Sunteți pe pagina 1din 10

Table of Contents

Chapter 1
Initiating Process................................................................................. 2
Answer Key 263
Explanations 290

Chapter 2
Planning Process............................................................................... 24
Answer Key 266
Explanations 312

Chapter 3
Executing Process............................................................................ 151
Answer Key 277
Explanations 427

Chapter 4
Monitoring and Controlling Process............................................. 191
Answer Key 281
Explanations 467

Chapter 5
Closing Process................................................................................ 233
Answer Key 285
Explanations 508

Chapter 6
Professional Responsibility............................................................. 248
Answer Key 287
Explanations 523
Project Management Professional Printables
Copyright 2006 by PrepLogic, Inc.
Product ID: 10652
Production Date: November 08, 2006
Total Questions: 548

All rights reserved. No part of this document shall be stored in a retrieval system
or transmitted by any means, electronic, mechanical, photocopying, recording, or
otherwise, without written permission from the publisher. No patent liability is
assumed with respect to the use of the information contained herein.

Warning and Disclaimer


Every effort has been made to make this document as complete and as accurate as
possible, but no warranty or fitness is implied. The publisher and authors assume
no responsibility for errors or omissions. The information provided is on an "as
is" basis. The authors and the publisher shall have neither liability nor
responsibility to any person or entity with respect to any loss or damages arising
from the information contained in this document.

Volume, Corporate, and Educational Sales


PrepLogic offers favorable discounts on all products when ordered in quantity.
For more information, please contact PrepLogic directly:

1-800-418-6789
solutions@preplogic.com
Initiating Process 2

Chapter 1
Initiating Process
1. Key features of a Project Management Office (PMO) include all of the following
EXCEPT:

Select the best answer.

A. An information system consisting of tools and techniques used to


gather, integrate and disseminate the outputs of project
management processes.
B. Coordination of overall project quality standards between the
project manager and any internal or external quality personnel or
standards organization.
C. Identification and development of project management
methodology, best practices, and standards.
D. A mentoring platform for project managers.
Find the Answer p. 263

2. Which of the following is a characteristic of most project life cycles?

Select the best answer.

A. The level of uncertainty and, hence, risk of failing to achieve the


objectives can increase during the later stages of the project.
B. Phases are generally sequential and are usually defined by some
form of technical information transfer or technical component
handoff.
C. Cost and staffing level are high at the beginning of the life cycle.
D. Stakeholders are provided with more opportunities later in the
project to refine the product as the delivery deadline approaches.
Find the Answer p. 263
Initiating Process 3

3. Development of the project charter is concerned with documenting all of the


following EXCEPT:

Select the best answer.

A. Providing a formal justification for beginning the project.


B. Providing an explanation of the business needs that the project
addresses.
C. Providing a process for how formal verification of the project
deliverables will be obtained.
D. Providing a description of the product or service the project will
deliver.
Find the Answer p. 263

4. Which of the following processes, when preceding the development of project


charter, provides the BEST tool for aiding project selection?

Select the best answer.

A. The completion of an intital WBS.


B. The completion of an order of magnitude cost estimate.
C. The completion of an influence diagram.
D. The completion of a formal needs assessment.
Find the Answer p. 263

5. Which of the following is an example of an organizational process asset?

Select the best answer.

A. A backward pass.
B. A matrix organization.
C. A network path.
D. A work breakdown structure template.
Find the Answer p. 263
Initiating Process 263

Answers: Chapter 1
1. A Review Question p. 2 Detailed Explanation p. 290

2. B Review Question p. 2 Detailed Explanation p. 290

3. C Review Question p. 3 Detailed Explanation p. 291

4. D Review Question p. 3 Detailed Explanation p. 291

5. D Review Question p. 3 Detailed Explanation p. 292

6. B Review Question p. 4 Detailed Explanation p. 292

7. D Review Question p. 4 Detailed Explanation p. 293

8. A Review Question p. 4 Detailed Explanation p. 293

9. D Review Question p. 5 Detailed Explanation p. 293

10. D Review Question p. 5 Detailed Explanation p. 294

11. B Review Question p. 6 Detailed Explanation p. 294

12. B Review Question p. 6 Detailed Explanation p. 295

13. D Review Question p. 7 Detailed Explanation p. 295

14. A Review Question p. 7 Detailed Explanation p. 296

15. C Review Question p. 8 Detailed Explanation p. 296

16. C Review Question p. 8 Detailed Explanation p. 297

17. B Review Question p. 9 Detailed Explanation p. 297

18. A Review Question p. 9 Detailed Explanation p. 298

19. A Review Question p. 10 Detailed Explanation p. 298

20. B Review Question p. 10 Detailed Explanation p. 298

21. D Review Question p. 10 Detailed Explanation p. 299

22. A Review Question p. 11 Detailed Explanation p. 299

23. C Review Question p. 11 Detailed Explanation p. 300


Initiating Process 290

Explanations: Chapter 1
1. Review Question p. 2
Answers: A
Explanation A. Correct. This is the PMBOK definition of a Project Management
Information System.
Explanation B. Incorrect. A PMO focuses on the coordinated planning and execution
of projects and subprojects that are tied to the parent organization's or client's overall
business objectives.
Explanation C. Incorrect. A specific PMO can have delegated authority to make
recommendations or terminate projects to keep the business objectives consistent.
Explanation D. Incorrect. A PMO can be involved in the selection, management, and
redeployment of dedicated project personnel.
More Information:
PMBOK - pg 17-18

PrepLogic Question: 10652-100

2. Review Question p. 2
Answers: B
Explanation A. Incorrect. The level of uncertainty is highest at the start of the project.
Explanation B. Correct. Linear or sequential steps are a foundation for nearly all
project life cycles.
Explanation C. Incorrect. Actually, cost and staffing levels are low at the start, peak
during the intermediate phases, and drop rapidly as the project draws to a conclusion.
Explanation D. Incorrect. The ability of the stakeholders to influence the final
characteristics of the project's product and the final cost of a project is highest at the
start and gets progressively lower as the project continues.
More Information:
PMBOK - pg 19-22

PrepLogic Question: 10652-101


Initiating Process 291

3. Review Question p. 3
Answers: C
Explanation A. Incorrect. First and foremost the Project Charter provides a formal
justification for the project.
Explanation B. Incorrect. The Project Charter is used to authorize the project.
Providing an explanation of the business needs that the project addresses helps
decision-makers assess how the project fits within an organization's strategy and
long-term goals.
Explanation C. Correct. Detailing the deliverable acceptance process is covered in the
Scope Management Plan and not in the Project Charter.
Explanation D. Incorrect. The Project Charter is used to authorize the project.
Providing a description of the product or service the project will deliver helps
decision-makers assess how a project fits within an organization's strategy and
long-term goals.
More Information:
PMBOK - pg81

PrepLogic Question: 10652-102

4. Review Question p. 3
Answers: D
Explanation A. Incorrect. A preliminary version of the Work Breakdown Structure may
be developed during the development of the Project Charter but not prior to it.
Explanation B. Incorrect. An order of magnitude cost estimate may be developed
during the development of the Project Charter but not prior to it.
Explanation C. Incorrect. Influence diagrams are used for the purpose of risk
identification. Although levels of risk implicit in projects may influence how an
organization views the project (tolerance for risk) and the organization's willingness to
take on the project (acceptance of risk), it is not a generally accepted project selection
method.
Explanation D. Correct. Many organizations require the completion of a formal needs
assessment before accepting a Project Charter to ensure that the project is aligned with
the organization's strategic objectives.
More Information:
PMBOK - pg81
Initiating Process 292

PrepLogic Question: 10652-103

5. Review Question p. 3
Answers: D
Explanation A. Incorrect. A backward pass is a project network diagram technique that
is used for the calculation of late finish dates and late start dates for schedule activities.
Explanation B. Incorrect. A matrix organization describes an organizational structure
in which the project manager shares responsibility with the functional managers for
allocating and applying resources to project activities.
Explanation C. Incorrect. A network path is used during the creation of a project
schedule networking diagram.
Explanation D. Correct. A Work Breakdown Structure Template is considered an
example of an organizational process asset. Organizational process assets provide
project teams with ready-made tools and other artifacts that aid in the planning,
execution, contol and closure of projects. They are generally derived from the collective
experience and expertise of the organization in carrying out projects.
More Information:
PMBOK - pg84

PrepLogic Question: 10652-104

6. Review Question p. 4
Answers: B
Explanation A. Incorrect. Professional and technical associations can be used for expert
judgement on technical details for the project.
Explanation B. Correct. Risk Assessment Templates are examples of organizational
process assets. They help to organize information about risks, but they do not provide
information and views about the nature of the risks themselves. This can only be
supplied by expert judgement.
Explanation C. Incorrect. Consultants can be used for expert judgement in determining
the impact of technical details for the project.
Explanation D. Incorrect. Stakeholders can be used for expert judgement in
determining the impact of technical or management details for the project.
More Information:

S-ar putea să vă placă și