Sunteți pe pagina 1din 17

---

ericstricker Internal
Only

SDR Project 3G

Cluster Test Method

2021-12-7 1, Total17

--- ericstricker
---
ericstricker Internal
Only

Contents

1 Test Summary......................................................................................................................3
2 Coverage KPI Acceptance Test...........................................................................................5
2.1 PCPICH RSCP & Ec/Io Acceptance Test.......................................................................5

3 Voice Test.............................................................................................................................6
3.1 Call Success Rate AMR Acceptance Test......................................................................6
3.2 AMR Call-Drop Rate Acceptance Test............................................................................7
3.3 AMR Soft Handover Success Rate Acceptance Test.....................................................8

4 Video Call Test.....................................................................................................................9


4.1 Call Success Rate of Video Call Acceptance Test..........................................................9
4.2 Video Call-Drop Rate Acceptance Test........................................................................10

5 HSPA Test..........................................................................................................................11
5.1 PDP Activate Success Rate of HSDPA Acceptance Test.............................................11
5.2 PS Drop Rate Acceptance Test....................................................................................12
5.3 HSDPA single user service Average DL Throughput Acceptance Test_CAT8..............13
5.4 HSUPA single user service Average UL Throughput Acceptance Test_CAT3.............14
5.5 PS Soft Handover Success Rate Acceptance Test.......................................................15

6 ISHO Inter System Handover Test.....................................................................................16


6.1 AMR handover from WCDMA to GSM..........................................................................16

2021-12-7 2, Total17

--- ericstricker
---
ericstricker Internal
Only

1 Test Summary

  Key Performance Indicator Test Method Result

EcIo > -14 dB Drivetest: Scanner ok


Coverage
RSCP > -90dBm Drivetest: Scanner ok
Call setup success rate:  
Drivetest: Voice, ok
AMR Voice (3G-3G)
(Duration 45 seconds)
Accessibility Drivetest: Video, ok
Video
(Duration 45 seconds)
Drivetest: HSDPA,
PS
(Duration 90 seconds)
Drop Call Rate:  
Drivetest: Voice, ok
AMR Voice (3G-3G)
(Duration 45 seconds)
Retainability Drivetest: Video, ok
Video
(Duration 45 seconds)
Drivetest: HSDPA,
PS
(Duration 90 seconds)
Drivetest: HSDPA,
Average DL Throughput
(Duration 90 seconds)
Drivetest: HSUPA,
Average UL Throughput
Integrity (Duration 90 seconds)
Soft Handover Success Drivetest: Voice, ok

Rate CS (Duration 45 seconds)


Soft Handover Success Drivetest: HSDPA

Mobility Rate PS (Duration 45 seconds)


Drivetest: Voice,
ISHO (Inter-System
(Duration 45 seconds,Idel 45
Handover) CS
seconds)

2021-12-7 3, Total17

--- ericstricker
---
ericstricker Internal
Only

2021-12-7 4, Total17

--- ericstricker
---
ericstricker Internal
Only

2 Coverage KPI Acceptance Test

2.1 PCPICH RSCP & Ec/Io Acceptance Test

Objective
Coverage Pilot Test (Ec/Io & RSCP)

KPI Definition
This test item aims to acquire general coverage effect of pilot network.
Coverage radio = valid test kilometers / total test kilometers
The valid test kilometers should be satisfied for PCPICH RSCP >= -90dbm & Ec/Io >= -14dB;

Preset Conditions
 WCDMA system is in normal operation.
 Network Optimization work is completed.
 Driver Test Tools is connecting with GPS/Scanner is ready and operate normally.

Test Procedures

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route.

Record the value of PCPICH RSCP and PCPICH Ec/Io.

Expected Results

Record the value of PCPICH RSCP and PCPICH Ec/Io and distributed information in geographical.

2021-12-7 5, Total17

--- ericstricker
---
ericstricker Internal
Only

3 Voice Test

3.1 Call Success Rate AMR Acceptance Test

Objective
Test the Acceptance of call success rate of UE origination AMR.

KPI Definition
 Call success rate of UE origination AMR = UE origination AMR call success times / UE origination
AMR call request times* 100%
 UE origination AMR call success times = sum of NAS message “Alerting” received successfully by
MO
 UE origination AMR call request times = sum of “RRC Connection Request” message sent by MO.
Resent of the message should only record once in the same calling procedure.
 The Call setup failure times caused by CAC should be eliminated;
 The Call setup failure times caused by CN or UE should be eliminated;

Preset Conditions
 WCDMA system is in normal operation and PSTN is well connected and runs normally.(If there is
no PSTN, UE can be used instead).
 Network Optimization work is completed.
 Driver Test Tools is connect with GPS/Scanner and Test UE is ready and operate normally.
 The drive test route is ready and should be satisfied for PCPICH RSCP >= -90dbm & Ec/Io >=
-11dB.
 The test UE is put in the test vehicle, and moved around within the predetermined drive test route.

Test Procedures

Configure the test plan of Voice Call in the probe , input the number of MT(PSTN or UE) firstly

The duration of one call is set 45s

The interval time between two calls is set 10s

Click the start test icon on the toolbar in the probe to start the test, at the same time save the log file

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route

Click the stop test icon on the toolbar to end the test after finishing the test

Expected Results

This KPI can be provided by Genex Assistant

2021-12-7 6, Total17

--- ericstricker
---
ericstricker Internal
Only

3.2 AMR Call-Drop Rate Acceptance Test

Objective
Test the KPI of AMR call-drop rate.

KPI Definition
 AMR Call-drop rate = AMR call drop times / AMR call setup success times * 100%
 AMR call setup success times = the times of NAS message “Alerting” received successfully by MO
 AMR call drop times should be the sum of the three conditions occurs in the procedure of Call as
below:
(a) Received any BCH message
(b) Received RRC release message and the cause is not “Normal”
(c) received CC DISCONNECT,CC Release Complete or CC Release, and the cause is not ”
Normal Clearing”, not “Normal”,” Unspecified”
 The Call Drop times caused by CN or UE should be eliminated

Preset Conditions
 WCDMA system is in normal operation
 Network Optimization work is completed.
 MT UE should be located in good coverage area (RSCP > -80dbm & Ec/Io > -8dB).
 The drive test route is ready and should be satisfied for PCPICH RSCP >= -90dbm & Ec/Io >=
-11dB.
 The test UE is put in the test car, and moved around within the predetermined drive test route.

Test Procedures

Configure the test plan of Voice call in the probe, input the number of the MT’s phone number firstly

The duration of one call is set 45s

The interval time between two calls is set 10s

Click the start test icon on the toolbar in the probe to start the test, at the same time save the log file

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route

Click the stop test icon on the toolbar to end the test after finishing the test

Expected Results

2021-12-7 7, Total17

--- ericstricker
---
ericstricker Internal
Only

3.3 AMR Soft Handover Success Rate Acceptance Test

Objective
Test the KPI of AMR soft handover success rate.

KPI Definition
 AMR Call Handover Successful Rate = Number(Active Set Update Complete) / Number(Active Set
Update)×100%
 The Soft Handover failure times caused by UE should be eliminated.

Preset Conditions
 WCDMA system is in normal operation.
 Network Optimization work is completed.
 Open the soft handover algorithm switch using this command line: SET CORRMALGOSWITCH:
HOSWITCH=SOFT_HANDOVER_SWITCH-1;
 Driver Test Tools is connect with GPS/Scanner and Test UE is ready and operate normally.
 The drive test route is ready and should be satisfied for PCPICH RSCP >= -90dbm & Ec/Io >=
-11dB
 Test UE is put in the test vehicle, and moved around within the predetermined drive test route.

Test Procedures

Configure the test plan of Voice call in the probe, input the number of the MT’s phone number firstly

The duration of one call is set 45s

The interval time between two calls is set 10s

Click the start test icon on the toolbar in the probe to start the test, at the same time save the log file

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route

Click the stop test icon on the toolbar to end the test after finishing the test

Expected Results

This KPI can be provided by Genex Assistant

2021-12-7 8, Total17

--- ericstricker
---
ericstricker Internal
Only

4 Video Call Test

4.1 Call Success Rate of Video Call Acceptance Test

Objective
Test the Acceptance of call success rate of VP Acceptance Test

KPI Definition
 Call success rate of video call = video call success times / video call request times * 100%
 UE origination VP call success times =sums of NAS message “Alerting” received successfully by
MO
 UE origination VP call request times =sum of “RRC Connection Request” message sent by MO.
Resent of the message should only record once in the same calling procedure.
 The Call setup failure times caused by CAC should be eliminated;
 The Call setup failure times caused by CN or UE should be eliminated;

Preset Conditions
 WCDMA system is in normal operation
 Network Optimization work is completed.
 Driver Test Tools is connect with GPS/Scanner and Test UE is ready and operate normally.
 The drive test route is ready and should be satisfied for PCPICH RSCP >= -90dbm & Ec/Io >=
-11dB.
 The test UE is put in the test vehicle, and moved around within the predetermined drive test route.
 The MT UE is in the condition of PCPICH RSCP >= -80dbm & Ec/Io >= -8dB

Test Procedures

Configure the test plan of Video phone in the probe, input the number of MT firstly

The duration of one call is set 45s

The interval time between two calls is set 10s

Click the start test icon on the toolbar in the probe to start the test, at the same time save the log file

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route

Click the stop test icon on the toolbar to end the test after finishing the test

Expected Results

This KPI can be provided by Genex Assistant

2021-12-7 9, Total17

--- ericstricker
---
ericstricker Internal
Only

4.2 Video Call-Drop Rate Acceptance Test

Objective
Test the KPI of Video call-drop rate.

KPI Definition
 Video Call-drop rate = call drop times / AMR call setup success times * 100%
 Video Call setup success times = the times of NAS message “Alerting” received successfully by
MO
 Video Call-drop times should be the sum of the three conditions occurs in the procedure of Call as
below:
(a) Received any BCH message
(b) Received RRC release message and the cause is “Not Normal”
(c) received CC DISCONNECT,CC Release Complete or CC Release, and the cause is not
“Normal Clearing”, not “Normal”,” Unspecified”
 The Call Drop times caused by CN or UE should be eliminated

Preset Conditions
 WCDMA system is in normal operation
 Network Optimization work is completed.
 MT UE should be located in good coverage area (RSCP > -80dbm & Ec/Io > -8dB).
 The drive test route is ready and should be satisfied for PCPICH RSCP >= -90dbm & Ec/Io >=
-11dB.
 The test UE is put in the test car, and moved around within the predetermined drive test route.

Test Procedures

Configure the test plan of Video phone in the probe, input the number of MT firstly

The duration of one call is set 45s

The interval time between two calls is set 10s

Click the start test icon on the toolbar in the probe to start the test, at the same time save the log file

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route

Click the stop test icon on the toolbar to end the test after finishing the test

Expected Results

This KPI can be provided by Genex Assistant

2021-12-7 10, Total17

--- ericstricker
---
ericstricker Internal
Only

5 HSPA Test

5.1 PDP Activate Success Rate of HSDPA Acceptance Test

Objective
Test the KPI of PDP activate success rate.

KPI Definition
 PDP activate success rate = PDP activate success times / PDP activate request times * 100%
 PDP activate success times = sum of NAS message “PDP Activation Accept” received successfully
by UE
 PDP activate request times = sum of “RRC Connection Request” message sent by the UE. Resent
of the message should only record once in the same calling procedure.
 The Call setup failure times caused by CAC should be eliminated;
 The Call setup failure times caused by CN or UE should be eliminated;.

Preset Conditions
 WCDMA system is in normal operation.
 Network Optimization work is completed.
 Set the UE's expansion service quantity parameters Max bit-rate as UL 64/DL64K in HLR.
 The drive test route is ready and should be satisfied for PCPICH RSCP >= -90dbm & Ec/Io >=
-11dB.
 The test UE is put in the test vehicle, and moved around within the predetermined drive test route.

Test Procedures

Configure the test plan of Ftp Download in the probe,input the remote file to be downloaded.

The duration of one call is set 90s

The interval time between two calls is set 30s

Click the start test icon on the toolbar in the probe to start the test, at the same time save the log file

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route

Click the stop test icon on the toolbar to end the test after finishing the test

Expected Results

This KPI can be provided by Genex Assistant

2021-12-7 11, Total17

--- ericstricker
---
ericstricker Internal
Only

5.2 PS Drop Rate Acceptance Test

Objective
Test the KPI of PS Plan Full-Coverage Bit Rate Drop Rate

KPI Definition
 PS-drop rate = PS-drop times / PS Activate success times * 100%

Preset Conditions
 WCDMA system is in normal operation.
 Network Optimization work is completed.
 Set the UE's expansion service quantity parameters Max bit-rate as UL 64/DL 64K in HLR.
 The test UE is put in the test car, and moved around within the predetermined drive test route.
 The drive test route is ready and should be satisfied for PCPICH RSCP >= -90dbm & Ec/Io >=
-11dB.

Test Procedures

Configure the test plan of Ftp Download in the probe,input the remote file to be downloaded.

The duration of one call is set 90s

The interval time between two calls is set 30s

Click the start test icon on the toolbar in the probe to start the test, at the same time save the log file

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route

Click the stop test icon on the toolbar to end the test after finishing the test

Use assistant to calculate the PS drop rate.

Expected Results

This KPI can be provided by Genex Assistant

2021-12-7 12, Total17

--- ericstricker
---
ericstricker Internal
Only

5.3 HSDPA single user service Average DL Throughput Acceptance


Test_CAT8

Objective
Test the KPI of HSDPA single user average DL throughput by CAT8

Network diagram
None

Preset Conditions
 WCDMA system is in normal operation.
 Network Optimization work is completed.
 This UE is subscribed to the Background/Interactive services at 384 Kbit/s (UL) and 7424Kbit/s
(DL) on the HLR.
 FTP server is ready, and make sure the FTP server can provide more higher than 3.6Mbps
upload/download data throughput.
 Test UE or high level software should have the ability of record service bit rates information.
 Driver Test Tools is connect with GPS/Scanner and Test UE is ready and operate normally.
 The drive test route is ready and should be satisfied for CQI >= 21.
 HsPdschCodeNum=10, MPO=6, PDU size=656, MaxTxPower=430, PCPICHPower=330,;
 The bandwidth of Iub is not limited, admeasure the power dynamic.
 Download by multithreading.
 MTU=1500.
 The test UE is put in the test car, and moved around within the predetermined drive test route.

Test Procedures

CAT8 UE is put in the test car; test UE connect to PC normally, and initiate PS UL384K DL7424K PDP
Active operation successfully, then start FTP (using 5 threads) to download given files (above 100MB).

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route.

FTP Tools begin to record the service download bit rates (or using monitor software such as DU Meter),
and RNC begin to record the DL Mac’s throughput of test UE.

Expected Results

This KPI can be provided by Genex Assistant

2021-12-7 13, Total17

--- ericstricker
---
ericstricker Internal
Only

5.4 HSUPA single user service Average UL Throughput Acceptance


Test_CAT3

Objective
Test the KPI of HSUPA single user average UL throughput by CAT3

Network diagram
None

Preset Conditions
 WCDMA system is in normal operation.
 Network Optimization work is completed.
 This UE is subscribed to the Background/Interactive services at 1536 Kbit/s (UL) and 3648Kbit/s
(DL) on the HLR.
 FTP server is ready, and make sure the FTP server can provide more higher than 2Mbps
upload/download data throughput.
 Test UE or high level software should have the ability of record service bit rates information.
 Driver Test Tools is connect with GPS/Scanner and Test UE is ready and operate normally.
 Average PCPICH RSCP = -80dbm &PCPICHPower=330,;
 The ULRTWP and bandwidth of Iub are not limited.
 Upload by multithreading.
 MTU=1500.
 The test UE is put in the test car, and moved around within the predetermined drive test route.

Test Procedures

CAT3 UE is put in the test car; test UE connect to PC normally, and initiate PS UL1536K DL3648K PDP
Active operation successfully, then start FTP (using 5 threads) to upload given files (above 20MB).

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route.

FTP Tools begin to record the service upload bit rates (or using monitor software such as DU Meter), and
RNC begin to record the UL Mac’s throughput of test UE.

Expected Results

This KPI can be provided by Genex Assistant

2021-12-7 14, Total17

--- ericstricker
---
ericstricker Internal
Only

5.5 PS Soft Handover Success Rate Acceptance Test

Objective
Test the KPI of PS soft handover success rate.

KPI Definition
 PS Softer Handover Successful Rate = Number(Active Set Update Complete) / Number(Active Set
Update)×100%
 The Soft Handover failure times caused by UE should be eliminated.

Preset Conditions
 WCDMA system is in normal operation.
 Network Optimization work is completed.
 Open the soft handover algorithm switch using this command line: SET CORRMALGOSWITCH:
HOSWITCH=SOFT_HANDOVER_SWITCH-1;
 Driver Test Tools is connect with GPS/Scanner and Test UE is ready and operate normally.
 The drive test route is ready and should be satisfied for PCPICH RSCP >= -90dbm & Ec/Io >= -11dB
 Test UE is put in the test vehicle, and moved around within the predetermined drive test route.

Test Procedures

Configure the test plan of Ftp Download in the probe,input the remote file to be downloaded.

The duration of one call is set 90s

The interval time between two calls is set 30s

Click the start test icon on the toolbar in the probe to start the test, at the same time save the log file

The test vehicle carried with GPS/Scanner/Test UE and DT Tools moved around within the predetermined
drive test route

Click the stop test icon on the toolbar to end the test after finishing the test

Expected Results

This KPI can be provided by Genex Assistant

2021-12-7 15, Total17

--- ericstricker
---
ericstricker Internal
Only

6 ISHO Inter System Handover Test

6.1 AMR handover from WCDMA to GSM

Objective
Check whether UE can perform Inter-System CS service handover from WCDMA to GSM

Prerequisites
The GSM and WCDMA system are both configured correctly and operate normally.
A WCDMA Cell 1 and a GSM Cell 2 are configured as adjacent cell
PSTN is well connected and also runs normally.
UE is a dual-mode phone which can support both GSM and WCDMA network. UE camp on 3G network in
Cell 1.
Tracing Uu and Iu Interface in RNC and tracing Iu Interface in MSC.
In 3G MSC Server, tracing user interface by IMSI or tracing links to 2G network in MSC Server

Procedure

Establish a UE-PSTN voice call successfully

The duration of one call is set 45s

The interval time between two calls is set 45s

When the UE handover from 3G to 2G and end in 2G ,the 2G network will force the UE reselect from 2G
to 3G

Remarks

BSC 2G MSC 3G MSC RNC UE

PREPARE HANDOVER RELOCATION REQUIRED


HANDOVER REQUEST REQUEST

HANDOVER RESPONSE
ack. PREPARE HANDOVER
RESPONSE
IAM
ACM HANDOVER FROM
RELOCATION COMMAND
UTRAN COMMAND
HANDOVER DETECT PROCESS SIGNALLING

HANDOVER COMPLETE SEND END SIGNAL


ANM
IU RELEASE COMMAND
IU RELEASE COMPLETE

 RELOCATION REQUIRED – relocation target CID


 HANDOVER REQUEST -- target CID in signal info container
 PREPARE HANDOVER RESPONSE – Handover Number
 RELOCATION COMMAND – container for 2G access network information
 PROCESS SIGNALLING – Handover Detect (optional message)
 SEND END SIGNAL – Handover Complete
 IU RELEASE COMMAND – (release RAN resource)

2021-12-7 16, Total17

--- ericstricker
---
ericstricker Internal
Only

 The 2G network message flow figure is only for reference

Thank You for

Reading

2021-12-7 17, Total17

--- ericstricker