Sunteți pe pagina 1din 4

Heunghwa Industry Co., Ltd. v. DJ Builders submit to voluntary arbitration.

Since the parties agreed


Corporation, G.R. No. to submit to voluntary arbitration in the construction
169095, December 8, 2008 contract, the authorization insisted upon by petitioner
Facts: was a mere superfluity.36
Heunghwa Industry Co., Ltd. (petitioner) is was able to The CA further cited National Irrigation Administration v.
secure a contract with the Department of Public Works Court of Appeals37 (NIA), where this Court ruled that
and Highways (DPWH) to construct the Roxas- active participation in the arbitration proceedings serves
Langogan Road in Palawan. to estop a party from denying that it had in fact agreed to
Petitioner entered into a subcontract agreement with submit the dispute for arbitration.
respondent DJ Builders Corporation to do earthwork,
sub base course and box culvert of said project. The Issue: whether or not the CIAC or the RTC has the
agreement contained an arbitration clause. The jurisdiction over the case.
agreed price was not fully paid, hence, respondent filed
before the Regional Trial Court (RTC) for "Breach of Held:
Contract, Collection of Sum of Money with Application Executive Order 100850 grants to the CIAC original and
for Preliminary Injunction, Preliminary Attachment, and exclusive jurisdiction over disputes arising from, or
Prayer for Temporary Restraining Order and Damages". connected with, contracts entered into by parties
Petitioner averred that it was not obliged to pay DJ involved in construction in the Philippines. In the case at
builders because the latter caused the stoppage of work. the bar, it is undeniable that the controversy involves a
Petitioner further claimed that it failed to collect from the construction dispute as can be seen from the issues
DPWH due to respondent's poor equipment referred to the CIAC, to wit:
performance. Parties submit specific issues, such as 1. Manpower and equipment standby time;
manpower and equipment standby time, unrecouped 2. Unrecouped mobilization expenses;
mobilization expenses, retention, discrepancy of billings, 3. Retention;
and price escalation for fuel and oil usage. The said 4. Discrepancy of billings; and
motion was granted by the RTC. 5. Price escalation for fuel and oil usage
Petitioner, filed with the RTC a motion to withdraw the
Order which referred the case to the CIAC, claiming it The Court notes that the Subcontract
never authorized the referral. Petitioner filed in the CIAC Agreement52 between the parties provides an arbitration
its opposition to the second motion to declare it in clause, to wit:
default, with a motion to dismiss informing the CIAC that Article 7
it was abandoning the submission of the case to it and Arbitration
asserting that the RTC had original and exclusive 7. Any controversy or claim between the Contractor and
jurisdiction over Civil Case No. 3421, including the five the Subcontractor arising out of or related to this
issues referred to the CIAC. Subcontract, or the breach thereof, shall be settled by
Respondent opposed the motion contending that arbitration, which shall be conducted in the same
petitioner was already estopped from asking for the manner and under the same procedure as provided
recall of the Order. in the Prime Contract with Respect to claims between
In other words, petitioner is questioning the jurisdiction of the Owner and the Contractor
the CIAC; while respondent is questioning the
jurisdiction of the RTC over the case. Submission to CIAC Jurisdiction - An arbitration clause
in a construction contract or a submission to
On appeal, CA: CA ruled against petitioner's main arbitration of a construction dispute shall be
argument that the arbitration clause found in the deemed an agreement to submit an existing or
subcontract agreement between the parties did not refer future controversy to CIAC
to CIAC as the arbitral body. The CA held that the CIAC jurisdiction, notwithstanding the reference to a
had jurisdiction over the controversy because the different arbitration institution or arbitral body in
construction agreement contained a provision to submit such contract or submission. When a contract
any dispute for arbitration, and there was a joint motion contains a clause for the submission of a future
to submit certain issues to the CIAC for arbitration.35 controversy to arbitration, it is not necessary for the
Anent petitioner's argument that its previous lawyer was parties to enter into a submission agreement before the
not authorized to submit the case for arbitration, the CA claimant may invoke the jurisdiction of CIAC.
held that what is required for a dispute to fall under the
jurisdiction of the CIAC is for the parties to agree to
Under the present Rules of Procedure, for a particular
construction contract to fall within the jurisdiction of
CIAC, it is merely required that the parties agree to LICOMCEN INC vs Foundation Specialist
submit the same to voluntary arbitration. Unlike in the
original version of Section 1, as applied in the Tesco Facts: The dispute arose between mall developer
case, the law as it now stands does not provide that the Licomcen, Inc. and contractor Foundation Specialists,
parties should agree to submit disputes arising from their Inc. (FSI) over the suspension of certain works and the
agreement specifically to the CIAC for the latter to payment of billings and other amounts. Licomcen and
acquire jurisdiction over the same. Rather, it is plain FSI had a Construction Agreement, with General
and clear that as long as the parties agree to submit Conditions of Contract (GCC), whereby FSI undertook to
to voluntary arbitration, regardless of what forum construct and install bored piles foundation for the LCC
they may choose, their agreement will fall within the Citimall project in Legazpi City.
jurisdiction of the CIAC, such that, even if they
specifically choose another forum, the parties will Immediately after signing the agreement, FSI began
not be precluded from electing to submit their work on the project but in January 1998, Licomcen
dispute before the CIAC because this right has been ordered it to halt construction due to an administrative
vested upon each party by law, i.e., E.O. No. 1008 case filed against officials of the City Government of
Legazpi and Licomcen before the Ombudsman. The
Based on the foregoing, there are two acts which may suspension was formalized through a letter of
vest the CIAC with jurisdiction over a construction Licomcens engineering consultant, E.S. de Castro &
dispute. One is the presence of an arbitration clause in a Associates (ESCA), to FSI on January 19, 1998. In its
construction contract, and the other is the agreement by reply letters, FSI claimed payment for work and
the parties to submit the dispute to the CIAC. materials. ESCA rejected FSIs claims in a letter dated
March 24, 1998.
The first act is applicable to the case at bar. The bare
fact that the parties incorporated an arbitration clause in Three years later, FSI sent a final demand letter to
their contract is sufficient to vest the CIAC with Licomcen for payment of its claims. As this letter was
jurisdiction over any construction controversy or claim ignored, FSI filed a request for arbitration with the CIAC
between the parties. The rule is explicit that the CIAC in October 2002, claiming upaid billings, costs,
has jurisdiction notwithstanding any reference made to unrealized profit, attorneys fees and interest. Licomcen
another arbitral body. contested the request, arguing, among others, that (a)
the claims were non-arbitrable because the arbitration
To stress, the CIAC was already vested with jurisdiction clause provides for the arbitration of disputes in
the moment both parties agreed to incorporate an connection with, or arising out of the execution of the
arbitration clause in the sub-contract agreement. Thus, a Works, but FSIs money claims do not involve a dispute
subsequent consent by the parties would be superfluous as to the execution of the Works since they do not
and unnecessary. involve an issue as to physical construction activities;
and (b) FSI failed to comply with the condition precedent
In section 4.2 of the CIAC Rules, the failure despite due that a dispute must first be referred to Licomcen for
notice which amounts to a refusal of the Respondent to resolution, and such resolution may only be assailed
arbitrate, shall not stay the proceedings notwithstanding within 30 days from receipt thereof through a notice to
the absence or lack of participation of the contest through arbitration.
Respondent. In such case, CIAC shall appoint the
arbitrator/s in accordance with these Rules. Arbitration The CIAC ruled in favor of FSI, which decision was
proceedings shall continue, and the award shall be upheld with some modification by the Court of Appeals.
made after receiving the evidence of the Claimant. Both parties moved for reconsideration, which was
Therefore, the proceedings cannot then be voided denied.
merely because of the non-participation of petitioner.
Section 4.2 of the CIAC Rules is clear and it leaves no Issue:
room for interpretation. Therefore, petitioner's prayer that 1.) Expansive interpretation of arbitration clause
the case be remanded to CIAC in order that it may be
given an opportunity to present evidence is untenable. Held:
Petitioner had its chance and lost it, more importantly so,
Section 4 of E.O. 1008 states:
by its own choice. This Court will not afford a relief that is
apparently inconsistent with the law.
Sec. 4.Jurisdiction. The CIAC shall have original and interpreted at its widest signification. The Tribunal
exclusive jurisdiction over disputes arising from, or liberally applied the parties arbitration clause so that
connected with, contracts entered into by parties FSIs money claims were considered connected with or
involved in construction in the Philippines, whether the arising out of construction activities, thereby making
dispute arises before or after the completion of the such claims arbitrable.
contract, or after the abandonment or breach thereof.
These disputes may involve government or private 2.) CIAC jurisdiction not subject to condition precedent
contracts. For the Board to acquire jurisdiction, the
In fact, all that is required for the CIAC to acquire
parties to a dispute must agree to submit the same to
jurisdiction is for the parties to a construction contract to
voluntary arbitration.
agree to submit their dispute to arbitration. Section 1,
The jurisdiction of the CIAC may include but is not Article III of the 1988 CIAC Rules of Procedure (as
limited to violation of specifications for materials and amended by CIAC Resolution Nos. 2-91 and 3-93)
workmanship; violation of the terms of agreement; states:
interpretation and/or application of contractual time and
Section 1.Submission to CIAC Jurisdiction. An
delays; maintenance and defects; payment, default of
arbitration clause in a construction contract or a
employer or contractor and changes in contract cost.
submission to arbitration of a construction dispute
Excluded from the coverage of this law are disputes shall be deemed an agreement to submit an existing
arising from employer-employee relationships which or future controversy to CIAC jurisdiction,
shall continue to be covered by the Labor Code of the notwithstanding the reference to a different
Philippines. arbitration institution or arbitral body in such
contract or submission. When a contract contains a
The jurisdiction of courts and quasi-judicial bodies is clause for the submission of a future controversy to
determined by the Constitution and the law.44 It cannot arbitration, it is not necessary for the parties to enter
be fixed by the will of the parties to a dispute;45 the into a submission agreement before the claimant
parties can neither expand nor diminish a tribunals may invoke the jurisdiction of CIAC.
jurisdiction by stipulation or agreement. The text of
Section 4 of E.O. 1008 is broad enough to cover any An arbitration agreement or a submission to arbitration
dispute arising from, or connected with construction shall be in writing, but it need not be signed by the
contracts, whether these involve mere contractual parties, as long as the intent is clear that the parties
money claims or execution of the works.46 Considering agree to submit a present or future controversy arising
the intent behind the law and the broad language from a construction contract to arbitration.
adopted, LICOMCEN erred in insisting on its restrictive
On the principle that the CIACs jurisdiction can neither
interpretation of GC-61. The CIACs jurisdiction cannot
be enlarged nor diminished by the parties, the Supreme
be limited by the parties stipulation that only disputes in
Court also held that such jurisdiction cannot be subject
connection with or arising out of the physical
to a condition precedent. Hence, even if FSI failed to
construction activities (execution of the works)
timely contest Licomcens denial of its money claims by
arearbitrable before it.
filing a proper notice of arbitration within 30 days from
The Supreme Court ruled that the CIACs jurisdiction the denial, the Supreme Court ruled that the CIAC
cannot be limited by the parties stipulation that only acquired jurisdiction of the parties dispute due to the
disputes in connection with or arising out of the mere presence of an arbitration clause in their
execution of the Works arearbitrable before the said construction contract.
agency. According to the Supreme Court, the mere fact
that the parties incorporated an arbitration clause in their
contract ipso facto vested the CIAC with jurisdiction over
HUTAMA-RSEA Joint Operations, Inc v. Citra
any construction controversy or claim between the
Metro Manila Tollways Corp
parties.

The Supreme Court also added that the parties did not Facts:Respondent is the general contractor and
intend to limit resort to arbitration only to disputes operator of the Skyway project. Petitioner and
relating to physical construction activities, holding that respondent entered into an Engineering Procurement
an arbitration clause pursuant to E.O 1008 Construction Contract (EPCC) whereby petitioner would
[Construction Industry Arbitration Law] should be undertake the construction of Stage 1 of the Skyway
Project. During said construction, petitioner wrote deemed as an agreement to submit an existing or future
respondent on several occasions requesting payment of controversy to CIAC jurisdiction, "notwithstanding the
the formers interim billings, pursuant to provisions of the reference to a different arbitration institution or arbitral
EPCC/ however, respondent only partially paid the body in such contract x xx." Elementary is the rule that
interim billings. Respondent failed to do so despite when laws or rules are clear, it is incumbent on the court
demands to pay its outstanding balance. Petitioner filed to apply them. When the law (or rule) is unambiguous
with CIAC a request for arbitration to enforce its money and unequivocal, application, not interpretation thereof,
claims against respondent. is imperative.
CIAC ruled that it had jurisdiction over the same. CA
reversed. Now that Section 1, Article III [CIAC Rules of Procedure
Governing Construction Arbitration], as amended, is
Issue: WON CIAC has jurisdiction despite the EPCC submitted to test in the present petition, we rule to
provision requiring prior referral by the parties of their uphold its validity with full certainty. However, this should
dispute to the Dispute Adjudication Board not be understood to mean that the parties may no
longer stipulate to submit their disputes to a different
HELD: forum or arbitral body. Parties may continue to stipulate
as regards their preferred forum in case of voluntary
Section 4 of Executive Order No. 100818 defines the arbitration, but in so doing, they may not divest the CIAC
jurisdiction of CIAC, thus: of jurisdiction as provided by law. Under the elementary
principle on the law on contracts that laws obtaining in a
SECTION 4.Jurisdiction. - The CIAC shall have original jurisdiction form part of all agreements, when the law
and exclusive jurisdiction over disputes arising from, or provides that the Board acquires jurisdiction when the
connected with, contracts entered into by parties
parties to the contract agree to submit the same to
involved in construction in the Philippines, whether
the disputes arises before or after the completion of voluntary arbitration, the law in effect, automatically
the contract, or after the abandonment or breach gives the parties an alternative forum before whom they
thereof. These disputes may involve government or may submit their disputes. That alternative forum is the
private contracts. For the Board to acquire jurisdiction, CIAC. This, to the mind of the Court, is the real spirit of
the parties to a dispute must agree to submit the same E.O. No. 1008, as implemented by Section 1, Article III
to voluntary arbitration.
of the CIAC Rules.

The jurisdiction of the CIAC may include but is not


limited to violation of specifications for materials and
workmanship; violation of the terms of agreement;
interpretation and/or application of contractual
provisions; amount of damages and penalties;
commencement time and delays; maintenance and
defects; payment default of employer or contractor and
changes in contract cost.

Excluded from the coverage of this law are disputes


arising from employer-employee relationships which
shall continue to be covered by the Labor Code of the
Philippines.

It is true that Clause 20.4 of the EPCC states that a


dispute between petitioner and respondent as regards
the EPCC shall be initially referred to the DAB for
decision, and only when the parties are dissatisfied with
the decision of the DAB should arbitration commence.
This does not mean, however, that the CIAC is barred
from assuming jurisdiction over the dispute if such
clause was not complied with.

Under Section 1, Article III of the CIAC Rules, an


arbitration clause in a construction contract shall be

S-ar putea să vă placă și