x-xxxx-xxxx Rev. 0
Page 1 of 2
Please ensure that the following design input data are available before
proceeding for design.
SR NO. TO BE
FURNISHED
LOADING/INFORMATION BY
i) EQUIPMENT LAYOUT +GAD'S +CIVIL FURNISHED/NOT PIPING
INFORMATION FURNISHED
INFORMATION DRAWINGS
(√) / (X)
a) Pipe Rack layout
b) Cross Sections and Location
c) Width and Span
d) Portal Spacing
e) Tier Elevations
f) Longitudinal beam Elevations
e) Requirement of intermediate beams
f) Equipment placed on rack
g) Monorails
h) Space allocation for Electrical and
Instrument trays/ducts
i) Transfer line size,schedule,insulation
thickness,location,elevation,location
and type of supports (rigid/ spring) and
location of cross guides.
j) Flare and O/H vapour line
sizes,schedule,insulation
thickness,location and elevation
k) Location and size of platforms for
equipments supported on pipe rack
l) Air fin cooler floor(if required to be in
RCC construction in place of steel
grating based on Piping Design basis.
m) Requirement of additional metal inserts
n) Size, schedule,insulation
thickness,location and elevation of
pipes above 30'' dia to be supported on
extended column/framework above top
tier.
o) Load category giving udl for each pipe
rack and tier.
p) The dia of largest pipe including
insulation thickness if it is more than
10m for calculating wind forces.
q) Size, schedule,insulation
thickness,location and elevation of
cooling tower lines if above 30'' dia.
r) Piping and platform arrangement at
battery limit.
ii) Electrical requirment of cable trees and Electrical
tiers,platforms ladders,stairs,etc.
iii) Instrumentation requirement of cable
ducts,platforms Instrum -
ladders,stairs,etc. -entation
iv) Capacity of monorails if any
Rotating
Eqpt.
GUIDE No.
x-xxxx-xxxx Rev. 0
Page 1 of 2
1.0 INTRODUCTION
1.0 This document presents the design for offsite pipe rack.
i) LOCATION =
NOS =
LOCATION =
GUIDE No.
x-xxxx-xxxx Rev. 0
Page 1 of 2
SEISMIC ZONE :
WIND(BASIC DESIGN WIND SPEED,TERRAIN
CATEGORY) :
Friction Coefficient
Concrete to Soil : 0.5
GUIDE No.
x-xxxx-xxxx Rev. 0
Page 1 of 2
Important Elevations
Sample Calculation
Dead load intensity = 1.2 kN/m2
( as applicable)
Sample Calculation
Electrical Cable Tray Load (say) per tier = 1.22 kN/m2
Dead Load= Electrical Cable Tray Load x No. Of Tiers = 1.225=x 4 4.9 kN/m2
UDL on Beams= Dead Load x Effective Span = 4.9 x 6 = 29.4 kN/m2
Pipe Operating Load is applied as UDL for pipes less than 12" dia
and an additional Point Load for pipes of dia 12" and above.
Calculation of Point Load :
EL Pipe DiaPipe Span Point
UDL Load
mm inch kg/m m (kN)
6500 26 533 6 23.81
12 147 6 5.17
28 575 6 25.70
12 178 6 6.99
20 351 6 14.85
Same as above.