Sunteți pe pagina 1din 13

PolicyBrief

SENATEECONOMICPLANNINGOFFICE

June2008 PB0803

AcceleratingPowerSectorReforms:

AmendingtheEPIRA
I. Introduction
Lower power rates,

sufficient capacity and an
The Electric Power Industry Reform Act (EPIRA) was enacted in
environment equally
protective of investors 2001 with the intention of ensuring affordable and reliable
and consumers these electricitytoallpowerconsumersinthePhilippines.TheEPIRA
were the end goals of the seeks to achieve this through the introduction of sweeping
Electric Power Industry reforms including the restructuring and deregulation of the
Reform Act when it was entirepowerindustryandtheprivatizationofmoststateowned
enacted seven years ago. power generation and transmission assets. Such reforms were
The pace of its intended to introduce more competition and choices for
implementation, however, consumerswhilelevelingtheplayingfieldinthepowerindustry
has been slower than inordertoencouragegreaterprivatesectorparticipation.
expected, prompting the
Senate to propose specific Unfortunately, for the most part, the pace of reforms in the
amendments to expedite powersectorhasbeenslowerthanmostpeoplehavehopedfor.
the much-envisioned
AlmostsevenyearssincetheEPIRAwaspassedintolaw,several
power reforms.
of its provisions have yet to be fully implemented and the
promiseofconsumerchoiceandlowerpowerrateshasyettobe
realized.

II. PowerSectorSituation

In terms of access to electricity, the Philippines performs quite
adequately.Attheendoflastyear,96.63percentofall41,980
barangays in the country are already electrified. The vast
majority of the remaining 1,413 unelectrified barangays are
located in the franchise areas of electric cooperatives. The
Autonomous Region of Muslim Mindanao (ARMM) has the
lowestelectrificationlevelamongallregionsinthecountrywith
a mere 83 percent, followed by Regions XII and V with 94.39%
and94.47%electrificationlevels,respectively.

The SEPO Policy Brief, a publication of the Local power rates, however, remain among the highest in Asia
Senate Economic Planning Office provides next only to Japan. This is partly due to the Philippines
analysisanddiscussiononimportantsocio
economic issues as inputs to the work of continueddependenceonimportedfuelforitspowerplantsand
Senators and Senate Officials. The SEPO the slow pace of privatization which derailed the promotion of
Policy Brief is also available at
www.senate.gov.ph.
competitioninthesector.Manyofthecountrysgeneration
plantsarestillheavilydependentonimportedfossilfuelssuch

ascoalandoilb
basedfuels.A
Attheendooflastyear,2
26.43%ofth
he
Table1.BaraangayElectrificationStatuss
installed generration capaccity was frrom coalpooweredplantts
asof31Decemberr2007
while22.79%waasoilbased..
R
REGION Electriffied Unelectrified Electrrifi
Baranggays Barangaays cation
Level(%)
Inreecentmonth hs,powerratesintheco ountryhave risenfurtheer,
N
NCR 1,694 0 1
100 averraging P7.43 3/kwh in Deecember 20 007 to P8.3//kwh in Aprril
C
CAR 1,122 54 95
5.41 2008inMetroM Manilamainllybecauseofhighergenerationcosts.
I 3,264 1 99
9.97 Allegations thatt the largesst distributio on utility in the countryy,
II 2,219 92 96
6.02 MER RALCO, has been overrcharging and passing on unduee
III 3,092 10 99
9.68
charrgestoitscu ustomershavealsosurffaced.More eover,asperr
the latest pow wer supply and demaand projecttions of th he
IV
VA 3,946 66 98
8.35
Dep partmentofEEnergys(DO OE),powershortagesw willlikelyoccu
ur
IV
VB 1,350 1
107 92
2.66
inthheMindanao ogridby201 11,intheViisayasgridby2012andiin
V
V 3,246 2
225 93
3.52
the Luzongridb by2014ifnonewgeneerationcapacityisadded d.
Luzon 1
19,933 5
555 97
7.29
Despite the re ecent impro ovements in the counttrys financial
V
VI 4,008 42 98
8.96
cond dition, the high
h cost of building andd maintaining new poweer
V
VII 2,999 4 99
9.87 plan nts makes itt very difficuult for the governmentt to fund th he
V
VIII 4,098 2
292 93
3.35 neceessary expaansion of the countrys power in nfrastructuree.
V
Visayas 1
11,105 3
338 97
7.05 Giveen that it taakes an averrage of five years1 for a
a new poweer
IX
X 1,724 1
180 90
0.55 plan nt to come on
o stream, it i is imperattive that thee governmen nt
X
X 1,918 1
102 94
4.95 enco ourage greater private sector participation and d attract neww
X
XI 1,155 5 99
9.57 inveestmentsintthepowerindustry.
X
XII 1,103 91 92
2.38

In light
l of theese develop pments, law wmakers havve sought to t
C
CARAGA 1,279 31 97
7.63
intro oduce amen ndments to the EPIRA in order to o address th he
A
ARMM 1,869 5
592 75
5.94
percceivedweaknessesandttoclarifytheeambiguoussprovisionsiin
M
Mindanao 9,048 1,0
001 90
0.04
the law.Senate Bill2121co onsolidatessseveralofthe eseproposals
P
Philippines 4
40,086 1,8
894 95
5.49
andiscurrentlyintheperiod dofinterpellationsinthe eSenate.
S
Source:Departm
mentofEnergyy(DOE)
III.CommentsontheProposedAmend dments
Fig.1.SShareofInstalledPower
GenerrationCapacity,2007 Thispaperseeksstoexploretthevariouso optionsforamendmentss
Othe
ers inth heEPIRAwhiilediscussinggtheimplicaationsofthesseproposalss
H
Hydro Natural 0.16
6%
onthevariousse ectorsconceerned.
20
0.61% Gas
17
7.48%
Geother
mal 3.1 TranscoPrivvatization
12.52% Coal
Oil 26.43% Secttion 4 of SBB 2121 is aimed at easiing the requ uirements fo or
b
based
22
2.79% privvatizing the National Traansmission C Corporation (Transco) byb
prop posing a nu umber of alternative m methods of privatization n
either through a contractt of sale or through a concessio on
agreeement. It was claimed that the difficulty of o securing a
Source:DOE
fran nchisehasledtoanumb beroffailed attemptsto oprivatizethhe
tran nsmissionnetwork.

1
Thenumberrofyearsneeddedtoconstructapowerpplantdependssonthetypeoffuelitusess.Coalpowerredplants
usuallytake6years,hydrop
u powerandgeo othermal5yeears,whiledie
esel,gasturbineandwindp poweredplanntsare
c
constructedinnabout4yearrs.

Thebillproposesthatiftheawardeeoftheconcessioncontract
ismerelyhiredunderacompensationschemethentherewillbe
noneedtoobtainanationalfranchisefromCongress.However,
ifthewinningbidder(incaseofasale)orawardee(inthecaseof
aconcessioncontract),takesoverpossessionandcontrolofthe
transmission assets and facilities, and operates Transco as its
ownbusinessthentherewillbeaneedforanationalfranchiseas
well as compliance with the nationality requirements of the
Constitution. In any case, there are sufficient safeguards in the
EPIRA which help ensure that the concessionaire does comply
with its mandate. The EPIRA requires the concessionaire to
complywith the GridCodeand TransmissionDevelopmentPlan
which sets certain performance targets and expansion
requirements for transmission network. There are also several
performance indicators set in the law with which the
concessionairemustcomply.
the implementation

of retail competition However, with the awarding of the 25year concession
and open access is agreementforTranscototheconsortiumofMonteOroGridCo.,
dependent on having CalacaHighPowerCorp.andtheStateGridCorp.ofChinaon12
in place the December 2007, there might no longer be a need for these
prerequisites which amendments. As of today, the Monte Oro consortium has
Congress believes are already applied for a congressional franchise and the House of
Representativesisalreadydeliberatingonthebill.
necessary to sustain a

fair and robust
The amendments proposed in the bill will probably only come
competitive market into play if the Monte Oro consortium is unable to secure a
and are in the public congressionalfranchisetooperateTransco.Iftheyfailtodoso,
interest. thePowerSectorAssetsandLiabilitiesManagementCorporation
(PSALM)mustconductyetanotherroundofbiddingforTransco
andinsuchacase,thisamendmentwillbecomeuseful.

3.2RetailCompetitionandOpenAccess

One of the most important reforms which the EPIRA intends to
bring about is the implementation of open access and retail
competition in the electric power industry in the Philippines. At
present, distribution utilities (DUs) have the exclusive right to
supplyelectricitytoconsumersconnectedtotheirnetwork(the
Captive Market). Under a regime of open access and retail
competitionasenvisionedintheEPIRA,DUswillnolongerenjoy
thisexclusivityandmustallowcompetingelectricitysuppliers
to transmit power through their distribution network thus
allowing certain consumers within their franchise area (the
ContestableMarket)theirchoiceofsupplier.TheContestable
Market will initially consist of consumers with a monthly
average peak demand of 1 MW. The threshold level for the
ContestableMarketwillbereducedprogressivelyoverthe

years until it eventually reaches the household level. It is


hopedthatwithretailcompetition,electricitysupplierswill
compete with each other to sell electricity to endusers,
thus,eventuallydrivingdownpowerrates.

Table2.GenerationAssetsSold However, the EPIRA sets forth five preconditions which
asofJune2007 mustbeachievedbythegovernmentbeforedeclaringopen
Power Rated Location Winning Price access.Thesepreconditions,asstatedinSection31ofthe
Plant Capacity Bidder (USD EPIRAinclude:
(MW) mill) a) establishmentoftheWholesaleElectricitySpot
TYPEOFFUEL:HYDRO
Talomo 3.5 Davao Hydroelectric 1.37
Market(WESM);
HEPP DevtCorp b) unbundlingoftransmissionanddistribution
AgusanHEPP 1.6 Bukidnon First 1.53 charges;
Generation c) initialremovalofcrosssubsidies;
Holdings
BaritHEPP 1.8 Camarines Atty.Ramon 0.48
d) privatizationofatleast70%oftotalgenerating
Sur Constancio capacityofNPCassetsinLuzonandVisayas;and
Cawayan 0.4 Sorsogon SorsogonII 0.41 e) transferofmanagementandcontrolofatleast
HEPP Electric 70%ofthetotalenergyoutputoftheNational
Cooperative
LobocHEPP 1.2 Bohol Sta.Clara 1.42
PowerCorp.IndependentPowerProducer(NPC
International IPPs)toIPPadministrators
Corporation
Pantabangan 112 NuevaEcija FirstGen 129
Masiway Hydropower Thepreconditionsregardingtheunbundlingofchargesand
HEPP Corp the removal of crosssubsidies have already been
MagatHEPP 360 Isabela SNAboitiz 530
PowerCorp
substantially completed. After more than a year of
Ambuklao 175 Benguet SNAboitiz 325 preparation and testing, the WESM commenced its full
BingaHEP PowerCorp commercialoperationsfortheentireLuzongridonJune26,
Complex
TYPEOFFUEL:COAL
2006. The establishment of a Visayas WESM however,
Masinloc 600 Zambales Masinloc 930
which was initially set for January 2008, will likely be
Power deferred in the near future after it was determined that
PartnersCo. conditionsinthemarketwerelessthanoptimalatpresent.
Ltd
Calaca 600 Batangas CalacaHoldco 787 Reasonscitedfortheseincludethelackofpreparednessof
Inc. somemarketparticipants,andthetightsupplyanddemand
Source:PSALM
balance in the Visayas grid. Preparations are also being
undertaken for the establishment of a WESM reserve
marketwiththepetitionsforsuchcurrentlybeingreviewed
by the Energy Regulatory Commission (ERC). The
government has also had great difficulty attaining the pre
conditions of privatization in a timely manner. The
PSALMwastaskedtoprivatizegeneratingplantswithatotal
capacityof4,335.7MWinLuzonandVisayas.Atpresent,
the total capacity of plants privatized in Luzon and
Visayas is 1,850.4 MW representing only 43% of the
total.Meanwhile,notasingleNPCIPPhasbeentransferred
toanIPPadministrator.

Because of the difficulty faced by the government in
privatizingNPCpowerplantsandNPCIPPs,thebillproposes
to lower the privatization thresholds for both NPC
generation plants and NPCIPPs from 70% to 50%, in order
to hasten the implementation of open access and retail
competition.

Amending the preconditions set in the EPIRA, however, might


have a negative effect on the proper implementation of open
access.Thepreconditionsweresetinthelawwiththeintention
of first fostering an environment which can sustain a fair and
robust competitive market for all players in the electric power
industry before moving forward with a regime of open access.
For this regime to be most effective, there is a need for a truly
competitivemarketwithanumberofcompetinggenerators,on
a level playing field, without a single dominant generator. The
requirementforNPCtodivestitselfofatleast70%ofitspower
plants and IPPs is to ensure that they would not have undue
marketpowerinthenewregimewhileallowingmoreplayersto
The present fiscal activelycompeteinthemarket.
condition of the
government makes it WhileitiscertainlypossiblethatNPCwillchoosenottoabuseits
dominantpositioninthemarket,recenthistoryhasshownthatit
difficult for it to
is quite capable of doing this. It will be recalled that sometime
invest in
around September 2006, concerns were raised over possible
constructing new pricefixingbytheNPCandPSALM,whichcollectivelycontrolled
power plants, hence around 80% of the power plants participating in the WESM.
the need to encourage Although the subsequent investigations conducted by the ERC
the private sector to found no evidence against PSALM for anticompetitive behavior
invest in expanding and market power abuse, which contradicted the results of the
the generation. internal investigation conducted by the WESM itself, the mere
perception of abuse and manipulation in the wholesale market
sector.
could serve as a disincentive towards greater private sector
participationinthepowersector.TheERCfurtherconcludedthat
much of the pricing result was due to the market being in its
infancy and that there was experimentation with the trading.
Regardless, this behavior resulted in significant price increases
over and above the ERCapproved time of use (TOU) rates.
Letting NPC and PSALM retain ownership or control of 50% of
their power plants (albeit temporarily), as proposed by the bill,
givesthegovernmenttoomuchleverageinthemarketplace.This
mightalsoserveasadisincentivetowardsgreaterprivatesector
investmentinthegenerationsectorwhichcouldleadtopotential
capacity shortages in the medium term. The present fiscal
conditionof thegovernmentmakesitdifficultforittoinvestin
constructingnewpowerplants,hencetheneedtoencouragethe
private sector to invest in expanding the generation sector.
Reducingthegovernmentsshareintheentirepowerindustryby
accelerating the privatization of governmentowned power
plantsshouldhelpreducetheriskofanticompetitivebehaviorin
the future, whether in the Spot Market or in the Contestable
Marketwhileenticinggreaterprivateinvestmentandavertinga
potentialpowercrisis.

3.3 Nonrecovery of Stranded Debts and Contract Costs of All


IndustryParticipants

The Universal Charge (UC) is a nonbypassable charge collected


from all endusers and remitted to PSALM for various purposes
specified in the EPIRA. The UC at present is composed of the
Table2.TotalIndicativeStrandedDebt following:a)paymentforstrandeddebtsandcontractcosts,b)
andStrandedContractCostasofend missionary electrification, c) the equalization of taxes and
December2007(inUS$million) royalties for indigenous energy sources visvis imported fuels,
d) an environmental charge which shall accrue for watershed
Particulars Principal Principal&
Only Interest management and rehabilitation, and e) a charge to account for
Indicative 8,480.71 13,210.5 all crosssubsidies. The bill proposes to amend the items which
Privatization constitutetheUCbydisallowingtherecoveryofstrandeddebts
Proceeds
NPCDebt 7,391.00 10,445.0 and stranded contract costs in the determination of the UC.
Obligations Eliminatingtheseitemswillultimatelyservetolowertheelectric
IPPLease 6,896.28 10,945.0 billsofconsumersbutwillhaveimplicationsonthegovernment
Obligations
TotalNPC 14,287.28 21,390.0 budget.ThemostrecentestimatesfromPSALMindicatethatthe
Obligations government will still incur a shortfall of US$ 8.179 billion which
TotalIndicative (5,806.57) (8,179.5)
mustberecoveredthroughtheUC.
Shortfall
Assumptions: TheEPIRAmandatesthattheproceedsarisingfromthesalesand
1. PrivatizationProceedsinclusiveofGenco
privatization of NPC assets would be used to liquidate the
&Transco
2. ZeroNPCCashflowbeforeIPP financialobligationsoftheNPC.Inadditiontothis,thenational
obligations government has already assumed two hundred billion pesos of
NPCs debts. PSALM is optimistic that with the privatization
proceeds and the debt absorption, it can minimize or even
completely eliminate all stranded debts, and thus, perhaps
negatetheneedtopassthisontopowerusersviatheUC.Their
optimism is supported by the fact that the latest attempts at
privatizing generation assets have yielded better than expected
results, with several entities participating in the bidding and
winning bids being way over the reserve price set. If this trend
continues then there will be no need after all for a UC for
stranded debts. However, if privatization proceeds will be less
than expected, the government will be forced to absorb even
more of NPCs debts if the new law disallows recovery of the
debtsthroughtheUC.

Strandedcontractcosts,ontheotherhand,areboundtoarisein
twoinstances:1)whenthevolumeofelectricitycontractedfrom
IPPsisgreaterthantheactualelectricityconsumedand2)when
the price of contracted electricity from IPPs is greater than the
actual market price (as determined by the WESM). In both
instances, because of takeorpay provisions embedded in
most IPP contracts, the cost of the excess volume or the price
differentialbecomesastrandedcostwhichwillthenhavetobe
absorbedbythegovernmentorrecoveredthroughendusersvia
the UC. The volume differential will likely be reduced over time
as electricity demand grows either through economic or
population growth. To a certain extent, the government has

already taken some steps to reduce stranded contract costs


through the review and renegotiation of IPP contracts. As
mandated by the EPIRA, PSALM, along with several other
agencies, was tasked to undertake a thorough review of all
existing IPP contracts with the ultimate goal of renegotiating
provisions which are found to be grossly disadvantageous or
oneroustothegovernment.PSALMhassubstantiallycompleted
thereviewandrenegotiationofalleligibleIPPcontractsandthey
Passing on the burden have reported that this has resulted in approximately US$ 1.03
to the government billioninsavingsforthegovernment.Savingsarisingfromthese
could be a calculated renegotiations were the result of IPPs reducing nominated
risk for the government capacity, spreading out total contract obligations over longer
contract periods, assumption of NPCs obligations to host
to take if it believes that
communities and the implementation of rural electrification
reducing power rates
projects.
by essentially
subsidizing stranded However, the renegotiated IPP contracts will not completely
contract costs could eliminate all stranded contract costs and someone will have to
ultimately attract more bear the cost in the transition period until the reform period is
completedandthepowermarkethassufficientlystabilized.This
foreign investors and
couldbeanyoneoracombinationofthefollowing:
appease residential
users. a)theIPPcontractholder,whichmaybeinthepublicsector
(inthecaseofNPCIPPs)ortheprivatesector;

b) the taxpayers at large, on the basis that power sector


reformisinthepublicinterest;or

c)theconsumersofelectricity,becausetheyaretheultimate
directbeneficiariesofthepowersectorreforms.

It could be argued that the IPP contract holders have already


borne some of the costs due to the IPP contract renegotiations
although this does not rule out the possibility of another round
ofrenegotiationsaltogether.Thisoption,however,wouldsenda
negativemessagetopotentialinvestorsinthepowersectorand
present the risk of the government undermining its credibility.
Voluntaryrenegotiationwouldbeamoreacceptablealternative
though, such as the firm but fair approach used by California
wherein if an IPP wanted to change any element of its contract
(size, location, fuel type, etc.) the purchaser would attempt to
restructurethefinancialtermsinreturn.

In the case of NPCIPPs, the proposed amendment disallowing


therecoveryofstrandedcoststhroughtheUCwouldalsomean
that the government, through taxpayers would also end up
paying for these costs. Allowing power consumers to bear the
stranded costs however, is usually considered to be a more
equitable method of pursuing this as this means that larger
poweruserswillbearaproportionatelyhighershareofthecosts.
Also, as with stranded debts, passing on the burden to the

governmentwillfurtherstrainthenationalbudget.However,this
could also be a calculated risk for the government to take if it
believes that reducing power rates by essentially subsidizing
stranded contract costs could ultimately attract more foreign
investorsandappeaseresidentialusers(albeitattheexpenseof
othergovernmentservices).

Thereisalsothepossibilitythatmarketpriceswillgrowbeyond
thecontractedpriceofelectricityfromtheIPPsduringtheperiod
which would instead result in stranded benefits instead of
strandedcosts.Shouldthegovernmentdisallowtherecoveryof
stranded costs as proposed in the amendment, then power
consumers will also lose out on the possibility of gaining from
possiblestrandedbenefits.
It is the duty of the
electric utility to 3.4Ratesetting
improve system
The EPIRA mandates the ERC to establish and enforce the
efficiency (by investing
methodology by which transmission and distribution wheeling
in better equipment rates and retail rates for the captive market of a distribution
and facilities) in order utility are determined. While the ERC currently uses the return
to reduce technical on rate base (RORB)2 methodology in setting the rates of
systems losses while it distribution utilities, the law also allows them to adopt
should be the joint alternative forms of internationallyaccepted ratesetting
responsibility of the mechanisms as it deems appropriate. The law also includes
specificguidelinestobefollowedbytheERCincaseswherethe
State and the DU to
RORBmethodologyisapplied.TheproposedEPIRAamendments
reduce losses due to
greatlyexpandontheguidelinestobeobservedindetermininga
pilferage. just and reasonable rate using the RORB. In addition to the
existing rules for RORB determination, the amendments
proposedtoincludethefollowingspecificguidelines:

i. defining the methodology for valuation method for


determining the rate base using the average
investment method which computes the
proportionate value of the property by getting the
average value of the properties, facilities and
improvements at the beginning and at the end of the
fiscalyear;
ii. disallowing the inclusion of the value of the utilitys
franchiseindeterminingtheratebase;and
iii. ensuringthatincometaxpaymentsofTranscoandthe
DUs shall not be passed on to the endusers of
electricity

Theseproposedamendmentsservetotightentherulesfurther,
andleavelittleroomforargumentastowhatitemsmayormay
not be included in determining the rate base. While this may

2
Using the RORB methodology, DUs are allowed to recover a 12% return on their investments related to electricity
distribution

seem to tie the hands of the ERC with regards to flexibility in


ratesetting,theexpandedguidelinesmightactuallybenecessary
toeliminateanygrayareasinRORBcomputation.

The bill also proposes changes to the cap for systems loss
recovery as a component of enduser electricity rates. The
present law on systems losses and pilferage losses, RA 7832,
allows for a 9.5% cap for private DUs and a 14% cap for rural
electric cooperatives. The proposed amendments uphold the
9.5% systems loss cap for densely populated urban areas while
mandatingtheERCtodetermineanewcapforruralareastaking
into account the inefficiencies inherent in rural electric
cooperatives in performing their missionary electrification
functions. Given the recent outcry from the consuming public
withregardtobeingchargedforsystemslosses,thisamendment
needs to be examined further. Systems losses, which include
both technical systems losses and losses due to pilferage, have
routinelybeenpassedontoconsumersinmostmarketsallover
the world. However, it is the duty of the electric utility to
improvesystemefficiency(byinvestinginbetterequipmentand
facilities) to reduce technical systems losses while it should be
thejointresponsibilityoftheStateandtheDUtoreducelosses
due to pilferage. The establishment of progressively lower caps
for systems loss recovery over a reasonable amount of time
might be worth considering to encourage greater efficiency in
thesector.Theexactlevelforthesystemslosscapthough,must
bestudiedcarefullytoconsidertheinvestmentcapacityoflocal
DUs.
Table3.MarketShareLimitations
Grid Installed %Market Installed 3.5 Crossownership, Market Power Abuse and Anti
Generating Share Generating CompetitiveBehavior
Capacity(kW) Limitation Capacity
Limit(kW)
It is important to place strict limits on market share and cross
Luzon 10,060,904.0 30% 3,018,271.2

ownership in the electric power industry to prevent market


Visayas 1,637,270.4 30% 491,181.1 power abuse. The EPIRA currently limits generation companies

toa30%shareofthemarketinasinglegridanda25%shareof
Mindanao 1,703,348.0 30% 511,004.4
the national grid. For 2008, the ERC has determined the total
National 13,401,522.4 25% 3,350,380.6 installedgeneratingcapacityineachgridandhassetthemarket

sharelimitationsshowninTable3.
Source:PSALM
Atpresent,theERChasdeterminedthatnoneofthegeneration
companies has violated the mandated market share limitations.
Theleadingprivatesectorparticipantinthegenerationindustry
isFirstGasPowerCorporationanditsaffiliateswitha16percent
shareintheLuzongridand12.4percentofthenationalgrid.

While the law disallows generators or DUs from participating in


the transmission sector, crossownership between generators
and DUs is allowed. As a safeguard to abuse though, the law
prevents DUs from sourcing more than 50 percent of its total
power demand from bilateral contracts with its related
generationcompanies.

Ideally, crossownership between generating and distributing


companies must be severely limited from the beginning and
guarded against after privatization, so that DUs that also own
generators cannot prevent other generators from accessing
customersthroughtheirdistributionnetworks.Themarketshare
ofgenerationcompaniesmustalsobestrictlylimitedtoprevent
abuseandanticompetitivebehavior.

However, completely disallowing all crossownership between


generation and distribution companies might not be feasible
given the present state of the Philippine power industry. Until
the industry achieves a sufficient level of maturity and
development, with several companies participating actively in
thesector,alimitedlevelofcrossownershipshouldbeallowed
betweengeneratorsandDUsinordertohelpinvestorsmanage
someoftheinherentrisksofthepowerindustry.Unfortunately,
Given the present in the Philippines, very few companies have shown the
willingness to venture into the power industry, as can be noted
state of the Philippine
from the fact that the same companies bid for the NPC
power industry,
generation assets that have been offered for privatization.
completely restricting Completely restricting crossownership between generators and
cross-ownership DUsmightprovetobetoomuchofabarriertoinvestmentand
between generators entry into the market and could also cause privatization to
and distribution becomesomewhatmoredifficult.
utilities might prove
Instead of completely disallowing crossownership, the caps on
to be too much of a
bilateral contracts and grid capacity ownership proposed in the
barrier to investment amendments to the EPIRA may be enough to promote
and entry into the competition in the power sector. If one wished to be even
market and could also stricter in this regard, further restricting the allowable level of
cause privatization to bilateral contracts between related generation and distribution
become somewhat companies from the proposed 50% cap to 33% could also be
more difficult. considered.Intheend,however,gridcapsandbilateralcapscan
only do so much and there is still no substitute for good
regulationandstrongantitrustandantimonopolyenforcement
whichshouldbethejobofatrulystrongandindependentERC.

It is interesting to note that various electricity markets around


the world have different approaches to the question of cross
ownership.InBrazil,ithasbeenrecommendedthatownershipof
generation by distribution companies should not exceed 25
percent.InUK,distributioncompaniesareallowedtoownonlya
limited share of generation. In the US, regulators in California
required the major utilities to sell half of their fossilfueled
generation, and the two largest voluntarily sold 100 percent.
Finally,someutilitiesintheUSaresellingalloftheirgeneration
to satisfy regulators that they will not be able to control the
emergingwholesalemarkets.Thus,whilethereareexamplesof
marketswhichhavenolevelsofcrossownershipatall,itisstill
unclearhowsuchasituationwillplayoutinthePhilippines.One

10

could consider the period of EPIRA implementation as a


transition phase for the power sector in the country and
completelyrestrictingcrossownershipinthepowersectorcould
perhaps be considered once the industry has sufficiently
matured.

3.6RoyaltiesandTaxesforIndigenousEnergyResources

The EPIRA seeks to reduce the royalties and taxes collected for
theexploitationofindigenousenergysourcessuchasnaturalgas
andgeothermalsteamtopromotegreateruseoftheseresources
as well as to ultimately reduce power rates. At present, three
different laws govern the extraction of indigenous fuels in the
Philippines,specifically:

In removing the a) PD 87 or the Oil Exploration and Development Act of


royalties for 1972, which governs natural gas exploration and
indigenous fuel, one development and allows the government to take a
minimum60percentsharefromthenetproceeds;
must also consider the

impact that such a
b) PD 1442 which governs the exploration and
move would have on development of geothermal resources and allows the
the revenues of the government to take a minimum 60 percent share of the
affected local netproceeds;and
governments as these
are usually poor rural c)PD972whichgovernstheextractionandexploitation
communities. ofindigenouscoalandallowsthegovernmenttotakea30
percentshareofnetproceeds

Forty percent of the total government share from these


operations is then given to the affected local government units
while 60 percent is remitted to the national government. While
removing the royalties for indigenous fuel will likely lead to the
reduction of power rates, estimates are still unavailable at this
time as to the extent of the reduction. One must also consider
theimpactthatsuchamovewouldhaveontherevenuesofthe
affected local governments as these are usually poor rural
communities. A possible compromise to this would involve
eliminatingonlytheportionremittedtothenationalgovernment
while retaining the portion of the royalties paid to the local
government.

3.7GrantingPEZAthePowertoRegulateDUsWithinEcozones

The proposal to allow the Philippine Economic Zone Authority


(PEZA) to exercise regulatory powersover DUs operating within
economic zones is also questionable. For one, it will create
confusionamongtheDUswhowillverylikelybeconfrontedwith
the possibility of having to comply with conflicting regulatory
requirementsimposedbytworegulatoryagencies,i.e.,ERCand
PEZA. Furthermore, the technical competence of PEZA to

11

regulate the DUs located within the ecozones is highly suspect.


Ontheotherhand,theERC,sinceitscreationin2001,hasbeen
slowly but surely building its staff capabilities, through
institutionaldevelopmentandtraining,toenableittoeffectively
meet its new responsibilities. Even assuming that PEZA will
ultimately have the technical capability to effectively regulate
theDUs,onemustquestionwhetherthecostofmaintainingtwo
regulatoryagencieshavingjurisdictionoverthesamesubsector
isjustifiedandinthepublicinterest.

3.8DistributionRelatedBusinesses

SB2121proposesthatDUsmustfirstundergohearingsandgain
approval from the ERC before engaging in related businesses.
This amendment aims to ensure that the distribution business
does not subsidize the related enterprise nor encumber its
distributionassetstosupportsuchrelatedbusiness.

While this amendment might seem to be putting too much
regulatoryinterventionintotheaffairsofDUs,thushinderingthe
competitiveness of the utility as well as adding to the already
heavyworkloadoftheERC,thismighthavetobeanecessityin
ordertoavoidabuseonthepartoftheDU.

3.9SelfgeneratedElectricity

The amendment also proposes that selfgenerated electricity


shouldbeexemptedfrompayingtheUniversalChargeexceptfor
the environmental charge component. This amendment should
encourage the development of more alternative generation
sources in the country while further promoting competition in
the market. The charge for the environmental fund must be
retainedthough.

3.10OtherAmendments

In addition to the proposed amendments discussed above, SB


2121 also proposes several other changes to the EPIRA aimed
mostly at clearing up vague provisions, improving or adding
definitions and strengthening consumer protection. The most
important of these is the expansion of the section detailing the
rightsofelectricityconsumers.Thebillexplicitlyspellsoutthese
rightsaswellasthe mandatesofthe ERC toensurethatthese
rightsareprotected.




12

IV. Conclusion

While some sectors have argued that it is probably too soon to
amendalawsuchastheEPIRAwhichhasonlybeenaroundfora
very short time, one cannot ignore the clamor of power
consumersforcheaperandbetterelectricityservice.Itishoped
that the amendments arising from the current debates in the
Senate will result in an improved version of the law which
ensures that the reforms envisioned in the EPIRA will come to
pass, ultimately leading to reasonable power rates, sufficient
capacityandanenvironmentequallyprotectiveofinvestorsand
consumers.

References

Asian Development Bank (2000). Developing Best Practices for


PromotingPrivateSectorInvestmentinInfrastructure:Power.
Bacon, R.W. and BesantJones, J. (June 2002). Global Electric Power
Reform, Privatization and Liberalization of the Electric Power
IndustryinDevelopingCountries.WorldBank.
BesantJones, J. (September 2006). Reforming Power Markets in
DevelopingCountries:WhatHaveWeLearned?,WorldBank.
Brown, G., de Dios, E. and Valderrama, H., Philippines: Power Sector
ProfileandRoadmap.,ADB
Department of Energy (2007). 11th Status Report on EPIRA
Implementation.
____________________ (2006) Philippine Energy Plan 2006: Power
DevelopmentPlanSupplement.
Lamech, R. and Saeed, K (May 2003). What International Investors
LookforWhenInvestinginDevelopingCountries:Resultsfrom
a Survey of International Investors in the Power Sector.World
Bank.
Murray, K. and Stevenson, T. (August 2004). Analysis of the state of
competition and investment and entry barriers to New
Zealands wholesale and retail electricity markets. Electricity
Commission(NewZealand).
Nikomborirak, D. and Manachotphong W. (July 2007). Electricity
Reform in Practice: The Case of Thailand, Malaysia, Indonesia
andthePhilippines.UNCTAD.
Pollitt, M. (January 2005). Electricity Reform in Chile: Lessons for
DevelopingCountries.UniversityofCambridge.
Thomas, S. (July 2006). Electricity Liberalization Experiences in the
World.UniversityofGreenwich.
Woodhouse, E. (September 2005). The IPP Experience in the
Philippines.StanfordUniversity.
Woolf, F. and Jonathan Halpern (November 2001). Integrating
Independent Power Producers into Emerging Wholesale
Markets.


ThisPolicyBriefwasprincipallypreparedby PeterTuringan underthesupervisionofDirectorsMariaCristina
RubioPardalis and Merwin Salazar, and the overall guidance of OfficerinCharge, Executive Director Ronald
Golding.

TheviewsandopinionsexpressedhereinarethoseoftheSEPOanddonotnecessarilyreflectthoseofthe
Senate,ofitsleadership,orofitsindividualmembers.
13

S-ar putea să vă placă și