Sunteți pe pagina 1din 1

LISTA DE INSUMOS DEL PRESUPUESTO

PROYECTO

ETAPA :
PROPIETARIO :
UBICACION :
FECHA PROYECTO : 30/06/2017
Cdigo Descripcin Unid. Cantidad Costo Total

MANO DE OBRA 21,933.60


471,060,002.00 OFICIAL hh 87.99 8.25 725.94
471,060,004.00 PEON hh 1,505.80 7.25 10,917.07
471,060,083.00 OPERADOR DE EQUIPO PESADO hh 833.26 10.75 8,957.59
471,060,005.00 TOPOGRAFO hh 124.00 10.75 1,333.00
MATERIALES 45,523.86
21,060,021.00 ALAMBRE NEGRO RECOCIDO N8 kg 6.00 5.00 30.00
20,040,183.00 CALAMINA DE 1.80 X 0.80 DE 16mm und 25.20 5.00 554.40
390,040,003.00 CARTEL DE IDENTIFICACION DE OBRA (BANNER) und 1.00 520.00 520.00
430,040,003.00 CLAVOS PARA MADERA C/C 3" kg 6.72 5.00 33.60
440,040,003.00 CLAVOS PARA MADERA C/C 4" kg 6.72 3.20 33.60
340,040,001.00 CLAVOS PARA MADERA CON CABEZA DE 4" kg 0.50 11.20 2.50
10,010,001.00 COMBUSTIBLE PETROLEO D-2 gln 2,462.53 35.50 27,580.28
480,040,003.00 ESTACA p 310.00 1,200.00 62.00
390,010,002.00 FLETE TERESTRE ABANCAY-CRUZPATA GLB 1.00 2,000.00 3,600.00
20,040,171.00 LUBRICANTE PARA TRACTOR ORUGA CAT D6M GLB 185.06 5.00 6,569.71
20,040,005.00 MADERA CORRIENTE p 129.00 5.00 412.80
590,040,001.00 MITIGACION AMBIENTAL GLB 2.00 22.00 2,400.00
290,040,003.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPO est 1.00 6.00 3,557.49
430,040,241.00 PINTURA ESMALTE gln 1.24 0.20 45.88
540,040,002.00 ROLLIZO DE EUCALIPTO und 2.00 37.00 10.00
320,040,003.00 YESO EN BOLSAS DE 25 KG. bol 18.60 3,557.49 111.60
EQUIPO 34,982.68
491,060,055.00 ESTACION TOTAL hm 24.80 46.00 1,140.80
300,040,004.00 PERFORACION Y DISPARO EN ROCA FIJA m 252.79 24.00 6,066.96
370,040,003.00 PERFORACION Y DISPARO EN ROCA SUELTA m 313.77 22.00 6,902.94
480,010,001.00 TRACTOR DE ORUGA -D6 similar hm 70.00 280.00 19,600.48
480,010,002.00 WINCHA DE 50m und 1.86 50.00 93.00
370,010,001.00 HERRAMIENTAS MANUALES %mo 5.37 21,933.60 1,178.50
TOTAL: 102,440.14