Documente Academic
Documente Profesional
Documente Cultură
The Supreme Court also added that the parties did not Facts:Respondent is the general contractor and
intend to limit resort to arbitration only to disputes operator of the Skyway project. Petitioner and
relating to physical construction activities, holding that respondent entered into an Engineering Procurement
an arbitration clause pursuant to E.O 1008 Construction Contract (EPCC) whereby petitioner would
[Construction Industry Arbitration Law] should be undertake the construction of Stage 1 of the Skyway
Project. During said construction, petitioner wrote deemed as an agreement to submit an existing or future
respondent on several occasions requesting payment of controversy to CIAC jurisdiction, "notwithstanding the
the formers interim billings, pursuant to provisions of the reference to a different arbitration institution or arbitral
EPCC/ however, respondent only partially paid the body in such contract x xx." Elementary is the rule that
interim billings. Respondent failed to do so despite when laws or rules are clear, it is incumbent on the court
demands to pay its outstanding balance. Petitioner filed to apply them. When the law (or rule) is unambiguous
with CIAC a request for arbitration to enforce its money and unequivocal, application, not interpretation thereof,
claims against respondent. is imperative.
CIAC ruled that it had jurisdiction over the same. CA
reversed. Now that Section 1, Article III [CIAC Rules of Procedure
Governing Construction Arbitration], as amended, is
Issue: WON CIAC has jurisdiction despite the EPCC submitted to test in the present petition, we rule to
provision requiring prior referral by the parties of their uphold its validity with full certainty. However, this should
dispute to the Dispute Adjudication Board not be understood to mean that the parties may no
longer stipulate to submit their disputes to a different
HELD: forum or arbitral body. Parties may continue to stipulate
as regards their preferred forum in case of voluntary
Section 4 of Executive Order No. 100818 defines the arbitration, but in so doing, they may not divest the CIAC
jurisdiction of CIAC, thus: of jurisdiction as provided by law. Under the elementary
principle on the law on contracts that laws obtaining in a
SECTION 4.Jurisdiction. - The CIAC shall have original jurisdiction form part of all agreements, when the law
and exclusive jurisdiction over disputes arising from, or provides that the Board acquires jurisdiction when the
connected with, contracts entered into by parties
parties to the contract agree to submit the same to
involved in construction in the Philippines, whether
the disputes arises before or after the completion of voluntary arbitration, the law in effect, automatically
the contract, or after the abandonment or breach gives the parties an alternative forum before whom they
thereof. These disputes may involve government or may submit their disputes. That alternative forum is the
private contracts. For the Board to acquire jurisdiction, CIAC. This, to the mind of the Court, is the real spirit of
the parties to a dispute must agree to submit the same E.O. No. 1008, as implemented by Section 1, Article III
to voluntary arbitration.
of the CIAC Rules.