hertz type simulation and risk include: 15
management process are not positively correlated with any
AI: Difficulty in obtaining input estimates and
of the listed reasons of using risk analysis. 15 This appears
assessment of their probabilities;
contrary to the results stated above regarding the use of
A2: Time involvement;
Hertz-type risk simulation and risk management process.
A3: Difficulty in understanding and interpreting out-
From these results, we may concude that risk management
comes of risk management process;
approaches are not widely used in project appraisal and
A4: Managers cannot agree on quantification of
selction in the Hong Kong public transportation industry.
uncertainty/subjective probability assessment;
The analysis on the barriers to successful implementation is
A5: Cost-justification of risk management process
described in the next section.
techniques.
3.3. Barriers to successful implementation of risk
Among these inherent problems, about 75% of the
management
respondents perceived the problem of obtaining input
As in the case of building services industry survey, the estimates and assessment of their probabilities is found to
respondents were asked the extent to which "inherent prob- be the most serious problem. As perceived by 72% of the
%
0 10 20 30 40 50 60 70 80

B3 ~ l I

BS

B6 ~ ~ ~ ~ ]

B7 ~ ,~N.'%~%.'~~ . ~ ~..~x~ ~-'~ ~-x,~l

B8 ~ ~%~-~ ~ ~ ~-%_'%.~ I

I Ira Agree [ ] Strongly Agree

Figure11 Implementationproblems encountered (pubhc transportation)

304
Practices, barriers and benefits of risk management: V M Rao Tummala et al.

respondents, the second serious problem is managers Table 3 Rotated factor matrix (inherent problemsencountered)
cannot agree on quantification of uncertainty/subjective Factor 1 Factor 2
probability assessment. About 47% of the respondents
perceived excessive time involvement is the next barrier. A4 0.88181 0.00682
Similarly, 44% of the respondents perceived that difficulty A1 0.82735 -0.08126
A5 0.58173 0.30205
in understanding and interpreting outcomes as another
A3 -0.01939 0.82667
barrier, and 31% of the respondents questioned about the A2 0.08936 0.70131
cost-justification of risk management process techniques.
Similarly, the barriers to implementation problems
include: 15
with statements of negative or unfavorable impacts, more
B3: Lack of top management support; people indicated their disagreement rather than agreement.
B4: Human/organizational resistance to change; For example, 42% of the respondents perceived from 'very
B5: Lack of computing resources and assistance; little extent' to 'little extent' while only 25% perceived
B6: Finding suitable risk management methods; from 'great extent' to very great extent' regarding the
B7: Non-availability of acceptable risk standards; benefit of risk management in lowering the capital
B8: Lack of training in risk management process. investment. Similarly, regarding the benefit of risk manage-
Figure 11 indicates that 73% of the respondents are ment in making it difficult to accept good proposal, 50% of
concerned with the non-availability of acceptable risk the respondents disagreed while only 25% agreed] 5 Thus,
standards. About 55% perceived that human/organization the majority of respondents agreed that risk management is
resistance to change as the next problem. Lack of training particularly useful for providing an insight into the project
in risk management process (53%) and finding suitable risk decision, and increasing the chance of the project's success.
management methods (47%) are the next important areas of
concern for implementation. The findings also indicate that 4. Risk management practices in electricity supply
relatively few managers suffer from lack of top manage- industry
ment support (only 17%) and availability of computing
resources and assistance (only 9%). As mentioned earlier, a questionnaire was prepared for
issue to electric utilities worldwide to obtain an insight into
3.4. Factor analysis of barriers to successful implementation their understanding, use and application of risk manage-
of risk management ment approaches in the evaluation of capital budgets and
The factor analysis related to the inherent problems examine the barriers to successful implementation of risk
encountered indicated two factors as shown in Table 3. management in electricity supply industry. 14 A question-
The first factor shows a positive correlation with the naire was mailed to senior managers by name of 140
problems A4, A1 and A5, which include "managers cannot electric utilities worldwide, who were considered suffi-
agree on quantification of uncertainty/subjective proba- ciently able to coordinate and collect the information
bility assessment", "difficulty in obtaining input estimates necessary for each type of question. Thirty questionnaires
and assessment of their probabilities" and "cost-justifica- were received with a response rate of 21.5%.
tion of risk management process techniques". The second
factor is positively correlated with problems A2 and A3, 4.1. Current practices of risk management and assessment
which include "time involvement" and "difficulty in
The respondents were asked on a six-point scale
understanding and interpreting outcomes of risk manage-
(Never = ' 1', Rarely = '2', Little = ' 3 ' , Sometimes = '4',
ment process".
O f t e n = ' 5 ' and Very O f t e n = ' 6 ' ) , the extent to which
With respect to implementation problems, the first factor
responding finns use each of the risk analysis techniques.
shows positive correlation with problems B3, B7 and B4 as
Among the various risk analysis methods listed, sensitivity
shown in Table 4. These problems include "lack of top
analysis was found to be the most commonly used
management support", "non-availability of acceptable risk
technique, with almost 60% using often to very often (see
standards", and "human/organizational resistance to
Figure 13). The next popular techniques were subjective or
change". The second factor shows positive correlation
intuitively assessment and three-point estimates with about
with problems B5 and B8, which include " l a c k of
43% and 26%, respectively. Indeed, these risk analysis
computer resources and assistance" and "lack of training
techniques require the use of subjective information and
in risk management process". The third factor is only
judgement, and is therefore found by managers to be
correlated with problem B6 which is "finding suitable risk
reliable and easy to use. It is found that about 37% of
management methods".
respondents use probability distributions in cash flows and
3.5. Perception of benefits of using risk management expected values. Other more advanced techniques, such as
risk management process and capital asset pricing models
The respondents were asked to indicate their perception of
the benefits of using risk management on a five-point scale
(To a very little e x t e n t = ' l ' , To a little e x t e n t = ' 2 ' , To Table 4 Rotated factor matrix 0mplementatlonproblemsencountered)
some e x t e n t = ' 3 ' , To a great e x t e n t = ' 4 ' and To a very Factor 1 Factor 2 Factor 3
great e x t e n t = ' 5 ' ) . Eight specific items covering both
positive and negative impacts were used in the question- B3 0.82119 0.7669 -0.02341
naire. The results are summarized in Figure 12. B7 0.67691 -0.40071 0.51954
B4 0.59314 -0.20628 0.17824
The survey findings show that the majority of respon-
B5 0.27742 0.85214 0.23876
dents are reasonably happy with their use of risk manage- B8 -0.41257 0.80468 -0.16104
ment. In general, more people agreed rather than disagreed
B6 0.7790 0.10783 0.95443
with statements of a positive or favorable impact. However,

305
Practices, barriers and benefits of risk management." V M Rao Tummala et al.

0 10 20 30 40 50 60 70 80 90
Positive Impacts
Provides a good insight
mL J --]
Increases the chance of success
I
Improves effectiveness of
investment decision m
Enhances communication among
managers m mmm
Reduces implementation time
m m m m J
Negative Imoacts

Makes difficult to accept good


proposal

Lowers capital investment

Reduces manager enthusiasm to


generate proposals

[ ] To a Some Extent [ ] To a Great Extent [ ] To a Very Great Extent

Figure 12 Perceived impact of risk management (pubhc transportation)

(CAPM) are rarely used, with only about 10% and 18% Very Often = '6') to indicate the extent to which they used
using often to very often, respectively as shown in Figure the risk analysis techniques. For easy comparison with the
13. These findings reveal that the advanced risk analysis results as described in Sections 2.2 and 3.2 in which a five-
techniques are highly developed in theory, but have not point scale was used, we combined score 5 with score 6 to
been in widespread use in major firms. A pilot study using become a scale of 'Very Important', and score 4 to become
the same questionnaire was conducted in China Light and a scale of 'Somewhat Important'.
Power Ltd, Hong Kong, and found similar comparative Figure 14 shows that the size of project (89%) and
results in the use of risk analysis techniques. 14 complexity of project (85%) are the most important factors
in the utilization of risk analysis (somewhat important to
4.2. Reasons for using risk management very important). Avoiding project delay (74%), determin-
As in the other two situations, this survey also examines the ing payback period for a project (64%), evaluating new
reasons for utilizing the risk analysis techniques. Respon- product development (64%), and avoiding cost overrun
dents were asked to use the six-point scale (Never = '1', (66%) are found to be the next important reasons of using
R a r e l y = ' 2 ', Little='3 ', S o m e t i m e s = ' 4 ', O f t e n = ' 5 ' and risk analysis techniques. New market (57%) and client

%
0 10 20 30 40 50 60 70 80 90

No explicit assessment

Subjective or intuitive
assesmnt

Three point estimates

Sensitivity analysis

Probability distributions in
cash flow

CAPM

Risk Management Process

I l l Sometimes [ ] Often [ ] Very Often

Figure 13 Use of risk assessment in capital investment decisions (electricity supply)

306
Practices, barriers and benefits of risk management." V M Rao Tummala et al.
%
0 10 20 30 40 50 60 70 80 9O

I I I i L I
Size of Project ~ M m]i
Complexity of project
I I I i I
New product
I I 1
New market
I I I
Deterring payback period I I I I
Client requirement
I I I
Potential for project I
delay

To avoid cost overrun I ' ~ , ~ ~'~\~,'~ ~.~'~


I t I

m Somewhat Important [ ] Very Important

Figure14 Reasonsfor using risk management (electricity supply)

requirement (59%) are identified as the less popular reasons sponsors, who may consider that uncertainty of a capital
for using risk analysis techniques. 14 investment needs further attention.
A number of correlation coefficients were found to
assess the relationship between the use of risk analysis
4.3. Barriers to successful implementation of risk
management
techniques and the reasons for using it. 14 The correlation
analysis demonstrated a wide use o f different risk As in the earlier two surveys, Figures 15 and 16 summarize
assessment tools but of particular interest is the require- the respondents' views on problems for successful
ments of the project sponsor which shows no correlation implementation of risk management approaches. The
with sensitivity analysis but a positive and significant respondents were asked the extent to which "inherent
correlation with risk management approaches. Also, it problems" and "implementation problems" were encoun-
indicated a wide use of probability distributions for net tered on a six-point scale. For easy comparison with the
cash flows and producing expected value of NPV, which results as described in Sections 2.3, and 3.3 where a five-
provides support for growing popularity of the use point scale was used, we combined score 4 with score 5 to
probability distributions and related analysis in risk become a scale o f " A g r e e " , and score 6 to become a scale
assessment. Thus sensitivity analysis and probability of "Strongly Agree". The inherent problems include: 14
distributions are applied generally and widely advocated,
wherease risk management techniques appear to be applied * A I : Difficulty in obtaining input estimates and
to meet specific demands which are of concern to project assessment of their probabilities;

0 20 40 60 80 100
A1

A2

A3 I

A4

A5 ~ I

A6 I

[[] Agree [] Strongly Agree

Figure15 Inherentproblems encountered(electricity supply)

307
Practices, barriers and benefits of risk management: V M Rao Tummala et al.

o lO 20 30 40 50 60 70

B2

B3

B4

B6

B6

[ [] Agree [ ] Strongly Agree

Figure 16 Implementation problems encountered (electricity supply)

A2: Time involvement; 4.4. Factor analysis of barriers to successful implementation


A3: Difficulty in understanding and interpreting out- of risk management
comes of risk management process; Table 5 shows that two factors are identified to represent
A4: Managers cannot agree on quantification of un- relationships among the six items or variables used for
certainty/subjective probability assessment; inherent problems encountered. The first factor shows
A5: Cost-justification of risk management process positive correlation with the A3, A4 and A5. These inherent
techniques; problems include "difficulty in understanding and inter-
A6: Difficulty in determining tradeoff between risk and preting outcomes of risk management process", "man-
return. agers cannot agree on quantification of uncertainty/
subjective probability assessment" and "cost-justification
As regards inherent problems (Figure 15), about 85% of of risk management process techniques".
the respondents agreed or strongly agreed that time Similarly, the second factor is positively correlated with
involvement is the most important problem. As perceived A6, A1 and A2 as shown in Table 5, which include
by 77% of respondents, the second most important problem 'difficulty in obtaining input estimates and assessment of
is difficulty in obtaining input estimates and assessment of their probabilities', and 'time involvement'. With respect to
their probabilities. About 76% of them found that managers implementation problems, it appears that all of the above
cannot agree on quantification of uncertainty/subjective mentioned problems (B2-B6) would affect implementation
probability assessment. Similarly, 65% of the respondents as they are not positively correlated with any factor.
felt that it is difficulty to determine the tradeoff between
risk and retum and 62% of the respondents perceived that 4.5. Perception of benefits of using risk management
there is difficulty in understanding and interpreting out- As in the earlier two surveys, the respondents were asked to
comes of the risk management process. In addition, about indicate their perception of benefits of using risk manage-
58% of the respondents questioned about the cost- ment on a five-point scale (To a very little extent =` 1', To a
justification of risk management process techniques. little e x t e n t = ' 2 ' , To some e x t e n t = ' 3 ' , To a great
Similarly, the "barriers to implementation problems" extent= '4' and To a very great extent = '5'). The results
include: 14 are summarized in Figure 17. The majority of respondents
perceived that the major benefits brought about by using
B2: Managers understanding of risk management risk management include "provides a useful insight into
process techniques; the project", "increases confidence in investment deci-
B3: Lack of top management support; sions", "increases quality of investment decisions",
B4: Human/organizational resistance to change; " m a k e s it easier to accept proposals", " i m p r o v e s
u B5: Lack of computing resources and assistance; efficiency of investment decisions", "enhances commu-
* B6: Finding suitable risk management methods. nication among managers", and "improve ultimate project
performance". From these results, it can be seen that the
For implementation problems encountered, Figure 16
shows that 68% of respondents felt that human/organiza- Table 5 Rotated factor matrix (inherent problems encountered)
tional resistance is the most important problem. About 67%
Factor 1 Factor 2
and 60% of the respondents, respectively, agreed or
strongly agreed that finding suitable risk management A3 0.86972 0.26957
methods and managers' understanding of risk management A4 0.85232 -0.08856
techniques are the other barriers. In addition, 40% and 24% A5 0.71275 0.54290
of the respondents, respectively, felt that lack of top A6 0.15599 0.85931
A1 0.49789 0.74415
management support and lack of computing resources and
A2 0.02064 0.74134
assistance are the problems which need to be overcome.

308
Practices, barriers and benefits of risk management: V M Rao Tummala et al.

0 10 20 30 40 50 60 70 80 90 100

Provides a useful insight into the


project
Improves quality of investment
decisions
Increase confidence in investment
decision
Improves efficiency of investment
decisions
Enhances communication among
managers
Improves ultimate project
performance
Makes it more easier to accept
proposals
Increases managers' enthusiasm
to generate/sponsor projects

Leads to lower capital expenditure

l [] To Some Extent [ ] To a Great Extent [] To a Very Great Extent

Figure 17 Perceived impact of risk management (electricity supply)

respondents consider risk management very useful; they inherent and implementation problems. As shown in Table
believe that risk management can provide more informa- 6 which summarizes the survey results obtained, all the
tion and increase confidence in the final decision making. three industries show that: (1) obtaining input information;
(2) human/organizational resistance to change; (3) time
involvement; (4) understanding and interpreting outcomes
5. Discussion and conclusions of risk management process; (5) quantification of un-
From the analysis of the results of the three surveys, we certainty/subjective probability assessment; and (6) cost-
conclude that the simple risk adjustment methods are still justification, are the major limitations in applying risk
adopted in three local industries in Hong Kong. The most analysis. Finding suitable methods of risk management
popular techniques used among the three industries in risk appears to be another roadblock for public transportation
management are the subjective or intuitive assessment and and electricity supply industries, whereas non-availability
sensitivity analysis. Risk discounted cash flows is very of acceptable risk standards and lack of training in risk
popular in public transportation and electricity supply management techniques are found to be two major barriers
industries. Use of three point estimates appears to be very in the public transportation industry.
popular in electricity supply industry. Indeed, decision With respect to inherent problems encountered, it
makers will find that these methods are easy to use due to appears that the time involvement of using risk manage-
their simplicity and use of subjective information and ment seems to worry most practitioners in building services
judgement, and the support provided by computerized and electricity supply industries, whereas the existence of
spreadsheet packages. Other more advanced risk analysis difficulty in obtaining input information and assessment of
techniques, such as probabilistic risk analysis/simulation probability distributions seems to worry most of them in all
and CAPM, although highly developed in theory, have not three industries surveyed. Undoubtedly, performing prob-
been widely used in assessing and managing risks. abilistic risk analysis requires more time than simple risk
On the other hand, the survey results from the three local adjustment methods. However, with the aid of computers
industries show that the size of project and its complexity and the use of software systems, the actual time spent in
are the most important factors in the utilization of risk conducting the analysis can be significantly reduced.
management. Contract types, schedule delays, cost over- Indeed, the increasing widespread use of microcomputers
runs and customer requirements appear to be playing and computer-based decision support systems would
significant roles in the application of risk management enhance the potential ease of use and efficiency of risk
approaches in buildiong services and electricitry supply management techniques. These, would in turn, justify the
industries. This is not surprising since they are very cost aspects of using risk management.
important factors in the construction activities. Most of As regards to the existence of difficulty in obtaining
these findings are similar to those obtained by McGregor, input estimates and assessment of their probability, there is
He and Pike. 9:1 These results also indicated that the a general misconception that risk management requires a
application of risk management is not primarily correlated very accurate measurement and assessment of risks. In fact,
with the type but rather the use is very much dependent on risk management requires the analyst to determine the
management's perception of risk within the specified probability distribuitions of risk factors, many of which are
project. determined using subjective beliefs and judgement rather
As mentioned earlier, the main reason for the lack of than objective information. On the other hand, if objective
acceptance of risk analysis is that it is marred by some information is available, they can use it in assessing

309
Practices, barriers and benefits of risk management: V M Rao Tummala et al.

Table 6 S u m m a r y of the inherent and implementation problems encountered

% of total reflecting agree to strongly agree

Inherent problems encountered Building services Transportation Electricity supply

A1 Difficulty in obtaining input estimates and assessment of their probabilities 78 75 77


A2 Time involvement 78 47 85
A3 Difficulty in understanding and interpreting outcomes of risk management process 62 44 62
A4 Managers cannot agree on quantification of uncertainty/subjective probabihty assessment 46 72 76
A5 Cost-justification of risk management process techniques 58 31 58
A6 Difficulty in determining tradeoff between risk and return * * 65
Implementation problems encountered
B1 Lack of middle managers/supervisors support 41 *
B2 Lack of managers understanding of risk management process techniques 56 * 60
B3 Lack of top management support 37 17 40
B4 Human/organizational resistance to change 60 55 68
B5 Lack of computing resources and assistance 53 9 24
B6 Finding statable risk management methods 47 67
B7 Non-availability of acceptable risk standards 73 *
B8 Lack of training in risk management process 53 *

probability distributions. Several software packages are ceived impact of risk management have been substantial.
available to fit an appropriate distribution for a given risk Even though some respondents believed that risk manage-
factor based on the objective data) 8 Also, several easy-to- ment will provide some negative impact, the results from
understand and effective tools of encoding subjective beliefs the three local industries also tend to agree that formal risk
and judgement with use of computers are now available. We management can provide a useful insight into the project,
expect that these tools would enable managers to assess enhance communication among managers, allow manage-
probability distributions without difficulty. The problem of rial judgement, improve project performance, and provide a
quantification of uncertainty/subjective probability assess- systematic and logical approach to decision making. These
ment would also be resolved. conclusions are supported by the conclusions that are
Meanwhile, it seems that the difficulty in understanding obtained by Hertz and Thomas, and Ho and Pike) '7'9
and interpreting outcomes of risk management process is Furthermore, the respondents in the electricity supply and
another major inherent problem among the practitioners of public transportation industries indicate that formal risk
building services and electricity supply industries. The management improves quality of investment decisions and
same is true for cost-justification of risk management increases confidence in investment decisions which are
techniques. This is possibly due to the people not having further supported by Hertz and Thomas, and Ho and Pike. It
enough training and understanding of the risk management appears that the percentages of respondents indicating
approaches. Indeed, risk analysis only requires the users to improved quality, and increased confidence in investment
have some basic knowledge on statistics and risk manage- decisions are larger than those obtained by McGregor, and
ment tools so that they can understand, use and interpret the Ho and Pike. This indicates that the risk management
outcomes of risk management techniques. techniques may become accepted by the selected Hong
Regarding the implementation problems encountered, Kong industries and hence we can expect their increased
the major concern as reflected in all three surveys is the use in the future.
human/organizational resistance to change. Indeed, people To establish the trend in the application of risk
with little background in statistics and other quantitative management in Hong Kong, respondents were asked if
methods of analysis would find the risk management the importance of risk analysis in their firms had changed
techniques are diffficult to use. However, when risk over the last five years. They were then asked to estimate
management is implemented for some time, and given the changes over the next five years. In fact, it can be
sufficient training and education, the human/organizational identified that the respondents' attitude on the use of risk
resistance problem will be lessened when people become management is positive. As shown in Table 7, the three
familiar with the use of risk management techniques and survey results also show that risk management will become
realize the benefits the technique provides. The problems of more important in the next five years. We can envisage that
not understanding risk management methods and balancing the application of risk management will be widely spread in
risk/return tradeoffs would also be resolved. It appears that the future. Indeed, if the observed trend continues, formal
there is sufficient top management support in utilizing risk risk analysis may become a standard technique for larger
management approaches in all three industries. This would projects.
encourage faster changes in the employee attitudes in using Overall, this paper provides a critical examination of
risk management techniques. Hong Kong practices of risk management in building
On the other hand, the survey findings show that the per- services, public transportation and electricity supply

Table 7 Changes in the role of risk management

Over the last five years risk analysis has been (%) Over the next five years risk analysis will become (%)

Less important No change More important Less important No change More important

Building services 36 38 26 4 20 76
Transportation 64 11 25 6 14 80
Electricity supply industry 19 15 66 0 7 93

310
Practices, barriers and benefits of risk management: V M Rao Tummala et al.

industries. These findings show that formal risk manage- 14. Burchett, J. F., Risk mangement in transmission construcUon
ment has not been widely adopted in the past in the local projects. MSc Dissertation in Enginering Management, Department
of Manufacturing Engineering, City Polytechnic of Hong Kong,
industries, because it has been marred by some inherent and Kowloon, Hong Kong, 1994.
implementation problems still to be resolved. However, the 15. Leung, Y. H., The application of risk management process to project
survey findings show that perceived impact of risk appraisal in rolling stock section of MTRC. MSc Dissertation in
management is substantial. Most respondents tend to agree Engineering Management, Department of Manufacturing Engineer-
lng, City Polytechnic of Hong Kong, Kowloon, Hong Kong, 1994.
that formal risk management would offer useful informa- 16. Ho, S. S. M. and Pike, R. H., Risk analysis in strategic capital
tion to decision makers in making decisions. Indeed, the budgeting: a review and survey. The Chinese University of Hong
three survey results show that the application of risk Kong. Working Paper Series, 1989.
management will become more important in the future. 17. SPSS for Windows Base System User's Guide release 6.0. SPSS Inc.,
1993.
18. BesO'it User's Guide. Palisade Corporation, New York, NY, 1993.
Acknowledgements
The material in writing this paper was extracted from the
three MSc dissertations which were submitted by Mr John Professor V M Rao Tummala is the
F Burchett, Mr Y H Leung and Mr C K Mok in successfully professor of productions~operations
completing their masters program in Engineering Manage- management at Eastern Michtgan
ment, Department of Manufacturing Engineering, City Universtty, USA. He is currently on
leave from EMU, and teaching in the
University of Hong Kong, Hong Kong. Professor V M Rao Manufacturing Engineering Depart-
Tummala, who is the dissertation supervisor for all three ment of the City University of Hong
dissertations, has further analyzed with statistical analysis Kong. He is the leader of the depart-
and summarized the survey results to provide the ment's systems team. His field is
decision analysis and his current
comparative analysis with the assistance of Mr H M
research interests include the analytic
Leung. The authors wish to express their gratitude for all hterarchy process, the risk manage-
survey participants in taking time and completing the ment process, project management
questionnaires. and quality management.

References
1. Hertz, D. B and Thomas, H., Risk Analysis and Its Application. John
Wiley & Sons, Chichester, 1983. Mr Leung Hon Ming received a
2. Hayes, R. W., Perry, J. G., Thompson, P. A. and Willmer, G., Risk BEng(Hons) in Mechanical and Man-
Management in Engineering Construction--Implications for Project ufacturing Engineering from the Uni-
Managers Project Management Group, UMIST, Thomas Telford versity of Melbourne in 1994. He is
Ltd, London, 1986. now an MPhil student and a Research
3. Baxendale, T., Construction resource models by Monte Carlo simu- Assistant with the Manufacturmg En-
lation. Construction management and Economtcs, 1984, 2, 201-217. gineering Department of the City
4. Bennett, J. and Ormerod, R. N., Simulation applied to construction Umversity of Hong Kong. His current
project. Construction Management and Economics, 1984, 2, 225- research interests include the areas of
263. project risk management and knowl-
5. Birnie, J. and Yates, A., Cost prediction using decision/risk analysis edge-based systems.
methodologies. Construction Management and Economics, 1991, 9,
171-186
6. Flanagan, R., Kendell, A., Norman, G. and Robinson, G. D., Life
cycle costing and rask management. Constructton Management and
Economies, 1987, 5, $52-$71.
7. Hertz, D. and Thomas, H., Practical Risk Analysis--An approach
Through Case Histories. John Wiley & Sons, Chichester, 1984.
8. Cooper, D. and Chapman, C., Risk Analysis for Large Projects--
Models, Methods & Cases. John Wiley & Sons, Chlchester, 1987.
C K Mok obtained his BSc(Eng)
9. Ho, S. S. M. and Pike, R. H., The use of risk analysis techniques in
degree in electrical engineering from
capital investment appraisal. In Risk Analysis Assessment and
University of Hong Kong in 1981
Management, eds J. Ansell and F. Wharton. John Wdey & Sons,
After graduation, he joined Public
Chlchester, 1992.
Works Department of Hong Kong
10. Hall, W. K, Why risk analysis isn't working. Long Range Planning,
Government and started his career in
1975, 18,25-29.
building services engineering. He is
11. McGregor, J. M., What users think about computer models. Long
now with the Architectural Services
Range Plannmg, 1983, 16, 45-57.
Department as Budding Services En-
12. Ho, S. S. M. and Pike, R. H., Risk analysis in capital budgetary:
gineer. In 1994, he obtained his
barriers and benefits. OMEGA International Journal of Management
Master of Science degree in Engineer-
Science, 1991, 19, 235-245.
ing management from City University
13. Mok, C. K., The application of risk management process in building
of Hong Kong. His dzssertation paper
services cost estimation. MSc Dissertation m Engineering manage-
is on the application of risk manage-
ment, department of Manufactunng Engineering, City Polytechnic of ment.
Hong Kong, Kowloon, Hong Kong, 1994.

311
Practices, barriers a n d benefits o f risk m a n a g e m e n t : V M R a o T u m m a l a et al.

John Burchett started his career with o,:. . . . "~ .... ~ ~ ~ o Y H Leung is the Mechanical Design
anelectricalpowerplantmanufac- ~ i Section Engineer in Rolling Stock
turer in England and then with an Design Section of Mass Transit Rail-
international power consultant Ken- way Cooperation. He is responsible
nedy & Donkin. He joined China Light for the mechanical design of rolhng
and Power Company Limited (CLP) in stock projects including Eastern Har-
1980 as Substation Design Engineer bour Crossing, Chopper Conversion
and was responsible for the engineer- and Additional Rolling Stock. He is
ing and construction of many major interested in risk-based project man-
multi-storey Primary Substations in agement. He obtained his MSc degree
Kowloon and New Territories of Hong in City University of Hong Kong. He is
Kong. Since 1991 he has directed and a member ofHong Kong Institution of
managed the building of new 400kV Engineers and a member of lnstltutlon
overhead lines from Black Point of Mechanical Engineers.
Power Station, including wayleave
acquisition; the first outlet was' completed in 1995 and the final hne
will be completed in 1996. In 1994 he obtained a Master of Science in
Engineering Management from City Polytechnic (University) of Hong
Kong with a dissertation on risk management. He has been acttvely
involved in the promotion of continous improvement processes In
1995 he co-authored papers "presented at the International Symposium
on Total Quality Management at the City University and APSCOM in
Hong Kong. He is a member of the CLP Transmission Business Group
(TBG) Change team. His current responsibdities include the procure-
ment of materials and services for asset creation in TBG.

312

S-ar putea să vă placă și