No Job Description Fitting Assembly Welding Test Handling Painting Others Rate (Rp)
1 Assembly the Bottom side panel 3164x 5690 mm 16,250,000
2 Paint Yellow Color bottom side panel 2,500,250
3 Assembly Frame Bottom side with WF 125 16,250,000
4 Connection side direction panels of the autoclave 17,550,000
Dimension 5525x 3895mm
5 Assembly Frame Bottom side with WF 125 16,350,000
6 Connection of back side panel 3925x3164 4,250,000
7 Connection and fabrication rectangular box Beam Hbeam 250 15,225,000
3624x3824mm
8 Connection of the door H beam 3752mm x 3624mm 4,520,000
9 Assembly of the autoclave body 6,500,000
10 Assembly autoclave body adn rectangular girder 5,400,250
11 Fabrication rectangular pipe and Panel by argon 15,500,000

12 Assembly of the autoclave body accessories 17,575,000


( Window observation, hydraulic cylinder, locker )
13 Emplacement of autoclave body 4,500,000
14 Install insulation panel and fastening into every block 4,350,000
15 Transfer and positioning the autoclave body to the foundation 6,250,000
16 Clean the autoclave body 5,250,000
17 Assembly the turn over bridge and the railways inside autoclave 3,950,000
18 Install the heating pipelines inside the autoclaves body 15,650,000
19 Cleannes inside the pipelines and sealing performance 2,500,000
20 Re clean and re grind the inner side of the autoclave body 2,500,000
21 Emplacement of non standard devices 6,350,000
( Vacuum unit, electrical heat , oil level, hydraulic system, electrical cabinet)
22 Leakage check of the autoclave body 6,250,000
23 Manufacture the trolly Tractor 15,000,000
24 Support tools and machinery 15,500,000
25 Accomodation 5,000,000
26 Safety Tools & Scafolding 5,500,000
27 Consumable ( Arc, Oxy Argon, etc ) 22,500,000
TOTAL 258,920,500