Documente Academic
Documente Profesional
Documente Cultură
-,
Failure of the Omai Tailings Dam
Steven G. Vick
GDp, and its 6-month shutdown follow- remained has provided a rare opportu- diversion conduit to temporarily pass
ing the failure caused financial hardship nity to understand the failure process. stream flows during starter dike con-
on a national scale. On an individual struction. Problems were encountered
Dam Design and Construction during conduit backfilling on two occa- I
level, many suffered from mine layoffs,
an embargo on seafood imports by sur- The configuration of the dam at the time sions when the CSP was crushed by
rounding Caribbean countries, and rip- of failure is shown on Fig. 1. It had been heavy equipment. Although the pipe
ple effects through the economy. Cash raised ahead of the rising impoundment was later repaired, portions of the over-
lying saprolite backfill were in-
tentionallyundercompacted to in-
crease its structural capacity un-
der these shallow-cover loading
conditions. The conduit con-
tained no conventional seepage
collars. Instead, only dry pow-
dered bentonite was sprinkled on
the surface of the saprolite back-
1- fill lifts. Moreover, downstream
portions of the conduit were back-
filled with sand that was not ade-
quately filtered at its contact with
the adjacentrockfill. Thus, thedi-
version conduit had no effective
seepage protection in any recog-
nized engineering sense despite
these conditions promoting con-
centrated seepage around it.
Fig. 1 also shows the thin filter
sand zone intended to provide
piping protection for the core. Un-
derlying the sloping core and
Crest and exposed core of the Omai tailings dam after failure in August, 1995. overhanging the rockfill, this fil-
ter sand was itself to be protected
flow interruption to OGML itself level in customary tailings dam fashion by transition rockfill immediately adja-
amounted to an estimated US$15 mil- from an initial starter dike to a height of cent to it. Gradation specifications on
lion, with direct losses approaching this 45 m. The dam contained an upstream- Fig. 2 show that with allowable particle
amount. sloping core and a downstream rockfill sizes from 25 to 600 mm, the transition
section, with foundation materials hav- rockfill was far to coarse to have been
Within days the government con- ing the classic weathering profile of re- placed without segregation. This not-
vened a Commission of Inquiry and es- sidual saprolite soils derived from par- withstanding, the sole gradation test
tablished three technical committees to ent andesite/diabase rocks. These performed during construction showed
report on various aspects of the failure. clayey, low-permeabilitysoils provided the rockfill to be substantially coarser
One of these, the Dam Review Tham fill material for the dam core, and they than even the specified range, with a
(DRT) was charged with determining also comprised a major component of rockfill/sand piping ratio (dlS/d8S)of as
technical causation, with an important the mine waste materials excavated as much as 100. This filter incompatibility
additional purpose of promoting an un- pit overburden. This saprolite mine is shown clearly on the photos of Fig. 3,
derstanding of these causes within the waste was deposited in a wide zone ad- illustrating how active piping of sand
professional community, the mining in- into rockfill on the dam crest was occur-
jacent to and contiguous with the down-
dustry, and the public of Guyana. stream rockfill section of the dam, ex- ring merely from surface infiltration.
From a geotechnical standpoint, the tending outward 400 m to the Omai Despite its evident flaws related to
failure was unusual in that nowhere did diversion conduit seepage protection
River and confining the rockfill zone in
the dam physically breach. Rather, the all except the two limited areas near the and filter incompatibility the dam was
integrity of its sloping core was com- abutments where the failure discharges well instrumented, and piezometric data
pletely lost, resulting in release of all of emerged. typical of that shown on Fig. 1 gave no
the contaminated water but compara- indication of impending internal ero-
tively little of the tailings solids con- Tho features on Fig. I are of special sion. These data did reveal, however, an
tained in the impoundment at the time. interest. The starterdike containeda 900 anomalous rise in water level within the
The virtually intact body of the dam that mm dia. corrugated steel pipe (CSP) rockfill that appears to have been pro-
GeotechnioalNews, September 1996 35
GEOSPEC
duced by blockage of underdrains be- overlying riprap, while some like that creased an additional 7 m to the higher
neath the saprolite mine waste that were shown on Fig.4b were open-throatsink- level shown on Fig. 1, directly contact-
intended to evacuate water from the holes in the core fill that continued to ing, saturating, and submerging a sub-
rockfill. This allowedsurface waterrun- form and collapse weeks after failure. stantial portion of this formerly dry
off to infiltrate, accumulate, and rise Together these sinkholes and subsi- f1ltersand.
within the rockfill beginning almost two dence featuresclearly showinternal ero- The hanging f1ltersand had been able
years before the failure and ending the sion to have been responsible for loss of to bridge the large voids in the rockfill
following year when the water level sta- core integrity. Measurements of sus- beneath it only by arching due to capil-
bilized at the pre-failure level shown on pended solids in the failure discharge larity at its original placement moisture
Fig. 1 with no evident effects on the suggest that about 25,000 m3 of core content. With its apparent cohesion de-
dam. material may have been lost, amounting stroyed by submergence and saturation,
to about 2% of total core volume. sand trickled freely downward into and
Forensic Studies Further evidence for piping around through the rockfill voids by gravity
The most striking and visible features of the diversionconduit was obtained from alone, reducing or eliminating support
the failure were longitudinal cracks ex- the angled boreholes shown on Fig. 5 for overlying portions of the inclined
tending the full length of the dam core (drilled from a fillpad extendinginto the core. This mechanism of f1lter sand
exposed on the crest. The widest of slimes not depicted) that indicated "dropout" occurred more-or-less uni-
these shown on the cover photo was voids, cavities, and softened zones at formly and simultaneously over the
accompanied by rotation and tilting of various locationsabove, around,andbe- length of the dam as the internal rockfill
the upstream portion of the crest inward neath the CSP conduit. After serving its water level rose accordingly.
toward the impoundment. While short temporary function, the conduit had The unsupported portion of the core
transverse cracks were present locally, been plugged with concrete at its up- then dropped and tilted as graben-like
continuous or pervasive transverse stream end, with the rest remaining blocks on the upstream slope, princi-
pally beneath the water contained in the
impoundment. Associated cracking and
he most striking and visible features of the failure related damage rapidly produced sink-
GEOSPEC
__ tailingsslimes
_ filter sand - -- pre-failure piezometric surface at base of dam
_ water
saprolite
rockfill - - - phreatic level in rockfill during failure
o 10 20 30 40 50m
I I I I I I
_
- -. rockfill tested during construction
saprolite (typ.)
"transition"rockfillspecification
PARTICLESIZE (mm)
1000 100 10 1.0 0.1 0.01 0.001
100
90
....
:r:: o
-
1:::1 80
LL.I
70
::...
oQ
cr: 60
LL.I
-
:e: 50
"'-
....
:e: 40
LL.I
c.:o
cr: 30
LL.I
Q.
20
10
C088LES/BOULDERSI GRAVEL
,I
Fig. (3a)
Dam crest showing (left to
right): remaining tailings,
riprap coil, filter sand (piles),
and roclifill
Fig. (3b)
Filter sandJroclifillcontact
Fig. (3c)
Filter sand piping into roclifill
from surface runoff
~
--,'"
GEOSPEC
Lessons Learned
The Omai case demonstrates yet again
that no dam, tailings or otherwise,with-
out adequate seepage protection around
conduits or without adequate filters can
be expected to survive for long. Even
Fig. (4a) Core cracks exposed inforensic trench.
with the factors specific to the Omai
situation, these failure mechanisms are
by no means unique or new. Piping fail- - -----,;--
ures of earth-core rockfill structures as
early as 1904 at AvalonDam and again
at Schofield Dam (1928) led eventually
to the "Growdon"-type rockfill design
in 1942 with its emphasis on graded
filters, followed by manyrefinementsin
filter design, placement criteria, and
construction techniques since then.
Similarly, the historic preponderance of
piping failures around outlet conduits
has promoted wide acknowledgement
of the internal erosion vulnerabilities
these features produce, and USBR and
others have responded by developing
special procedures and design details to
combat them.
,..~t~ "..
. .~~
.
_ voidsor cavities
softened zones
I ..
[Z] forensicdrillholes
0
I
10
I
20m
I
--
Figure 5. Maximum extent of cavities and softened zones from forensic drilling
saprolitecorefill
fill markerlayers _
~ tensionzone
displacement
vectors
[Z] mapped
cracks
_ filtersand
rockfill
! Maximum
~L. duringfailure2
j
\ Zoneoffiller sand"dropouf'
o
I
10
1
20m
I