2017 Outage Unit 1 EMJ Execution Plan

ID Task Name % Complete Duration Start Finish RO Qtr 4, 2017 Q


Oct Nov Dec
0 BLCP
BLCP Outage 2017 Unit 1 5% 86.07 days Sun 10/1/17 Tue 12/26/17
1 Shutdown
Shutdown 100% 13.83 days Sun 10/1/17 Sun 10/15/17
15 EMJ U
EMJ Unit 1 Execution Plan 2017 4% 72.23 days Sun 10/15/17 Tue 12/26/17
16 Operation Shut down
Operation Shut down 100% 2.88 days Sun 10/15/17 Wed 10/18/17
22 Maint
Maintenance Window 3% 72.07 days Sun 10/15/17 Tue 12/26/17
23 Water and steam s
Water and steam system inspection 7% 59.19 days Wed 10/18/17 Sat 12/16/17 LAB
43 Boiler
Boiler Overhaul 3% 72.07 days Sun 10/15/17 Tue 12/26/17 BL
44 Sun Oct 15 Mon Oct 16
Boiler water wall clean inside furnance 100% 14 hrs Sun 10/15/17 Mon 10/16/17 BL
45 Mon Oct 16 Mon Oct 16
Cutting slot (hole) and clearing accumulation ash 100% 6 hrs Mon 10/16/17 Mon 10/16/17
in penthouse for winch installation
46 Install scaffolding
Install scaffolding 45% 6.21 days Mon 10/16/17 Sun 10/22/17 ES
77 Sand Blasting for internal boiler tube
Sand Blasting for internal boiler tube 0% 7.08 days Sun 10/22/17 Sun 10/29/17 BL
95 Sun Oct 29 Sun Nov 5
Boiler internal inspection confirm the damage 0% 7 days Sun 10/29/17 Sun 11/5/17 BL
condtion after blasting
96 Boiler
Boiler pressure part inspection and repair 3% 72.07 days Sun 10/15/17 Tue 12/26/17 BL
97 1ry RH
1ry RH tube replacement 2% 72.07 days Sun 10/15/17 Tue 12/26/17 BL
98 Preparation Work
Preparation Work 100% 2.67 days Sun 10/15/17 Wed 10/18/17
99 Scaffolding Installation - Outside Inlet Header 100% 1 day Sun 10/15/17 Mon 10/16/17 ES Sun Oct 15 Mon Oct 16
100 Remove of Insulation and Lagging at inlet 100% 2 days Mon 10/16/17 Wed 10/18/17 ES Mon Oct 16 Wed Oct 18

header up to top cutting point


101 Remove skin casing and seal box at inlet HDR
Remove skin casing and seal box at inlet HDR80% 7 days Tue 10/17/17 Tue 10/24/17
102 Remove Skin Casing at Inlet Header
Remove Skin Casing at Inlet Header 85% 6 days Tue 10/17/17 Mon 10/23/17 BL
103 Right Side 100% 2 days Tue 10/17/17 Thu 10/19/17 Tue Oct 17 Thu Oct 19
104 Left Side 100% 2 days Tue 10/17/17 Fri 10/20/17 Tue Oct 17 Fri Oct 20
105 Front Side 70% 4 days Thu 10/19/17 Mon 10/23/17 Thu Oct 19 Mon Oct 23
106 Remove Seal box at Inlet Header
Remove Seal box at Inlet Header 67% 3 days Sat 10/21/17 Tue 10/24/17
107 Right Side 100% 1 day Sat 10/21/17 Sun 10/22/17 Sat Oct 21 Sun Oct 22
108 Left Side 100% 1 day Sun 10/22/17 Mon 10/23/17 Sun Oct 22 Mon Oct 23
109 Front Side 0% 1 day Mon 10/23/17 Tue 10/24/17 Mon Oct 23 Tue Oct 24
110 Remove of refractory for 1ry RH inlet header 7% 4 days Mon 10/23/17 Fri 10/27/17 ES
tube penetration part
111 Right Side 20% 3 days Mon 10/23/17 Thu 10/26/17 Mon Oct 23 Thu Oct 26
112 Left Side 0% 3 days Mon 10/23/17 Thu 10/26/17 Mon Oct 23 Thu Oct 26
113 Front Side 0% 3 days Tue 10/24/17 Fri 10/27/17 Tue Oct 24 Fri Oct 27
115 Setting of temporary Support for 1ry RH inlet header fixing *before tube cutting
Setting of temporary Support for 1ry RH inlet 67% 3 days Sun 10/22/17 Wed 10/25/17 BL
header fixing *before tube cutting
116 Right Side - 12 PCS 100% 1 day Sun 10/22/17 Mon 10/23/17 Sun Oct 22 Mon Oct 23
117 Left Side - 12 PCS 100% 1 day Sun 10/22/17 Mon 10/23/17 Sun Oct 22 Mon Oct 23
118 Front Side - 24 PCS 0% 1 day Tue 10/24/17 Wed 10/25/17 Tue Oct 24 Wed Oct 25
119 Remove stopper from top level - remaining on EL +47180
Remove stopper from top level - remaining 0% 17 days Mon 10/23/17 Thu 11/9/17 BL
on EL +47180
120 Right Side - 148 points 0% 15 days Mon 10/23/17 Tue 11/7/17 Mon Oct 23 Tue Nov 7
121 Left Side - 111 points 0% 15 days Wed 10/25/17 Thu 11/9/17 Wed Oct 25 Thu Nov 9

Task Rolled Up Baseline Group By Summary Manual Summary Rollup Baseline Milestone
Critical Rolled Up Baseline Milestone Inactive Task Manual Summary Baseline Summary

Project: BLCP Outage 2017 Unit 1 Critical Split Rolled Up Progress Inactive Milestone Start-only Progress
Date: Mon 10/23/17 Milestone Split Inactive Milestone Finish-only Deadline
Prepared: Paramee Kullanatpokin
Summary Baseline Split Inactive Summary External Tasks
Rolled Up Task External Tasks Manual Task External Milestone
Rolled Up Milestone Project Summary Duration-only Baseline

Page 1
2017 Outage Unit 1 EMJ Execution Plan
ID Task Name % Complete Duration Start Finish RO Qtr 4, 2017 Q
Oct Nov Dec
122 Front Side - 225 points 0% 15 days Wed 10/25/17 Thu 11/9/17 Wed Oct 25 Thu Nov 9
123 Temporary winch setting for 1ry RH tube lift
Temporary winch setting for 1ry RH tube lift 0% 7.54 days Mon 10/23/17 Mon 10/30/17 BL
124 Install temporary support at Roof Housing 0% 2 days Mon 10/23/17 Wed 10/25/17 Mon Oct 23 Wed Oct 25
125 Install temporary winch at Boiler Inside
Install temporary winch at Boiler Inside 0% 1 day Sun 10/29/17 Mon 10/30/17
126 Install temporary winch - Left side 0% 1 day Sun 10/29/17 Mon 10/30/17 Sun Oct 29 Mon Oct 30
127 Install temporary winch - Right Side 0% 1 day Sun 10/29/17 Mon 10/30/17 Sun Oct 29 Mon Oct 30
128 Install temporary winch - Front Side 0% 1 day Sun 10/29/17 Mon 10/30/17 Sun Oct 29 Mon Oct 30
129 RH Tube Cutting(1ry RH inlet header) 0% 10 days Wed 10/25/17 Sat 11/4/17 BL
130 Right Side - 145 Joints 0% 10 days Wed 10/25/17 Sat 11/4/17 Wed Oct 25 Sat Nov 4
131 Left Side - 145 Joints 0% 10 days Wed 10/25/17 Sat 11/4/17 Wed Oct 25 Sat Nov 4
132 Front Side - 297 Joints 0% 20 days Wed 10/25/17 Tue 11/14/17 Wed Oct 25 Tue Nov 14
RH Tube Beveling 1ry RH inlet header
133 RH Tube Beveling 1ry RH inlet header 0% 20 days Fri 10/27/17 Thu 11/16/17 BL
134 Right Side - 145 Joints 0% 10 days Fri 10/27/17 Mon 11/6/17 Fri Oct 27 Mon Nov 6
135 Left Side - 145 Joints 0% 10 days Fri 10/27/17 Mon 11/6/17 Fri Oct 27 Mon Nov 6
136 Front Side - 297 Joints 0% 20 days Fri 10/27/17 Thu 11/16/17 Fri Oct 27 Thu Nov 16
137 Sun Oct 29 Tue Nov 28
Cutting 1ry RH tube (Furnace inside - Bottom) 0% 30 days Sun 10/29/17 Tue 11/28/17
138 Cutting 1ry RH tube (Furnace inside - Top)
Cutting 1ry RH tube (Furnace inside - Top) 0% 15 days Mon 10/30/17 Tue 11/14/17
139 Right Side - 145 Joints 0% 10 days Mon 10/30/17 Thu 11/9/17 Mon Oct 30 Thu Nov 9
140 Left Side - 145 Joints 0% 10 days Mon 10/30/17 Thu 11/9/17 Mon Oct 30 Thu Nov 9
141 Front Side - 297 Joints 0% 15 days Mon 10/30/17 Tue 11/14/17 Mon Oct 30 Tue Nov 14
142 Remove stopper bottom side
Remove stopper bottom side 0% 15 days Mon 10/30/17 Tue 11/14/17 BL
143 Right Side - 37 PCS 0% 10 days Mon 10/30/17 Thu 11/9/17 Mon Oct 30 Thu Nov 9
144 Left Side - 37 PCS 0% 10 days Mon 10/30/17 Thu 11/9/17 Mon Oct 30 Thu Nov 9
145 Front Side - 75 PCS 0% 15 days Mon 10/30/17 Tue 11/14/17 Mon Oct 30 Tue Nov 14
146 Tube Remove to outside 0% 30 days Mon 10/30/17 Wed 11/29/17 BL Mon Oct 30 Wed Nov 29
147 Tube Beveling (Furnace inside)
Tube Beveling (Furnace inside) 0% 30 days Mon 10/30/17 Wed 11/29/17 BL
148 Right Side - 145 Joints 0% 30 days Mon 10/30/17 Wed 11/29/17 Mon Oct 30 Wed Nov 29
149 Left Side - 145 Joints 0% 30 days Mon 10/30/17 Wed 11/29/17 Mon Oct 30 Wed Nov 29
150 Front Side - 297 Joints 0% 30 days Mon 10/30/17 Wed 11/29/17 Mon Oct 30 Wed Nov 29
151 New 1ry RH tube Carry in Boiler 0% 30 days Mon 10/30/17 Wed 11/29/17 BL Mon Oct 30 Wed Nov 29
152 Fit up and welding 1ry RH
Fit up and welding 1ry RH Tube Front Side : 0% 37 days Sat 11/4/17 Mon 12/11/17 BL
594 Joints
153 Top Level (Inside) - 297 Joints 0% 37 days Sat 11/4/17 Mon 12/11/17 Sat Nov 4 Mon Dec 11
154 Bottom Level (Outside) - 297 Joints 0% 37 days Sat 11/4/17 Mon 12/11/17 Sat Nov 4 Mon Dec 11
155 Fit up and welding 1ry RH
Fit up and welding 1ry RH Tube Right Side : 0% 37 days Sat 11/4/17 Mon 12/11/17 BL
290 Joints
156 Top Level (Inside) - 145 Joints 0% 37 days Sat 11/4/17 Mon 12/11/17 Sat Nov 4 Mon Dec 11
157 Bottom Level (Outside) - 145 Joints 0% 37 days Sat 11/4/17 Mon 12/11/17 Sat Nov 4 Mon Dec 11
158 Fit up and welding 1ry RH
Fit up and welding 1ry RH Tube Left Side : 0% 37 days Sat 11/4/17 Mon 12/11/17 BL
290 Joints
159 Top Level (Inside) - 145 Joints 0% 37 days Sat 11/4/17 Mon 12/11/17 Sat Nov 4 Mon Dec 11
160 Bottom Level (Outside) - 145 Joints 0% 37 days Sat 11/4/17 Mon 12/11/17 Sat Nov 4 Mon Dec 11
161 Inspe
Inspection Nozzle 0% 26.4 days Thu 11/30/17 Tue 12/26/17

Task Rolled Up Baseline Group By Summary Manual Summary Rollup Baseline Milestone
Critical Rolled Up Baseline Milestone Inactive Task Manual Summary Baseline Summary

Project: BLCP Outage 2017 Unit 1 Critical Split Rolled Up Progress Inactive Milestone Start-only Progress
Date: Mon 10/23/17 Milestone Split Inactive Milestone Finish-only Deadline
Prepared: Paramee Kullanatpokin
Summary Baseline Split Inactive Summary External Tasks
Rolled Up Task External Tasks Manual Task External Milestone
Rolled Up Milestone Project Summary Duration-only Baseline

Page 2
2017 Outage Unit 1 EMJ Execution Plan
ID Task Name % Complete Duration Start Finish RO Qtr 4, 2017 Q
Oct Nov Dec
162 Inspection Hole (RH Inlet HDR) Cutting 0% 2 days Thu 11/30/17 Sat 12/2/17 BL Thu Nov 30 Sat Dec 2
163 HDR Inside Cleaning / Bore scope inspection 0% 1 day Sun 12/24/17 Mon 12/25/17 BL Sun Dec 24 Mon De
164 Fit up and welding for Inspection nozzle end 0% 1 day Mon 12/25/17 Tue 12/26/17 BL Mon Dec 25 Tue De

cap by PT Test.
165 Skin casing reins
Skin casing reinstallation (remainning for 0% 11 days Wed 12/6/17 Sun 12/17/17 BL
observation port- before hydrostatic test)
166 Right Side 0% 11 days Wed 12/6/17 Sun 12/17/17 Wed Dec 6 Sun Dec 17
167 Left Side 0% 11 days Wed 12/6/17 Sun 12/17/17 Wed Dec 6 Sun Dec 17
168 Front Side 0% 11 days Wed 12/6/17 Sun 12/17/17 Wed Dec 6 Sun Dec 17
169 Installation Refractory (remainning for 0% 16 days Fri 12/1/17 Sun 12/17/17 ES
observation port - before hydrostatic test)
170 Righ Side - 1 m3 (Approx.) 0% 4 days Fri 12/1/17 Tue 12/5/17 Fri Dec 1 Tue Dec 5
171 Left Side- 1 m3 (Approx.) 0% 4 days Fri 12/1/17 Tue 12/5/17 Fri Dec 1 Tue Dec 5
172 Front Side - 2 m3 (Approx.) 0% 6 days Fri 12/1/17 Thu 12/7/17 Fri Dec 1 Thu Dec 7
173 Mon Dec 18 Wed Dec 20
Skin casing reinstallation for observation port 0% 2 days Mon 12/18/17 Wed 12/20/17
174 Mon Dec 18 Wed Dec 20
Insulation& Lagging Restoration 0% 2 days Mon 12/18/17 Wed 12/20/17 ES
175 Wed Dec 20 Fri Dec 22
Scaffolding Dismantle 0% 2 days Wed 12/20/17 Fri 12/22/17 ES
176 1ry RH bypas
1ry RH bypass line pipe 8% 62.33 days Thu 10/19/17 Wed 12/20/17 BL
184 Stub tub
Stub tube replacement 19% 68.78 days Mon 10/16/17 Sun 12/24/17
193 Boiler Testing
Boiler Testing 0% 4.33 days Thu 12/14/17 Mon 12/18/17 BL
199 Mon Dec 18 Fri Dec 22
Remove scaffolding 0% 4 days Mon 12/18/17 Fri 12/22/17 BL
200 Operation Start Up
Operation Start Up Plant 0% 1.04 days Fri 12/15/17 Sat 12/16/17
210 Main
Main Turbine actual MOST test 0% 0.69 days Mon 12/25/17 Tue 12/26/17

Task Rolled Up Baseline Group By Summary Manual Summary Rollup Baseline Milestone
Critical Rolled Up Baseline Milestone Inactive Task Manual Summary Baseline Summary

Project: BLCP Outage 2017 Unit 1 Critical Split Rolled Up Progress Inactive Milestone Start-only Progress
Date: Mon 10/23/17 Milestone Split Inactive Milestone Finish-only Deadline
Prepared: Paramee Kullanatpokin
Summary Baseline Split Inactive Summary External Tasks
Rolled Up Task External Tasks Manual Task External Milestone
Rolled Up Milestone Project Summary Duration-only Baseline

Page 3