Documente Academic
Documente Profesional
Documente Cultură
Appendix A (Page 1
Lifting and Rigging Job Safety Analysis
Rigging and Lifting Task Description
Crane Manufacturer TADANO Date of Lifting: 22-06-2017 / 21-09-2017
SModel GR-800 EX Area KEMYA
Type MOBILE CRANE Location U-63B / C
Gross Crane Capacity 8O TON Permit needed YES
Crane Matting can be calculated 75% of the gross weight of crane and load acting for a single outrigger pad
Minimum Mats Area per single outrigger = {Total Weight of Crane 59.7 TONS +2.5 TONS total weight of load} (tons) X 0.75 = 2.9 (sq. mts)
Ground Bearing Capacity (tons/m) 16
Appendix AB
(Page 2/2)
Job Safety Analysis
TASKS HAZARDS EXTRA PRECAUTION TO BE TAKEN
REQUIRED FLAG MAN TO ESCOURT THE VEHICLE
LOADING / UNLOADING / INSTALLATION OF TRAFIC HAZARDS AND HIT BY OTHER AS PER ROUTE PLAN. REQUIRED FIRE
OBJECTS. FIRE HAZARD, UNKNOWN
STRUCTURAL ASSY, BEAMS, SUPPORT AND ESTINGUISHER, CHECK THE WIND SPEED,
WEIGHT
FALL HAZARD & FAILURE OF LIFTING
OTHER MATERAILS CHECK THE WEIGHT OF THE LOAD, KNOW THE
GEARS
THE WORK AND USED CORRECT TOOLS W/
SLIP, TRIPS HAZARDS.
COLOR CODE. CLEA THE AREA AFTER WORK.
The following sketches, drawing, and plan shall be prepared in addition to this Rigging and Lifting analysis (see examples
Appendix AZ)
A. Elevation view drawing(s) of the crane, load, and any nearby structures that could cause interference problems. The
drawing shall be to scale and note:
1. Crane manufacturer(s), model(s) and counterweights
2. Boom length(s) and lifting radius(i)
3. Maximum load elevation during lifting procedure
4. Any jibs or special lifting devices required
5. Minimum number of parts of crane hoist line required to lift the load
6. Clearances from obstructions and power lines
B. Plan view drawing(s) of the crane, load, and nearby structures which could cause interference. The drawing shall be to
scale and include:
1. Route the transport will take to position the load for lifting
2. Initial position of the load, including radius
3. Final placement position of the load, including radius
4. Location of the crane(s), including tail-swing limits
5. Location and depth of nearby underground pipes and structures
APPENDIX AC
(1/2)
PRE-LIFT CHECKLIST
The purpose of this checklist is to recognize hazards associated with lifting job and to take corrective action on site before lifting
take place.
Yes/ No Comments
1. Is approved lifting plan provided?
2. Necessary Work permit from operation obtained?
3. Contingency Plan (if LCM matrix required, e.g. near process operation) approved and on site?
4. Is physical location as per lifting plan? Load is rigged according to planned
5. Is the combined rated capacity of the rigging components adequate to carry the load safely?
6. All slings & shackles inspected, certified and color coded as per Kemya requirements
7. Rigging equipments (cranes, lifting bars, etc.) checked, certified, color-coded & free of defects?
8. Crane visually checked, (Hook block, wire ropes, tires, outriggers & pulleys).
9. Swing radius and elevation confirmed & clear of obstruction ( piping, structures, equipment, etc.)
10. Lifting radius / swing radius/ exhaust pipes barricaded and guarded
11. Outriggers fully extended and crane leveled. Tyres (tires) off the ground?
12. All parts of the crane and load unobstructed and will not be obstructed
13. Correct matting and/or foundation in place
14. Ground and site condition stable enough to allow lifting?
15. Will the lifting activity affect other nearby workers? Only rigging jobs during
lifting activities.
16. Swivel hook locked (where required)
17. Are operators / riggers having a valid certification?
18. Are the number of riggers adequate to execute the job safely?
19. Is there an independent signalman and is he wearing the appropriate green vest?
20. Specific Communication required? Is there a need for special communication equipment, i.e. radio, Hand signal only,no
etc. (Test before start lifting operation other device used.
21. Is crane provided with interlock systems (PLC), is it active/ functional (confirm no by-passed
devices)?
22. Wind velocity considered? (Pls. see at the back). (Max 35 Kph)
23. Tag line provided to control load?
24. Pre-lift work method / plan discussed by entire work group?
25. Equipment Daily Inspection (and operation) logs up to date
26. Engineering review of Lifting Attachments completed (where required)
27. Non Destructive Examination of welded lugs completed (where required)
Note:
If answer is NO to any of above, lifting shall not be executed till comment is satisfied.
Crane should not be used to pull or drag loads.
If it is necessary to change to the Lift Plan the change shall be reviewed by the people who reviewed the original plan
Remarks:
Area Assigned Operator: (ensure form are filled on site prior to lifting)
__________________
SHEM-08 Safe Work Practices/ OIMS-5.1 Personnel Safety Issue No.: 4 Date: November 2015
Always comply with the details in the load capacity tables concerning maximum permissible wind velocities. If the
permissible wind force limit is reached, crane operation must be discontinued and boom lowered.
Appendix AD
Daily Crane Inspection Checklist
(To be used also for qualifying hired/contractor crane)
DATE ___________________ CRANE NO :________________Operator/Inspector__________________________
S.L. DESCRIPTION SAT. UNSAT. N/A REMARKS
1 Carrier Doors, Panels/Display, Mirrors
2 Under chassis leak, Deformities, Cracks, corrosion
3 Air Reservoir. Loose bolts
4 Tire Condition and air Pressure
5 Coolant Level
6 Engine Oil level
7 Wire Rope Conditions & Drum Lay (SWL marked)
8 Seat Belts, Windscreen, Platforms and Walkways
9 Load Charts, Rigging Signals, Hazards instruction posted
10 CO2 Fire Extinguishers (Do not use carbon tetrachloride)
11 Hydraulic Oil Level & system (Tubes, hoses, tanks)
12 Battery Terminals and cables
13 Engine Starting
14 Voltmeters/ ammeters
15 Turn Signals/ hazards
16 Horn, Lights, wipers
17 Tachometer
18 Engine Oil Pressure gauge
19 Engine Coolant temperature Gauge
20 Fuel gauge Level
21 Air Pressure gauge/ Brake Checks
22 Suspension System
23 Anti-Two Block / LMI (Load Moment Indicator)/LID (Load Indicator
Devices) RCL (Rated Capacity Limiter)
24 Boom Angle / Length / SLI
25 Outriggers Stabilizers
26 Spirit Level
27 Hoist Control / operation
28 Swing lock
29 Swing control /Operation (check operators cab)
30 Back Up Alarm and Moving Alarm
31 Anemometer, wind speed
32 Engine Oil leak Check
33 Sheaves Main hook Block & Aux. Hook, pins, cracks (SWL marked)
34 Swing away Jib
35 Battery Distilled water level
36 Fan belts
37 Transmission & Conversion temperature gauge
38 Transmission Oil level
39 Air Filter condition
40 Hydraulic Filter Condition
41 Steering System
42 Rear axle oscillation Lock Out System
43 Boom extension / Lift Controls
Appendix AG
LIFTING AND RIGGING PLAN
B) Capacity of Hoist Wire Ropes 6.6 D) Load Description Loading / Unloading/ Installation of structural supports
Capacity of Hook Blocks 80 T Beams, Bracings, Gratings, Ladders, Handrail and other materails
(Minimun Hoist required__________)
4
C) Attachm ents and Rigging: Net Load Weights: 1,500 + 150 KG (10%) (Lbs/Kgs)
1- Sling type: WEB SLING
Stew ed Erected N/A Lbs/Kgs
2- Size: 3"/2" x 6M No. 2 Pcs.
Jib Extension: N/ A
3 total capacity 6,000 KG Hook block (Main) 700 KG
Att. Boom Head N/ A
4- Hitch Arrangement Used: Headache Ball 165 KG
(Single, choker, basket, ) Slings, Schackles, etc. 50 KG
2 LEG BRIDDLE / CHOKER Others
5- Capacity of above Arrangem ent
Total 2,565 KG
(Refer to Lifting & Rigging JSA, as needed)
4157 KG / 2771 KG (Lbs / Kgs) Gross Load Weight 2,565 KG
Note: If Jib is used, refer to proper load chart & safety notes on load chart
E) Total Boom Length: 38.3 M (Mtr / Ft)
H) Maximum lifting capacity of crane in above configuration as per load chart: 4,200 KG - 61%