Documente Academic
Documente Profesional
Documente Cultură
AbstractThis paper presents a concept for local monitoring of Power systems become more vulnerable to voltage collapse
the onset of voltage collapse, protective, and emergency control in whenever generator reactive-power limits are encountered [10],
the presence of voltage-sensitive loads. The onset of voltage collapse [11]. Encountering the reactive-power limits instantaneously
point is calculated based on the load characteristics and simulated
voltage and current phasors measurements, which are provided by changes the dimension of the state space and the system
a network of phasor-measurement units. If the stability margin is equations, causing discontinuous change in the stability margin
small and the reactive-power reserves are nearly exhausted, then of the system. The system may become immediately unstable.
controls to steer the power system away from the critical point will Therefore, the estimate of voltage-stability margin can be
be activated. misleading if not combined with generator reactive-power
Index TermsEmergency control, load modeling, protective re- limitations.
laying, voltage stability, voltage-stability index. In this paper, we propose a wide-area network of phasor
measurement units as agents for voltage-stability monitoring
I. INTRODUCTION and control. The criticality of the current operating point is de-
termined based on the estimates of the voltage-stability margin
Fig. 1. Load bus and the rest of the system represented as a voltage source,
transmission line, and the corresponding phasor diagram.
VSI VSLBI (4) where represents a set of generator units operating in the
PV mode. The time remaining to the next PV-PQ transition rep-
resents the reactive-power reserve index RPRI
where denotes the load-bus index and represents a set of
the system load buses. Comparison of VSLBI provides infor-
mation on relative vulnerability of various buses, which can be RPRI (7)
used for remedial actions.
Everytime RPRI gets close to zero, a generator may reach
A. Reactive-Power Reserve Index its reactive-power limit.
The two main causes of a reactive-power reaching a limit
in a generator are the excitation current limit and the armature III. PROTECTION AND CONTROL SCHEME AGAINST
thermal limit [12]. Potentially adverse effects of generator reac- VOLTAGE COLLAPSE
tive capability limits on voltage stability are well known [10],
[11]. For heavy loading conditions, reactive-power produced by The PMUs are placed at all load buses (denoted PMU )
the generator increases with load to maintain its terminal voltage and generator buses (denoted PMU buses). A PMU mea-
and when it reaches its limit, the generator loses voltage control sures voltage and all incident current phasors in discrete time
and switches from PV (constant terminal voltage) to PQ (con- intervals at the bus where it is installed, which enable: 1)
stant reactive-power output) mode of operation. At the transition monitoring of the power injection at the bus; and 2) tracking of
points, VSI changes abruptly. The outcomes of the PV-PQ tran- the parameters of the voltage source and line modeling the rest
sitions are hard to predict, because they introduce the disconti- of the system as seen from the bus, at every time instant .
nuities in the model. As the system moves closer to the stability The existence of the high-speed Synchronous Optical Net-
limit and VSI approaches unity, the PV-PQ transitions become work (SONET) among PMUs is assumed (see Fig. 2). SONET
more dangerous. Therefore, it is necessary to monitor the system allows each PMU to be provided with real-time information on
reactive-power reserves and deploy protective/control actions if generator reactive-power margins and estimates when generator
the reserves are nearly exhausted and is below a certain reactive-power reserves will be exhausted. The line rate ranges
threshold. from 51.84 Mb/s to 9.953 Gb/s. Latency times of information
The PV-PQ transition of generator can be estimated by mon- through the network are more than adequate for the proposed
itoring its reactive-power reserve , where the gen- application.
erator reactive-power output at a time instant is modeled as a Parameters of each two-bus equivalent and , which
nonlinear function of time that fits a sliding window of data sam- model the rest of the system as seen from load bus , are
ples. For the sake of illustration, lets assume the linear model continuously updated from a sliding window of voltage and
and estimate the time instant at which the reactive-power of unit current phasor measurements.
will be exhausted as The process of determining the voltage-stability margin at
load bus and the appropriate control actions can be summa-
(5) rized in the following steps.
Step 1) Perform local phasor voltage and current measure-
ments at .
where denotes the current time instant, while Step 2) Calculate parameters of a two-bus equivalent
represents the rate of change of reactive-power generated by and .
unit , which is calculated from two consecutive measurements. Step 3) Determine the VSLBI value and translate it into a
Therefore, the occurrence of the next PV-PQ transition in the time estimate (see Section IV).
system is estimated by Step 4) From the received information on reactive-power re-
serve of every generator, estimate the occurrence of
(6) a new PV-PQ transition .
MILOSEVIC AND BEGOVIC: PROTECTION AND CONTROL USING A NETWORK OF PHASOR MEASUREMENTS 123
(8)
Fig. 4. Equivalent of a simple two-bus system with the ZIP load. Fig. 6. VSI for the IEEE 39-bus system without reactive constraints.
Fig. 5. Upper portions of P -V curves obtained with the different types of Fig. 7. Load voltage V and voltage drop across the equivalent impedance
load in the two-bus system in Fig. 1. 1 V at bus 29 for the IEEE 39-bus system without reactive constraints.
Fig. 8. V SI for the IEEE 39-bus system with reactive-power limits enforced.
Fig. 11. Rate of change of reactive-power generated by unit 37 in IEEE 39-bus
system with 75% P and 25% Z loads.
Fig. 12. Reactive-power reserve indicator (RPRI) for the IEEE 39-bus system
Fig. 9. Load voltage V and voltage drop across the equivalent impedance
1 V at bus number 23 for the IEEE 39-bus system with reactive constraints.
with 75% P and 25% Z load.
Fig. 13. Estimates of the time to voltage collapse for 23 and the next PV-PQ
Fig. 10. Estimated time margin to voltage collapse t for bus 23 in the IEEE
39-bus system with reactive-power limits enforced.
=0
transition with respect to t in the IEEE 39-bus system with 75% PQ and
25% Z load.
that precedes voltage instability, increases above unity as the faster than during the light loading conditions, when all gener-
voltage-dependent loads represent a greater potion of the total ators in the system operate in the PV mode.
system load when the system operates with the limited reac- Fig. 12 shows RPRI for the 39-bus system with 75% PQ and
tive-power resources. This suggests that the voltage security as- 25% Z load. Between the initial loading and the critical
sessment and control should not rely solely on the VSI. Since loading , the RPRI reached the value of zero six
the critical points are transition points, the VSI needs to be com- times, indicating that six generator units reached their reactive-
bined with the estimates of the unit PV-PQ transitions. power limits. These are generators 30, 32, 35, 36, 33, and 34.
The rate at which the reactive-power reserve of unit is being The VSI smaller than a certain threshold, for example, VSI
exhausted depends on the number of units already op- and the RPRI close to zero, are predictors of voltage collapse.
erating at reactive-power limits and on the closeness of unit These parameters represent a trigger for the control activation
to the critical buses. Fig. 11 illustrates for unit 37, at a certain bus.
which stays in the PV mode at all times. Discontinuities in its Fig. 13 shows the estimate of the time margin to voltage col-
correspond to the PV-PQ transitions in the system. lapse for bus 23 from its time-varying two-bus equivalent and
When the system is close to the voltage-stability limit, the re- the estimate of the minimum margin to the next PV-PQ transi-
active-power is being exhausted from unit 37 almost 10 times tion , which is calculated as in (6). Note that both variables
126 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 18, NO.1, FEBRUARY 2003
are calculated with respect to the time instant . The PV-PQ system of two linear equations with four unknowns, which can
transitions occur every time when there is a stepup change in be written in the following form:
and a stepdown change in . Two curves approach one another
and become dangerously close if the next estimated PV-PQ tran- (16)
sition is a critical one. The dark circle illustrates a zone where where
the protective and the control actions must be deployed to avoid
voltage collapse.
The control actions in the vicinity of the critical bus may be
1) activation of the available reactive-power reserves;
2) blocking of the tap changers;
3) voltage reduction at the feeders connected to the corre-
sponding and the neighboring buses
4) load shedding of the nearest consumers if the above mea- Having the stream of voltage and current phasor measure-
sures do not prove to be effective. ments, the vector of unknowns can be determined by using
the RLS scheme
VI. CONCLUSION
A novel concept for the detection of voltage instability and
the corresponding control in the presence of voltage-dependent
loads has been presented. The onset of the voltage collapse (17)
point to current operating conditions is determined based on the
VSLBI indicator calculated from the local voltage and the cur- where is the identity matrix, while is a forgetting factor,
rent phasors measurements and the system-wide information on which assigns lower weight to the old measurements in the re-
reactive-power reserves. The algorithm suggests control actions cursive scheme.
to be deployed when the stability margin is small and the reac- Note that and can be identified only if there is a change
tive-power reserves are nearly exhausted. Namely, limitations in in the system state. However, if the system stays in the same op-
reactive-power generation cause sudden changes in the VSLBI erating point, its steady state does not change and voltage col-
and prevent the operator from acting in time. As illustrated in lapse cannot occur. As soon as there is a change of the system
the paper, this problem is more emphasized as voltage-depen- state that can lead to deterioration of voltage stability, it is pos-
dent loads represent a greater portion of the total load. For these sible to determine the parameters of the system equivalent and
reasons, a decision on the triggering of protective/emergency proceed with the decision regarding any protective action.
controls cannot be made by considering the VSLBI value only.
It needs to be revised by using the information on generator-re- REFERENCES
active reserves. The proposed concept for voltage-stability pro-
[1] I. Dobson, The irrelevance of load dynamics for the loading margin to
tection and control does not jeopardize the existing protection voltage collapse and its sensitivities, Bulk Power Syst. PhenomenaIII:
systems. On the contrary, it is supposed to be added on top of Voltage Stability, Security Contr., pp. 509519, Aug. 1994.
the existing control schemes to give them an extra quality. [2] F. Gubina and B. Strmcnik, Voltage collapse proximity index determi-
nation using voltage phasor approach, IEEE Trans. Power Syst., vol.
10, pp. 788793, May 1995.
APPENDIX [3] G. Verbi and F. Gubina, A new concept of protection against voltage
collapse based on local phasors, in Proc. Int. Conf. Power Syst.
IDENTIFICATION OF THE SYSTEM EQUIVALENT PARAMETERS Technol., vol. 2, Dec. 2000, pp. 965970.
[4] K. Vu, M. M. Begovic, D. Novosel, and M. M. Saha, Use of local
The parameters of the system equivalent used for modeling measurements to estimate voltage-stability margin, IEEE Trans. Power
the rest of the system as seen from the local bus are not constant Syst., vol. 14, pp. 10291035, Aug. 1999.
(see Fig. 1), but vary slightly reflecting changes in the power [5] A. G. Phadke, Synchronized phasor measurements in power systems,
IEEE Comput. Appl. Power, vol. 6, pp. 1015, Apr. 1993.
system operating conditions. Those parameters can identified [6] C. Barbier and J. P. Barret, An analysis of phenomena of voltage col-
from a sliding window of discrete data samples by using a pa- lapse on a transmission system, Revue Gnerale d Electricit, vol. 5,
rameter identification algorithm, such as the least square algo- pp. 672690, Oct. 1980.
[7] M. K. Pal, Voltage stability conditions considering load characteris-
rithm (LS) or the recursive least square (RLS) scheme with a tics, IEEE Trans. Power Syst., vol. 7, pp. 243249, Feb. 1992.
forgetting factor . The will give larger weight to recent [8] C. Concordia and S. Ihar, Load representation in power system stability
phasor measurements. studies, IEEE Trans. Power App. Syst., vol. PAS-101, pp. 969977, Apr.
1982.
The relationship among unknown parameters of the equiva- [9] T. J. Overbye, Effects of load modeling on analysis of power system
lent voltage source and as voltage stability, J. Int. Elect. Power Energy Syst., vol. 16, no. 5, pp.
well as the voltage phasor and current phasor 329338, Oct. 1994.
[10] M. A. Pai and M. G. OGrady, Voltage collapse analysis with reac-
measured at the load bus, at a time instant , tive generation and voltage dependent load constraints, Electric Mach.
is given as Power Syst., vol. 17, pp. 379390, 1989.
[11] I. Dobson and L. Lu, Voltage collapse precipitated by the immediate
(15) change in stability when generator reactive-power limits are encoun-
tered, IEEE Trans. Circuits Syst., pt. 1, vol. 39, pp. 762766, Sept. 1992.
[12] T. V. Cutsem and C. Vournas, Voltage Stability of Electric Power Sys-
After separating the imaginary and real parts, (15) yields the tems. Boston, MA: Kluwer, 1998.
MILOSEVIC AND BEGOVIC: PROTECTION AND CONTROL USING A NETWORK OF PHASOR MEASUREMENTS 127
Borka Milosevic (S98) received the B.Sc. degree Miroslav Begovic (S87M89SM92) received
in electrical engineering from the University of Bel- the B.Sc. and M.Sc. degrees in electrical engineering
grade, Belgrade, Yugoslavia, in 1992 and the M.Sc. from Belgrade University, Belgrade, Yugoslavia,
degree in electrical engineering from Georgia Insti- and the Ph.D. degree in electrical engineering from
tute of Technology, Atlanta, in 1998. She is pursuing Virginia Polytechnic Institute and State University,
the Ph.D. degree at Georgia Institute of Technology. Blacksburg.
She was a Research Engineer at EE Institute Currently, he is an Associate Professor in the
Nikola Tesla in Belgrade, from 1994 to 1997. Her School of Electrical and Computer Engineering,
research interests include power system security Georgia Institute of Technology, Atlanta. His
assessment and stability, application of multiagent interests are in the areas of computer applications
systems, and genetic algorithms to power systems in power system monitoring, protection and control,
monitoring and control. and design and analysis of renewable energy sources.