Sunteți pe pagina 1din 50

2016 2017 2018 2019

Line Name Duration Start Finish


M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1 First Stage Works 45w 2d 20 May 16 21 Apr 17 1

2
2 First Stage Tender Process 15w 4d 23 May 16 13 Sep 16
3 ABP Appoint Multiplex as FSA Contractor 23 May 16 23 May 16 3

4 Agree Contract Terms 5w 23 May 16 27 Jun 16 4

5 Prepare Package Scope Documents 1w 4d 23 May 16 03 Jun 16 5

6 Design Review 6w 06 Jun 16 15 Jul 16 6

7 VE & Buildability Review 6w 24 Jun 16 04 Aug 16 7

8
8 70% Works Package Pricing 15w 2h 27 May 16 13 Sep 16
9 UXO Survey 6w 1d 27 May 16 11 Jul 16 9

10 Piling 8w 3d 27 May 16 27 Jul 16 10

11 Precast Concrete Cladding 10w 3d 27 May 16 10 Aug 16 11

12 MEP/Infrastructure Works 12w 2d 02 Jun 16 26 Aug 16 12

13 Concrete Frame 9w 3d 06 Jun 16 10 Aug 16 13

14 Windows 10w 2d 06 Jun 16 16 Aug 16 14

15 Groundworks/ Infrastructure Works 10w 3d 13 Jun 16 24 Aug 16 15

16 Lifts 9w 3d 13 Jun 16 17 Aug 16 16

17 Blockwork 9w 3d 13 Jun 16 17 Aug 16 17

18 Roofing 9w 3d 20 Jun 16 24 Aug 16 18

19 Dry Lining 9w 3d 20 Jun 16 24 Aug 16 19

20 Provisional Sums Fit Out Packages 6w 4d 25 Jul 16 09 Sep 16 20

21 Compile and Agree Contract Sum 5w 2h 08 Aug 16 13 Sep 16 21

22 Submit First Stage Deliverables Incl. GMP 13 Sep 16 13 Sep 16 22

23
23 FSA Schedule 2 Pre-Construction Period Services 30w 4d 20 May 16 23 Dec 16
24 Part 1 - Management / Pricing 30w 4d 20 May 16 23 Dec 16 24

25 Review of the current proposed design 14w 2d 23 May 16 01 Sep 16 25

26 Assist the Cost Consultant to produce a revised Cost Plan 14w 2d 23 May 16 01 Sep 16 26

27 Investigation into Precasting/Preforming and off-site construction techniques 11w 1s 10 Jun 16 26 Aug 16 27

28 Milestone 2:- Examine the Cost Plan in detail and be satisfied that it represents a reasonably sufficient estimate 6w 13 Jun 16 25 Jul 16 28

29 Assist the Employer and Contractor in obtaining any further consents approvals licences agreements or other matters 11w 3d 08 Jun 16 26 Aug 16 29

30 Participate in the BIM modelling in accordance with the BIM execution plan 12w 2d 02 Jun 16 26 Aug 16 30

31 Assist the Employer and Contractor in initiating, managing and coordinating all liaison with Third Parties 11w 3d 08 Jun 16 26 Aug 16 31

32 Inspect the site and research the likelihood of impact on or interest by Third Parties 12w 1d 08 Jun 16 01 Sep 16 32

33 Prepare a Strategy for management of these Third Party issues 8w 3d 04 Jul 16 01 Sep 16 33

34 Prepare a Third Party Stakeholder Plan 3w 2d 09 Aug 16 01 Sep 16 34

35 Initiate regular neighbouring meetings in conjunction with the Employer and Contractor 3w 08 Jul 16 29 Jul 16 35

Carry out a pre-construction survey of buildings, highways and the like that may be affected by the Project and agree with the Contractor. 36
36 1w 19 Dec 16 23 Dec 16
Provide a report on the same.
37 Milestone 9:- Prepare project specific policy for safety and agree with the Contractor 5w 11 Jul 16 15 Aug 16 37

38 Milestone 9:- Prepare project specific policy for training and agree with the Contractor 5w 11 Jul 16 15 Aug 16 38

39 Milestone 9:- Prepare project specific policy for sustainabilty and agree with the Contractor 5w 11 Jul 16 15 Aug 16 39

40 Milestone 9:- Prepare project specific policy for Industrial Relations and agree with the Contractor 5w 11 Jul 16 15 Aug 16 40

Milestone 9:- Prepare and agree KPIs with the Contractor and report regularly on compliance against them including statistical 41
41 5w 11 Jul 16 15 Aug 16
records
Milestone 10:- Provide logistics advice to the Contractor. Prepare logistics statement and method statement for execution of the 42
42 9w 20 May 16 25 Jul 16
project as part of the Construction Management Plan
43 Milestone 10:- Produce a Project Specific Fire Safety Manual 5w 1d 22 Jul 16 26 Aug 16 43

44 Milestone 11:- Prepare an Integrated Master Programme. 7w 4d 17 Jun 16 11 Aug 16 44

45 Milestone 12:- Prepare material component flows and identify those that need advance ordering and processing 4w 1d 23 May 16 22 Jun 16 45

Provide advice to the Contractor on the consequences of the design on; Packaging of the work; Interface management; ease of 46
46 11w 3d 08 Jun 16 26 Aug 16
construction; sequencing; availability of materials and labour; durability and maintenance; programme and costs
47 Manage the progress of the design 13w 4d 23 May 16 26 Aug 16 47

48 Advise the Contractor on Information Release Dates and Approval Periods 10w 20 Jun 16 26 Aug 16 48

49 Assist the Contractor in instituting a change control process 3w 23 May 16 13 Jun 16 49

50 Notify the contractor of the failure of any Named Specialist to perform their services. 13w 4d 23 May 16 26 Aug 16 50

51 Milestone 16:- Prepare and agree with the Contractor a Package Procurement Programme 1w 23 May 16 31 May 16 51

Milestone 17:- Investigate and report on the capability and financial standing of the proposed Work Sub-Contractors - organise 52
52 3w 31 May 16 21 Jun 16
and attend selection interviews
Milestone 18:- Recommend the most effective bidding procedures; propose and discuss with the Contractor the most appropriate 53
53 3w 31 May 16 21 Jun 16
procurement route for individual packages
Agree with the Contractor and his legal advisors any requirement for Third Party Rights, collateral warranties and/or assignments to Third 54
54 11w 3d 13 Jun 16 01 Sep 16
Parties and/or product or professional indemnity insurances and incorporate these into the Work Sub-Contracts.
55 Advise and agree with the Contractor and his legal advisors any requirements for bonds, parent company guarantees or legal opinion letters 14w 2d 23 May 16 01 Sep 16 55

56 Prepare for the placing of work sub-contracts so that they can be placed once the Sub Building Contract is entered into 8w 1d 01 Jul 16 26 Aug 16 56

Milestone 22:- Institute a system of documentation and records for reporting upon the performance of all the work sub contractos 57
57 3w 1d 31 May 16 22 Jun 16
in a form acceptable to the agreement of the Contractor
58 Verify on site the survey control and setting out information. Bring to the attention of the Contractor any discrepancies. 9w 2d 28 Jun 16 20 Sep 16 58

Milestone 24:- Verify the content of any site investigation and existing underground utility services information provided by the
59 Contractor. Verify the location of all logged underground utilities adjacent to or crossing the site. Bring any discrepancies or 3w 29 Jun 16 20 Jul 16 59

clashes with the Project or Temporary Works to the attention of the Contractor
Milestone 25:- Prepare the Proposals with the Pre-appointed Consultants designs, all design information developed by the 60
60 10w 2d 10 Jun 16 23 Aug 16
Principal Sub-Contractor, and any necessary input from the Work Sub-Contractors
61 Provide information to the Contractor for the purposes of claimimg capital allowances on plant and machinery expenditure 8w 4d 01 Jul 16 01 Sep 16 61

Milestone 27:- Assist the Contractor's discussions on crane oversailing licenses with adjoining freeholders, City Airport and 62
62 7w 1d 01 Jun 16 21 Jul 16
tenants as required. Provide the Employer and Contractor with confirmation of any agreements reached
63 Liaise as necessary with Third Party Stakeholders to include: LBN; CLA; UEL; DLR; RoDMA; London Regatta Centre; TfL; GVA etc 13w 4d 23 May 16 26 Aug 16 63

Provide assistance to and provide and maintain appropriate resources to assist the Employer in complying with its responsibilities under 64
64 13w 4d 23 May 16 26 Aug 16
Clause 5.5A of the GLA Development Agreement.
Provide assistance to the Employer in complying with its responsibilities under Clause 43.6 of the GLA Development Agreement, in respect 65
65 13w 4d 23 May 16 26 Aug 16
of the FoI Act 2004 and the EIR 2004
66
66 Part 2 : Design Services 22w 3d 23 May 16 31 Oct 16
Carry out or procure the carrying out of all of the services contained in all the forms of appointment of all the Named Specialists appended 67
67 13w 4d 23 May 16 26 Aug 16
in Schedule 11 up to the execution of the Sub Building Contract.
68 Appointment of Pre-appointed Consultants 31 Oct 16 31 Oct 16 68

69 Appointment of Farrells (London) LLP 31 Oct 16 31 Oct 16 69

70 Appointment of AKT II Limited 31 Oct 16 31 Oct 16 70

71 Appointment of Hilson Moran Partnership Limited 31 Oct 16 31 Oct 16 71

72 Appointment of Vital Energi Utilities Limited 31 Oct 16 31 Oct 16 72

73 Appointment of Gillespies LLP 31 Oct 16 31 Oct 16 73

74 Appointment of Signage Consultant 31 Oct 16 31 Oct 16 74

75 Appointment of Geotechnical & Environmental Associates 31 Oct 16 31 Oct 16 75

76 Client Award DB Contract 31w 4d 25 Aug 16 21 Apr 17 76

77 PSC Stage 2 Price Review 4w 1d 25 Aug 16 23 Sep 16 77

78 Finalise PSC Second Stage Appointment and Mezzanine Funding in Place 3w 26 Sep 16 09 Nov 16 78

79 ABP submit Contract to GLA for approval 10 Nov 16 10 Nov 16 79

80 GLA Approval of PSC Contract 4w 4d 10 Nov 16 13 Dec 16 80

81 Award Main Works Contract 10 Nov 16 10 Nov 16 81

82 ABP Issue Works commencement Order 27 Mar 17 27 Mar 17 82

83 MPX Mobilization Period 3w 3d 27 Mar 17 21 Apr 17 83

84 Instructions Required from ABP/WTP 50w 3d 22 Jul 16 02 Aug 17 84

85 ABP / WTP to instruct provision of Early Production Design Information 06 Sep 16 06 Sep 16 85

86 ABP/WTP instruct site access bridge design CCR017 05 Sep 16 05 Sep 16 86

87 ABP/WTP instruct site access bridge construction CCRTBC 13 Dec 16 13 Dec 16 87

88 ABP/WTP instructs placing of test piling subcontract CCR006 01 Aug 16 13 Dec 16 88

89 ABP/WTP instructs soil investigations CCR019 13 Dec 16 13 Dec 16 89

90 ABP/WTP to place orders for necessary consultants to satisfy Planning Conditions CCRs 007, 010 & 012 22 Jul 16 22 Jul 16 90

91 ABP/WTP instruct Placing of contract for Site Accommodation CCR TBC 13 Dec 16 13 Dec 16 91

92 ABP/WTP instruct Placing of contract for Water testing CCR014 01 Aug 16 01 Aug 16 92

93 ABP/WTP instruct Placing of contract for Hoardings CCR TBC 13 Dec 16 13 Dec 16 93

94 ABP/WTP instruct Placing of contract with Bactec for UXO survey CCR018 13 Dec 16 13 Dec 16 94

95 ABP/WTP instruct Intrusive survey to Dock Wall CCR015 13 Mar 17 13 Mar 17 95

96 ABP/WTP Instruct placing of contract with Pre-cast cladding sub-contractor for design of the works and production of Mock-ups CCR016 05 Sep 16 05 Sep 16 96

97 ABP/WTP Instruct placing of contract with Window sub-contractor for design of the works and production of Mock-ups CCR023 03 Oct 16 03 Oct 16 97

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
98 ABP/WTP instruct Placing of contract with Groundworker 13 Dec 16 13 Dec 16 98

99 ABP/WTP instruct Placing of contract with Dewatering Sub-contractor CCR TBC 13 Dec 16 13 Dec 16 99

100 ABP/WTP instruct Placing of contract with Windows Sub-contractor for Bulk material purchase and production slot CCR023a 13 Dec 16 13 Dec 16 100

101 ABP/WTP instruct fees for additional planning discharge C11 CCR 024 20 Sep 16 20 Sep 16 101

102 ABP/WTP instruct fees for additional planning discharge C08 CCR 025 28 Sep 16 28 Sep 16 102

103 ABP/WTP instruct fees for additional planning discharge Tecnical Safeguarding of Cranes C11 CCR 026 03 Oct 16 03 Oct 16 103

104 ABP/WTP instruct design change to Lift core size CCR027 03 Oct 16 03 Oct 16 104

105 ABP/WTP instruct Placing of contract with Site Setting Out Sub-contractor CCR TBC 07 Oct 16 07 Oct 16 105

106 ABP/WTP instruct design change to Ground slab edge design CCR TBC 03 Oct 16 03 Oct 16 106

107 BP/WTP instruct Placing of contract with Surface Geophysics Sub-contractor CCR TBC 03 Oct 16 03 Oct 16 107

108 ABP/WTP instruct design change to Windows to Fixed Lights CCR TBC 12 Oct 16 12 Oct 16 108

109 ABP/WTP instruct design change to Cladding for Soldier Course and Granite Plinth CCR TBC 12 Oct 16 12 Oct 16 109

110 ABP/WTP instruct design change for Brick Slip Alternatives CCR TBC 07 Oct 16 07 Oct 16 110

111 ABP/WTP instruct design change for slab edge extension CCR 003 03 Oct 16 03 Oct 16 111

112 ABP/WTP instruct design change for PCC columns, stairs and twinwall cores CCR 005 03 Oct 16 03 Oct 16 112

113 ABP/WTP instruct design change for PCC cladding to be 'stacked' not hung CCR 021 03 Oct 16 03 Oct 16 113

114 ABP/WTP instruct placing or order for site temporary services feeds CCR TBC 13 Dec 16 13 Dec 16 114

115 ABP/WTP instruct design change for CFA Piling CCR 022 03 Oct 16 03 Oct 16 115

116 ABP / WTP Place Minor Works Contract with MPX 14w 2d 01 Aug 16 13 Dec 16 116

117 ABP Pay for works to Water Main 02 Aug 17 02 Aug 17 117

118 MPX request changes to piling 24 Feb 17 24 Feb 17 118

119 LBN Planning - consider piling changes 8w 24 Feb 17 24 Apr 17 119

120 LBN Planning - approve piling changes 09 May 17 09 May 17 120

121 ABP instruction to Redesign TEC Stage F (Instruction C17) 19 Jun 17 19 Jun 17 121
122 Instruction to proceed with temporary external works design & Procurement 13 Jul 17 13 Jul 17 122

123 Expenditure of Provisional Sums (Some are undefined provisional sums and will result in pre-agreed instructions) 111w 28 Nov 16 06 Mar 19 123

124 Defined Provisional Sums - issue of instruction to expend and Stage E design 46w 28 Nov 16 06 Nov 17 124

125 Raised Access Floors 31 Mar 17 31 Mar 17 125


Soft Landscaping, Street Furniture and Railings (Trees and associated items must be bought earlier and novated to successful trade
126 31 Mar 17 31 Mar 17 126
contractor)
127 Energy Supplier - Vital Energi - DH/DC Network 28 Nov 16 28 Nov 16 127
128 Water Feature 10 Aug 17 10 Aug 17 128
129 Temporary Energy centre and ancillary buildings (C17) 19 Jun 17 19 Jun 17 129
130 Ground works Package - E4 dockside coping stone 06 Nov 17 06 Nov 17 130
Windows Package - Canopies - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed
131 03 Jul 17 03 Jul 17 131
in the base scheme)
132 Dewatering Package - Discharge into Dock 23 May 17 23 May 17 132
Extra Low Voltage (ELV) Package - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been
133 31 Mar 17 31 Mar 17 133
designed in the base scheme)
134 Dock Wall Repairs & Alteration works 09 Aug 17 09 Aug 17 134

135 Undefined Provisional Sums - Issue of instruction to expend and provision of Stage E design 43w 3d 26 Apr 17 12 Mar 18 135

136 Signage - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed in the base scheme) 22 Jan 18 22 Jan 18 136

Information Light Wall - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed in the
137 12 Feb 18 12 Feb 18 137
base scheme)
138 External Lighting - Fixtures 09 Aug 17 09 Aug 17 138
External Lighting - Distribution - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed
139 09 Aug 17 09 Aug 17 139
in the base scheme)
140 Incoming Utilities 11 Dec 17 11 Dec 17 140
Fixed Fibre Telecommunications - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been
141 11 Dec 17 11 Dec 17 141
designed in the base scheme)
142 Temporary External Works - Temporary Carpark 13 Jul 17 13 Jul 17 142
143 Temporary External works 12 Feb 18 12 Feb 18 143
Security - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed in the base scheme.
144 Also assumes that all necessary wireways in all internal and external doors are already coordinated with the design team to facilitate design 09 Aug 17 09 Aug 17 144
and procurement)
145 Asbestos Removal to Listed Buildings 26 Apr 17 26 Apr 17 145
Type B Lobby Fitout - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed in the
146 06 Nov 17 06 Nov 17 146
base scheme and that any infrastructure necessary has been coordinated already with the base build design)
147 Temporary Car Park 12 Mar 18 12 Mar 18 147
148
148 Work to Listed Buildings 10A and 10B (Based on minimal structural alterations to the buildings) 100w 27 Feb 17 06 Mar 19
ABP/WTP provide a detailed brief showing the proposed use for the buildings, a scope for the works and request price and programme for 149
149 27 Feb 17 27 Feb 17
the design works
150 CITIC/MPX respond with price and programme for the design 1w 27 Feb 17 03 Mar 17 150

151 MPX to submit CCR for Asbestos Survey, Asbestos removal & Pigeon guano removal 2w 31 Mar 17 13 Apr 17 151

152 CI for Asbestos Survey, Asbestos removal & Pigeon guano removal 1w 11 May 17 17 May 17 152

153 Carry out Asbestos Survey & Pigeon guano removal 4w 2d 17 May 17 16 Jun 17 153

154 Issue reports to ABP for review 19 Jun 17 19 Jun 17 154


155 Instruction from ABP to proceed with asbestos removal 1w 12 Jun 17 16 Jun 17 155
156 MPX to procure/tender Asbestos removal 19 Jun 17 19 Jun 17 156
157 Carry out Asbestos removal including Mobilisation and HSE approval period 4w 03 Jul 17 04 Aug 17 157

158 MPX to Obtain "Clear Building Cerificate" 04 Aug 17 04 Aug 17 158

159 Procure Timber survey 10w 15 May 17 16 Oct 17 159

160 Procure Facade Survey 10w 15 May 17 16 Oct 17 160

161 Procure Fabric Survey Including trial pits to foundations 10w 15 May 17 16 Oct 17 161

162 Procure Drainage & Incoming services surveys 10w 15 May 17 16 Oct 17 162

163 Procure 3D Revit survey 10w 15 May 17 16 Oct 17 163

164 MPX review survey tenders and produce tender reports 4d 17 Oct 17 20 Oct 17 164

165 MPX to Submit tender reports & Recommendation for Carrying out surveys to ABP 16 Oct 17 16 Oct 17 165

166 ABP Review period 1w 16 Oct 17 20 Oct 17 166

167 WI to issue CI to carry out Surveys and Obtain reports 06 Nov 17 06 Nov 17 167

168 Carry Out Archaeological survey(MoLA) & issue reports to WTP/ABP 5w 06 Nov 17 08 Dec 17 168

169 Carry out remaining surveys, Obtain reports & and issue reports to WTP/ABP 6w 06 Nov 17 15 Dec 17 169

170 MPX to Prepare and submit survey report 2w 18 Dec 17 09 Jan 18 170

171 ABP/WT Review and instruct design of Listed building works 1w 10 Jan 18 16 Jan 18 171

172 Obtain prices from Design team to carry out design 2w 17 Jan 18 30 Jan 18 172

173 Submit prices to WTP 1w 31 Jan 18 06 Feb 18 173

174 WTP instruct design for listed buildings 2w 07 Feb 18 20 Feb 18 174

175 Prepare Stage C design for listed buildings 5w 21 Feb 18 27 Mar 18 175

176 Prepare cost plan for the Stage C design 2w 28 Mar 18 12 Apr 18 176

177 Submit Stage C design, programme and costplan for client review 13 Apr 18 13 Apr 18 177

178 ABP/WTP Review Stage C Design, Programme and Cost plan and provide comments 2w 13 Apr 18 26 Apr 18 178

179 Adapt design to take cognisance of comments 2w 30 Apr 18 14 May 18 179

180 Submit design for listed building approval 15 May 18 15 May 18 180

181 Listed Building Review Period 12w 15 May 18 07 Aug 18 181

182 Listed Building Approval 08 Aug 18 08 Aug 18 182

183 Go to supply chain to obtain tenders for works 8w 15 May 18 10 Jul 18 183

184 Tender review and recommendation 2w 11 Jul 18 24 Jul 18 184

185 ABP/WTP Review, approve and instruct the works 3w 25 Jul 18 14 Aug 18 185

186 CITIC/BM Instruct the works 1w 15 Aug 18 21 Aug 18 186

187 Lead-in 2w 22 Aug 18 05 Sep 18 187

188
188 Shell & Core Works 20w 06 Sep 18 06 Feb 19
189 Cut back and disposal of bushes and shrubs surrounding the listed buildings and gardens 2w 06 Sep 18 19 Sep 18 189

190 Devegetate facade and treat affected areas, clean facade, windows and doors prior to decoration 2w 18 Sep 18 01 Oct 18 190

191 Removal of existing debris and rubbish 2w 06 Sep 18 19 Sep 18 191

192 Temporary measures to ensure building security and water tightness 4w 13 Sep 18 10 Oct 18 192

193 Repair defects in the precast concrete components 4w 13 Sep 18 10 Oct 18 193

Remove falling historical repairs, defective precast concrete panels and mouldings, and treat cast in reinforcement or replace with s/s bars 194
194 10w 17 Sep 18 23 Nov 18
and reinstate.
195 Repair or Replace any barge boards, fascia boards and any other external woodwork 3w 12 Oct 18 01 Nov 18 195

196 Repair or replace broken tiles including special tiles to encure water tightening incl. repair of lead flashings 10w 27 Sep 18 05 Dec 18 196

197 Replace missing or defective rainwater goods 10w 25 Sep 18 03 Dec 18 197

Removal of loose defective paint, filling hairline cracks, rubbing down, preparation and decoration to all window, doors, woodwork, metal 198
198 12w 18 Sep 18 10 Dec 18
work, stonework, pebble dashing and render
199 Strip out existing reduntant services, cap and make safe 8w 03 Oct 18 27 Nov 18 199

200 Remove existing non-structural partitions 8w 03 Oct 18 27 Nov 18 200

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
201 Replacement of Existing defective structural elements 12w 20 Sep 18 12 Dec 18 201

202 Structural Improvements, alterations and internal adaptions 12w 20 Sep 18 12 Dec 18 202

203 Overhaul existing floor replacement 8w 18 Oct 18 12 Dec 18 203

204 Linings to existing structural internal and external walls incl. ceilings 8w 18 Oct 18 12 Dec 18 204

205 Damp Proofing to external walls/floors 8w 18 Oct 18 12 Dec 18 205

206 Internal Frames and fire doors, ironmongery to maintian fire intergrity 8w 18 Oct 18 12 Dec 18 206

207 Roof and wall insulation as required 6w 12 Nov 18 21 Dec 18 207

208 Overhaul existing staircases, balustrades and handrails to ensure safe access 4w 26 Nov 18 21 Dec 18 208

209 Connection to DH/DC network, LV Connections, Main water connection, Open reach & Telecoms connections 4w 26 Nov 18 21 Dec 18 209

210 Connection to new drainage networks 4w 26 Nov 18 21 Dec 18 210

211 Emergency, Temporary lighting, Smoke detectors, fire alarms as required to maintain fire integrity 8w 29 Nov 18 06 Feb 19 211

212 Snagging, Commissioning and Handover 4w 07 Feb 19 06 Mar 19 212

213 Listed Buildings Heating/Cooling, Water and Electrical Connections 66w 05 Dec 16 13 Apr 18 213

214 Sizing of the Deep level connections to District Heating and Cooling ring mains 05 Dec 16 05 Dec 16 214

215 Pipework etc to the buildings 9w 07 Feb 18 13 Apr 18 215

216 ABP/WTP instruct the design works 2w 07 Feb 18 20 Feb 18 216

217 CITIC/BM Prepare cost plan for the design 2w 21 Feb 18 06 Mar 18 217

218 Submit design, programme and costplan for client review 07 Mar 18 07 Mar 18 218

219 ABP Review Design, Programme and Cost plan and provide comments 2w 07 Mar 18 20 Mar 18 219

220 Adapt design to take cognisance of comments 3w 21 Mar 18 12 Apr 18 220

221 Submit design for approval 13 Apr 18 13 Apr 18 221

222 Design 68w 1d 09 May 16 20 Sep 17222


223 Client Acceptance of Remaining Stage D Design 2w 08 Sep 16 21 Sep 16 223

224
224 Planning Consent 29w 03 Jun 16 23 Dec 16
225 Planning Conditions Precedent to Start on Site Cleared 21w 3d 03 Jun 16 23 Dec 16 225

226 Stage E Design 30w 4d 18 Jul 16 03 Mar 17 226

227 AKT II provide structural design for temporary energy centre 6w 23 Jan 17 03 Mar 17 227

228 'Stacked' Facade substructure re-design 11w 2d 08 Sep 16 20 Dec 16 228

229 Slab Edge Extension to accommodate 'Stacked' Facade 10w 1d 08 Sep 16 20 Dec 16 229

230 Reduced Lift shaft sizing impact on structure 10w 2d 04 Oct 16 20 Dec 16 230

231 Facade Design Freeze on elevations to Buildings 5A and B 03 Oct 16 03 Oct 16 231

232 Facade Design Freeze on elevations to Buildings 8A, 8B and 9A 30 Aug 16 30 Aug 16 232

233
233 Revised Stage E Piling Design for CFA piling 21w 18 Jul 16 13 Dec 16
234 ABP/WTP instruction to produce revised Stage E piling design for CFA and to provide Test Pile 18 Jul 16 18 Jul 16 234

235 Stage E redesign of Piling as CFA 6w 2d 08 Sep 16 21 Oct 16 235

236 Building 9A Piling layout and loads P1 issue 21 Oct 16 21 Oct 16 236

237 Building 8B Piling layout and loads P1 issue 21 Oct 16 21 Oct 16 237

238 Building 8A Piling layout and loads P1 issue 21 Oct 16 21 Oct 16 238

239 Building 5B Piling layout and loads P1 issue 21 Oct 16 21 Oct 16 239

240 Building 5A Piling layout and loads P1 issue 21 Oct 16 21 Oct 16 240

241 Piling subcontractor reviews piling design 4w 24 Oct 16 30 Nov 16 241

242 BM/CITIC Place piling subcontract 13 Dec 16 13 Dec 16 242

243 Re-design of sub-structure for CFA piling 8w 29 Sep 16 23 Nov 16 243

244 Stage F Design 52w 25 Jul 16 14 Aug 17 244

245 Designers mobilisation 1w 06 Sep 16 12 Sep 16 245

246 Infrastructure and Buried Services 37w 2d 25 Jul 16 28 Apr 17 246

247 Stage F Infrastructure Enabling Works Design 9w 25 Jul 16 26 Sep 16 247

248 Stage F Infrastructure Design 16w 4d 27 Sep 16 28 Apr 17 248

249 Design release dates 27 Sep 16 26 Apr 17 249

250 Shallow services design 16w 05 Sep 16 23 Dec 16 250

251
251 Piling 23w 2d 26 Aug 16 21 Feb 17
252 Piling Design 6w 23 Nov 16 21 Feb 17 252

253 Building 9A Piling layout and loads C1 issue 31 Jan 17 31 Jan 17 253

254 Building 8B Piling layout and loads C1 issue 31 Jan 17 31 Jan 17 254

255 Building 8A Piling layout and loads C1 issue 31 Jan 17 31 Jan 17 255

256 Building 5B Piling layout and loads C1 issue 21 Feb 17 21 Feb 17 256

257 Building 5A Piling layout and loads C1 issue 21 Feb 17 21 Feb 17 257

258 Keltbray issue typical piling details and layouts 26 Aug 16 26 Aug 16 258

259
259 Substructure and Under Slab Drainage 32w 4d 06 Sep 16 11 May 17
260 ABP review Keltbray proposed pile design 1w 1d 06 Sep 16 13 Sep 16 260

261 AKT2 issue typical pilecap details to Farrells 14 Sep 16 14 Sep 16 261

262 Stage F Lift pit and shaft design 9w 1d 26 Sep 16 28 Nov 16 262

263 Stage F Design Substructure 15w 4d 06 Sep 16 23 Dec 16 263

264 Buildings 8A, 8B and 9A Pilecap and ground floor slab design including under slab services 08 Dec 16 08 Dec 16 264

265 C1 Design Information for Buildings 9A, 8A & 8B 31 Jan 17 31 Jan 17 265

266 Building 9A & 8B Substructure Rebar Design Intent 31 Jan 17 31 Jan 17 266

267 Buildings 5A & 5B Pilecap and ground floor slab design including under slab services 24 Feb 17 24 Feb 17 267

268 Building 8A Substructure Rebar Design Intent 31 Jan 17 31 Jan 17 268

269 C1 Design Information for Buildings 5A & 5B 06 Mar 17 06 Mar 17 269

270 Building 5A & 5B Substructure Rebar Design Intent 11 May 17 11 May 17 270

271 Facade 14w 05 Sep 16 09 Dec 16 271

272 Facade Visual Mock-Up Design 26 Sep 16 26 Sep 16 272

273 Facade Performance Mock-Up Design 14 Oct 16 14 Oct 16 273

274 Building 8A, 8B and 9A Facade Design - C1 issue 7w 05 Sep 16 21 Oct 16 274

275 Building 5A and 5B Facade Design - C1 Issue 6w 31 Oct 16 09 Dec 16 275

276
276 Superstructure Design 44w 3d 15 Sep 16 14 Aug 17
277 Stage F Structural Design 23w 08 Dec 16 07 Jun 17 277

278 Stage F Superstructure Design 9w 2d 08 Dec 16 24 Feb 17 278

279 P1 Issue of Construction Information for Buildings 9A, 8A & 8B 22 Dec 16 22 Dec 16 279

280 Provide Reinforcement Intent for Core Walls and Columns - Building 8A, 8B and 9A 20 Jan 17 20 Jan 17 280

281 Provide Post Tension Slab Loading and deflection design - Building 9A and 8B 20 Jan 17 20 Jan 17 281

282 P1 Issue of Construction Information for Buildings 5A & 5B 10 Apr 17 10 Apr 17 282

283 C1 Issue of Construction Information for Buildings 9A, 8A & 8B 24 Feb 17 24 Feb 17 283

284 Building 9A Ground & First Floor GAs 18 Apr 17 18 Apr 17 284

285 Building 8B Ground & First Floor GAs 01 Mar 17 01 Mar 17 285

286 Provide Reinforcement Intent for Core Walls and Columns - Building 5A and 5B 25 Apr 17 25 Apr 17 286

287 Provide Post Tension Slab Loading and deflection design - Building 8A 25 Apr 17 25 Apr 17 287

288 C1 Issue of Construction Information for Buildings 5A & 5B 04 May 17 04 May 17 288

289 Building 8A Ground & First Floor GAs 05 May 17 05 May 17 289

290 Provide Post Tension Slab Loading and deflection design - Buildings 5A and 5B 11 May 17 11 May 17 290

291 Building 5A and 5B ground & First Floor GAs 07 Jun 17 07 Jun 17 291

292 Stage F Architectural Design 24w 1d 15 Sep 16 17 Mar 17 292

293 Stage F Architectural Design 23w 1d 22 Sep 16 16 Mar 17 293

294 Frozen GA's and Elevations Building 5A 21 Oct 16 21 Oct 16 294

295 Frozen GA's and Elevations Building 5B 21 Oct 16 21 Oct 16 295

296 Frozen GA's and Elevations Building 8A 15 Sep 16 15 Sep 16 296

297 Frozen GA's and Elevations Building 8B 15 Sep 16 15 Sep 16 297

298 Frozen GA's and Elevations Building 9A 15 Sep 16 15 Sep 16 298

299 Finalised fully dimensioned Elevational Details 09 Dec 16 09 Dec 16 299

300 Finalised fully dimensioned GA's 17 Mar 17 17 Mar 17 300

301 Provide full GAs for all 2nd floor and above - Building 8A & 8B 06 Mar 17 06 Mar 17 301

302 Provide full GAs for all 2nd floor and above - Building 9A 06 Mar 17 06 Mar 17 302

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
303 Provide full GAs for all 2nd floor and above - Building 5A & 5B 06 Mar 17 06 Mar 17 303

304 Stage F Mechanical and Electrical Design 22w 22 Sep 16 08 Mar 17 304

305 Lifts 10 Jul 17 10 Jul 17 305

306 Roofing 20 Mar 17 20 Mar 17 306

307 Aluminium Roofing 20 Mar 17 20 Mar 17 307

308 Drylining and Ceilings 19 Jun 17 19 Jun 17 308

309 Raised Access Floors 31 Mar 17 31 Mar 17 309

310 External Works and Soft Landscaping 31 Mar 17 31 Mar 17 310

311 Metalwork, Handrails and Balustrades 17 May 17 17 May 17 311

312 Carpentry & Joinery 19 Jun 17 19 Jun 17 312

313 Carpet and Vinyl 20 Feb 17 20 Feb 17 313

314 MEP Services - Buildings 9A, 8A & 8B 19 Jun 17 19 Jun 17 314

315 MEP Services Buildings 5A & 5B 19 Jun 17 19 Jun 17 315

316 BMS (ELV) 20 Apr 17 20 Apr 17 316

317 Fire Alarms and Detection including Disabled Refuges 19 Jun 17 19 Jun 17 317

318 Smoke Extract Systems 19 Jun 17 19 Jun 17 318

319 Screeding 20 Mar 17 20 Mar 17 319

320 Tiling 20 Mar 17 20 Mar 17 320

321 Fire Curtains 20 Mar 17 20 Mar 17 321

322 Roof Louvres 20 Mar 17 20 Mar 17 322

323 Painting and Decorating 14 Aug 17 14 Aug 17 323

324 Loading Bay Doors 27 Jun 17 27 Jun 17 324

325 External Render 27 Jun 17 27 Jun 17 325

326 Mansafe latchway systems 20 Mar 17 20 Mar 17 326

327 Toilet Cubicle System 20 Mar 17 20 Mar 17 327

328 Fire Protection 20 Mar 17 20 Mar 17 328

329 Blockwork 31 Jan 17 31 Jan 17 329

330 Sprinklers 09 Jan 17 09 Jan 17 330

331 BWIC 09 Jan 17 09 Jan 17 331

332 Utilities 31 Oct 16 31 Oct 16 332

333 Provisional Sums Stage F Design 8w 2d 24 Jul 17 20 Sep 17 333

334 Undefined Provisional Sums 8w 2d 24 Jul 17 20 Sep 17 334

335 Temporary Car Park Design 8w 2d 24 Jul 17 20 Sep 17 335


336 MPX Instruct Design Team 1w 24 Jul 17 28 Jul 17 336
337 Farrells produce Stage F Architectural Design 5w 2d 31 Jul 17 06 Sep 17 337
338 AKT 2 Design 2w 07 Sep 17 20 Sep 17 338
339 HMP Design 2w 07 Sep 17 20 Sep 17 339

340 Vital Energy Design of Systems (defined provisional Sum) 65w 09 May 16 30 Aug 17340
341 Vital Energy produce Stage D design 7w 4d 09 May 16 01 Jul 16 341
342 Consultants review Vital Energy Stage D design and comment 2w 04 Jul 16 15 Jul 16 342

343 Vital Energy Produce Stage E design and coordinate with remainder of Infrastructure design 8w 18 Jul 16 12 Sep 16 343

344 ABP decision and order to Vital Enegi to proceed 4w 21 Nov 16 16 Dec 16 344

345 Vital Enegi produce Stage F design 6w 19 Dec 16 10 Feb 17 345

346 Order Pipework 21 Apr 17 21 Apr 17 346

347 Fabrication and delivery of pipework and valves 20w 30 Jan 17 22 Jun 17 347

348 Temporary Energy Centre Design (Undefined provisional Sum) 57w 2d 01 Jul 16 30 Aug 17 348

349 Temporary Energy Centre excluding Anxillary Buildings 57w 2d 01 Jul 16 30 Aug 17 349

350 Vital Energi provide Stage C design for temporary energy centre 01 Jul 16 01 Jul 16 350

351 ABP/WTP review Design and approve 1w 3d 01 Jul 16 12 Jul 16 351

352 Farrells prepare and submit Temporary energy centre for planning 1w 13 Jul 16 19 Jul 16 352

353 LBN Planning Approval 5w 3d 20 Jul 16 26 Aug 16 353

354 Stage D Temporary Energy Centre Design 8w 13 Jul 16 07 Sep 16 354

355 Temporary Energy Centre ABP/WTP Review and accept Stage D design 1w 08 Sep 16 14 Sep 16 355

356 Stage E design of Temporary Energy Centre 8w 20 Jan 17 16 Mar 17 356

357 ABP/WTP Acceptance of Vital Energi design of Temporary Energy Centre 1w 13 Mar 17 17 Mar 17 357

358 Stage F Temporary Energy Centre (Undefined provisional Sum) 10w 2d 20 Mar 17 05 Jun 17 358

359 MPX instruction to Consultant inorder to redesign Stage F 19 Jun 17 19 Jun 17 359
360 Detailed design development by Architect and Structural Engineer for VE 5w 27 Jun 17 31 Jul 17 360
361 Farrells design Freeze date for VE 01 Aug 17 01 Aug 17 361
362 Planning Submission 1w 01 Aug 17 07 Aug 17 362

363 Consultant review of design (other consultants) for VE 4w 01 Aug 17 29 Aug 17 363
Release of final Stage F design (Information regarding the additional steel member for the landscape store released earlier due to 8
364 30 Aug 17 30 Aug 17 364
weeks lead time)
365 Statutory Authorities and Third Party Interfaces 91w 2d 31 May 16 04 Apr 18 365

366 Develop Programme and Logistics 9w 2d 28 Jun 16 03 Oct 16 366

367 Prepare & Submit Construction Environmental Management & Logistics Plan 4w 19 Jul 16 15 Aug 16 367

368 LBN Approval of Logistics Plan 11w 4d 16 Aug 16 01 Dec 16 368

369 MOLA Report and Investigation 6w 28 Jun 16 08 Aug 16 369

370 Site Investigation and Sampling for Soil Contamination 8w 31 Oct 16 23 Dec 16 370

371 Undertake Background Noise Level Survey 6w 14 Nov 16 23 Dec 16 371

372 UXO Plan 12w 12 Jul 16 05 Oct 16 372

373 Application To EA For Working Near a Watercourse 17w 31 May 16 23 Dec 16 373

374 Prepare Scheme For Monitoring Magnetic Interference & Submit To LBN For Approval 17w 1d 05 Aug 16 20 Mar 17 374

375 Complete negotiations with Thames Water and agree price for connections and manholes 10w 3d 23 Aug 16 09 Dec 16 375

376 Enter into contract with Thames Water for Connection works 12w 12 Dec 16 01 Aug 17 376

377 Thames Water / DLR lead-in (assumed) 24w 02 Aug 17 09 Feb 18 377

378 Prepare Application To LBN For Working Above Designated Maximum Height and approval of same 16w 01 Aug 16 09 Dec 16 378

379 Prepare Water Discharge License Applications To LBN, RoDMA & Thames Water 4w 19 Dec 16 27 Jan 17 379

380 Planning Conditions 85w 2d 12 Jul 16 04 Apr 18 380

381 Procure consultant and consultants lead-in 2w 22 Jul 16 04 Aug 16 381

382 Pre-construction Condition A06 - Physical Facade Mock Up 77w 4d 05 Sep 16 04 Apr 18 382

383 CITIC/MPX Place orders for precast, windows and metalwork 4w 05 Sep 16 30 Sep 16 383

384 Prepare Brick Sample panels and submit 4w 13 Sep 16 10 Oct 16 384

385 LBN approval period for brick samples 3w 05 Dec 16 07 Apr 17 385

386 Place Brick Order 2d 10 Apr 17 11 Apr 17 386

387 Brick Delivery period 3w 12 Apr 17 05 May 17 387

388 Detailed design development of Precast Concrete Panels 14w 2d 12 Sep 16 20 Dec 16 388

389 Outline design of mock up windows and other components 3w 10 Oct 16 28 Oct 16 389

390 Detailed Design of windows, shopfronts, balconies etc 7w 2d 31 Oct 16 20 Dec 16 390

391 Provide samples and Specifications of all materials 26 Sep 16 26 Sep 16 391

392 Details of the typical ground floor facade treatment 03 Oct 16 03 Oct 16 392

393 Details of the typical facade treatments for the elevations facing any courtyard or square 10 Oct 16 10 Oct 16 393

394 Details of the top floor facade treatments 31 Oct 16 31 Oct 16 394

395 Details of windows, doors, entrances, reveals and sills, balconies, canopies, balustrades and material junctions 19 Dec 16 19 Dec 16 395

396 Annotated plans of the above 21 Dec 16 21 Dec 16 396

397 Manufacture of moulds, casting and delivery of Installation of Physical Facade Mock Up 4w 20 Feb 17 17 Mar 17 397

398 Manufacture of windows and other components 3w 04 Apr 17 26 Apr 17 398

399 Production of Physical Facade Mock Up (PC Concrete Panels) 2w 13 Apr 17 28 Apr 17 399

400 Installation of windows for mock up panels 1w 09 May 17 16 Jun 17 400

401 LBN Inspection and Comment on Physical Mock ups for Type and Type B buildings 1w 28 Apr 17 05 May 17 401

402 Carry out any necessary alterations to design, moulds etc 2w 08 May 17 19 May 17 402

403 Produce revised physical mockups and install on site 4w 19 May 17 16 Jun 17 403

404 LBN approval of Physical Facade Mock Up 6w 3d 24 Apr 17 14 Jul 17 404

405 Start production of precast cladding units 15 May 17 15 May 17 405

406 Produce precast cladding units 40w 15 May 17 26 Mar 18 406

407 Install windows to precast units (assumed off site) 27w 01 Sep 17 04 Apr 18 407

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
408 Start installation of precast units 06 Nov 17 06 Nov 17 408

409
409 Pre-construction Condition C01 - UXO Site Safety & Emergency Procedures 10w 12 Jul 16 21 Sep 16
410 Provide an UXO site safety and emergency procedures plan for submission to LBN 1w 12 Jul 16 18 Jul 16 410

411 Review and submit UXO site safety and emergency procedures plan 1w 19 Jul 16 25 Jul 16 411

412 LBN consider UXO site safety and emergency procedures plan 8w 26 Jul 16 20 Sep 16 412

413 LBN approve site safety and emergency procedures plan 21 Sep 16 21 Sep 16 413

414 Pre-construction Condition C09 - Monitoring of Magnetic Interference during Construction 30w 05 Aug 16 20 Mar 17 414

415 Produce a scheme for monitoring magnetic interference during construction 4w 05 Aug 16 02 Sep 16 415

416 Submit a scheme for monitoring magnetic interference during construction 05 Sep 16 05 Sep 16 416

417 LBN consider scheme for monitoring magnetic interference during construction 8w 31 Oct 16 23 Dec 16 417

418 LBN approve scheme for monitoring magnetic interference during construction 20 Mar 17 20 Mar 17 418

419
419 Pre-construction Condition C12 - Signage prohibiting feeding of wildlife and waterfowl. 16w 05 Aug 16 28 Nov 16
420 Produce details of the number and location of signs prohibiting the feeding of wildlife and waterfowl 4w 05 Aug 16 02 Sep 16 420

421 Submit details of the number and location of signs prohibiting the feeding of wildlife and waterfowl 05 Sep 16 05 Sep 16 421

422 LBN consider details of the number and location of signs prohibiting the feeding of wildlife and waterfowl 8w 05 Sep 16 25 Nov 16 422

423 LBN approve details of the number and location of signs prohibiting the feeding of wildlife and waterfowl 28 Nov 16 28 Nov 16 423

424 Pre-construction Condition C36 - EA approval for working adjacent to Watercourse 22w 4d 14 Dec 16 09 Jun 17 424

425 Carry out water sampling and testing and report 1w 14 Dec 16 20 Dec 16 425

426 Produce plan for dealing with water run-off from site 2d 25 Apr 17 26 Apr 17 426

427 EA approval of plan for control of water from site 6w 27 Apr 17 09 Jun 17 427

428 Complete liaison with Utilities Providers 16w 4d 13 Jun 16 07 Oct 16 428

429
429 Sub-Sub-Contract Package Procurement 134w 17 Jun 16 07 Mar 19
430 Prelim Packages Lead-ins 27w 17 Jun 16 09 Jan 17 430

431 Site Hoarding 26w 1d 17 Jun 16 20 Dec 16 431

432 Site Hoarding 4w 1d 21 Nov 16 20 Dec 16 432

433 ABP/WTP Approval and Instruction 3w 16 Sep 16 10 Oct 16 433

434 Submit RAMS, Specification and drawings showing hoardings etc. 11 Jul 16 11 Jul 16 434

435 GLA Approval to start on site 2w 11 Jul 16 22 Jul 16 435

436 Hoarding tender returns 1d 17 Jun 16 17 Jun 16 436

437 Recommendation 3w 20 Jun 16 08 Jul 16 437

438 Site Accommodation 6w 03 Nov 16 09 Jan 17 438

439 Dewatering 5w 2d 10 Nov 16 16 Dec 16 439

440 Place order for dewatering 1w 10 Nov 16 16 Nov 16 440

441 Mobilise dewatering including RAMS approval 1w 12 Dec 16 16 Dec 16 441

442 Place order for Site Setting out 2w 07 Oct 16 20 Oct 16 442

443 Works Package Orders and Lead-in 128w 4d 25 Jul 16 07 Mar 19 443

444
444 Prelims and Early Works 76w 2d 25 Jul 16 12 Feb 18
445 Site Setting out and Survey - SES - A17.2 5w 12 Sep 16 05 Dec 16 445

446 Hoarding and Site Set Up - Pacific - A1201 7w 2d 12 Sep 16 05 Dec 16 446

447 Site Security Early Works - Phoenix - A22 8w 4d 25 Jul 16 07 Nov 16 447

448 Site Security Main Works - Phoenix - A22 7w 4d 01 Nov 16 09 Jan 17 448

449 UXO Survey - Dynasafe Bactec 8w 30 Aug 16 09 Jan 17 449

450 Test Pile and Temporary Access Bridge Piles - Keltbray 9w 09 Sep 16 18 Jan 17 450

451 Site Welfare and Accommodation - Premier Modular 12w 30 Aug 16 23 Jan 17 451

452 Logistics - A1301 12w 30 Aug 16 04 May 17 452

453 Temporary Site Services - EMS - A27 9w 30 Aug 16 09 Jan 17 453

454 Environmental Monitoring - Various 3w 17 Oct 16 09 Jan 17 454

455 Hoisting 35w 4d 28 Mar 17 12 Feb 18 455

456
456 Provisional Sums 127w 05 Aug 16 07 Mar 19
457 Raised Access Floors 41w 1d 16 May 17 08 Oct 18 457

458 Soft Landscaping 34w 3d 15 Jun 17 09 Mar 18 458

459 Energy Supplier - Vital Energi 18w 13 Feb 17 17 Jul 17 459

460 Windows Package - Canopies Fabrication & Install 27w 25 Jan 17 07 Feb 18 460

461 Windows Package - Canopies Design 17w 26 Jan 17 17 Nov 17 461

462 Water Feature 41w 2d 06 Nov 17 10 Sep 18 462

463 Listed Building 75w 1d 23 Feb 17 29 Aug 18 463


464 Asbestos Survey & Guano Removal 8w 2d 23 Feb 17 22 May 17 464

465 Asbestos removal 10w 30 Mar 17 24 Jul 17


465
466 Scope and Tender List 1w 13 Apr 17 21 Apr 17 466
467 Finalise Scope 24 Apr 17 24 Apr 17 467
468 Pre-Qualfication (PAM 12 / 41) 1w 24 Apr 17 28 Apr 17 468

469 Complete Pre-Qualification 02 May 17 02 May 17 469

470 Tender Design complete 02 May 17 02 May 17 470


471 Prepare Tender Documents 1w 02 May 17 08 May 17 471

472 Out to Tender 09 May 17 09 May 17 472

473 Tender Period 1w 09 May 17 15 May 17 473

474 Tender Return Date 2w 09 May 17 18 Aug 17 474


475 Tender reconciliation 2w 21 Aug 17 22 Sep 17 475

476 Recommended sub-contractor (PAM 16) 25 Sep 17 25 Sep 17 476

477 Review recommendation 2w 15 Sep 17 28 Sep 17 477

478 Issue final design information 1w 25 Sep 17 29 Sep 17 478


479 Issue Approval to Let (PAM 18) 2w 02 Oct 17 13 Oct 17 479

480 Agree Ts and Cs and execute Sub-contract (PAM 20) 1w 17 Oct 17 23 Oct 17 480

481 Sub-contractor fabrication, procurement and mobilisation 2w 16 Oct 17 27 Oct 17 481

482 Sub-contract signed by both parties 4d 24 Oct 17 27 Oct 17 482

483 Start on Site 30 Oct 17 30 Oct 17 483


484 Scope and Tender List 1w 13 Apr 17 21 Apr 17 484
485 Finalise Scope 24 Apr 17 24 Apr 17 485
486 Pre-Qualfication (PAM 12 / 41) 1w 24 Apr 17 28 Apr 17 486
487 Complete Pre-Qualification 02 May 17 02 May 17 487
488 Tender Design complete 02 May 17 02 May 17 488
489 Prepare Tender Documents 1w 02 May 17 08 May 17 489
490 Out to Tender 09 May 17 09 May 17 490
491 Tender Period 1w 09 May 17 15 May 17 491
492 Tender Return Date 2w 16 May 17 18 Aug 17 492

493 Tender reconciliation 2w 21 Aug 17 22 Sep 17 493

494 Recommended sub-contractor (PAM 16) 25 Sep 17 25 Sep 17 494

495 Review recommendation 2w 18 Sep 17 29 Sep 17 495

496 Issue final design information 1w 25 Sep 17 29 Sep 17 496


497 Issue Approval to Let (PAM 18) 2w 02 Oct 17 13 Oct 17 497

498 Agree Ts and Cs and execute Sub-contract (PAM 20) 1w 17 Oct 17 23 Oct 17 498

499 Sub-contractor fabrication, procurement and mobilisation 2w 16 Oct 17 27 Oct 17 499

500 Sub-contract signed by both parties 4d 24 Oct 17 27 Oct 17 500

501 Start on Site 30 Oct 17 30 Oct 17 501


502 Scope and Tender List 1w 13 Apr 17 21 Apr 17 502
503 Finalise Scope 24 Apr 17 24 Apr 17 503
504 Pre-Qualfication (PAM 12 / 41) 1w 24 Apr 17 28 Apr 17 504
505 Complete Pre-Qualification 02 May 17 02 May 17 505
506 Tender Design complete 02 May 17 02 May 17 506
507 Prepare Tender Documents 1w 02 May 17 08 May 17 507
508 Out to Tender 09 May 17 09 May 17 508
509 Tender Period 1w 09 May 17 15 May 17 509
510 Tender Return Date 2w 16 May 17 18 Aug 17 510
511 Tender reconciliation 2w 21 Aug 17 22 Sep 17 511

512 Recommended sub-contractor (PAM 16) 25 Sep 17 25 Sep 17 512

513 Review recommendation 2w 18 Sep 17 29 Sep 17 513

514 Issue final design information 1w 25 Sep 17 29 Sep 17 514


515 Issue Approval to Let (PAM 18) 2w 02 Oct 17 13 Oct 17 515

516 Agree Ts and Cs and execute Sub-contract (PAM 20) 1w 17 Oct 17 23 Oct 17 516

517 Sub-contractor fabrication, procurement and mobilisation 2w 16 Oct 17 27 Oct 17 517

518 Sub-contract signed by both parties 4d 24 Oct 17 27 Oct 17 518

519 Start on Site 30 Oct 17 30 Oct 17 519


520 Scope and Tender List 1w 13 Apr 17 21 Apr 17 520
521 Finalise Scope 24 Apr 17 24 Apr 17 521
522 Pre-Qualfication (PAM 12 / 41) 1w 24 Apr 17 28 Apr 17 522

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
523 Complete Pre-Qualification 02 May 17 02 May 17 523
524 Tender Design complete 02 May 17 02 May 17 524
525 Prepare Tender Documents 1w 02 May 17 08 May 17 525
526 Out to Tender 09 May 17 09 May 17 526
527 Tender Period 1w 09 May 17 15 May 17 527
528 Tender Return Date 2w 16 May 17 18 Aug 17 528
529 Tender reconciliation 2w 21 Aug 17 22 Sep 17 529
530 Recommended sub-contractor (PAM 16) 25 Sep 17 25 Sep 17 530

531 Review recommendation 2w 18 Sep 17 29 Sep 17 531

532 Issue final design information 1w 25 Sep 17 29 Sep 17 532

533 Issue Approval to Let (PAM 18) 2w 02 Oct 17 13 Oct 17 533

534 Agree Ts and Cs and execute Sub-contract (PAM 20) 1w 17 Oct 17 23 Oct 17 534

535 Sub-contractor fabrication, procurement and mobilisation 2w 16 Oct 17 27 Oct 17 535

536 Sub-contract signed by both parties 4d 24 Oct 17 27 Oct 17 536

537 Start on Site 30 Oct 17 30 Oct 17 537


538 Scope and Tender List 1w 13 Apr 17 21 Apr 17 538
539 Finalise Scope 24 Apr 17 24 Apr 17 539
540 Pre-Qualfication (PAM 12 / 41) 1w 24 Apr 17 28 Apr 17 540
541 Complete Pre-Qualification 02 May 17 02 May 17 541
542 Tender Design complete 02 May 17 02 May 17 542
543 Prepare Tender Documents 1w 02 May 17 08 May 17 543
544 Out to Tender 09 May 17 09 May 17 544
545 Tender Period 1w 09 May 17 15 May 17 545
546 Tender Return Date 2w 16 May 17 18 Aug 17 546
547 Tender reconciliation 2w 21 Aug 17 22 Sep 17 547
548 Recommended sub-contractor (PAM 16) 25 Sep 17 25 Sep 17 548

549 Review recommendation 2w 18 Sep 17 29 Sep 17 549

550 Issue final design information 1w 25 Sep 17 29 Sep 17 550


551 Issue Approval to Let (PAM 18) 2w 02 Oct 17 13 Oct 17 551

552 Agree Ts and Cs and execute Sub-contract (PAM 20) 1w 17 Oct 17 23 Oct 17 552

553 Sub-contractor fabrication, procurement and mobilisation 2w 16 Oct 17 27 Oct 17 553

554 Sub-contract signed by both parties 4d 24 Oct 17 27 Oct 17 554

555 Start on Site 30 Oct 17 30 Oct 17 555

556 Shell & Core Restoration 33w 17 Jan 18 29 Aug 18 556


557 Temporary Energy Centre 51w 1d 24 Apr 17 04 May 18 557

558 Services 13w 3d 24 Apr 17 31 Jul 17 558

559 Concrete works 12w 4d 25 May 17 23 Aug 17 559

560 Steel Frame 15w 4d 14 Jun 17 28 Nov 17 560


561 Cladding 17w 1d 30 Jun 17 24 Jan 18 561
562 TEC Equipment 30w 26 Apr 17 13 Feb 18 562
563 Modular Unit 35w 3d 22 May 17 04 May 18 563

564 Ground works Package - E4 dockside coping stone 26w 2d 06 Nov 17 22 May 18 564

565 Dewatering Package - Discharge into Docks 30w 05 Aug 16 22 May 17 565

566 Extra Low Voltage (ELV) Package 40w 31 Mar 17 07 Feb 18 566

567 Signage 37w 3d 22 Jan 18 19 Oct 18 567

568 Dock Wall Repairs & Alteration works 22w 12 Sep 17 08 Mar 18 568

569 Information Light Wall 30w 3d 12 Feb 18 21 Sep 18 569

570 External Lighting - Fixtures 40w 06 Nov 17 30 Aug 18 570

571 External Lighting - Distribution 40w 06 Nov 17 30 Aug 18 571

572 Temporary Carpark - Procurement 16w 2d 21 Sep 17 24 Jan 18 572


573 Temporary Carpark 14w 2d 21 Sep 17 24 Jan 18 573

574 Security 22w 2d 18 Sep 18 07 Mar 19 574

575 Type B Lobby Fitout 39w 4d 06 Nov 17 16 Aug 18 575

576 Incoming Utilities 71w 2d 02 Mar 17 08 Aug 18 576

577 Water Mains and Building connections 28w 1d 02 Mar 17 25 Sep 17 577
578 Thames Water sewer connection 33w 2d 09 Oct 17 29 Jun 18 578
579 Medium pressure gas connection 35w 2d 06 Nov 17 27 Jul 18 579
580 LV Switchgear and distribution 34w 06 Nov 17 18 Jul 18 580
581 VDV - Fibre Network 39w 09 Oct 17 08 Aug 18 581

582 Construction Works 110w 3d 22 Aug 16 14 Nov 18 582

583 Groundworks, Infrastructure and Dewatering - Galldris 14w 12 Sep 16 09 Jan 17 583

584 Piling - Keltbray 19w 3d 16 Nov 16 12 May 17 584

585 Pre-Cast Concrete Cladding - Thorp - D713 53w 2d 22 Aug 16 20 Feb 18 585

586 Concrete Works - Mitchellson 26w 23 Sep 16 19 Jun 17 586

587 Windows/ Curtain Walling - Prater - D802 30w 17 Nov 16 17 Jan 18 587

588 Roofing and Waterproofing - Prater - D802 24w 4d 17 Nov 16 12 Jan 18 588

589 Lifts / Vertical Transportation - Schindler - F601 36w 4d 11 Jan 17 14 Mar 18 589

590 Scope and Tender List 3w 2d 18 Jan 17 09 Feb 17 590

591 Finalise Scope 2w 10 Feb 17 23 Feb 17 591

592 Pre-Qualfication (PAM 12 / 41) 24 Feb 17 24 Feb 17 592

593 Tender Design complete 24 Feb 17 24 Feb 17 593

594 Prepare Tender Documents 2w 24 Feb 17 09 Mar 17 594

595 Complete Pre-Qualification 10 Mar 17 10 Mar 17 595

596 Out to Tender 1w 10 Mar 17 16 Mar 17 596

597 Tender Period 4w 10 Apr 17 10 May 17 597

598 Tender reconciliation 2w 26 Jun 17 07 Jul 17 598

599 Tender Return Date 10 Jul 17 10 Jul 17 599

600 Recommended sub-contractor (PAM 16) 10 Jul 17 10 Jul 17 600

601
601 Issue final design information and re-price 2w 30 Jun 17 13 Jul 17

602 Review recommendation 1w 14 Jul 17 20 Jul 17 602

603 Issue Approval to Let (PAM 18) 1w 21 Jul 17 27 Jul 17 603

604 Agree Ts and Cs and execute Sub-contract (PAM 20) 2w 28 Jul 17 10 Aug 17 604

605 Sub-contract signed by both parties 1w 11 Aug 17 17 Aug 17 605

606 Sub-contractor Design Portion 6w 18 Aug 17 10 Nov 17 606

607
607 Sub-contractor fabrication, procurement and mobilisation 10w 11 Oct 17 11 Jan 18

608 Start on Site 12 Jan 18 12 Jan 18 608

609 Dry lining, Ceilings & associated works 37w 4d 06 Apr 17 26 Jan 18 609

610 Metalwork - Architectural and General - GK Engineering - E101 19w 3d 22 Dec 16 23 Aug 17 610

611 Doors and Joinery - Doug Phillips - E1001 36w 2d 17 Jan 17 22 Feb 18 611

612 Mechanical & Electrical Services and Plumbing - Mercury 26w 06 Feb 17 05 Dec 17 612

613 Dry Risers and Sprinklers - Argus Fire 30w 4d 24 Jan 17 04 Sep 17 613

614 External & Hard Landscaping Works 25w 2d 23 Jan 17 18 May 18 614

615 Scope and Tender List 4w 23 Nov 16 20 Dec 16 615

616 Finalise Scope 2w 21 Dec 16 17 Jan 17 616

617 Pre-Qualfication (PAM 12 / 41) 18 Jan 17 18 Jan 17 617

618 Complete Pre-Qualification 18 Jan 17 18 Jan 17 618

619 Tender Design complete 18 Jan 17 18 Jan 17 619

620 Prepare Tender Documents 2w 18 Jan 17 31 Jan 17 620

621 Out to Tender 2d 01 Feb 17 02 Feb 17 621

622 Tender Period 4w 03 Feb 17 02 Mar 17 622

623 Tender Return Date 03 Mar 17 03 Mar 17 623

624 Tender reconciliation 2w 03 Mar 17 16 Mar 17 624

625 Recommended sub-contractor (PAM 16) 1w 22 May 17 26 May 17 625

626 Issue final design information 2w 30 May 17 12 Jun 17 626

627 Review recommendation 3w 13 Jun 17 03 Jul 17 627

628 Issue Approval to Let (PAM 18) 04 Jul 17 04 Jul 17 628

629 Agree Ts and Cs and execute Sub-contract (PAM 20) 2w 04 Jul 17 17 Jul 17 629

630 Sub-contract signed by both parties 3d 18 Jul 17 20 Jul 17 630

631 Sub-contractor Design Portion 5w 21 Jul 17 24 Aug 17 631

632 Sub-contractor fabrication, procurement and mobilisation 5w 25 Aug 17 17 Nov 17 632

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
633 Start on Site 20 Nov 17 20 Nov 17 633

634 Floor and Wall Tiling, and Stone Flooring 25w 09 Oct 17 30 Apr 18 634

635 Screeding 20w 23 Aug 17 16 Mar 18 635

636 Painting and Decorating 23w 4d 23 Aug 17 16 Apr 18 636

637 Carpet Tiling and Soft Flooring 37w 26 Jan 18 22 Oct 18 637

638 Part L Air Leakage Testing 26w 2d 19 Jan 17 05 Jul 18 638

639 Builders Clean 31w 05 Apr 18 14 Nov 18 639

640 Sub-Sub-Contractor Design Portions 93w 4d 01 Aug 16 26 Jun 18 640

641 Thermographic Modelling 4w 31 Oct 16 25 Nov 16 641

642 Thermographic Analysis 4w 30 May 18 26 Jun 18 642

643 CPD Piling design and approval by AKT II 5w 21 Nov 16 23 Dec 16 643

644 Gas/waterpoofing membrane design 4w 28 Nov 16 23 Dec 16 644

645
645 Temporary Works Design 26w 05 Sep 16 17 Mar 17
646 Site Access Bridge 12w 05 Sep 16 25 Nov 16 646

647 Site access bridge temporary works design 6w 05 Sep 16 09 Nov 16 647

648 Site access bridge pricing 1w 10 Nov 16 16 Nov 16 648

649 Instruct S/C 2d 17 Nov 16 18 Nov 16 649

650 Lead-in including RAMS approval by GLA 1w 21 Nov 16 25 Nov 16 650

651
651 Groundworks and Infrastructure 14w 28 Nov 16 17 Mar 17
652 Temporary Works Excavation design for trenching 3w 31 Jan 17 10 Mar 17 652

653 MPX approval of Temporary Works Design 1w 13 Mar 17 17 Mar 17 653

654 Procure materials for trenching 2w 12 Dec 16 23 Dec 16 654

655 Crane mat design 4w 28 Nov 16 23 Dec 16 655

656 Piling mat design 2w 12 Dec 16 23 Dec 16 656

657 Substructure Reinforcement Detailing 14w 08 Dec 16 29 Mar 17 657

658 Substructure Reinforcement detailing 10w 08 Dec 16 01 Mar 17 658

659 Substructure Reinforcement AKT II approvals 10w 22 Dec 16 15 Mar 17 659

660 Substructure Reinforcement Procurement Lead-in 10w 19 Jan 17 29 Mar 17 660

661 Building 9A 3w 02 Feb 17 22 Feb 17 661

662 Building 8B 3w 06 Feb 17 24 Feb 17 662

663 Building 8A 3w 08 Feb 17 28 Feb 17 663

664 Building 5A 3w 10 Feb 17 02 Mar 17 664

665 Building 5B 3w 14 Feb 17 06 Mar 17 665

666
666 Superstructure Reinforcement detailing 13w 1d 27 Feb 17 02 Jun 17
667 Superstructure Post tensioned concrete design and detailing 13w 27 Feb 17 02 Jun 17 667

668 Superstructure Precast / RC design and/or detailing 11w 13 Mar 17 02 Jun 17 668

669 Precast Cladding 30w 4d 01 Aug 16 17 Mar 17 669

670 Precast concrete design and fixing to structure 4w 01 Aug 16 26 Aug 16 670

671 Precast concrete cladding Subcontractor to advise stacking loads and eccentricity 15 Aug 16 15 Aug 16 671

672 Facade precast concrete design 16w 05 Sep 16 17 Mar 17 672

673 Structural steelwork fabrication drawings for TEC 6w 19 Jun 17 28 Jul 17 673

674 Secondary steelwork design 3w 3d 17 May 17 13 Jul 17 674

675 Plant support steelwork design 3w 3d 14 Jul 17 08 Aug 17 675

676 BWIC under 200mm in size 8w 03 Jul 17 25 Aug 17 676

677 Windows and associated doors, copings, screens and flashings 6w 03 Oct 16 02 Jun 17 677

678 Facade insulation and waterproofing 4w 17 Oct 16 30 Jun 17 678

679 Facade Access System 7w 18 Sep 17 17 Nov 17 679

680 Blockwork windposts, lintols and ties 4w 25 Apr 17 20 Jul 17 680

681 Movement joints, acoustic and fireproofing of joints to masonry and dry-lining 5w 21 Nov 16 23 Dec 16 681

682 Masonry ventilation ducts 4w 21 Jul 17 17 Aug 17 682

683 Louvre screens to roof 6w 18 Aug 17 29 Sep 17 683

684 Lightning Protection 7w 17 Jul 17 04 Sep 17 684

685 Sprinkler system 7w 24 Jul 17 16 Oct 17 685

686 BMS 7w 24 Jul 17 16 Oct 17 686

687 Fire detection and alarms 7w 24 Jul 17 16 Oct 17 687

688 Containment to Security / Access Control/CCTV/IDS 7w 24 Jul 17 16 Oct 17 688

689 Containment for AV/IT/Data 7w 24 Jul 17 16 Oct 17 689

690 Smoke extraction systems 7w 24 Jul 17 16 Oct 17 690

691 Vertical Transportation (VT) (Lifts) incl intercom and CCTV 13w 22 Aug 16 31 Aug 17 691

692 Type B Building lifts 36w 1d 22 Jun 17 13 Mar 18 692

693 Start workshop and issue information 22 Jun 17 22 Jun 17 693

694 Drawing 4w 22 Jun 17 19 Jul 17 694

695 MPX Comment 2w 20 Jul 17 02 Aug 17 695

696 Revise Drawings 2w 03 Aug 17 19 Oct 17 696

697 MPX Comment 2w 20 Oct 17 16 Nov 17 697

698 Materials Order, Manufacture, Transport and Delivery 15w 1d 17 Nov 17 13 Mar 18 698

699
699 Type A Building Lifts 28w 1d 19 May 17 05 Dec 17
700 Drawing 2w 19 May 17 02 Jun 17 700

701 MPX Comment 2w 19 Jun 17 30 Jun 17 701

702 Revise Drawings 2w 03 Jul 17 21 Jul 17 702

703 MPX Comment 2w 24 Jul 17 04 Aug 17 703

704 Materials Order, Manufacture, Transport and Delivery 10w 07 Aug 17 05 Dec 17 704

705
705 Construction Works 129w 3d 18 Jul 16 06 Mar 19
706 Early Works and Phase 1 Enabling works 50w 4d 21 Sep 16 02 Oct 17 706

707 Establish primary settting out stations and grids on site 1w 21 Oct 16 27 Oct 16 707

708 Potential Early Start for Site Hoardings 2w 3d 21 Sep 16 10 Oct 16 708

709 MPX submit information for GLA Licence 3d 21 Sep 16 23 Sep 16 709

710 ABP to apply for GLA Licence for use of Site Areas outwith Phase 1 26 Sep 16 26 Sep 16 710

711 GLA Consider Licence Application 2w 26 Sep 16 07 Oct 16 711

712 GLA Grant Licence for use of Site Areas Outwith Phase 1 10 Oct 16 10 Oct 16 712

713 ABP/WTP Instruct CITIC/MPX to proceed with Hoardings 10 Oct 16 10 Oct 16 713

714 Potential Eartly Start to Hoardings 09 Jan 17 09 Jan 17 714

715
715 Hoarding To Site 14w 3d 10 Nov 16 06 Mar 17
716 Place order with S/C 10 Nov 16 10 Nov 16 716

717 Order concrete blocks 10 Nov 16 10 Nov 16 717

718 Lead in - including GLA re-approval of RAMS 2w 10 Nov 16 23 Nov 16 718

719 Start installing posts in soft ground to NW corner of site adjacent to 1000 - (360 metres) 2w 09 Feb 17 06 Mar 17 719

720 Deliver concrete blocks 09 Jan 17 30 Jan 17 720

721 Erect hoarding to Dock side and decorate / brand (740 metres) 3w 13 Jan 17 02 Feb 17 721

722 Erect hoarding to remainder of site up to Becton Park Station from West to East (510 m) 1w 23 Jan 17 27 Jan 17 722

723 Erect remainder of hoarding to East end of site (500m) 1w 24 Jan 17 30 Jan 17 723

724 Test Pile 12w 2d 10 Nov 16 17 Feb 17 724

725 MPX / CITIC Instruct piling contractor 10 Nov 16 10 Nov 16 725

726 Piling contractor lead in / mobilisation for rig 4w 08 Dec 16 18 Jan 17 726

727 Test pile works and Report 6w 09 Jan 17 17 Feb 17 727

728 Set out for test pile 1d 09 Jan 17 09 Jan 17 728

729 Break out hardstandings at pile locations 1d 10 Jan 17 10 Jan 17 729

730 UXO survey for test piling 1d 11 Jan 17 11 Jan 17 730

731 Excavate (assume U/S) and cart to tip for piling platform 1d 12 Jan 17 12 Jan 17 731

732 Form piling platform and get approval to use. 1d 13 Jan 17 13 Jan 17 732

733 Install test pile and anchor piles 2d 19 Jan 17 20 Jan 17 733

734 Cure test pile 1w 30 Jan 17 03 Feb 17 734

735 Load test pile 2d 06 Feb 17 07 Feb 17 735

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
736 Provide test pile report 2w 06 Feb 17 17 Feb 17 736

737
737 Dock Wall survey 19w 4d 15 May 17 02 Oct 17
738 MPX Issue Tender report intrusive survey for ABP/WTP approval 2w 15 May 17 26 May 17 738

739 ABP/WTP to review and instruct Intrusive survey 2w 30 May 17 12 Jun 17 739

740 MPX Proceed with Survey and issue Reports 15w 24 May 17 02 Oct 17 740

741
741 Entrance Access Bridge 5w 16 Jan 17 17 Feb 17
742 Install mini piles for entrance bridge slab 3d 16 Jan 17 18 Jan 17 742

743 Construct access bridge 4w 23 Jan 17 17 Feb 17 743

744 Dig down, expose and cap off existing drainage from the apron into the dock where shown on the drawings or visible. 4w 10 Apr 17 10 May 17 744

745 Set up dewatering system 3w 09 Jan 17 27 Jan 17 745

746 UXO Survey including drilling through hardstandings 8w 12 Dec 16 17 Feb 17 746

747 Carry out soil investigation to identify areas and extent of contamination and report on remediation necessary 3w 23 Jan 17 10 Feb 17 747

748 Site Accommodation 21w 4d 24 Nov 16 15 May 17 748

749 Prepare site for site accommodation 4w 20 Dec 16 30 Jan 17 749

750 Install below ground drainage and temporary services to site accommodation area 2w 30 Jan 17 10 Feb 17 750

751 Construct Site Accommodation 21w 4d 24 Nov 16 15 May 17 751

752 Construct Site Accommodation 5w 1d 24 Nov 16 28 Apr 17 752

753 Install IT into Site Accommodation 2w 28 Apr 17 12 May 17 753

754 Fit out furniture to Site Accommodation 2w 28 Apr 17 12 May 17 754

755 Site Accommodation ready 15 May 17 15 May 17 755

756 Base Slab & Ducts for Substation (by others direct) 3w 30 Jan 17 17 Feb 17 756

757 Install temporary feeds for power, lighting, water and telecomms 3w 02 Feb 17 04 May 17 757

758 Start Phase 1 Works 1d 25 Apr 17 25 Apr 17 758

759 Start Phase 1 Works 1d 25 Apr 17 25 Apr 17 759

760 Phase 1 Ground and Infrastructure Works 78w 08 Mar 17 28 Sep 18 760

761 Ground Works 15w 4d 08 Mar 17 30 Jun 17 761

762 Mobilise Crusher 1w 4d 28 Mar 17 07 Apr 17 762

763 Set up Concrete Crusher on Site 1w 1d 10 Apr 17 19 Apr 17 763

764 Site Clearance 3w 10 Apr 17 03 May 17 764

765 Break up Concrete Hardstandings 8w 22 Mar 17 19 May 17 765

766 Break up Tarmac Hardstandings 8w 22 Mar 17 19 May 17 766

767 Break Out Underground Obstructions 8w 22 Mar 17 19 May 17 767

768 Crush Concrete on Site 10w 08 Mar 17 19 May 17 768

769 Reduced level dig throughout and cart to tip as necessary 10w 08 Mar 17 19 May 17 769

770 Generate phasing and alignment of temp roads 5w 12 Apr 17 19 May 17 770

771 Carry out any remediation of soils that may be necessary (Variation) 5w 12 Apr 17 19 May 17 771

772 Lay Temporary Site Roads 6w 21 Apr 17 30 Jun 17 772

773 Retaining wall between Buildings 9A & 10A 5w 18 May 17 22 Jun 17 773

774
774 Drainage & Services Between Manholes SM11/FM11 to SM9/FM9 & FM11/SM11 to FM31 and SM38(Stage 1) 59w 4d 03 Apr 17 18 Jun 18
775 Stage 1 Deep level infrastructure 55w 3d 03 Apr 17 17 May 18 775

776 Trench Support System 2w 03 Apr 17 18 Apr 17 776

777 Excavation & Temporary Propping 2w 11 Apr 17 26 Apr 17 777

778 Build Manhole FM11 & SM11 (including rocker pipes towards Sewer connections) 2w 19 Apr 17 03 May 17 778

779 Build Manholes FM10 and SM10 2w 26 Apr 17 10 May 17 779

780 Lay Foul & Surface Water drainage Pipes FM 11/SM11 To FM9/SM9 1w 1d 04 May 17 11 May 17 780

781 Backfill & Compact Over Pipes 1w 1d 09 May 17 16 May 17 781

782 Lay Foul & Surface Water drainage Pipes SM38 & FM31 To FM11 & SM11 2w 1d 24 Apr 17 09 May 17 782

783 Backfill & Compact Over Pipes 2w 1d 25 Apr 17 10 May 17 783

784 Connection into Main Sewer in Royal Albert Way 13w 12 Feb 18 17 May 18 784

785 High level services 10w 1d 04 Apr 18 18 Jun 18 785

786 Excavate & Construct Service Ducts for Electric cables 2w 04 Apr 18 17 Apr 18 786

787 Excavate for water main 1w 18 Apr 18 24 Apr 18 787

788 Install Water main 1w 25 Apr 18 02 May 18 788

789 Backfill water main 3d 03 May 18 08 May 18 789

790 Excavate Trenches & Lay Ducts for data and Telecoms 2w 09 May 18 22 May 18 790

791 Excavate For District Heating and Cooling Pipes 1w 23 May 18 30 May 18 791

792 Install District Heating and Cooling Pipes for Building 10A 1w 31 May 18 06 Jun 18 792

793 Backfill District Heating and Cooling Pipes 1w 2d 08 Jun 18 18 Jun 18 793

794 Connect DH/DC to Building 10A 1w 07 Jun 18 13 Jun 18 794

795
795 Drainage & Services Between Manholes SM30/FM24 to SM7/FM7 (Stage 1A) 2w 1d 05 May 17 19 May 17
796 Stage 1A Deep level services 2w 1d 05 May 17 19 May 17 796

797 Excavation & Temporary Propping For Drainage 2w 08 May 17 19 May 17 797

798 Build Manhole FM26 & SM29 2w 1d 05 May 17 19 May 17 798

799 Lay Foul & Surface Water drainage Pipes FM 25 To FM7 2w 1d 05 May 17 19 May 17 799

800 Backfill & Compact Over Pipes 2w 08 May 17 19 May 17 800

801
801 Dockside Mews Buried Services 58w 4d 19 Jun 17 21 Aug 18
802 Prater clear of Mews on 8A side 12 Mar 18 12 Mar 18 802

803 Prater clear of Mews on 8B side 12 Mar 18 12 Mar 18 803

804 Prater clear of Mews on 5A side, East Elevation 24 Apr 18 24 Apr 18 804

805 Prater clear of Mews on 5A side, South Elevation 09 May 18 09 May 18 805

806 Between 8A and 8B 15w 1d 12 Mar 18 02 Jul 18 806


807 Drainage 4w 12 Mar 18 10 Apr 18 807
808 Storm Drainage 3w 2d 12 Mar 18 05 Apr 18 808
809 SM29 to SM33 4d 12 Mar 18 15 Mar 18 809
810 Build SM33 1d 16 Mar 18 16 Mar 18 810
811 SM33 to SM32 3d 19 Mar 18 21 Mar 18 811
812 Build SM 32 1d 22 Mar 18 22 Mar 18 812
813 SM32 to SM31 4d 23 Mar 18 28 Mar 18 813

814 Build SM31 1d 29 Mar 18 29 Mar 18 814


815 SM31 to SM30 2d 03 Apr 18 04 Apr 18 815

816 Build SM 30 1d 05 Apr 18 05 Apr 18 816


817 Foul Drainage 3w 19 Mar 18 10 Apr 18 817
818 FM26 to FM25 4d 19 Mar 18 22 Mar 18 818

819 Build FM 25 1d 23 Mar 18 23 Mar 18 819


820 FM25 to FM24 4d 26 Mar 18 29 Mar 18 820

821 Build FM24 1d 03 Apr 18 03 Apr 18 821


822 Connections in Formation 1w 04 Apr 18 10 Apr 18 822

823 Services 9w 3d 11 Apr 18 20 Jun 18 823

824 District Heating and Cooling 5w 3d 11 Apr 18 22 May 18 824


825 Excavate for District Heating and Cooling 1w 11 Apr 18 17 Apr 18 825
826 Install by others 4w 1d 18 Apr 18 18 May 18 826
827 Backfill 2d 21 May 18 22 May 18 827
828 Water Main 2w 21 May 18 04 Jun 18 828
829 Excavate for Water main 1w 21 May 18 25 May 18 829
830 Install by Others 3d 29 May 18 31 May 18 830
831 Backfill 2d 01 Jun 18 04 Jun 18 831
832 Combined Service Trench 2w 2d 05 Jun 18 20 Jun 18 832
833 Excavate for Combined Services 1w 05 Jun 18 11 Jun 18 833
834 Install ducts 1w 12 Jun 18 18 Jun 18 834
835 Backfill 2d 19 Jun 18 20 Jun 18 835

836 Complete drainage connection FM 26 to Building 8B / 2 3d 24 Apr 18 26 Apr 18 836

837 Complete drainage connection FM 26 to Building 8B / 1 3d 24 Apr 18 26 Apr 18 837

838 Prep for Paving 1w 3d 21 Jun 18 02 Jul 18 838


839 Install Tree Pits 6 Number 4d 21 Jun 18 26 Jun 18 839

840 Prep to formation level 1w 26 Jun 18 02 Jul 18 840

841 Between 5A and 8A 5w 2d 24 Apr 18 04 Jun 18 841


842 Excavate trench for DH/DC 3d 24 Apr 18 26 Apr 18 842

843 Install DH/DC mains 1w 30 Apr 18 04 May 18 843


844 Backfill 2d 08 May 18 09 May 18 844
845 Excavate for water main 2d 10 May 18 11 May 18 845

846 Install Water main 3d 14 May 18 16 May 18 846


847 Backfill water main 2d 17 May 18 18 May 18 847

848 Excavate for and install electric, data and telecoms ducts 1w 21 May 18 25 May 18 848

849 Prepare formation 1w 29 May 18 04 Jun 18 849

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
850 Ready to start flushing TEC to Buildings 8A and 8B 05 Jul 18 05 Jul 18 850

851 Dockside Mews GL 7 to 5 58w 4d 19 Jun 17 21 Aug 18 851

852 Drainage 7w 2d 19 Jun 17 08 Aug 17 852


853 SM18 to SM17 4d 19 Jun 17 22 Jun 17 853
854 Build SM 17 1d 23 Jun 17 23 Jun 17 854
855 SM17 to SM16 3d 26 Jun 17 28 Jun 17 855

856 Build SM 16 1d 29 Jun 17 29 Jun 17 856


857 SM16 to SM 15 1w 30 Jun 17 06 Jul 17 857
858 Build SM15 1d 07 Jul 17 07 Jul 17 858
859 SM15 to SM14 2d 10 Jul 17 11 Jul 17 859

860 Build SM 14 1d 12 Jul 17 12 Jul 17 860


861 FM17 to FM15 4d 13 Jul 17 18 Jul 17 861
862 Build FM 15 1d 19 Jul 17 19 Jul 17 862

863 FM15 to FM14 4d 20 Jul 17 25 Jul 17 863


864 Build FM 14 1d 26 Jul 17 26 Jul 17 864
865 FM14 to FM13 3d 27 Jul 17 31 Jul 17 865
866 Build FM13 1d 01 Aug 17 01 Aug 17 866
867 FM13 to FM12 2d 02 Aug 17 03 Aug 17 867
868 Build FM12 1d 04 Aug 17 04 Aug 17 868
869 Connections in Formation 2w 26 Jul 17 08 Aug 17 869
870 Services 10w 4d 07 Jun 18 21 Aug 18 870
871 District Heating and Cooling 6w 2d 07 Jun 18 20 Jul 18 871
872 Excavate for district heating and Cooling 1w 07 Jun 18 13 Jun 18 872
873 Install by Vital 5w 14 Jun 18 18 Jul 18 873
874 Backfill 2d 19 Jul 18 20 Jul 18 874
875 Water Main 2w 23 Jul 18 03 Aug 18 875
876 Excavate for Water Main 3d 23 Jul 18 25 Jul 18 876
877 Install by Thames Water 1w 26 Jul 18 01 Aug 18 877

878 Backfill 2d 02 Aug 18 03 Aug 18 878

879 Combined Service Trench 2w 2d 06 Aug 18 21 Aug 18 879

880 Excavate for Combined Service Trench 1w 06 Aug 18 10 Aug 18 880


881 Install Ducts 1w 13 Aug 18 17 Aug 18 881

882 Backfill 2d 20 Aug 18 21 Aug 18 882

883 Prater clear of Mews on 5A side 24 May 18 24 May 18 883

884 Prater clear of Mews on 5B side 07 Jun 18 07 Jun 18 884

885
885 Stage 1B services 57w 4d 12 Jul 17 07 Sep 18
886 Deep Services 4d 12 Jul 17 17 Jul 17 886
887 SM4 to SM 18 3d 12 Jul 17 14 Jul 17 887
888 Build SM18 1d 17 Jul 17 17 Jul 17 888
889 FM4 to FM17 3d 12 Jul 17 14 Jul 17 889
890 Build FM 17 1d 14 Jul 17 14 Jul 17 890

891 Shallow Services 15w 1d 23 May 18 07 Sep 18 891

892 Drainage & Services Between Manholes FM26 to FM17/FM4 (Stage 1B) 7w 23 May 18 11 Jul 18 892

893 Install Manholes SM 25, 26, 27, 28 3w 24 May 18 14 Jun 18 893


894 Surface Water Drainage between manholes 29 - 25 3w 30 May 18 19 Jun 18 894
895 Foul water Manhole 22 & 23 1w 1d 15 Jun 18 22 Jun 18 895
896 Foul water drainage from FM 26 - 23- 22 2w 20 Jun 18 03 Jul 18 896

897 Install Water Pipes in Trenches and all connections between main runs and buildings including heating and cooling pipework 6w 23 May 18 04 Jul 18 897

898 Excavate Trenches & Lay Ducts 5w 07 Jun 18 11 Jul 18 898

899 Trench Support Sytem Excavation 1w 3d 24 May 18 05 Jun 18 899

900 Excavate For District Heating Pipes 1w 06 Jun 18 12 Jun 18 900

901 Install District Heating Pipes 3w 13 Jun 18 03 Jul 18 901

902 Backfill District Heating Pipes 1w 04 Jul 18 10 Jul 18 902

903 Excavation & Temporary Propping For Drainage 2w 11 Jul 18 24 Jul 18 903

904 Excavation & Temporary Propping 2w 2d 25 Jul 18 09 Aug 18 904

905 Build Manhole FM22,FM23 & SM25, SM26, SM27, SM28 4w 27 Jul 18 23 Aug 18 905

906 Attenuation Tanks 3w 06 Aug 18 24 Aug 18 906

907 Lay Foul & Surface Water drainage Pipes FM 26 To FM 22 3w 1d 13 Aug 18 04 Sep 18 907

908 Backfill & Compact Over Pipes 3w 1d 16 Aug 18 07 Sep 18 908

909 Drainage & Services Between Manholes SM9/FM9 to SM7/FM7 (Stage 2) 62w 3d 28 Apr 17 31 Jul 18 909

910 Stage 2 Deep level infrastructure 6w 4d 28 Apr 17 16 Jun 17 910

911 Trench Support Sytem Excavation 2w 2d 04 May 17 19 May 17 911

912 Excavation & Temporary Propping 2w 08 May 17 19 May 17 912

913 Build Manhole FM9 & SM9 3w 28 Apr 17 19 May 17 913

914 Lay Foul & Surface Water drainage Pipes FM/SM 9 To FM/SM 8 1w 4d 16 May 17 16 Jun 17 914

915 Backfill & Compact Over Pipes 1w 2d 17 May 17 16 Jun 17 915

916 Build Manhole FM8 & SM8 2w 4d 11 May 17 16 Jun 17 916

917 Lay Foul & Surface Water drainage Pipes FM/SM 8 To FM/SM 7 1w 2d 17 May 17 16 Jun 17 917

918 Build Manhole FM7 & SM7 2w 2d 12 May 17 16 Jun 17 918

919 Backfill & Compact Over Pipes 1w 1d 17 May 17 16 Jun 17 919

920 High level services to 9A 2w 1d 04 Apr 18 18 Apr 18 920

921 Excavate for DH/DC connection to Building 9A 4d 04 Apr 18 09 Apr 18 921

922 Install District Heating Cooling connections to buildings 1w 10 Apr 18 16 Apr 18 922

923 Backfill DH/DC Connection 2d 17 Apr 18 18 Apr 18 923

924 Complete services runs to Building 9A 6w 18 Apr 18 31 Jul 18 924

925 North of 8A 10w 4d 15 May 18 30 Jul 18 925

926 District Heating and Cooling 4w 2d 15 May 18 14 Jun 18 926


927 Excavate for District Heating and Cooling 1w 15 May 18 21 May 18 927

928 Install by others 3w 22 May 18 12 Jun 18 928

929 Backfill 2d 13 Jun 18 14 Jun 18 929


930 Water Main 4w 2d 13 Jun 18 12 Jul 18 930

931 Excavate for Water main 1w 13 Jun 18 19 Jun 18 931


932 Install by Others 1w 20 Jun 18 26 Jun 18 932

933 Install Thames Water Main 1w 04 Jul 18 10 Jul 18 933

934 Backfill 2d 11 Jul 18 12 Jul 18 934


935 Combined Service Trench 2w 2d 13 Jul 18 30 Jul 18 935
936 Excavate for Combined Services 1w 13 Jul 18 19 Jul 18 936
937 Install ducts 1w 20 Jul 18 26 Jul 18 937
938 Backfill 2d 27 Jul 18 30 Jul 18 938

939 Drainage & Services Between Manholes SM7/FM7 to SM3/FM3 (Stage 3) 67w 3d 09 May 17 13 Sep 18 939

940 Stage 3 Deep level infrastructure 9w 3d 09 May 17 14 Jul 17 940

941 Trench Support Sytem Excavation 3w 4d 09 May 17 16 Jun 17 941

942 Excavation & Temporary Propping 3w 2d 10 May 17 16 Jun 17 942

943 Build Manhole FM6 & SM6 2w 3d 12 May 17 16 Jun 17 943

944 Lay Foul & Surface Water drainage Pipes FM 7 To FM 6 1w 3d 16 May 17 16 Jun 17 944

945 Backfill & Compact Over Pipes 1w 3d 16 May 17 16 Jun 17 945

946 Build Manhole FM5 & SM5 2w 3d 12 May 17 16 Jun 17 946

947 Lay Foul & Surface Water drainage Pipes FM 6 To FM5 2w 15 May 17 11 Jul 17 947

948 Build manhole SW7 2d 15 Jun 17 16 Jun 17 948


949 SW7 TO SW6 3d 14 Jun 17 16 Jun 17 949
950 Build manhole SW6 2d 15 Jun 17 16 Jun 17 950

951 SW6 TO SW5 3d 14 Jun 17 16 Jun 17 951


952 Build manhole SW5 2d 15 Jun 17 16 Jun 17 952
953 SW5 TO SW4 3d 14 Jun 17 16 Jun 17 953
954 Build manhole SW4 2d 10 Jul 17 11 Jul 17 954
955 SW4 to SW3 3d 12 Jul 17 14 Jul 17 955

956 DH / DC Main North of 5A GL 7 to 7+45m 3w 2d 05 Jun 18 27 Jun 18 956

957 Prater clear of North elevation of Building 5A 05 Jun 18 05 Jun 18 957

958 Excavate DH Main 1w 05 Jun 18 11 Jun 18 958

959 Excavate DC Main 1w 05 Jun 18 11 Jun 18 959

960 Install 450 dia Flow and return DH Main 1w 4d 12 Jun 18 22 Jun 18 960

961 Install 600 dia Flow and return DC Main 1w 2d 12 Jun 18 20 Jun 18 961

962 Connect to existing lower level DH main 2d 25 Jun 18 26 Jun 18 962

963 Connect to existing lower level DC main 3d 21 Jun 18 25 Jun 18 963

964 Backfill DH Main 1d 27 Jun 18 27 Jun 18 964

965 Backfill DC Main 1d 26 Jun 18 26 Jun 18 965

966 North of 5A 13w 2d 12 Jun 18 13 Sep 18 966


967 Services 9w 4d 12 Jun 18 17 Aug 18 967
968 District Heating and Cooling 3w 4d 12 Jun 18 06 Jul 18 968

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
969 Excavate for District Heating and Cooling 1w 12 Jun 18 18 Jun 18 969
970 Install DH/DC 1w 3d 25 Jun 18 04 Jul 18 970
971 Backfill 2d 05 Jul 18 06 Jul 18 971
972 Water Main 4w 05 Jul 18 01 Aug 18 972
973 Excavate for Sprinkler and Water main 1w 05 Jul 18 11 Jul 18 973
974 Install Spinkler Main 3d 12 Jul 18 16 Jul 18 974
975 Install Thames Water Pipes in Trench 1w 24 Jul 18 30 Jul 18 975
976 Backfill 2d 31 Jul 18 01 Aug 18 976
977 Combined Service Trench 2w 2d 02 Aug 18 17 Aug 18 977

978 Excavate for Combined Services 1w 02 Aug 18 08 Aug 18 978


979 Install ducts 1w 09 Aug 18 15 Aug 18 979
980 Backfill 2d 16 Aug 18 17 Aug 18 980

981 Pull HV/LV Cables Through Ducts 2w 16 Aug 18 30 Aug 18 981

982 Prep for Kerbs 3w 3d 20 Aug 18 13 Sep 18 982


983 Install 5 Tree Pits 3d 20 Aug 18 22 Aug 18 983
984 Installl two bus stop bases 2w 23 Aug 18 06 Sep 18 984
985 install two bollards 1d 22 Aug 18 22 Aug 18 985
986 Import to Formation 1w 07 Sep 18 13 Sep 18 986

987 Drainage & Services Between Manholes SM3/FM3 to SM1/FM1 (Stage 4) 12w 3d 14 Jun 17 11 Sep 17 987

988 Stage 4 deep level infrastructure 9w 14 Jun 17 15 Aug 17 988

989 Build manhole FM3 2d 14 Jun 17 15 Jun 17 989


990 FM3 to FM2 3d 17 Jul 17 19 Jul 17 990
991 Build manhole FM2 2d 20 Jul 17 21 Jul 17 991

992 FM2 to FM1 3d 24 Jul 17 26 Jul 17 992

993 Build manhole FM1 2d 27 Jul 17 28 Jul 17 993


994 Build manhole SW3 2d 31 Jul 17 01 Aug 17 994

995 SW3 to SW2 3d 02 Aug 17 04 Aug 17 995


996 Build manhole SW2 2d 07 Aug 17 08 Aug 17 996

997 SW2 to SW1 3d 09 Aug 17 11 Aug 17 997

998 Build manhole SW1 2d 14 Aug 17 15 Aug 17 998

999 Excavate For District Heating Pipes 1w 17 Jul 17 21 Jul 17 999

1000 Install District Heating Pipes 2w 24 Jul 17 04 Aug 17 1000

1001 Backfill District Heating Pipes 1w 07 Aug 17 11 Aug 17 1001

1002 Stage 4 high level services 4w 14 Aug 17 11 Sep 17 1002

1003 Excavate & Construct Service Ducts 3w 14 Aug 17 04 Sep 17 1003

1004 Install Sprinkler Main in Trench 1w 14 Aug 17 18 Aug 17 1004

1005 Install Thames Water Main in Trench 1w 21 Aug 17 25 Aug 17 1005

1006 Excavate Trenches & Lay Ducts 3w 21 Aug 17 11 Sep 17 1006

1007 Drainage & Services Between Manholes FM29 to FM27 (Stage 5) 24w 3d 22 May 17 10 Nov 17 1007

1008 Stage 5 deep level services 11w 4d 22 May 17 11 Aug 17 1008

1009 Trench Support Sytem Excavation 2w 3d 09 Jun 17 27 Jun 17 1009

1010 Excavation & Temporary Propping 2w 14 Jun 17 27 Jun 17 1010

1011 Build Manhole FM29, 28 & 27 & SM34, 35, 36 2w 1d 21 Jun 17 05 Jul 17 1011

1012 Lay Foul & Surface Water drainage Pipes FM 10 To FM 27 and attenuation tanks 3w 22 May 17 12 Jun 17 1012

1013 Backfill & Compact Over Pipes 1w 3d 09 Jun 17 20 Jun 17 1013

1014 Build Manhole FM1 & SM1 2w 1d 17 Jul 17 31 Jul 17 1014

1015 Lay Foul & Surface Water drainage Pipes FM 2 To FM1 2w 17 Jul 17 28 Jul 17 1015

1016 Backfill & Compact Over Pipes 1w 4d 20 Jul 17 01 Aug 17 1016

1017 Trench Support Sytem Excavation 1w 05 Jul 17 11 Jul 17 1017

1018 Excavate For District Heating Pipes 1w 10 Jul 17 14 Jul 17 1018

1019 Install District Heating Pipes 3w 17 Jul 17 04 Aug 17 1019

1020 Backfill District Heating Pipes 1w 07 Aug 17 11 Aug 17 1020

1021 Stage 5 high level services 9w 11 Sep 17 10 Nov 17 1021

1022 Install Water Pipes in Trenches and all connections between main runs and buildings including heating and cooling pipework 1w 25 Sep 17 29 Sep 17 1022

1023 Install Thames Water main 2w 02 Oct 17 10 Nov 17 1023

1024 Excavate Trenches & Lay Ducts 4w 11 Sep 17 06 Oct 17 1024

1025 Drainage & Services Between Manholes FM17 to FM12 (Stage 1C) 53w 2d 05 Jul 17 31 Jul 18 1025

1026 Stage 1C Deep level services 21w 3d 05 Jul 17 04 Dec 17 1026

1027 SM4 to SM 18 3d 05 Jul 17 07 Jul 17 1027


1028 Build SM18 1d 10 Jul 17 10 Jul 17 1028
1029 FM4 to FM17 3d 11 Jul 17 13 Jul 17 1029
1030 Build FM 17 1d 14 Jul 17 14 Jul 17 1030
1031 Reduced Level Dig 1w 31 Jul 17 04 Aug 17 1031
1032 Excavate for District Heating Coling 1w 02 Oct 17 18 Oct 17 1032
1033 Install by Others 3w 1d 09 Oct 17 06 Nov 17 1033
1034 Backfill 1w 27 Oct 17 09 Nov 17 1034

1035 Excavate for Water Main 1w 16 Oct 17 20 Oct 17 1035


1036 Install by Others 1w 16 Oct 17 20 Oct 17 1036
1037 Backfill 1w 16 Oct 17 20 Oct 17 1037
1038 Excavate for Combined Service Trench 1w 16 Oct 17 20 Oct 17 1038
1039 Install Ducts 1w 16 Oct 17 20 Oct 17 1039
1040 Backfill 1w 16 Oct 17 20 Oct 17 1040

1041 Fill to underside of Tarmac 2w 10 Nov 17 23 Nov 17 1041


1042 Manhole Covers 1w 24 Nov 17 30 Nov 17 1042
1043 Tarmac 2d 01 Dec 17 04 Dec 17 1043

1044 Stage 1C High level services 10w 22 May 18 31 Jul 18 1044

1045 Pull HV/LV Cables Through Ducts & Terminate 10w 22 May 18 31 Jul 18 1045

1046 Drainage Connections to existing Thames Water Sewers 57w 3d 03 Aug 17 28 Sep 18 1046

1047 Thames Water construct manhole on existing sewer, and new manholes FM30 and SM13 10w 29 Jun 18 07 Sep 18 1047

1048 Thames Water lay drains and backfill 3w 10 Sep 18 28 Sep 18 1048

1049 Complete drainage between FM30 & FM11, SM12 and SM11 4w 03 Aug 17 12 Sep 17 1049

1050 Main Utility Services Onto Site 78w 4d 07 Mar 17 03 Oct 18 1050

1051 Water Main From Royal Albert Way To Site Ring Main 14w 30 Jun 17 06 Oct 17 1051

1052 Hydrant Main From Royal Albert Way To Site Ring Main 12w 14 Jul 17 06 Oct 17 1052

1053 Gas Main From Royal Albert Way To Site Ring Main 10w 28 Jul 17 06 Oct 17 1053

1054 LV Switchgear and distribution 7w 4d 18 Jul 18 11 Sep 18 1054

1055 HV Electrical Supply Cable From Albert Way To Temporary Site Sub Station 12w 07 Mar 17 02 Jun 17 1055

1056 VDV - Fibre Network 8w 08 Aug 18 03 Oct 18 1056


1057
1057 Buildings 9A, 8A, 8B & Temp Energy Centre Works 126w 3d 18 Jul 16 13 Feb 19
1058 Thorp Contract duration for panel installation 21w 06 Dec 17 16 May 18 1058
1059 Extra time due to Mitchellson 'holiday' 3w 1d 17 May 18 08 Jun 18 1059

1060 Building 9A 81w 3d 25 Apr 17 07 Dec 18 1060

1061 Mobilise Piling Rigs 3w 25 Apr 17 16 May 17 1061

1062 Piling 16w 2d 18 May 17 12 Sep 17 1062

1063 Lay Pile Mat 1w 18 May 17 24 May 17 1063

1064 Lay Crane Mat 2w 1d 12 Jun 17 12 Sep 17 1064

1065 Set up rig 2 2d 18 May 17 19 May 17 1065

1066 Piling 2w 2d 22 Jun 17 07 Jul 17 1066

1067 SHEET PILE BASEMENT AREA 2w 10 Jul 17 21 Jul 17 1067

1068 Structure 33w 1d 24 Jul 17 22 Mar 18 1068

1069 Substructure 15w 24 Jul 17 06 Nov 17 1069


1070 Basement Structure 13w 4d 24 Jul 17 27 Oct 17 1070
1071 Excavate 2w 4d 24 Jul 17 10 Aug 17 1071
1072 Break Down Piles 1w 2d 11 Aug 17 21 Aug 17 1072
1073 FRC Pile Caps 1w 2d 17 Aug 17 25 Aug 17 1073
1074 FIll Grade and Compact to Basement Slab formation 1w 4d 23 Aug 17 05 Sep 17 1074
1075 FRC Basement Slab 4d 01 Sep 17 06 Sep 17 1075
1076 Dismantle Strutting 3d 07 Sep 17 11 Sep 17 1076
1077 FRC Wall Basement to Groundfloor(including corbel) 2w 1d 12 Sep 17 26 Sep 17 1077
1078 Groundfloor slab over basement 2w 3d 25 Sep 17 27 Oct 17 1078

1079 Core Pile Cap 3w 1d 11 Aug 17 04 Sep 17 1079


1080 Excavate 1w 1d 11 Aug 17 18 Aug 17 1080

1081 Break Down Piles 1w 4d 14 Aug 17 24 Aug 17 1081


1082 FRC Base of Pile Cap 2w 3d 16 Aug 17 04 Sep 17 1082

1083 General Pile Cap 5w 4d 21 Aug 17 29 Sep 17 1083


1084 Excavate Pile Caps 3w 4d 21 Aug 17 15 Sep 17 1084
1085 Break Down Piles 4w 3d 23 Aug 17 25 Sep 17 1085
1086 FRC Pile Caps 5w 1d 24 Aug 17 29 Sep 17 1086

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1087 Ground Floor 9w 05 Sep 17 06 Nov 17 1087
1088 Pour 1 1w 05 Sep 17 11 Sep 17 1088
1089 Pour 2 2w 1d 07 Sep 17 21 Sep 17 1089
1090 Pour 3 1w 3d 25 Sep 17 04 Oct 17 1090
1091 Pour 4 1w 1d 02 Oct 17 18 Oct 17 1091
1092 Pour 5 2w 17 Oct 17 06 Nov 17 1092
Install ducts to take incoming electricity cables, DH/DC flow and return pipework and Sprinkler main to Building 9A and surround in
1093 2w 22 Sep 17 27 Oct 17 1093
concrete if necessary
1094 Superstructure 27w 1d 05 Sep 17 22 Mar 18 1094
1095 FRC 500mm high core wall from 4.500m and set platform to take slipform 1w 4d 05 Sep 17 15 Sep 17 1095
1096 SET UP SLIP FORM TO CORE WALLS 3w 18 Sep 17 06 Oct 17 1096
1097 SLIP 1ST LIFT 2d 09 Oct 17 10 Oct 17 1097
1098 INSTALL FOLLOW UP PLATFORMS 4d 16 Oct 17 19 Oct 17 1098
1099 SLIP CORE TO ROOF 4w 2d 20 Oct 17 20 Nov 17 1099
1100 DISMANTLE SLIP 1w 21 Nov 17 27 Nov 17 1100

1101 Precast Stairflights & Landings 2w 28 Nov 17 11 Dec 17 1101

1102 FRC COLUMNS GROUND - 1ST FLOOR 1w 2d 12 Oct 17 09 Nov 17 1102


1103 FRC 1ST FLOOR SLAB 4w 1d 16 Oct 17 20 Nov 17 1103
1104 FRC COLUMNS 1ST - 2ND FLOOR 3w 2d 23 Oct 17 22 Nov 17 1104
1105 FRC 2ND FLOOR SLAB 3w 26 Oct 17 24 Nov 17 1105
1106 FRC COLUMNS 2ND - 3RD FLOOR 2w 3d 13 Nov 17 29 Nov 17 1106
1107 FRC 3RD FLOOR SLAB 3w 20 Nov 17 08 Dec 17 1107
1108 FRC COLUMNS 3RD - 4TH FLOOR 2w 3d 27 Nov 17 13 Dec 17 1108
1109 FRC 4TH FLOOR SLAB 3w 04 Dec 17 22 Dec 17 1109
1110 FRC COLUMNS 4TH - 5TH FLOOR 2w 3d 11 Dec 17 05 Jan 18 1110
1111 FRC 5TH FLOOR SLAB 3w 18 Dec 17 16 Jan 18 1111
1112 FRC COLUMNS 5TH - 6TH FLOOR 2w 2d 04 Jan 18 19 Jan 18 1112
1113 FRC 6TH FLOOR SLAB 3w 11 Jan 18 31 Jan 18 1113
1114 FRC COLUMNS 6TH - 7TH FLOOR 2w 3d 19 Jan 18 06 Feb 18 1114
1115 FRC 7TH FLOOR SLAB 3w 26 Jan 18 15 Feb 18 1115
1116 FRC COLUMNS 7TH - 8TH FLOOR 2w 3d 05 Feb 18 21 Feb 18 1116
1117 FRC 8TH FLOOR SLAB 3w 12 Feb 18 02 Mar 18 1117
1118 FRC COLUMNS 8TH - ROOF 2w 3d 20 Feb 18 08 Mar 18 1118
1119 FRC ROOF SLAB 3w 27 Feb 18 19 Mar 18 1119

1120 Construct Plant Bases & Plinths 2w 09 Mar 18 22 Mar 18 1120

1121 FRC CAPPING SLAB TO CORES 1w 2d 14 Mar 18 22 Mar 18 1121


1122 Staircase Basement to GF - Cast insitu 2w 27 Nov 17 08 Dec 17 1122
1123 Precast Stairs & Handrails 18w 28 Nov 17 13 Apr 18 1123

1124 Facade 26w 4d 23 Mar 18 04 Oct 18 1124

1125 Precast Concrete Panels - West elevation 1w 1d 23 Mar 18 03 Apr 18 1125

1126 Precast Concrete Panels - South elevation 1w 2d 04 Apr 18 12 Apr 18 1126

1127 Precast Concrete Panels - East elevation 1w 1d 13 Apr 18 20 Apr 18 1127

1128 Precast Concrete Panels - North elevation 1w 2d 23 Apr 18 02 May 18 1128

1129 Shopfronts, windows External Doors & Louvres at Ground and First floors 7w 4d 10 Apr 18 06 Jun 18 1129

1130 Shopfronts, windows External Doors & Louvres at Ground and First floors - West 4w 10 Apr 18 09 May 18 1130

1131 Shopfronts, windows External Doors & Louvres at Ground and First floors - South 4w 18 Apr 18 17 May 18 1131

1132 Shopfronts, windows External Doors & Louvres at Ground and First floors - East 4w 30 Apr 18 29 May 18 1132
1133 Shopfronts, windows External Doors & Louvres at Ground and First floors - North 4w 09 May 18 06 Jun 18 1133

1134 Parapet Cladding to Level 9 6w 17 Apr 18 31 May 18 1134

1135 Infill where hoists removed 1w 07 Sep 18 13 Sep 18 1135

1136 Install windows 1w 14 Sep 18 20 Sep 18 1136

1137 Aluminium panelling at hoist locations 2w 21 Sep 18 04 Oct 18 1137

1138 Roofing 12w 23 Mar 18 21 Jun 18 1138

1139 Erect posts for Roof Louvres 2w 23 Mar 18 09 Apr 18 1139

1140 Roof Slab Waterproofing 6w 10 Apr 18 23 May 18 1140

1141 Roof Finishes 6w 24 Apr 18 07 Jun 18 1141

1142 Install Roof Louvres and Mansafe Latchways 5w 02 May 18 07 Jun 18 1142

1143 Stair core Cladding and Render 5w 24 Apr 18 31 May 18 1143

1144 Building Temporary Waterproof 24 Apr 18 24 Apr 18 1144

1145 Building Watertight 24 May 18 24 May 18 1145

1146 Roof Balustrade 2w 23 Mar 18 09 Apr 18 1146


1147 Access Hatch and ladders 2w 08 Jun 18 21 Jun 18 1147

1148 Latest Date for ABP/WTP to omit Cat A Shell and Core Services scope of works to Building 9A 08 Aug 17 08 Aug 17 1148

1149 M & E Installation 29w 4d 21 Dec 17 02 Aug 18 1149

1150 Prefabricated Riser Installation 1w 4d 17 Jan 18 30 Apr 18 1150

1151 Lift floor modules onto floors 1 - 4 1w 15 Feb 18 21 Feb 18 1151

1152 Lift floor modules onto floors 5 - 9 1w 14 Mar 18 20 Mar 18 1152

1153 Installation of Siphonic drainage 2w 13 Mar 18 27 Mar 18 1153

1154 Ground Floor Plant Installation 9A 7w 21 Mar 18 14 May 18 1154

1155 Basement Plant Room Installation 9A 10w 21 Dec 17 09 Mar 18 1155

1156 Roof Plant Installation 9A 10w 24 May 18 02 Aug 18 1156

1157 Hoists and Cantidecks 25w 3d 05 Mar 18 06 Sep 18 1157

1158 Window for Cantidecks t load out upper floors - levels 5 - Roof (Level 9) 2w 1d 05 Mar 18 19 Mar 18 1158
1159 Construct hoist base 1 (North) 4d 19 Apr 18 24 Apr 18 1159

1160 Construct hoist base 2 (South) 4d 10 May 18 15 May 18 1160

1161 Hoist 1 16w 25 Apr 18 17 Aug 18 1161

1162 Hoist 2 16w 16 May 18 06 Sep 18 1162

1163 Lift /Toilet Core Fit Out 56w 2d 23 Oct 17 07 Dec 18 1163

1164 Lift Installation 56w 2d 23 Oct 17 07 Dec 18 1164

1165 Delivery of temporary lift doors 23 Oct 17 23 Oct 17 1165

1166 Lift 1 12w 24 Apr 18 19 Jul 18 1166

1167 Lift Guides and Doors 10w 24 Apr 18 05 Jul 18 1167

1168 Lift car 1w 06 Jul 18 12 Jul 18 1168

1169 Commission lift 1w 13 Jul 18 19 Jul 18 1169

1170 Lift 2 12w 01 May 18 25 Jul 18 1170

1171 Lift Guides and Doors 10w 01 May 18 11 Jul 18 1171

1172 Lift car 1w 12 Jul 18 18 Jul 18 1172

1173 Commission lift 1w 19 Jul 18 25 Jul 18 1173

1174 Lift 3 12w 09 May 18 01 Aug 18 1174

1175 Lift Guides and Doors 10w 09 May 18 18 Jul 18 1175

1176 Lift car 1w 19 Jul 18 25 Jul 18 1176

1177 Commission lift 1w 26 Jul 18 01 Aug 18 1177

1178 Lift 4 12w 16 May 18 08 Aug 18 1178

1179 Lift Guides and Doors 10w 16 May 18 25 Jul 18 1179

1180 Lift car 1w 26 Jul 18 01 Aug 18 1180

1181 Commission lift 1w 02 Aug 18 08 Aug 18 1181

1182 Hand Back lifts to Schindler 26 Nov 18 26 Nov 18 1182


1183 Recommission lifts and complete finishes 2w 26 Nov 18 07 Dec 18 1183

1184 Toilet Fit out 19w 2d 24 Apr 18 11 Sep 18 1184

1185 Toilet Fit-out Ground floor 12w 2d 24 Apr 18 23 Jul 18 1185

1186 Perimeter drylining walls 3d 24 Apr 18 26 Apr 18 1186


1187 Screed 3d 30 Apr 18 02 May 18 1187
1188 High level domestic pipework 3d 03 May 18 08 May 18 1188
1189 Low level mechanical pipework 3d 09 May 18 11 May 18 1189
1190 High level LV electrical containment 3d 14 May 18 16 May 18 1190
1191 Wire and terminate to Distribution Boards 3d 17 May 18 21 May 18 1191
1192 Lighting, Fire Alarms, BMS, Control Wiring 3d 22 May 18 24 May 18 1192
1193 High level mechanical 1st Fix 3d 25 May 18 30 May 18 1193
1194 Wall Partition incl. Noggins and Vanity Frames 3d 31 May 18 04 Jun 18 1194
1195 Inspection to Proceed Ceiling closure 31 May 18 31 May 18 1195
1196 Plasterboard Ceiling 3d 05 Jun 18 07 Jun 18 1196
1197 Floor tiling 3d 08 Jun 18 12 Jun 18 1197
1198 Joinery and doors 3d 13 Jun 18 15 Jun 18 1198
1199 Sanitaryware and Vanity units 1w 3d 18 Jun 18 27 Jun 18 1199

1200 Mist and one coat 3d 28 Jun 18 02 Jul 18 1200


1201 2nd Fix Mechanical to ceilings 4d 03 Jul 18 06 Jul 18 1201
1202 2nd fix light fittings and electrical to ceilings 3d 09 Jul 18 11 Jul 18 1202
1203 Partition system walls - Cubicles 1w 12 Jul 18 18 Jul 18 1203
1204 Final decorations 3d 19 Jul 18 23 Jul 18 1204

1205 1st Floor Toilet Fit-out 12w 2d 24 Apr 18 23 Jul 18 1205

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1206 Perimeter drylining walls 3d 24 Apr 18 26 Apr 18 1206
1207 Screed 3d 30 Apr 18 02 May 18 1207
1208 High level domestic pipework 3d 03 May 18 08 May 18 1208
1209 Low level mechanical pipework 3d 09 May 18 11 May 18 1209
1210 High level LV electrical containment 3d 14 May 18 16 May 18 1210
1211 Wire and terminate to Distribution Boards 3d 17 May 18 21 May 18 1211
1212 Lighting, Fire Alarms, BMS, Control Wiring 3d 22 May 18 24 May 18 1212
1213 High level mechanical 1st Fix 3d 25 May 18 30 May 18 1213
1214 Wall Partition incl. Noggins and Vanity Frames 3d 31 May 18 04 Jun 18 1214

1215 Inspection to Proceed Ceiling closure 31 May 18 31 May 18 1215

1216 Plasterboard Ceiling 3d 05 Jun 18 07 Jun 18 1216


1217 Floor tiling 3d 08 Jun 18 12 Jun 18 1217

1218 Joinery and doors 3d 13 Jun 18 15 Jun 18 1218

1219 Sanitaryware and Vanity units 1w 3d 18 Jun 18 27 Jun 18 1219

1220 Mist and one coat 3d 28 Jun 18 02 Jul 18 1220

1221 2nd Fix Mechanical to ceilings 4d 03 Jul 18 06 Jul 18 1221

1222 2nd fix light fittings and electrical to ceilings 3d 09 Jul 18 11 Jul 18 1222

1223 Partition system walls - Cubicles 1w 12 Jul 18 18 Jul 18 1223


1224 Final decorations 3d 19 Jul 18 23 Jul 18 1224

1225 2nd Floor Toilet Fit-out 12w 2d 02 May 18 30 Jul 18 1225

1226 Perimeter drylining walls 3d 02 May 18 04 May 18 1226


1227 Screed 3d 08 May 18 10 May 18 1227

1228 High level domestic pipework 3d 11 May 18 15 May 18 1228

1229 Low level mechanical pipework 3d 16 May 18 18 May 18 1229

1230 High level LV electrical containment 3d 21 May 18 23 May 18 1230


1231 Wire and terminate to Distribution Boards 3d 24 May 18 29 May 18 1231

1232 Lighting, Fire Alarms, BMS, Control Wiring 3d 30 May 18 01 Jun 18 1232

1233 High level mechanical 1st Fix 3d 04 Jun 18 06 Jun 18 1233

1234 Drylining walls 3d 07 Jun 18 11 Jun 18 1234

1235 Inspection to Proceed Ceiling closure 07 Jun 18 07 Jun 18 1235

1236 Plasterboard Ceiling 3d 12 Jun 18 14 Jun 18 1236


1237 Floor tiling 3d 15 Jun 18 19 Jun 18 1237

1238 Joinery and doors 3d 20 Jun 18 22 Jun 18 1238

1239 Sanitaryware and Vanity units 1w 3d 25 Jun 18 04 Jul 18 1239


1240 Mist and one coat 3d 05 Jul 18 09 Jul 18 1240
1241 2nd Fix Mechanical to ceilings 4d 10 Jul 18 13 Jul 18 1241
1242 2nd fix light fittings and electrical to ceilings 3d 16 Jul 18 18 Jul 18 1242
1243 Partition system walls - Cubicles 1w 19 Jul 18 25 Jul 18 1243
1244 Final decorations 3d 26 Jul 18 30 Jul 18 1244

1245 3rd Floor Toilet Fit-out 12w 2d 10 May 18 06 Aug 18 1245

1246 Perimeter drylining walls 3d 10 May 18 14 May 18 1246


1247 Screed 3d 15 May 18 17 May 18 1247
1248 High level domestic pipework 3d 18 May 18 22 May 18 1248
1249 Low level mechanical pipework 3d 23 May 18 25 May 18 1249
1250 High level LV electrical containment 3d 29 May 18 31 May 18 1250
1251 Wire and terminate to Distribution Boards 3d 01 Jun 18 05 Jun 18 1251
1252 Lighting, Fire Alarms, BMS, Control Wiring 3d 06 Jun 18 08 Jun 18 1252
1253 High level mechanical 1st Fix 3d 11 Jun 18 13 Jun 18 1253
1254 Drylining walls 3d 14 Jun 18 18 Jun 18 1254
1255 Inspection to Proceed Ceiling closure 14 Jun 18 14 Jun 18 1255
1256 Plasterboard Ceiling 3d 19 Jun 18 21 Jun 18 1256
1257 Floor tiling 3d 22 Jun 18 26 Jun 18 1257
1258 Joinery and doors 3d 27 Jun 18 29 Jun 18 1258
1259 Sanitaryware and Vanity units 1w 3d 02 Jul 18 11 Jul 18 1259
1260 Mist and one coat 3d 12 Jul 18 16 Jul 18 1260
1261 2nd Fix Mechanical to ceilings 4d 17 Jul 18 20 Jul 18 1261
1262 2nd fix light fittings and electrical to ceilings 3d 23 Jul 18 25 Jul 18 1262
1263 Partition system walls - Cubicles 1w 26 Jul 18 01 Aug 18 1263
1264 Final decorations 3d 02 Aug 18 06 Aug 18 1264

1265 4th Floor Toilet Fit-out 12w 2d 17 May 18 13 Aug 18 1265

1266 Perimeter drylining walls 3d 17 May 18 21 May 18 1266


1267 Screed 3d 22 May 18 24 May 18 1267
1268 High level domestic pipework 3d 25 May 18 30 May 18 1268
1269 Low level mechanical pipework 3d 31 May 18 04 Jun 18 1269
1270 High level LV electrical containment 3d 05 Jun 18 07 Jun 18 1270
1271 Wire and terminate to Distribution Boards 3d 08 Jun 18 12 Jun 18 1271
1272 Lighting, Fire Alarms, BMS, Control Wiring 3d 13 Jun 18 15 Jun 18 1272
1273 High level mechanical 1st Fix 3d 18 Jun 18 20 Jun 18 1273
1274 Drylining walls 3d 21 Jun 18 25 Jun 18 1274
1275 Inspection to Proceed Ceiling closure 21 Jun 18 21 Jun 18 1275

1276 Plasterboard Ceiling 3d 26 Jun 18 28 Jun 18 1276


1277 Floor tiling 3d 29 Jun 18 03 Jul 18 1277

1278 Joinery and doors 3d 04 Jul 18 06 Jul 18 1278


1279 Sanitaryware and Vanity units 1w 3d 09 Jul 18 18 Jul 18 1279
1280 Mist and one coat 3d 19 Jul 18 23 Jul 18 1280

1281 2nd Fix Mechanical to ceilings 4d 24 Jul 18 27 Jul 18 1281

1282 2nd fix light fittings and electrical to ceilings 3d 30 Jul 18 01 Aug 18 1282

1283 Partition system walls - Cubicles 1w 02 Aug 18 08 Aug 18 1283

1284 Final decorations 3d 09 Aug 18 13 Aug 18 1284

1285 5th Floor Toilet Fit-out 12w 2d 24 May 18 20 Aug 18 1285

1286 Perimeter drylining walls 3d 24 May 18 29 May 18 1286


1287 Screed 3d 30 May 18 01 Jun 18 1287

1288 High level domestic pipework 3d 04 Jun 18 06 Jun 18 1288

1289 Low level mechanical pipework 3d 07 Jun 18 11 Jun 18 1289

1290 High level LV electrical containment 3d 12 Jun 18 14 Jun 18 1290

1291 Wire and terminate to Distribution Boards 3d 15 Jun 18 19 Jun 18 1291


1292 Lighting, Fire Alarms, BMS, Control Wiring 3d 20 Jun 18 22 Jun 18 1292

1293 High level mechanical 1st Fix 3d 25 Jun 18 27 Jun 18 1293

1294 Drylining walls 3d 28 Jun 18 02 Jul 18 1294

1295 Inspection to Proceed Ceiling closure 28 Jun 18 28 Jun 18 1295

1296 Plasterboard Ceiling 3d 03 Jul 18 05 Jul 18 1296


1297 Floor tiling 3d 06 Jul 18 10 Jul 18 1297

1298 Joinery and doors 3d 11 Jul 18 13 Jul 18 1298

1299 Sanitaryware and Vanity units 1w 3d 16 Jul 18 25 Jul 18 1299


1300 Mist and one coat 3d 26 Jul 18 30 Jul 18 1300
1301 2nd Fix Mechanical to ceilings 4d 31 Jul 18 03 Aug 18 1301
1302 2nd fix light fittings and electrical to ceilings 3d 06 Aug 18 08 Aug 18 1302
1303 Partition system walls - Cubicles 1w 09 Aug 18 15 Aug 18 1303
1304 Final decorations 3d 16 Aug 18 20 Aug 18 1304

1305 6th Floor Toilet Fit-out 12w 2d 01 Jun 18 28 Aug 18 1305

1306 Perimeter drylining walls 3d 01 Jun 18 05 Jun 18 1306


1307 Screed 3d 06 Jun 18 08 Jun 18 1307

1308 High level domestic pipework 3d 11 Jun 18 13 Jun 18 1308


1309 Low level mechanical pipework 3d 14 Jun 18 18 Jun 18 1309

1310 High level LV electrical containment 3d 19 Jun 18 21 Jun 18 1310

1311 Wire and terminate to Distribution Boards 3d 22 Jun 18 26 Jun 18 1311


1312 Lighting, Fire Alarms, BMS, Control Wiring 3d 27 Jun 18 29 Jun 18 1312
1313 High level mechanical 1st Fix 3d 02 Jul 18 04 Jul 18 1313
1314 Drylining walls 3d 05 Jul 18 09 Jul 18 1314
1315 Inspection to Proceed Ceiling closure 05 Jul 18 05 Jul 18 1315
1316 Plasterboard Ceiling 3d 10 Jul 18 12 Jul 18 1316
1317 Floor tiling 3d 13 Jul 18 17 Jul 18 1317
1318 Joinery and doors 3d 18 Jul 18 20 Jul 18 1318
1319 Sanitaryware and Vanity units 1w 3d 23 Jul 18 01 Aug 18 1319
1320 Mist and one coat 3d 02 Aug 18 06 Aug 18 1320
1321 2nd Fix Mechanical to ceilings 4d 07 Aug 18 10 Aug 18 1321
1322 2nd fix light fittings and electrical to ceilings 3d 13 Aug 18 15 Aug 18 1322
1323 Partition system walls - Cubicles 1w 16 Aug 18 22 Aug 18 1323

1324 Final decorations 3d 23 Aug 18 28 Aug 18 1324

1325 7th Floor Toilet Fit-out 12w 2d 08 Jun 18 04 Sep 18 1325

1326 Perimeter drylining walls 3d 08 Jun 18 12 Jun 18 1326


1327 Screed 3d 13 Jun 18 15 Jun 18 1327
1328 High level domestic pipework 3d 18 Jun 18 20 Jun 18 1328
1329 Low level mechanical pipework 3d 21 Jun 18 25 Jun 18 1329
1330 High level LV electrical containment 3d 26 Jun 18 28 Jun 18 1330
1331 Wire and terminate to Distribution Boards 3d 29 Jun 18 03 Jul 18 1331
1332 Lighting, Fire Alarms, BMS, Control Wiring 3d 04 Jul 18 06 Jul 18 1332
1333 High level mechanical 1st Fix 3d 09 Jul 18 11 Jul 18 1333
1334 Drylining walls 3d 12 Jul 18 16 Jul 18 1334
1335 Inspection to Proceed Ceiling closure 12 Jul 18 12 Jul 18 1335

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1336 Plasterboard Ceiling 3d 17 Jul 18 19 Jul 18 1336
1337 Floor tiling 3d 20 Jul 18 24 Jul 18 1337
1338 Joinery and doors 3d 25 Jul 18 27 Jul 18 1338
1339 Sanitaryware and Vanity units 1w 3d 30 Jul 18 08 Aug 18 1339
1340 Mist and one coat 3d 09 Aug 18 13 Aug 18 1340
1341 2nd Fix Mechanical to ceilings 4d 14 Aug 18 17 Aug 18 1341
1342 2nd fix light fittings and electrical to ceilings 3d 20 Aug 18 22 Aug 18 1342
1343 Partition system walls - Cubicles 1w 23 Aug 18 30 Aug 18 1343
1344 Final decorations 3d 31 Aug 18 04 Sep 18 1344

1345 8th Floor Toilet Fit-out 12w 2d 15 Jun 18 11 Sep 18 1345

1346 Perimeter drylining walls 3d 15 Jun 18 19 Jun 18 1346


1347 Screed 3d 20 Jun 18 22 Jun 18 1347
1348 High level domestic pipework 3d 25 Jun 18 27 Jun 18 1348
1349 Low level mechanical pipework 3d 28 Jun 18 02 Jul 18 1349
1350 High level LV electrical containment 3d 03 Jul 18 05 Jul 18 1350
1351 Wire and terminate to Distribution Boards 3d 06 Jul 18 10 Jul 18 1351
1352 Lighting, Fire Alarms, BMS, Control Wiring 3d 11 Jul 18 13 Jul 18 1352
1353 High level mechanical 1st Fix 3d 16 Jul 18 18 Jul 18 1353
1354 Drylining walls 3d 19 Jul 18 23 Jul 18 1354
1355 Inspection to Proceed Ceiling closure 19 Jul 18 19 Jul 18 1355
1356 Plasterboard Ceiling 3d 24 Jul 18 26 Jul 18 1356
1357 Floor tiling 3d 27 Jul 18 31 Jul 18 1357
1358 Joinery and doors 3d 01 Aug 18 03 Aug 18 1358
1359 Sanitaryware and Vanity units 1w 3d 06 Aug 18 15 Aug 18 1359
1360 Mist and one coat 3d 16 Aug 18 20 Aug 18 1360
1361 2nd Fix Mechanical to ceilings 4d 21 Aug 18 24 Aug 18 1361
1362 2nd fix light fittings and electrical to ceilings 3d 28 Aug 18 30 Aug 18 1362
1363 Partition system walls - Cubicles 1w 31 Aug 18 06 Sep 18 1363
1364 Final decorations 3d 07 Sep 18 11 Sep 18 1364

1365 Circulation & Lobby Fitout 11w 16 Aug 18 01 Nov 18 1365

1366 Gnd Floor Lift Lobby Fit Out 6w 1d 16 Aug 18 28 Sep 18 1366

1367 Dry Lining works 1w 16 Aug 18 22 Aug 18 1367


1368 High level mechanical 1st Fix incl. Duct works 2d 23 Aug 18 24 Aug 18 1368
1369 High level domestic pipework 2d 28 Aug 18 29 Aug 18 1369
1370 High level LV electrical containment 2d 30 Aug 18 31 Aug 18 1370
1371 Lighting, Fire Alarms, BMS, Control Wiring 2d 03 Sep 18 04 Sep 18 1371
1372 Wire and terminate to Distribution Boards 2d 05 Sep 18 06 Sep 18 1372
1373 Ceiling works 3d 07 Sep 18 11 Sep 18 1373
1374 Tape and joint walls 3d 12 Sep 18 14 Sep 18 1374
1375 Mist and one coat 3d 17 Sep 18 19 Sep 18 1375
1376 Joinery and doors 2d 20 Sep 18 21 Sep 18 1376
1377 Final Coat on ceiling 2d 24 Sep 18 25 Sep 18 1377
1378 Fix Final MEP fixtures 3d 26 Sep 18 28 Sep 18 1378

1379 1st Floor Lift Lobby Fit Out 6w 1d 21 Aug 18 03 Oct 18 1379

1380 Perimeter drylining walls 1w 21 Aug 18 28 Aug 18 1380

1381 High level mechanical 1st Fix incl. Duct works 2d 29 Aug 18 30 Aug 18 1381

1382 High level domestic pipework 2d 31 Aug 18 03 Sep 18 1382

1383 High level LV electrical containment 2d 04 Sep 18 05 Sep 18 1383

1384 Lighting, Fire Alarms, BMS, Control Wiring 2d 06 Sep 18 07 Sep 18 1384

1385 Wire and terminate to Distribution Boards 2d 10 Sep 18 11 Sep 18 1385

1386 Partition system walls and ceilings 3d 12 Sep 18 14 Sep 18 1386

1387 Tape and joint walls 3d 17 Sep 18 19 Sep 18 1387

1388 Joinery and doors 2d 20 Sep 18 21 Sep 18 1388

1389 Mist and one coat 3d 24 Sep 18 26 Sep 18 1389

1390 Final Coat on ceiling 2d 27 Sep 18 28 Sep 18 1390

1391 Final Ceiling Final MEP fixtures 3d 01 Oct 18 03 Oct 18 1391

1392 2nd Floor Lift Lobby Fit Out 6w 1d 24 Aug 18 08 Oct 18 1392

1393 Perimeter drylining walls 1w 24 Aug 18 31 Aug 18 1393

1394 High level mechanical 1st Fix incl. Duct works 2d 03 Sep 18 04 Sep 18 1394

1395 High level domestic pipework 2d 05 Sep 18 06 Sep 18 1395

1396 High level LV electrical containment 2d 07 Sep 18 10 Sep 18 1396

1397 Lighting, Fire Alarms, BMS, Control Wiring 2d 11 Sep 18 12 Sep 18 1397

1398 Wire and terminate to Distribution Boards 2d 13 Sep 18 14 Sep 18 1398

1399 Partition system walls and ceilings 3d 17 Sep 18 19 Sep 18 1399

1400 Tape and joint walls 3d 20 Sep 18 24 Sep 18 1400

1401 Joinery and doors 2d 25 Sep 18 26 Sep 18 1401

1402 Mist and one coat 3d 27 Sep 18 01 Oct 18 1402

1403 Final Coat on ceiling 2d 02 Oct 18 03 Oct 18 1403

1404 Final Ceiling Final MEP fixtures 3d 04 Oct 18 08 Oct 18 1404

1405 3rd Floor Lift Lobby Fit Out 6w 1d 30 Aug 18 11 Oct 18 1405

1406 Perimeter drylining walls 2d 30 Aug 18 31 Aug 18 1406

1407 High level mechanical 1st Fix incl. Duct works 2d 03 Sep 18 04 Sep 18 1407

1408 High level domestic pipework 2d 05 Sep 18 06 Sep 18 1408

1409 High level LV electrical containment 2d 07 Sep 18 10 Sep 18 1409

1410 Lighting, Fire Alarms, BMS, Control Wiring 2d 11 Sep 18 12 Sep 18 1410

1411 Wire and terminate to Distribution Boards 2d 13 Sep 18 14 Sep 18 1411

1412 Partition system walls and ceilings 3d 17 Sep 18 19 Sep 18 1412

1413 Tape and joint walls 3d 20 Sep 18 24 Sep 18 1413

1414 Raised access flooring 3d 25 Sep 18 27 Sep 18 1414

1415 Joinery and doors 2d 28 Sep 18 01 Oct 18 1415

1416 Mist and one coat 3d 02 Oct 18 04 Oct 18 1416

1417 Final Coat on ceiling 2d 05 Oct 18 08 Oct 18 1417

1418 Final Ceiling Final MEP fixtures 3d 09 Oct 18 11 Oct 18 1418

1419 4th Floor Lift Lobby Fit Out 6w 1d 04 Sep 18 16 Oct 18 1419

1420 Perimeter drylining walls 2d 04 Sep 18 05 Sep 18 1420

1421 High level mechanical 1st Fix incl. Duct works 2d 06 Sep 18 07 Sep 18 1421

1422 High level domestic pipework 2d 10 Sep 18 11 Sep 18 1422

1423 High level LV electrical containment 2d 12 Sep 18 13 Sep 18 1423

1424 Lighting, Fire Alarms, BMS, Control Wiring 2d 14 Sep 18 17 Sep 18 1424

1425 Wire and terminate to Distribution Boards 2d 18 Sep 18 19 Sep 18 1425

1426 Partition system walls and ceilings 3d 20 Sep 18 24 Sep 18 1426

1427 Tape and joint walls 3d 25 Sep 18 27 Sep 18 1427

1428 Raised access flooring 3d 28 Sep 18 02 Oct 18 1428

1429 Joinery and doors 2d 03 Oct 18 04 Oct 18 1429

1430 Mist and one coat 3d 05 Oct 18 09 Oct 18 1430

1431 Final Coat on ceiling 2d 10 Oct 18 11 Oct 18 1431

1432 Final Ceiling Final MEP fixtures 3d 12 Oct 18 16 Oct 18 1432

1433 5th Floor Lift Lobby Fit Out 6w 1d 07 Sep 18 19 Oct 18 1433

1434 Perimeter drylining walls 2d 07 Sep 18 10 Sep 18 1434

1435 High level mechanical 1st Fix incl. Duct works 2d 11 Sep 18 12 Sep 18 1435

1436 High level domestic pipework 2d 13 Sep 18 14 Sep 18 1436

1437 High level LV electrical containment 2d 17 Sep 18 18 Sep 18 1437

1438 Lighting, Fire Alarms, BMS, Control Wiring 2d 19 Sep 18 20 Sep 18 1438

1439 Wire and terminate to Distribution Boards 2d 21 Sep 18 24 Sep 18 1439

1440 Partition system walls and ceilings 3d 25 Sep 18 27 Sep 18 1440

1441 Tape and joint walls 3d 28 Sep 18 02 Oct 18 1441

1442 Raised access flooring 3d 03 Oct 18 05 Oct 18 1442

1443 Joinery and doors 2d 08 Oct 18 09 Oct 18 1443

1444 Mist and one coat 3d 10 Oct 18 12 Oct 18 1444

1445 Final Coat on ceiling 2d 15 Oct 18 16 Oct 18 1445

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1446 Final Ceiling Final MEP fixtures 3d 17 Oct 18 19 Oct 18 1446

1447 6th Floor Lift Lobby Fit Out 6w 1d 12 Sep 18 24 Oct 18 1447

1448 Perimeter drylining walls 2d 12 Sep 18 13 Sep 18 1448

1449 High level mechanical 1st Fix incl. Duct works 2d 14 Sep 18 17 Sep 18 1449

1450 High level domestic pipework 2d 18 Sep 18 19 Sep 18 1450

1451 High level LV electrical containment 2d 20 Sep 18 21 Sep 18 1451

1452 Lighting, Fire Alarms, BMS, Control Wiring 2d 24 Sep 18 25 Sep 18 1452

1453 Wire and terminate to Distribution Boards 2d 26 Sep 18 27 Sep 18 1453

1454 Partition system walls and ceilings 3d 28 Sep 18 02 Oct 18 1454

1455 Tape and joint walls 3d 03 Oct 18 05 Oct 18 1455

1456 Raised access flooring 3d 08 Oct 18 10 Oct 18 1456

1457 Joinery and doors 2d 11 Oct 18 12 Oct 18 1457

1458 Mist and one coat 3d 15 Oct 18 17 Oct 18 1458

1459 Final Coat on ceiling 2d 18 Oct 18 19 Oct 18 1459

1460 Final Ceiling Final MEP fixtures 3d 22 Oct 18 24 Oct 18 1460

1461 7th Floor Lift Lobby Fit Out 6w 1d 17 Sep 18 29 Oct 18 1461

1462 Perimeter drylining walls 2d 17 Sep 18 18 Sep 18 1462

1463 High level mechanical 1st Fix incl. Duct works 2d 19 Sep 18 20 Sep 18 1463

1464 High level domestic pipework 2d 21 Sep 18 24 Sep 18 1464

1465 High level LV electrical containment 2d 25 Sep 18 26 Sep 18 1465

1466 Lighting, Fire Alarms, BMS, Control Wiring 2d 27 Sep 18 28 Sep 18 1466

1467 Wire and terminate to Distribution Boards 2d 01 Oct 18 02 Oct 18 1467

1468 Partition system walls and ceilings 3d 03 Oct 18 05 Oct 18 1468

1469 Tape and joint walls 3d 08 Oct 18 10 Oct 18 1469

1470 Raised access flooring 3d 11 Oct 18 15 Oct 18 1470

1471 Joinery and doors 2d 16 Oct 18 17 Oct 18 1471

1472 Mist and one coat 3d 18 Oct 18 22 Oct 18 1472

1473 Final Coat on ceiling 2d 23 Oct 18 24 Oct 18 1473

1474 Final Ceiling Final MEP fixtures 3d 25 Oct 18 29 Oct 18 1474

1475 8th Floor Lift Lobby Fit Out 6w 1d 20 Sep 18 01 Nov 18 1475

1476 Perimeter drylining walls 2d 20 Sep 18 21 Sep 18 1476

1477 High level mechanical 1st Fix incl. Duct works 2d 24 Sep 18 25 Sep 18 1477

1478 High level domestic pipework 2d 26 Sep 18 27 Sep 18 1478

1479 High level LV electrical containment 2d 28 Sep 18 01 Oct 18 1479

1480 Lighting, Fire Alarms, BMS, Control Wiring 2d 02 Oct 18 03 Oct 18 1480

1481 Wire and terminate to Distribution Boards 2d 04 Oct 18 05 Oct 18 1481

1482 Partition system walls and ceilings 3d 08 Oct 18 10 Oct 18 1482

1483 Tape and joint walls 3d 11 Oct 18 15 Oct 18 1483

1484 Raised access flooring 3d 16 Oct 18 18 Oct 18 1484

1485 Joinery and doors 2d 19 Oct 18 22 Oct 18 1485

1486 Mist and one coat 3d 23 Oct 18 25 Oct 18 1486

1487 Final Coat on ceiling 2d 26 Oct 18 29 Oct 18 1487

1488 Final Ceiling Final MEP fixtures 3d 30 Oct 18 01 Nov 18 1488

1489 Staircase Fit Out 13w 23 Aug 18 22 Nov 18 1489

1490 L01 - Staircase 01 3w 3d 23 Aug 18 18 Sep 18 1490

1491 High level LV electrical containment 2d 23 Aug 18 24 Aug 18 1491

1492 Lighting, Fire Alarms, BMS, Control Wiring 2d 28 Aug 18 29 Aug 18 1492

1493 Wire and terminate to Distribution Boards 2d 30 Aug 18 31 Aug 18 1493

1494 Partition system walls and ceilings 2d 03 Sep 18 04 Sep 18 1494

1495 Tape and joint walls 2d 05 Sep 18 06 Sep 18 1495

1496 Joinery and doors 2d 07 Sep 18 10 Sep 18 1496

1497 Mist and one coat 2d 11 Sep 18 12 Sep 18 1497

1498 Final Coat on ceiling 2d 13 Sep 18 14 Sep 18 1498

1499 Final Ceiling Final MEP fixtures 2d 17 Sep 18 18 Sep 18 1499

1500 L02 - Staircase 01 3w 3d 24 Aug 18 20 Sep 18 1500

1501 High level LV electrical containment 2d 24 Aug 18 29 Aug 18 1501

1502 Lighting, Fire Alarms, BMS, Control Wiring 2d 29 Aug 18 31 Aug 18 1502

1503 Wire and terminate to Distribution Boards 2d 31 Aug 18 04 Sep 18 1503

1504 Partition system walls and ceilings 2d 04 Sep 18 06 Sep 18 1504

1505 Tape and joint walls 2d 06 Sep 18 10 Sep 18 1505

1506 Joinery and doors 2d 10 Sep 18 12 Sep 18 1506

1507 Mist and one coat 2d 12 Sep 18 14 Sep 18 1507

1508 Final Coat on ceiling 2d 14 Sep 18 18 Sep 18 1508

1509 Final Ceiling Final MEP fixtures 2d 18 Sep 18 20 Sep 18 1509

1510 L03 - Staircase 01 3w 3d 29 Aug 18 24 Sep 18 1510

1511 High level LV electrical containment 2d 29 Aug 18 31 Aug 18 1511

1512 Lighting, Fire Alarms, BMS, Control Wiring 2d 31 Aug 18 04 Sep 18 1512

1513 Wire and terminate to Distribution Boards 2d 04 Sep 18 06 Sep 18 1513

1514 Partition system walls and ceilings 2d 06 Sep 18 10 Sep 18 1514

1515 Tape and joint walls 2d 10 Sep 18 12 Sep 18 1515

1516 Joinery and doors 2d 12 Sep 18 14 Sep 18 1516

1517 Mist and one coat 2d 14 Sep 18 18 Sep 18 1517

1518 Final Coat on ceiling 2d 18 Sep 18 20 Sep 18 1518

1519 Final Ceiling Final MEP fixtures 2d 20 Sep 18 24 Sep 18 1519

1520 L04 - Staircase 01 3w 3d 31 Aug 18 26 Sep 18 1520

1521 High level LV electrical containment 2d 31 Aug 18 04 Sep 18 1521

1522 Lighting, Fire Alarms, BMS, Control Wiring 2d 04 Sep 18 06 Sep 18 1522

1523 Wire and terminate to Distribution Boards 2d 06 Sep 18 10 Sep 18 1523

1524 Partition system walls and ceilings 2d 10 Sep 18 12 Sep 18 1524

1525 Tape and joint walls 2d 12 Sep 18 14 Sep 18 1525

1526 Joinery and doors 2d 14 Sep 18 18 Sep 18 1526

1527 Mist and one coat 2d 18 Sep 18 20 Sep 18 1527

1528 Final Coat on ceiling 2d 20 Sep 18 24 Sep 18 1528

1529 Final Ceiling Final MEP fixtures 2d 24 Sep 18 26 Sep 18 1529

1530 L05 - Staircase 01 3w 3d 04 Sep 18 28 Sep 18 1530

1531 High level LV electrical containment 2d 04 Sep 18 06 Sep 18 1531

1532 Lighting, Fire Alarms, BMS, Control Wiring 2d 06 Sep 18 10 Sep 18 1532

1533 Wire and terminate to Distribution Boards 2d 10 Sep 18 12 Sep 18 1533

1534 Partition system walls and ceilings 2d 12 Sep 18 14 Sep 18 1534

1535 Tape and joint walls 2d 14 Sep 18 18 Sep 18 1535

1536 Joinery and doors 2d 18 Sep 18 20 Sep 18 1536

1537 Mist and one coat 2d 20 Sep 18 24 Sep 18 1537

1538 Final Coat on ceiling 2d 24 Sep 18 26 Sep 18 1538

1539 Final Ceiling Final MEP fixtures 2d 26 Sep 18 28 Sep 18 1539

1540 L06 - Staircase 01 3w 3d 06 Sep 18 02 Oct 18 1540

1541 High level LV electrical containment 2d 06 Sep 18 10 Sep 18 1541

1542 Lighting, Fire Alarms, BMS, Control Wiring 2d 10 Sep 18 12 Sep 18 1542

1543 Wire and terminate to Distribution Boards 2d 12 Sep 18 14 Sep 18 1543

1544 Partition system walls and ceilings 2d 14 Sep 18 18 Sep 18 1544

1545 Tape and joint walls 2d 18 Sep 18 20 Sep 18 1545

1546 Joinery and doors 2d 20 Sep 18 24 Sep 18 1546

1547 Mist and one coat 2d 24 Sep 18 26 Sep 18 1547

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1548 Final Coat on ceiling 2d 26 Sep 18 28 Sep 18 1548

1549 Final Ceiling Final MEP fixtures 2d 28 Sep 18 02 Oct 18 1549

1550 L07 - Staircase 01 3w 3d 10 Sep 18 04 Oct 18 1550

1551 High level LV electrical containment 2d 10 Sep 18 12 Sep 18 1551

1552 Lighting, Fire Alarms, BMS, Control Wiring 2d 12 Sep 18 14 Sep 18 1552

1553 Wire and terminate to Distribution Boards 2d 14 Sep 18 18 Sep 18 1553

1554 Partition system walls and ceilings 2d 18 Sep 18 20 Sep 18 1554

1555 Tape and joint walls 2d 20 Sep 18 24 Sep 18 1555

1556 Joinery and doors 2d 24 Sep 18 26 Sep 18 1556

1557 Mist and one coat 2d 26 Sep 18 28 Sep 18 1557

1558 Final Coat on ceiling 2d 28 Sep 18 02 Oct 18 1558

1559 Final Ceiling Final MEP fixtures 2d 02 Oct 18 04 Oct 18 1559

1560 L08 to Roof - Staircase 01 3w 3d 12 Sep 18 08 Oct 18 1560

1561 High level LV electrical containment 2d 12 Sep 18 14 Sep 18 1561

1562 Lighting, Fire Alarms, BMS, Control Wiring 2d 14 Sep 18 18 Sep 18 1562

1563 Wire and terminate to Distribution Boards 2d 18 Sep 18 20 Sep 18 1563

1564 Partition system walls and ceilings 2d 20 Sep 18 24 Sep 18 1564

1565 Tape and joint walls 2d 24 Sep 18 26 Sep 18 1565

1566 Joinery and doors 2d 26 Sep 18 28 Sep 18 1566

1567 Mist and one coat 2d 28 Sep 18 02 Oct 18 1567

1568 Final Coat on ceiling 2d 02 Oct 18 04 Oct 18 1568

1569 Final Ceiling Final MEP fixtures 2d 04 Oct 18 08 Oct 18 1569

1570 L01 - Staircase 02 3w 3d 19 Sep 18 12 Oct 18 1570

1571 High level LV electrical containment 2d 19 Sep 18 20 Sep 18 1571

1572 Lighting, Fire Alarms, BMS, Control Wiring 2d 21 Sep 18 24 Sep 18 1572

1573 Wire and terminate to Distribution Boards 2d 25 Sep 18 26 Sep 18 1573

1574 Partition system walls and ceilings 2d 27 Sep 18 28 Sep 18 1574

1575 Tape and joint walls 2d 01 Oct 18 02 Oct 18 1575

1576 Joinery and doors 2d 03 Oct 18 04 Oct 18 1576

1577 Mist and one coat 2d 05 Oct 18 08 Oct 18 1577

1578 Final Coat on ceiling 2d 09 Oct 18 10 Oct 18 1578

1579 Final Ceiling Final MEP fixtures 2d 11 Oct 18 12 Oct 18 1579

1580 L02 - Staircase 02 3w 3d 21 Sep 18 16 Oct 18 1580

1581 High level LV electrical containment 2d 21 Sep 18 24 Sep 18 1581

1582 Lighting, Fire Alarms, BMS, Control Wiring 2d 25 Sep 18 26 Sep 18 1582

1583 Wire and terminate to Distribution Boards 2d 27 Sep 18 28 Sep 18 1583

1584 Partition system walls and ceilings 2d 01 Oct 18 02 Oct 18 1584

1585 Tape and joint walls 2d 03 Oct 18 04 Oct 18 1585

1586 Joinery and doors 2d 05 Oct 18 08 Oct 18 1586

1587 Mist and one coat 2d 09 Oct 18 10 Oct 18 1587

1588 Final Coat on ceiling 2d 11 Oct 18 12 Oct 18 1588

1589 Final Ceiling Final MEP fixtures 2d 15 Oct 18 16 Oct 18 1589

1590 L03 - Staircase 02 3w 3d 25 Sep 18 18 Oct 18 1590

1591 High level LV electrical containment 2d 25 Sep 18 26 Sep 18 1591

1592 Lighting, Fire Alarms, BMS, Control Wiring 2d 27 Sep 18 28 Sep 18 1592

1593 Wire and terminate to Distribution Boards 2d 01 Oct 18 02 Oct 18 1593

1594 Partition system walls and ceilings 2d 03 Oct 18 04 Oct 18 1594

1595 Tape and joint walls 2d 05 Oct 18 08 Oct 18 1595

1596 Joinery and doors 2d 09 Oct 18 10 Oct 18 1596

1597 Mist and one coat 2d 11 Oct 18 12 Oct 18 1597

1598 Final Coat on ceiling 2d 15 Oct 18 16 Oct 18 1598

1599 Final Ceiling Final MEP fixtures 2d 17 Oct 18 18 Oct 18 1599

1600 L04 - Staircase 02 3w 3d 27 Sep 18 22 Oct 18 1600

1601 High level LV electrical containment 2d 27 Sep 18 28 Sep 18 1601

1602 Lighting, Fire Alarms, BMS, Control Wiring 2d 01 Oct 18 02 Oct 18 1602

1603 Wire and terminate to Distribution Boards 2d 03 Oct 18 04 Oct 18 1603

1604 Partition system walls and ceilings 2d 05 Oct 18 08 Oct 18 1604

1605 Tape and joint walls 2d 09 Oct 18 10 Oct 18 1605

1606 Joinery and doors 2d 11 Oct 18 12 Oct 18 1606

1607 Mist and one coat 2d 15 Oct 18 16 Oct 18 1607

1608 Final Coat on ceiling 2d 17 Oct 18 18 Oct 18 1608

1609 Final Ceiling Final MEP fixtures 2d 19 Oct 18 22 Oct 18 1609

1610 L05 - Staircase 02 3w 3d 01 Oct 18 24 Oct 18 1610

1611 High level LV electrical containment 2d 01 Oct 18 02 Oct 18 1611

1612 Lighting, Fire Alarms, BMS, Control Wiring 2d 03 Oct 18 04 Oct 18 1612

1613 Wire and terminate to Distribution Boards 2d 05 Oct 18 08 Oct 18 1613

1614 Partition system walls and ceilings 2d 09 Oct 18 10 Oct 18 1614

1615 Tape and joint walls 2d 11 Oct 18 12 Oct 18 1615

1616 Joinery and doors 2d 15 Oct 18 16 Oct 18 1616

1617 Mist and one coat 2d 17 Oct 18 18 Oct 18 1617

1618 Final Coat on ceiling 2d 19 Oct 18 22 Oct 18 1618

1619 Final Ceiling Final MEP fixtures 2d 23 Oct 18 24 Oct 18 1619

1620 L06 - Staircase 02 3w 3d 03 Oct 18 26 Oct 18 1620

1621 High level LV electrical containment 2d 03 Oct 18 04 Oct 18 1621

1622 Lighting, Fire Alarms, BMS, Control Wiring 2d 05 Oct 18 08 Oct 18 1622

1623 Wire and terminate to Distribution Boards 2d 09 Oct 18 10 Oct 18 1623

1624 Partition system walls and ceilings 2d 11 Oct 18 12 Oct 18 1624

1625 Tape and joint walls 2d 15 Oct 18 16 Oct 18 1625

1626 Joinery and doors 2d 17 Oct 18 18 Oct 18 1626

1627 Mist and one coat 2d 19 Oct 18 22 Oct 18 1627

1628 Final Coat on ceiling 2d 23 Oct 18 24 Oct 18 1628

1629 Final Ceiling Final MEP fixtures 2d 25 Oct 18 26 Oct 18 1629

1630 L07 - Staircase 02 3w 3d 05 Oct 18 30 Oct 18 1630

1631 High level LV electrical containment 2d 05 Oct 18 08 Oct 18 1631

1632 Lighting, Fire Alarms, BMS, Control Wiring 2d 09 Oct 18 10 Oct 18 1632

1633 Wire and terminate to Distribution Boards 2d 11 Oct 18 12 Oct 18 1633

1634 Partition system walls and ceilings 2d 15 Oct 18 16 Oct 18 1634

1635 Tape and joint walls 2d 17 Oct 18 18 Oct 18 1635

1636 Joinery and doors 2d 19 Oct 18 22 Oct 18 1636

1637 Mist and one coat 2d 23 Oct 18 24 Oct 18 1637

1638 Final Coat on ceiling 2d 25 Oct 18 26 Oct 18 1638

1639 Final Ceiling Final MEP fixtures 2d 29 Oct 18 30 Oct 18 1639

1640 L08 to Roof - Staircase 02 3w 3d 09 Oct 18 01 Nov 18 1640

1641 High level LV electrical containment 2d 09 Oct 18 10 Oct 18 1641

1642 Lighting, Fire Alarms, BMS, Control Wiring 2d 11 Oct 18 12 Oct 18 1642

1643 Wire and terminate to Distribution Boards 2d 15 Oct 18 16 Oct 18 1643

1644 Partition system walls and ceilings 2d 17 Oct 18 18 Oct 18 1644

1645 Tape and joint walls 2d 19 Oct 18 22 Oct 18 1645

1646 Joinery and doors 2d 23 Oct 18 24 Oct 18 1646

1647 Mist and one coat 2d 25 Oct 18 26 Oct 18 1647

1648 Final Coat on ceiling 2d 29 Oct 18 30 Oct 18 1648

1649 Final Ceiling Final MEP fixtures 2d 31 Oct 18 01 Nov 18 1649

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1650 Staircase Flooring incl. Nosing 4w 26 Oct 18 22 Nov 18 1650

1651 Fit riser boxes 2d 23 Aug 18 24 Aug 18 1651

1652 Reception Fit-out 16w 24 Jul 18 13 Nov 18 1652

1653 Groundfloor refuse room cladding 2w 22 Jun 18 05 Jul 18 1653

1654 Latest Date for ABP/WTP to omit Cat A Shell and Core Fit-out scope of works to Building 9A 13 Dec 17 13 Dec 17 1654

1655 Cat A Fit Out 48w 2d 04 Dec 17 23 Nov 18 1655

1656 Blockwork Walls at Ground 5w 04 Dec 17 17 May 18 1656

1657 Install Sprinkler Pipes to Ground Floor 1w 08 May 18 14 May 18 1657

1658 Fit out Ground Floor 6w 2d 18 May 18 03 Jul 18 1658

1659
1659 Install conduit to cleaners sockets to core walls 1w 18 May 18 24 May 18
1660 Boarding and Insulation to external and core walls 2w 18 May 18 01 Jun 18 1660

1661
1661 Taping and Joining to Walls 1w 30 May 18 05 Jun 18
1662 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 30 May 18 12 Jun 18 1662

1663
1663 Install Joinery incl Doors 2w 13 Jun 18 26 Jun 18
1664 Decoration 2w 20 Jun 18 03 Jul 18 1664

1665 Fit out First Floor 19w 4d 15 Feb 18 10 Jul 18 1665

1666 Install conduit to cleaners sockets to core walls 1w 25 May 18 01 Jun 18 1666

1667
1667 Boarding and Insulation to external and core walls 2w 25 May 18 08 Jun 18
1668 Taping and Joining to Walls 1w 06 Jun 18 12 Jun 18 1668

1669 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 06 Jun 18 19 Jun 18 1669

1670 Install Joinery incl Doors 2w 20 Jun 18 03 Jul 18 1670

1671 Decoration 2w 27 Jun 18 10 Jul 18 1671

1672 Install Sprinkler Pipes to 1st Floor 1w 25 Apr 18 02 May 18 1672

1673 High Level Services First Floor 8w 15 Feb 18 13 Apr 18 1673

1674 Fit out Second Floor 19w 3d 22 Feb 18 16 Jul 18 1674

1675 Install conduit to cleaners sockets to core walls 1w 04 Jun 18 08 Jun 18 1675

1676
1676 Boarding and Insulation to external and core walls 2w 04 Jun 18 15 Jun 18
1677 Taping and Joining to Walls 1w 13 Jun 18 19 Jun 18 1677

1678
1678 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 13 Jun 18 26 Jun 18
1679 Install Joinery incl Doors 2w 27 Jun 18 10 Jul 18 1679

1680
1680 Decoration 2w 03 Jul 18 16 Jul 18
1681 Install Sprinkler Pipes to 2nd Floor 1w 03 May 18 10 May 18 1681

1682
1682 High Level Services Second Floor 8w 22 Feb 18 20 Apr 18
1683 Fit out Third Floor 19w 4d 01 Mar 18 24 Jul 18 1683

1684
1684 Install conduit to cleaners sockets to core walls 1w 11 Jun 18 15 Jun 18
1685 Boarding and Insulation to external and core walls 2w 11 Jun 18 22 Jun 18 1685

1686
1686 Taping and Joining to Walls 1w 20 Jun 18 26 Jun 18
1687 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 20 Jun 18 03 Jul 18 1687

1688
1688 Install Joinery incl Doors 2w 04 Jul 18 17 Jul 18
1689 Decoration 2w 11 Jul 18 24 Jul 18 1689

1690 Install Sprinkler Pipes to 3rd Floor 1w 11 May 18 17 May 18 1690

1691 High Level Services Third Floor 8w 01 Mar 18 30 Apr 18 1691

1692 Fit out Fourth Floor 19w 4d 08 Mar 18 31 Jul 18 1692

1693 Install conduit to cleaners sockets to core walls 1w 18 Jun 18 22 Jun 18 1693

1694
1694 Boarding and Insulation to external and core walls 2w 18 Jun 18 29 Jun 18
1695 Taping and Joining to Walls 1w 27 Jun 18 03 Jul 18 1695

1696
1696 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 27 Jun 18 10 Jul 18
1697 Install Joinery incl Doors 2w 11 Jul 18 24 Jul 18 1697

1698
1698 Decoration 2w 18 Jul 18 31 Jul 18
1699 Install Sprinkler Pipes to 4th Floor 1w 18 May 18 24 May 18 1699

1700
1700 High Level Services Fourth Floor 8w 08 Mar 18 08 May 18
1701 Fit out Fifth Floor 19w 4d 15 Mar 18 07 Aug 18 1701

1702
1702 Install conduit to cleaners sockets to core walls 1w 25 Jun 18 29 Jun 18
1703 Boarding and Insulation to external and core walls 2w 25 Jun 18 06 Jul 18 1703

1704
1704 Taping and Joining to Walls 1w 04 Jul 18 10 Jul 18
1705 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 04 Jul 18 17 Jul 18 1705

1706 Install Joinery incl Doors 2w 18 Jul 18 31 Jul 18 1706

1707
1707 Decoration 2w 25 Jul 18 07 Aug 18
1708 Install Sprinkler Pipes to 5th Floor 1w 25 May 18 01 Jun 18 1708

1709
1709 High Level Services Fifth Floor 8w 15 Mar 18 15 May 18
1710 Fit out Sixth Floor 19w 4d 22 Mar 18 14 Aug 18 1710

1711
1711 Install conduit to cleaners sockets to core walls 1w 02 Jul 18 06 Jul 18
1712 Boarding and Insulation to external and core walls 2w 02 Jul 18 13 Jul 18 1712

1713
1713 Taping and Joining to Walls 1w 11 Jul 18 17 Jul 18
1714 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 11 Jul 18 24 Jul 18 1714

1715
1715 Install Joinery incl Doors 2w 25 Jul 18 07 Aug 18
1716 Decoration 2w 01 Aug 18 14 Aug 18 1716

1717 Install Sprinkler Pipes to 6th Floor 1w 04 Jun 18 08 Jun 18 1717

1718 High Level Services Sixth Floor 8w 22 Mar 18 22 May 18 1718

1719 Fit out Seventh Floor 19w 4d 29 Mar 18 21 Aug 18 1719

1720 Install conduit to cleaners sockets to core walls 1w 09 Jul 18 13 Jul 18 1720

1721
1721 Boarding and Insulation to external and core walls 2w 09 Jul 18 20 Jul 18
1722 Taping and Joining to Walls 1w 18 Jul 18 24 Jul 18 1722

1723
1723 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 18 Jul 18 31 Jul 18
1724 Install Joinery incl Doors 2w 01 Aug 18 14 Aug 18 1724

1725
1725 Decoration 2w 08 Aug 18 21 Aug 18
1726 Install Sprinkler Pipes to 7th Floor 1w 11 Jun 18 15 Jun 18 1726

1727
1727 High Level Services Seventh Floor 8w 29 Mar 18 30 May 18
1728 Fit out Eighth Floor 18w 2d 25 Apr 18 05 Sep 18 1728

1729
1729 Install conduit to cleaners sockets to core walls 1w 23 Jul 18 27 Jul 18
1730 Boarding and Insulation to external and core walls 2w 23 Jul 18 03 Aug 18 1730

1731
1731 Taping and Joining to Walls 1w 01 Aug 18 07 Aug 18
1732 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 01 Aug 18 14 Aug 18 1732

1733
1733 Install Joinery incl Doors 2w 15 Aug 18 29 Aug 18
1734 Decoration 2w 22 Aug 18 05 Sep 18 1734

1735 Install Sprinkler Pipes to 8th Floor 1w 18 Jun 18 22 Jun 18 1735

1736 High Level Services Eighth Floor 8w 25 Apr 18 22 Jun 18 1736

1737 Hoist Temporary Access Closure 3w 1d 07 Sep 18 28 Sep 18 1737

1738 Fit out First Floor 2d 27 Sep 18 28 Sep 18 1738

1739 Partition closure 2d 27 Sep 18 28 Sep 18 1739

1740 Fit out Second Floor 2d 25 Sep 18 26 Sep 18 1740

1741 Partition closure 2d 25 Sep 18 26 Sep 18 1741

1742 Fit out Third Floor 2d 21 Sep 18 24 Sep 18 1742

1743 Partition closure 2d 21 Sep 18 24 Sep 18 1743

1744 Fit out Fourth Floor 2d 19 Sep 18 20 Sep 18 1744

1745 Partition closure 2d 19 Sep 18 20 Sep 18 1745

1746 Fit out Fifth Floor 2d 17 Sep 18 18 Sep 18 1746

1747 Partition closure 2d 17 Sep 18 18 Sep 18 1747

1748 Fit out Sixth Floor 2d 13 Sep 18 14 Sep 18 1748

1749 Partition closure 2d 13 Sep 18 14 Sep 18 1749

1750 Fit out Seventh Floor 2d 11 Sep 18 12 Sep 18 1750

1751 Partition closure 2d 11 Sep 18 12 Sep 18 1751

1752 Fit out Eighth Floor 2d 07 Sep 18 10 Sep 18 1752

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1753 Partition closure 2d 07 Sep 18 10 Sep 18 1753

1754 Prepare Floors for Handover 8w 01 Oct 18 23 Nov 18 1754

1755 Prepare Ground Floor for Handover 4w 01 Oct 18 26 Oct 18 1755

1756
1756 Complete Ceiling Tiles 1w 01 Oct 18 05 Oct 18
1757 Install Raised Access Floor incl Below Floor Barriers 2w 08 Oct 18 19 Oct 18 1757

1758
1758 Soft Floor Coverings 1w 22 Oct 18 26 Oct 18
1759 Prepare 1st Floor for Handover 4w 03 Oct 18 30 Oct 18 1759

1760
1760 Complete Ceiling Tiles 1w 03 Oct 18 09 Oct 18
1761 Install Raised Access Floor incl Below Floor Barriers 2w 10 Oct 18 23 Oct 18 1761

1762
1762 Soft Floor Coverings 1w 24 Oct 18 30 Oct 18
1763 Prepare 2nd Floor for Handover 4w 08 Oct 18 02 Nov 18 1763

1764
1764 Complete Ceiling Tiles 1w 08 Oct 18 12 Oct 18
1765 Install Raised Access Floor incl Below Floor Barriers 2w 15 Oct 18 26 Oct 18 1765

1766
1766 Soft Floor Coverings 1w 29 Oct 18 02 Nov 18
1767 Prepare 3rd Floor for Handover 4w 11 Oct 18 07 Nov 18 1767

1768
1768 Complete Ceiling Tiles 1w 11 Oct 18 17 Oct 18
1769 Install Raised Access Floor incl Below Floor Barriers 2w 18 Oct 18 31 Oct 18 1769

1770
1770 Soft Floor Coverings 1w 01 Nov 18 07 Nov 18
1771 Prepare 4th Floor for Handover 4w 16 Oct 18 12 Nov 18 1771

1772
1772 Complete Ceiling Tiles 1w 16 Oct 18 22 Oct 18
1773 Install Raised Access Floor incl Below Floor Barriers 2w 23 Oct 18 05 Nov 18 1773

1774
1774 Soft Floor Coverings 1w 06 Nov 18 12 Nov 18
1775 Prepare 5th Floor for handover 4w 19 Oct 18 15 Nov 18 1775

1776 Complete Ceiling Tiles 1w 19 Oct 18 25 Oct 18 1776

1777
1777 Install Raised Access Floor incl Below Floor Barriers 2w 26 Oct 18 08 Nov 18
1778 Soft Floor Coverings 1w 09 Nov 18 15 Nov 18 1778

1779 Prepare 6th Floor for Handover 4w 24 Oct 18 20 Nov 18 1779

1780 Complete Ceiling Tiles 1w 24 Oct 18 30 Oct 18 1780

1781
1781 Install Raised Access Floor incl Below Floor Barriers 2w 31 Oct 18 13 Nov 18
1782 Soft Floor Coverings 1w 14 Nov 18 20 Nov 18 1782

1783 Prepare 7th floor for Handover 4w 29 Oct 18 23 Nov 18 1783

1784 Complete Ceiling Tiles 1w 29 Oct 18 02 Nov 18 1784

1785
1785 Install Raised Access Floor incl Below Floor Barriers 2w 05 Nov 18 16 Nov 18
1786 Soft Floor Coverings 1w 19 Nov 18 23 Nov 18 1786

1787 Prepare 8th floor for handover 4w 29 Oct 18 23 Nov 18 1787

1788 Complete Ceiling Tiles 1w 29 Oct 18 02 Nov 18 1788

1789
1789 Install Raised Access Floor incl Below Floor Barriers 2w 05 Nov 18 16 Nov 18
1790 Soft Floor Coverings 1w 19 Nov 18 23 Nov 18 1790

1791 Building 9 Complete 04 Feb 19 04 Feb 19 1791

1792 External Roads & Landscaping to Building 9A 35w 4d 18 May 18 08 Feb 19 1792

1793 Prep for Kerbs 3w 20 Aug 18 10 Sep 18 1793

1794 Loading Bay Bases 1w 20 Aug 18 24 Aug 18 1794


1795 Import to formation level 2w 28 Aug 18 10 Sep 18 1795

1796 Kerbs 16w 2d 11 Sep 18 16 Jan 19 1796

1797 Paving and Tarmac 16w 2d 11 Sep 18 16 Jan 19 1797


1798 Lay Roadside Kerbs (250 linear maters)M 2w 3d 11 Sep 18 27 Sep 18 1798
1799 Lay Sets (250M2) 5w 02 Oct 18 05 Nov 18 1799
1800 Lay Chanel Kerb 1w 25 Sep 18 01 Oct 18 1800
1801 Lay Paving to western elevation of 9a (100m2) 2w 06 Nov 18 19 Nov 18 1801
1802 Paving to Southen Elevation of 9A (68m2) 1w 20 Nov 18 26 Nov 18 1802
1803 Mistal Paving to area (210m2) 2w 4d 27 Nov 18 14 Dec 18 1803
1804 Regulate for Tarmac 3d 17 Dec 18 19 Dec 18 1804
1805 Tarmac to Area 1w 20 Dec 18 09 Jan 19 1805
1806 Snag and Handover 1w 10 Jan 19 16 Jan 19 1806

1807 External underground Services 8w 18 May 18 13 Jul 18 1807

1808 Retaining wall along Building 10B 5w 16 Jul 18 17 Aug 18 1808

1809 Sub Base to Roads 5w 07 Sep 18 11 Oct 18 1809

1810 Kerbs to Roads 5w 25 Jun 18 27 Jul 18 1810

1811 Drainage and Gullies to Roads 5w 23 Jul 18 24 Aug 18 1811

1812 Base Course to Roads 4w 20 Aug 18 17 Sep 18 1812

1813 Wearing Course to Roads 2w 18 Sep 18 01 Oct 18 1813

1814 Sub-Base to Paved Areas 4w 4d 30 Jul 18 31 Aug 18 1814

1815 Hard Landscaping 10w 10 Aug 18 19 Oct 18 1815

1816 External Lighting 3w 4d 08 Jan 19 01 Feb 19 1816

1817 WaterFeature 20w 10 Sep 18 08 Feb 19 1817


1818 Plant Room 12w 10 Sep 18 30 Nov 18 1818

1819 External Waterfeature 8w 03 Dec 18 08 Feb 19 1819

1820 Soft Landscaping 5w 07 Jan 19 08 Feb 19 1820

1821 Building 8A 80w 1d 04 May 17 06 Dec 18 1821

1822 Piling 10w 1d 04 May 17 14 Jul 17 1822

1823 Lay Pile Mat 1w 04 May 17 10 May 17 1823

1824 Lay Crane Mat 1w 15 Jun 17 21 Jun 17 1824

1825 Piling 3w 2d 22 Jun 17 14 Jul 17 1825

1826 Structure - 8A 24w 19 Jul 17 12 Jan 18 1826

1827 Substructure 9w 3d 19 Jul 17 25 Sep 17 1827


1828 Core 01 4w 19 Jul 17 15 Aug 17 1828
1829 Excavation 3w 19 Jul 17 08 Aug 17 1829
1830 Break Down Piles 2w 4d 24 Jul 17 10 Aug 17 1830
1831 FRC Base of Cap 3w 26 Jul 17 15 Aug 17 1831
1832 Core 02 4w 1d 27 Jul 17 24 Aug 17 1832
1833 Excavation 3w 27 Jul 17 16 Aug 17 1833
1834 Break Down Piles 2w 4d 01 Aug 17 18 Aug 17 1834
1835 FRC Base of Cap 3w 1d 03 Aug 17 24 Aug 17 1835
1836 General Pile Caps 4w 3d 09 Aug 17 11 Sep 17 1836

1837 Excavation 4w 09 Aug 17 06 Sep 17 1837


1838 Break Down Piles 4w 11 Aug 17 08 Sep 17 1838

1839 FRC Base of Cap 4w 14 Aug 17 11 Sep 17 1839

1840 Groundfloor Slab 4w 2d 24 Aug 17 25 Sep 17 1840


1841 Pour 1 2w 24 Aug 17 07 Sep 17 1841

1842 Pour 2 2w 12 Sep 17 25 Sep 17 1842


1843 Superstructure 16w 3d 11 Sep 17 12 Jan 18 1843

1844 STAND PRECAST CORE WALLS GND - 1ST FLOOR 4d 11 Sep 17 27 Sep 17 1844

1845 STAND PRECAST COLUMNS GROUND - 1ST FLOOR 2w 13 Sep 17 26 Sep 17 1845
1846 FRC 1ST FLOOR SLAB 2w 2d 27 Sep 17 12 Oct 17 1846

1847 STAND PRECAST CORE WALLS 1ST - 2ND FLOOR 4d 06 Oct 17 16 Oct 17 1847
1848 STAND PRECAST COLUMNS 1ST - 2ND FLOOR 1w 4d 09 Oct 17 19 Oct 17 1848
1849 FRC 2ND FLOOR SLAB 1w 3d 10 Oct 17 25 Oct 17 1849
1850 STAND PRECAST WALLS 2ND - 3RD FLOOR 4d 24 Oct 17 27 Oct 17 1850
1851 STAND PRECAST COLUMNS 2ND - 3RD FLOOR 1w 2d 19 Oct 17 27 Oct 17 1851
1852 FRC 3RD FLOOR SLAB 2w 25 Oct 17 07 Nov 17 1852
1853 STAND PRECAST CORE WALLS 3RD - 4TH FLOOR 4d 02 Nov 17 09 Nov 17 1853
1854 STAND PRECAST COLUMNS 3RD - 4TH FLOOR 1w 2d 02 Nov 17 10 Nov 17 1854
1855 FRC 4TH FLOOR SLAB 2w 02 Nov 17 15 Nov 17 1855
1856 STAND PRECAST CORE WALLS 4TH - 5TH FLOOR 4d 09 Nov 17 17 Nov 17 1856
1857 STAND PRECAST COLUMNS 4TH - 5TH FLOOR 1w 3d 10 Nov 17 21 Nov 17 1857
1858 FRC 5TH FLOOR SLAB 2w 14 Nov 17 27 Nov 17 1858
1859 STAND PRECAST WALLS 5TH - 6TH FLOOR 4d 21 Nov 17 29 Nov 17 1859

1860 STAND PRECAST COLUMNS 5TH - 6TH FLOOR 1w 3d 21 Nov 17 30 Nov 17 1860
1861 FRC 6TH FLOOR SLAB 2w 2d 24 Nov 17 11 Dec 17 1861

1862 STAND PRECAST WALLS 6TH - ROOF 4d 05 Dec 17 13 Dec 17 1862


1863 STAND PRECAST COLUMNS 6TH - ROOF 1w 3d 07 Dec 17 18 Dec 17 1863
1864 FRC ROOF SLAB 2w 12 Dec 17 03 Jan 18 1864

1865 STAND PRECAST CORE WALL OVERRUNS 4d 20 Dec 17 05 Jan 18 1865


1866 FRC CAPPING SLAB TO CORES 2w 1d 20 Dec 17 12 Jan 18 1866

1867 FRC PERIMETER UPSTAND TO ROOF 1w 4d 20 Dec 17 10 Jan 18 1867

1868 Construct Plant Bases & Plinths 2w 19 Dec 17 10 Jan 18 1868

1869 Precast Stairs & Handrails 13w 06 Sep 17 12 Dec 17 1869

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1870 Facades 35w 4d 15 Jan 18 28 Sep 18 1870

1871 Precast Cladding 5w 4d 15 Jan 18 22 Feb 18 1871


1872 Precast Cladding Panels South elevation 2w 15 Jan 18 26 Jan 18 1872
1873 Precast Cladding Panels North elevation 2w 29 Jan 18 09 Feb 18 1873

1874 Precast Cladding Panels West elevation 4d 12 Feb 18 15 Feb 18 1874

1875 Precast Cladding Panels East elevation 1w 16 Feb 18 22 Feb 18 1875

1876 Mastic Sealing externally 6w 22 Jan 18 02 Mar 18 1876


1877 Windows 8w 22 Jan 18 16 Mar 18 1877
1878 Install SFS, Windows & Cladding Level 06 8w 22 Jan 18 16 Mar 18 1878

1879 Install SFS, Windows and Cladding Level 6 South elevation 7w 22 Jan 18 09 Mar 18 1879

1880 Install SFS, Windows and Cladding Level 6 North East and West Elevation 5w 12 Feb 18 16 Mar 18 1880

1881 Install ribbon window curtain walling to North Elevation 5w 12 Feb 18 16 Mar 18 1881

1882 Curtain Walling/ Doors Ground Floor 7w 29 Jan 18 16 Mar 18 1882

1883 Windows & Shopfronts at Ground 7w 29 Jan 18 16 Mar 18 1883

1884 External Doors & Louvres at Ground 2w 2d 01 Mar 18 16 Mar 18 1884

1885 Complete ribbon windows after hoists removed 3w 04 Jun 18 22 Jun 18 1885
1886 Canopies 31w 16 Feb 18 28 Sep 18 1886
1887 Install Frame for the Canopies 1w 16 Feb 18 22 Feb 18 1887
1888 Complete cantilevered frame & glazing for Canopies 1w 24 Sep 18 28 Sep 18 1888

1889 Roofing 11w 15 Jan 18 03 Apr 18 1889

1890 Erect Terrace Balustrades 2w 15 Jan 18 26 Jan 18 1890

1891 Erect posts for Roof Louvres 2w 15 Jan 18 26 Jan 18 1891

1892 Terrace Slab Waterproofing 1w 2d 29 Jan 18 06 Feb 18 1892

1893 Roof Slab Waterproofing 4w 29 Jan 18 23 Feb 18 1893

1894 Building 8A Temporary Weatherproof 12 Feb 18 12 Feb 18 1894

1895 Install Stair Core Roofing and cladding 4w 19 Feb 18 16 Mar 18 1895

1896 Roof Finishes to roof and terrace incl. Aluminum copings 4w 19 Feb 18 16 Mar 18 1896

1897 Install Roof Louvres 3w 19 Feb 18 09 Mar 18 1897

1898 Roof ladders 2w 19 Mar 18 03 Apr 18 1898

1899 Latest Date for ABP/WTP to omit Cat A Shell and Core Services scope of works to Building 8A 25 Jul 17 25 Jul 17 1899

1900 M & E Installation 24w 3d 16 Nov 17 22 May 18 1900

1901 Riser Platform Installation 2w 1d 16 Nov 17 04 Jan 18 1901

1902 Lift floor modules onto floors 1 - 3 1w 12 Dec 17 18 Dec 17 1902

1903 Lift floor modules onto floors 4 - 6 1w 11 Jan 18 17 Jan 18 1903

1904 Installation of Siphonic drainage 2w 11 Jan 18 24 Jan 18 1904

1905 Ground Floor Plant Installation 8A 11w 12 Jan 18 29 Mar 18 1905

1906 Roof Plant Installation 8A 12w 22 Feb 18 22 May 18 1906

1907 Blockwork 28w 4d 20 Nov 17 25 Jun 18 1907

1908 First VIsit 10w 1d 20 Nov 17 07 Feb 18 1908

1909 Blockwork Walls at Ground 2w 2d 20 Nov 17 05 Dec 17 1909

1910 Blockwork Walls at L1 1w 22 Nov 17 28 Nov 17 1910

1911 Blockwork Walls at L2 1w 30 Nov 17 06 Dec 17 1911

1912 Blockwork Walls at L3 1w 12 Dec 17 18 Dec 17 1912

1913 Blockwork Walls at L4 1w 08 Jan 18 12 Jan 18 1913

1914 Blockwork Walls at L5 1w 18 Jan 18 24 Jan 18 1914

1915 Blockwork Walls at L6 1w 01 Feb 18 07 Feb 18 1915

1916 Return Visit 2w 2d 08 Jun 18 25 Jun 18 1916

1917 Level 06 2d 08 Jun 18 11 Jun 18 1917

1918 Level 05 2d 12 Jun 18 13 Jun 18 1918

1919 Level 04 2d 14 Jun 18 15 Jun 18 1919

1920 Level 03 2d 18 Jun 18 19 Jun 18 1920

1921 Level 02 2d 20 Jun 18 21 Jun 18 1921

1922 Level 01 2d 22 Jun 18 25 Jun 18 1922

1923 Hoists 19w 4d 15 Jan 18 07 Jun 18 1923

1924 Window for Cantidecks to load out upper floors 4w 4d 15 Jan 18 15 Feb 18 1924

1925 Hoist 1 15w 12 Feb 18 01 Jun 18 1925

1926 Hoist 2 14w 4d 19 Feb 18 07 Jun 18 1926

1927 Remove Hoist 2w 04 Jun 18 15 Jun 18 1927

1928 Lift /Toilet Core Fit Out 63w 05 Sep 17 06 Dec 18 1928

1929 Lifts 63w 05 Sep 17 06 Dec 18 1929

1930 Delivery of temporary lift doors 05 Sep 17 05 Sep 17 1930

1931 Lift 1 10w 22 Feb 18 08 May 18 1931

1932 Lift 1 Guides and doors 8w 22 Feb 18 20 Apr 18 1932

1933 Lift 1 Car 1w 23 Apr 18 30 Apr 18 1933

1934 Lift 1 Commission 1w 01 May 18 08 May 18 1934

1935 Lift 2 38w 01 Mar 18 29 Nov 18 1935

1936 Lift 2 Guides and doors 8w 01 Mar 18 30 Apr 18 1936

1937 Lift 2 Car 1w 01 May 18 08 May 18 1937

1938 Lift 2 Commission 1w 09 May 18 15 May 18 1938

1939 Hand back Lift 2 after builders beneficial use 16 Nov 18 16 Nov 18 1939
1940 Recommission Lift 2 2w 16 Nov 18 29 Nov 18 1940

1941 Lift 3 10w 08 Mar 18 22 May 18 1941

1942 Lift 3 Guides and doors 8w 08 Mar 18 08 May 18 1942

1943 Lift 3 Car 1w 09 May 18 15 May 18 1943

1944 Lift 3 Commission 1w 16 May 18 22 May 18 1944

1945 Lift 4 37w 15 Mar 18 06 Dec 18 1945

1946 Lift 4 Guides and doors 8w 15 Mar 18 15 May 18 1946

1947 Lift 4 Car 1w 16 May 18 22 May 18 1947

1948 Lift 4 Commission 1w 23 May 18 30 May 18 1948

1949 Hand back Lift 4 after builders beneficial use 23 Nov 18 23 Nov 18 1949

1950 Recommission Lift 4 2w 23 Nov 18 06 Dec 18 1950


1951 Toilet & Lobby 26w 08 Feb 18 15 Aug 18 1951

1952 Level 01 - CORE 01 12w 08 Feb 18 08 May 18 1952


1953 Toilet 12w 08 Feb 18 08 May 18 1953
1954 Floor slab available 08 Feb 18 08 Feb 18 1954
1955 1st Fix Wall with Head tracks 1w 08 Feb 18 14 Feb 18 1955
1956 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 15 Feb 18 14 Mar 18 1956
1957 Fix Pocket Doors 1w 15 Feb 18 21 Feb 18 1957
1958 Inspection and Ceiling Grid Clearance 15 Mar 18 15 Mar 18 1958
1959 2nd Fix wall 1w 15 Mar 18 21 Mar 18 1959
1960 IPS Frame (Box Out only) incl. Backing ply 3d 22 Mar 18 26 Mar 18 1960
1961 Screed 2d 27 Mar 18 28 Mar 18 1961
1962 Fix Ceiling Grid Works 3d 29 Mar 18 04 Apr 18 1962
1963 Floor Tiling Works 3d 05 Apr 18 09 Apr 18 1963
1964 Wall Tiling works incl. IPS Panels 3d 10 Apr 18 12 Apr 18 1964

1965 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 13 Apr 18 20 Apr 18 1965

1966 Mark and Cut openings for MEP on walls including Ceiling 2d 23 Apr 18 24 Apr 18 1966

1967 Install Vanity Tops 4d 23 Apr 18 26 Apr 18 1967


1968 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 25 Apr 18 01 May 18 1968

1969 Fix MEP Final Fixtures 3d 01 May 18 03 May 18 1969

1970 Final Coat Paint on Ceiling 2d 04 May 18 08 May 18 1970

1971 Lobby 8w 3d 15 Feb 18 18 Apr 18 1971

1972 1st Fix Wall with Head tracks 1w 15 Feb 18 21 Feb 18 1972
1973 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 22 Feb 18 21 Mar 18 1973

1974 Fix Ceiling Grid 3d 22 Mar 18 26 Mar 18 1974

1975 Paint 1st Coat 2d 27 Mar 18 28 Mar 18 1975

1976 Fix doors incl. Ironmongery 2d 29 Mar 18 03 Apr 18 1976


1977 Mark and Cut openings for MEP on walls 2d 04 Apr 18 05 Apr 18 1977
1978 Install Ceiling Tiles 3d 06 Apr 18 10 Apr 18 1978
1979 Fix MEP Final Fixtures 3d 11 Apr 18 13 Apr 18 1979
1980 Final Coat Paint on walls and ceiling 3d 16 Apr 18 18 Apr 18 1980
1981 Staircase Level 01 - CORE 01 2w 1d 12 Mar 18 26 Mar 18 1981
1982 H/L Electrical Containment & Conduits - 1st Fix 2d 12 Mar 18 13 Mar 18 1982
1983 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 14 Mar 18 15 Mar 18 1983
1984 Ceiling Rose fixing 1d 16 Mar 18 16 Mar 18 1984
1985 First Coat Paint on Walls & Ceiliings 2d 19 Mar 18 20 Mar 18 1985
1986 MEP Final Fixtures on Wall & Ceilings 2d 21 Mar 18 22 Mar 18 1986

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1987 Final Coat Paint on walls & Ceilings 2d 23 Mar 18 26 Mar 18 1987
1988 Level 02 - CORE 01 12w 22 Feb 18 22 May 18 1988
1989 Toilet 12w 22 Feb 18 22 May 18 1989
1990 1st Fix Wall with Head tracks 1w 22 Feb 18 28 Feb 18 1990
1991 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 Mar 18 28 Mar 18 1991
1992 Fix Pocket Doors 1w 01 Mar 18 07 Mar 18 1992
1993 Inspection and Ceiling Grid Clearance 29 Mar 18 29 Mar 18 1993
1994 2nd Fix wall 1w 29 Mar 18 06 Apr 18 1994
1995 IPS Frame (Box Out only) incl. Backing ply 3d 09 Apr 18 11 Apr 18 1995

1996 Screed 2d 12 Apr 18 13 Apr 18 1996


1997 Fix Ceiling Grid Works 3d 16 Apr 18 18 Apr 18 1997
1998 Floor Tiling Works 3d 19 Apr 18 23 Apr 18 1998

1999 Wall Tiling works incl. IPS Panels 3d 24 Apr 18 26 Apr 18 1999
2000 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 30 Apr 18 08 May 18 2000
2001 Mark and Cut openings for MEP on walls including Ceiling 2d 09 May 18 10 May 18 2001

2002 Install Vanity Tops 4d 09 May 18 14 May 18 2002

2003 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 11 May 18 16 May 18 2003
2004 Fix MEP Final Fixtures 3d 16 May 18 18 May 18 2004
2005 Final Coat Paint on Ceiling 2d 21 May 18 22 May 18 2005
2006 Lobby 8w 3d 01 Mar 18 03 May 18 2006
2007 1st Fix Wall with Head tracks 1w 01 Mar 18 07 Mar 18 2007
2008 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 08 Mar 18 06 Apr 18 2008
2009 Fix Ceiling Grid 3d 09 Apr 18 11 Apr 18 2009
2010 Paint 1st Coat 2d 12 Apr 18 13 Apr 18 2010
2011 Fix doors incl. Ironmongery 2d 16 Apr 18 17 Apr 18 2011
2012 Mark and Cut openings for MEP on walls 2d 18 Apr 18 19 Apr 18 2012
2013 Install Ceiling Tiles 3d 20 Apr 18 24 Apr 18 2013
2014 Fix MEP Final Fixtures 3d 25 Apr 18 30 Apr 18 2014
2015 Final Coat Paint on walls and ceiling 3d 01 May 18 03 May 18 2015
2016 Staircase Level 02 - CORE 01 2w 1d 19 Mar 18 04 Apr 18 2016
2017 H/L Electrical Containment & Conduits - 1st Fix 2d 19 Mar 18 20 Mar 18 2017
2018 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 21 Mar 18 22 Mar 18 2018
2019 Ceiling Rose fixing 1d 23 Mar 18 23 Mar 18 2019
2020 First Coat Paint on Walls & Ceiliings 2d 26 Mar 18 27 Mar 18 2020

2021 MEP Final Fixtures on Wall & Ceilings 2d 28 Mar 18 29 Mar 18 2021

2022 Final Coat Paint on walls & Ceilings 2d 03 Apr 18 04 Apr 18 2022

2023 Level 03 - CORE 01 12w 08 Mar 18 06 Jun 18 2023


2024 Toilet 12w 08 Mar 18 06 Jun 18 2024
2025 1st Fix Wall with Head tracks 1w 08 Mar 18 14 Mar 18 2025

2026 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 15 Mar 18 13 Apr 18 2026
2027 Fix Pocket Doors 1w 15 Mar 18 21 Mar 18 2027
2028 Inspection and Ceiling Grid Clearance 16 Apr 18 16 Apr 18 2028
2029 2nd Fix wall 1w 16 Apr 18 20 Apr 18 2029
2030 IPS Frame (Box Out only) incl. Backing ply 3d 23 Apr 18 25 Apr 18 2030
2031 Screed 2d 26 Apr 18 30 Apr 18 2031
2032 Fix Ceiling Grid Works 3d 01 May 18 03 May 18 2032
2033 Floor Tiling Works 3d 04 May 18 09 May 18 2033
2034 Wall Tiling works incl. IPS Panels 3d 10 May 18 14 May 18 2034
2035 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 15 May 18 22 May 18 2035
2036 Mark and Cut openings for MEP on walls including Ceiling 2d 23 May 18 24 May 18 2036
2037 Install Vanity Tops 4d 23 May 18 29 May 18 2037
2038 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 25 May 18 31 May 18 2038
2039 Fix MEP Final Fixtures 3d 31 May 18 04 Jun 18 2039
2040 Final Coat Paint on Ceiling 2d 05 Jun 18 06 Jun 18 2040
2041 Lobby 8w 3d 15 Mar 18 18 May 18 2041
2042 1st Fix Wall with Head tracks 1w 15 Mar 18 21 Mar 18 2042
2043 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 22 Mar 18 20 Apr 18 2043
2044 Fix Ceiling Grid 3d 23 Apr 18 25 Apr 18 2044

2045 Paint 1st Coat 2d 26 Apr 18 30 Apr 18 2045

2046 Fix doors incl. Ironmongery 2d 01 May 18 02 May 18 2046


2047 Mark and Cut openings for MEP on walls 2d 03 May 18 04 May 18 2047

2048 Install Ceiling Tiles 3d 08 May 18 10 May 18 2048


2049 Fix MEP Final Fixtures 3d 11 May 18 15 May 18 2049
2050 Final Coat Paint on walls and ceiling 3d 16 May 18 18 May 18 2050

2051 Staircase Level 03 - CORE 01 2w 1d 11 Apr 18 25 Apr 18 2051

2052 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Apr 18 12 Apr 18 2052
2053 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Apr 18 16 Apr 18 2053

2054 Ceiling Rose fixing 1d 17 Apr 18 17 Apr 18 2054

2055 First Coat Paint on Walls & Ceiliings 2d 18 Apr 18 19 Apr 18 2055

2056 MEP Final Fixtures on Wall & Ceilings 2d 20 Apr 18 23 Apr 18 2056
2057 Final Coat Paint on walls & Ceilings 2d 24 Apr 18 25 Apr 18 2057
2058 Level 04 - CORE 01 12w 22 Mar 18 20 Jun 18 2058
2059 Toilet 12w 22 Mar 18 20 Jun 18 2059
2060 1st Fix Wall with Head tracks 1w 22 Mar 18 28 Mar 18 2060
2061 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 29 Mar 18 30 Apr 18 2061
2062 Fix Pocket Doors 1w 29 Mar 18 06 Apr 18 2062
2063 Inspection and Ceiling Grid Clearance 01 May 18 01 May 18 2063
2064 2nd Fix wall 1w 01 May 18 08 May 18 2064
2065 IPS Frame (Box Out only) incl. Backing ply 3d 09 May 18 11 May 18 2065
2066 Screed 2d 14 May 18 15 May 18 2066
2067 Fix Ceiling Grid Works 3d 16 May 18 18 May 18 2067
2068 Floor Tiling Works 3d 21 May 18 23 May 18 2068

2069 Wall Tiling works incl. IPS Panels 3d 24 May 18 29 May 18 2069
2070 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 30 May 18 06 Jun 18 2070

2071 Mark and Cut openings for MEP on walls including Ceiling 2d 07 Jun 18 08 Jun 18 2071
2072 Install Vanity Tops 4d 07 Jun 18 12 Jun 18 2072
2073 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 11 Jun 18 14 Jun 18 2073
2074 Fix MEP Final Fixtures 3d 14 Jun 18 18 Jun 18 2074
2075 Final Coat Paint on Ceiling 2d 19 Jun 18 20 Jun 18 2075

2076 Lobby 8w 3d 29 Mar 18 04 Jun 18 2076

2077 1st Fix Wall with Head tracks 1w 29 Mar 18 06 Apr 18 2077

2078 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 Apr 18 08 May 18 2078

2079 Fix Ceiling Grid 3d 09 May 18 11 May 18 2079


2080 Paint 1st Coat 2d 14 May 18 15 May 18 2080
2081 Fix doors incl. Ironmongery 2d 16 May 18 17 May 18 2081
2082 Mark and Cut openings for MEP on walls 2d 18 May 18 21 May 18 2082
2083 Install Ceiling Tiles 3d 22 May 18 24 May 18 2083
2084 Fix MEP Final Fixtures 3d 25 May 18 30 May 18 2084
2085 Final Coat Paint on walls and ceiling 3d 31 May 18 04 Jun 18 2085
2086 Staircase Level 04 - CORE 01 2w 1d 25 Apr 18 11 May 18 2086
2087 H/L Electrical Containment & Conduits - 1st Fix 2d 25 Apr 18 26 Apr 18 2087
2088 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 30 Apr 18 01 May 18 2088
2089 Ceiling Rose fixing 1d 02 May 18 02 May 18 2089
2090 First Coat Paint on Walls & Ceiliings 2d 03 May 18 04 May 18 2090
2091 MEP Final Fixtures on Wall & Ceilings 2d 08 May 18 09 May 18 2091
2092 Final Coat Paint on walls & Ceilings 2d 10 May 18 11 May 18 2092
2093 Level 05 - CORE 01 12w 09 Apr 18 04 Jul 18 2093

2094 Toilet 12w 09 Apr 18 04 Jul 18 2094


2095 1st Fix Wall with Head tracks 1w 09 Apr 18 13 Apr 18 2095
2096 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 Apr 18 15 May 18 2096

2097 Fix Pocket Doors 1w 16 Apr 18 20 Apr 18 2097


2098 Inspection and Ceiling Grid Clearance 16 May 18 16 May 18 2098

2099 2nd Fix wall 1w 16 May 18 22 May 18 2099


2100 IPS Frame (Box Out only) incl. Backing ply 3d 23 May 18 25 May 18 2100

2101 Screed 2d 29 May 18 30 May 18 2101

2102 Fix Ceiling Grid Works 3d 31 May 18 04 Jun 18 2102


2103 Floor Tiling Works 3d 05 Jun 18 07 Jun 18 2103

2104 Wall Tiling works incl. IPS Panels 3d 08 Jun 18 12 Jun 18 2104
2105 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 13 Jun 18 20 Jun 18 2105
2106 Mark and Cut openings for MEP on walls including Ceiling 2d 21 Jun 18 22 Jun 18 2106
2107 Install Vanity Tops 4d 21 Jun 18 26 Jun 18 2107
2108 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 25 Jun 18 28 Jun 18 2108
2109 Fix MEP Final Fixtures 3d 28 Jun 18 02 Jul 18 2109
2110 Final Coat Paint on Ceiling 2d 03 Jul 18 04 Jul 18 2110
2111 Lobby 8w 3d 16 Apr 18 18 Jun 18 2111
2112 1st Fix Wall with Head tracks 1w 16 Apr 18 20 Apr 18 2112
2113 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 Apr 18 22 May 18 2113
2114 Fix Ceiling Grid 3d 23 May 18 25 May 18 2114
2115 Paint 1st Coat 2d 29 May 18 30 May 18 2115
2116 Fix doors incl. Ironmongery 2d 31 May 18 01 Jun 18 2116

2117 Mark and Cut openings for MEP on walls 2d 04 Jun 18 05 Jun 18 2117
2118 Install Ceiling Tiles 3d 06 Jun 18 08 Jun 18 2118

2119 Fix MEP Final Fixtures 3d 11 Jun 18 13 Jun 18 2119


2120 Final Coat Paint on walls and ceiling 3d 14 Jun 18 18 Jun 18 2120
2121 Staircase Level 05 - CORE 01 2w 1d 11 May 18 25 May 18 2121

2122 H/L Electrical Containment & Conduits - 1st Fix 2d 11 May 18 14 May 18 2122
2123 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 15 May 18 16 May 18 2123

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2124 Ceiling Rose fixing 1d 17 May 18 17 May 18 2124
2125 First Coat Paint on Walls & Ceiliings 2d 18 May 18 21 May 18 2125
2126 MEP Final Fixtures on Wall & Ceilings 2d 22 May 18 23 May 18 2126
2127 Final Coat Paint on walls & Ceilings 2d 24 May 18 25 May 18 2127
2128 Level 06 - CORE 01 12w 23 Apr 18 18 Jul 18 2128
2129 Toilet 12w 23 Apr 18 18 Jul 18 2129
2130 1st Fix Wall with Head tracks 1w 23 Apr 18 30 Apr 18 2130
2131 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 May 18 30 May 18 2131
2132 Fix Pocket Doors 1w 01 May 18 08 May 18 2132

2133 Inspection and Ceiling Grid Clearance 31 May 18 31 May 18 2133

2134 2nd Fix wall 1w 31 May 18 06 Jun 18 2134


2135 IPS Frame (Box Out only) incl. Backing ply 3d 07 Jun 18 11 Jun 18 2135

2136 Screed 2d 12 Jun 18 13 Jun 18 2136


2137 Fix Ceiling Grid Works 3d 14 Jun 18 18 Jun 18 2137
2138 Floor Tiling Works 3d 19 Jun 18 21 Jun 18 2138

2139 Wall Tiling works incl. IPS Panels 3d 22 Jun 18 26 Jun 18 2139

2140 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 27 Jun 18 04 Jul 18 2140

2141 Mark and Cut openings for MEP on walls including Ceiling 2d 05 Jul 18 06 Jul 18 2141
2142 Install Vanity Tops 4d 05 Jul 18 10 Jul 18 2142
2143 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 09 Jul 18 12 Jul 18 2143
2144 Fix MEP Final Fixtures 3d 12 Jul 18 16 Jul 18 2144
2145 Final Coat Paint on Ceiling 2d 17 Jul 18 18 Jul 18 2145
2146 Lobby 8w 3d 01 May 18 02 Jul 18 2146
2147 1st Fix Wall with Head tracks 1w 01 May 18 08 May 18 2147
2148 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 2148
2149 Fix Ceiling Grid 3d 07 Jun 18 11 Jun 18 2149
2150 Paint 1st Coat 2d 12 Jun 18 13 Jun 18 2150
2151 Fix doors incl. Ironmongery 2d 14 Jun 18 15 Jun 18 2151
2152 Mark and Cut openings for MEP on walls 2d 18 Jun 18 19 Jun 18 2152
2153 Install Ceiling Tiles 3d 20 Jun 18 22 Jun 18 2153
2154 Fix MEP Final Fixtures 3d 25 Jun 18 27 Jun 18 2154
2155 Final Coat Paint on walls and ceiling 3d 28 Jun 18 02 Jul 18 2155
2156 Staircase Level 06 - CORE 01 2w 1d 25 May 18 11 Jun 18 2156
2157 H/L Electrical Containment & Conduits - 1st Fix 2d 25 May 18 29 May 18 2157

2158 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 30 May 18 31 May 18 2158

2159 Ceiling Rose fixing 1d 01 Jun 18 01 Jun 18 2159

2160 First Coat Paint on Walls & Ceiliings 2d 04 Jun 18 05 Jun 18 2160

2161 MEP Final Fixtures on Wall & Ceilings 2d 06 Jun 18 07 Jun 18 2161
2162 Final Coat Paint on walls & Ceilings 2d 08 Jun 18 11 Jun 18 2162

2163 Level GF - CORE 01 12w 09 May 18 01 Aug 18 2163


2164 Toilet 12w 09 May 18 01 Aug 18 2164
2165 1st Fix Wall with Head tracks 1w 09 May 18 15 May 18 2165

2166 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 2166
2167 Fix Pocket Doors 1w 16 May 18 22 May 18 2167

2168 Inspection and Ceiling Grid Clearance 14 Jun 18 14 Jun 18 2168


2169 2nd Fix wall 1w 14 Jun 18 20 Jun 18 2169
2170 IPS Frame (Box Out only) incl. Backing ply 3d 21 Jun 18 25 Jun 18 2170
2171 Screed 2d 26 Jun 18 27 Jun 18 2171
2172 Fix Ceiling Grid Works 3d 28 Jun 18 02 Jul 18 2172
2173 Floor Tiling Works 3d 03 Jul 18 05 Jul 18 2173
2174 Wall Tiling works incl. IPS Panels 3d 06 Jul 18 10 Jul 18 2174
2175 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 11 Jul 18 18 Jul 18 2175
2176 Mark and Cut openings for MEP on walls including Ceiling 2d 19 Jul 18 20 Jul 18 2176
2177 Install Vanity Tops 4d 19 Jul 18 24 Jul 18 2177
2178 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 23 Jul 18 26 Jul 18 2178
2179 Fix MEP Final Fixtures 3d 26 Jul 18 30 Jul 18 2179
2180 Final Coat Paint on Ceiling 2d 31 Jul 18 01 Aug 18 2180
2181 Lobby 8w 3d 16 May 18 16 Jul 18 2181

2182 1st Fix Wall with Head tracks 1w 16 May 18 22 May 18 2182

2183 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 2183

2184 Fix Ceiling Grid 3d 21 Jun 18 25 Jun 18 2184

2185 Paint 1st Coat 2d 26 Jun 18 27 Jun 18 2185

2186 Fix doors incl. Ironmongery 2d 28 Jun 18 29 Jun 18 2186


2187 Mark and Cut openings for MEP on walls 2d 02 Jul 18 03 Jul 18 2187

2188 Install Ceiling Tiles 3d 04 Jul 18 06 Jul 18 2188

2189 Fix MEP Final Fixtures 3d 09 Jul 18 11 Jul 18 2189

2190 Final Coat Paint on walls and ceiling 3d 12 Jul 18 16 Jul 18 2190
2191 Staircase Level GF - CORE 01 2w 1d 11 Jun 18 25 Jun 18 2191

2192 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Jun 18 12 Jun 18 2192
2193 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Jun 18 14 Jun 18 2193
2194 Ceiling Rose fixing 1d 15 Jun 18 15 Jun 18 2194
2195 First Coat Paint on Walls & Ceiliings 2d 18 Jun 18 19 Jun 18 2195
2196 MEP Final Fixtures on Wall & Ceilings 2d 20 Jun 18 21 Jun 18 2196
2197 Final Coat Paint on walls & Ceilings 2d 22 Jun 18 25 Jun 18 2197

2198 Level 01 - CORE 02 12w 22 Feb 18 22 May 18 2198


2199 Toilet 12w 22 Feb 18 22 May 18 2199
2200 Floor slab available 22 Feb 18 22 Feb 18 2200
2201 1st Fix Wall with Head tracks 1w 22 Feb 18 28 Feb 18 2201
2202 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 Mar 18 28 Mar 18 2202
2203 Fix Pocket Doors 1w 01 Mar 18 07 Mar 18 2203
2204 Inspection and Ceiling Grid Clearance 29 Mar 18 29 Mar 18 2204

2205 2nd Fix wall 1w 29 Mar 18 06 Apr 18 2205


2206 IPS Frame (Box Out only) incl. Backing ply 3d 09 Apr 18 11 Apr 18 2206

2207 Screed 2d 12 Apr 18 13 Apr 18 2207


2208 Fix Ceiling Grid Works 3d 16 Apr 18 18 Apr 18 2208
2209 Floor Tiling Works 3d 19 Apr 18 23 Apr 18 2209
2210 Wall Tiling works incl. IPS Panels 3d 24 Apr 18 26 Apr 18 2210
2211 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 30 Apr 18 08 May 18 2211

2212 Mark and Cut openings for MEP on walls including Ceiling 2d 09 May 18 10 May 18 2212

2213 Install Vanity Tops 4d 09 May 18 14 May 18 2213

2214 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 11 May 18 16 May 18 2214

2215 Fix MEP Final Fixtures 3d 16 May 18 18 May 18 2215


2216 Final Coat Paint on Ceiling 2d 21 May 18 22 May 18 2216
2217 Lobby 8w 3d 01 Mar 18 03 May 18 2217
2218 1st Fix Wall with Head tracks 1w 01 Mar 18 07 Mar 18 2218
2219 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 08 Mar 18 06 Apr 18 2219
2220 Fix Ceiling Grid 3d 09 Apr 18 11 Apr 18 2220
2221 Paint 1st Coat 2d 12 Apr 18 13 Apr 18 2221
2222 Fix doors incl. Ironmongery 2d 16 Apr 18 17 Apr 18 2222
2223 Mark and Cut openings for MEP on walls 2d 18 Apr 18 19 Apr 18 2223
2224 Install Ceiling Tiles 3d 20 Apr 18 24 Apr 18 2224
2225 Fix MEP Final Fixtures 3d 25 Apr 18 30 Apr 18 2225
2226 Final Coat Paint on walls and ceiling 3d 01 May 18 03 May 18 2226
2227 Staircase Level 01 - CORE 02 2w 1d 26 Mar 18 11 Apr 18 2227
2228 H/L Electrical Containment & Conduits - 1st Fix 2d 26 Mar 18 27 Mar 18 2228
2229 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 28 Mar 18 29 Mar 18 2229

2230 Ceiling Rose fixing 1d 03 Apr 18 03 Apr 18 2230


2231 First Coat Paint on Walls & Ceiliings 2d 04 Apr 18 05 Apr 18 2231
2232 MEP Final Fixtures on Wall & Ceilings 2d 06 Apr 18 09 Apr 18 2232

2233 Final Coat Paint on walls & Ceilings 2d 10 Apr 18 11 Apr 18 2233
2234 Level 02 - CORE 02 12w 08 Mar 18 06 Jun 18 2234

2235 Toilet 12w 08 Mar 18 06 Jun 18 2235


2236 1st Fix Wall with Head tracks 1w 08 Mar 18 14 Mar 18 2236

2237 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 15 Mar 18 13 Apr 18 2237

2238 Fix Pocket Doors 1w 15 Mar 18 21 Mar 18 2238


2239 Inspection and Ceiling Grid Clearance 16 Apr 18 16 Apr 18 2239

2240 2nd Fix wall 1w 16 Apr 18 20 Apr 18 2240


2241 IPS Frame (Box Out only) incl. Backing ply 3d 23 Apr 18 25 Apr 18 2241
2242 Screed 2d 26 Apr 18 30 Apr 18 2242
2243 Fix Ceiling Grid Works 3d 01 May 18 03 May 18 2243
2244 Floor Tiling Works 3d 04 May 18 09 May 18 2244
2245 Wall Tiling works incl. IPS Panels 3d 10 May 18 14 May 18 2245
2246 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 15 May 18 22 May 18 2246
2247 Mark and Cut openings for MEP on walls including Ceiling 2d 23 May 18 24 May 18 2247
2248 Install Vanity Tops 4d 23 May 18 29 May 18 2248
2249 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 25 May 18 31 May 18 2249
2250 Fix MEP Final Fixtures 3d 31 May 18 04 Jun 18 2250
2251 Final Coat Paint on Ceiling 2d 05 Jun 18 06 Jun 18 2251
2252 Lobby 8w 3d 15 Mar 18 18 May 18 2252
2253 1st Fix Wall with Head tracks 1w 15 Mar 18 21 Mar 18 2253
2254 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 22 Mar 18 20 Apr 18 2254

2255 Fix Ceiling Grid 3d 23 Apr 18 25 Apr 18 2255


2256 Paint 1st Coat 2d 26 Apr 18 30 Apr 18 2256
2257 Fix doors incl. Ironmongery 2d 01 May 18 02 May 18 2257

2258 Mark and Cut openings for MEP on walls 2d 03 May 18 04 May 18 2258
2259 Install Ceiling Tiles 3d 08 May 18 10 May 18 2259

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2260 Fix MEP Final Fixtures 3d 11 May 18 15 May 18 2260
2261 Final Coat Paint on walls and ceiling 3d 16 May 18 18 May 18 2261
2262 Staircase Level 02 - CORE 02 2w 1d 11 Apr 18 25 Apr 18 2262
2263 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Apr 18 12 Apr 18 2263
2264 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Apr 18 16 Apr 18 2264
2265 Ceiling Rose fixing 1d 17 Apr 18 17 Apr 18 2265
2266 First Coat Paint on Walls & Ceiliings 2d 18 Apr 18 19 Apr 18 2266
2267 MEP Final Fixtures on Wall & Ceilings 2d 20 Apr 18 23 Apr 18 2267
2268 Final Coat Paint on walls & Ceilings 2d 24 Apr 18 25 Apr 18 2268

2269 Level 03 - CORE 02 12w 22 Mar 18 20 Jun 18 2269


2270 Toilet 12w 22 Mar 18 20 Jun 18 2270
2271 1st Fix Wall with Head tracks 1w 22 Mar 18 28 Mar 18 2271
2272 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 29 Mar 18 30 Apr 18 2272
2273 Fix Pocket Doors 1w 29 Mar 18 06 Apr 18 2273
2274 Inspection and Ceiling Grid Clearance 01 May 18 01 May 18 2274
2275 2nd Fix wall 1w 01 May 18 08 May 18 2275
2276 IPS Frame (Box Out only) incl. Backing ply 3d 09 May 18 11 May 18 2276
2277 Screed 2d 14 May 18 15 May 18 2277
2278 Fix Ceiling Grid Works 3d 16 May 18 18 May 18 2278
2279 Floor Tiling Works 3d 21 May 18 23 May 18 2279
2280 Wall Tiling works incl. IPS Panels 3d 24 May 18 29 May 18 2280
2281 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 30 May 18 06 Jun 18 2281
2282 Mark and Cut openings for MEP on walls including Ceiling 2d 07 Jun 18 08 Jun 18 2282
2283 Install Vanity Tops 4d 07 Jun 18 12 Jun 18 2283
2284 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 11 Jun 18 14 Jun 18 2284
2285 Fix MEP Final Fixtures 3d 14 Jun 18 18 Jun 18 2285
2286 Final Coat Paint on Ceiling 2d 19 Jun 18 20 Jun 18 2286
2287 Lobby 8w 3d 29 Mar 18 04 Jun 18 2287
2288 1st Fix Wall with Head tracks 1w 29 Mar 18 06 Apr 18 2288
2289 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 Apr 18 08 May 18 2289
2290 Fix Ceiling Grid 3d 09 May 18 11 May 18 2290
2291 Paint 1st Coat 2d 14 May 18 15 May 18 2291
2292 Fix doors incl. Ironmongery 2d 16 May 18 17 May 18 2292
2293 Mark and Cut openings for MEP on walls 2d 18 May 18 21 May 18 2293
2294 Install Ceiling Tiles 3d 22 May 18 24 May 18 2294
2295 Fix MEP Final Fixtures 3d 25 May 18 30 May 18 2295
2296 Final Coat Paint on walls and ceiling 3d 31 May 18 04 Jun 18 2296
2297 Staircase Level 03 - CORE 02 2w 1d 25 Apr 18 11 May 18 2297
2298 H/L Electrical Containment & Conduits - 1st Fix 2d 25 Apr 18 26 Apr 18 2298

2299 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 30 Apr 18 01 May 18 2299
2300 Ceiling Rose fixing 1d 02 May 18 02 May 18 2300
2301 First Coat Paint on Walls & Ceiliings 2d 03 May 18 04 May 18 2301

2302 MEP Final Fixtures on Wall & Ceilings 2d 08 May 18 09 May 18 2302
2303 Final Coat Paint on walls & Ceilings 2d 10 May 18 11 May 18 2303
2304 Level 04 - CORE 02 12w 09 Apr 18 04 Jul 18 2304
2305 Toilet 12w 09 Apr 18 04 Jul 18 2305
2306 1st Fix Wall with Head tracks 1w 09 Apr 18 13 Apr 18 2306
2307 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 Apr 18 15 May 18 2307
2308 Fix Pocket Doors 1w 16 Apr 18 20 Apr 18 2308
2309 Inspection and Ceiling Grid Clearance 16 May 18 16 May 18 2309
2310 2nd Fix wall 1w 16 May 18 22 May 18 2310
2311 IPS Frame (Box Out only) incl. Backing ply 3d 23 May 18 25 May 18 2311
2312 Screed 2d 29 May 18 30 May 18 2312
2313 Fix Ceiling Grid Works 3d 31 May 18 04 Jun 18 2313
2314 Floor Tiling Works 3d 05 Jun 18 07 Jun 18 2314
2315 Wall Tiling works incl. IPS Panels 3d 08 Jun 18 12 Jun 18 2315
2316 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 13 Jun 18 20 Jun 18 2316

2317 Mark and Cut openings for MEP on walls including Ceiling 2d 21 Jun 18 22 Jun 18 2317

2318 Install Vanity Tops 4d 21 Jun 18 26 Jun 18 2318

2319 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 25 Jun 18 28 Jun 18 2319
2320 Fix MEP Final Fixtures 3d 28 Jun 18 02 Jul 18 2320

2321 Final Coat Paint on Ceiling 2d 03 Jul 18 04 Jul 18 2321


2322 Lobby 8w 3d 16 Apr 18 18 Jun 18 2322
2323 1st Fix Wall with Head tracks 1w 16 Apr 18 20 Apr 18 2323
2324 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 Apr 18 22 May 18 2324

2325 Fix Ceiling Grid 3d 23 May 18 25 May 18 2325


2326 Paint 1st Coat 2d 29 May 18 30 May 18 2326

2327 Fix doors incl. Ironmongery 2d 31 May 18 01 Jun 18 2327

2328 Mark and Cut openings for MEP on walls 2d 04 Jun 18 05 Jun 18 2328

2329 Install Ceiling Tiles 3d 06 Jun 18 08 Jun 18 2329


2330 Fix MEP Final Fixtures 3d 11 Jun 18 13 Jun 18 2330
2331 Final Coat Paint on walls and ceiling 3d 14 Jun 18 18 Jun 18 2331
2332 Staircase Level 04 - CORE 02 2w 1d 11 May 18 25 May 18 2332
2333 H/L Electrical Containment & Conduits - 1st Fix 2d 11 May 18 14 May 18 2333
2334 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 15 May 18 16 May 18 2334
2335 Ceiling Rose fixing 1d 17 May 18 17 May 18 2335
2336 First Coat Paint on Walls & Ceiliings 2d 18 May 18 21 May 18 2336
2337 MEP Final Fixtures on Wall & Ceilings 2d 22 May 18 23 May 18 2337
2338 Final Coat Paint on walls & Ceilings 2d 24 May 18 25 May 18 2338
2339 Level 05 - CORE 02 12w 23 Apr 18 18 Jul 18 2339
2340 Toilet 12w 23 Apr 18 18 Jul 18 2340
2341 1st Fix Wall with Head tracks 1w 23 Apr 18 30 Apr 18 2341

2342 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 May 18 30 May 18 2342
2343 Fix Pocket Doors 1w 01 May 18 08 May 18 2343

2344 Inspection and Ceiling Grid Clearance 31 May 18 31 May 18 2344


2345 2nd Fix wall 1w 31 May 18 06 Jun 18 2345
2346 IPS Frame (Box Out only) incl. Backing ply 3d 07 Jun 18 11 Jun 18 2346

2347 Screed 2d 12 Jun 18 13 Jun 18 2347


2348 Fix Ceiling Grid Works 3d 14 Jun 18 18 Jun 18 2348

2349 Floor Tiling Works 3d 19 Jun 18 21 Jun 18 2349

2350 Wall Tiling works incl. IPS Panels 3d 22 Jun 18 26 Jun 18 2350

2351 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 27 Jun 18 04 Jul 18 2351

2352 Mark and Cut openings for MEP on walls including Ceiling 2d 05 Jul 18 06 Jul 18 2352
2353 Install Vanity Tops 4d 05 Jul 18 10 Jul 18 2353
2354 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 09 Jul 18 12 Jul 18 2354
2355 Fix MEP Final Fixtures 3d 12 Jul 18 16 Jul 18 2355
2356 Final Coat Paint on Ceiling 2d 17 Jul 18 18 Jul 18 2356
2357 Lobby 8w 3d 01 May 18 02 Jul 18 2357
2358 1st Fix Wall with Head tracks 1w 01 May 18 08 May 18 2358
2359 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 2359
2360 Fix Ceiling Grid 3d 07 Jun 18 11 Jun 18 2360
2361 Paint 1st Coat 2d 12 Jun 18 13 Jun 18 2361
2362 Fix doors incl. Ironmongery 2d 14 Jun 18 15 Jun 18 2362
2363 Mark and Cut openings for MEP on walls 2d 18 Jun 18 19 Jun 18 2363
2364 Install Ceiling Tiles 3d 20 Jun 18 22 Jun 18 2364
2365 Fix MEP Final Fixtures 3d 25 Jun 18 27 Jun 18 2365
2366 Final Coat Paint on walls and ceiling 3d 28 Jun 18 02 Jul 18 2366

2367 Staircase Level 05 - CORE 02 2w 1d 25 May 18 11 Jun 18 2367


2368 H/L Electrical Containment & Conduits - 1st Fix 2d 25 May 18 29 May 18 2368
2369 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 30 May 18 31 May 18 2369

2370 Ceiling Rose fixing 1d 01 Jun 18 01 Jun 18 2370


2371 First Coat Paint on Walls & Ceiliings 2d 04 Jun 18 05 Jun 18 2371

2372 MEP Final Fixtures on Wall & Ceilings 2d 06 Jun 18 07 Jun 18 2372
2373 Final Coat Paint on walls & Ceilings 2d 08 Jun 18 11 Jun 18 2373

2374 Level 06 - CORE 02 12w 09 May 18 01 Aug 18 2374


2375 Toilet 12w 09 May 18 01 Aug 18 2375
2376 1st Fix Wall with Head tracks 1w 09 May 18 15 May 18 2376

2377 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 2377
2378 Fix Pocket Doors 1w 16 May 18 22 May 18 2378
2379 Inspection and Ceiling Grid Clearance 14 Jun 18 14 Jun 18 2379
2380 2nd Fix wall 1w 14 Jun 18 20 Jun 18 2380
2381 IPS Frame (Box Out only) incl. Backing ply 3d 21 Jun 18 25 Jun 18 2381
2382 Screed 2d 26 Jun 18 27 Jun 18 2382
2383 Fix Ceiling Grid Works 3d 28 Jun 18 02 Jul 18 2383
2384 Floor Tiling Works 3d 03 Jul 18 05 Jul 18 2384
2385 Wall Tiling works incl. IPS Panels 3d 06 Jul 18 10 Jul 18 2385
2386 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 11 Jul 18 18 Jul 18 2386
2387 Mark and Cut openings for MEP on walls including Ceiling 2d 19 Jul 18 20 Jul 18 2387
2388 Install Vanity Tops 4d 19 Jul 18 24 Jul 18 2388
2389 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 23 Jul 18 26 Jul 18 2389
2390 Fix MEP Final Fixtures 3d 26 Jul 18 30 Jul 18 2390
2391 Final Coat Paint on Ceiling 2d 31 Jul 18 01 Aug 18 2391

2392 Lobby 8w 3d 16 May 18 16 Jul 18 2392


2393 1st Fix Wall with Head tracks 1w 16 May 18 22 May 18 2393
2394 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 2394
2395 Fix Ceiling Grid 3d 21 Jun 18 25 Jun 18 2395
2396 Paint 1st Coat 2d 26 Jun 18 27 Jun 18 2396

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2397 Fix doors incl. Ironmongery 2d 28 Jun 18 29 Jun 18 2397
2398 Mark and Cut openings for MEP on walls 2d 02 Jul 18 03 Jul 18 2398
2399 Install Ceiling Tiles 3d 04 Jul 18 06 Jul 18 2399
2400 Fix MEP Final Fixtures 3d 09 Jul 18 11 Jul 18 2400
2401 Final Coat Paint on walls and ceiling 3d 12 Jul 18 16 Jul 18 2401
2402 Staircase 5w 2d 11 Jun 18 17 Jul 18 2402
2403 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Jun 18 12 Jun 18 2403
2404 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Jun 18 14 Jun 18 2404
2405 Ceiling Rose fixing 1d 15 Jun 18 15 Jun 18 2405

2406 First Coat Paint on Walls & Ceiliings 2d 28 Jun 18 29 Jun 18 2406
2407 MEP Final Fixtures on Wall & Ceilings 2d 12 Jul 18 13 Jul 18 2407
2408 Final Coat Paint on walls & Ceilings 2d 16 Jul 18 17 Jul 18 2408

2409 Level GF - CORE 02 12w 23 May 18 15 Aug 18 2409


2410 Toilet 12w 23 May 18 15 Aug 18 2410
2411 1st Fix Wall with Head tracks 1w 23 May 18 30 May 18 2411

2412 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 31 May 18 27 Jun 18 2412
2413 Fix Pocket Doors 1w 31 May 18 06 Jun 18 2413
2414 Inspection and Ceiling Grid Clearance 28 Jun 18 28 Jun 18 2414
2415 2nd Fix wall 1w 28 Jun 18 04 Jul 18 2415
2416 IPS Frame (Box Out only) incl. Backing ply 3d 05 Jul 18 09 Jul 18 2416
2417 Screed 2d 10 Jul 18 11 Jul 18 2417
2418 Fix Ceiling Grid Works 3d 12 Jul 18 16 Jul 18 2418
2419 Floor Tiling Works 3d 17 Jul 18 19 Jul 18 2419
2420 Wall Tiling works incl. IPS Panels 3d 20 Jul 18 24 Jul 18 2420
2421 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 25 Jul 18 01 Aug 18 2421
2422 Mark and Cut openings for MEP on walls including Ceiling 2d 02 Aug 18 03 Aug 18 2422
2423 Install Vanity Tops 4d 02 Aug 18 07 Aug 18 2423
2424 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 06 Aug 18 09 Aug 18 2424
2425 Fix MEP Final Fixtures 3d 09 Aug 18 13 Aug 18 2425
2426 Final Coat Paint on Ceiling 2d 14 Aug 18 15 Aug 18 2426
2427 Lobby 8w 3d 31 May 18 30 Jul 18 2427
2428 1st Fix Wall with Head tracks 1w 31 May 18 06 Jun 18 2428
2429 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 07 Jun 18 04 Jul 18 2429
2430 Fix Ceiling Grid 3d 05 Jul 18 09 Jul 18 2430
2431 Paint 1st Coat 2d 10 Jul 18 11 Jul 18 2431
2432 Fix doors incl. Ironmongery 2d 12 Jul 18 13 Jul 18 2432
2433 Mark and Cut openings for MEP on walls 2d 16 Jul 18 17 Jul 18 2433
2434 Install Ceiling Tiles 3d 18 Jul 18 20 Jul 18 2434
2435 Fix MEP Final Fixtures 3d 23 Jul 18 25 Jul 18 2435
2436 Final Coat Paint on walls and ceiling 3d 26 Jul 18 30 Jul 18 2436
2437 Staircase 5w 2d 25 Jun 18 31 Jul 18 2437

2438 H/L Electrical Containment & Conduits - 1st Fix 2d 25 Jun 18 26 Jun 18 2438

2439 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 27 Jun 18 28 Jun 18 2439

2440 Ceiling Rose fixing 1d 29 Jun 18 29 Jun 18 2440

2441 First Coat Paint on Walls & Ceiliings 2d 12 Jul 18 13 Jul 18 2441

2442 MEP Final Fixtures on Wall & Ceilings 2d 26 Jul 18 27 Jul 18 2442
2443 Final Coat Paint on walls & Ceilings 2d 30 Jul 18 31 Jul 18 2443

2444 Staircase Flooring incl. Nosing 4w 26 Oct 18 22 Nov 18 2444

2445 Groundfloor BOH areas 12w 12 Feb 18 10 May 18 2445

2446 Groundfloor refuse room cladding 2w 19 Mar 18 03 Apr 18 2446

2447 Latest Date for ABP/WTP to omit Cat A Shell and Core Fit-out scope of works to Building 8A 28 Nov 17 28 Nov 17 2447

2448 Cat A Fit Out 48w 4d 29 Nov 17 22 Nov 18 2448

2449 Ground Floor Units 2 and 3 4w 3d 22 Mar 18 25 Apr 18 2449

2450 Install conduit to cleaners sockets to core walls 3d 22 Mar 18 26 Mar 18 2450

2451 Boarding and Insulation to external and core walls 1w 27 Mar 18 04 Apr 18 2451

2452 Install wiring to containment in ceilings 1w 05 Apr 18 11 Apr 18 2452

2453 Taping and Jointing to Walls 2d 05 Apr 18 06 Apr 18 2453

2454 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 12 Apr 18 18 Apr 18 2454

2455 Install Joinery incl Doors 1w 19 Apr 18 25 Apr 18 2455

2456 Decoration 1w 13 Apr 18 20 Apr 18 2456

2457 Fit-out First Floor 6w 1d 05 Apr 18 21 May 18 2457

2458 Units 1 and 2 5w 05 Apr 18 11 May 18 2458

2459 Install conduit to cleaners sockets to core walls 3d 05 Apr 18 09 Apr 18 2459

2460 Boarding and Insulation to external walls 1w 10 Apr 18 16 Apr 18 2460

2461 Install wiring to containment in ceilings 1w 19 Apr 18 25 Apr 18 2461

2462 Taping and Jointing to Walls 2d 17 Apr 18 18 Apr 18 2462

2463 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 26 Apr 18 03 May 18 2463

2464 Install Joinery incl Doors 1w 04 May 18 11 May 18 2464

2465 Decoration 1w 30 Apr 18 08 May 18 2465

2466 Units 3 and 4 4w 3d 17 Apr 18 21 May 18 2466

2467 Install conduit to cleaners sockets to core walls 3d 17 Apr 18 19 Apr 18 2467

2468 Boarding and Insulation to external and core walls 1w 20 Apr 18 26 Apr 18 2468

2469 Install wiring to containment in ceilings 1w 30 Apr 18 04 May 18 2469

2470 Taping and Jointing to Walls 3d 30 Apr 18 02 May 18 2470

2471 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 08 May 18 14 May 18 2471

2472 Install Joinery incl Doors 1w 15 May 18 21 May 18 2472

2473 Decoration 1w 09 May 18 16 May 18 2473

2474 High Level Services First Floor 8w 29 Nov 17 01 Feb 18 2474

2475 Fit-out Second Floor 6w 1d 19 Apr 18 05 Jun 18 2475

2476 Units 1 and 2 4w 3d 19 Apr 18 23 May 18 2476

2477 Install conduit to cleaners sockets to core walls 3d 19 Apr 18 23 Apr 18 2477

2478 Boarding and Insulation to external and core walls 1w 24 Apr 18 01 May 18 2478

2479 Install wiring to containment in ceilings 1w 02 May 18 09 May 18 2479

2480 Taping and Jointing to Walls 2d 02 May 18 03 May 18 2480

2481 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 10 May 18 16 May 18 2481

2482 Install Joinery incl Doors 1w 17 May 18 23 May 18 2482

2483 Decoration 1w 11 May 18 18 May 18 2483

2484 Units 3 and 4 4w 3d 02 May 18 05 Jun 18 2484

2485 Install conduit to cleaners sockets to core walls 3d 02 May 18 04 May 18 2485

2486 Boarding and Insulation to external and core walls 1w 08 May 18 14 May 18 2486

2487 Install wiring to containment in ceilings 1w 15 May 18 21 May 18 2487

2488 Taping and Jointing to Walls 2d 15 May 18 16 May 18 2488

2489 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 22 May 18 29 May 18 2489

2490 Install Joinery incl Doors 1w 30 May 18 05 Jun 18 2490

2491 Decoration 1w 23 May 18 31 May 18 2491

2492 High Level Services Second Floor 8w 13 Dec 17 15 Feb 18 2492

2493 Fit-out Third Floor 6w 1d 04 May 18 19 Jun 18 2493

2494 Units 1 and 2 4w 3d 04 May 18 07 Jun 18 2494

2495 Install conduit to cleaners sockets to core walls 3d 04 May 18 09 May 18 2495

2496 Boarding and Insulation to external and core walls 1w 10 May 18 16 May 18 2496

2497 Install wiring to containment in ceilings 1w 17 May 18 23 May 18 2497

2498 Taping and Jointing to Walls 2d 17 May 18 18 May 18 2498

2499 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 24 May 18 31 May 18 2499

2500 Install Joinery incl Doors 1w 01 Jun 18 07 Jun 18 2500

2501 Decoration 1w 25 May 18 04 Jun 18 2501

2502 Units 3 and 4 4w 3d 17 May 18 19 Jun 18 2502

2503 Install conduit to cleaners sockets to core walls 3d 17 May 18 21 May 18 2503

2504 Boarding and Insulation to external and core walls 1w 22 May 18 29 May 18 2504

2505 Install wiring to containment in ceilings 1w 30 May 18 05 Jun 18 2505

2506 Taping and Jointing to Walls 2d 30 May 18 31 May 18 2506

2507 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 06 Jun 18 12 Jun 18 2507

Install Joinery incl Doors


2508 Install Joinery incl Doors 1w 13 Jun 18 19 Jun 18 2508

2509 Decoration 1w 07 Jun 18 14 Jun 18 2509

2510 High Level Services Third Floor 8w 05 Jan 18 01 Mar 18 2510

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2511 Fit-out Fourth Floor 6w 1d 21 May 18 03 Jul 18 2511

2512 Units 1 and 2 4w 3d 21 May 18 21 Jun 18 2512

2513 Install conduit to cleaners sockets to core walls 3d 21 May 18 23 May 18 2513

2514 Boarding and Insulation to external and core walls 1w 24 May 18 31 May 18 2514

2515 Install wiring to containment in ceilings 1w 01 Jun 18 07 Jun 18 2515

2516 Taping and Jointing to Walls 2d 01 Jun 18 04 Jun 18 2516

2517 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 08 Jun 18 14 Jun 18 2517

2518 Install Joinery incl Doors 1w 15 Jun 18 21 Jun 18 2518

2519 Decoration 1w 11 Jun 18 18 Jun 18 2519

2520 Units 3 and 4 4w 3d 01 Jun 18 03 Jul 18 2520

2521 Install conduit to cleaners sockets to core walls 3d 01 Jun 18 05 Jun 18 2521

2522 Boarding and Insulation to external and core walls 1w 06 Jun 18 12 Jun 18 2522

2523 Install wiring to containment in ceilings 1w 13 Jun 18 19 Jun 18 2523

2524 Taping and Jointing to Walls 2d 13 Jun 18 14 Jun 18 2524

2525 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 20 Jun 18 26 Jun 18 2525

2526 Install Joinery incl Doors 1w 27 Jun 18 03 Jul 18 2526

2527 Decoration 1w 21 Jun 18 28 Jun 18 2527

2528 High Level Services Fourth Floor 8w 19 Jan 18 15 Mar 18 2528

2529 Fit-out Fifth Floor 6w 1d 05 Jun 18 17 Jul 18 2529

2530 Units 1 and 2 4w 3d 05 Jun 18 05 Jul 18 2530

2531 Install conduit to cleaners sockets to core walls 3d 05 Jun 18 07 Jun 18 2531

2532 Boarding and Insulation to external and core walls 1w 08 Jun 18 14 Jun 18 2532

2533 Install wiring to containment in ceilings 1w 15 Jun 18 21 Jun 18 2533

2534 Taping and Jointing to Walls 2d 15 Jun 18 18 Jun 18 2534

2535 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 22 Jun 18 28 Jun 18 2535

2536 Install Joinery incl Doors 1w 29 Jun 18 05 Jul 18 2536

2537 Decoration 1w 25 Jun 18 02 Jul 18 2537

2538 Units 3 and 4 4w 3d 15 Jun 18 17 Jul 18 2538

2539 Install conduit to cleaners sockets to core walls 3d 15 Jun 18 19 Jun 18 2539

2540 Boarding and Insulation to external and core walls 1w 20 Jun 18 26 Jun 18 2540

2541 Install wiring to containment in ceilings 1w 27 Jun 18 03 Jul 18 2541

2542 Taping and Jointing to Walls 2d 27 Jun 18 28 Jun 18 2542

2543 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 04 Jul 18 10 Jul 18 2543

2544 Install Joinery incl Doors 1w 11 Jul 18 17 Jul 18 2544

2545 Decoration 1w 05 Jul 18 12 Jul 18 2545

2546 High Level Services Fifth Floor 8w 02 Feb 18 29 Mar 18 2546

2547 Fit-out Sixth Floor 6w 1d 19 Jun 18 31 Jul 18 2547

2548 Units 1 and 2 4w 3d 19 Jun 18 19 Jul 18 2548

2549 Install conduit to cleaners sockets to core walls 3d 19 Jun 18 21 Jun 18 2549

2550 Boarding and Insulation to external and core walls 1w 22 Jun 18 28 Jun 18 2550

2551 Install wiring to containment in ceilings 1w 29 Jun 18 05 Jul 18 2551

2552 Taping and Jointing to Walls 2d 29 Jun 18 02 Jul 18 2552

2553 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 06 Jul 18 12 Jul 18 2553

2554 Install Joinery incl Doors 1w 13 Jul 18 19 Jul 18 2554

2555 Decoration 1w 09 Jul 18 16 Jul 18 2555

2556 Units 3 and 4 4w 3d 29 Jun 18 31 Jul 18 2556

2557 Install conduit to cleaners sockets to core walls 3d 29 Jun 18 03 Jul 18 2557

2558 Boarding and Insulation to external and core walls 1w 04 Jul 18 10 Jul 18 2558

2559 Install wiring to containment in ceilings 1w 11 Jul 18 17 Jul 18 2559

2560 Taping and Jointing to Walls 2d 11 Jul 18 12 Jul 18 2560

2561 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 18 Jul 18 24 Jul 18 2561

2562 Install Joinery incl Doors 1w 25 Jul 18 31 Jul 18 2562

2563 Decoration 1w 19 Jul 18 26 Jul 18 2563

2564 High Level Services Sixth Floor 8w 16 Feb 18 16 Apr 18 2564

2565 Temporary Access Closure - Cat A Fit Out 2w 2d 01 Aug 18 16 Aug 18 2565

2566 Fit out First Floor 2d 15 Aug 18 16 Aug 18 2566

2567 Partition closure 2d 15 Aug 18 16 Aug 18 2567

2568 Fit out Second Floor 2d 13 Aug 18 14 Aug 18 2568

2569 Partition closure 2d 13 Aug 18 14 Aug 18 2569

2570 Fit out Third Floor 2d 09 Aug 18 10 Aug 18 2570

2571 Partition closure 2d 09 Aug 18 10 Aug 18 2571

2572 Fit out Fourth Floor 2d 07 Aug 18 08 Aug 18 2572

2573 Partition closure 2d 07 Aug 18 08 Aug 18 2573

2574 Fit out Fifth Floor 2d 03 Aug 18 06 Aug 18 2574

2575 Partition closure 2d 03 Aug 18 06 Aug 18 2575

2576 Fit out Sixth Floor 2d 01 Aug 18 02 Aug 18 2576

2577 Partition closure 2d 01 Aug 18 02 Aug 18 2577

2578 Prepare to Hand Over Units 1 & 2 6w 2d 03 Oct 18 15 Nov 18 2578

2579 Ground floor 2w 4d 03 Oct 18 22 Oct 18 2579

2580 Complete Ceiling Tiles 1w 03 Oct 18 09 Oct 18 2580

2581 Install Raised Access Floor incl Below Floor Barriers 1w 10 Oct 18 16 Oct 18 2581

2582 Soft Floor Coverings 4d 17 Oct 18 22 Oct 18 2582

2583 First floor 2w 4d 08 Oct 18 26 Oct 18 2583

2584 Complete Ceiling Tiles 1w 08 Oct 18 15 Oct 18 2584

2585 Install Raised Access Floor incl Below Floor Barriers 1w 15 Oct 18 22 Oct 18 2585

2586 Soft Floor Coverings 4d 22 Oct 18 26 Oct 18 2586

2587 Second Floor 2w 4d 11 Oct 18 31 Oct 18 2587

2588 Complete Ceiling Tiles 1w 11 Oct 18 18 Oct 18 2588

2589 Install Raised Access Floor incl Below Floor Barriers 1w 18 Oct 18 25 Oct 18 2589

2590 Soft Floor Coverings 4d 25 Oct 18 31 Oct 18 2590

2591 Third Floor 2w 4d 16 Oct 18 05 Nov 18 2591

2592 Complete Ceiling Tiles 1w 16 Oct 18 23 Oct 18 2592

2593 Install Raised Access Floor incl Below Floor Barriers 1w 23 Oct 18 30 Oct 18 2593

2594 Soft Floor Coverings 4d 30 Oct 18 05 Nov 18 2594

2595 Fourth Floor 2w 4d 19 Oct 18 08 Nov 18 2595

2596 Complete Ceiling Tiles 1w 19 Oct 18 26 Oct 18 2596

2597 Install Raised Access Floor incl Below Floor Barriers 1w 26 Oct 18 02 Nov 18 2597

2598 Soft Floor Coverings 4d 02 Nov 18 08 Nov 18 2598

2599 Fifth Floor 2w 4d 24 Oct 18 13 Nov 18 2599

2600 Complete Ceiling Tiles 1w 24 Oct 18 31 Oct 18 2600

2601 Install Raised Access Floor incl Below Floor Barriers 1w 31 Oct 18 07 Nov 18 2601

2602 Soft Floor Coverings 4d 07 Nov 18 13 Nov 18 2602

2603 Sixth Floor 2w 4d 29 Oct 18 15 Nov 18 2603

2604 Complete Ceiling Tiles 1w 29 Oct 18 02 Nov 18 2604

2605 Install Raised Access Floor incl Below Floor Barriers 1w 05 Nov 18 09 Nov 18 2605

2606 Soft Floor Coverings 4d 12 Nov 18 15 Nov 18 2606

2607 Prepare to Hand Over Units 3 & 4 6w 2d 10 Oct 18 22 Nov 18 2607

2608 Ground Floor 2w 4d 10 Oct 18 29 Oct 18 2608

2609 Complete Ceiling Tiles 1w 10 Oct 18 16 Oct 18 2609

2610 Install Raised Access Floor incl Below Floor Barriers 1w 17 Oct 18 23 Oct 18 2610

2611 Soft Floor Coverings 4d 24 Oct 18 29 Oct 18 2611

2612 First Floor 2w 4d 15 Oct 18 01 Nov 18 2612

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2613 Complete Ceiling Tiles 1w 15 Oct 18 19 Oct 18 2613

2614 Install Raised Access Floor incl Below Floor Barriers 1w 22 Oct 18 26 Oct 18 2614

2615 Soft Floor Coverings 4d 29 Oct 18 01 Nov 18 2615

2616 Second Floor 2w 4d 18 Oct 18 06 Nov 18 2616

2617 Complete Ceiling Tiles 1w 18 Oct 18 24 Oct 18 2617

2618 Install Raised Access Floor incl Below Floor Barriers 1w 25 Oct 18 31 Oct 18 2618

2619 Soft Floor Coverings 4d 01 Nov 18 06 Nov 18 2619

2620 Third Floor 2w 4d 23 Oct 18 09 Nov 18 2620

2621 Complete Ceiling Tiles 1w 23 Oct 18 29 Oct 18 2621

2622 Install Raised Access Floor incl Below Floor Barriers 1w 30 Oct 18 05 Nov 18 2622

2623 Soft Floor Coverings 4d 06 Nov 18 09 Nov 18 2623

2624 Fourth Floor 2w 4d 26 Oct 18 14 Nov 18 2624

2625 Complete Ceiling Tiles 1w 26 Oct 18 01 Nov 18 2625

2626 Install Raised Access Floor incl Below Floor Barriers 1w 02 Nov 18 08 Nov 18 2626

2627 Soft Floor Coverings 4d 09 Nov 18 14 Nov 18 2627

2628 Fifth Floor 2w 4d 31 Oct 18 19 Nov 18 2628

2629 Complete Ceiling Tiles 1w 31 Oct 18 06 Nov 18 2629

2630 Install Raised Access Floor incl Below Floor Barriers 1w 07 Nov 18 13 Nov 18 2630

2631 Soft Floor Coverings 4d 14 Nov 18 19 Nov 18 2631

2632 Sixth Floor 2w 4d 05 Nov 18 22 Nov 18 2632

2633 Complete Ceiling Tiles 1w 05 Nov 18 09 Nov 18 2633

2634 Install Raised Access Floor incl Below Floor Barriers 1w 12 Nov 18 16 Nov 18 2634

2635 Soft Floor Coverings 4d 19 Nov 18 22 Nov 18 2635

2636 Building 8A Complete 01 Feb 19 01 Feb 19 2636

2637 Building 8B 82w 4d 26 Apr 17 18 Dec 18 2637

2638 Piling 7w 4d 26 Apr 17 21 Jun 17 2638

2639 Lay Pile Mat 2w 26 Apr 17 10 May 17 2639

2640 Lay Crane Mat 2w 08 May 17 19 May 17 2640

2641 Test and confirm Piling Mat Compliance with requirements 2d 11 May 17 12 May 17 2641
2642 Handover to Keltbray 1d 15 May 17 15 May 17 2642

2643 Piling rig set up on site 3d 16 May 17 18 May 17 2643

2644 Piling 4w 3d 19 May 17 21 Jun 17 2644

2645 Structure - 8B 23w 1d 26 Jun 17 05 Dec 17 2645

2646 Substructure 11w 4d 26 Jun 17 15 Sep 17 2646

2647 Core 1 5w 3d 26 Jun 17 02 Aug 17 2647


2648 Excavation 4w 26 Jun 17 21 Jul 17 2648
2649 Break Down Piles 4w 28 Jun 17 25 Jul 17 2649

2650 FRC Base of Cap 4w 3d 03 Jul 17 02 Aug 17 2650

2651 Core 2 7w 29 Jun 17 16 Aug 17 2651


2652 Excavation 5w 29 Jun 17 02 Aug 17 2652
2653 Break Down Piles 6w 03 Jul 17 11 Aug 17 2653
2654 FRC Base of Cap 6w 06 Jul 17 16 Aug 17 2654

2655 Core 3 5w 24 Jul 17 25 Aug 17 2655


2656 Excavation 3w 3d 24 Jul 17 16 Aug 17 2656
2657 Break Down Piles 4w 26 Jul 17 22 Aug 17 2657
2658 FRC Base of Cap 4w 31 Jul 17 25 Aug 17 2658

2659 General Pile Caps 5w 4d 24 Jul 17 01 Sep 17 2659


2660 Excavation 3w 24 Jul 17 11 Aug 17 2660
2661 Break Down Piles 3w 2d 26 Jul 17 17 Aug 17 2661
2662 FRC Base of Cap 5w 1d 27 Jul 17 01 Sep 17 2662

2663 Groundfloor Slab 6w 1d 03 Aug 17 15 Sep 17 2663


2664 Pour 01 2w 03 Aug 17 16 Aug 17 2664

2665 Pour 02 2w 17 Aug 17 31 Aug 17 2665


2666 Pour 03 2w 04 Sep 17 15 Sep 17 2666
2667 Superstructure 15w 3d 17 Aug 17 05 Dec 17 2667
2668 STAND PRECAST CORE WALLS GND - 1ST FLOOR 1w 1d 17 Aug 17 19 Sep 17 2668
2669 STAND PRECAST COLUMNS GROUND - 1ST FLOOR 5w 18 Aug 17 22 Sep 17 2669

2670 FRC 1ST FLOOR SLAB 4w 3d 25 Aug 17 27 Sep 17 2670


2671 STAND PRECAST CORE WALLS 1ST - 2ND FLOOR 1w 1d 06 Sep 17 29 Sep 17 2671

2672 STAND PRECAST COLUMNS 1ST - 2ND FLOOR 4w 2d 05 Sep 17 04 Oct 17 2672
2673 FRC 2ND FLOOR SLAB 4w 12 Sep 17 09 Oct 17 2673
2674 STAND PRECAST WALLS 2ND - 3RD FLOOR 1w 1d 20 Sep 17 17 Oct 17 2674
2675 STAND PRECAST COLUMNS 2ND - 3RD FLOOR 3w 1d 21 Sep 17 17 Oct 17 2675
2676 FRC 3RD FLOOR SLAB 2w 4d 02 Oct 17 25 Oct 17 2676
2677 STAND PRECAST CORE WALLS 3RD - 4TH FLOOR 1w 1d 09 Oct 17 27 Oct 17 2677
2678 STAND PRECAST COLUMNS 3RD - 4TH FLOOR 2w 2d 10 Oct 17 27 Oct 17 2678
2679 FRC 4TH FLOOR SLAB 3w 2d 05 Oct 17 03 Nov 17 2679
2680 STAND PRECAST CORE WALLS 4TH - 5TH FLOOR 1w 1d 24 Oct 17 07 Nov 17 2680
2681 STAND PRECAST COLUMNS 4TH - 5TH FLOOR 2w 1d 24 Oct 17 07 Nov 17 2681
2682 FRC 5TH FLOOR SLAB 3w 3d 26 Oct 17 20 Nov 17 2682
2683 STAND PRECAST WALLS 5TH - ROOF 1w 1d 06 Nov 17 22 Nov 17 2683
2684 STAND PRECAST COLUMNS 5TH - ROOF 2w 3d 06 Nov 17 22 Nov 17 2684
2685 FRC ROOF SLAB 3w 3d 06 Nov 17 29 Nov 17 2685
2686 STAND PRECAST CORE WALL OVERRUNS 1w 1d 15 Nov 17 01 Dec 17 2686

2687 FRC CAPPING SLAB TO CORES 3w 15 Nov 17 05 Dec 17 2687


2688 FRC PERIMETER UPSTAND TO ROOF 2w 4d 16 Nov 17 05 Dec 17 2688
2689 Precast Stairs & Handrails 12w 14 Aug 17 13 Nov 17 2689

2690 Facades 39w 06 Dec 17 21 Sep 18 2690

2691 Pre-Cast Panels 6w 4d 06 Dec 17 31 Jan 18 2691


2692 North Elevation 2w 3d 06 Dec 17 22 Dec 17 2692

2693 Precast Cladding Panels North elevation Bay 1 3d 06 Dec 17 08 Dec 17 2693

2694 Precast Cladding Panels North elevation Bay 2 3d 11 Dec 17 13 Dec 17 2694

2695 Precast Cladding Panels North elevation Bay 3 3d 14 Dec 17 18 Dec 17 2695

2696 Precast Cladding Panels North elevation Bay 4 4d 19 Dec 17 22 Dec 17 2696

2697 Precast Cladding Panels West elevation 3d 03 Jan 18 05 Jan 18 2697

2698 South Elevation 2w 3d 08 Jan 18 24 Jan 18 2698

2699 Precast Cladding Panels South elevation Bay 1 3d 08 Jan 18 10 Jan 18 2699

2700 Precast Cladding Panels South elevation Bay 2 3d 11 Jan 18 15 Jan 18 2700

2701 Precast Cladding Panels South elevation Bay 3 3d 16 Jan 18 18 Jan 18 2701

2702 Precast Cladding Panels South elevation Bay 4 4d 19 Jan 18 24 Jan 18 2702

2703 Precast Cladding Panels East elevation 4d 25 Jan 18 30 Jan 18 2703

2704 Mastic Sealing externally 6w 1d 11 Dec 17 31 Jan 18 2704

2705 Bring in Crane Barge and Set up 1d 05 Jan 18 05 Jan 18 2705

2706 Windows 10w 08 Jan 18 16 Mar 18 2706


2707 Install SFS, Windows & Cladding Level 05 9w 08 Jan 18 09 Mar 18 2707

2708 Install SFS, Windows and Cladding Level 5 North 9w 08 Jan 18 09 Mar 18 2708

2709 Install ribbon window curtain walling to South Elevation 7w 19 Jan 18 08 Mar 18 2709

2710 Install SFS, Windows and Cladding Level 5 South East and West 6w 1d 25 Jan 18 08 Mar 18 2710
2711 Curtain Walling/ Doors Ground Floor 10w 08 Jan 18 16 Mar 18 2711

2712 Windows & Shopfronts at Ground 10w 08 Jan 18 16 Mar 18 2712

2713 External Doors & Louvres at Ground 3w 05 Feb 18 23 Feb 18 2713

2714 Complete ribbon windows after hoists removed 3w 04 Jun 18 22 Jun 18 2714
2715 Canopies 31w 2d 07 Feb 18 21 Sep 18 2715
2716 Install Frame for the Canopies 1w 07 Feb 18 13 Feb 18 2716
2717 Complete Frame & glazing for Canopies 1w 17 Sep 18 21 Sep 18 2717

2718 Roofing 13w 3d 06 Dec 17 20 Mar 18 2718

2719 Erect Terrace Balustrades 2w 06 Dec 17 19 Dec 17 2719

2720 Erect posts for Roof Louvres 2w 06 Dec 17 19 Dec 17 2720

2721 Terrace Slab Waterproofing 1w 2d 08 Jan 18 16 Jan 18 2721

2722 Roof Slab Waterproofing 6w 08 Jan 18 16 Feb 18 2722

2723 Roof Finishes to roof and terrace incl. Aluminum copings 5w 2d 29 Jan 18 06 Mar 18 2723

2724 Install Stair Core Roofing and cladding 5w 2d 22 Jan 18 27 Feb 18 2724
2725 Building 8B Temporary Weatherproof 22 Jan 18 22 Jan 18 2725

2726 Install Roof Louvres 3w 14 Feb 18 06 Mar 18 2726

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2727 Access ladders 2w 07 Mar 18 20 Mar 18 2727

2728 Latest Date for ABP/WTP to omit Cat A Shell and Core Services scope of works to Building 8B 28 Jul 17 28 Jul 17 2728

2729 M & E Installation 26w 2d 06 Nov 17 23 May 18 2729

2730 Riser Platform Installation 2w 06 Nov 17 01 Dec 17 2730

2731 Lift floor modules onto floors 1 - 3 1w 30 Nov 17 06 Dec 17 2731

2732 Lift floor modules onto floors 4 - 6 1w 07 Dec 17 13 Dec 17 2732

2733 Installation of Siphonic drainage 2w 06 Dec 17 19 Dec 17 2733

2734 Ground Floor Plant Installation 8B 11w 08 Jan 18 23 Mar 18 2734

2735 Lift Roof Plant to roof 8B 2w 16 Feb 18 01 Mar 18 2735

2736 Install roof plant and connect to risers 11w 02 Mar 18 23 May 18 2736

2737 Blockwork 29w 3d 06 Nov 17 15 Jun 18 2737

2738 Main works 8w 3d 06 Nov 17 12 Jan 18 2738

2739 Blockwork Walls at Ground 3w 06 Nov 17 24 Nov 17 2739

2740 Blockwork Walls at L1 1w 09 Nov 17 15 Nov 17 2740

2741 Blockwork Walls at L2 1w 20 Nov 17 24 Nov 17 2741

2742 Blockwork Walls at L3 1w 05 Dec 17 11 Dec 17 2742

2743 Blockwork Walls at L4 1w 14 Dec 17 20 Dec 17 2743

2744 Blockwork Walls at L5 1w 08 Jan 18 12 Jan 18 2744

2745 Return Visit 2w 04 Jun 18 15 Jun 18 2745

2746 Level 05 2d 04 Jun 18 05 Jun 18 2746

2747 Level 04 2d 06 Jun 18 07 Jun 18 2747

2748 Level 03 2d 08 Jun 18 11 Jun 18 2748

2749 Level 02 2d 12 Jun 18 13 Jun 18 2749

2750 Level 01 2d 14 Jun 18 15 Jun 18 2750

2751 Hoist 20w 3d 03 Jan 18 01 Jun 18 2751

2752 Window for Cantidecks to load out upper floor 2w 03 Jan 18 16 Jan 18 2752
2753 Erect Hoist 2w 16 Jan 18 29 Jan 18 2753

2754 Hoist 1 14w 3d 14 Feb 18 01 Jun 18 2754

2755 Hoist 2 13w 1d 23 Feb 18 01 Jun 18 2755

2756 Lift /Toilet Core Fit Out 67w 2d 15 Aug 17 18 Dec 18 2756

2757 Lifts 67w 2d 15 Aug 17 18 Dec 18 2757

2758 Delivery of temporary lift doors 15 Aug 17 15 Aug 17 2758

2759 Lift 1 6w 19 Feb 18 03 Apr 18 2759

2760 Lift 1 Guides and doors 4w 19 Feb 18 16 Mar 18 2760

2761 Lift 1 Car 1w 19 Mar 18 23 Mar 18 2761

2762 Lift 1 Commission 1w 26 Mar 18 03 Apr 18 2762

2763 Lift 2 6w 19 Feb 18 03 Apr 18 2763

2764 Lift 2 Guides and doors 4w 19 Feb 18 16 Mar 18 2764

2765 Lift 2 Car 1w 19 Mar 18 23 Mar 18 2765

2766 Lift 2 Commission 1w 26 Mar 18 03 Apr 18 2766

2767 Hand back Lift 2 after builders beneficial use 21 Nov 18 21 Nov 18 2767
2768 Recommission Lift 2 2w 21 Nov 18 04 Dec 18 2768

2769 Lift 3 6w 19 Mar 18 02 May 18 2769

2770 Lift 3 Guides and doors 4w 19 Mar 18 17 Apr 18 2770

2771 Lift 3 Car 1w 18 Apr 18 24 Apr 18 2771

2772 Lift 3 Commission 1w 25 Apr 18 02 May 18 2772

2773 Lift 4 6w 19 Mar 18 02 May 18 2773

2774 Lift 4 Guides and doors 4w 19 Mar 18 17 Apr 18 2774

2775 Lift 4 Car 1w 18 Apr 18 24 Apr 18 2775

2776 Lift 4 Commission 1w 25 Apr 18 02 May 18 2776

2777 Hand back Lift 4 after builders beneficial use 28 Nov 18 28 Nov 18 2777
2778 Recommission Lift 4 2w 28 Nov 18 11 Dec 18 2778

2779 Lift 5 6w 18 Apr 18 01 Jun 18 2779

2780 Lift 5 Guides and doors 4w 18 Apr 18 17 May 18 2780

2781 Lift 5 Car 1w 18 May 18 24 May 18 2781

2782 Lift 5 Commission 1w 25 May 18 01 Jun 18 2782

2783 Lift 6 6w 18 Apr 18 01 Jun 18 2783

2784 Lift 6 Guides and doors 4w 18 Apr 18 17 May 18 2784

2785 Lift 6 Car 1w 18 May 18 24 May 18 2785

2786 Lift 6 Commission 1w 25 May 18 01 Jun 18 2786

2787 Hand back Lift 6 after builders beneficial use 05 Dec 18 05 Dec 18 2787

2788 Recommission Lift 6 2w 05 Dec 18 18 Dec 18 2788

2789 Toilet & Lobby 26w 4d 16 Jan 18 27 Jul 18 2789

2790 Level 01 - CORE 01 12w 16 Jan 18 11 Apr 18 2790

2791 Toilet 12w 16 Jan 18 11 Apr 18 2791


2792 Floor slab available 16 Jan 18 16 Jan 18 2792

2793 1st Fix Wall with Head tracks 1w 16 Jan 18 22 Jan 18 2793

2794 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 Jan 18 19 Feb 18 2794
2795 Fix Pocket Doors 1w 23 Jan 18 29 Jan 18 2795

2796 Inspection and Ceiling Grid Clearance 20 Feb 18 20 Feb 18 2796


2797 2nd Fix wall 1w 20 Feb 18 26 Feb 18 2797

2798 IPS Frame (Box Out only) incl. Backing ply 3d 27 Feb 18 01 Mar 18 2798

2799 Screed 2d 02 Mar 18 05 Mar 18 2799


2800 Fix Ceiling Grid Works 3d 06 Mar 18 08 Mar 18 2800

2801 Floor Tiling Works 3d 09 Mar 18 13 Mar 18 2801


2802 Wall Tiling works incl. IPS Panels 3d 14 Mar 18 16 Mar 18 2802

2803 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 19 Mar 18 26 Mar 18 2803
2804 Mark and Cut openings for MEP on walls including Ceiling 2d 27 Mar 18 28 Mar 18 2804
2805 Install Vanity Tops 4d 27 Mar 18 03 Apr 18 2805
2806 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 29 Mar 18 05 Apr 18 2806
2807 Fix MEP Final Fixtures 3d 05 Apr 18 09 Apr 18 2807
2808 Final Coat Paint on Ceiling 2d 10 Apr 18 11 Apr 18 2808
2809 Lobby 8w 3d 23 Jan 18 22 Mar 18 2809
2810 1st Fix Wall with Head tracks 1w 23 Jan 18 29 Jan 18 2810
2811 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 30 Jan 18 26 Feb 18 2811
2812 Fix Ceiling Grid 3d 27 Feb 18 01 Mar 18 2812
2813 Paint 1st Coat 2d 02 Mar 18 05 Mar 18 2813
2814 Fix doors incl. Ironmongery 2d 06 Mar 18 07 Mar 18 2814
2815 Mark and Cut openings for MEP on walls 2d 08 Mar 18 09 Mar 18 2815

2816 Install Ceiling Tiles 3d 12 Mar 18 14 Mar 18 2816

2817 Fix MEP Final Fixtures 3d 15 Mar 18 19 Mar 18 2817

2818 Final Coat Paint on walls and ceiling 3d 20 Mar 18 22 Mar 18 2818
2819 Staircase Level 01 - CORE 01 2w 1d 04 Apr 18 18 Apr 18 2819
2820 H/L Electrical Containment & Conduits - 1st Fix 2d 04 Apr 18 05 Apr 18 2820

2821 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 06 Apr 18 09 Apr 18 2821

2822 Ceiling Rose fixing 1d 10 Apr 18 10 Apr 18 2822

2823 First Coat Paint on Walls & Ceiliings 2d 11 Apr 18 12 Apr 18 2823

2824 MEP Final Fixtures on Wall & Ceilings 2d 13 Apr 18 16 Apr 18 2824
2825 Final Coat Paint on walls & Ceilings 2d 17 Apr 18 18 Apr 18 2825

2826 Level 02 - CORE 01 12w 30 Jan 18 25 Apr 18 2826

2827 Toilet 12w 30 Jan 18 25 Apr 18 2827


2828 1st Fix Wall with Head tracks 1w 30 Jan 18 05 Feb 18 2828
2829 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 06 Feb 18 05 Mar 18 2829
2830 Fix Pocket Doors 1w 06 Feb 18 12 Feb 18 2830
2831 Inspection and Ceiling Grid Clearance 06 Mar 18 06 Mar 18 2831
2832 2nd Fix wall 1w 06 Mar 18 12 Mar 18 2832
2833 IPS Frame (Box Out only) incl. Backing ply 3d 13 Mar 18 15 Mar 18 2833
2834 Screed 2d 16 Mar 18 19 Mar 18 2834
2835 Fix Ceiling Grid Works 3d 20 Mar 18 22 Mar 18 2835
2836 Floor Tiling Works 3d 23 Mar 18 27 Mar 18 2836
2837 Wall Tiling works incl. IPS Panels 3d 28 Mar 18 03 Apr 18 2837
2838 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 04 Apr 18 11 Apr 18 2838
2839 Mark and Cut openings for MEP on walls including Ceiling 2d 12 Apr 18 13 Apr 18 2839
2840 Install Vanity Tops 4d 12 Apr 18 17 Apr 18 2840
2841 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 16 Apr 18 19 Apr 18 2841

2842 Fix MEP Final Fixtures 3d 19 Apr 18 23 Apr 18 2842


2843 Final Coat Paint on Ceiling 2d 24 Apr 18 25 Apr 18 2843

2844 Lobby 8w 3d 06 Feb 18 09 Apr 18 2844

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2845 1st Fix Wall with Head tracks 1w 06 Feb 18 12 Feb 18 2845
2846 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 13 Feb 18 12 Mar 18 2846
2847 Fix Ceiling Grid 3d 13 Mar 18 15 Mar 18 2847
2848 Paint 1st Coat 2d 16 Mar 18 19 Mar 18 2848
2849 Fix doors incl. Ironmongery 2d 20 Mar 18 21 Mar 18 2849
2850 Mark and Cut openings for MEP on walls 2d 22 Mar 18 23 Mar 18 2850
2851 Install Ceiling Tiles 3d 26 Mar 18 28 Mar 18 2851
2852 Fix MEP Final Fixtures 3d 29 Mar 18 04 Apr 18 2852
2853 Final Coat Paint on walls and ceiling 3d 05 Apr 18 09 Apr 18 2853

2854 Staircase Level 02 - CORE 01 2w 1d 06 Apr 18 20 Apr 18 2854


2855 H/L Electrical Containment & Conduits - 1st Fix 2d 06 Apr 18 09 Apr 18 2855
2856 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 10 Apr 18 11 Apr 18 2856
2857 Ceiling Rose fixing 1d 12 Apr 18 12 Apr 18 2857
2858 First Coat Paint on Walls & Ceiliings 2d 13 Apr 18 16 Apr 18 2858
2859 MEP Final Fixtures on Wall & Ceilings 2d 17 Apr 18 18 Apr 18 2859
2860 Final Coat Paint on walls & Ceilings 2d 19 Apr 18 20 Apr 18 2860
2861 Level 03 - CORE 01 12w 13 Feb 18 11 May 18 2861

2862 Toilet 12w 13 Feb 18 11 May 18 2862


2863 1st Fix Wall with Head tracks 1w 13 Feb 18 19 Feb 18 2863
2864 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 20 Feb 18 19 Mar 18 2864

2865 Fix Pocket Doors 1w 20 Feb 18 26 Feb 18 2865


2866 Inspection and Ceiling Grid Clearance 20 Mar 18 20 Mar 18 2866
2867 2nd Fix wall 1w 20 Mar 18 26 Mar 18 2867
2868 IPS Frame (Box Out only) incl. Backing ply 3d 27 Mar 18 29 Mar 18 2868
2869 Screed 2d 03 Apr 18 04 Apr 18 2869
2870 Fix Ceiling Grid Works 3d 05 Apr 18 09 Apr 18 2870
2871 Floor Tiling Works 3d 10 Apr 18 12 Apr 18 2871
2872 Wall Tiling works incl. IPS Panels 3d 13 Apr 18 17 Apr 18 2872
2873 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 18 Apr 18 25 Apr 18 2873
2874 Mark and Cut openings for MEP on walls including Ceiling 2d 26 Apr 18 30 Apr 18 2874
2875 Install Vanity Tops 4d 26 Apr 18 02 May 18 2875
2876 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 01 May 18 04 May 18 2876
2877 Fix MEP Final Fixtures 3d 04 May 18 09 May 18 2877
2878 Final Coat Paint on Ceiling 2d 10 May 18 11 May 18 2878

2879 Lobby 8w 3d 20 Feb 18 23 Apr 18 2879

2880 1st Fix Wall with Head tracks 1w 20 Feb 18 26 Feb 18 2880

2881 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 27 Feb 18 26 Mar 18 2881

2882 Fix Ceiling Grid 3d 27 Mar 18 29 Mar 18 2882


2883 Paint 1st Coat 2d 03 Apr 18 04 Apr 18 2883

2884 Fix doors incl. Ironmongery 2d 05 Apr 18 06 Apr 18 2884


2885 Mark and Cut openings for MEP on walls 2d 09 Apr 18 10 Apr 18 2885

2886 Install Ceiling Tiles 3d 11 Apr 18 13 Apr 18 2886

2887 Fix MEP Final Fixtures 3d 16 Apr 18 18 Apr 18 2887

2888 Final Coat Paint on walls and ceiling 3d 19 Apr 18 23 Apr 18 2888
2889 Staircase Level 03 - CORE 01 5w 2d 15 Mar 18 24 Apr 18 2889
2890 H/L Electrical Containment & Conduits - 1st Fix 2d 15 Mar 18 16 Mar 18 2890
2891 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 19 Mar 18 20 Mar 18 2891
2892 Ceiling Rose fixing 1d 21 Mar 18 21 Mar 18 2892
2893 First Coat Paint on Walls & Ceiliings 2d 05 Apr 18 06 Apr 18 2893
2894 MEP Final Fixtures on Wall & Ceilings 2d 19 Apr 18 20 Apr 18 2894
2895 Final Coat Paint on walls & Ceilings 2d 23 Apr 18 24 Apr 18 2895
2896 Level 04 - CORE 01 12w 27 Feb 18 25 May 18 2896
2897 Toilet 12w 27 Feb 18 25 May 18 2897
2898 1st Fix Wall with Head tracks 1w 27 Feb 18 05 Mar 18 2898
2899 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 06 Mar 18 04 Apr 18 2899
2900 Fix Pocket Doors 1w 06 Mar 18 12 Mar 18 2900
2901 Inspection and Ceiling Grid Clearance 05 Apr 18 05 Apr 18 2901
2902 2nd Fix wall 1w 05 Apr 18 11 Apr 18 2902

2903 IPS Frame (Box Out only) incl. Backing ply 3d 12 Apr 18 16 Apr 18 2903
2904 Screed 2d 17 Apr 18 18 Apr 18 2904
2905 Fix Ceiling Grid Works 3d 19 Apr 18 23 Apr 18 2905
2906 Floor Tiling Works 3d 24 Apr 18 26 Apr 18 2906
2907 Wall Tiling works incl. IPS Panels 3d 30 Apr 18 02 May 18 2907
2908 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 03 May 18 11 May 18 2908
2909 Mark and Cut openings for MEP on walls including Ceiling 2d 14 May 18 15 May 18 2909
2910 Install Vanity Tops 4d 14 May 18 17 May 18 2910
2911 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 16 May 18 21 May 18 2911
2912 Fix MEP Final Fixtures 3d 21 May 18 23 May 18 2912

2913 Final Coat Paint on Ceiling 2d 24 May 18 25 May 18 2913


2914 Lobby 8w 3d 06 Mar 18 09 May 18 2914
2915 1st Fix Wall with Head tracks 1w 06 Mar 18 12 Mar 18 2915
2916 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 13 Mar 18 11 Apr 18 2916
2917 Fix Ceiling Grid 3d 12 Apr 18 16 Apr 18 2917
2918 Paint 1st Coat 2d 17 Apr 18 18 Apr 18 2918
2919 Fix doors incl. Ironmongery 2d 19 Apr 18 20 Apr 18 2919
2920 Mark and Cut openings for MEP on walls 2d 23 Apr 18 24 Apr 18 2920
2921 Install Ceiling Tiles 3d 25 Apr 18 30 Apr 18 2921
2922 Fix MEP Final Fixtures 3d 01 May 18 03 May 18 2922
2923 Final Coat Paint on walls and ceiling 3d 04 May 18 09 May 18 2923
2924 Staircase Level 04 - CORE 01 5w 2d 29 Mar 18 10 May 18 2924
2925 H/L Electrical Containment & Conduits - 1st Fix 2d 29 Mar 18 03 Apr 18 2925
2926 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 04 Apr 18 05 Apr 18 2926

2927 Ceiling Rose fixing 1d 06 Apr 18 06 Apr 18 2927


2928 First Coat Paint on Walls & Ceiliings 2d 19 Apr 18 20 Apr 18 2928

2929 MEP Final Fixtures on Wall & Ceilings 2d 04 May 18 08 May 18 2929
2930 Final Coat Paint on walls & Ceilings 2d 09 May 18 10 May 18 2930
2931 Level 05 - CORE 01 12w 13 Mar 18 11 Jun 18 2931

2932 Toilet 12w 13 Mar 18 11 Jun 18 2932


2933 1st Fix Wall with Head tracks 1w 13 Mar 18 19 Mar 18 2933

2934 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 20 Mar 18 18 Apr 18 2934

2935 Fix Pocket Doors 1w 20 Mar 18 26 Mar 18 2935

2936 Inspection and Ceiling Grid Clearance 19 Apr 18 19 Apr 18 2936

2937 2nd Fix wall 1w 19 Apr 18 25 Apr 18 2937


2938 IPS Frame (Box Out only) incl. Backing ply 3d 26 Apr 18 01 May 18 2938
2939 Screed 2d 02 May 18 03 May 18 2939
2940 Fix Ceiling Grid Works 3d 04 May 18 09 May 18 2940
2941 Floor Tiling Works 3d 10 May 18 14 May 18 2941
2942 Wall Tiling works incl. IPS Panels 3d 15 May 18 17 May 18 2942
2943 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 18 May 18 25 May 18 2943
2944 Mark and Cut openings for MEP on walls including Ceiling 2d 29 May 18 30 May 18 2944
2945 Install Vanity Tops 4d 29 May 18 01 Jun 18 2945
2946 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 31 May 18 05 Jun 18 2946
2947 Fix MEP Final Fixtures 3d 05 Jun 18 07 Jun 18 2947
2948 Final Coat Paint on Ceiling 2d 08 Jun 18 11 Jun 18 2948
2949 Lobby 8w 3d 20 Mar 18 23 May 18 2949
2950 1st Fix Wall with Head tracks 1w 20 Mar 18 26 Mar 18 2950
2951 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 27 Mar 18 25 Apr 18 2951

2952 Fix Ceiling Grid 3d 26 Apr 18 01 May 18 2952

2953 Paint 1st Coat 2d 02 May 18 03 May 18 2953


2954 Fix doors incl. Ironmongery 2d 04 May 18 08 May 18 2954

2955 Mark and Cut openings for MEP on walls 2d 09 May 18 10 May 18 2955
2956 Install Ceiling Tiles 3d 11 May 18 15 May 18 2956

2957 Fix MEP Final Fixtures 3d 16 May 18 18 May 18 2957


2958 Final Coat Paint on walls and ceiling 3d 21 May 18 23 May 18 2958

2959 Staircase Level 05 - CORE 01 5w 2d 16 Apr 18 24 May 18 2959


2960 H/L Electrical Containment & Conduits - 1st Fix 2d 16 Apr 18 17 Apr 18 2960
2961 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 18 Apr 18 19 Apr 18 2961

2962 Ceiling Rose fixing 1d 20 Apr 18 20 Apr 18 2962


2963 First Coat Paint on Walls & Ceiliings 2d 04 May 18 08 May 18 2963
2964 MEP Final Fixtures on Wall & Ceilings 2d 21 May 18 22 May 18 2964
2965 Final Coat Paint on walls & Ceilings 2d 23 May 18 24 May 18 2965
2966 Level GF - CORE 01 12w 27 Mar 18 25 Jun 18 2966
2967 Toilet 12w 27 Mar 18 25 Jun 18 2967
2968 1st Fix Wall with Head tracks 1w 27 Mar 18 04 Apr 18 2968
2969 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 05 Apr 18 03 May 18 2969
2970 Fix Pocket Doors 1w 05 Apr 18 11 Apr 18 2970
2971 Inspection and Ceiling Grid Clearance 04 May 18 04 May 18 2971
2972 2nd Fix wall 1w 04 May 18 11 May 18 2972
2973 IPS Frame (Box Out only) incl. Backing ply 3d 14 May 18 16 May 18 2973
2974 Screed 2d 17 May 18 18 May 18 2974

2975 Fix Ceiling Grid Works 3d 21 May 18 23 May 18 2975


2976 Floor Tiling Works 3d 24 May 18 29 May 18 2976

2977 Wall Tiling works incl. IPS Panels 3d 30 May 18 01 Jun 18 2977
2978 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 04 Jun 18 11 Jun 18 2978
2979 Mark and Cut openings for MEP on walls including Ceiling 2d 12 Jun 18 13 Jun 18 2979

2980 Install Vanity Tops 4d 12 Jun 18 15 Jun 18 2980


2981 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 14 Jun 18 19 Jun 18 2981

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2982 Fix MEP Final Fixtures 3d 19 Jun 18 21 Jun 18 2982
2983 Final Coat Paint on Ceiling 2d 22 Jun 18 25 Jun 18 2983
2984 Lobby 8w 3d 05 Apr 18 07 Jun 18 2984
2985 1st Fix Wall with Head tracks 1w 05 Apr 18 11 Apr 18 2985
2986 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 12 Apr 18 11 May 18 2986
2987 Fix Ceiling Grid 3d 14 May 18 16 May 18 2987
2988 Paint 1st Coat 2d 17 May 18 18 May 18 2988
2989 Fix doors incl. Ironmongery 2d 21 May 18 22 May 18 2989
2990 Mark and Cut openings for MEP on walls 2d 23 May 18 24 May 18 2990

2991 Install Ceiling Tiles 3d 25 May 18 30 May 18 2991

2992 Fix MEP Final Fixtures 3d 31 May 18 04 Jun 18 2992


2993 Final Coat Paint on walls and ceiling 3d 05 Jun 18 07 Jun 18 2993

2994 Staircase Level GF - CORE 01 5w 2d 01 May 18 08 Jun 18 2994


2995 H/L Electrical Containment & Conduits - 1st Fix 2d 01 May 18 02 May 18 2995
2996 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 03 May 18 04 May 18 2996

2997 Ceiling Rose fixing 1d 08 May 18 08 May 18 2997


2998 First Coat Paint on Walls & Ceiliings 2d 21 May 18 22 May 18 2998
2999 MEP Final Fixtures on Wall & Ceilings 2d 05 Jun 18 06 Jun 18 2999
3000 Final Coat Paint on walls & Ceilings 2d 07 Jun 18 08 Jun 18 3000

3001 Level 01 - CORE 02 12w 05 Feb 18 02 May 18 3001


3002 Toilet 12w 05 Feb 18 02 May 18 3002
3003 Floor slab available 05 Feb 18 05 Feb 18 3003
3004 1st Fix Wall with Head tracks 1w 05 Feb 18 09 Feb 18 3004
3005 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 12 Feb 18 09 Mar 18 3005
3006 Fix Pocket Doors 1w 12 Feb 18 16 Feb 18 3006
3007 Inspection and Ceiling Grid Clearance 12 Mar 18 12 Mar 18 3007
3008 2nd Fix wall 1w 12 Mar 18 16 Mar 18 3008
3009 IPS Frame (Box Out only) incl. Backing ply 3d 19 Mar 18 21 Mar 18 3009
3010 Screed 2d 22 Mar 18 23 Mar 18 3010
3011 Fix Ceiling Grid Works 3d 26 Mar 18 28 Mar 18 3011
3012 Floor Tiling Works 3d 29 Mar 18 04 Apr 18 3012

3013 Wall Tiling works incl. IPS Panels 3d 05 Apr 18 09 Apr 18 3013

3014 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 10 Apr 18 17 Apr 18 3014

3015 Mark and Cut openings for MEP on walls including Ceiling 2d 18 Apr 18 19 Apr 18 3015

3016 Install Vanity Tops 4d 18 Apr 18 23 Apr 18 3016


3017 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 20 Apr 18 25 Apr 18 3017

3018 Fix MEP Final Fixtures 3d 25 Apr 18 30 Apr 18 3018


3019 Final Coat Paint on Ceiling 2d 01 May 18 02 May 18 3019

3020 Lobby 8w 3d 12 Feb 18 13 Apr 18 3020

3021 1st Fix Wall with Head tracks 1w 12 Feb 18 16 Feb 18 3021

3022 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 19 Feb 18 16 Mar 18 3022

3023 Fix Ceiling Grid 3d 19 Mar 18 21 Mar 18 3023

3024 Paint 1st Coat 2d 22 Mar 18 23 Mar 18 3024


3025 Fix doors incl. Ironmongery 2d 26 Mar 18 27 Mar 18 3025
3026 Mark and Cut openings for MEP on walls 2d 28 Mar 18 29 Mar 18 3026
3027 Install Ceiling Tiles 3d 03 Apr 18 05 Apr 18 3027
3028 Fix MEP Final Fixtures 3d 06 Apr 18 10 Apr 18 3028
3029 Final Coat Paint on walls and ceiling 3d 11 Apr 18 13 Apr 18 3029
3030 Staircase Level 01 - CORE 02 5w 2d 07 Mar 18 16 Apr 18 3030
3031 H/L Electrical Containment & Conduits - 1st Fix 2d 07 Mar 18 08 Mar 18 3031
3032 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 09 Mar 18 12 Mar 18 3032
3033 Ceiling Rose fixing 1d 13 Mar 18 13 Mar 18 3033
3034 First Coat Paint on Walls & Ceiliings 2d 26 Mar 18 27 Mar 18 3034
3035 MEP Final Fixtures on Wall & Ceilings 2d 11 Apr 18 12 Apr 18 3035
3036 Final Coat Paint on walls & Ceilings 2d 13 Apr 18 16 Apr 18 3036

3037 Level 02 - CORE 02 12w 19 Feb 18 17 May 18 3037

3038 Toilet 12w 19 Feb 18 17 May 18 3038


3039 1st Fix Wall with Head tracks 1w 19 Feb 18 23 Feb 18 3039

3040 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 26 Feb 18 23 Mar 18 3040
3041 Fix Pocket Doors 1w 26 Feb 18 02 Mar 18 3041
3042 Inspection and Ceiling Grid Clearance 26 Mar 18 26 Mar 18 3042
3043 2nd Fix wall 1w 26 Mar 18 03 Apr 18 3043

3044 IPS Frame (Box Out only) incl. Backing ply 3d 04 Apr 18 06 Apr 18 3044
3045 Screed 2d 09 Apr 18 10 Apr 18 3045

3046 Fix Ceiling Grid Works 3d 11 Apr 18 13 Apr 18 3046

3047 Floor Tiling Works 3d 16 Apr 18 18 Apr 18 3047

3048 Wall Tiling works incl. IPS Panels 3d 19 Apr 18 23 Apr 18 3048
3049 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 24 Apr 18 02 May 18 3049
3050 Mark and Cut openings for MEP on walls including Ceiling 2d 03 May 18 04 May 18 3050
3051 Install Vanity Tops 4d 03 May 18 09 May 18 3051
3052 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 08 May 18 11 May 18 3052
3053 Fix MEP Final Fixtures 3d 11 May 18 15 May 18 3053
3054 Final Coat Paint on Ceiling 2d 16 May 18 17 May 18 3054
3055 Lobby 8w 3d 26 Feb 18 30 Apr 18 3055
3056 1st Fix Wall with Head tracks 1w 26 Feb 18 02 Mar 18 3056
3057 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 05 Mar 18 03 Apr 18 3057
3058 Fix Ceiling Grid 3d 04 Apr 18 06 Apr 18 3058
3059 Paint 1st Coat 2d 09 Apr 18 10 Apr 18 3059
3060 Fix doors incl. Ironmongery 2d 11 Apr 18 12 Apr 18 3060

3061 Mark and Cut openings for MEP on walls 2d 13 Apr 18 16 Apr 18 3061

3062 Install Ceiling Tiles 3d 17 Apr 18 19 Apr 18 3062

3063 Fix MEP Final Fixtures 3d 20 Apr 18 24 Apr 18 3063

3064 Final Coat Paint on walls and ceiling 3d 25 Apr 18 30 Apr 18 3064
3065 Staircase Level 02 - CORE 02 5w 2d 21 Mar 18 01 May 18 3065

3066 H/L Electrical Containment & Conduits - 1st Fix 2d 21 Mar 18 22 Mar 18 3066
3067 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 23 Mar 18 26 Mar 18 3067

3068 Ceiling Rose fixing 1d 27 Mar 18 27 Mar 18 3068

3069 First Coat Paint on Walls & Ceiliings 2d 11 Apr 18 12 Apr 18 3069

3070 MEP Final Fixtures on Wall & Ceilings 2d 25 Apr 18 26 Apr 18 3070

3071 Final Coat Paint on walls & Ceilings 2d 30 Apr 18 01 May 18 3071
3072 Level 03 - CORE 02 12w 05 Mar 18 01 Jun 18 3072
3073 Toilet 12w 05 Mar 18 01 Jun 18 3073
3074 1st Fix Wall with Head tracks 1w 05 Mar 18 09 Mar 18 3074
3075 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 12 Mar 18 10 Apr 18 3075
3076 Fix Pocket Doors 1w 12 Mar 18 16 Mar 18 3076
3077 Inspection and Ceiling Grid Clearance 11 Apr 18 11 Apr 18 3077
3078 2nd Fix wall 1w 11 Apr 18 17 Apr 18 3078
3079 IPS Frame (Box Out only) incl. Backing ply 3d 18 Apr 18 20 Apr 18 3079
3080 Screed 2d 23 Apr 18 24 Apr 18 3080
3081 Fix Ceiling Grid Works 3d 25 Apr 18 30 Apr 18 3081
3082 Floor Tiling Works 3d 01 May 18 03 May 18 3082
3083 Wall Tiling works incl. IPS Panels 3d 04 May 18 09 May 18 3083
3084 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 10 May 18 17 May 18 3084
3085 Mark and Cut openings for MEP on walls including Ceiling 2d 18 May 18 21 May 18 3085

3086 Install Vanity Tops 4d 18 May 18 23 May 18 3086

3087 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 22 May 18 25 May 18 3087
3088 Fix MEP Final Fixtures 3d 25 May 18 30 May 18 3088

3089 Final Coat Paint on Ceiling 2d 31 May 18 01 Jun 18 3089


3090 Lobby 8w 3d 12 Mar 18 15 May 18 3090

3091 1st Fix Wall with Head tracks 1w 12 Mar 18 16 Mar 18 3091
3092 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 19 Mar 18 17 Apr 18 3092

3093 Fix Ceiling Grid 3d 18 Apr 18 20 Apr 18 3093

3094 Paint 1st Coat 2d 23 Apr 18 24 Apr 18 3094


3095 Fix doors incl. Ironmongery 2d 25 Apr 18 26 Apr 18 3095

3096 Mark and Cut openings for MEP on walls 2d 30 Apr 18 01 May 18 3096

3097 Install Ceiling Tiles 3d 02 May 18 04 May 18 3097


3098 Fix MEP Final Fixtures 3d 08 May 18 10 May 18 3098
3099 Final Coat Paint on walls and ceiling 3d 11 May 18 15 May 18 3099
3100 Staircase 5w 2d 06 Apr 18 16 May 18 3100
3101 H/L Electrical Containment & Conduits - 1st Fix 2d 06 Apr 18 09 Apr 18 3101
3102 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 10 Apr 18 11 Apr 18 3102
3103 Ceiling Rose fixing 1d 12 Apr 18 12 Apr 18 3103
3104 First Coat Paint on Walls & Ceiliings 2d 25 Apr 18 26 Apr 18 3104
3105 MEP Final Fixtures on Wall & Ceilings 2d 11 May 18 14 May 18 3105
3106 Final Coat Paint on walls & Ceilings 2d 15 May 18 16 May 18 3106
3107 Level 04 - CORE 02 12w 19 Mar 18 15 Jun 18 3107
3108 Toilet 12w 19 Mar 18 15 Jun 18 3108
3109 1st Fix Wall with Head tracks 1w 19 Mar 18 23 Mar 18 3109
3110 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 26 Mar 18 24 Apr 18 3110

3111 Fix Pocket Doors 1w 26 Mar 18 03 Apr 18 3111


3112 Inspection and Ceiling Grid Clearance 25 Apr 18 25 Apr 18 3112
3113 2nd Fix wall 1w 25 Apr 18 02 May 18 3113

3114 IPS Frame (Box Out only) incl. Backing ply 3d 03 May 18 08 May 18 3114
3115 Screed 2d 09 May 18 10 May 18 3115

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3116 Fix Ceiling Grid Works 3d 11 May 18 15 May 18 3116
3117 Floor Tiling Works 3d 16 May 18 18 May 18 3117
3118 Wall Tiling works incl. IPS Panels 3d 21 May 18 23 May 18 3118
3119 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 24 May 18 01 Jun 18 3119
3120 Mark and Cut openings for MEP on walls including Ceiling 2d 04 Jun 18 05 Jun 18 3120
3121 Install Vanity Tops 4d 04 Jun 18 07 Jun 18 3121
3122 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 06 Jun 18 11 Jun 18 3122
3123 Fix MEP Final Fixtures 3d 11 Jun 18 13 Jun 18 3123
3124 Final Coat Paint on Ceiling 2d 14 Jun 18 15 Jun 18 3124

3125 Lobby 8w 3d 26 Mar 18 30 May 18 3125

3126 1st Fix Wall with Head tracks 1w 26 Mar 18 03 Apr 18 3126
3127 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 04 Apr 18 02 May 18 3127

3128 Fix Ceiling Grid 3d 03 May 18 08 May 18 3128

3129 Paint 1st Coat 2d 09 May 18 10 May 18 3129

3130 Fix doors incl. Ironmongery 2d 11 May 18 14 May 18 3130

3131 Mark and Cut openings for MEP on walls 2d 15 May 18 16 May 18 3131

3132 Install Ceiling Tiles 3d 17 May 18 21 May 18 3132

3133 Fix MEP Final Fixtures 3d 22 May 18 24 May 18 3133


3134 Final Coat Paint on walls and ceiling 3d 25 May 18 30 May 18 3134
3135 Staircase 5w 2d 20 Apr 18 31 May 18 3135
3136 H/L Electrical Containment & Conduits - 1st Fix 2d 20 Apr 18 23 Apr 18 3136
3137 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 24 Apr 18 25 Apr 18 3137
3138 Ceiling Rose fixing 1d 26 Apr 18 26 Apr 18 3138
3139 First Coat Paint on Walls & Ceiliings 2d 11 May 18 14 May 18 3139
3140 MEP Final Fixtures on Wall & Ceilings 2d 25 May 18 29 May 18 3140
3141 Final Coat Paint on walls & Ceilings 2d 30 May 18 31 May 18 3141
3142 Level 05 - CORE 02 12w 04 Apr 18 29 Jun 18 3142
3143 Toilet 12w 04 Apr 18 29 Jun 18 3143
3144 1st Fix Wall with Head tracks 1w 04 Apr 18 10 Apr 18 3144
3145 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 11 Apr 18 10 May 18 3145
3146 Fix Pocket Doors 1w 11 Apr 18 17 Apr 18 3146
3147 Inspection and Ceiling Grid Clearance 11 May 18 11 May 18 3147
3148 2nd Fix wall 1w 11 May 18 17 May 18 3148
3149 IPS Frame (Box Out only) incl. Backing ply 3d 18 May 18 22 May 18 3149

3150 Screed 2d 23 May 18 24 May 18 3150

3151 Fix Ceiling Grid Works 3d 25 May 18 30 May 18 3151

3152 Floor Tiling Works 3d 31 May 18 04 Jun 18 3152

3153 Wall Tiling works incl. IPS Panels 3d 05 Jun 18 07 Jun 18 3153
3154 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 08 Jun 18 15 Jun 18 3154

3155 Mark and Cut openings for MEP on walls including Ceiling 2d 18 Jun 18 19 Jun 18 3155
3156 Install Vanity Tops 4d 18 Jun 18 21 Jun 18 3156

3157 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 20 Jun 18 25 Jun 18 3157

3158 Fix MEP Final Fixtures 3d 25 Jun 18 27 Jun 18 3158

3159 Final Coat Paint on Ceiling 2d 28 Jun 18 29 Jun 18 3159

3160 Lobby 8w 3d 11 Apr 18 13 Jun 18 3160


3161 1st Fix Wall with Head tracks 1w 11 Apr 18 17 Apr 18 3161
3162 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 18 Apr 18 17 May 18 3162
3163 Fix Ceiling Grid 3d 18 May 18 22 May 18 3163
3164 Paint 1st Coat 2d 23 May 18 24 May 18 3164
3165 Fix doors incl. Ironmongery 2d 25 May 18 29 May 18 3165
3166 Mark and Cut openings for MEP on walls 2d 30 May 18 31 May 18 3166
3167 Install Ceiling Tiles 3d 01 Jun 18 05 Jun 18 3167
3168 Fix MEP Final Fixtures 3d 06 Jun 18 08 Jun 18 3168
3169 Final Coat Paint on walls and ceiling 3d 11 Jun 18 13 Jun 18 3169
3170 Staircase 5w 2d 08 May 18 14 Jun 18 3170
3171 H/L Electrical Containment & Conduits - 1st Fix 2d 08 May 18 09 May 18 3171
3172 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 10 May 18 11 May 18 3172

3173 Ceiling Rose fixing 1d 14 May 18 14 May 18 3173

3174 First Coat Paint on Walls & Ceiliings 2d 25 May 18 29 May 18 3174

3175 MEP Final Fixtures on Wall & Ceilings 2d 11 Jun 18 12 Jun 18 3175

3176 Final Coat Paint on walls & Ceilings 2d 13 Jun 18 14 Jun 18 3176

3177 Level GF - CORE 02 12w 18 Apr 18 13 Jul 18 3177


3178 Toilet 12w 18 Apr 18 13 Jul 18 3178
3179 1st Fix Wall with Head tracks 1w 18 Apr 18 24 Apr 18 3179
3180 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 25 Apr 18 24 May 18 3180
3181 Fix Pocket Doors 1w 25 Apr 18 02 May 18 3181
3182 Inspection and Ceiling Grid Clearance 25 May 18 25 May 18 3182
3183 2nd Fix wall 1w 25 May 18 01 Jun 18 3183

3184 IPS Frame (Box Out only) incl. Backing ply 3d 04 Jun 18 06 Jun 18 3184
3185 Screed 2d 07 Jun 18 08 Jun 18 3185
3186 Fix Ceiling Grid Works 3d 11 Jun 18 13 Jun 18 3186
3187 Floor Tiling Works 3d 14 Jun 18 18 Jun 18 3187
3188 Wall Tiling works incl. IPS Panels 3d 19 Jun 18 21 Jun 18 3188
3189 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 22 Jun 18 29 Jun 18 3189
3190 Mark and Cut openings for MEP on walls including Ceiling 2d 02 Jul 18 03 Jul 18 3190
3191 Install Vanity Tops 4d 02 Jul 18 05 Jul 18 3191
3192 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 04 Jul 18 09 Jul 18 3192
3193 Fix MEP Final Fixtures 3d 09 Jul 18 11 Jul 18 3193
3194 Final Coat Paint on Ceiling 2d 12 Jul 18 13 Jul 18 3194
3195 Lobby 8w 3d 25 Apr 18 27 Jun 18 3195
3196 1st Fix Wall with Head tracks 1w 25 Apr 18 02 May 18 3196
3197 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 03 May 18 01 Jun 18 3197

3198 Fix Ceiling Grid 3d 04 Jun 18 06 Jun 18 3198


3199 Paint 1st Coat 2d 07 Jun 18 08 Jun 18 3199

3200 Fix doors incl. Ironmongery 2d 11 Jun 18 12 Jun 18 3200


3201 Mark and Cut openings for MEP on walls 2d 13 Jun 18 14 Jun 18 3201
3202 Install Ceiling Tiles 3d 15 Jun 18 19 Jun 18 3202
3203 Fix MEP Final Fixtures 3d 20 Jun 18 22 Jun 18 3203
3204 Final Coat Paint on walls and ceiling 3d 25 Jun 18 27 Jun 18 3204

3205 Staircase 5w 2d 22 May 18 28 Jun 18 3205

3206 H/L Electrical Containment & Conduits - 1st Fix 2d 22 May 18 23 May 18 3206

3207 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 24 May 18 25 May 18 3207

3208 Ceiling Rose fixing 1d 29 May 18 29 May 18 3208


3209 First Coat Paint on Walls & Ceiliings 2d 11 Jun 18 12 Jun 18 3209
3210 MEP Final Fixtures on Wall & Ceilings 2d 25 Jun 18 26 Jun 18 3210
3211 Final Coat Paint on walls & Ceilings 2d 27 Jun 18 28 Jun 18 3211

3212 Level 01 - CORE 03 12w 19 Feb 18 17 May 18 3212


3213 Toilet 12w 19 Feb 18 17 May 18 3213
3214 Floor slab available 19 Feb 18 19 Feb 18 3214
3215 1st Fix Wall with Head tracks 1w 19 Feb 18 23 Feb 18 3215
3216 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 26 Feb 18 23 Mar 18 3216
3217 Fix Pocket Doors 1w 26 Feb 18 02 Mar 18 3217
3218 Inspection and Ceiling Grid Clearance 26 Mar 18 26 Mar 18 3218
3219 2nd Fix wall 1w 26 Mar 18 03 Apr 18 3219
3220 IPS Frame (Box Out only) incl. Backing ply 3d 04 Apr 18 06 Apr 18 3220

3221 Screed 2d 09 Apr 18 10 Apr 18 3221

3222 Fix Ceiling Grid Works 3d 11 Apr 18 13 Apr 18 3222


3223 Floor Tiling Works 3d 16 Apr 18 18 Apr 18 3223

3224 Wall Tiling works incl. IPS Panels 3d 19 Apr 18 23 Apr 18 3224
3225 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 24 Apr 18 02 May 18 3225

3226 Mark and Cut openings for MEP on walls including Ceiling 2d 03 May 18 04 May 18 3226
3227 Install Vanity Tops 4d 03 May 18 09 May 18 3227

3228 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 08 May 18 11 May 18 3228

3229 Fix MEP Final Fixtures 3d 11 May 18 15 May 18 3229


3230 Final Coat Paint on Ceiling 2d 16 May 18 17 May 18 3230

3231 Lobby 8w 3d 26 Feb 18 30 Apr 18 3231


3232 1st Fix Wall with Head tracks 1w 26 Feb 18 02 Mar 18 3232
3233 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 05 Mar 18 03 Apr 18 3233
3234 Fix Ceiling Grid 3d 04 Apr 18 06 Apr 18 3234
3235 Paint 1st Coat 2d 09 Apr 18 10 Apr 18 3235
3236 Fix doors incl. Ironmongery 2d 11 Apr 18 12 Apr 18 3236
3237 Mark and Cut openings for MEP on walls 2d 13 Apr 18 16 Apr 18 3237
3238 Install Ceiling Tiles 3d 17 Apr 18 19 Apr 18 3238
3239 Fix MEP Final Fixtures 3d 20 Apr 18 24 Apr 18 3239
3240 Final Coat Paint on walls and ceiling 3d 25 Apr 18 30 Apr 18 3240
3241 Staircase 5w 2d 21 Mar 18 01 May 18 3241
3242 H/L Electrical Containment & Conduits - 1st Fix 2d 21 Mar 18 22 Mar 18 3242
3243 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 23 Mar 18 26 Mar 18 3243

3244 Ceiling Rose fixing 1d 27 Mar 18 27 Mar 18 3244

3245 First Coat Paint on Walls & Ceiliings 2d 11 Apr 18 12 Apr 18 3245

3246 MEP Final Fixtures on Wall & Ceilings 2d 25 Apr 18 26 Apr 18 3246

3247 Final Coat Paint on walls & Ceilings 2d 30 Apr 18 01 May 18 3247
3248 Level 02 - CORE 03 12w 05 Mar 18 01 Jun 18 3248

3249 Toilet 12w 05 Mar 18 01 Jun 18 3249


3250 1st Fix Wall with Head tracks 1w 05 Mar 18 09 Mar 18 3250

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3251 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 12 Mar 18 10 Apr 18 3251
3252 Fix Pocket Doors 1w 12 Mar 18 16 Mar 18 3252
3253 Inspection and Ceiling Grid Clearance 11 Apr 18 11 Apr 18 3253
3254 2nd Fix wall 1w 11 Apr 18 17 Apr 18 3254
3255 IPS Frame (Box Out only) incl. Backing ply 3d 18 Apr 18 20 Apr 18 3255
3256 Screed 2d 23 Apr 18 24 Apr 18 3256
3257 Fix Ceiling Grid Works 3d 25 Apr 18 30 Apr 18 3257
3258 Floor Tiling Works 3d 01 May 18 03 May 18 3258
3259 Wall Tiling works incl. IPS Panels 3d 04 May 18 09 May 18 3259

3260 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 10 May 18 17 May 18 3260

3261 Mark and Cut openings for MEP on walls including Ceiling 2d 18 May 18 21 May 18 3261
3262 Install Vanity Tops 4d 18 May 18 23 May 18 3262

3263 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 22 May 18 25 May 18 3263

3264 Fix MEP Final Fixtures 3d 25 May 18 30 May 18 3264

3265 Final Coat Paint on Ceiling 2d 31 May 18 01 Jun 18 3265

3266 Lobby 8w 3d 12 Mar 18 15 May 18 3266

3267 1st Fix Wall with Head tracks 1w 12 Mar 18 16 Mar 18 3267

3268 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 19 Mar 18 17 Apr 18 3268
3269 Fix Ceiling Grid 3d 18 Apr 18 20 Apr 18 3269
3270 Paint 1st Coat 2d 23 Apr 18 24 Apr 18 3270
3271 Fix doors incl. Ironmongery 2d 25 Apr 18 26 Apr 18 3271
3272 Mark and Cut openings for MEP on walls 2d 30 Apr 18 01 May 18 3272
3273 Install Ceiling Tiles 3d 02 May 18 04 May 18 3273
3274 Fix MEP Final Fixtures 3d 08 May 18 10 May 18 3274
3275 Final Coat Paint on walls and ceiling 3d 11 May 18 15 May 18 3275
3276 Staircase 5w 2d 06 Apr 18 16 May 18 3276
3277 H/L Electrical Containment & Conduits - 1st Fix 2d 06 Apr 18 09 Apr 18 3277
3278 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 10 Apr 18 11 Apr 18 3278
3279 Ceiling Rose fixing 1d 12 Apr 18 12 Apr 18 3279
3280 First Coat Paint on Walls & Ceiliings 2d 25 Apr 18 26 Apr 18 3280
3281 MEP Final Fixtures on Wall & Ceilings 2d 11 May 18 14 May 18 3281
3282 Final Coat Paint on walls & Ceilings 2d 15 May 18 16 May 18 3282
3283 Level 03 - CORE 03 12w 19 Mar 18 15 Jun 18 3283
3284 Toilet 12w 19 Mar 18 15 Jun 18 3284

3285 1st Fix Wall with Head tracks 1w 19 Mar 18 23 Mar 18 3285

3286 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 26 Mar 18 24 Apr 18 3286

3287 Fix Pocket Doors 1w 26 Mar 18 03 Apr 18 3287

3288 Inspection and Ceiling Grid Clearance 25 Apr 18 25 Apr 18 3288


3289 2nd Fix wall 1w 25 Apr 18 02 May 18 3289

3290 IPS Frame (Box Out only) incl. Backing ply 3d 03 May 18 08 May 18 3290
3291 Screed 2d 09 May 18 10 May 18 3291

3292 Fix Ceiling Grid Works 3d 11 May 18 15 May 18 3292

3293 Floor Tiling Works 3d 16 May 18 18 May 18 3293

3294 Wall Tiling works incl. IPS Panels 3d 21 May 18 23 May 18 3294

3295 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 24 May 18 01 Jun 18 3295

3296 Mark and Cut openings for MEP on walls including Ceiling 2d 04 Jun 18 05 Jun 18 3296
3297 Install Vanity Tops 4d 04 Jun 18 07 Jun 18 3297
3298 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 06 Jun 18 11 Jun 18 3298
3299 Fix MEP Final Fixtures 3d 11 Jun 18 13 Jun 18 3299
3300 Final Coat Paint on Ceiling 2d 14 Jun 18 15 Jun 18 3300
3301 Lobby 8w 3d 26 Mar 18 30 May 18 3301
3302 1st Fix Wall with Head tracks 1w 26 Mar 18 03 Apr 18 3302
3303 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 04 Apr 18 02 May 18 3303
3304 Fix Ceiling Grid 3d 03 May 18 08 May 18 3304
3305 Paint 1st Coat 2d 09 May 18 10 May 18 3305
3306 Fix doors incl. Ironmongery 2d 11 May 18 14 May 18 3306
3307 Mark and Cut openings for MEP on walls 2d 15 May 18 16 May 18 3307
3308 Install Ceiling Tiles 3d 17 May 18 21 May 18 3308

3309 Fix MEP Final Fixtures 3d 22 May 18 24 May 18 3309

3310 Final Coat Paint on walls and ceiling 3d 25 May 18 30 May 18 3310

3311 Staircase 5w 2d 20 Apr 18 31 May 18 3311

3312 H/L Electrical Containment & Conduits - 1st Fix 2d 20 Apr 18 23 Apr 18 3312

3313 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 24 Apr 18 25 Apr 18 3313

3314 Ceiling Rose fixing 1d 26 Apr 18 26 Apr 18 3314

3315 First Coat Paint on Walls & Ceiliings 2d 11 May 18 14 May 18 3315

3316 MEP Final Fixtures on Wall & Ceilings 2d 25 May 18 29 May 18 3316

3317 Final Coat Paint on walls & Ceilings 2d 30 May 18 31 May 18 3317
3318 Level 04 - CORE 03 12w 04 Apr 18 29 Jun 18 3318

3319 Toilet 12w 04 Apr 18 29 Jun 18 3319


3320 1st Fix Wall with Head tracks 1w 04 Apr 18 10 Apr 18 3320
3321 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 11 Apr 18 10 May 18 3321
3322 Fix Pocket Doors 1w 11 Apr 18 17 Apr 18 3322
3323 Inspection and Ceiling Grid Clearance 11 May 18 11 May 18 3323
3324 2nd Fix wall 1w 11 May 18 17 May 18 3324
3325 IPS Frame (Box Out only) incl. Backing ply 3d 18 May 18 22 May 18 3325
3326 Screed 2d 23 May 18 24 May 18 3326
3327 Fix Ceiling Grid Works 3d 25 May 18 30 May 18 3327
3328 Floor Tiling Works 3d 31 May 18 04 Jun 18 3328
3329 Wall Tiling works incl. IPS Panels 3d 05 Jun 18 07 Jun 18 3329
3330 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 08 Jun 18 15 Jun 18 3330
3331 Mark and Cut openings for MEP on walls including Ceiling 2d 18 Jun 18 19 Jun 18 3331
3332 Install Vanity Tops 4d 18 Jun 18 21 Jun 18 3332

3333 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 20 Jun 18 25 Jun 18 3333
3334 Fix MEP Final Fixtures 3d 25 Jun 18 27 Jun 18 3334

3335 Final Coat Paint on Ceiling 2d 28 Jun 18 29 Jun 18 3335


3336 Lobby 8w 3d 11 Apr 18 13 Jun 18 3336
3337 1st Fix Wall with Head tracks 1w 11 Apr 18 17 Apr 18 3337
3338 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 18 Apr 18 17 May 18 3338
3339 Fix Ceiling Grid 3d 18 May 18 22 May 18 3339

3340 Paint 1st Coat 2d 23 May 18 24 May 18 3340

3341 Fix doors incl. Ironmongery 2d 25 May 18 29 May 18 3341

3342 Mark and Cut openings for MEP on walls 2d 30 May 18 31 May 18 3342

3343 Install Ceiling Tiles 3d 01 Jun 18 05 Jun 18 3343


3344 Fix MEP Final Fixtures 3d 06 Jun 18 08 Jun 18 3344
3345 Final Coat Paint on walls and ceiling 3d 11 Jun 18 13 Jun 18 3345
3346 Staircase 5w 2d 08 May 18 14 Jun 18 3346
3347 H/L Electrical Containment & Conduits - 1st Fix 2d 08 May 18 09 May 18 3347
3348 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 10 May 18 11 May 18 3348
3349 Ceiling Rose fixing 1d 14 May 18 14 May 18 3349
3350 First Coat Paint on Walls & Ceiliings 2d 25 May 18 29 May 18 3350
3351 MEP Final Fixtures on Wall & Ceilings 2d 11 Jun 18 12 Jun 18 3351
3352 Final Coat Paint on walls & Ceilings 2d 13 Jun 18 14 Jun 18 3352
3353 Level 05 - CORE 03 12w 18 Apr 18 13 Jul 18 3353
3354 Toilet 12w 18 Apr 18 13 Jul 18 3354
3355 1st Fix Wall with Head tracks 1w 18 Apr 18 24 Apr 18 3355
3356 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 25 Apr 18 24 May 18 3356
3357 Fix Pocket Doors 1w 25 Apr 18 02 May 18 3357

3358 Inspection and Ceiling Grid Clearance 25 May 18 25 May 18 3358

3359 2nd Fix wall 1w 25 May 18 01 Jun 18 3359


3360 IPS Frame (Box Out only) incl. Backing ply 3d 04 Jun 18 06 Jun 18 3360

3361 Screed 2d 07 Jun 18 08 Jun 18 3361


3362 Fix Ceiling Grid Works 3d 11 Jun 18 13 Jun 18 3362

3363 Floor Tiling Works 3d 14 Jun 18 18 Jun 18 3363


3364 Wall Tiling works incl. IPS Panels 3d 19 Jun 18 21 Jun 18 3364

3365 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 22 Jun 18 29 Jun 18 3365

3366 Mark and Cut openings for MEP on walls including Ceiling 2d 02 Jul 18 03 Jul 18 3366
3367 Install Vanity Tops 4d 02 Jul 18 05 Jul 18 3367

3368 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 04 Jul 18 09 Jul 18 3368
3369 Fix MEP Final Fixtures 3d 09 Jul 18 11 Jul 18 3369
3370 Final Coat Paint on Ceiling 2d 12 Jul 18 13 Jul 18 3370
3371 Lobby 8w 3d 25 Apr 18 27 Jun 18 3371
3372 1st Fix Wall with Head tracks 1w 25 Apr 18 02 May 18 3372
3373 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 03 May 18 01 Jun 18 3373
3374 Fix Ceiling Grid 3d 04 Jun 18 06 Jun 18 3374
3375 Paint 1st Coat 2d 07 Jun 18 08 Jun 18 3375
3376 Fix doors incl. Ironmongery 2d 11 Jun 18 12 Jun 18 3376
3377 Mark and Cut openings for MEP on walls 2d 13 Jun 18 14 Jun 18 3377
3378 Install Ceiling Tiles 3d 15 Jun 18 19 Jun 18 3378
3379 Fix MEP Final Fixtures 3d 20 Jun 18 22 Jun 18 3379
3380 Final Coat Paint on walls and ceiling 3d 25 Jun 18 27 Jun 18 3380

3381 Staircase 5w 2d 22 May 18 28 Jun 18 3381

3382 H/L Electrical Containment & Conduits - 1st Fix 2d 22 May 18 23 May 18 3382

3383 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 24 May 18 25 May 18 3383

3384 Ceiling Rose fixing 1d 29 May 18 29 May 18 3384


3385 First Coat Paint on Walls & Ceiliings 2d 11 Jun 18 12 Jun 18 3385

3386 MEP Final Fixtures on Wall & Ceilings 2d 25 Jun 18 26 Jun 18 3386

3387 Final Coat Paint on walls & Ceilings 2d 27 Jun 18 28 Jun 18 3387

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3388 Level GF - CORE 03 12w 03 May 18 27 Jul 18 3388
3389 Toilet 12w 03 May 18 27 Jul 18 3389
3390 1st Fix Wall with Head tracks 1w 03 May 18 10 May 18 3390
3391 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 11 May 18 08 Jun 18 3391
3392 Fix Pocket Doors 1w 11 May 18 17 May 18 3392
3393 Inspection and Ceiling Grid Clearance 11 Jun 18 11 Jun 18 3393
3394 2nd Fix wall 1w 11 Jun 18 15 Jun 18 3394
3395 IPS Frame (Box Out only) incl. Backing ply 3d 18 Jun 18 20 Jun 18 3395
3396 Screed 2d 21 Jun 18 22 Jun 18 3396

3397 Fix Ceiling Grid Works 3d 25 Jun 18 27 Jun 18 3397

3398 Floor Tiling Works 3d 28 Jun 18 02 Jul 18 3398


3399 Wall Tiling works incl. IPS Panels 3d 03 Jul 18 05 Jul 18 3399

3400 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 06 Jul 18 13 Jul 18 3400
3401 Mark and Cut openings for MEP on walls including Ceiling 2d 16 Jul 18 17 Jul 18 3401
3402 Install Vanity Tops 4d 16 Jul 18 19 Jul 18 3402

3403 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 18 Jul 18 23 Jul 18 3403

3404 Fix MEP Final Fixtures 3d 23 Jul 18 25 Jul 18 3404

3405 Final Coat Paint on Ceiling 2d 26 Jul 18 27 Jul 18 3405


3406 Lobby 8w 3d 11 May 18 11 Jul 18 3406
3407 1st Fix Wall with Head tracks 1w 11 May 18 17 May 18 3407
3408 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 18 May 18 15 Jun 18 3408
3409 Fix Ceiling Grid 3d 18 Jun 18 20 Jun 18 3409
3410 Paint 1st Coat 2d 21 Jun 18 22 Jun 18 3410
3411 Fix doors incl. Ironmongery 2d 25 Jun 18 26 Jun 18 3411
3412 Mark and Cut openings for MEP on walls 2d 27 Jun 18 28 Jun 18 3412
3413 Install Ceiling Tiles 3d 29 Jun 18 03 Jul 18 3413
3414 Fix MEP Final Fixtures 3d 04 Jul 18 06 Jul 18 3414
3415 Final Coat Paint on walls and ceiling 3d 09 Jul 18 11 Jul 18 3415
3416 Staircase 5w 2d 06 Jun 18 12 Jul 18 3416
3417 H/L Electrical Containment & Conduits - 1st Fix 2d 06 Jun 18 07 Jun 18 3417
3418 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 08 Jun 18 11 Jun 18 3418
3419 Ceiling Rose fixing 1d 12 Jun 18 12 Jun 18 3419
3420 First Coat Paint on Walls & Ceiliings 2d 25 Jun 18 26 Jun 18 3420
3421 MEP Final Fixtures on Wall & Ceilings 2d 09 Jul 18 10 Jul 18 3421
3422 Final Coat Paint on walls & Ceilings 2d 11 Jul 18 12 Jul 18 3422

3423 Staircase Fit Out 10w 31 Aug 18 08 Nov 18 3423

3424 Staircase Flooring incl. Nosing 4w 08 Nov 18 05 Dec 18 3424

3425 Groundfloor refuse room cladding 2w 21 Mar 18 05 Apr 18 3425

3426 Latest Date for ABP/WTP to omit Cat A Shell and Core Fit-out scope of works to Building 8B 14 Nov 17 14 Nov 17 3426

3427 Cat A Fit Out 51w 4d 20 Nov 17 04 Dec 18 3427

3428 Fit out Ground Floor 8w 1d 22 Jan 18 19 Mar 18 3428

3429 Fit out Ground Floor Unit 1 and 2 5w 2d 22 Jan 18 27 Feb 18 3429

3430
3430 Install conduit to cleaners sockets to core walls 3d 22 Jan 18 24 Jan 18
3431 Boarding and Insulation to external and core walls 1w 25 Jan 18 31 Jan 18 3431

3432 Install wiring to containment in ceilings 1w 07 Feb 18 13 Feb 18 3432

3433 Taping and Joining to Walls 2d 01 Feb 18 02 Feb 18 3433

3434
3434 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 14 Feb 18 20 Feb 18
3435 Install Joinery incl Doors 1w 21 Feb 18 27 Feb 18 3435

3436
3436 Decoration 1w 16 Feb 18 22 Feb 18
3437 Fit out Ground Floor Units 3 & 4 4w 3d 05 Feb 18 07 Mar 18 3437

3438
3438 Install conduit to cleaners sockets to core walls 3d 05 Feb 18 07 Feb 18
3439 Boarding and Insulation to external and core walls 1w 08 Feb 18 14 Feb 18 3439

3440 Install wiring to containment in ceilings 1w 15 Feb 18 21 Feb 18 3440

3441 Taping and Joining to Walls 2d 15 Feb 18 16 Feb 18 3441

3442
3442 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 22 Feb 18 28 Feb 18
3443 Install Joinery incl Doors 1w 01 Mar 18 07 Mar 18 3443

3444
3444 Decoration 1w 26 Feb 18 02 Mar 18
3445 Fit Out Ground Floor Unit 5 and 6 4w 3d 15 Feb 18 19 Mar 18 3445

3446 Install conduit to cleaners sockets to core walls 3d 15 Feb 18 19 Feb 18 3446

3447 Boarding and Insulation to external and core walls 1w 20 Feb 18 26 Feb 18 3447

3448 Install wiring to containment in ceilings 1w 27 Feb 18 05 Mar 18 3448

3449
3449 Taping and Joining to Walls 2d 27 Feb 18 28 Feb 18
3450 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 06 Mar 18 12 Mar 18 3450

3451
3451 Decoration 1w 07 Mar 18 13 Mar 18
3452 Install Joinery incl Doors 1w 13 Mar 18 19 Mar 18 3452

3453 Fit-out First Floor 17w 20 Nov 17 27 Mar 18 3453

3454 Units 1 and 2 5w 1d 30 Jan 18 06 Mar 18 3454

3455
3455 Install conduit to cleaners sockets to core walls 3d 30 Jan 18 01 Feb 18
3456 Boarding and Insulation to external and core walls 1w 02 Feb 18 08 Feb 18 3456

3457 Install wiring to containment in ceilings 1w 09 Feb 18 15 Feb 18 3457

3458 Taping and Joining to Walls 2d 09 Feb 18 12 Feb 18 3458

3459
3459 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 16 Feb 18 22 Feb 18
3460 Install Joinery incl Doors 1w 28 Feb 18 06 Mar 18 3460

3461
3461 Decoration 1w 20 Feb 18 26 Feb 18
3462 Units 3 and 4 5w 09 Feb 18 15 Mar 18 3462

3463
3463 Install conduit to cleaners sockets to core walls 3d 09 Feb 18 13 Feb 18
3464 Boarding and Insulation to external and core walls 1w 2d 14 Feb 18 22 Feb 18 3464

3465 Install wiring to containment in ceilings 1w 23 Feb 18 01 Mar 18 3465

3466 Taping and Joining to Walls 3d 23 Feb 18 27 Feb 18 3466

3467
3467 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 02 Mar 18 08 Mar 18
3468 Install Joinery incl Doors 1w 09 Mar 18 15 Mar 18 3468

3469
3469 Decoration 1w 06 Mar 18 12 Mar 18
3470 Units 5 and 6 4w 3d 23 Feb 18 27 Mar 18 3470

3471 Install conduit to cleaners sockets to core walls 3d 23 Feb 18 27 Feb 18 3471

3472 Boarding and Insulation to external and core walls 1w 28 Feb 18 06 Mar 18 3472

3473 Install wiring to containment in ceilings 1w 07 Mar 18 13 Mar 18 3473

3474 Taping and Joining to Walls 2d 07 Mar 18 08 Mar 18 3474

3475 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 14 Mar 18 20 Mar 18 3475

3476 Install Joinery incl Doors 1w 21 Mar 18 27 Mar 18 3476

3477 Decoration 1w 16 Mar 18 22 Mar 18 3477

3478 High Level Services First Floor 8w 20 Nov 17 23 Jan 18 3478

3479 Fit-out Second Floor 16w 4d 27 Nov 17 04 Apr 18 3479

3480 Units 1 and 2 4w 3d 07 Feb 18 09 Mar 18 3480

3481 Install conduit to cleaners sockets to core walls 3d 07 Feb 18 09 Feb 18 3481

3482 Boarding and Insulation to external and core walls 1w 12 Feb 18 16 Feb 18 3482

3483 Install wiring to containment in ceilings 1w 19 Feb 18 23 Feb 18 3483

3484 Taping and Joining to Walls 2d 19 Feb 18 20 Feb 18 3484

3485 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 26 Feb 18 02 Mar 18 3485

3486 Install Joinery incl Doors 1w 05 Mar 18 09 Mar 18 3486

3487 Decoration 1w 28 Feb 18 06 Mar 18 3487

3488 Units 3 and 4 4w 3d 19 Feb 18 21 Mar 18 3488

3489 Install conduit to cleaners sockets to core walls 3d 19 Feb 18 21 Feb 18 3489

3490 Boarding and Insulation to external and core walls 1w 22 Feb 18 28 Feb 18 3490

3491 Install wiring to containment in ceilings 1w 01 Mar 18 07 Mar 18 3491

3492 Taping and Joining to Walls 2d 01 Mar 18 02 Mar 18 3492

3493 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 08 Mar 18 14 Mar 18 3493

3494 Install Joinery incl Doors 1w 15 Mar 18 21 Mar 18 3494

3495 Decoration 1w 12 Mar 18 16 Mar 18 3495

3496 Units 5 and 6 4w 3d 01 Mar 18 04 Apr 18 3496

3497 Install conduit to cleaners sockets to core walls 3d 01 Mar 18 05 Mar 18 3497

3498 Boarding and Insulation to external and core walls 1w 06 Mar 18 12 Mar 18 3498

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3499 Install wiring to containment in ceilings 1w 13 Mar 18 19 Mar 18 3499

3500 Taping and Joining to Walls 2d 13 Mar 18 14 Mar 18 3500

3501 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 20 Mar 18 26 Mar 18 3501

3502 Decoration 1w 22 Mar 18 28 Mar 18 3502

3503 Install Joinery incl Doors 1w 27 Mar 18 04 Apr 18 3503

3504 High Level Services Second Floor 8w 27 Nov 17 30 Jan 18 3504

3505 Fit-out Third Floor 15w 3d 12 Dec 17 11 Apr 18 3505

3506 Units 1 and 2 4w 3d 14 Feb 18 16 Mar 18 3506

3507 Install conduit to cleaners sockets to core walls 3d 14 Feb 18 16 Feb 18 3507

3508 Boarding and Insulation to external and core walls 1w 19 Feb 18 23 Feb 18 3508

3509 Install wiring to containment in ceilings 1w 26 Feb 18 02 Mar 18 3509

3510 Taping and Joining to Walls 2d 26 Feb 18 27 Feb 18 3510

3511 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 05 Mar 18 09 Mar 18 3511

3512 Install Joinery incl Doors 1w 12 Mar 18 16 Mar 18 3512

3513 Decoration 1w 07 Mar 18 13 Mar 18 3513

3514 Units 3 and 4 4w 3d 26 Feb 18 28 Mar 18 3514

3515 Install conduit to cleaners sockets to core walls 3d 26 Feb 18 28 Feb 18 3515

3516 Boarding and Insulation to external and core walls 1w 01 Mar 18 07 Mar 18 3516

3517 Install wiring to containment in ceilings 1w 08 Mar 18 14 Mar 18 3517

3518 Taping and Joining to Walls 2d 08 Mar 18 09 Mar 18 3518

3519 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 15 Mar 18 21 Mar 18 3519

3520 Install Joinery incl Doors 1w 22 Mar 18 28 Mar 18 3520

3521 Decoration 1w 19 Mar 18 23 Mar 18 3521

3522 Units 5 and 6 4w 3d 08 Mar 18 11 Apr 18 3522

3523 Install conduit to cleaners sockets to core walls 3d 08 Mar 18 12 Mar 18 3523

3524 Boarding and Insulation to external and core walls 1w 13 Mar 18 19 Mar 18 3524

3525 Install wiring to containment in ceilings 1w 20 Mar 18 26 Mar 18 3525

3526 Taping and Joining to Walls 2d 20 Mar 18 21 Mar 18 3526

3527 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 27 Mar 18 04 Apr 18 3527

3528 Install Joinery incl Doors 1w 05 Apr 18 11 Apr 18 3528

3529 Decoration 1w 29 Mar 18 06 Apr 18 3529

3530 High Level Services Third Floor 8w 12 Dec 17 14 Feb 18 3530

3531 Fit-out Fourth Floor 14w 1d 03 Jan 18 13 Apr 18 3531

3532 Units 1 and 2 4w 21 Feb 18 20 Mar 18 3532

3533 Install conduit to cleaners sockets to core walls 3d 21 Feb 18 23 Feb 18 3533

3534 Boarding and Insulation to external and core walls 1w 26 Feb 18 02 Mar 18 3534

3535 Install wiring to containment in ceilings 1w 05 Mar 18 09 Mar 18 3535

3536 Taping and Joining to Walls 2d 05 Mar 18 06 Mar 18 3536

3537 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 12 Mar 18 16 Mar 18 3537

3538 Install Joinery incl Doors 1w 12 Mar 18 16 Mar 18 3538

3539 Decoration 1w 14 Mar 18 20 Mar 18 3539

3540 Units 3 and 4 4w 05 Mar 18 03 Apr 18 3540

3541 Install conduit to cleaners sockets to core walls 3d 05 Mar 18 07 Mar 18 3541

3542 Boarding and Insulation to external and core walls 1w 08 Mar 18 14 Mar 18 3542

3543 Install wiring to containment in ceilings 1w 15 Mar 18 21 Mar 18 3543

3544 Taping and Joining to Walls 2d 15 Mar 18 16 Mar 18 3544

3545 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 22 Mar 18 28 Mar 18 3545

3546 Install Joinery incl Doors 1w 19 Mar 18 23 Mar 18 3546

3547 Decoration 1w 26 Mar 18 03 Apr 18 3547

3548 Units 5 and 6 4w 15 Mar 18 13 Apr 18 3548

3549 Install conduit to cleaners sockets to core walls 3d 15 Mar 18 19 Mar 18 3549

3550 Boarding and Insulation to external and core walls 1w 20 Mar 18 26 Mar 18 3550

3551 Install wiring to containment in ceilings 1w 27 Mar 18 04 Apr 18 3551

3552 Taping and Joining to Walls 2d 27 Mar 18 28 Mar 18 3552

3553 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 05 Apr 18 11 Apr 18 3553

3554 Install Joinery incl Doors 1w 05 Apr 18 11 Apr 18 3554

3555 Decoration 1w 09 Apr 18 13 Apr 18 3555

3556 High Level Services Fourth Floor 8w 03 Jan 18 27 Feb 18 3556

3557 Fit-out Fifth Floor 13w 4d 17 Jan 18 25 Apr 18 3557

3558 Units 1 and 2 4w 3d 28 Feb 18 03 Apr 18 3558

3559 Install conduit to cleaners sockets to core walls 3d 28 Feb 18 02 Mar 18 3559

3560 Boarding and Insulation to external and core walls 1w 05 Mar 18 09 Mar 18 3560

3561 Install wiring to containment in ceilings 1w 12 Mar 18 16 Mar 18 3561

3562 Taping and Joining to Walls 2d 12 Mar 18 13 Mar 18 3562

3563 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 19 Mar 18 23 Mar 18 3563

3564 Install Joinery incl Doors 1w 26 Mar 18 03 Apr 18 3564

3565 Decoration 1w 21 Mar 18 27 Mar 18 3565

3566 Units 3 and 4 4w 12 Mar 18 10 Apr 18 3566

3567 Install conduit to cleaners sockets to core walls 3d 12 Mar 18 14 Mar 18 3567

3568 Boarding and Insulation to external and core walls 1w 15 Mar 18 21 Mar 18 3568

3569 Install wiring to containment in ceilings 1w 22 Mar 18 28 Mar 18 3569

3570 Taping and Joining to Walls 2d 22 Mar 18 23 Mar 18 3570

3571 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 29 Mar 18 06 Apr 18 3571

3572 Install Joinery incl Doors 1w 26 Mar 18 03 Apr 18 3572

3573 Decoration 1w 04 Apr 18 10 Apr 18 3573

3574 Units 5 and 6 4w 3d 22 Mar 18 25 Apr 18 3574

3575 Install conduit to cleaners sockets to core walls 3d 22 Mar 18 26 Mar 18 3575

3576 Boarding and Insulation to external and core walls 1w 27 Mar 18 04 Apr 18 3576

3577 Install wiring to containment in ceilings 1w 05 Apr 18 11 Apr 18 3577

3578 Taping and Joining to Walls 2d 05 Apr 18 06 Apr 18 3578

3579 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 12 Apr 18 18 Apr 18 3579

3580 Install Joinery incl Doors 1w 19 Apr 18 25 Apr 18 3580

3581 Decoration 1w 16 Apr 18 20 Apr 18 3581

3582 High Level Services Fifth Floor 8w 17 Jan 18 13 Mar 18 3582

3583 Temporary Hoist Access Closure - CAT A Fitout 2w 2d 04 Jun 18 19 Jun 18 3583

3584 Fit out First Floor 2d 18 Jun 18 19 Jun 18 3584

3585 Partition closure 2d 18 Jun 18 19 Jun 18 3585

3586 Fit out Second Floor 2d 14 Jun 18 15 Jun 18 3586

3587 Partition closure 2d 14 Jun 18 15 Jun 18 3587

3588 Fit out Third Floor 2d 12 Jun 18 13 Jun 18 3588

3589 Partition closure 2d 12 Jun 18 13 Jun 18 3589

3590 Fit out Fourth Floor 2d 06 Jun 18 07 Jun 18 3590

3591 Partition closure 2d 06 Jun 18 07 Jun 18 3591

3592 Fit out Fifth Floor 2d 04 Jun 18 05 Jun 18 3592

3593 Partition closure 2d 04 Jun 18 05 Jun 18 3593

3594 Prepare to Handover Units 7w 4d 11 Oct 18 04 Dec 18 3594

3595 Prepare to Hand Over Units 1 and 2 5w 4d 11 Oct 18 20 Nov 18 3595

3596 Ground floor 2w 4d 11 Oct 18 30 Oct 18 3596

3597
3597 Complete Ceiling Tiles 1w 11 Oct 18 17 Oct 18
3598 Install Raised Access Floor incl Below Floor Barriers 1w 18 Oct 18 24 Oct 18 3598

3599
3599 Soft Floor Coverings 4d 25 Oct 18 30 Oct 18
3600 First floor 2w 4d 16 Oct 18 02 Nov 18 3600

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3601 Complete Ceiling Tiles 1w 16 Oct 18 22 Oct 18 3601

3602
3602 Install Raised Access Floor incl Below Floor Barriers 1w 23 Oct 18 29 Oct 18
3603 Soft Floor Coverings 4d 30 Oct 18 02 Nov 18 3603

3604 Second Floor 2w 4d 19 Oct 18 07 Nov 18 3604

3605 Complete Ceiling Tiles 1w 19 Oct 18 25 Oct 18 3605

3606 Install Raised Access Floor incl Below Floor Barriers 1w 26 Oct 18 01 Nov 18 3606

3607 Soft Floor Coverings 4d 02 Nov 18 07 Nov 18 3607

3608 Third Floor 2w 4d 24 Oct 18 12 Nov 18 3608

3609 Complete Ceiling Tiles 1w 24 Oct 18 30 Oct 18 3609

3610 Install Raised Access Floor incl Below Floor Barriers 1w 31 Oct 18 06 Nov 18 3610

3611 Soft Floor Coverings 4d 07 Nov 18 12 Nov 18 3611

3612 Fourth Floor 2w 4d 29 Oct 18 15 Nov 18 3612

3613 Complete Ceiling Tiles 1w 29 Oct 18 02 Nov 18 3613

3614 Install Raised Access Floor incl Below Floor Barriers 1w 05 Nov 18 09 Nov 18 3614

3615 Soft Floor Coverings 4d 12 Nov 18 15 Nov 18 3615

3616 Fifth Floor 2w 4d 01 Nov 18 20 Nov 18 3616

3617 Complete Ceiling Tiles 1w 01 Nov 18 07 Nov 18 3617

3618 Install Raised Access Floor incl Below Floor Barriers 1w 08 Nov 18 14 Nov 18 3618

3619 Soft Floor Coverings 4d 15 Nov 18 20 Nov 18 3619

3620 Prepare to Hand Over Units 3 & 4 5w 4d 18 Oct 18 27 Nov 18 3620

3621 Ground Floor 2w 4d 18 Oct 18 06 Nov 18 3621

3622
3622 Complete Ceiling Tiles 1w 18 Oct 18 24 Oct 18
3623 Install Raised Access Floor incl Below Floor Barriers 1w 25 Oct 18 31 Oct 18 3623

3624 Soft Floor Coverings 4d 01 Nov 18 06 Nov 18 3624

3625 First Floor 2w 4d 23 Oct 18 09 Nov 18 3625

3626 Complete Ceiling Tiles 1w 23 Oct 18 29 Oct 18 3626

3627
3627 Install Raised Access Floor incl Below Floor Barriers 1w 30 Oct 18 05 Nov 18
3628 Soft Floor Coverings 4d 06 Nov 18 09 Nov 18 3628

3629 Second Floor 2w 4d 26 Oct 18 14 Nov 18 3629

3630 Complete Ceiling Tiles 1w 26 Oct 18 01 Nov 18 3630

3631 Install Raised Access Floor incl Below Floor Barriers 1w 02 Nov 18 08 Nov 18 3631

3632 Soft Floor Coverings 4d 09 Nov 18 14 Nov 18 3632

3633 Third Floor 2w 4d 31 Oct 18 19 Nov 18 3633

3634 Complete Ceiling Tiles 1w 31 Oct 18 06 Nov 18 3634

3635 Install Raised Access Floor incl Below Floor Barriers 1w 07 Nov 18 13 Nov 18 3635

3636 Soft Floor Coverings 4d 14 Nov 18 19 Nov 18 3636

3637 Fourth Floor 2w 4d 05 Nov 18 22 Nov 18 3637

3638 Complete Ceiling Tiles 1w 05 Nov 18 09 Nov 18 3638

3639 Install Raised Access Floor incl Below Floor Barriers 1w 12 Nov 18 16 Nov 18 3639

3640 Soft Floor Coverings 4d 19 Nov 18 22 Nov 18 3640

3641 Fifth Floor 2w 4d 08 Nov 18 27 Nov 18 3641

3642 Complete Ceiling Tiles 1w 08 Nov 18 14 Nov 18 3642

3643 Install Raised Access Floor incl Below Floor Barriers 1w 15 Nov 18 21 Nov 18 3643

3644 Soft Floor Coverings 4d 22 Nov 18 27 Nov 18 3644

3645 Prepare to Hand Over Units 5 & 6 5w 4d 25 Oct 18 04 Dec 18 3645

3646 Ground Floor 2w 3d 25 Oct 18 12 Nov 18 3646

3647
3647 Complete Ceiling Tiles 1w 25 Oct 18 31 Oct 18
3648 Install Raised Access Floor incl Below Floor Barriers 1w 01 Nov 18 07 Nov 18 3648

3649
3649 Soft Floor Coverings 4d 07 Nov 18 12 Nov 18
3650 First Floor 2w 4d 30 Oct 18 16 Nov 18 3650

3651 Complete Ceiling Tiles 1w 30 Oct 18 05 Nov 18 3651

3652 Install Raised Access Floor incl Below Floor Barriers 1w 06 Nov 18 12 Nov 18 3652

3653 Soft Floor Coverings 4d 13 Nov 18 16 Nov 18 3653

3654 Second Floor 2w 4d 02 Nov 18 21 Nov 18 3654

3655 Complete Ceiling Tiles 1w 02 Nov 18 08 Nov 18 3655

3656 Install Raised Access Floor incl Below Floor Barriers 1w 09 Nov 18 15 Nov 18 3656

3657 Soft Floor Coverings 4d 16 Nov 18 21 Nov 18 3657

3658 Third Floor 2w 4d 07 Nov 18 26 Nov 18 3658

3659 Complete Ceiling Tiles 1w 07 Nov 18 13 Nov 18 3659

3660 Install Raised Access Floor incl Below Floor Barriers 1w 14 Nov 18 20 Nov 18 3660

3661 Soft Floor Coverings 4d 21 Nov 18 26 Nov 18 3661

3662 Fourth Floor 2w 4d 12 Nov 18 29 Nov 18 3662

3663 Complete Ceiling Tiles 1w 12 Nov 18 16 Nov 18 3663

3664 Install Raised Access Floor incl Below Floor Barriers 1w 19 Nov 18 23 Nov 18 3664

3665 Soft Floor Coverings 4d 26 Nov 18 29 Nov 18 3665

3666 Fifth Floor 2w 4d 15 Nov 18 04 Dec 18 3666

3667 Complete Ceiling Tiles 1w 15 Nov 18 21 Nov 18 3667

3668 Install Raised Access Floor incl Below Floor Barriers 1w 22 Nov 18 28 Nov 18 3668

3669 Soft Floor Coverings 4d 29 Nov 18 04 Dec 18 3669

3670 Building 8B Complete 13 Feb 19 13 Feb 19 3670

3671 Dock Wall Refurbishment (Undefined Provisional Sum) 55w 4d 19 Oct 17 30 Nov 18 3671

3672 Structural Repairs to Dock Wall (Undefined provisional Sum - indicative programme) 20w 08 Mar 18 01 Aug 18 3672

3673 Drainage South of 8B 1w 2d 19 Oct 17 27 Oct 17 3673


3674 Outfall to Dock 2d 19 Oct 17 20 Oct 17 3674
3675 Build SM8B-3 1d 23 Oct 17 23 Oct 17 3675
3676 SM8B-3 TO SM8B-2 2d 23 Oct 17 24 Oct 17 3676
3677 Build SMB-2 1d 24 Oct 17 24 Oct 17 3677
3678 SMB-2 to SMB1 2d 25 Oct 17 26 Oct 17 3678
3679 Build SMB1 1d 26 Oct 17 26 Oct 17 3679
3680 SMB3 to SMB-4 2d 26 Oct 17 27 Oct 17 3680

3681 Build SMB-4 1d 27 Oct 17 27 Oct 17 3681

3682 SMB-3 to SMB5 2d 26 Oct 17 27 Oct 17 3682

3683 Build SMB5 1d 27 Oct 17 27 Oct 17 3683


3684 SMB-5 to SMB-6 2d 26 Oct 17 27 Oct 17 3684
3685 Build SMB-6 1d 27 Oct 17 27 Oct 17 3685

3686 External Works and Paving South of 8B 18w 4d 04 Jun 18 12 Oct 18 3686

3687 Prep for Paving 6w 1d 04 Jun 18 16 Jul 18 3687

3688 Install Coping stones to Dock Wall (78m) 3w 04 Jun 18 22 Jun 18 3688
3689 Install Hand Rail 1w 20 Jun 18 26 Jun 18 3689

3690 Install Three number Tree Pits 3d 27 Jun 18 29 Jun 18 3690

3691 Install two number Bollards 1d 02 Jul 18 02 Jul 18 3691


3692 Install Ten number Granite Thresholds 1w 2d 29 Jun 18 09 Jul 18 3692
3693 Prep for Sets 2w 03 Jul 18 16 Jul 18 3693
3694 Paving 12w 3d 17 Jul 18 12 Oct 18 3694
3695 Lay P6a Sets (330m2) 6w 3d 17 Jul 18 31 Aug 18 3695
3696 Lay internal Paving demarked by Sets (245m2) 3w 1d 23 Aug 18 14 Sep 18 3696
3697 Paving to Eastern Elevation P1 sets (90M2) 2w 17 Sep 18 28 Sep 18 3697
3698 Snag and Handover 2w 01 Oct 18 12 Oct 18 3698
3699 Drainage South of 5B 1w 06 Mar 18 13 Mar 18 3699
3700 SM3B-3 to Outfall 1d 06 Mar 18 07 Mar 18 3700
3701 SM3B-3 to SM3B-1 3d 07 Mar 18 12 Mar 18 3701
3702 SM3B-3 TO SMB-4 1d 12 Mar 18 13 Mar 18 3702
3703 Prep for Paving South of 5B 6w 4d 06 Jul 18 22 Aug 18 3703
3704 Install Coping Stone to Dock Wall (76m) 3w 06 Jul 18 26 Jul 18 3704
3705 Install Handrail 1w 27 Jul 18 02 Aug 18 3705
3706 Install 15 number Tree Pits 1w 03 Aug 18 09 Aug 18 3706

3707 Install ten number bollards 3d 03 Aug 18 07 Aug 18 3707


3708 Install 5 number Granite Threashold 4d 10 Aug 18 15 Aug 18 3708

3709 Inport to Formation Level 1w 16 Aug 18 22 Aug 18 3709


3710 Paving South of 5B 14w 1d 23 Aug 18 30 Nov 18 3710

3711 Lay Sets to Muse Area (156m2) 4w 23 Aug 18 20 Sep 18 3711


3712 Lay sets to Dockside Area (156m2) 4w 21 Sep 18 18 Oct 18 3712

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3713 Paving to Dockside (270m2) 4w 19 Oct 18 15 Nov 18 3713
3714 Tarmac Finishes to Muse Area 2w 12 Nov 18 23 Nov 18 3714
3715 Snag and Handover 1w 26 Nov 18 30 Nov 18 3715
3716 Progressively take down hoardings to Dock Edge and replace with heras fencing. 4w 19 Jun 17 14 Jul 17 3716

3717 Surface water drainage to 3B through the dock wall 2w 17 Jul 17 28 Jul 17 3717

3718 Temporary Car Park 5w 24 Jan 18 27 Feb 18 3718

3719 External Roads & Landscaping to Buildings 8A & 8B 25w 1d 26 Jun 18 19 Dec 18 3719

3720 North of 8A (Area 6) 15w 3d 31 Jul 18 16 Nov 18 3720


3721 Prep for Kerbs Paving 2w 2d 31 Jul 18 15 Aug 18 3721

3722 Install 10 Tree Pits 1w 31 Jul 18 06 Aug 18 3722


3723 Install 11 number bollards 2d 07 Aug 18 08 Aug 18 3723
3724 Import to Formation 1w 09 Aug 18 15 Aug 18 3724
3725 Kerbs 3w 16 Aug 18 06 Sep 18 3725
3726 Lay Kerbs to road (184 linear meters 2w 16 Aug 18 30 Aug 18 3726
3727 Lay Channel Kerbs 1w 31 Aug 18 06 Sep 18 3727
3728 Paving and Tarmac 10w 1d 07 Sep 18 16 Nov 18 3728
3729 Lay Sets to Foothpath (128m2) 2w 4d 07 Sep 18 26 Sep 18 3729
3730 Lay Flags to Footpath(128m2) 2w 27 Sep 18 10 Oct 18 3730
3731 Laty Mistal Paving West of 5A(168M2) 2w 2d 11 Oct 18 26 Oct 18 3731
3732 Regulate for Tarmac 1w 29 Oct 18 02 Nov 18 3732
3733 Tarmac 1w 05 Nov 18 09 Nov 18 3733
3734 Snag and Handover 1w 12 Nov 18 16 Nov 18 3734

3735 External Lighting 8w 21 Sep 18 15 Nov 18 3735

3736 Soft Landscaping 7w 01 Nov 18 19 Dec 18 3736

3737 Between 8A and 8B 11w 3d 26 Jun 18 14 Sep 18 3737


3738 Install Two Number Bollards 1d 27 Jun 18 27 Jun 18 3738
3739 Ironwork to Finish Level 4d 26 Jun 18 29 Jun 18 3739

3740 Kerbing 2w 02 Jul 18 13 Jul 18 3740


3741 Lay Kerbs (100 linear Meters 1w 02 Jul 18 06 Jul 18 3741

3742 Lay Granite Banding (60 linear meters) 3d 09 Jul 18 11 Jul 18 3742

3743 Install Country Bridge 2d 12 Jul 18 13 Jul 18 3743


3744 Paving 8w 4d 16 Jul 18 14 Sep 18 3744

3745 Paving to Central Area (468m2)Mistal 6w 16 Jul 18 24 Aug 18 3745

3746 Install Paving to Eastern Elevation 2w 17 Aug 18 31 Aug 18 3746


3747 Snag and Handover 2w 03 Sep 18 14 Sep 18 3747
3748
3748 Temporary Energy Centre and Ancillary Buildings (Provisional Sum - indicative programme) 103w 4d 18 Jul 16 21 Aug 18
3749 Remedials to DH/DC tranch 2d 25 Sep 17 26 Sep 17 3749

3750 Backfill DH/DC trench 2d 27 Sep 17 28 Sep 17 3750


3751 Excavate for Edge deepening and blind slab areas 1w 1d 27 Sep 17 04 Oct 17 3751
3752 Lay Membrane and insulation 1w 02 Oct 17 06 Oct 17 3752
3753 Premier shutters 1w 04 Oct 17 10 Oct 17 3753
3754 Fix rebar 1w 1d 06 Oct 17 13 Oct 17 3754
3755 Fix HD Bolt cluster 1w 10 Oct 17 16 Oct 17 3755
3756 Pour GF slab 2d 12 Oct 17 17 Oct 17 3756
3757 Pour Upstands 1w 1d 13 Oct 17 24 Oct 17 3757
3758 Install DH/DC pipework outside building and backfill 1w 29 Sep 17 05 Oct 17 3758
3759 Design Freeze on steel work 06 Nov 17 06 Nov 17 3759
3760 Steel Fabrication 4w 06 Nov 17 01 Dec 17 3760
3761 Primary and Secondary steel erection 2w 04 Dec 17 15 Dec 17 3761
3762 Handover to Prater 18 Dec 17 18 Dec 17 3762
3763 Drawing Sign off 06 Nov 17 06 Nov 17 3763
3764 Order Materials 1w 07 Nov 17 13 Nov 17 3764

3765 Fabricate Sheeting 6w 14 Nov 17 03 Jan 18 3765


3766 Erect netting 2d 18 Dec 17 19 Dec 17 3766
3767 Install Roof Sheeting 2w 04 Jan 18 17 Jan 18 3767

3768 Install Wall cladding 3w 4d 18 Jan 18 13 Feb 18 3768


3769 Stitch roofing 1w 18 Jan 18 24 Jan 18 3769

3770 Blockworks 1w 18 Jan 18 24 Jan 18 3770


3771 Floor Finishes (Flowcem, 2days drying time, two coats flowseal 1 day drying between coats and before trafficking) 1w 1d 25 Jan 18 01 Feb 18 3771

3772 Earliest access for Vital Energi 02 Feb 18 02 Feb 18 3772

3773 Construct slab for Estate Management Office 8w 14 Feb 18 12 Apr 18 3773

3774 Install Estates Management Office Modular Units 2w 13 Apr 18 26 Apr 18 3774

3775 Fit out Estates Management Office 16w 30 Apr 18 21 Aug 18 3775

3776 Construct Slab for Cycle Store and Refuse Store 8w 21 Feb 18 19 Apr 18 3776

3777 Install Units for Cycle Store 2w 20 Apr 18 04 May 18 3777

3778 Fit out Cycle Store and Showers 15w 08 May 18 21 Aug 18 3778

3779 Main Utility Underground Services 11w 08 Jan 18 23 Mar 18 3779

3780 M & E Fit Out 26w 02 Feb 18 09 Aug 18 3780

3781 Install Temporary Sub Station 15w 18 Jul 16 31 Oct 16 3781

3782 Drainage and Buried Services to roads and hardstandings for TEC area 10w 09 Oct 17 22 Dec 17 3782

3783 External works to TEC area 16w 03 Jan 18 26 Apr 18 3783

3784 Soft Landscaping 6w 06 Apr 18 21 May 18 3784

3785 Power on To Temporary Substation 27 Jun 18 27 Jun 18 3785

3786 External Landscaping to Buildings 3A & 3B 33w 3d 06 Nov 17 13 Jul 18 3786

3787 External underground Services 8w 06 Nov 17 09 Jan 18 3787

3788 Sub Base to Roads 3w 30 Nov 17 20 Dec 17 3788

3789 Kerbs to Roads 6w 21 Dec 17 09 Feb 18 3789

3790 Sub-Base to Paved Areas 7w 1d 12 Feb 18 04 Apr 18 3790

3791 Hard Landscaping 9w 05 Apr 18 11 Jun 18 3791

3792 Drainage and Gullies to Roads 4w 14 May 18 11 Jun 18 3792

3793 Base Course to Roads 3w 12 Jun 18 02 Jul 18 3793

3794 Wearing Course to Roads 1w 4d 03 Jul 18 13 Jul 18 3794

3795 External Lighting 7w 26 Apr 18 18 Jun 18 3795

3796 Soft Landscaping 8w 18 May 18 13 Jul 18 3796

3797 Complete Buildings 9A, 8A, 8B & Temporary Energy Centre 13 Feb 19 13 Feb 19 3797

3798 Buildings 5A & 5B Works 84w 4d 16 Jun 17 06 Mar 19 3798

3799
3799 Building 5A 77w 2d 26 Jun 17 21 Jan 19
3800 Piling 7w 26 Jun 17 11 Aug 17 3800

3801 Lay Piling Mat 1w 03 Jul 17 07 Jul 17 3801

3802 Lay Crane Mat 2w 26 Jun 17 07 Jul 17 3802

3803 Piling East half 2w 18 Jul 17 31 Jul 17 3803

3804 Piling West half 2w 31 Jul 17 11 Aug 17 3804

3805 Structure 24w 05 Sep 17 28 Feb 18 3805

3806 Substructure 9w 4d 05 Sep 17 10 Nov 17 3806


3807 Core 1 and Adjacent Pile caps 3w 3d 05 Sep 17 28 Sep 17 3807
3808 Excavate 2w 2d 05 Sep 17 20 Sep 17 3808
3809 Break down piles 2w 3d 07 Sep 17 25 Sep 17 3809
3810 FRC Base of Cap 2w 3d 12 Sep 17 28 Sep 17 3810

3811 Core 2 and Adjacent Pile caps 3w 3d 08 Sep 17 03 Oct 17 3811


3812 Excavate 2w 2d 08 Sep 17 25 Sep 17 3812
3813 Break down Piles 2w 3d 11 Sep 17 27 Sep 17 3813
3814 FRC Base of Cap 2w 3d 15 Sep 17 03 Oct 17 3814

3815 Core 3 and Adjacent Pile caps 6w 3d 13 Sep 17 27 Oct 17 3815


3816 Excavate 2w 3d 13 Sep 17 29 Sep 17 3816
3817 Break down Piles 2w 4d 14 Sep 17 03 Oct 17 3817

3818 FRC Base of Cap 2w 3d 20 Sep 17 27 Oct 17 3818

3819 General Pile Caps 4w 4d 26 Sep 17 27 Oct 17 3819

3820 Excavate 3w 26 Sep 17 27 Oct 17 3820


3821 Break down Piles 3w 1d 27 Sep 17 27 Oct 17 3821

3822 FRC Base of Cap 3w 2d 28 Sep 17 27 Oct 17 3822

3823 GroundFloor Slab 4w 3d 11 Oct 17 10 Nov 17 3823

3824 Pour 1 1w 4d 11 Oct 17 23 Oct 17 3824


3825 Pour 2 2w 16 Oct 17 27 Oct 17 3825

3826 Pour 3 1w 3d 25 Oct 17 10 Nov 17 3826


3827 Superstructure 16w 4d 25 Oct 17 28 Feb 18 3827

3828 STAND PRECAST CORE WALLS GND - 1ST FLOOR 1w 1d 26 Oct 17 14 Nov 17 3828

3829 STAND PRECAST COLUMNS GROUND - 1ST FLOOR 2w 2d 25 Oct 17 16 Nov 17 3829

3830 FRC 1ST FLOOR SLAB 3w 3d 25 Oct 17 23 Nov 17 3830

3831 STAND PRECAST CORE WALLS 1ST - 2ND FLOOR 1w 1d 09 Nov 17 24 Nov 17 3831

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3832 STAND PRECAST COLUMNS 1ST - 2ND FLOOR 2w 4d 10 Nov 17 29 Nov 17 3832

3833 FRC 2ND FLOOR SLAB 3w 2d 14 Nov 17 06 Dec 17 3833

3834 STAND PRECAST WALLS 2ND - 3RD FLOOR 1w 1d 22 Nov 17 08 Dec 17 3834

3835 STAND PRECAST COLUMNS 2ND - 3RD FLOOR 2w 2d 23 Nov 17 08 Dec 17 3835

3836 FRC 3RD FLOOR SLAB 3w 2d 27 Nov 17 19 Dec 17 3836

3837 STAND PRECAST CORE WALLS 3RD - 4TH FLOOR 1w 1d 05 Dec 17 21 Dec 17 3837

3838 STAND PRECAST COLUMNS 3RD - 4TH FLOOR 2w 2d 06 Dec 17 21 Dec 17 3838

3839 FRC 4TH FLOOR SLAB 3w 2d 11 Dec 17 11 Jan 18 3839

3840 STAND PRECAST CORE WALLS 4TH - 5TH FLOOR 1w 1d 19 Dec 17 15 Jan 18 3840

3841 STAND PRECAST COLUMNS 4TH - 5TH FLOOR 2w 2d 20 Dec 17 15 Jan 18 3841

3842 FRC 5TH FLOOR SLAB 3w 2d 21 Dec 17 23 Jan 18 3842

3843 STAND PRECAST WALLS 5TH - 6TH FLOOR 1w 1d 09 Jan 18 25 Jan 18 3843

3844 STAND PRECAST COLUMNS 5TH - 6TH FLOOR 2w 2d 11 Jan 18 26 Jan 18 3844

3845 FRC 6TH FLOOR SLAB 3w 1d 16 Jan 18 06 Feb 18 3845

3846 STAND PRECAST CORE WALLS 6TH - ROOF 1w 1d 24 Jan 18 08 Feb 18 3846

3847 STAND PRECAST COLUMNS 6TH - ROOF 2w 2d 29 Jan 18 13 Feb 18 3847

3848 FRC ROOF SLAB 3w 31 Jan 18 20 Feb 18 3848

3849 STAND PRECAST CORE WALL OVERRUNS 1w 1d 07 Feb 18 22 Feb 18 3849

3850 FRC CAPPING SLAB TO CORES 2w 4d 09 Feb 18 28 Feb 18 3850

3851 FRC PERIMETER UPSTAND TO ROOF 3w 08 Feb 18 28 Feb 18 3851

3852 Precast Stairs & Handrails 14w 13 Nov 17 27 Feb 18 3852

3853 Facades 45w 19 Feb 18 21 Jan 19 3853

3854 Precast Cladding 7w 3d 19 Feb 18 13 Apr 18 3854


3855 Precast Cladding Panels South elevation 4w 4d 19 Feb 18 22 Mar 18 3855
3856 1st Half (East Side) 1w 3d 19 Feb 18 28 Feb 18 3856
3857 2nd Half (West Side) 1w 3d 13 Mar 18 22 Mar 18 3857

3858 Precast Cladding Panels North Elevation 4w 4d 01 Mar 18 05 Apr 18 3858

3859 1st Half (East Side) 1w 3d 01 Mar 18 12 Mar 18 3859


3860 2nd Half (West Side) 1w 3d 23 Mar 18 05 Apr 18 3860
3861 Precast Cladding Panels West elevation 3d 06 Apr 18 10 Apr 18 3861

3862 Precast Cladding Panels East elevation 3d 11 Apr 18 13 Apr 18 3862

3863 Mastic Sealing externally 8w 22 Feb 18 20 Apr 18 3863


3864 Windows 24w 4d 23 Mar 18 20 Sep 18 3864
3865 Install SFS, Windows & Cladding L06 8w 3d 23 Mar 18 29 May 18 3865

3866 Install SFS, Windows and cladding to Level 6 South elevation 8w 23 Mar 18 23 May 18 3866

3867 Install SFS, Windows and cladding to Level 6 North elevation 7w 06 Apr 18 29 May 18 3867

3868 Install ribbon window curtain walling to North Elevation 5w 3d 06 Apr 18 17 May 18 3868

3869 Parapet Cladding to Level 7 5w 3d 09 Apr 18 18 May 18 3869

3870 Curtain Walling/ Doors Ground Floor 4w 1d 06 Apr 18 08 May 18 3870

3871 Windows & Shopfronts at Ground 4w 06 Apr 18 04 May 18 3871

3872 External Doors & Louvres at Ground 3w 16 Apr 18 08 May 18 3872

3873 Complete ribbon windows after hoists removed 4w 23 Aug 18 20 Sep 18 3873
3874 Canopies 38w 3d 06 Apr 18 21 Jan 19 3874
3875 Install Frame for the Canopies 1w 06 Apr 18 12 Apr 18 3875
3876 Complete glazing for Canopies 1w 15 Jan 19 21 Jan 19 3876

3877 Roofing 14w 01 Mar 18 13 Jun 18 3877

3878 Erect Terrace Balustrades 2w 01 Mar 18 14 Mar 18 3878

3879 Erect posts for Roof Louvres 2w 01 Mar 18 14 Mar 18 3879

3880 Terrace Slab Waterproofing 1w 2d 15 Mar 18 23 Mar 18 3880

3881 Roof Slab Waterproofing 6w 15 Mar 18 30 Apr 18 3881

3882 Roof Finishes and Mansafe Latchways 7w 09 Apr 18 30 May 18 3882

3883 Install Roof Louvres 6w 16 Apr 18 30 May 18 3883

3884 Access Hatch and ladders 2w 31 May 18 13 Jun 18 3884

3885 Latest Date for ABP/WTP to omit Cat A Shell and Core Services scope of works to Building 5A 30 Oct 17 30 Oct 17 3885

3886 M & E Installation 20w 2d 22 Dec 17 30 May 18 3886

3887 Prefabricated Riser Installation 2w 4d 22 Dec 17 28 Feb 18 3887

3888 Prefabricated Floor Modules Levels G-3 1w 28 Mar 18 05 Apr 18 3888

3889 Installation of Siphonic drainage 2w 21 Feb 18 06 Mar 18 3889

3890 Prefabricated Floor Modules Levels 4-7 1w 01 Mar 18 07 Mar 18 3890

3891 Roof Plant Installation 5A 8w 29 Mar 18 30 May 18 3891

3892 Ground Floor Plant Installation 5A 9w 26 Feb 18 02 May 18 3892

3893 Blockwork 33w 08 Jan 18 03 Sep 18 3893

3894 Main Works 11w 2d 08 Jan 18 27 Mar 18 3894

3895 Blockwork Walls at Ground 3w 08 Jan 18 26 Jan 18 3895

3896 Blockwork Walls at L1 1w 12 Jan 18 18 Jan 18 3896

3897 Blockwork Walls at L2 1w 26 Jan 18 01 Feb 18 3897

3898 Blockwork Walls at L3 1w 07 Feb 18 13 Feb 18 3898

3899 Blockwork Walls at L4 1w 21 Feb 18 27 Feb 18 3899

3900 Blockwork Walls at L5 1w 07 Mar 18 13 Mar 18 3900

3901 Blockwork Walls at L6 1w 21 Mar 18 27 Mar 18 3901

3902 Return Visit 1w 2d 23 Aug 18 03 Sep 18 3902

3903 Level 06 2d 23 Aug 18 24 Aug 18 3903

3904 Level 05 2d 24 Aug 18 28 Aug 18 3904

3905 Level 04 2d 28 Aug 18 29 Aug 18 3905

3906 Level 03 2d 29 Aug 18 30 Aug 18 3906

3907 Level 02 2d 30 Aug 18 31 Aug 18 3907

3908 Level 01 2d 31 Aug 18 03 Sep 18 3908

3909 Hoist 25w 1d 21 Feb 18 22 Aug 18 3909

3910 Window for Cantidecks to load out upper floors 1w 21 Feb 18 27 Feb 18 3910

3911 Hoist 1 11w 4d 02 May 18 25 Jul 18 3911

3912 Hoist 2 13w 09 May 18 08 Aug 18 3912

3913 Hoist 3 12w 4d 24 May 18 22 Aug 18 3913

3914 Lift /Toilet Core Fit Out 57w 3d 30 Oct 17 07 Jan 19 3914

3915 Lifts 57w 3d 30 Oct 17 07 Jan 19 3915

3916 Delivery of temporary lift doors 30 Oct 17 30 Oct 17 3916

3917 Lift 1 10w 01 May 18 11 Jul 18 3917

3918 Lift 1 Guides and doors 8w 01 May 18 27 Jun 18 3918

3919 Lift 1 Car 1w 28 Jun 18 04 Jul 18 3919

3920 Lift 1 Commission 1w 05 Jul 18 11 Jul 18 3920

3921 Lift 2 30w 2d 09 May 18 10 Dec 18 3921

3922 Lift 2 Guides and doors 8w 09 May 18 04 Jul 18 3922

3923 Lift 2 Car 1w 05 Jul 18 11 Jul 18 3923

3924 Lift 2 Commission 1w 12 Jul 18 18 Jul 18 3924

3925 Hand back Lift 2 after builders beneficial use 27 Nov 18 27 Nov 18 3925

3926 Recommission Lift 2 2w 27 Nov 18 10 Dec 18 3926

3927 Lift 3 10w 16 May 18 25 Jul 18 3927

3928 Lift 3 Guides and doors 8w 16 May 18 11 Jul 18 3928

3929 Lift 3 Car 1w 12 Jul 18 18 Jul 18 3929

3930 Lift 3 Commission 1w 19 Jul 18 25 Jul 18 3930

3931 Lift 4 29w 2d 23 May 18 17 Dec 18 3931

3932 Lift 4 Guides and doors 8w 23 May 18 18 Jul 18 3932

3933 Lift 4 Car 1w 19 Jul 18 25 Jul 18 3933

3934 Lift 4 Commission 1w 26 Jul 18 01 Aug 18 3934

3935 Hand back Lift 4 after builders beneficial use 04 Dec 18 04 Dec 18 3935
3936 Recommission Lift 4 2w 04 Dec 18 17 Dec 18 3936

3937 Lift 5 10w 31 May 18 08 Aug 18 3937

3938 Lift 5 Guides and doors 8w 31 May 18 25 Jul 18 3938

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3939 Lift 5 Car 1w 26 Jul 18 01 Aug 18 3939

3940 Lift 5 Commission 1w 02 Aug 18 08 Aug 18 3940

3941 Lift 6 28w 2d 07 Jun 18 07 Jan 19 3941

3942 Lift 6 Guides and doors 8w 07 Jun 18 01 Aug 18 3942

3943 Lift 6 Car 1w 02 Aug 18 08 Aug 18 3943

3944 Lift 6 Commission 1w 09 Aug 18 15 Aug 18 3944

3945 Hand back Lift 6 after builders beneficial use 11 Dec 18 11 Dec 18 3945
3946 Recommission Lift 6 2w 11 Dec 18 07 Jan 19 3946
3947 Toilet & Lobby 22w 29 Mar 18 06 Sep 18 3947

3948 Level 01 - CORE 01 12w 29 Mar 18 27 Jun 18 3948


3949 Toilet 12w 29 Mar 18 27 Jun 18 3949
3950 Floor slab available 29 Mar 18 29 Mar 18 3950

3951 1st Fix Wall with Head tracks 1w 29 Mar 18 06 Apr 18 3951
3952 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 Apr 18 08 May 18 3952

3953 Fix Pocket Doors 1w 09 Apr 18 13 Apr 18 3953


3954 Inspection and Ceiling Grid Clearance 09 May 18 09 May 18 3954
3955 2nd Fix wall 1w 09 May 18 15 May 18 3955
3956 IPS Frame (Box Out only) incl. Backing ply 3d 16 May 18 18 May 18 3956
3957 Screed 2d 21 May 18 22 May 18 3957
3958 Fix Ceiling Grid Works 3d 23 May 18 25 May 18 3958
3959 Floor Tiling Works 3d 29 May 18 31 May 18 3959
3960 Wall Tiling works incl. IPS Panels 3d 01 Jun 18 05 Jun 18 3960
3961 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 06 Jun 18 13 Jun 18 3961
3962 Mark and Cut openings for MEP on walls including Ceiling 2d 14 Jun 18 15 Jun 18 3962
3963 Install Vanity Tops 4d 14 Jun 18 19 Jun 18 3963
3964 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 18 Jun 18 21 Jun 18 3964
3965 Fix MEP Final Fixtures 3d 21 Jun 18 25 Jun 18 3965
3966 Final Coat Paint on Ceiling 2d 26 Jun 18 27 Jun 18 3966
3967 Lobby 9w 1d 04 Apr 18 11 Jun 18 3967
3968 1st Fix Wall with Head tracks 1w 04 Apr 18 10 Apr 18 3968
3969 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 Apr 18 15 May 18 3969
3970 Fix Ceiling Grid 3d 16 May 18 18 May 18 3970
3971 Paint 1st Coat 2d 21 May 18 22 May 18 3971
3972 Fix doors incl. Ironmongery 2d 23 May 18 24 May 18 3972
3973 Mark and Cut openings for MEP on walls 2d 25 May 18 29 May 18 3973
3974 Install Ceiling Tiles 3d 30 May 18 01 Jun 18 3974
3975 Fix MEP Final Fixtures 3d 04 Jun 18 06 Jun 18 3975
3976 Final Coat Paint on walls and ceiling 3d 07 Jun 18 11 Jun 18 3976
3977 Staircase 5w 2d 03 May 18 12 Jun 18 3977
3978 H/L Electrical Containment & Conduits - 1st Fix 2d 03 May 18 04 May 18 3978
3979 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 08 May 18 09 May 18 3979
3980 Ceiling Rose fixing 1d 10 May 18 10 May 18 3980
3981 First Coat Paint on Walls & Ceiliings 2d 23 May 18 24 May 18 3981
3982 MEP Final Fixtures on Wall & Ceilings 2d 07 Jun 18 08 Jun 18 3982
3983 Final Coat Paint on walls & Ceilings 2d 11 Jun 18 12 Jun 18 3983

3984 Level 02 - CORE 01 12w 09 Apr 18 04 Jul 18 3984


3985 Toilet 12w 09 Apr 18 04 Jul 18 3985
3986 1st Fix Wall with Head tracks 1w 09 Apr 18 13 Apr 18 3986
3987 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 Apr 18 15 May 18 3987
3988 Fix Pocket Doors 1w 16 Apr 18 20 Apr 18 3988
3989 Inspection and Ceiling Grid Clearance 16 May 18 16 May 18 3989
3990 2nd Fix wall 1w 16 May 18 22 May 18 3990
3991 IPS Frame (Box Out only) incl. Backing ply 3d 23 May 18 25 May 18 3991
3992 Screed 2d 29 May 18 30 May 18 3992
3993 Fix Ceiling Grid Works 3d 31 May 18 04 Jun 18 3993
3994 Floor Tiling Works 3d 05 Jun 18 07 Jun 18 3994
3995 Wall Tiling works incl. IPS Panels 3d 08 Jun 18 12 Jun 18 3995
3996 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 13 Jun 18 20 Jun 18 3996
3997 Mark and Cut openings for MEP on walls including Ceiling 2d 21 Jun 18 22 Jun 18 3997
3998 Install Vanity Tops 4d 21 Jun 18 26 Jun 18 3998

3999 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 25 Jun 18 28 Jun 18 3999
4000 Fix MEP Final Fixtures 3d 28 Jun 18 02 Jul 18 4000
4001 Final Coat Paint on Ceiling 2d 03 Jul 18 04 Jul 18 4001
4002 Lobby 9w 1d 11 Apr 18 18 Jun 18 4002

4003 1st Fix Wall with Head tracks 1w 11 Apr 18 17 Apr 18 4003

4004 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 Apr 18 22 May 18 4004

4005 Fix Ceiling Grid 3d 23 May 18 25 May 18 4005

4006 Paint 1st Coat 2d 29 May 18 30 May 18 4006

4007 Fix doors incl. Ironmongery 2d 31 May 18 01 Jun 18 4007


4008 Mark and Cut openings for MEP on walls 2d 04 Jun 18 05 Jun 18 4008

4009 Install Ceiling Tiles 3d 06 Jun 18 08 Jun 18 4009

4010 Fix MEP Final Fixtures 3d 11 Jun 18 13 Jun 18 4010


4011 Final Coat Paint on walls and ceiling 3d 14 Jun 18 18 Jun 18 4011
4012 Staircase 5w 2d 11 May 18 19 Jun 18 4012
4013 H/L Electrical Containment & Conduits - 1st Fix 2d 11 May 18 14 May 18 4013
4014 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 15 May 18 16 May 18 4014
4015 Ceiling Rose fixing 1d 17 May 18 17 May 18 4015
4016 First Coat Paint on Walls & Ceiliings 2d 31 May 18 01 Jun 18 4016
4017 MEP Final Fixtures on Wall & Ceilings 2d 14 Jun 18 15 Jun 18 4017
4018 Final Coat Paint on walls & Ceilings 2d 18 Jun 18 19 Jun 18 4018
4019 Level 03 - CORE 01 12w 16 Apr 18 11 Jul 18 4019
4020 Toilet 12w 16 Apr 18 11 Jul 18 4020
4021 1st Fix Wall with Head tracks 1w 16 Apr 18 20 Apr 18 4021
4022 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 Apr 18 22 May 18 4022
4023 Fix Pocket Doors 1w 23 Apr 18 30 Apr 18 4023

4024 Inspection and Ceiling Grid Clearance 23 May 18 23 May 18 4024

4025 2nd Fix wall 1w 23 May 18 30 May 18 4025


4026 IPS Frame (Box Out only) incl. Backing ply 3d 31 May 18 04 Jun 18 4026

4027 Screed 2d 05 Jun 18 06 Jun 18 4027

4028 Fix Ceiling Grid Works 3d 07 Jun 18 11 Jun 18 4028

4029 Floor Tiling Works 3d 12 Jun 18 14 Jun 18 4029

4030 Wall Tiling works incl. IPS Panels 3d 15 Jun 18 19 Jun 18 4030
4031 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 20 Jun 18 27 Jun 18 4031

4032 Mark and Cut openings for MEP on walls including Ceiling 2d 28 Jun 18 29 Jun 18 4032

4033 Install Vanity Tops 4d 28 Jun 18 03 Jul 18 4033

4034 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 02 Jul 18 05 Jul 18 4034

4035 Fix MEP Final Fixtures 3d 05 Jul 18 09 Jul 18 4035


4036 Final Coat Paint on Ceiling 2d 10 Jul 18 11 Jul 18 4036
4037 Lobby 9w 1d 18 Apr 18 25 Jun 18 4037
4038 1st Fix Wall with Head tracks 1w 18 Apr 18 24 Apr 18 4038
4039 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 May 18 30 May 18 4039
4040 Fix Ceiling Grid 3d 31 May 18 04 Jun 18 4040
4041 Paint 1st Coat 2d 05 Jun 18 06 Jun 18 4041
4042 Fix doors incl. Ironmongery 2d 07 Jun 18 08 Jun 18 4042
4043 Mark and Cut openings for MEP on walls 2d 11 Jun 18 12 Jun 18 4043
4044 Install Ceiling Tiles 3d 13 Jun 18 15 Jun 18 4044
4045 Fix MEP Final Fixtures 3d 18 Jun 18 20 Jun 18 4045
4046 Final Coat Paint on walls and ceiling 3d 21 Jun 18 25 Jun 18 4046
4047 Staircase 5w 2d 18 May 18 26 Jun 18 4047

4048 H/L Electrical Containment & Conduits - 1st Fix 2d 18 May 18 21 May 18 4048
4049 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 22 May 18 23 May 18 4049

4050 Ceiling Rose fixing 1d 24 May 18 24 May 18 4050


4051 First Coat Paint on Walls & Ceiliings 2d 07 Jun 18 08 Jun 18 4051

4052 MEP Final Fixtures on Wall & Ceilings 2d 21 Jun 18 22 Jun 18 4052

4053 Final Coat Paint on walls & Ceilings 2d 25 Jun 18 26 Jun 18 4053
4054 Level 04 - CORE 01 12w 23 Apr 18 18 Jul 18 4054

4055 Toilet 12w 23 Apr 18 18 Jul 18 4055


4056 1st Fix Wall with Head tracks 1w 23 Apr 18 30 Apr 18 4056

4057 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 May 18 30 May 18 4057

4058 Fix Pocket Doors 1w 01 May 18 08 May 18 4058


4059 Inspection and Ceiling Grid Clearance 31 May 18 31 May 18 4059
4060 2nd Fix wall 1w 31 May 18 06 Jun 18 4060
4061 IPS Frame (Box Out only) incl. Backing ply 3d 07 Jun 18 11 Jun 18 4061
4062 Screed 2d 12 Jun 18 13 Jun 18 4062
4063 Fix Ceiling Grid Works 3d 14 Jun 18 18 Jun 18 4063
4064 Floor Tiling Works 3d 19 Jun 18 21 Jun 18 4064
4065 Wall Tiling works incl. IPS Panels 3d 22 Jun 18 26 Jun 18 4065
4066 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 27 Jun 18 04 Jul 18 4066
4067 Mark and Cut openings for MEP on walls including Ceiling 2d 05 Jul 18 06 Jul 18 4067
4068 Install Vanity Tops 4d 05 Jul 18 10 Jul 18 4068
4069 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 09 Jul 18 12 Jul 18 4069
4070 Fix MEP Final Fixtures 3d 12 Jul 18 16 Jul 18 4070
4071 Final Coat Paint on Ceiling 2d 17 Jul 18 18 Jul 18 4071
4072 Lobby 9w 1d 25 Apr 18 02 Jul 18 4072

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4073 1st Fix Wall with Head tracks 1w 25 Apr 18 02 May 18 4073
4074 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 4074
4075 Fix Ceiling Grid 3d 07 Jun 18 11 Jun 18 4075
4076 Paint 1st Coat 2d 12 Jun 18 13 Jun 18 4076
4077 Fix doors incl. Ironmongery 2d 14 Jun 18 15 Jun 18 4077
4078 Mark and Cut openings for MEP on walls 2d 18 Jun 18 19 Jun 18 4078
4079 Install Ceiling Tiles 3d 20 Jun 18 22 Jun 18 4079
4080 Fix MEP Final Fixtures 3d 25 Jun 18 27 Jun 18 4080
4081 Final Coat Paint on walls and ceiling 3d 28 Jun 18 02 Jul 18 4081

4082 Staircase 5w 2d 25 May 18 03 Jul 18 4082

4083 H/L Electrical Containment & Conduits - 1st Fix 2d 25 May 18 29 May 18 4083
4084 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 30 May 18 31 May 18 4084

4085 Ceiling Rose fixing 1d 01 Jun 18 01 Jun 18 4085

4086 First Coat Paint on Walls & Ceiliings 2d 14 Jun 18 15 Jun 18 4086

4087 MEP Final Fixtures on Wall & Ceilings 2d 28 Jun 18 29 Jun 18 4087

4088 Final Coat Paint on walls & Ceilings 2d 02 Jul 18 03 Jul 18 4088
4089 Level 05 - CORE 01 12w 01 May 18 25 Jul 18 4089

4090 Toilet 12w 01 May 18 25 Jul 18 4090


4091 1st Fix Wall with Head tracks 1w 01 May 18 08 May 18 4091
4092 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 4092

4093 Fix Pocket Doors 1w 09 May 18 15 May 18 4093


4094 Inspection and Ceiling Grid Clearance 07 Jun 18 07 Jun 18 4094
4095 2nd Fix wall 1w 07 Jun 18 13 Jun 18 4095
4096 IPS Frame (Box Out only) incl. Backing ply 3d 14 Jun 18 18 Jun 18 4096
4097 Screed 2d 19 Jun 18 20 Jun 18 4097
4098 Fix Ceiling Grid Works 3d 21 Jun 18 25 Jun 18 4098
4099 Floor Tiling Works 3d 26 Jun 18 28 Jun 18 4099
4100 Wall Tiling works incl. IPS Panels 3d 29 Jun 18 03 Jul 18 4100
4101 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 04 Jul 18 11 Jul 18 4101
4102 Mark and Cut openings for MEP on walls including Ceiling 2d 12 Jul 18 13 Jul 18 4102
4103 Install Vanity Tops 4d 12 Jul 18 17 Jul 18 4103
4104 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 16 Jul 18 19 Jul 18 4104
4105 Fix MEP Final Fixtures 3d 19 Jul 18 23 Jul 18 4105
4106 Final Coat Paint on Ceiling 2d 24 Jul 18 25 Jul 18 4106

4107 Lobby 9w 1d 03 May 18 09 Jul 18 4107

4108 1st Fix Wall with Head tracks 1w 03 May 18 10 May 18 4108

4109 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 4109

4110 Fix Ceiling Grid 3d 14 Jun 18 18 Jun 18 4110


4111 Paint 1st Coat 2d 19 Jun 18 20 Jun 18 4111

4112 Fix doors incl. Ironmongery 2d 21 Jun 18 22 Jun 18 4112


4113 Mark and Cut openings for MEP on walls 2d 25 Jun 18 26 Jun 18 4113

4114 Install Ceiling Tiles 3d 27 Jun 18 29 Jun 18 4114

4115 Fix MEP Final Fixtures 3d 02 Jul 18 04 Jul 18 4115

4116 Final Coat Paint on walls and ceiling 3d 05 Jul 18 09 Jul 18 4116

4117 Staircase 5w 2d 04 Jun 18 10 Jul 18 4117

4118 H/L Electrical Containment & Conduits - 1st Fix 2d 04 Jun 18 05 Jun 18 4118
4119 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 06 Jun 18 07 Jun 18 4119
4120 Ceiling Rose fixing 1d 08 Jun 18 08 Jun 18 4120
4121 First Coat Paint on Walls & Ceiliings 2d 21 Jun 18 22 Jun 18 4121
4122 MEP Final Fixtures on Wall & Ceilings 2d 05 Jul 18 06 Jul 18 4122
4123 Final Coat Paint on walls & Ceilings 2d 09 Jul 18 10 Jul 18 4123
4124 Level 06 - CORE 01 12w 09 May 18 01 Aug 18 4124
4125 Toilet 12w 09 May 18 01 Aug 18 4125
4126 1st Fix Wall with Head tracks 1w 09 May 18 15 May 18 4126
4127 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 4127
4128 Fix Pocket Doors 1w 16 May 18 22 May 18 4128
4129 Inspection and Ceiling Grid Clearance 14 Jun 18 14 Jun 18 4129
4130 2nd Fix wall 1w 14 Jun 18 20 Jun 18 4130

4131 IPS Frame (Box Out only) incl. Backing ply 3d 21 Jun 18 25 Jun 18 4131
4132 Screed 2d 26 Jun 18 27 Jun 18 4132
4133 Fix Ceiling Grid Works 3d 28 Jun 18 02 Jul 18 4133
4134 Floor Tiling Works 3d 03 Jul 18 05 Jul 18 4134
4135 Wall Tiling works incl. IPS Panels 3d 06 Jul 18 10 Jul 18 4135
4136 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 11 Jul 18 18 Jul 18 4136
4137 Mark and Cut openings for MEP on walls including Ceiling 2d 19 Jul 18 20 Jul 18 4137
4138 Install Vanity Tops 4d 19 Jul 18 24 Jul 18 4138
4139 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 23 Jul 18 26 Jul 18 4139
4140 Fix MEP Final Fixtures 3d 26 Jul 18 30 Jul 18 4140

4141 Final Coat Paint on Ceiling 2d 31 Jul 18 01 Aug 18 4141


4142 Lobby 9w 1d 11 May 18 16 Jul 18 4142
4143 1st Fix Wall with Head tracks 1w 11 May 18 17 May 18 4143
4144 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 4144
4145 Fix Ceiling Grid 3d 21 Jun 18 25 Jun 18 4145
4146 Paint 1st Coat 2d 26 Jun 18 27 Jun 18 4146
4147 Fix doors incl. Ironmongery 2d 28 Jun 18 29 Jun 18 4147
4148 Mark and Cut openings for MEP on walls 2d 02 Jul 18 03 Jul 18 4148
4149 Install Ceiling Tiles 3d 04 Jul 18 06 Jul 18 4149
4150 Fix MEP Final Fixtures 3d 09 Jul 18 11 Jul 18 4150
4151 Final Coat Paint on walls and ceiling 3d 12 Jul 18 16 Jul 18 4151
4152 Staircase 5w 2d 11 Jun 18 17 Jul 18 4152
4153 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Jun 18 12 Jun 18 4153
4154 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Jun 18 14 Jun 18 4154

4155 Ceiling Rose fixing 1d 15 Jun 18 15 Jun 18 4155


4156 First Coat Paint on Walls & Ceiliings 2d 28 Jun 18 29 Jun 18 4156

4157 MEP Final Fixtures on Wall & Ceilings 2d 12 Jul 18 13 Jul 18 4157
4158 Final Coat Paint on walls & Ceilings 2d 16 Jul 18 17 Jul 18 4158
4159 Level GF - CORE 01 12w 16 May 18 08 Aug 18 4159

4160 Toilet 12w 16 May 18 08 Aug 18 4160


4161 1st Fix Wall with Head tracks 1w 16 May 18 22 May 18 4161

4162 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 4162

4163 Fix Pocket Doors 1w 23 May 18 30 May 18 4163

4164 Inspection and Ceiling Grid Clearance 21 Jun 18 21 Jun 18 4164

4165 2nd Fix wall 1w 21 Jun 18 27 Jun 18 4165


4166 IPS Frame (Box Out only) incl. Backing ply 3d 28 Jun 18 02 Jul 18 4166
4167 Screed 2d 03 Jul 18 04 Jul 18 4167
4168 Fix Ceiling Grid Works 3d 05 Jul 18 09 Jul 18 4168
4169 Floor Tiling Works 3d 10 Jul 18 12 Jul 18 4169
4170 Wall Tiling works incl. IPS Panels 3d 13 Jul 18 17 Jul 18 4170
4171 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 18 Jul 18 25 Jul 18 4171
4172 Mark and Cut openings for MEP on walls including Ceiling 2d 26 Jul 18 27 Jul 18 4172
4173 Install Vanity Tops 4d 26 Jul 18 31 Jul 18 4173
4174 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 30 Jul 18 02 Aug 18 4174
4175 Fix MEP Final Fixtures 3d 02 Aug 18 06 Aug 18 4175
4176 Final Coat Paint on Ceiling 2d 07 Aug 18 08 Aug 18 4176
4177 Lobby 9w 1d 18 May 18 23 Jul 18 4177
4178 1st Fix Wall with Head tracks 1w 18 May 18 24 May 18 4178
4179 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 31 May 18 27 Jun 18 4179

4180 Fix Ceiling Grid 3d 28 Jun 18 02 Jul 18 4180

4181 Paint 1st Coat 2d 03 Jul 18 04 Jul 18 4181


4182 Fix doors incl. Ironmongery 2d 05 Jul 18 06 Jul 18 4182

4183 Mark and Cut openings for MEP on walls 2d 09 Jul 18 10 Jul 18 4183
4184 Install Ceiling Tiles 3d 11 Jul 18 13 Jul 18 4184

4185 Fix MEP Final Fixtures 3d 16 Jul 18 18 Jul 18 4185


4186 Final Coat Paint on walls and ceiling 3d 19 Jul 18 23 Jul 18 4186

4187 Staircase 5w 2d 18 Jun 18 24 Jul 18 4187

4188 H/L Electrical Containment & Conduits - 1st Fix 2d 18 Jun 18 19 Jun 18 4188
4189 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 20 Jun 18 21 Jun 18 4189

4190 Ceiling Rose fixing 1d 22 Jun 18 22 Jun 18 4190

4191 First Coat Paint on Walls & Ceiliings 2d 05 Jul 18 06 Jul 18 4191
4192 MEP Final Fixtures on Wall & Ceilings 2d 19 Jul 18 20 Jul 18 4192
4193 Final Coat Paint on walls & Ceilings 2d 23 Jul 18 24 Jul 18 4193

4194 Level 01 - CORE 02 12w 16 Apr 18 11 Jul 18 4194


4195 Toilet 12w 16 Apr 18 11 Jul 18 4195
4196 Floor slab available 16 Apr 18 16 Apr 18 4196
4197 1st Fix Wall with Head tracks 1w 16 Apr 18 20 Apr 18 4197
4198 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 Apr 18 22 May 18 4198
4199 Fix Pocket Doors 1w 23 Apr 18 30 Apr 18 4199
4200 Inspection and Ceiling Grid Clearance 23 May 18 23 May 18 4200
4201 2nd Fix wall 1w 23 May 18 30 May 18 4201
4202 IPS Frame (Box Out only) incl. Backing ply 3d 31 May 18 04 Jun 18 4202
4203 Screed 2d 05 Jun 18 06 Jun 18 4203

4204 Fix Ceiling Grid Works 3d 07 Jun 18 11 Jun 18 4204


4205 Floor Tiling Works 3d 12 Jun 18 14 Jun 18 4205
4206 Wall Tiling works incl. IPS Panels 3d 15 Jun 18 19 Jun 18 4206

4207 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 20 Jun 18 27 Jun 18 4207
4208 Mark and Cut openings for MEP on walls including Ceiling 2d 28 Jun 18 29 Jun 18 4208

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4209 Install Vanity Tops 4d 28 Jun 18 03 Jul 18 4209
4210 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 02 Jul 18 05 Jul 18 4210
4211 Fix MEP Final Fixtures 3d 05 Jul 18 09 Jul 18 4211
4212 Final Coat Paint on Ceiling 2d 10 Jul 18 11 Jul 18 4212
4213 Lobby 9w 1d 18 Apr 18 25 Jun 18 4213
4214 1st Fix Wall with Head tracks 1w 18 Apr 18 24 Apr 18 4214
4215 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 May 18 30 May 18 4215
4216 Fix Ceiling Grid 3d 31 May 18 04 Jun 18 4216
4217 Paint 1st Coat 2d 05 Jun 18 06 Jun 18 4217

4218 Fix doors incl. Ironmongery 2d 07 Jun 18 08 Jun 18 4218

4219 Mark and Cut openings for MEP on walls 2d 11 Jun 18 12 Jun 18 4219
4220 Install Ceiling Tiles 3d 13 Jun 18 15 Jun 18 4220

4221 Fix MEP Final Fixtures 3d 18 Jun 18 20 Jun 18 4221

4222 Final Coat Paint on walls and ceiling 3d 21 Jun 18 25 Jun 18 4222

4223 Staircase 5w 2d 18 May 18 26 Jun 18 4223

4224 H/L Electrical Containment & Conduits - 1st Fix 2d 18 May 18 21 May 18 4224

4225 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 22 May 18 23 May 18 4225

4226 Ceiling Rose fixing 1d 24 May 18 24 May 18 4226


4227 First Coat Paint on Walls & Ceiliings 2d 07 Jun 18 08 Jun 18 4227
4228 MEP Final Fixtures on Wall & Ceilings 2d 21 Jun 18 22 Jun 18 4228
4229 Final Coat Paint on walls & Ceilings 2d 25 Jun 18 26 Jun 18 4229
4230 Level 02 - CORE 02 12w 23 Apr 18 18 Jul 18 4230
4231 Toilet 12w 23 Apr 18 18 Jul 18 4231
4232 1st Fix Wall with Head tracks 1w 23 Apr 18 30 Apr 18 4232
4233 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 May 18 30 May 18 4233
4234 Fix Pocket Doors 1w 01 May 18 08 May 18 4234
4235 Inspection and Ceiling Grid Clearance 31 May 18 31 May 18 4235
4236 2nd Fix wall 1w 31 May 18 06 Jun 18 4236
4237 IPS Frame (Box Out only) incl. Backing ply 3d 07 Jun 18 11 Jun 18 4237
4238 Screed 2d 12 Jun 18 13 Jun 18 4238
4239 Fix Ceiling Grid Works 3d 14 Jun 18 18 Jun 18 4239
4240 Floor Tiling Works 3d 19 Jun 18 21 Jun 18 4240
4241 Wall Tiling works incl. IPS Panels 3d 22 Jun 18 26 Jun 18 4241
4242 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 27 Jun 18 04 Jul 18 4242

4243 Mark and Cut openings for MEP on walls including Ceiling 2d 05 Jul 18 06 Jul 18 4243

4244 Install Vanity Tops 4d 05 Jul 18 10 Jul 18 4244

4245 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 09 Jul 18 12 Jul 18 4245
4246 Fix MEP Final Fixtures 3d 12 Jul 18 16 Jul 18 4246
4247 Final Coat Paint on Ceiling 2d 17 Jul 18 18 Jul 18 4247

4248 Lobby 9w 1d 25 Apr 18 02 Jul 18 4248


4249 1st Fix Wall with Head tracks 1w 25 Apr 18 02 May 18 4249
4250 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 4250

4251 Fix Ceiling Grid 3d 07 Jun 18 11 Jun 18 4251


4252 Paint 1st Coat 2d 12 Jun 18 13 Jun 18 4252

4253 Fix doors incl. Ironmongery 2d 14 Jun 18 15 Jun 18 4253


4254 Mark and Cut openings for MEP on walls 2d 18 Jun 18 19 Jun 18 4254
4255 Install Ceiling Tiles 3d 20 Jun 18 22 Jun 18 4255
4256 Fix MEP Final Fixtures 3d 25 Jun 18 27 Jun 18 4256
4257 Final Coat Paint on walls and ceiling 3d 28 Jun 18 02 Jul 18 4257
4258 Staircase 5w 2d 25 May 18 03 Jul 18 4258
4259 H/L Electrical Containment & Conduits - 1st Fix 2d 25 May 18 29 May 18 4259
4260 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 30 May 18 31 May 18 4260
4261 Ceiling Rose fixing 1d 01 Jun 18 01 Jun 18 4261
4262 First Coat Paint on Walls & Ceiliings 2d 14 Jun 18 15 Jun 18 4262
4263 MEP Final Fixtures on Wall & Ceilings 2d 28 Jun 18 29 Jun 18 4263
4264 Final Coat Paint on walls & Ceilings 2d 02 Jul 18 03 Jul 18 4264
4265 Level 03 - CORE 02 12w 01 May 18 25 Jul 18 4265

4266 Toilet 12w 01 May 18 25 Jul 18 4266

4267 1st Fix Wall with Head tracks 1w 01 May 18 08 May 18 4267

4268 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 4268
4269 Fix Pocket Doors 1w 09 May 18 15 May 18 4269

4270 Inspection and Ceiling Grid Clearance 07 Jun 18 07 Jun 18 4270


4271 2nd Fix wall 1w 07 Jun 18 13 Jun 18 4271
4272 IPS Frame (Box Out only) incl. Backing ply 3d 14 Jun 18 18 Jun 18 4272
4273 Screed 2d 19 Jun 18 20 Jun 18 4273

4274 Fix Ceiling Grid Works 3d 21 Jun 18 25 Jun 18 4274


4275 Floor Tiling Works 3d 26 Jun 18 28 Jun 18 4275

4276 Wall Tiling works incl. IPS Panels 3d 29 Jun 18 03 Jul 18 4276

4277 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 04 Jul 18 11 Jul 18 4277

4278 Mark and Cut openings for MEP on walls including Ceiling 2d 12 Jul 18 13 Jul 18 4278
4279 Install Vanity Tops 4d 12 Jul 18 17 Jul 18 4279
4280 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 16 Jul 18 19 Jul 18 4280
4281 Fix MEP Final Fixtures 3d 19 Jul 18 23 Jul 18 4281
4282 Final Coat Paint on Ceiling 2d 24 Jul 18 25 Jul 18 4282
4283 Lobby 9w 1d 03 May 18 09 Jul 18 4283
4284 1st Fix Wall with Head tracks 1w 03 May 18 10 May 18 4284
4285 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 4285
4286 Fix Ceiling Grid 3d 14 Jun 18 18 Jun 18 4286
4287 Paint 1st Coat 2d 19 Jun 18 20 Jun 18 4287
4288 Fix doors incl. Ironmongery 2d 21 Jun 18 22 Jun 18 4288
4289 Mark and Cut openings for MEP on walls 2d 25 Jun 18 26 Jun 18 4289
4290 Install Ceiling Tiles 3d 27 Jun 18 29 Jun 18 4290

4291 Fix MEP Final Fixtures 3d 02 Jul 18 04 Jul 18 4291

4292 Final Coat Paint on walls and ceiling 3d 05 Jul 18 09 Jul 18 4292

4293 Staircase 5w 2d 04 Jun 18 10 Jul 18 4293

4294 H/L Electrical Containment & Conduits - 1st Fix 2d 04 Jun 18 05 Jun 18 4294
4295 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 06 Jun 18 07 Jun 18 4295

4296 Ceiling Rose fixing 1d 08 Jun 18 08 Jun 18 4296


4297 First Coat Paint on Walls & Ceiliings 2d 21 Jun 18 22 Jun 18 4297

4298 MEP Final Fixtures on Wall & Ceilings 2d 05 Jul 18 06 Jul 18 4298

4299 Final Coat Paint on walls & Ceilings 2d 09 Jul 18 10 Jul 18 4299

4300 Level 04 - CORE 02 12w 09 May 18 01 Aug 18 4300


4301 Toilet 12w 09 May 18 01 Aug 18 4301
4302 1st Fix Wall with Head tracks 1w 09 May 18 15 May 18 4302
4303 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 4303
4304 Fix Pocket Doors 1w 16 May 18 22 May 18 4304
4305 Inspection and Ceiling Grid Clearance 14 Jun 18 14 Jun 18 4305
4306 2nd Fix wall 1w 14 Jun 18 20 Jun 18 4306
4307 IPS Frame (Box Out only) incl. Backing ply 3d 21 Jun 18 25 Jun 18 4307
4308 Screed 2d 26 Jun 18 27 Jun 18 4308
4309 Fix Ceiling Grid Works 3d 28 Jun 18 02 Jul 18 4309
4310 Floor Tiling Works 3d 03 Jul 18 05 Jul 18 4310
4311 Wall Tiling works incl. IPS Panels 3d 06 Jul 18 10 Jul 18 4311
4312 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 11 Jul 18 18 Jul 18 4312
4313 Mark and Cut openings for MEP on walls including Ceiling 2d 19 Jul 18 20 Jul 18 4313
4314 Install Vanity Tops 4d 19 Jul 18 24 Jul 18 4314
4315 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 23 Jul 18 26 Jul 18 4315

4316 Fix MEP Final Fixtures 3d 26 Jul 18 30 Jul 18 4316


4317 Final Coat Paint on Ceiling 2d 31 Jul 18 01 Aug 18 4317
4318 Lobby 9w 1d 11 May 18 16 Jul 18 4318
4319 1st Fix Wall with Head tracks 1w 11 May 18 17 May 18 4319
4320 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 4320

4321 Fix Ceiling Grid 3d 21 Jun 18 25 Jun 18 4321


4322 Paint 1st Coat 2d 26 Jun 18 27 Jun 18 4322

4323 Fix doors incl. Ironmongery 2d 28 Jun 18 29 Jun 18 4323

4324 Mark and Cut openings for MEP on walls 2d 02 Jul 18 03 Jul 18 4324
4325 Install Ceiling Tiles 3d 04 Jul 18 06 Jul 18 4325

4326 Fix MEP Final Fixtures 3d 09 Jul 18 11 Jul 18 4326


4327 Final Coat Paint on walls and ceiling 3d 12 Jul 18 16 Jul 18 4327
4328 Staircase 5w 2d 11 Jun 18 17 Jul 18 4328
4329 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Jun 18 12 Jun 18 4329
4330 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Jun 18 14 Jun 18 4330
4331 Ceiling Rose fixing 1d 15 Jun 18 15 Jun 18 4331
4332 First Coat Paint on Walls & Ceiliings 2d 28 Jun 18 29 Jun 18 4332
4333 MEP Final Fixtures on Wall & Ceilings 2d 12 Jul 18 13 Jul 18 4333
4334 Final Coat Paint on walls & Ceilings 2d 16 Jul 18 17 Jul 18 4334
4335 Level 05 - CORE 02 12w 16 May 18 08 Aug 18 4335
4336 Toilet 12w 16 May 18 08 Aug 18 4336
4337 1st Fix Wall with Head tracks 1w 16 May 18 22 May 18 4337
4338 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 4338

4339 Fix Pocket Doors 1w 23 May 18 30 May 18 4339


4340 Inspection and Ceiling Grid Clearance 21 Jun 18 21 Jun 18 4340

4341 2nd Fix wall 1w 21 Jun 18 27 Jun 18 4341


4342 IPS Frame (Box Out only) incl. Backing ply 3d 28 Jun 18 02 Jul 18 4342
4343 Screed 2d 03 Jul 18 04 Jul 18 4343

4344 Fix Ceiling Grid Works 3d 05 Jul 18 09 Jul 18 4344


4345 Floor Tiling Works 3d 10 Jul 18 12 Jul 18 4345

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4346 Wall Tiling works incl. IPS Panels 3d 13 Jul 18 17 Jul 18 4346
4347 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 18 Jul 18 25 Jul 18 4347
4348 Mark and Cut openings for MEP on walls including Ceiling 2d 26 Jul 18 27 Jul 18 4348
4349 Install Vanity Tops 4d 26 Jul 18 31 Jul 18 4349
4350 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 30 Jul 18 02 Aug 18 4350
4351 Fix MEP Final Fixtures 3d 02 Aug 18 06 Aug 18 4351
4352 Final Coat Paint on Ceiling 2d 07 Aug 18 08 Aug 18 4352
4353 Lobby 9w 1d 18 May 18 23 Jul 18 4353
4354 1st Fix Wall with Head tracks 1w 18 May 18 24 May 18 4354

4355 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 31 May 18 27 Jun 18 4355

4356 Fix Ceiling Grid 3d 28 Jun 18 02 Jul 18 4356


4357 Paint 1st Coat 2d 03 Jul 18 04 Jul 18 4357

4358 Fix doors incl. Ironmongery 2d 05 Jul 18 06 Jul 18 4358

4359 Mark and Cut openings for MEP on walls 2d 09 Jul 18 10 Jul 18 4359

4360 Install Ceiling Tiles 3d 11 Jul 18 13 Jul 18 4360

4361 Fix MEP Final Fixtures 3d 16 Jul 18 18 Jul 18 4361

4362 Final Coat Paint on walls and ceiling 3d 19 Jul 18 23 Jul 18 4362

4363 Staircase 5w 2d 18 Jun 18 24 Jul 18 4363


4364 H/L Electrical Containment & Conduits - 1st Fix 2d 18 Jun 18 19 Jun 18 4364
4365 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 20 Jun 18 21 Jun 18 4365
4366 Ceiling Rose fixing 1d 22 Jun 18 22 Jun 18 4366
4367 First Coat Paint on Walls & Ceiliings 2d 05 Jul 18 06 Jul 18 4367
4368 MEP Final Fixtures on Wall & Ceilings 2d 19 Jul 18 20 Jul 18 4368
4369 Final Coat Paint on walls & Ceilings 2d 23 Jul 18 24 Jul 18 4369
4370 Level 06 - CORE 02 12w 23 May 18 15 Aug 18 4370
4371 Toilet 12w 23 May 18 15 Aug 18 4371
4372 1st Fix Wall with Head tracks 1w 23 May 18 30 May 18 4372
4373 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 31 May 18 27 Jun 18 4373
4374 Fix Pocket Doors 1w 31 May 18 06 Jun 18 4374
4375 Inspection and Ceiling Grid Clearance 28 Jun 18 28 Jun 18 4375
4376 2nd Fix wall 1w 28 Jun 18 04 Jul 18 4376
4377 IPS Frame (Box Out only) incl. Backing ply 3d 05 Jul 18 09 Jul 18 4377
4378 Screed 2d 10 Jul 18 11 Jul 18 4378
4379 Fix Ceiling Grid Works 3d 12 Jul 18 16 Jul 18 4379

4380 Floor Tiling Works 3d 17 Jul 18 19 Jul 18 4380

4381 Wall Tiling works incl. IPS Panels 3d 20 Jul 18 24 Jul 18 4381

4382 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 25 Jul 18 01 Aug 18 4382

4383 Mark and Cut openings for MEP on walls including Ceiling 2d 02 Aug 18 03 Aug 18 4383
4384 Install Vanity Tops 4d 02 Aug 18 07 Aug 18 4384

4385 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 06 Aug 18 09 Aug 18 4385
4386 Fix MEP Final Fixtures 3d 09 Aug 18 13 Aug 18 4386

4387 Final Coat Paint on Ceiling 2d 14 Aug 18 15 Aug 18 4387

4388 Lobby 9w 1d 25 May 18 30 Jul 18 4388

4389 1st Fix Wall with Head tracks 1w 25 May 18 01 Jun 18 4389

4390 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 07 Jun 18 04 Jul 18 4390
4391 Fix Ceiling Grid 3d 05 Jul 18 09 Jul 18 4391
4392 Paint 1st Coat 2d 10 Jul 18 11 Jul 18 4392
4393 Fix doors incl. Ironmongery 2d 12 Jul 18 13 Jul 18 4393
4394 Mark and Cut openings for MEP on walls 2d 16 Jul 18 17 Jul 18 4394
4395 Install Ceiling Tiles 3d 18 Jul 18 20 Jul 18 4395
4396 Fix MEP Final Fixtures 3d 23 Jul 18 25 Jul 18 4396
4397 Final Coat Paint on walls and ceiling 3d 26 Jul 18 30 Jul 18 4397
4398 Staircase 5w 2d 25 Jun 18 31 Jul 18 4398
4399 H/L Electrical Containment & Conduits - 1st Fix 2d 25 Jun 18 26 Jun 18 4399
4400 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 27 Jun 18 28 Jun 18 4400
4401 Ceiling Rose fixing 1d 29 Jun 18 29 Jun 18 4401
4402 First Coat Paint on Walls & Ceiliings 2d 12 Jul 18 13 Jul 18 4402

4403 MEP Final Fixtures on Wall & Ceilings 2d 26 Jul 18 27 Jul 18 4403

4404 Final Coat Paint on walls & Ceilings 2d 30 Jul 18 31 Jul 18 4404

4405 Level GF - CORE 02 12w 31 May 18 22 Aug 18 4405


4406 Toilet 12w 31 May 18 22 Aug 18 4406
4407 1st Fix Wall with Head tracks 1w 31 May 18 06 Jun 18 4407
4408 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 07 Jun 18 04 Jul 18 4408
4409 Fix Pocket Doors 1w 07 Jun 18 13 Jun 18 4409
4410 Inspection and Ceiling Grid Clearance 05 Jul 18 05 Jul 18 4410
4411 2nd Fix wall 1w 05 Jul 18 11 Jul 18 4411
4412 IPS Frame (Box Out only) incl. Backing ply 3d 12 Jul 18 16 Jul 18 4412
4413 Screed 2d 17 Jul 18 18 Jul 18 4413

4414 Fix Ceiling Grid Works 3d 19 Jul 18 23 Jul 18 4414


4415 Floor Tiling Works 3d 24 Jul 18 26 Jul 18 4415
4416 Wall Tiling works incl. IPS Panels 3d 27 Jul 18 31 Jul 18 4416
4417 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 01 Aug 18 08 Aug 18 4417
4418 Mark and Cut openings for MEP on walls including Ceiling 2d 09 Aug 18 10 Aug 18 4418
4419 Install Vanity Tops 4d 09 Aug 18 14 Aug 18 4419
4420 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 13 Aug 18 16 Aug 18 4420
4421 Fix MEP Final Fixtures 3d 16 Aug 18 20 Aug 18 4421
4422 Final Coat Paint on Ceiling 2d 21 Aug 18 22 Aug 18 4422
4423 Lobby 9w 1d 04 Jun 18 06 Aug 18 4423
4424 1st Fix Wall with Head tracks 1w 04 Jun 18 08 Jun 18 4424
4425 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 14 Jun 18 11 Jul 18 4425
4426 Fix Ceiling Grid 3d 12 Jul 18 16 Jul 18 4426
4427 Paint 1st Coat 2d 17 Jul 18 18 Jul 18 4427

4428 Fix doors incl. Ironmongery 2d 19 Jul 18 20 Jul 18 4428


4429 Mark and Cut openings for MEP on walls 2d 23 Jul 18 24 Jul 18 4429

4430 Install Ceiling Tiles 3d 25 Jul 18 27 Jul 18 4430


4431 Fix MEP Final Fixtures 3d 30 Jul 18 01 Aug 18 4431
4432 Final Coat Paint on walls and ceiling 3d 02 Aug 18 06 Aug 18 4432
4433 Staircase 5w 2d 02 Jul 18 07 Aug 18 4433
4434 H/L Electrical Containment & Conduits - 1st Fix 2d 02 Jul 18 03 Jul 18 4434

4435 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 04 Jul 18 05 Jul 18 4435

4436 Ceiling Rose fixing 1d 06 Jul 18 06 Jul 18 4436

4437 First Coat Paint on Walls & Ceiliings 2d 19 Jul 18 20 Jul 18 4437

4438 MEP Final Fixtures on Wall & Ceilings 2d 02 Aug 18 03 Aug 18 4438
4439 Final Coat Paint on walls & Ceilings 2d 06 Aug 18 07 Aug 18 4439

4440 Level 01 - CORE 03 12w 01 May 18 25 Jul 18 4440


4441 Toilet 12w 01 May 18 25 Jul 18 4441
4442 Floor slab available 01 May 18 01 May 18 4442
4443 1st Fix Wall with Head tracks 1w 01 May 18 08 May 18 4443
4444 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 4444
4445 Fix Pocket Doors 1w 09 May 18 15 May 18 4445
4446 Inspection and Ceiling Grid Clearance 07 Jun 18 07 Jun 18 4446
4447 2nd Fix wall 1w 07 Jun 18 13 Jun 18 4447
4448 IPS Frame (Box Out only) incl. Backing ply 3d 14 Jun 18 18 Jun 18 4448
4449 Screed 2d 19 Jun 18 20 Jun 18 4449
4450 Fix Ceiling Grid Works 3d 21 Jun 18 25 Jun 18 4450
4451 Floor Tiling Works 3d 26 Jun 18 28 Jun 18 4451

4452 Wall Tiling works incl. IPS Panels 3d 29 Jun 18 03 Jul 18 4452

4453 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 04 Jul 18 11 Jul 18 4453
4454 Mark and Cut openings for MEP on walls including Ceiling 2d 12 Jul 18 13 Jul 18 4454

4455 Install Vanity Tops 4d 12 Jul 18 17 Jul 18 4455


4456 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 16 Jul 18 19 Jul 18 4456

4457 Fix MEP Final Fixtures 3d 19 Jul 18 23 Jul 18 4457


4458 Final Coat Paint on Ceiling 2d 24 Jul 18 25 Jul 18 4458

4459 Lobby 9w 1d 03 May 18 09 Jul 18 4459

4460 1st Fix Wall with Head tracks 1w 03 May 18 10 May 18 4460
4461 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 4461

4462 Fix Ceiling Grid 3d 14 Jun 18 18 Jun 18 4462


4463 Paint 1st Coat 2d 19 Jun 18 20 Jun 18 4463
4464 Fix doors incl. Ironmongery 2d 21 Jun 18 22 Jun 18 4464
4465 Mark and Cut openings for MEP on walls 2d 25 Jun 18 26 Jun 18 4465
4466 Install Ceiling Tiles 3d 27 Jun 18 29 Jun 18 4466
4467 Fix MEP Final Fixtures 3d 02 Jul 18 04 Jul 18 4467
4468 Final Coat Paint on walls and ceiling 3d 05 Jul 18 09 Jul 18 4468
4469 Staircase 5w 2d 04 Jun 18 10 Jul 18 4469
4470 H/L Electrical Containment & Conduits - 1st Fix 2d 04 Jun 18 05 Jun 18 4470
4471 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 06 Jun 18 07 Jun 18 4471
4472 Ceiling Rose fixing 1d 08 Jun 18 08 Jun 18 4472
4473 First Coat Paint on Walls & Ceiliings 2d 21 Jun 18 22 Jun 18 4473
4474 MEP Final Fixtures on Wall & Ceilings 2d 05 Jul 18 06 Jul 18 4474

4475 Final Coat Paint on walls & Ceilings 2d 09 Jul 18 10 Jul 18 4475
4476 Level 02 - CORE 03 12w 09 May 18 01 Aug 18 4476

4477 Toilet 12w 09 May 18 01 Aug 18 4477


4478 1st Fix Wall with Head tracks 1w 09 May 18 15 May 18 4478
4479 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 4479

4480 Fix Pocket Doors 1w 16 May 18 22 May 18 4480


4481 Inspection and Ceiling Grid Clearance 14 Jun 18 14 Jun 18 4481

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4482 2nd Fix wall 1w 14 Jun 18 20 Jun 18 4482
4483 IPS Frame (Box Out only) incl. Backing ply 3d 21 Jun 18 25 Jun 18 4483
4484 Screed 2d 26 Jun 18 27 Jun 18 4484
4485 Fix Ceiling Grid Works 3d 28 Jun 18 02 Jul 18 4485
4486 Floor Tiling Works 3d 03 Jul 18 05 Jul 18 4486
4487 Wall Tiling works incl. IPS Panels 3d 06 Jul 18 10 Jul 18 4487
4488 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 11 Jul 18 18 Jul 18 4488
4489 Mark and Cut openings for MEP on walls including Ceiling 2d 19 Jul 18 20 Jul 18 4489
4490 Install Vanity Tops 4d 19 Jul 18 24 Jul 18 4490

4491 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 23 Jul 18 26 Jul 18 4491

4492 Fix MEP Final Fixtures 3d 26 Jul 18 30 Jul 18 4492


4493 Final Coat Paint on Ceiling 2d 31 Jul 18 01 Aug 18 4493

4494 Lobby 9w 1d 11 May 18 16 Jul 18 4494

4495 1st Fix Wall with Head tracks 1w 11 May 18 17 May 18 4495

4496 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 4496

4497 Fix Ceiling Grid 3d 21 Jun 18 25 Jun 18 4497

4498 Paint 1st Coat 2d 26 Jun 18 27 Jun 18 4498

4499 Fix doors incl. Ironmongery 2d 28 Jun 18 29 Jun 18 4499


4500 Mark and Cut openings for MEP on walls 2d 02 Jul 18 03 Jul 18 4500
4501 Install Ceiling Tiles 3d 04 Jul 18 06 Jul 18 4501
4502 Fix MEP Final Fixtures 3d 09 Jul 18 11 Jul 18 4502
4503 Final Coat Paint on walls and ceiling 3d 12 Jul 18 16 Jul 18 4503
4504 Staircase 5w 2d 11 Jun 18 17 Jul 18 4504
4505 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Jun 18 12 Jun 18 4505
4506 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Jun 18 14 Jun 18 4506
4507 Ceiling Rose fixing 1d 15 Jun 18 15 Jun 18 4507
4508 First Coat Paint on Walls & Ceiliings 2d 28 Jun 18 29 Jun 18 4508
4509 MEP Final Fixtures on Wall & Ceilings 2d 12 Jul 18 13 Jul 18 4509
4510 Final Coat Paint on walls & Ceilings 2d 16 Jul 18 17 Jul 18 4510
4511 Level 03 - CORE 03 12w 16 May 18 08 Aug 18 4511
4512 Toilet 12w 16 May 18 08 Aug 18 4512
4513 1st Fix Wall with Head tracks 1w 16 May 18 22 May 18 4513
4514 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 4514
4515 Fix Pocket Doors 1w 23 May 18 30 May 18 4515

4516 Inspection and Ceiling Grid Clearance 21 Jun 18 21 Jun 18 4516

4517 2nd Fix wall 1w 21 Jun 18 27 Jun 18 4517

4518 IPS Frame (Box Out only) incl. Backing ply 3d 28 Jun 18 02 Jul 18 4518
4519 Screed 2d 03 Jul 18 04 Jul 18 4519
4520 Fix Ceiling Grid Works 3d 05 Jul 18 09 Jul 18 4520

4521 Floor Tiling Works 3d 10 Jul 18 12 Jul 18 4521


4522 Wall Tiling works incl. IPS Panels 3d 13 Jul 18 17 Jul 18 4522
4523 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 18 Jul 18 25 Jul 18 4523

4524 Mark and Cut openings for MEP on walls including Ceiling 2d 26 Jul 18 27 Jul 18 4524
4525 Install Vanity Tops 4d 26 Jul 18 31 Jul 18 4525

4526 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 30 Jul 18 02 Aug 18 4526
4527 Fix MEP Final Fixtures 3d 02 Aug 18 06 Aug 18 4527
4528 Final Coat Paint on Ceiling 2d 07 Aug 18 08 Aug 18 4528
4529 Lobby 9w 1d 18 May 18 23 Jul 18 4529
4530 1st Fix Wall with Head tracks 1w 18 May 18 24 May 18 4530
4531 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 31 May 18 27 Jun 18 4531
4532 Fix Ceiling Grid 3d 28 Jun 18 02 Jul 18 4532
4533 Paint 1st Coat 2d 03 Jul 18 04 Jul 18 4533
4534 Fix doors incl. Ironmongery 2d 05 Jul 18 06 Jul 18 4534
4535 Mark and Cut openings for MEP on walls 2d 09 Jul 18 10 Jul 18 4535
4536 Install Ceiling Tiles 3d 11 Jul 18 13 Jul 18 4536
4537 Fix MEP Final Fixtures 3d 16 Jul 18 18 Jul 18 4537
4538 Final Coat Paint on walls and ceiling 3d 19 Jul 18 23 Jul 18 4538
4539 Staircase 5w 2d 18 Jun 18 24 Jul 18 4539

4540 H/L Electrical Containment & Conduits - 1st Fix 2d 18 Jun 18 19 Jun 18 4540

4541 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 20 Jun 18 21 Jun 18 4541

4542 Ceiling Rose fixing 1d 22 Jun 18 22 Jun 18 4542

4543 First Coat Paint on Walls & Ceiliings 2d 05 Jul 18 06 Jul 18 4543

4544 MEP Final Fixtures on Wall & Ceilings 2d 19 Jul 18 20 Jul 18 4544
4545 Final Coat Paint on walls & Ceilings 2d 23 Jul 18 24 Jul 18 4545

4546 Level 04 - CORE 03 12w 23 May 18 15 Aug 18 4546

4547 Toilet 12w 23 May 18 15 Aug 18 4547


4548 1st Fix Wall with Head tracks 1w 23 May 18 30 May 18 4548

4549 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 31 May 18 27 Jun 18 4549

4550 Fix Pocket Doors 1w 31 May 18 06 Jun 18 4550

4551 Inspection and Ceiling Grid Clearance 28 Jun 18 28 Jun 18 4551


4552 2nd Fix wall 1w 28 Jun 18 04 Jul 18 4552
4553 IPS Frame (Box Out only) incl. Backing ply 3d 05 Jul 18 09 Jul 18 4553
4554 Screed 2d 10 Jul 18 11 Jul 18 4554
4555 Fix Ceiling Grid Works 3d 12 Jul 18 16 Jul 18 4555
4556 Floor Tiling Works 3d 17 Jul 18 19 Jul 18 4556
4557 Wall Tiling works incl. IPS Panels 3d 20 Jul 18 24 Jul 18 4557
4558 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 25 Jul 18 01 Aug 18 4558
4559 Mark and Cut openings for MEP on walls including Ceiling 2d 02 Aug 18 03 Aug 18 4559
4560 Install Vanity Tops 4d 02 Aug 18 07 Aug 18 4560
4561 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 06 Aug 18 09 Aug 18 4561
4562 Fix MEP Final Fixtures 3d 09 Aug 18 13 Aug 18 4562
4563 Final Coat Paint on Ceiling 2d 14 Aug 18 15 Aug 18 4563

4564 Lobby 9w 1d 25 May 18 30 Jul 18 4564

4565 1st Fix Wall with Head tracks 1w 25 May 18 01 Jun 18 4565

4566 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 07 Jun 18 04 Jul 18 4566

4567 Fix Ceiling Grid 3d 05 Jul 18 09 Jul 18 4567


4568 Paint 1st Coat 2d 10 Jul 18 11 Jul 18 4568

4569 Fix doors incl. Ironmongery 2d 12 Jul 18 13 Jul 18 4569


4570 Mark and Cut openings for MEP on walls 2d 16 Jul 18 17 Jul 18 4570

4571 Install Ceiling Tiles 3d 18 Jul 18 20 Jul 18 4571

4572 Fix MEP Final Fixtures 3d 23 Jul 18 25 Jul 18 4572

4573 Final Coat Paint on walls and ceiling 3d 26 Jul 18 30 Jul 18 4573

4574 Staircase 5w 2d 25 Jun 18 31 Jul 18 4574

4575 H/L Electrical Containment & Conduits - 1st Fix 2d 25 Jun 18 26 Jun 18 4575
4576 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 27 Jun 18 28 Jun 18 4576
4577 Ceiling Rose fixing 1d 29 Jun 18 29 Jun 18 4577
4578 First Coat Paint on Walls & Ceiliings 2d 12 Jul 18 13 Jul 18 4578
4579 MEP Final Fixtures on Wall & Ceilings 2d 26 Jul 18 27 Jul 18 4579
4580 Final Coat Paint on walls & Ceilings 2d 30 Jul 18 31 Jul 18 4580
4581 Level 05 - CORE 03 12w 31 May 18 22 Aug 18 4581
4582 Toilet 12w 31 May 18 22 Aug 18 4582
4583 1st Fix Wall with Head tracks 1w 31 May 18 06 Jun 18 4583
4584 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 07 Jun 18 04 Jul 18 4584
4585 Fix Pocket Doors 1w 07 Jun 18 13 Jun 18 4585
4586 Inspection and Ceiling Grid Clearance 05 Jul 18 05 Jul 18 4586
4587 2nd Fix wall 1w 05 Jul 18 11 Jul 18 4587
4588 IPS Frame (Box Out only) incl. Backing ply 3d 12 Jul 18 16 Jul 18 4588

4589 Screed 2d 17 Jul 18 18 Jul 18 4589


4590 Fix Ceiling Grid Works 3d 19 Jul 18 23 Jul 18 4590
4591 Floor Tiling Works 3d 24 Jul 18 26 Jul 18 4591
4592 Wall Tiling works incl. IPS Panels 3d 27 Jul 18 31 Jul 18 4592
4593 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 01 Aug 18 08 Aug 18 4593

4594 Mark and Cut openings for MEP on walls including Ceiling 2d 09 Aug 18 10 Aug 18 4594
4595 Install Vanity Tops 4d 09 Aug 18 14 Aug 18 4595

4596 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 13 Aug 18 16 Aug 18 4596

4597 Fix MEP Final Fixtures 3d 16 Aug 18 20 Aug 18 4597


4598 Final Coat Paint on Ceiling 2d 21 Aug 18 22 Aug 18 4598

4599 Lobby 9w 1d 04 Jun 18 06 Aug 18 4599


4600 1st Fix Wall with Head tracks 1w 04 Jun 18 08 Jun 18 4600
4601 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 14 Jun 18 11 Jul 18 4601
4602 Fix Ceiling Grid 3d 12 Jul 18 16 Jul 18 4602
4603 Paint 1st Coat 2d 17 Jul 18 18 Jul 18 4603
4604 Fix doors incl. Ironmongery 2d 19 Jul 18 20 Jul 18 4604
4605 Mark and Cut openings for MEP on walls 2d 23 Jul 18 24 Jul 18 4605
4606 Install Ceiling Tiles 3d 25 Jul 18 27 Jul 18 4606
4607 Fix MEP Final Fixtures 3d 30 Jul 18 01 Aug 18 4607
4608 Final Coat Paint on walls and ceiling 3d 02 Aug 18 06 Aug 18 4608
4609 Staircase 5w 2d 02 Jul 18 07 Aug 18 4609
4610 H/L Electrical Containment & Conduits - 1st Fix 2d 02 Jul 18 03 Jul 18 4610
4611 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 04 Jul 18 05 Jul 18 4611
4612 Ceiling Rose fixing 1d 06 Jul 18 06 Jul 18 4612
4613 First Coat Paint on Walls & Ceiliings 2d 19 Jul 18 20 Jul 18 4613

4614 MEP Final Fixtures on Wall & Ceilings 2d 02 Aug 18 03 Aug 18 4614
4615 Final Coat Paint on walls & Ceilings 2d 06 Aug 18 07 Aug 18 4615
4616 Level 06 - CORE 03 12w 07 Jun 18 30 Aug 18 4616

4617 Toilet 12w 07 Jun 18 30 Aug 18 4617


4618 1st Fix Wall with Head tracks 1w 07 Jun 18 13 Jun 18 4618

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4619 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 14 Jun 18 11 Jul 18 4619
4620 Fix Pocket Doors 1w 14 Jun 18 20 Jun 18 4620
4621 Inspection and Ceiling Grid Clearance 12 Jul 18 12 Jul 18 4621
4622 2nd Fix wall 1w 12 Jul 18 18 Jul 18 4622
4623 IPS Frame (Box Out only) incl. Backing ply 3d 19 Jul 18 23 Jul 18 4623
4624 Screed 2d 24 Jul 18 25 Jul 18 4624
4625 Fix Ceiling Grid Works 3d 26 Jul 18 30 Jul 18 4625
4626 Floor Tiling Works 3d 31 Jul 18 02 Aug 18 4626
4627 Wall Tiling works incl. IPS Panels 3d 03 Aug 18 07 Aug 18 4627

4628 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 08 Aug 18 15 Aug 18 4628

4629 Mark and Cut openings for MEP on walls including Ceiling 2d 16 Aug 18 17 Aug 18 4629
4630 Install Vanity Tops 4d 16 Aug 18 21 Aug 18 4630

4631 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 20 Aug 18 23 Aug 18 4631

4632 Fix MEP Final Fixtures 3d 23 Aug 18 28 Aug 18 4632

4633 Final Coat Paint on Ceiling 2d 29 Aug 18 30 Aug 18 4633

4634 Lobby 9w 1d 11 Jun 18 13 Aug 18 4634

4635 1st Fix Wall with Head tracks 1w 11 Jun 18 15 Jun 18 4635

4636 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 21 Jun 18 18 Jul 18 4636
4637 Fix Ceiling Grid 3d 19 Jul 18 23 Jul 18 4637
4638 Paint 1st Coat 2d 24 Jul 18 25 Jul 18 4638
4639 Fix doors incl. Ironmongery 2d 26 Jul 18 27 Jul 18 4639
4640 Mark and Cut openings for MEP on walls 2d 30 Jul 18 31 Jul 18 4640
4641 Install Ceiling Tiles 3d 01 Aug 18 03 Aug 18 4641
4642 Fix MEP Final Fixtures 3d 06 Aug 18 08 Aug 18 4642
4643 Final Coat Paint on walls and ceiling 3d 09 Aug 18 13 Aug 18 4643
4644 Staircase 5w 2d 09 Jul 18 14 Aug 18 4644
4645 H/L Electrical Containment & Conduits - 1st Fix 2d 09 Jul 18 10 Jul 18 4645
4646 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 11 Jul 18 12 Jul 18 4646
4647 Ceiling Rose fixing 1d 13 Jul 18 13 Jul 18 4647
4648 First Coat Paint on Walls & Ceiliings 2d 26 Jul 18 27 Jul 18 4648
4649 MEP Final Fixtures on Wall & Ceilings 2d 09 Aug 18 10 Aug 18 4649
4650 Final Coat Paint on walls & Ceilings 2d 13 Aug 18 14 Aug 18 4650
4651 Level GF - CORE 03 12w 14 Jun 18 06 Sep 18 4651
4652 Toilet 12w 14 Jun 18 06 Sep 18 4652

4653 1st Fix Wall with Head tracks 1w 14 Jun 18 20 Jun 18 4653

4654 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 21 Jun 18 18 Jul 18 4654

4655 Fix Pocket Doors 1w 21 Jun 18 27 Jun 18 4655

4656 Inspection and Ceiling Grid Clearance 19 Jul 18 19 Jul 18 4656


4657 2nd Fix wall 1w 19 Jul 18 25 Jul 18 4657

4658 IPS Frame (Box Out only) incl. Backing ply 3d 26 Jul 18 30 Jul 18 4658
4659 Screed 2d 31 Jul 18 01 Aug 18 4659

4660 Fix Ceiling Grid Works 3d 02 Aug 18 06 Aug 18 4660

4661 Floor Tiling Works 3d 07 Aug 18 09 Aug 18 4661

4662 Wall Tiling works incl. IPS Panels 3d 10 Aug 18 14 Aug 18 4662

4663 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 15 Aug 18 22 Aug 18 4663
4664 Mark and Cut openings for MEP on walls including Ceiling 2d 23 Aug 18 24 Aug 18 4664
4665 Install Vanity Tops 4d 23 Aug 18 29 Aug 18 4665
4666 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 28 Aug 18 31 Aug 18 4666
4667 Fix MEP Final Fixtures 3d 31 Aug 18 04 Sep 18 4667
4668 Final Coat Paint on Ceiling 2d 05 Sep 18 06 Sep 18 4668
4669 Lobby 9w 1d 18 Jun 18 20 Aug 18 4669
4670 1st Fix Wall with Head tracks 1w 18 Jun 18 22 Jun 18 4670
4671 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 28 Jun 18 25 Jul 18 4671
4672 Fix Ceiling Grid 3d 26 Jul 18 30 Jul 18 4672
4673 Paint 1st Coat 2d 31 Jul 18 01 Aug 18 4673
4674 Fix doors incl. Ironmongery 2d 02 Aug 18 03 Aug 18 4674
4675 Mark and Cut openings for MEP on walls 2d 06 Aug 18 07 Aug 18 4675

4676 Install Ceiling Tiles 3d 08 Aug 18 10 Aug 18 4676

4677 Fix MEP Final Fixtures 3d 13 Aug 18 15 Aug 18 4677

4678 Final Coat Paint on walls and ceiling 3d 16 Aug 18 20 Aug 18 4678

4679 Staircase 5w 2d 16 Jul 18 21 Aug 18 4679

4680 H/L Electrical Containment & Conduits - 1st Fix 2d 16 Jul 18 17 Jul 18 4680

4681 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 18 Jul 18 19 Jul 18 4681

4682 Ceiling Rose fixing 1d 20 Jul 18 20 Jul 18 4682

4683 First Coat Paint on Walls & Ceiliings 2d 02 Aug 18 03 Aug 18 4683

4684 MEP Final Fixtures on Wall & Ceilings 2d 16 Aug 18 17 Aug 18 4684

4685 Final Coat Paint on walls & Ceilings 2d 20 Aug 18 21 Aug 18 4685

4686 Staircase Flooring incl. Nosing 4w 09 Nov 18 06 Dec 18 4686

4687 Groundfloor refuse room cladding 2w 02 Jul 18 13 Jul 18 4687

4688 Latest Date for ABP/WTP to omit Cat A Shell and Core scope of works to Building 5A 01 Mar 18 01 Mar 18 4688

4689 Cat A Fit Out 34w 3d 06 Apr 18 10 Dec 18 4689

4690 Fit out Ground Floor 6w 1d 21 Jun 18 02 Aug 18 4690

4691 Fit out Ground Floor Unit 2 and 3 5w 3d 21 Jun 18 30 Jul 18 4691

4692
4692 Install conduit to cleaners sockets to core walls 3d 21 Jun 18 25 Jun 18
4693 Boarding and Insulation to external and core walls 1w 26 Jun 18 02 Jul 18 4693

4694 Install wiring to containment in ceilings 1w 03 Jul 18 09 Jul 18 4694

4695 Taping and Joining to Walls 2d 03 Jul 18 04 Jul 18 4695

4696
4696 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 10 Jul 18 16 Jul 18
4697 Install Joinery incl Doors 1w 17 Jul 18 23 Jul 18 4697

4698
4698 Decoration 1w 24 Jul 18 30 Jul 18
4699 Fit Out Ground Floor Units 4 and 5 5w 3d 26 Jun 18 02 Aug 18 4699

4700
4700 Install conduit to cleaners sockets to core walls 3d 26 Jun 18 28 Jun 18
4701 Boarding and Insulation to external and core walls 1w 29 Jun 18 05 Jul 18 4701

4702 Install wiring to containment in ceilings 1w 06 Jul 18 12 Jul 18 4702

4703 Taping and Joining to Walls 2d 06 Jul 18 09 Jul 18 4703

4704
4704 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 13 Jul 18 19 Jul 18
4705 Install Joinery incl Doors 1w 20 Jul 18 26 Jul 18 4705

4706
4706 Decoration 1w 27 Jul 18 02 Aug 18

4707 Fit-out First Floor 17w 3d 06 Apr 18 10 Aug 18 4707

4708 Units 1 and 2 6w 26 Jun 18 06 Aug 18 4708

4709 Install conduit to cleaners sockets to core walls 3d 26 Jun 18 28 Jun 18 4709

4710 Boarding and Insulation to external and core walls 1w 29 Jun 18 05 Jul 18 4710

4711 Install wiring to containment in ceilings 1w 06 Jul 18 12 Jul 18 4711

4712 Taping and Joining to Walls 2d 06 Jul 18 09 Jul 18 4712

4713 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 13 Jul 18 19 Jul 18 4713

4714 Install Joinery incl Doors 1w 20 Jul 18 26 Jul 18 4714

4715 Decoration 1w 31 Jul 18 06 Aug 18 4715

4716 Units 3 and 4 6w 29 Jun 18 09 Aug 18 4716

4717 Install conduit to cleaners sockets to core walls 3d 29 Jun 18 03 Jul 18 4717

4718 Boarding and Insulation to external and core walls 1w 04 Jul 18 10 Jul 18 4718

4719 Install wiring to containment in ceilings 1w 11 Jul 18 17 Jul 18 4719

4720 Taping and Joining to Walls 2d 11 Jul 18 12 Jul 18 4720

4721 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 18 Jul 18 24 Jul 18 4721

4722 Install Joinery incl Doors 1w 25 Jul 18 31 Jul 18 4722

4723 Decoration 1w 03 Aug 18 09 Aug 18 4723

4724 Units 5 and 6 5w 3d 04 Jul 18 10 Aug 18 4724

4725 Install conduit to cleaners sockets to core walls 3d 04 Jul 18 06 Jul 18 4725

4726 Boarding and Insulation to external and core walls 1w 09 Jul 18 13 Jul 18 4726

4727 Install wiring to containment in ceilings 1w 16 Jul 18 20 Jul 18 4727

4728 Taping and Joining to Walls 2d 16 Jul 18 17 Jul 18 4728

4729 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 23 Jul 18 27 Jul 18 4729

4730 Install Joinery incl Doors 1w 30 Jul 18 03 Aug 18 4730

4731 Decoration 1w 06 Aug 18 10 Aug 18 4731

4732 High Level Services First Floor 8w 2d 06 Apr 18 07 Jun 18 4732

4733 Fit-out Second Floor 16w 3d 20 Apr 18 17 Aug 18 4733

4734 Units 1 and 2 5w 3d 29 Jun 18 07 Aug 18 4734

4735
4735 Install conduit to cleaners sockets to core walls 3d 29 Jun 18 03 Jul 18
4736 Boarding and Insulation to external and core walls 1w 04 Jul 18 10 Jul 18 4736

4737 Install wiring to containment in ceilings 1w 11 Jul 18 17 Jul 18 4737

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4738 Taping and Joining to Walls 2d 11 Jul 18 12 Jul 18 4738

4739
4739 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 18 Jul 18 24 Jul 18
4740 Install Joinery incl Doors 1w 25 Jul 18 31 Jul 18 4740

4741
4741 Decoration 1w 01 Aug 18 07 Aug 18
4742 Units 3 and 4 5w 3d 04 Jul 18 10 Aug 18 4742

4743
4743 Install conduit to cleaners sockets to core walls 3d 04 Jul 18 06 Jul 18
4744 Boarding and Insulation to external and core walls 1w 09 Jul 18 13 Jul 18 4744

4745 Install wiring to containment in ceilings 1w 16 Jul 18 20 Jul 18 4745

4746 Taping and Joining to Walls 2d 16 Jul 18 17 Jul 18 4746

4747
4747 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 23 Jul 18 27 Jul 18
4748 Install Joinery incl Doors 1w 30 Jul 18 03 Aug 18 4748

4749
4749 Decoration 1w 06 Aug 18 10 Aug 18
4750 Units 5 and 6 6w 09 Jul 18 17 Aug 18 4750

4751
4751 Install conduit to cleaners sockets to core walls 3d 09 Jul 18 11 Jul 18
4752 Boarding and Insulation to external and core walls 1w 12 Jul 18 18 Jul 18 4752

4753 Install wiring to containment in ceilings 1w 19 Jul 18 25 Jul 18 4753

4754 Taping and Joining to Walls 2d 19 Jul 18 20 Jul 18 4754

4755
4755 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 26 Jul 18 01 Aug 18
4756 Install Joinery incl Doors 1w 02 Aug 18 08 Aug 18 4756

4757
4757 Decoration 1w 13 Aug 18 17 Aug 18
4758 High Level Services Second Floor 8w 1d 20 Apr 18 20 Jun 18 4758

4759 Fit-out Third Floor 14w 4d 08 May 18 20 Aug 18 4759

4760 Units 1 and 2 5w 3d 04 Jul 18 10 Aug 18 4760

4761 Install conduit to cleaners sockets to core walls 3d 04 Jul 18 06 Jul 18 4761

4762
4762 Boarding and Insulation to external and core walls 1w 09 Jul 18 13 Jul 18
4763 Install wiring to containment in ceilings 1w 16 Jul 18 20 Jul 18 4763

4764
4764 Taping and Joining to Walls 2d 16 Jul 18 17 Jul 18
4765 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 23 Jul 18 27 Jul 18 4765

4766
4766 Install Joinery incl Doors 1w 30 Jul 18 03 Aug 18
4767 Decoration 1w 06 Aug 18 10 Aug 18 4767

4768 Units 3 and 4 5w 3d 09 Jul 18 15 Aug 18 4768

4769 Install conduit to cleaners sockets to core walls 3d 09 Jul 18 11 Jul 18 4769

4770
4770 Boarding and Insulation to external and core walls 1w 12 Jul 18 18 Jul 18
4771 Install wiring to containment in ceilings 1w 19 Jul 18 25 Jul 18 4771

4772
4772 Taping and Joining to Walls 2d 19 Jul 18 20 Jul 18
4773 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 26 Jul 18 01 Aug 18 4773

4774
4774 Install Joinery incl Doors 1w 02 Aug 18 08 Aug 18
4775 Decoration 1w 09 Aug 18 15 Aug 18 4775

4776 Units 5 and 6 5w 3d 12 Jul 18 20 Aug 18 4776

4777 Install conduit to cleaners sockets to core walls 3d 12 Jul 18 16 Jul 18 4777

4778
4778 Boarding and Insulation to external and core walls 1w 17 Jul 18 23 Jul 18
4779 Install wiring to containment in ceilings 1w 24 Jul 18 30 Jul 18 4779

4780
4780 Taping and Joining to Walls 2d 24 Jul 18 25 Jul 18
4781 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 31 Jul 18 06 Aug 18 4781

4782
4782 Install Joinery incl Doors 1w 07 Aug 18 13 Aug 18
4783 Decoration 1w 14 Aug 18 20 Aug 18 4783

4784 High Level Services Third Floor 8w 1d 08 May 18 04 Jul 18 4784

4785 Fit-out Fourth Floor 13w 2d 22 May 18 23 Aug 18 4785

4786 Units 1 and 2 5w 3d 09 Jul 18 15 Aug 18 4786

4787 Install conduit to cleaners sockets to core walls 3d 09 Jul 18 11 Jul 18 4787

4788
4788 Boarding and Insulation to external and core walls 1w 12 Jul 18 18 Jul 18
4789 Install wiring to containment in ceilings 1w 19 Jul 18 25 Jul 18 4789

4790
4790 Taping and Joining to Walls 3d 19 Jul 18 23 Jul 18
4791 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 26 Jul 18 01 Aug 18 4791

4792
4792 Install Joinery incl Doors 1w 02 Aug 18 08 Aug 18
4793 Decoration 1w 09 Aug 18 15 Aug 18 4793

4794 Units 3 and 4 6w 12 Jul 18 22 Aug 18 4794

4795 Install conduit to cleaners sockets to core walls 3d 12 Jul 18 16 Jul 18 4795

4796 Boarding and Insulation to external and core walls 1w 17 Jul 18 23 Jul 18 4796

4797 Install wiring to containment in ceilings 1w 24 Jul 18 30 Jul 18 4797

4798 Taping and Joining to Walls 3d 24 Jul 18 26 Jul 18 4798

4799
4799 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 31 Jul 18 06 Aug 18
4800 Install Joinery incl Doors 1w 07 Aug 18 13 Aug 18 4800

4801
4801 Decoration 1w 16 Aug 18 22 Aug 18
4802 Units 5 and 6 5w 3d 17 Jul 18 23 Aug 18 4802

4803
4803 Install conduit to cleaners sockets to core walls 3d 17 Jul 18 19 Jul 18
4804 Boarding and Insulation to external and core walls 1w 20 Jul 18 26 Jul 18 4804

4805 Install wiring to containment in ceilings 1w 27 Jul 18 02 Aug 18 4805

4806 Taping and Joining to Walls 3d 27 Jul 18 31 Jul 18 4806

4807
4807 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 03 Aug 18 09 Aug 18
4808 Install Joinery incl Doors 1w 10 Aug 18 16 Aug 18 4808

4809
4809 Decoration 1w 17 Aug 18 23 Aug 18
4810 High Level Services Fourth Floor 8w 22 May 18 17 Jul 18 4810

4811 Fit-out Fifth Floor 12w 2d 06 Jun 18 31 Aug 18 4811

4812 Units 1 and 2 5w 3d 12 Jul 18 20 Aug 18 4812

4813
4813 Install conduit to cleaners sockets to core walls 3d 12 Jul 18 16 Jul 18
4814 Boarding and Insulation to external and core walls 1w 17 Jul 18 23 Jul 18 4814

4815 Install wiring to containment in ceilings 1w 24 Jul 18 30 Jul 18 4815

4816 Taping and Joining to Walls 2d 24 Jul 18 25 Jul 18 4816

4817
4817 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 31 Jul 18 06 Aug 18
4818 Install Joinery incl Doors 1w 07 Aug 18 13 Aug 18 4818

4819
4819 Decoration 1w 14 Aug 18 20 Aug 18
4820 Units 3 and 4 5w 3d 17 Jul 18 23 Aug 18 4820

4821
4821 Install conduit to cleaners sockets to core walls 3d 17 Jul 18 19 Jul 18
4822 Boarding and Insulation to external and core walls 1w 20 Jul 18 26 Jul 18 4822

4823 Install wiring to containment in ceilings 1w 27 Jul 18 02 Aug 18 4823

4824 Taping and Joining to Walls 3d 27 Jul 18 31 Jul 18 4824

4825
4825 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 03 Aug 18 09 Aug 18
4826 Install Joinery incl Doors 1w 10 Aug 18 16 Aug 18 4826

4827
4827 Decoration 1w 17 Aug 18 23 Aug 18
4828 Units 5 and 6 6w 20 Jul 18 31 Aug 18 4828

4829
4829 Install conduit to cleaners sockets to core walls 3d 20 Jul 18 24 Jul 18
4830 Boarding and Insulation to external and core walls 1w 25 Jul 18 31 Jul 18 4830

4831 Install wiring to containment in ceilings 1w 01 Aug 18 07 Aug 18 4831

4832 Taping and Joining to Walls 2d 01 Aug 18 02 Aug 18 4832

4833 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 08 Aug 18 14 Aug 18 4833

4834
4834 Install Joinery incl Doors 1w 15 Aug 18 21 Aug 18
4835 Decoration 1w 24 Aug 18 31 Aug 18 4835

4836 High Level Services Fifth Floor 8w 06 Jun 18 31 Jul 18 4836

4837 Fit-out Sixth Floor 10w 3d 20 Jun 18 03 Sep 18 4837

4838 Units 1 and 2 5w 3d 17 Jul 18 23 Aug 18 4838

4839 Install conduit to cleaners sockets to core walls 3d 17 Jul 18 19 Jul 18 4839

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4840 Boarding and Insulation to external and core walls 1w 20 Jul 18 26 Jul 18 4840

4841 Install wiring to containment in ceilings 1w 27 Jul 18 02 Aug 18 4841

4842 Taping and Joining to Walls 2d 27 Jul 18 30 Jul 18 4842

4843
4843 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 03 Aug 18 09 Aug 18
4844 Install Joinery incl Doors 1w 10 Aug 18 16 Aug 18 4844

4845
4845 Decoration 1w 17 Aug 18 23 Aug 18
4846 Units 3 and 4 6w 20 Jul 18 31 Aug 18 4846

4847
4847 Install conduit to cleaners sockets to core walls 3d 20 Jul 18 24 Jul 18
4848 Boarding and Insulation to external and core walls 1w 25 Jul 18 31 Jul 18 4848

4849 Install wiring to containment in ceilings 1w 01 Aug 18 07 Aug 18 4849

4850 Taping and Joining to Walls 3d 01 Aug 18 03 Aug 18 4850

4851
4851 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 08 Aug 18 14 Aug 18
4852 Install Joinery incl Doors 1w 15 Aug 18 21 Aug 18 4852

4853
4853 Decoration 1w 24 Aug 18 31 Aug 18
4854 Units 5 and 6 5w 3d 25 Jul 18 03 Sep 18 4854

4855
4855 Install conduit to cleaners sockets to core walls 3d 25 Jul 18 27 Jul 18
4856 Boarding and Insulation to external and core walls 1w 30 Jul 18 03 Aug 18 4856

4857 Install wiring to containment in ceilings 1w 06 Aug 18 10 Aug 18 4857

4858 Taping and Joining to Walls 2d 06 Aug 18 07 Aug 18 4858

4859
4859 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 13 Aug 18 17 Aug 18
4860 Install Joinery incl Doors 1w 20 Aug 18 24 Aug 18 4860

4861
4861 Decoration 1w 28 Aug 18 03 Sep 18
4862 High Level Services Sixth Floor 8w 20 Jun 18 14 Aug 18 4862

4863 Temporary Access Closure - CAT A Fitout 2w 2d 28 Aug 18 12 Sep 18 4863

4864 Fit out First Floor 2d 11 Sep 18 12 Sep 18 4864

4865 Partition closure 2d 11 Sep 18 12 Sep 18 4865

4866 Fit out Second Floor 2d 07 Sep 18 10 Sep 18 4866

4867 Partition closure 2d 07 Sep 18 10 Sep 18 4867

4868 Fit out Third Floor 2d 05 Sep 18 06 Sep 18 4868

4869 Partition closure 2d 05 Sep 18 06 Sep 18 4869

4870 Fit out Fourth Floor 2d 03 Sep 18 04 Sep 18 4870

4871 Partition closure 2d 03 Sep 18 04 Sep 18 4871

4872 Fit out Fifth Floor 2d 30 Aug 18 31 Aug 18 4872

4873 Partition closure 2d 30 Aug 18 31 Aug 18 4873

4874 Fit out Sixth Floor 2d 28 Aug 18 29 Aug 18 4874

4875 Partition closure 2d 28 Aug 18 29 Aug 18 4875

4876 Prepare to Handover Units 8w 2d 12 Oct 18 10 Dec 18 4876

4877 Prepare to Hand Over Units 1 and 2 6w 2d 12 Oct 18 26 Nov 18 4877

4878 Ground floor 2w 4d 12 Oct 18 31 Oct 18 4878

4879 Complete Ceiling Tiles 1w 12 Oct 18 18 Oct 18 4879

4880 Install Raised Access Floor incl Below Floor Barriers 1w 19 Oct 18 25 Oct 18 4880

4881 Soft Floor Coverings 4d 26 Oct 18 31 Oct 18 4881

4882 First floor 2w 4d 17 Oct 18 05 Nov 18 4882

4883 Complete Ceiling Tiles 1w 17 Oct 18 23 Oct 18 4883

4884 Install Raised Access Floor incl Below Floor Barriers 1w 24 Oct 18 30 Oct 18 4884

4885 Soft Floor Coverings 4d 31 Oct 18 05 Nov 18 4885

4886 Second Floor 2w 4d 22 Oct 18 08 Nov 18 4886

4887 Complete Ceiling Tiles 1w 22 Oct 18 26 Oct 18 4887

4888 Install Raised Access Floor incl Below Floor Barriers 1w 29 Oct 18 02 Nov 18 4888

4889 Soft Floor Coverings 4d 05 Nov 18 08 Nov 18 4889

4890 Third Floor 2w 4d 25 Oct 18 13 Nov 18 4890

4891 Complete Ceiling Tiles 1w 25 Oct 18 31 Oct 18 4891

4892 Install Raised Access Floor incl Below Floor Barriers 1w 01 Nov 18 07 Nov 18 4892

4893 Soft Floor Coverings 4d 08 Nov 18 13 Nov 18 4893

4894 Fourth Floor 2w 4d 30 Oct 18 16 Nov 18 4894

4895 Complete Ceiling Tiles 1w 30 Oct 18 05 Nov 18 4895

4896 Install Raised Access Floor incl Below Floor Barriers 1w 06 Nov 18 12 Nov 18 4896

4897 Soft Floor Coverings 4d 13 Nov 18 16 Nov 18 4897

4898 Fifth Floor 2w 4d 02 Nov 18 21 Nov 18 4898

4899 Complete Ceiling Tiles 1w 02 Nov 18 08 Nov 18 4899

4900 Install Raised Access Floor incl Below Floor Barriers 1w 09 Nov 18 15 Nov 18 4900

4901 Soft Floor Coverings 4d 16 Nov 18 21 Nov 18 4901

4902 Sixth Floor 2w 4d 07 Nov 18 26 Nov 18 4902

4903 Complete Ceiling Tiles 1w 07 Nov 18 13 Nov 18 4903

4904 Install Raised Access Floor incl Below Floor Barriers 1w 14 Nov 18 20 Nov 18 4904

4905 Soft Floor Coverings 4d 21 Nov 18 26 Nov 18 4905

4906 Prepare to Hand Over Units 3 and 4 6w 2d 19 Oct 18 03 Dec 18 4906

4907 Ground Floor 2w 4d 19 Oct 18 07 Nov 18 4907

4908 Complete Ceiling Tiles 1w 19 Oct 18 25 Oct 18 4908

4909 Install Raised Access Floor incl Below Floor Barriers 1w 26 Oct 18 01 Nov 18 4909

4910 Soft Floor Coverings 4d 02 Nov 18 07 Nov 18 4910

4911 First Floor 2w 4d 24 Oct 18 12 Nov 18 4911

4912 Complete Ceiling Tiles 1w 24 Oct 18 30 Oct 18 4912

4913 Install Raised Access Floor incl Below Floor Barriers 1w 31 Oct 18 06 Nov 18 4913

4914 Soft Floor Coverings 4d 07 Nov 18 12 Nov 18 4914

4915 Second Floor 2w 4d 29 Oct 18 15 Nov 18 4915

4916 Complete Ceiling Tiles 1w 29 Oct 18 02 Nov 18 4916

4917 Install Raised Access Floor incl Below Floor Barriers 1w 05 Nov 18 09 Nov 18 4917

4918 Soft Floor Coverings 4d 12 Nov 18 15 Nov 18 4918

4919 Third Floor 2w 4d 01 Nov 18 20 Nov 18 4919

4920 Complete Ceiling Tiles 1w 01 Nov 18 07 Nov 18 4920

4921 Install Raised Access Floor incl Below Floor Barriers 1w 08 Nov 18 14 Nov 18 4921

4922 Soft Floor Coverings 4d 15 Nov 18 20 Nov 18 4922

4923 Fourth Floor 2w 4d 06 Nov 18 23 Nov 18 4923

4924 Complete Ceiling Tiles 1w 06 Nov 18 12 Nov 18 4924

4925 Install Raised Access Floor incl Below Floor Barriers 1w 13 Nov 18 19 Nov 18 4925

4926 Soft Floor Coverings 4d 20 Nov 18 23 Nov 18 4926

4927 Fifth Floor 2w 4d 09 Nov 18 28 Nov 18 4927

4928 Complete Ceiling Tiles 1w 09 Nov 18 15 Nov 18 4928

4929 Install Raised Access Floor incl Below Floor Barriers 1w 16 Nov 18 22 Nov 18 4929

4930 Soft Floor Coverings 4d 23 Nov 18 28 Nov 18 4930

4931 Sixth Floor 2w 4d 14 Nov 18 03 Dec 18 4931

4932 Complete Ceiling Tiles 1w 14 Nov 18 20 Nov 18 4932

4933 Install Raised Access Floor incl Below Floor Barriers 1w 21 Nov 18 27 Nov 18 4933

4934 Soft Floor Coverings 4d 28 Nov 18 03 Dec 18 4934

4935 Prepare to Hand Over Units 5 and 6 6w 2d 26 Oct 18 10 Dec 18 4935

4936 Ground Floor 2w 4d 26 Oct 18 14 Nov 18 4936

4937 Complete Ceiling Tiles 1w 26 Oct 18 01 Nov 18 4937

4938 Install Raised Access Floor incl Below Floor Barriers 1w 02 Nov 18 08 Nov 18 4938

4939 Soft Floor Coverings 4d 09 Nov 18 14 Nov 18 4939

4940 First Floor 2w 4d 31 Oct 18 19 Nov 18 4940

4941 Complete Ceiling Tiles 1w 31 Oct 18 06 Nov 18 4941

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4942 Install Raised Access Floor incl Below Floor Barriers 1w 07 Nov 18 13 Nov 18 4942

4943 Soft Floor Coverings 4d 14 Nov 18 19 Nov 18 4943

4944 Second Floor 2w 4d 05 Nov 18 22 Nov 18 4944

4945 Complete Ceiling Tiles 1w 05 Nov 18 09 Nov 18 4945

4946 Install Raised Access Floor incl Below Floor Barriers 1w 12 Nov 18 16 Nov 18 4946

4947 Soft Floor Coverings 4d 19 Nov 18 22 Nov 18 4947

4948 Third Floor 2w 4d 08 Nov 18 27 Nov 18 4948

4949 Complete Ceiling Tiles 1w 08 Nov 18 14 Nov 18 4949

4950 Install Raised Access Floor incl Below Floor Barriers 1w 15 Nov 18 21 Nov 18 4950

4951 Soft Floor Coverings 4d 22 Nov 18 27 Nov 18 4951

4952 Fourth Floor 2w 4d 13 Nov 18 30 Nov 18 4952

4953 Complete Ceiling Tiles 1w 13 Nov 18 19 Nov 18 4953

4954 Install Raised Access Floor incl Below Floor Barriers 1w 20 Nov 18 26 Nov 18 4954

4955 Soft Floor Coverings 4d 27 Nov 18 30 Nov 18 4955

4956 Fifth Floor 2w 4d 16 Nov 18 05 Dec 18 4956

4957 Complete Ceiling Tiles 1w 16 Nov 18 22 Nov 18 4957

4958 Install Raised Access Floor incl Below Floor Barriers 1w 23 Nov 18 29 Nov 18 4958

4959 Soft Floor Coverings 4d 30 Nov 18 05 Dec 18 4959

4960 Sixth Floor 2w 4d 21 Nov 18 10 Dec 18 4960

4961 Complete Ceiling Tiles 1w 21 Nov 18 27 Nov 18 4961

4962 Install Raised Access Floor incl Below Floor Barriers 1w 28 Nov 18 04 Dec 18 4962

4963 Soft Floor Coverings 4d 05 Dec 18 10 Dec 18 4963

4964 Building 5A Complete 19 Feb 19 19 Feb 19 4964

4965 Building 5B 78w 4d 16 Jun 17 22 Jan 19 4965

4966 Piling 8w 16 Jun 17 10 Aug 17 4966

4967 Lay Pile Mat 2w 16 Jun 17 29 Jun 17 4967

4968 Lay Crane Mat 2w 22 Jun 17 05 Jul 17 4968

4969 Piling 3w 4d 17 Jul 17 10 Aug 17 4969

4970 Structure 22w 2d 26 Sep 17 09 Mar 18 4970

4971 Substructure 9w 4d 26 Sep 17 01 Dec 17 4971


4972 Core 1 6w 2d 26 Sep 17 08 Nov 17 4972
4973 Excavate 3w 2d 26 Sep 17 27 Oct 17 4973
4974 Break down piles 3w 1d 02 Oct 17 27 Oct 17 4974
4975 FRC Base of Cap including drainage 3w 2d 05 Oct 17 08 Nov 17 4975

4976 Core 2 7w 2d 29 Sep 17 20 Nov 17 4976


4977 Excavate 3w 3d 29 Sep 17 09 Nov 17 4977
4978 Break down piles 3w 2d 04 Oct 17 13 Nov 17 4978
4979 FRC Base of Cap including drainage 3w 3d 10 Oct 17 20 Nov 17 4979

4980 General Pile Caps 4w 3d 25 Oct 17 24 Nov 17 4980


4981 Excavate 2w 3d 25 Oct 17 17 Nov 17 4981
4982 Break down piles 2w 2d 06 Nov 17 21 Nov 17 4982

4983 FRC Base of Cap 2w 3d 08 Nov 17 24 Nov 17 4983

4984 GroundFloor Slab 3w 3d 08 Nov 17 01 Dec 17 4984


4985 Pour 1 2w 08 Nov 17 21 Nov 17 4985

4986 Pour 2 2w 20 Nov 17 01 Dec 17 4986


4987 Superstructure 14w 1d 22 Nov 17 09 Mar 18 4987

4988 STAND PRECAST CORE WALLS GND - 1ST FLOOR 4d 22 Nov 17 05 Dec 17 4988

4989 STAND PRECAST COLUMNS GROUND - 1ST FLOOR 1w 3d 23 Nov 17 04 Dec 17 4989

4990 FRC 1ST FLOOR SLAB 2w 2d 28 Nov 17 13 Dec 17 4990

4991 STAND PRECAST CORE WALLS 1ST - 2ND FLOOR 4d 07 Dec 17 15 Dec 17 4991

4992 STAND PRECAST COLUMNS 1ST - 2ND FLOOR 2w 08 Dec 17 21 Dec 17 4992

4993 FRC 2ND FLOOR SLAB 2w 1d 12 Dec 17 04 Jan 18 4993

4994 STAND PRECAST WALLS 2ND - 3RD FLOOR 4d 20 Dec 17 08 Jan 18 4994

4995 STAND PRECAST COLUMNS 2ND - 3RD FLOOR 1w 4d 21 Dec 17 11 Jan 18 4995

4996 FRC 3RD FLOOR SLAB 2w 1d 03 Jan 18 17 Jan 18 4996

4997 STAND PRECAST CORE WALLS 3RD - 4TH FLOOR 4d 11 Jan 18 19 Jan 18 4997

4998 STAND PRECAST COLUMNS 3RD - 4TH FLOOR 1w 4d 12 Jan 18 24 Jan 18 4998

4999 FRC 4TH FLOOR SLAB 2w 1d 16 Jan 18 30 Jan 18 4999

5000 STAND PRECAST CORE WALLS 4TH - 5TH FLOOR 4d 24 Jan 18 01 Feb 18 5000

5001 STAND PRECAST COLUMNS 4TH - 5TH FLOOR 2w 25 Jan 18 07 Feb 18 5001

5002 FRC 5TH FLOOR SLAB 2w 2d 30 Jan 18 14 Feb 18 5002

5003 STAND PRECAST WALLS 5TH - ROOF 4d 07 Feb 18 16 Feb 18 5003

5004 STAND PRECAST COLUMNS 5TH - ROOF 1w 4d 08 Feb 18 20 Feb 18 5004

5005 FRC ROOF SLAB 2w 2d 12 Feb 18 27 Feb 18 5005

5006 STAND PRECAST CORE WALL OVERRUNS 4d 21 Feb 18 01 Mar 18 5006

5007 FRC CAPPING SLAB TO CORES 2w 1d 23 Feb 18 09 Mar 18 5007

5008 FRC PERIMETER UPSTAND TO ROOF 2w 2d 21 Feb 18 08 Mar 18 5008

5009 Precast Stairs & Handrails 12w 28 Nov 17 28 Feb 18 5009

5010 Facades 41w 12 Mar 18 14 Jan 19 5010

5011 Precast Cladding 6w 12 Mar 18 24 Apr 18 5011

5012 Precast Cladding Panels North elevation 2w 2d 12 Mar 18 27 Mar 18 5012

5013 South Elevation 2w 3d 28 Mar 18 17 Apr 18 5013

5014 Precast Cladding Panels South elevation Bay 1 3d 28 Mar 18 03 Apr 18 5014

5015 Precast Cladding Panels South elevation Bay 2 3d 04 Apr 18 06 Apr 18 5015

5016 Precast Cladding Panels South elevation Bay 3 3d 09 Apr 18 11 Apr 18 5016

5017 Precast Cladding Panels South elevation Bay 4 4d 12 Apr 18 17 Apr 18 5017

5018 Precast Cladding Panels West elevation 3d 18 Apr 18 20 Apr 18 5018

5019 Precast Cladding Panels East elevation 2d 23 Apr 18 24 Apr 18 5019

5020 Mastic Sealing externally 6w 19 Mar 18 02 May 18 5020


5021 Windows 19w 26 Mar 18 10 Aug 18 5021

5022 Complete ribbon windows after hoists removed 4w 16 Jul 18 10 Aug 18 5022
5023 Install SFS, Windows & Cladding L05 9w 3d 26 Mar 18 06 Jun 18 5023

5024 Install SFS, Windows and cladding Level 5 North elevation 9w 3d 26 Mar 18 06 Jun 18 5024

5025 Install SFS, Windows and cladding Level 5 South, East and West Elevations 6w 13 Apr 18 29 May 18 5025

5026 Install ribbon window curtain walling to South Elevation 4w 3d 25 Apr 18 30 May 18 5026

5027 Parapet Cladding to Level 6 5w 25 Apr 18 01 Jun 18 5027

5028 Curtain Walling/ Doors Ground Floor 3w 4d 18 Apr 18 16 May 18 5028

5029 Windows & Shopfronts at Ground 3w 3d 18 Apr 18 15 May 18 5029

5030 External Doors & Louvres at Ground 2w 4d 25 Apr 18 16 May 18 5030

5031 Canopies 35w 25 Apr 18 14 Jan 19 5031

5032 Install Frame for the Canopies 1w 25 Apr 18 02 May 18 5032

5033 Complete glazing for Canopies 1w 08 Jan 19 14 Jan 19 5033

5034 Roofing 13w 1d 09 Mar 18 15 Jun 18 5034

5035 Erect Terrace Balustrades 2w 09 Mar 18 22 Mar 18 5035

5036 Erect posts for Roof Louvres 2w 09 Mar 18 22 Mar 18 5036

5037 Terrace Slab Waterproofing 1w 2d 23 Mar 18 04 Apr 18 5037

5038 Roof Slab Waterproofing 5w 23 Mar 18 01 May 18 5038

5039 Cladding to Stair Cores 5w 10 Apr 18 16 May 18 5039

5040 Roof Finishes and Mansafe Latchways 5w 25 Apr 18 01 Jun 18 5040

5041 Install Roof Louvres 4w 17 Apr 18 16 May 18 5041

5042 Access Hatch and ladders 2w 04 Jun 18 15 Jun 18 5042

5043 Latest Date for ABP/WTP to omit Cat A Shell and Core Services scope of works to Building 5B 14 Nov 17 14 Nov 17 5043

5044 M & E Installation 18w 2d 31 Jan 18 14 Jun 18 5044

5045 Riser Installation 1w 4d 31 Jan 18 14 Mar 18 5045

5046 Prefabricated Floor Modules Levels G-2 1w 16 Apr 18 20 Apr 18 5046

5047 Prefabricated Floor Modules Levels 3-6 1w 09 Mar 18 15 Mar 18 5047

5048 Installation of Siphonic drainage 2w 12 Mar 18 23 Mar 18 5048

5049 Roof Plant Installation 6w 02 May 18 14 Jun 18 5049

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5050 Ground Floor Plant Installation 5B 6w 09 Mar 18 23 Apr 18 5050

5051 Blockwork 27w 1d 19 Jan 18 03 Aug 18 5051

5052 Main Works 10w 3d 19 Jan 18 05 Apr 18 5052

5053 Blockwork Walls at Ground 3w 19 Jan 18 08 Feb 18 5053

5054 Blockwork Walls at L1 1w 01 Feb 18 07 Feb 18 5054

5055 Blockwork Walls at L2 1w 14 Feb 18 20 Feb 18 5055

5056 Blockwork Walls at L3 1w 01 Mar 18 07 Mar 18 5056

5057 Blockwork Walls at L4 1w 14 Mar 18 20 Mar 18 5057

5058
5058 Blockwork Walls at L5 1w 28 Mar 18 05 Apr 18
5059 Revist 1w 1d 27 Jul 18 03 Aug 18 5059

5060 Level 05 2d 27 Jul 18 30 Jul 18 5060

5061 Level 04 2d 30 Jul 18 31 Jul 18 5061

5062 Level 03 2d 31 Jul 18 01 Aug 18 5062

5063 Level 02 2d 01 Aug 18 02 Aug 18 5063

5064 Level 01 2d 02 Aug 18 03 Aug 18 5064

5065 Hoist 21w 23 Feb 18 26 Jul 18 5065

5066 Window for Cantidecks to load out upper floor 2w 23 Feb 18 08 Mar 18 5066

5067 Hoist 1 14w 3d 28 Mar 18 13 Jul 18 5067

5068 Hoist 2 15w 10 Apr 18 26 Jul 18 5068

5069 Lift /Toilet Core Fit Out 56w 2d 22 Nov 17 22 Jan 19 5069

5070 Lifts 56w 2d 22 Nov 17 22 Jan 19 5070

5071 Delivery of temporary lift doors to 5B 22 Nov 17 22 Nov 17 5071

5072 Lift 1 9w 02 May 18 05 Jul 18 5072

5073 Lift 1 Guides and doors 7w 02 May 18 21 Jun 18 5073

5074 Lift 1 Car 1w 22 Jun 18 28 Jun 18 5074

5075 Lift 1 Commission 1w 29 Jun 18 05 Jul 18 5075

5076 Lift 2 33w 4d 10 May 18 17 Jan 19 5076

5077 Lift 2 Guides and doors 7w 10 May 18 28 Jun 18 5077

5078 Lift 2 Car 1w 29 Jun 18 05 Jul 18 5078

5079 Lift 2 Commission 1w 06 Jul 18 12 Jul 18 5079

5080 Hand back Lift 2 after builders beneficial use 21 Dec 18 21 Dec 18 5080
5081 Recommission Lift 2 2w 21 Dec 18 17 Jan 19 5081

5082 Lift 3 9w 17 May 18 19 Jul 18 5082

5083 Lift 3 Guides and doors 7w 17 May 18 05 Jul 18 5083

5084 Lift 3 Car 1w 06 Jul 18 12 Jul 18 5084

5085 Lift 3 Commission 1w 13 Jul 18 19 Jul 18 5085

5086 Lift 4 32w 2d 24 May 18 22 Jan 19 5086

5087 Lift 4 Guides and doors 7w 24 May 18 12 Jul 18 5087

5088 Lift 4 Car 1w 13 Jul 18 19 Jul 18 5088

5089 Lift 4 Commission 1w 20 Jul 18 26 Jul 18 5089

5090 Hand back Lift 4 after builders beneficial use 09 Jan 19 09 Jan 19 5090

5091 Recommission Lift 4 2w 09 Jan 19 22 Jan 19 5091


5092 Toilet & Lobby 19w 17 Apr 18 31 Aug 18 5092

5093 Level 01 - CORE 01 12w 17 Apr 18 12 Jul 18 5093


5094 Toilet 12w 17 Apr 18 12 Jul 18 5094
5095 Floor slab available 17 Apr 18 17 Apr 18 5095
5096 1st Fix Wall with Head tracks 1w 17 Apr 18 23 Apr 18 5096
5097 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 24 Apr 18 23 May 18 5097
5098 Fix Pocket Doors 1w 24 Apr 18 01 May 18 5098
5099 Inspection and Ceiling Grid Clearance 24 May 18 24 May 18 5099
5100 2nd Fix wall 1w 24 May 18 31 May 18 5100
5101 IPS Frame (Box Out only) incl. Backing ply 3d 01 Jun 18 05 Jun 18 5101
5102 Screed 2d 06 Jun 18 07 Jun 18 5102
5103 Fix Ceiling Grid Works 3d 08 Jun 18 12 Jun 18 5103

5104 Floor Tiling Works 3d 13 Jun 18 15 Jun 18 5104

5105 Wall Tiling works incl. IPS Panels 3d 18 Jun 18 20 Jun 18 5105

5106 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 21 Jun 18 28 Jun 18 5106

5107 Mark and Cut openings for MEP on walls including Ceiling 2d 29 Jun 18 02 Jul 18 5107

5108 Install Vanity Tops 4d 29 Jun 18 04 Jul 18 5108


5109 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 03 Jul 18 06 Jul 18 5109

5110 Fix MEP Final Fixtures 3d 06 Jul 18 10 Jul 18 5110

5111 Final Coat Paint on Ceiling 2d 11 Jul 18 12 Jul 18 5111

5112 Lobby 9w 1d 19 Apr 18 26 Jun 18 5112

5113 1st Fix Wall with Head tracks 1w 19 Apr 18 25 Apr 18 5113

5114 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 02 May 18 31 May 18 5114

5115 Fix Ceiling Grid 3d 01 Jun 18 05 Jun 18 5115


5116 Paint 1st Coat 2d 06 Jun 18 07 Jun 18 5116
5117 Fix doors incl. Ironmongery 2d 08 Jun 18 11 Jun 18 5117
5118 Mark and Cut openings for MEP on walls 2d 12 Jun 18 13 Jun 18 5118
5119 Install Ceiling Tiles 3d 14 Jun 18 18 Jun 18 5119
5120 Fix MEP Final Fixtures 3d 19 Jun 18 21 Jun 18 5120
5121 Final Coat Paint on walls and ceiling 3d 22 Jun 18 26 Jun 18 5121
5122 Staircase 5w 2d 21 May 18 27 Jun 18 5122
5123 H/L Electrical Containment & Conduits - 1st Fix 2d 21 May 18 22 May 18 5123
5124 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 23 May 18 24 May 18 5124
5125 Ceiling Rose fixing 1d 25 May 18 25 May 18 5125
5126 First Coat Paint on Walls & Ceiliings 2d 08 Jun 18 11 Jun 18 5126
5127 MEP Final Fixtures on Wall & Ceilings 2d 22 Jun 18 25 Jun 18 5127

5128 Final Coat Paint on walls & Ceilings 2d 26 Jun 18 27 Jun 18 5128

5129 Level 02 - CORE 01 12w 24 Apr 18 19 Jul 18 5129


5130 Toilet 12w 24 Apr 18 19 Jul 18 5130

5131 1st Fix Wall with Head tracks 1w 24 Apr 18 01 May 18 5131
5132 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 02 May 18 31 May 18 5132
5133 Fix Pocket Doors 1w 02 May 18 09 May 18 5133

5134 Inspection and Ceiling Grid Clearance 01 Jun 18 01 Jun 18 5134


5135 2nd Fix wall 1w 01 Jun 18 07 Jun 18 5135

5136 IPS Frame (Box Out only) incl. Backing ply 3d 08 Jun 18 12 Jun 18 5136
5137 Screed 2d 13 Jun 18 14 Jun 18 5137
5138 Fix Ceiling Grid Works 3d 15 Jun 18 19 Jun 18 5138

5139 Floor Tiling Works 3d 20 Jun 18 22 Jun 18 5139


5140 Wall Tiling works incl. IPS Panels 3d 25 Jun 18 27 Jun 18 5140
5141 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 28 Jun 18 05 Jul 18 5141
5142 Mark and Cut openings for MEP on walls including Ceiling 2d 06 Jul 18 09 Jul 18 5142
5143 Install Vanity Tops 4d 06 Jul 18 11 Jul 18 5143
5144 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 10 Jul 18 13 Jul 18 5144
5145 Fix MEP Final Fixtures 3d 13 Jul 18 17 Jul 18 5145
5146 Final Coat Paint on Ceiling 2d 18 Jul 18 19 Jul 18 5146
5147 Lobby 9w 1d 26 Apr 18 03 Jul 18 5147
5148 1st Fix Wall with Head tracks 1w 26 Apr 18 03 May 18 5148
5149 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 10 May 18 07 Jun 18 5149
5150 Fix Ceiling Grid 3d 08 Jun 18 12 Jun 18 5150
5151 Paint 1st Coat 2d 13 Jun 18 14 Jun 18 5151

5152 Fix doors incl. Ironmongery 2d 15 Jun 18 18 Jun 18 5152


5153 Mark and Cut openings for MEP on walls 2d 19 Jun 18 20 Jun 18 5153

5154 Install Ceiling Tiles 3d 21 Jun 18 25 Jun 18 5154

5155 Fix MEP Final Fixtures 3d 26 Jun 18 28 Jun 18 5155

5156 Final Coat Paint on walls and ceiling 3d 29 Jun 18 03 Jul 18 5156

5157 Staircase 5w 2d 29 May 18 04 Jul 18 5157


5158 H/L Electrical Containment & Conduits - 1st Fix 2d 29 May 18 30 May 18 5158

5159 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 31 May 18 01 Jun 18 5159

5160 Ceiling Rose fixing 1d 04 Jun 18 04 Jun 18 5160

5161 First Coat Paint on Walls & Ceiliings 2d 15 Jun 18 18 Jun 18 5161

5162 MEP Final Fixtures on Wall & Ceilings 2d 29 Jun 18 02 Jul 18 5162
5163 Final Coat Paint on walls & Ceilings 2d 03 Jul 18 04 Jul 18 5163
5164 Level 03 - CORE 01 12w 02 May 18 26 Jul 18 5164
5165 Toilet 12w 02 May 18 26 Jul 18 5165
5166 1st Fix Wall with Head tracks 1w 02 May 18 09 May 18 5166
5167 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 10 May 18 07 Jun 18 5167
5168 Fix Pocket Doors 1w 10 May 18 16 May 18 5168
5169 Inspection and Ceiling Grid Clearance 08 Jun 18 08 Jun 18 5169
5170 2nd Fix wall 1w 08 Jun 18 14 Jun 18 5170
5171 IPS Frame (Box Out only) incl. Backing ply 3d 15 Jun 18 19 Jun 18 5171
5172 Screed 2d 20 Jun 18 21 Jun 18 5172
5173 Fix Ceiling Grid Works 3d 22 Jun 18 26 Jun 18 5173

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5174 Floor Tiling Works 3d 27 Jun 18 29 Jun 18 5174
5175 Wall Tiling works incl. IPS Panels 3d 02 Jul 18 04 Jul 18 5175
5176 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 05 Jul 18 12 Jul 18 5176
5177 Mark and Cut openings for MEP on walls including Ceiling 2d 13 Jul 18 16 Jul 18 5177
5178 Install Vanity Tops 4d 13 Jul 18 18 Jul 18 5178
5179 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 17 Jul 18 20 Jul 18 5179
5180 Fix MEP Final Fixtures 3d 20 Jul 18 24 Jul 18 5180
5181 Final Coat Paint on Ceiling 2d 25 Jul 18 26 Jul 18 5181
5182 Lobby 9w 1d 04 May 18 10 Jul 18 5182

5183 1st Fix Wall with Head tracks 1w 04 May 18 11 May 18 5183

5184 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 17 May 18 14 Jun 18 5184
5185 Fix Ceiling Grid 3d 15 Jun 18 19 Jun 18 5185

5186 Paint 1st Coat 2d 20 Jun 18 21 Jun 18 5186

5187 Fix doors incl. Ironmongery 2d 22 Jun 18 25 Jun 18 5187

5188 Mark and Cut openings for MEP on walls 2d 26 Jun 18 27 Jun 18 5188

5189 Install Ceiling Tiles 3d 28 Jun 18 02 Jul 18 5189

5190 Fix MEP Final Fixtures 3d 03 Jul 18 05 Jul 18 5190

5191 Final Coat Paint on walls and ceiling 3d 06 Jul 18 10 Jul 18 5191
5192 Staircase 5w 2d 05 Jun 18 11 Jul 18 5192
5193 H/L Electrical Containment & Conduits - 1st Fix 2d 05 Jun 18 06 Jun 18 5193
5194 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 07 Jun 18 08 Jun 18 5194
5195 Ceiling Rose fixing 1d 11 Jun 18 11 Jun 18 5195
5196 First Coat Paint on Walls & Ceiliings 2d 22 Jun 18 25 Jun 18 5196
5197 MEP Final Fixtures on Wall & Ceilings 2d 06 Jul 18 09 Jul 18 5197
5198 Final Coat Paint on walls & Ceilings 2d 10 Jul 18 11 Jul 18 5198
5199 Level 04 - CORE 01 12w 10 May 18 02 Aug 18 5199
5200 Toilet 12w 10 May 18 02 Aug 18 5200
5201 1st Fix Wall with Head tracks 1w 10 May 18 16 May 18 5201
5202 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 17 May 18 14 Jun 18 5202
5203 Fix Pocket Doors 1w 17 May 18 23 May 18 5203
5204 Inspection and Ceiling Grid Clearance 15 Jun 18 15 Jun 18 5204
5205 2nd Fix wall 1w 15 Jun 18 21 Jun 18 5205
5206 IPS Frame (Box Out only) incl. Backing ply 3d 22 Jun 18 26 Jun 18 5206
5207 Screed 2d 27 Jun 18 28 Jun 18 5207

5208 Fix Ceiling Grid Works 3d 29 Jun 18 03 Jul 18 5208

5209 Floor Tiling Works 3d 04 Jul 18 06 Jul 18 5209

5210 Wall Tiling works incl. IPS Panels 3d 09 Jul 18 11 Jul 18 5210
5211 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 12 Jul 18 19 Jul 18 5211
5212 Mark and Cut openings for MEP on walls including Ceiling 2d 20 Jul 18 23 Jul 18 5212

5213 Install Vanity Tops 4d 20 Jul 18 25 Jul 18 5213


5214 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 24 Jul 18 27 Jul 18 5214
5215 Fix MEP Final Fixtures 3d 27 Jul 18 31 Jul 18 5215

5216 Final Coat Paint on Ceiling 2d 01 Aug 18 02 Aug 18 5216


5217 Lobby 9w 1d 14 May 18 17 Jul 18 5217

5218 1st Fix Wall with Head tracks 1w 14 May 18 18 May 18 5218
5219 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 24 May 18 21 Jun 18 5219
5220 Fix Ceiling Grid 3d 22 Jun 18 26 Jun 18 5220
5221 Paint 1st Coat 2d 27 Jun 18 28 Jun 18 5221
5222 Fix doors incl. Ironmongery 2d 29 Jun 18 02 Jul 18 5222
5223 Mark and Cut openings for MEP on walls 2d 03 Jul 18 04 Jul 18 5223
5224 Install Ceiling Tiles 3d 05 Jul 18 09 Jul 18 5224
5225 Fix MEP Final Fixtures 3d 10 Jul 18 12 Jul 18 5225
5226 Final Coat Paint on walls and ceiling 3d 13 Jul 18 17 Jul 18 5226
5227 Staircase 5w 2d 12 Jun 18 18 Jul 18 5227
5228 H/L Electrical Containment & Conduits - 1st Fix 2d 12 Jun 18 13 Jun 18 5228
5229 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 14 Jun 18 15 Jun 18 5229
5230 Ceiling Rose fixing 1d 18 Jun 18 18 Jun 18 5230

5231 First Coat Paint on Walls & Ceiliings 2d 29 Jun 18 02 Jul 18 5231

5232 MEP Final Fixtures on Wall & Ceilings 2d 13 Jul 18 16 Jul 18 5232

5233 Final Coat Paint on walls & Ceilings 2d 17 Jul 18 18 Jul 18 5233
5234 Level 05 - CORE 01 12w 17 May 18 09 Aug 18 5234

5235 Toilet 12w 17 May 18 09 Aug 18 5235


5236 1st Fix Wall with Head tracks 1w 17 May 18 23 May 18 5236
5237 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 24 May 18 21 Jun 18 5237
5238 Fix Pocket Doors 1w 24 May 18 31 May 18 5238

5239 Inspection and Ceiling Grid Clearance 22 Jun 18 22 Jun 18 5239


5240 2nd Fix wall 1w 22 Jun 18 28 Jun 18 5240

5241 IPS Frame (Box Out only) incl. Backing ply 3d 29 Jun 18 03 Jul 18 5241

5242 Screed 2d 04 Jul 18 05 Jul 18 5242

5243 Fix Ceiling Grid Works 3d 06 Jul 18 10 Jul 18 5243


5244 Floor Tiling Works 3d 11 Jul 18 13 Jul 18 5244
5245 Wall Tiling works incl. IPS Panels 3d 16 Jul 18 18 Jul 18 5245
5246 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 19 Jul 18 26 Jul 18 5246
5247 Mark and Cut openings for MEP on walls including Ceiling 2d 27 Jul 18 30 Jul 18 5247
5248 Install Vanity Tops 4d 27 Jul 18 01 Aug 18 5248
5249 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 31 Jul 18 03 Aug 18 5249
5250 Fix MEP Final Fixtures 3d 03 Aug 18 07 Aug 18 5250
5251 Final Coat Paint on Ceiling 2d 08 Aug 18 09 Aug 18 5251
5252 Lobby 9w 1d 21 May 18 24 Jul 18 5252
5253 1st Fix Wall with Head tracks 1w 21 May 18 25 May 18 5253
5254 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 Jun 18 28 Jun 18 5254
5255 Fix Ceiling Grid 3d 29 Jun 18 03 Jul 18 5255

5256 Paint 1st Coat 2d 04 Jul 18 05 Jul 18 5256

5257 Fix doors incl. Ironmongery 2d 06 Jul 18 09 Jul 18 5257

5258 Mark and Cut openings for MEP on walls 2d 10 Jul 18 11 Jul 18 5258

5259 Install Ceiling Tiles 3d 12 Jul 18 16 Jul 18 5259


5260 Fix MEP Final Fixtures 3d 17 Jul 18 19 Jul 18 5260

5261 Final Coat Paint on walls and ceiling 3d 20 Jul 18 24 Jul 18 5261
5262 Staircase 5w 2d 19 Jun 18 25 Jul 18 5262

5263 H/L Electrical Containment & Conduits - 1st Fix 2d 19 Jun 18 20 Jun 18 5263

5264 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 21 Jun 18 22 Jun 18 5264

5265 Ceiling Rose fixing 1d 25 Jun 18 25 Jun 18 5265

5266 First Coat Paint on Walls & Ceiliings 2d 06 Jul 18 09 Jul 18 5266

5267 MEP Final Fixtures on Wall & Ceilings 2d 20 Jul 18 23 Jul 18 5267
5268 Final Coat Paint on walls & Ceilings 2d 24 Jul 18 25 Jul 18 5268
5269 Level GF- CORE 01 12w 24 May 18 16 Aug 18 5269
5270 Toilet 12w 24 May 18 16 Aug 18 5270
5271 1st Fix Wall with Head tracks 1w 24 May 18 31 May 18 5271
5272 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 Jun 18 28 Jun 18 5272
5273 Fix Pocket Doors 1w 01 Jun 18 07 Jun 18 5273
5274 Inspection and Ceiling Grid Clearance 29 Jun 18 29 Jun 18 5274
5275 2nd Fix wall 1w 29 Jun 18 05 Jul 18 5275
5276 IPS Frame (Box Out only) incl. Backing ply 3d 06 Jul 18 10 Jul 18 5276
5277 Screed 2d 11 Jul 18 12 Jul 18 5277
5278 Fix Ceiling Grid Works 3d 13 Jul 18 17 Jul 18 5278
5279 Floor Tiling Works 3d 18 Jul 18 20 Jul 18 5279
5280 Wall Tiling works incl. IPS Panels 3d 23 Jul 18 25 Jul 18 5280

5281 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 26 Jul 18 02 Aug 18 5281

5282 Mark and Cut openings for MEP on walls including Ceiling 2d 03 Aug 18 06 Aug 18 5282
5283 Install Vanity Tops 4d 03 Aug 18 08 Aug 18 5283

5284 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 07 Aug 18 10 Aug 18 5284
5285 Fix MEP Final Fixtures 3d 10 Aug 18 14 Aug 18 5285

5286 Final Coat Paint on Ceiling 2d 15 Aug 18 16 Aug 18 5286


5287 Lobby 9w 1d 29 May 18 31 Jul 18 5287

5288 1st Fix Wall with Head tracks 1w 29 May 18 04 Jun 18 5288

5289 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 08 Jun 18 05 Jul 18 5289
5290 Fix Ceiling Grid 3d 06 Jul 18 10 Jul 18 5290

5291 Paint 1st Coat 2d 11 Jul 18 12 Jul 18 5291


5292 Fix doors incl. Ironmongery 2d 13 Jul 18 16 Jul 18 5292
5293 Mark and Cut openings for MEP on walls 2d 17 Jul 18 18 Jul 18 5293
5294 Install Ceiling Tiles 3d 19 Jul 18 23 Jul 18 5294
5295 Fix MEP Final Fixtures 3d 24 Jul 18 26 Jul 18 5295
5296 Final Coat Paint on walls and ceiling 3d 27 Jul 18 31 Jul 18 5296
5297 Staircase 5w 2d 26 Jun 18 01 Aug 18 5297
5298 H/L Electrical Containment & Conduits - 1st Fix 2d 26 Jun 18 27 Jun 18 5298
5299 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 28 Jun 18 29 Jun 18 5299
5300 Ceiling Rose fixing 1d 02 Jul 18 02 Jul 18 5300
5301 First Coat Paint on Walls & Ceiliings 2d 13 Jul 18 16 Jul 18 5301
5302 MEP Final Fixtures on Wall & Ceilings 2d 27 Jul 18 30 Jul 18 5302
5303 Final Coat Paint on walls & Ceilings 2d 31 Jul 18 01 Aug 18 5303

5304 Level 01 - CORE 02 12w 02 May 18 26 Jul 18 5304


5305 Toilet 12w 02 May 18 26 Jul 18 5305
5306 Floor slab available 02 May 18 02 May 18 5306

5307 1st Fix Wall with Head tracks 1w 02 May 18 09 May 18 5307
5308 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 10 May 18 07 Jun 18 5308

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5309 Fix Pocket Doors 1w 10 May 18 16 May 18 5309
5310 Inspection and Ceiling Grid Clearance 08 Jun 18 08 Jun 18 5310
5311 2nd Fix wall 1w 08 Jun 18 14 Jun 18 5311
5312 IPS Frame (Box Out only) incl. Backing ply 3d 15 Jun 18 19 Jun 18 5312
5313 Screed 2d 20 Jun 18 21 Jun 18 5313
5314 Fix Ceiling Grid Works 3d 22 Jun 18 26 Jun 18 5314
5315 Floor Tiling Works 3d 27 Jun 18 29 Jun 18 5315
5316 Wall Tiling works incl. IPS Panels 3d 02 Jul 18 04 Jul 18 5316
5317 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 05 Jul 18 12 Jul 18 5317

5318 Mark and Cut openings for MEP on walls including Ceiling 2d 13 Jul 18 16 Jul 18 5318

5319 Install Vanity Tops 4d 13 Jul 18 18 Jul 18 5319


5320 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 17 Jul 18 20 Jul 18 5320

5321 Fix MEP Final Fixtures 3d 20 Jul 18 24 Jul 18 5321

5322 Final Coat Paint on Ceiling 2d 25 Jul 18 26 Jul 18 5322

5323 Lobby 9w 1d 04 May 18 10 Jul 18 5323

5324 1st Fix Wall with Head tracks 1w 04 May 18 11 May 18 5324

5325 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 17 May 18 14 Jun 18 5325

5326 Fix Ceiling Grid 3d 15 Jun 18 19 Jun 18 5326


5327 Paint 1st Coat 2d 20 Jun 18 21 Jun 18 5327
5328 Fix doors incl. Ironmongery 2d 22 Jun 18 25 Jun 18 5328
5329 Mark and Cut openings for MEP on walls 2d 26 Jun 18 27 Jun 18 5329
5330 Install Ceiling Tiles 3d 28 Jun 18 02 Jul 18 5330
5331 Fix MEP Final Fixtures 3d 03 Jul 18 05 Jul 18 5331
5332 Final Coat Paint on walls and ceiling 3d 06 Jul 18 10 Jul 18 5332
5333 Staircase 5w 2d 05 Jun 18 11 Jul 18 5333
5334 H/L Electrical Containment & Conduits - 1st Fix 2d 05 Jun 18 06 Jun 18 5334
5335 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 07 Jun 18 08 Jun 18 5335
5336 Ceiling Rose fixing 1d 11 Jun 18 11 Jun 18 5336
5337 First Coat Paint on Walls & Ceiliings 2d 22 Jun 18 25 Jun 18 5337
5338 MEP Final Fixtures on Wall & Ceilings 2d 06 Jul 18 09 Jul 18 5338
5339 Final Coat Paint on walls & Ceilings 2d 10 Jul 18 11 Jul 18 5339
5340 Level 02 - CORE 02 12w 10 May 18 02 Aug 18 5340
5341 Toilet 12w 10 May 18 02 Aug 18 5341
5342 1st Fix Wall with Head tracks 1w 10 May 18 16 May 18 5342

5343 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 17 May 18 14 Jun 18 5343

5344 Fix Pocket Doors 1w 17 May 18 23 May 18 5344

5345 Inspection and Ceiling Grid Clearance 15 Jun 18 15 Jun 18 5345


5346 2nd Fix wall 1w 15 Jun 18 21 Jun 18 5346
5347 IPS Frame (Box Out only) incl. Backing ply 3d 22 Jun 18 26 Jun 18 5347

5348 Screed 2d 27 Jun 18 28 Jun 18 5348


5349 Fix Ceiling Grid Works 3d 29 Jun 18 03 Jul 18 5349
5350 Floor Tiling Works 3d 04 Jul 18 06 Jul 18 5350

5351 Wall Tiling works incl. IPS Panels 3d 09 Jul 18 11 Jul 18 5351
5352 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 12 Jul 18 19 Jul 18 5352

5353 Mark and Cut openings for MEP on walls including Ceiling 2d 20 Jul 18 23 Jul 18 5353
5354 Install Vanity Tops 4d 20 Jul 18 25 Jul 18 5354
5355 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 24 Jul 18 27 Jul 18 5355
5356 Fix MEP Final Fixtures 3d 27 Jul 18 31 Jul 18 5356
5357 Final Coat Paint on Ceiling 2d 01 Aug 18 02 Aug 18 5357
5358 Lobby 9w 1d 14 May 18 17 Jul 18 5358
5359 1st Fix Wall with Head tracks 1w 14 May 18 18 May 18 5359
5360 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 24 May 18 21 Jun 18 5360
5361 Fix Ceiling Grid 3d 22 Jun 18 26 Jun 18 5361
5362 Paint 1st Coat 2d 27 Jun 18 28 Jun 18 5362
5363 Fix doors incl. Ironmongery 2d 29 Jun 18 02 Jul 18 5363
5364 Mark and Cut openings for MEP on walls 2d 03 Jul 18 04 Jul 18 5364
5365 Install Ceiling Tiles 3d 05 Jul 18 09 Jul 18 5365

5366 Fix MEP Final Fixtures 3d 10 Jul 18 12 Jul 18 5366

5367 Final Coat Paint on walls and ceiling 3d 13 Jul 18 17 Jul 18 5367

5368 Staircase 5w 2d 12 Jun 18 18 Jul 18 5368

5369 H/L Electrical Containment & Conduits - 1st Fix 2d 12 Jun 18 13 Jun 18 5369

5370 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 14 Jun 18 15 Jun 18 5370

5371 Ceiling Rose fixing 1d 18 Jun 18 18 Jun 18 5371


5372 First Coat Paint on Walls & Ceiliings 2d 29 Jun 18 02 Jul 18 5372

5373 MEP Final Fixtures on Wall & Ceilings 2d 13 Jul 18 16 Jul 18 5373

5374 Final Coat Paint on walls & Ceilings 2d 17 Jul 18 18 Jul 18 5374

5375 Level 03 - CORE 02 12w 17 May 18 09 Aug 18 5375


5376 Toilet 12w 17 May 18 09 Aug 18 5376
5377 1st Fix Wall with Head tracks 1w 17 May 18 23 May 18 5377
5378 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 24 May 18 21 Jun 18 5378
5379 Fix Pocket Doors 1w 24 May 18 31 May 18 5379
5380 Inspection and Ceiling Grid Clearance 22 Jun 18 22 Jun 18 5380
5381 2nd Fix wall 1w 22 Jun 18 28 Jun 18 5381
5382 IPS Frame (Box Out only) incl. Backing ply 3d 29 Jun 18 03 Jul 18 5382
5383 Screed 2d 04 Jul 18 05 Jul 18 5383
5384 Fix Ceiling Grid Works 3d 06 Jul 18 10 Jul 18 5384
5385 Floor Tiling Works 3d 11 Jul 18 13 Jul 18 5385
5386 Wall Tiling works incl. IPS Panels 3d 16 Jul 18 18 Jul 18 5386
5387 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 19 Jul 18 26 Jul 18 5387
5388 Mark and Cut openings for MEP on walls including Ceiling 2d 27 Jul 18 30 Jul 18 5388
5389 Install Vanity Tops 4d 27 Jul 18 01 Aug 18 5389
5390 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 31 Jul 18 03 Aug 18 5390
5391 Fix MEP Final Fixtures 3d 03 Aug 18 07 Aug 18 5391
5392 Final Coat Paint on Ceiling 2d 08 Aug 18 09 Aug 18 5392
5393 Lobby 9w 1d 21 May 18 24 Jul 18 5393
5394 1st Fix Wall with Head tracks 1w 21 May 18 25 May 18 5394
5395 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 Jun 18 28 Jun 18 5395
5396 Fix Ceiling Grid 3d 29 Jun 18 03 Jul 18 5396
5397 Paint 1st Coat 2d 04 Jul 18 05 Jul 18 5397

5398 Fix doors incl. Ironmongery 2d 06 Jul 18 09 Jul 18 5398


5399 Mark and Cut openings for MEP on walls 2d 10 Jul 18 11 Jul 18 5399

5400 Install Ceiling Tiles 3d 12 Jul 18 16 Jul 18 5400


5401 Fix MEP Final Fixtures 3d 17 Jul 18 19 Jul 18 5401
5402 Final Coat Paint on walls and ceiling 3d 20 Jul 18 24 Jul 18 5402
5403 Staircase 5w 2d 19 Jun 18 25 Jul 18 5403
5404 H/L Electrical Containment & Conduits - 1st Fix 2d 19 Jun 18 20 Jun 18 5404
5405 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 21 Jun 18 22 Jun 18 5405
5406 Ceiling Rose fixing 1d 25 Jun 18 25 Jun 18 5406
5407 First Coat Paint on Walls & Ceiliings 2d 06 Jul 18 09 Jul 18 5407
5408 MEP Final Fixtures on Wall & Ceilings 2d 20 Jul 18 23 Jul 18 5408
5409 Final Coat Paint on walls & Ceilings 2d 24 Jul 18 25 Jul 18 5409
5410 Level 04 - CORE 02 12w 24 May 18 16 Aug 18 5410
5411 Toilet 12w 24 May 18 16 Aug 18 5411
5412 1st Fix Wall with Head tracks 1w 24 May 18 31 May 18 5412
5413 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 Jun 18 28 Jun 18 5413
5414 Fix Pocket Doors 1w 01 Jun 18 07 Jun 18 5414
5415 Inspection and Ceiling Grid Clearance 29 Jun 18 29 Jun 18 5415

5416 2nd Fix wall 1w 29 Jun 18 05 Jul 18 5416


5417 IPS Frame (Box Out only) incl. Backing ply 3d 06 Jul 18 10 Jul 18 5417
5418 Screed 2d 11 Jul 18 12 Jul 18 5418

5419 Fix Ceiling Grid Works 3d 13 Jul 18 17 Jul 18 5419


5420 Floor Tiling Works 3d 18 Jul 18 20 Jul 18 5420

5421 Wall Tiling works incl. IPS Panels 3d 23 Jul 18 25 Jul 18 5421
5422 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 26 Jul 18 02 Aug 18 5422

5423 Mark and Cut openings for MEP on walls including Ceiling 2d 03 Aug 18 06 Aug 18 5423

5424 Install Vanity Tops 4d 03 Aug 18 08 Aug 18 5424


5425 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 07 Aug 18 10 Aug 18 5425

5426 Fix MEP Final Fixtures 3d 10 Aug 18 14 Aug 18 5426


5427 Final Coat Paint on Ceiling 2d 15 Aug 18 16 Aug 18 5427
5428 Lobby 9w 1d 29 May 18 31 Jul 18 5428
5429 1st Fix Wall with Head tracks 1w 29 May 18 04 Jun 18 5429
5430 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 08 Jun 18 05 Jul 18 5430
5431 Fix Ceiling Grid 3d 06 Jul 18 10 Jul 18 5431
5432 Paint 1st Coat 2d 11 Jul 18 12 Jul 18 5432
5433 Fix doors incl. Ironmongery 2d 13 Jul 18 16 Jul 18 5433
5434 Mark and Cut openings for MEP on walls 2d 17 Jul 18 18 Jul 18 5434
5435 Install Ceiling Tiles 3d 19 Jul 18 23 Jul 18 5435
5436 Fix MEP Final Fixtures 3d 24 Jul 18 26 Jul 18 5436
5437 Final Coat Paint on walls and ceiling 3d 27 Jul 18 31 Jul 18 5437
5438 Staircase 5w 2d 26 Jun 18 01 Aug 18 5438

5439 H/L Electrical Containment & Conduits - 1st Fix 2d 26 Jun 18 27 Jun 18 5439
5440 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 28 Jun 18 29 Jun 18 5440

5441 Ceiling Rose fixing 1d 02 Jul 18 02 Jul 18 5441


5442 First Coat Paint on Walls & Ceiliings 2d 13 Jul 18 16 Jul 18 5442
5443 MEP Final Fixtures on Wall & Ceilings 2d 27 Jul 18 30 Jul 18 5443

5444 Final Coat Paint on walls & Ceilings 2d 31 Jul 18 01 Aug 18 5444
5445 Level 05 - CORE 02 12w 01 Jun 18 23 Aug 18 5445

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5446 Toilet 12w 01 Jun 18 23 Aug 18 5446
5447 1st Fix Wall with Head tracks 1w 01 Jun 18 07 Jun 18 5447
5448 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 08 Jun 18 05 Jul 18 5448
5449 Fix Pocket Doors 1w 08 Jun 18 14 Jun 18 5449
5450 Inspection and Ceiling Grid Clearance 06 Jul 18 06 Jul 18 5450
5451 2nd Fix wall 1w 06 Jul 18 12 Jul 18 5451
5452 IPS Frame (Box Out only) incl. Backing ply 3d 13 Jul 18 17 Jul 18 5452
5453 Screed 2d 18 Jul 18 19 Jul 18 5453
5454 Fix Ceiling Grid Works 3d 20 Jul 18 24 Jul 18 5454

5455 Floor Tiling Works 3d 25 Jul 18 27 Jul 18 5455

5456 Wall Tiling works incl. IPS Panels 3d 30 Jul 18 01 Aug 18 5456
5457 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 02 Aug 18 09 Aug 18 5457

5458 Mark and Cut openings for MEP on walls including Ceiling 2d 10 Aug 18 13 Aug 18 5458

5459 Install Vanity Tops 4d 10 Aug 18 15 Aug 18 5459

5460 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 14 Aug 18 17 Aug 18 5460

5461 Fix MEP Final Fixtures 3d 17 Aug 18 21 Aug 18 5461

5462 Final Coat Paint on Ceiling 2d 22 Aug 18 23 Aug 18 5462

5463 Lobby 9w 1d 05 Jun 18 07 Aug 18 5463


5464 1st Fix Wall with Head tracks 1w 05 Jun 18 11 Jun 18 5464
5465 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 15 Jun 18 12 Jul 18 5465
5466 Fix Ceiling Grid 3d 13 Jul 18 17 Jul 18 5466
5467 Paint 1st Coat 2d 18 Jul 18 19 Jul 18 5467
5468 Fix doors incl. Ironmongery 2d 20 Jul 18 23 Jul 18 5468
5469 Mark and Cut openings for MEP on walls 2d 24 Jul 18 25 Jul 18 5469
5470 Install Ceiling Tiles 3d 26 Jul 18 30 Jul 18 5470
5471 Fix MEP Final Fixtures 3d 31 Jul 18 02 Aug 18 5471
5472 Final Coat Paint on walls and ceiling 3d 03 Aug 18 07 Aug 18 5472
5473 Staircase 5w 2d 03 Jul 18 08 Aug 18 5473
5474 H/L Electrical Containment & Conduits - 1st Fix 2d 03 Jul 18 04 Jul 18 5474
5475 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 05 Jul 18 06 Jul 18 5475
5476 Ceiling Rose fixing 1d 09 Jul 18 09 Jul 18 5476
5477 First Coat Paint on Walls & Ceiliings 2d 20 Jul 18 23 Jul 18 5477
5478 MEP Final Fixtures on Wall & Ceilings 2d 03 Aug 18 06 Aug 18 5478
5479 Final Coat Paint on walls & Ceilings 2d 07 Aug 18 08 Aug 18 5479

5480 Level GF - CORE 02 12w 08 Jun 18 31 Aug 18 5480

5481 Toilet 12w 08 Jun 18 31 Aug 18 5481

5482 1st Fix Wall with Head tracks 1w 08 Jun 18 14 Jun 18 5482

5483 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 15 Jun 18 12 Jul 18 5483
5484 Fix Pocket Doors 1w 15 Jun 18 21 Jun 18 5484

5485 Inspection and Ceiling Grid Clearance 13 Jul 18 13 Jul 18 5485


5486 2nd Fix wall 1w 13 Jul 18 19 Jul 18 5486

5487 IPS Frame (Box Out only) incl. Backing ply 3d 20 Jul 18 24 Jul 18 5487

5488 Screed 2d 25 Jul 18 26 Jul 18 5488

5489 Fix Ceiling Grid Works 3d 27 Jul 18 31 Jul 18 5489

5490 Floor Tiling Works 3d 01 Aug 18 03 Aug 18 5490

5491 Wall Tiling works incl. IPS Panels 3d 06 Aug 18 08 Aug 18 5491
5492 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 09 Aug 18 16 Aug 18 5492
5493 Mark and Cut openings for MEP on walls including Ceiling 2d 17 Aug 18 20 Aug 18 5493
5494 Install Vanity Tops 4d 17 Aug 18 22 Aug 18 5494
5495 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 21 Aug 18 24 Aug 18 5495
5496 Fix MEP Final Fixtures 3d 24 Aug 18 29 Aug 18 5496
5497 Final Coat Paint on Ceiling 2d 30 Aug 18 31 Aug 18 5497
5498 Lobby 9w 1d 12 Jun 18 14 Aug 18 5498
5499 1st Fix Wall with Head tracks 1w 12 Jun 18 18 Jun 18 5499
5500 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 22 Jun 18 19 Jul 18 5500
5501 Fix Ceiling Grid 3d 20 Jul 18 24 Jul 18 5501
5502 Paint 1st Coat 2d 25 Jul 18 26 Jul 18 5502
5503 Fix doors incl. Ironmongery 2d 27 Jul 18 30 Jul 18 5503

5504 Mark and Cut openings for MEP on walls 2d 31 Jul 18 01 Aug 18 5504

5505 Install Ceiling Tiles 3d 02 Aug 18 06 Aug 18 5505

5506 Fix MEP Final Fixtures 3d 07 Aug 18 09 Aug 18 5506

5507 Final Coat Paint on walls and ceiling 3d 10 Aug 18 14 Aug 18 5507

5508 Staircase 5w 2d 10 Jul 18 15 Aug 18 5508

5509 H/L Electrical Containment & Conduits - 1st Fix 2d 10 Jul 18 11 Jul 18 5509

5510 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 12 Jul 18 13 Jul 18 5510

5511 Ceiling Rose fixing 1d 16 Jul 18 16 Jul 18 5511

5512 First Coat Paint on Walls & Ceiliings 2d 27 Jul 18 30 Jul 18 5512

5513 MEP Final Fixtures on Wall & Ceilings 2d 10 Aug 18 13 Aug 18 5513

5514 Final Coat Paint on walls & Ceilings 2d 14 Aug 18 15 Aug 18 5514

5515 Staircase Flooring incl. Nosing 4w 26 Nov 18 21 Dec 18 5515

5516 Groundfloor refuse room cladding 2w 18 Jun 18 29 Jun 18 5516

5517 Latest Date for ABP/WTP to omit Cat A Shell and Core Fit-out scope of works to Building 5B 01 Mar 18 01 Mar 18 5517

5518 Cat A Fit Out 35w 2d 23 Apr 18 14 Jan 19 5518

5519 Fit out Ground Floor Unit 2 and 3 5w 1d 21 Jun 18 26 Jul 18 5519

5520 Install conduit to cleaners sockets to core walls 3d 21 Jun 18 25 Jun 18 5520

5521
5521 Boarding and Insulation to external and core walls 1w 26 Jun 18 02 Jul 18
5522 Install wiring to containment in ceilings 1w 03 Jul 18 09 Jul 18 5522

5523
5523 Taping and Joining to Walls 2d 03 Jul 18 04 Jul 18
5524 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 10 Jul 18 16 Jul 18 5524

5525
5525 Install Joinery incl Doors 1w 17 Jul 18 23 Jul 18
5526 Decoration 1w 20 Jul 18 26 Jul 18 5526

5527 Fit-out First Floor 16w 4d 23 Apr 18 21 Aug 18 5527

5528 Units 1 and 2 5w 1d 05 Jul 18 09 Aug 18 5528

5529
5529 Install conduit to cleaners sockets to core walls 3d 05 Jul 18 09 Jul 18
5530 Boarding and Insulation to external and core walls 1w 10 Jul 18 16 Jul 18 5530

5531 Install wiring to containment in ceilings 1w 17 Jul 18 23 Jul 18 5531

5532 Taping and Joining to Walls 2d 17 Jul 18 18 Jul 18 5532

5533
5533 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 24 Jul 18 30 Jul 18
5534 Install Joinery incl Doors 1w 31 Jul 18 06 Aug 18 5534

5535
5535 Decoration 1w 03 Aug 18 09 Aug 18
5536 Units 3 and 4 5w 1d 17 Jul 18 21 Aug 18 5536

5537
5537 Install conduit to cleaners sockets to core walls 3d 17 Jul 18 19 Jul 18
5538 Boarding and Insulation to external and core walls 1w 20 Jul 18 26 Jul 18 5538

5539 Install wiring to containment in ceilings 1w 27 Jul 18 02 Aug 18 5539

5540 Taping and Joining to Walls 3d 27 Jul 18 31 Jul 18 5540

5541
5541 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 03 Aug 18 09 Aug 18
5542 Install Joinery incl Doors 1w 10 Aug 18 16 Aug 18 5542

5543
5543 Decoration 1w 15 Aug 18 21 Aug 18
5544 High Level Services First Floor 8w 23 Apr 18 20 Jun 18 5544

5545 Fit-out Second Floor 16w 4d 09 May 18 05 Sep 18 5545

5546 Units 1 and 2 5w 1d 19 Jul 18 23 Aug 18 5546

5547
5547 Install conduit to cleaners sockets to core walls 3d 19 Jul 18 23 Jul 18
5548 Boarding and Insulation to external and core walls 1w 24 Jul 18 30 Jul 18 5548

5549 Install wiring to containment in ceilings 1w 31 Jul 18 06 Aug 18 5549

5550
5550 Taping and Joining to Walls 2d 31 Jul 18 01 Aug 18
5551 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 07 Aug 18 13 Aug 18 5551

5552
5552 Install Joinery incl Doors 1w 14 Aug 18 20 Aug 18
5553 Decoration 1w 17 Aug 18 23 Aug 18 5553

5554 Units 3 and 4 5w 1d 31 Jul 18 05 Sep 18 5554

5555 Install conduit to cleaners sockets to core walls 3d 31 Jul 18 02 Aug 18 5555

5556
5556 Boarding and Insulation to external and core walls 1w 03 Aug 18 09 Aug 18
5557 Install wiring to containment in ceilings 1w 10 Aug 18 16 Aug 18 5557

5558
5558 Taping and Joining to Walls 3d 10 Aug 18 14 Aug 18
5559 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 17 Aug 18 23 Aug 18 5559

5560
5560 Install Joinery incl Doors 1w 24 Aug 18 31 Aug 18
5561 Decoration 1w 30 Aug 18 05 Sep 18 5561

5562 High Level Services Second Floor 8w 09 May 18 04 Jul 18 5562

5563 Fit-out Third Floor 16w 4d 23 May 18 19 Sep 18 5563

5564 Units 1 and 2 5w 1d 02 Aug 18 07 Sep 18 5564

5565 Install conduit to cleaners sockets to core walls 3d 02 Aug 18 06 Aug 18 5565

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5566 Boarding and Insulation to external and core walls 1w 07 Aug 18 13 Aug 18 5566

5567 Install wiring to containment in ceilings 1w 14 Aug 18 20 Aug 18 5567

5568 Taping and Joining to Walls 2d 14 Aug 18 15 Aug 18 5568

5569
5569 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 21 Aug 18 28 Aug 18
5570 Install Joinery incl Doors 1w 29 Aug 18 04 Sep 18 5570

5571
5571 Decoration 1w 03 Sep 18 07 Sep 18
5572 Units 3 and 4 5w 1d 14 Aug 18 19 Sep 18 5572

5573
5573 Install conduit to cleaners sockets to core walls 3d 14 Aug 18 16 Aug 18
5574 Boarding and Insulation to external and core walls 1w 17 Aug 18 23 Aug 18 5574

5575 Install wiring to containment in ceilings 1w 24 Aug 18 31 Aug 18 5575

5576 Taping and Joining to Walls 3d 24 Aug 18 29 Aug 18 5576

5577
5577 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 03 Sep 18 07 Sep 18
5578 Install Joinery incl Doors 1w 10 Sep 18 14 Sep 18 5578

5579
5579 Decoration 1w 13 Sep 18 19 Sep 18
5580 High Level Services Third Floor 8w 23 May 18 18 Jul 18 5580

5581 Fit-out Fourth Floor 16w 4d 07 Jun 18 03 Oct 18 5581

5582 Units 1 and 2 5w 1d 16 Aug 18 21 Sep 18 5582

5583
5583 Install conduit to cleaners sockets to core walls 3d 16 Aug 18 20 Aug 18
5584 Boarding and Insulation to external and core walls 1w 21 Aug 18 28 Aug 18 5584

5585 Install wiring to containment in ceilings 1w 29 Aug 18 04 Sep 18 5585

5586 Taping and Joining to Walls 2d 29 Aug 18 30 Aug 18 5586

5587
5587 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 05 Sep 18 11 Sep 18
5588 Install Joinery incl Doors 1w 12 Sep 18 18 Sep 18 5588

5589 Decoration 1w 17 Sep 18 21 Sep 18 5589

5590 Units 3 and 4 5w 1d 29 Aug 18 03 Oct 18 5590

5591 Install conduit to cleaners sockets to core walls 3d 29 Aug 18 31 Aug 18 5591

5592
5592 Boarding and Insulation to external and core walls 1w 03 Sep 18 07 Sep 18
5593 Install wiring to containment in ceilings 1w 10 Sep 18 14 Sep 18 5593

5594
5594 Taping and Joining to Walls 3d 10 Sep 18 12 Sep 18
5595 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 17 Sep 18 21 Sep 18 5595

5596
5596 Install Joinery incl Doors 1w 24 Sep 18 28 Sep 18
5597 Decoration 1w 27 Sep 18 03 Oct 18 5597

5598 High Level Services Fourth Floor 8w 07 Jun 18 01 Aug 18 5598

5599 Fit-out Fifth Floor 16w 4d 21 Jun 18 17 Oct 18 5599

5600 Units 1 and 2 5w 1d 31 Aug 18 05 Oct 18 5600

5601 Install conduit to cleaners sockets to core walls 3d 31 Aug 18 04 Sep 18 5601

5602
5602 Boarding and Insulation to external and core walls 1w 05 Sep 18 11 Sep 18
5603 Install wiring to containment in ceilings 1w 12 Sep 18 18 Sep 18 5603

5604
5604 Taping and Joining to Walls 2d 12 Sep 18 13 Sep 18
5605 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 19 Sep 18 25 Sep 18 5605

5606
5606 Install Joinery incl Doors 1w 26 Sep 18 02 Oct 18
5607 Decoration 1w 01 Oct 18 05 Oct 18 5607

5608 Units 3 and 4 5w 1d 12 Sep 18 17 Oct 18 5608

5609 Install conduit to cleaners sockets to core walls 3d 12 Sep 18 14 Sep 18 5609

5610
5610 Boarding and Insulation to external and core walls 1w 17 Sep 18 21 Sep 18
5611 Install wiring to containment in ceilings 1w 24 Sep 18 28 Sep 18 5611

5612
5612 Taping and Joining to Walls 3d 24 Sep 18 26 Sep 18
5613 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 01 Oct 18 05 Oct 18 5613

5614
5614 Install Joinery incl Doors 1w 08 Oct 18 12 Oct 18
5615 Decoration 1w 11 Oct 18 17 Oct 18 5615

5616 High Level Services Fifth Floor 8w 21 Jun 18 15 Aug 18 5616

5617 Temporary Access Closure - CAT A Fitout 2w 15 Oct 18 26 Oct 18 5617

5618 Fit out First Floor 2d 25 Oct 18 26 Oct 18 5618

5619 Partition closure 2d 25 Oct 18 26 Oct 18 5619

5620 Fit out Second Floor 2d 23 Oct 18 24 Oct 18 5620

5621 Partition closure 2d 23 Oct 18 24 Oct 18 5621

5622 Fit out Third Floor 2d 19 Oct 18 22 Oct 18 5622

5623 Partition closure 2d 19 Oct 18 22 Oct 18 5623

5624 Fit out Fourth Floor 2d 17 Oct 18 18 Oct 18 5624

5625 Partition closure 2d 17 Oct 18 18 Oct 18 5625

5626 Fit out Fifth Floor 2d 15 Oct 18 16 Oct 18 5626

5627 Partition closure 2d 15 Oct 18 16 Oct 18 5627

5628 Prepare to Handover Units 7w 1d 12 Nov 18 14 Jan 19 5628

5629 Prepare to Hand Over Units 1 and 2 5w 4d 12 Nov 18 20 Dec 18 5629

5630 Ground floor 2w 4d 12 Nov 18 29 Nov 18 5630

5631 Complete Ceiling Tiles 1w 12 Nov 18 16 Nov 18 5631

5632 Install Raised Access Floor incl Below Floor Barriers 1w 19 Nov 18 23 Nov 18 5632

5633 Soft Floor Coverings 4d 26 Nov 18 29 Nov 18 5633

5634 First floor 2w 4d 15 Nov 18 04 Dec 18 5634

5635 Complete Ceiling Tiles 1w 15 Nov 18 21 Nov 18 5635

5636 Install Raised Access Floor incl Below Floor Barriers 1w 22 Nov 18 28 Nov 18 5636

5637 Soft Floor Coverings 4d 29 Nov 18 04 Dec 18 5637

5638 Second Floor 2w 4d 20 Nov 18 07 Dec 18 5638

5639 Complete Ceiling Tiles 1w 20 Nov 18 26 Nov 18 5639

5640 Install Raised Access Floor incl Below Floor Barriers 1w 27 Nov 18 03 Dec 18 5640

5641 Soft Floor Coverings 4d 04 Dec 18 07 Dec 18 5641

5642 Third Floor 2w 4d 23 Nov 18 12 Dec 18 5642

5643 Complete Ceiling Tiles 1w 23 Nov 18 29 Nov 18 5643

5644 Install Raised Access Floor incl Below Floor Barriers 1w 30 Nov 18 06 Dec 18 5644

5645 Soft Floor Coverings 4d 07 Dec 18 12 Dec 18 5645

5646 Fourth Floor 2w 4d 28 Nov 18 17 Dec 18 5646

5647 Complete Ceiling Tiles 1w 28 Nov 18 04 Dec 18 5647

5648 Install Raised Access Floor incl Below Floor Barriers 1w 05 Dec 18 11 Dec 18 5648

5649 Soft Floor Coverings 4d 12 Dec 18 17 Dec 18 5649

5650 Fifth Floor 2w 4d 03 Dec 18 20 Dec 18 5650

5651 Complete Ceiling Tiles 1w 03 Dec 18 07 Dec 18 5651

5652 Install Raised Access Floor incl Below Floor Barriers 1w 10 Dec 18 14 Dec 18 5652

5653 Soft Floor Coverings 4d 17 Dec 18 20 Dec 18 5653

5654 Prepare to Hand Over Units 3 and 4 6w 1d 19 Nov 18 14 Jan 19 5654

5655 Ground Floor 2w 4d 19 Nov 18 06 Dec 18 5655

5656 Complete Ceiling Tiles 1w 19 Nov 18 23 Nov 18 5656

5657 Install Raised Access Floor incl Below Floor Barriers 1w 26 Nov 18 30 Nov 18 5657

5658 Soft Floor Coverings 4d 03 Dec 18 06 Dec 18 5658

5659 First Floor 2w 4d 22 Nov 18 11 Dec 18 5659

5660 Complete Ceiling Tiles 1w 22 Nov 18 28 Nov 18 5660

5661 Install Raised Access Floor incl Below Floor Barriers 1w 29 Nov 18 05 Dec 18 5661

5662 Soft Floor Coverings 4d 06 Dec 18 11 Dec 18 5662

5663 Second Floor 2w 4d 27 Nov 18 14 Dec 18 5663

5664 Complete Ceiling Tiles 1w 27 Nov 18 03 Dec 18 5664

5665 Install Raised Access Floor incl Below Floor Barriers 1w 04 Dec 18 10 Dec 18 5665

5666 Soft Floor Coverings 4d 11 Dec 18 14 Dec 18 5666

5667 Third Floor 2w 4d 30 Nov 18 19 Dec 18 5667

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5668 Complete Ceiling Tiles 1w 30 Nov 18 06 Dec 18 5668

5669 Install Raised Access Floor incl Below Floor Barriers 1w 07 Dec 18 13 Dec 18 5669

5670 Soft Floor Coverings 4d 14 Dec 18 19 Dec 18 5670

5671 Fourth Floor 2w 4d 05 Dec 18 07 Jan 19 5671

5672 Complete Ceiling Tiles 1w 05 Dec 18 11 Dec 18 5672

5673 Install Raised Access Floor incl Below Floor Barriers 1w 12 Dec 18 18 Dec 18 5673

5674 Soft Floor Coverings 4d 19 Dec 18 07 Jan 19 5674

5675 Fifth Floor 2w 4d 12 Dec 18 14 Jan 19 5675

5676 Complete Ceiling Tiles 1w 12 Dec 18 18 Dec 18 5676

5677 Install Raised Access Floor incl Below Floor Barriers 1w 19 Dec 18 08 Jan 19 5677

5678 Soft Floor Coverings 4d 09 Jan 19 14 Jan 19 5678

5679 Building 5B complete 06 Mar 19 06 Mar 19 5679

5680 External Landscaping to Buildings 5A & 5B 16w 10 Sep 18 11 Jan 19 5680

5681 Kerbs North of 5A 4w 14 Sep 18 11 Oct 18 5681

5682 Lay Road Kerbs (250 linear meters ) 3w 14 Sep 18 04 Oct 18 5682
5683 Lay Channel Kerb 1w 3d 28 Sep 18 09 Oct 18 5683
5684 Lay Kerb To Foothpath 1w 05 Oct 18 11 Oct 18 5684
5685 Paving and Tarmac North of 5A 10w 2d 12 Oct 18 07 Jan 19 5685
5686 Sets to Footpath 4w 12 Oct 18 08 Nov 18 5686
5687 Flags to Footpath 2w 4d 09 Nov 18 28 Nov 18 5687
5688 Mistal Paving to west of 5A 2w 29 Nov 18 12 Dec 18 5688
5689 Regulate for Tarmac 3d 13 Dec 18 17 Dec 18 5689
5690 Tarmac 1w 18 Dec 18 07 Jan 19 5690
5691 Hard Landscaping Between 5A and 5B 13w 10 Sep 18 07 Dec 18 5691
5692 Prep Works 3w 10 Sep 18 28 Sep 18 5692
5693 Import work to Finish Level 1w 10 Sep 18 14 Sep 18 5693
5694 Install ten number tree pits 1w 17 Sep 18 21 Sep 18 5694
5695 Prep for Paving and Kerbs 1w 24 Sep 18 28 Sep 18 5695
5696 Kerbs and Stairs 2w 01 Oct 18 12 Oct 18 5696

5697 Lay Kerbs (221 linear meters ) 2w 01 Oct 18 12 Oct 18 5697


5698 Install Stairs 1w 08 Oct 18 12 Oct 18 5698
5699 Paving 8w 15 Oct 18 07 Dec 18 5699
5700 Sets to GL7 (160m2 ) 3w 1d 15 Oct 18 05 Nov 18 5700

5701 Paving to central area GL7-5 (496M2) 6w 3d 22 Oct 18 05 Dec 18 5701


5702 Sets to GL 5 (64M2) 1w 2d 29 Nov 18 07 Dec 18 5702

5703 External Lighting 7w 17 Sep 18 02 Nov 18 5703

5704 Soft Landscaping 8w 05 Nov 18 11 Jan 19 5704

5705 Landscaping complete to Building 5A and 5B 14 Jan 19 14 Jan 19 5705

5706 Commissioning 27w 1d 05 Jul 18 25 Jan 19 5706

5707
5707 TEC (Provisional Sum) 13w 1d 05 Jul 18 05 Oct 18
5708 Flush Water Primary Systems 7w 05 Jul 18 22 Aug 18 5708

5709 Commission Energy Centre 8w 10 Aug 18 05 Oct 18 5709

5710 Building 8B 18w 08 Aug 18 12 Dec 18 5710

5711 Precommission M & E Plant 8w 08 Aug 18 03 Oct 18 5711

5712 Commission Floors 10w 04 Oct 18 12 Dec 18 5712

5713
5713 Building 8A 16w 14 Aug 18 04 Dec 18
5714 Precommission M & E Plant 7w 14 Aug 18 02 Oct 18 5714

5715 Commission Floors 10w 26 Sep 18 04 Dec 18 5715

5716 Building 9A 15w 16 Aug 18 29 Nov 18 5716

5717 Precommission M & E Plant 6w 16 Aug 18 27 Sep 18 5717

5718 Commission Floors 10w 21 Sep 18 29 Nov 18 5718

5719 Building 5A 20w 16 Aug 18 17 Jan 19 5719

5720 Precommission M & E Plant 8w 16 Aug 18 11 Oct 18 5720

5721 Commission Floors 13w 05 Oct 18 17 Jan 19 5721

5722
5722 Building 5B 15w 01 Oct 18 25 Jan 19
5723 Precommission M & E Plant 6w 01 Oct 18 09 Nov 18 5723

5724 Commission Floors 10w 05 Nov 18 25 Jan 19 5724

5725 Handover 14w 3d 09 Nov 18 06 Mar 19 5725

5726
5726 Building 8B Snag and Handover to CITIC / ABP 11w 14 Nov 18 13 Feb 19
5727 Units 1 & 2 9w 14 Nov 18 30 Jan 19 5727

5728 Inspection and Snagging of Units 1 & 2 2w 14 Nov 18 27 Nov 18 5728

5729 De-snagging Units 1 & 2 2w 21 Nov 18 04 Dec 18 5729

5730 Hand Over Units 1 & 2 to CITIC 05 Dec 18 05 Dec 18 5730

5731 CITIC prepare defects list 1w 05 Dec 18 11 Dec 18 5731

5732 Desnag CITIC Defects 2w 12 Dec 18 08 Jan 19 5732

5733 Present Units 1 & 2 to ABP 09 Jan 19 09 Jan 19 5733

5734 ABP prepare defects list 1w 09 Jan 19 15 Jan 19 5734

5735 Desnag ABP defects 2w 16 Jan 19 29 Jan 19 5735

5736 Hand units 1 & 2 to ABP 30 Jan 19 30 Jan 19 5736

5737 Units 3 & 4 9w 21 Nov 18 06 Feb 19 5737

5738 Inspection and Snagging of Units 3 & 4 2w 21 Nov 18 04 Dec 18 5738

5739 De-snagging Units 3 & 4 2w 28 Nov 18 11 Dec 18 5739

5740 Hand Over Units 3 & 4 to CITIC 12 Dec 18 12 Dec 18 5740

5741 CITIC prepare defects list 1w 12 Dec 18 18 Dec 18 5741

5742 Desnag CITIC Defects 2w 19 Dec 18 15 Jan 19 5742

5743 Present Units 3 & 4 to ABP 16 Jan 19 16 Jan 19 5743

5744 ABP prepare defects list 1w 16 Jan 19 22 Jan 19 5744

5745 Desnag ABP defects 2w 23 Jan 19 05 Feb 19 5745

5746 Hand units 3 & 4 to ABP 06 Feb 19 06 Feb 19 5746

5747 Units 5 & 6 9w 28 Nov 18 13 Feb 19 5747

5748 Inspection and Snagging of Units 5 & 6 2w 28 Nov 18 11 Dec 18 5748

5749 De-snagging Units 5 & 6 2w 05 Dec 18 18 Dec 18 5749

5750 Hand Over Units 5 & 6 to CITIC 19 Dec 18 19 Dec 18 5750

5751 CITIC prepare defects list 1w 19 Dec 18 08 Jan 19 5751

5752 Desnag CITIC Defects 2w 09 Jan 19 22 Jan 19 5752

5753 Present Units 5 & 6 to ABP 23 Jan 19 23 Jan 19 5753

5754 ABP prepare defects list 1w 23 Jan 19 29 Jan 19 5754

5755 Desnag ABP defects 2w 30 Jan 19 12 Feb 19 5755

5756 Hand units 5 & 6 to ABP 13 Feb 19 13 Feb 19 5756

5757
5757 Building 8A Snag and Handover to CITIC / ABP 10w 09 Nov 18 01 Feb 19
5758 Units 1 & 2 9w 09 Nov 18 25 Jan 19 5758

5759 Inspection and Snagging of Units 1 & 2 2w 09 Nov 18 22 Nov 18 5759

5760 De-snagging Units 1 & 2 2w 16 Nov 18 29 Nov 18 5760

5761 Hand Over Units 1 & 2 to CITIC 30 Nov 18 30 Nov 18 5761

5762 CITIC prepare defects list 1w 30 Nov 18 06 Dec 18 5762

5763 Desnag CITIC Defects 2w 07 Dec 18 20 Dec 18 5763

5764 Present Units 1 & 2 to ABP 21 Dec 18 21 Dec 18 5764

5765 ABP prepare defects list 1w 21 Dec 18 10 Jan 19 5765

5766 Desnag ABP defects 2w 11 Jan 19 24 Jan 19 5766

5767 Hand units 1 & 2 to ABP 25 Jan 19 25 Jan 19 5767

5768 Units 3 & 4 9w 16 Nov 18 01 Feb 19 5768

5769 Inspection and Snagging of Units 3 & 4 2w 16 Nov 18 29 Nov 18 5769

5770 De-snagging Units 3 & 4 2w 23 Nov 18 06 Dec 18 5770

5771 Hand Over Units 3 & 4 to CITIC 07 Dec 18 07 Dec 18 5771

5772 CITIC prepare defects list 1w 07 Dec 18 13 Dec 18 5772

5773 Desnag CITIC Defects 2w 14 Dec 18 10 Jan 19 5773

5774 Present Units 3 & 4 to ABP 11 Jan 19 11 Jan 19 5774

5775 ABP prepare defects list 1w 11 Jan 19 17 Jan 19 5775

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5776 Desnag ABP defects 2w 18 Jan 19 31 Jan 19 5776

5777 Hand units 3 & 4 to ABP 01 Feb 19 01 Feb 19 5777

5778 Building 9A Snag and Handover to CITIC / ABP 9w 4d 13 Nov 18 04 Feb 19 5778

5779 Inspection and Snagging of Building 9A 2w 13 Nov 18 26 Nov 18 5779

5780 De-snagging Floors Building 9A 2w 20 Nov 18 03 Dec 18 5780

5781 Hand Over Building 9A to CITIC 10 Dec 18 10 Dec 18 5781

5782 CITIC prepare defects list 1w 10 Dec 18 14 Dec 18 5782

5783 Desnag CITIC Defects 2w 17 Dec 18 11 Jan 19 5783

5784 Present Building 9A to ABP 14 Jan 19 14 Jan 19 5784

5785 ABP prepare defects list 1w 14 Jan 19 18 Jan 19 5785

5786 Desnag ABP defects 2w 21 Jan 19 01 Feb 19 5786

5787 Hand Building 9A to ABP 04 Feb 19 04 Feb 19 5787

5788 Building 5B Snag and Handover to CITIC / ABP 10w 2d 10 Dec 18 06 Mar 19 5788

5789
5789 Units 1 & 2 9w 4d 10 Dec 18 01 Mar 19
5790 Inspection and Snagging of Units 1 & 2 2w 10 Dec 18 21 Dec 18 5790

5791 De-snagging Units 1 & 2 2w 17 Dec 18 11 Jan 19 5791

5792 Hand Over Units 1 & 2 to CITIC 18 Jan 19 18 Jan 19 5792

5793 CITIC prepare defects list 1w 18 Jan 19 24 Jan 19 5793

5794 Desnag CITIC Defects 2w 25 Jan 19 07 Feb 19 5794

5795 Present Units 1 & 2 to ABP 08 Feb 19 08 Feb 19 5795

5796 ABP prepare defects list 1w 08 Feb 19 14 Feb 19 5796

5797 Desnag ABP defects 2w 15 Feb 19 28 Feb 19 5797

5798 Hand units 1 & 2 to ABP 01 Mar 19 01 Mar 19 5798

5799 Units 3 & 4 9w 19 Dec 18 06 Mar 19 5799

5800 Inspection and Snagging of Units 3 & 4 2w 19 Dec 18 15 Jan 19 5800

5801 De-snagging Units 3 & 4 2w 09 Jan 19 22 Jan 19 5801

5802 Hand Over Units 3 & 4 to CITIC 23 Jan 19 23 Jan 19 5802

5803 CITIC prepare defects list 1w 23 Jan 19 29 Jan 19 5803

5804 Desnag CITIC Defects 2w 30 Jan 19 12 Feb 19 5804

5805 Present Units 3 & 4 to ABP 13 Feb 19 13 Feb 19 5805

5806 ABP prepare defects list 1w 13 Feb 19 19 Feb 19 5806

5807 Desnag ABP defects 2w 20 Feb 19 05 Mar 19 5807

5808 Hand units 3 & 4 to ABP 06 Mar 19 06 Mar 19 5808

5809 Building 5A Snag and Handover to CITIC / ABP 11w 4d 14 Nov 18 19 Feb 19 5809

5810
5810 Units 1 & 2 9w 4d 14 Nov 18 05 Feb 19
5811 Inspection and Snagging of Units 1 & 2 2w 14 Nov 18 27 Nov 18 5811

5812 De-snagging Units 1 & 2 2w 21 Nov 18 04 Dec 18 5812

5813 Hand Over Units 1 & 2 to CITIC 11 Dec 18 11 Dec 18 5813

5814 CITIC prepare defects list 1w 11 Dec 18 17 Dec 18 5814

5815 Desnag CITIC Defects 2w 18 Dec 18 14 Jan 19 5815

5816 Present Units 1 & 2 to ABP 15 Jan 19 15 Jan 19 5816

5817 ABP prepare defects list 1w 15 Jan 19 21 Jan 19 5817

5818 Desnag ABP defects 2w 22 Jan 19 04 Feb 19 5818

5819 Hand units 1 & 2 to ABP 05 Feb 19 05 Feb 19 5819

5820
5820 Units 3 & 4 9w 4d 21 Nov 18 12 Feb 19
5821 Inspection and Snagging of Units 3 & 4 2w 21 Nov 18 04 Dec 18 5821

5822 De-snagging Units 3 & 4 2w 28 Nov 18 11 Dec 18 5822

5823 Hand Over Units 3 & 4 to CITIC 18 Dec 18 18 Dec 18 5823

5824 CITIC prepare defects list 1w 18 Dec 18 07 Jan 19 5824

5825 Desnag CITIC Defects 2w 08 Jan 19 21 Jan 19 5825

5826 Present Units 3 & 4 to ABP 22 Jan 19 22 Jan 19 5826

5827 ABP prepare defects list 1w 22 Jan 19 28 Jan 19 5827

5828 Desnag ABP defects 2w 29 Jan 19 11 Feb 19 5828

5829 Hand units 3 & 4 to ABP 12 Feb 19 12 Feb 19 5829

5830
5830 Units 5 & 6 9w 4d 28 Nov 18 19 Feb 19
5831 Inspection and Snagging of Units 5 & 6 2w 28 Nov 18 11 Dec 18 5831

5832 De-snagging Units 5 & 6 2w 05 Dec 18 18 Dec 18 5832

5833 Hand Over Units 5 & 6 to CITIC 08 Jan 19 08 Jan 19 5833

5834 CITIC prepare defects list 1w 08 Jan 19 14 Jan 19 5834

5835 Desnag CITIC Defects 2w 15 Jan 19 28 Jan 19 5835

5836 Present Units 5 & 6 to ABP 29 Jan 19 29 Jan 19 5836

5837 ABP prepare defects list 1w 29 Jan 19 04 Feb 19 5837

5838 Desnag ABP defects 2w 05 Feb 19 18 Feb 19 5838

5839 Hand units 5 & 6 to ABP 19 Feb 19 19 Feb 19 5839

5840 Handover of External Works 6w 09 Jan 19 19 Feb 19 5840

5841 Handover of External Works 6w 09 Jan 19 19 Feb 19 5841

5842 Completion of The Works 06 Mar 19 06 Mar 19 5842

-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
Work Packages
MPX ABP/WTP Piling Pre-cast Cladding AKT Structural Design Hilson Moran MEP design Farrells Architectural Design Vital Energi UXO
Windows Hoarding Site Accommodation Canopies MEP Infrastructure/Groundworks Concrete Frame Architectural Metalwork Roofing & Waterproofing
Blockwork Lifts Logistics Repairs to Dock Wall Thames Water Sprinklers and Dry Risers Utilities Roof Louvres & Mansafe Dry Lining & Ceilings Hoist
Joinery and Doors SCreed Tiling Decorations Cubicles Flooring Raised Floors Soft Landscaping Hard Landscaping Commissioning
Baselines
RAD Phase 1 Revised Contract Programme Rev 06 161017

S-ar putea să vă placă și