1, Mahottari
Earth Work Calculation Sheet
S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earth work in excavation
For foundation in ordinary soil, U/S 2 7.45 1.50 1.75 39.11 m
U/S 1 4.25 4.00 1.75 29.75 m
D/S 1 8.90 3.00 1.75 46.73 m
For gabion foundation (launching) U/S 1 12.50 6.00 0.50 37.50 m
D/S 1 6.10 3.00 0.50 9.15 m
Total 162.24 162.24 m
2 Earthwork for backfilling (1/3 of
excavation) 54.08 54.08 m
3 PCC (1:3:6),
Base (with return), U/S 2 7.45 1.5 0.6 13.41 m
1 4.25 3.00 0.60 7.65 m
D/S (with return) 1 8.90 2.00 0.60 10.68 m
U/S Floor 1 3.00 2.73 0.40 3.28 m3 , B = (4.46+1)/2=2.73
1 3.25 1.00 0.50 1.63 m3 , H = (0.6+0.4)/2=0.5
Triangular portion 0.5 1.00 0.15 0.15 0.01 m
Crest 1 1.00 0.75 0.55 0.41 m
Glacis 1 3.00 1.00 0.50 1.50 m3 , H = (0.6+0.4)/2=0.5
D/S Floor 5 5.00 1.00 0.50 12.50 m3 H = (0.6+0.4)/2=0.5
U/S Cutoff 1 4.46 0.40 1.00 1.78 m
D/S Cutoff 1 1.00 0.40 1.00 0.40 m
Triangular portion 0.5 1.00 0.40 0.30 0.06 m
U/S Wall 2 11.70 0.85 2.10 41.77 m3 B = (0.4+1.3)/2=0.85
D/S Wall 2 8.90 0.55 1.40 13.71 m3 B = (0.3+0.8)/2=0.55
Step 1 0.95 0.30 0.30 0.09 m
1 0.95 0.30 0.60 0.17 m
1 0.95 0.30 0.90 0.26 m
SubTotal 109.30 108.01 m
Deduction wearing coat -1.29
Total 108.01
4 PCC for RCC (1:2:4)
Operating slab 1 2.60 1.60 0.20 0.83 m3 (1.2+2x.7=2.6)
Breast wall 1 1.00 0.15 0.50 0.08 m
wearing coat 1 8.60 1.00 0.15 1.29
Total 2.20 2.20 m
5 M/S bar @0.4% of RCC 2.63x0.4% 28.48 28.48 Kg
6 Formwork
Foundation, U/S 2 4.25 0.60 5.10 m2
U/S 4 7.45 0.60 17.88 m2
D/S 2 8.9 0.60 10.68 m2
U/S Cutoff 2 4.46 1.00 8.92 m2
D/S Cutoff 2 1.00 1.00 2.00 m2
Wall, U/S 2 11.7 1.5 35.10 m2
D/S 2 8.90 1.40 24.92 m2
Operating slab, bottom 1 1.00 1.20 1.20 m2
Side 4 1.20 0.70 3.36 m2
Total 109.16 109.16 m2
7 Steel gate (1.30 x0.7) 1 1.30 0.70 0.91 0.91 m2
8 Gabion work
U/S (3 x 1.5 x 0.5) 1 12.00 6.00 0.50 36.00 m
D/S 1 6.00 3.00 0.50 9.00 m
Total 45.00 45.00 m
Supplying & Weaving of gabion box
9 (3x1.5x0.5) 20 270.00 270.00 m2 20x13.5 =270
S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 a.Earth work in excavation in foundation
S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
7 Formwork
u/s cutoff 1 16.00 1.00 16.00 m2
S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earthwork in excav. for foundation
Canal portion, Total length 1 11.50 2.80 1.00 32.20 m
Return wall 8 1.00 1.40 1.00 11.20 m
Total 43.40 43.40 m
2 Backfill, 1/3 of excavtion 1 14.47 14.47 m
3 P.C.C. (1:2:4)
Canal portion wall m
Base 1 11.50 2.80 0.80 25.76 m
Superstructure 2 11.50 0.60 1.50 20.70 m
Return wall 8 1.00 1.40 0.40 4.48 m
Return wall 8 1.00 0.70 1.90 10.64 m
Parapet 2 1.80 0.30 0.40 0.43 m
Cutoff 4 1.00 0.30 0.40 0.48 m
Canal bed 1 13.80 1.00 0.20 2.76 m
Total 65.25 65.25 m
4 P.C.C. (1:2:4) for R.C.C.
Slab 1 5.00 1.80 0.20 1.80 1.80 m
5 Steel @ 1% of 1.8 m3 141.30 141.30 Kg
6 Formwork for RCC
Slab, Bottom 1 5.00 1.00 5.00 m2
Side 2 5.00 0.20 2.00 m2
Side 2 1.80 0.20 0.72 m2
Canal portion, wall
Outer face 2 11.50 2.30 52.90 m2
Side 2 2.80 0.80 4.48 m2
Innerface 2 11.50 1.50 34.50 m2
Return wall 16 1.00 2.30 36.80 m2
Side 16 1.40 0.40 8.96 m2
Side 16 0.70 1.90 21.28 m2
Total 166.64 166.64 m2
S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earthwork in excav. In foundation
Headwall 2 1.00 0.75 0.70 1.05 m3
Wing wall 4 3.00 0.75 0.70 6.30 m3
u/s cutoff + d/s cutoff 2 1.00 0.30 0.40 0.24 m3
Support wall for collar joint 1 1.00 0.50 0.70 0.35 m3
Total 7.94 23.82 m3
2 Backfill, 1/3 of excavation 2.65 m3
Earth filling on pipe 1 4.40 5.00 0.45 9.90 m3
Total 12.55 37.64
3 PCC (1:3:6)
Headwall 2 1.00 0.75 0.20 0.30 m3
Wing wall 4 3.00 0.75 0.20 1.80 m3
u/s cutoff + d/s cutoff 2 1.00 0.30 0.40 0.24 m3
Support wall for collar joint 1 1.00 0.50 0.20 0.10 m3
Superstructure
Headwall 2 1.00 0.53 2.00 2.10 m3 B=(0.75+0.3)/2 = 0.53
Wing wall 4 3.00 0.53 2.00 12.60 m3 B=(0.75+0.3)/2 = 0.53
Support wall for collar joint 1 1.00 0.50 1.15 0.58 m3
Concreting for pipe embeding 1 5.00 1.00 1.00 5.00
Total 22.72 68.15 m3
Deduction for hume pipe 3 0.21 m3
Qt after dedu 22.51 67.52 m3
4 RCC Hume pipe 40 cm dia. 2 2.50 5.00 15.00 rm
5 Formwork
Inner +outer face 4 8.00 1.75 56.00 m2
Side 4 0.53 1.75 3.68 m2 L= (0.75+0.3)/2 =0.53
Total 59.68 179.03 m2
S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earthwork in excavation 1 11.00 4.80 0.80 42.24 126.72 m3
2 Earthwork in backfill, 1/3 of excav 1 14.08 42.24 m3
3 PCC 1:2:4
Wall, base 1 4.30 2.80 0.80 9.63 m3
Return 4 1.00 0.90 0.80 2.88 m3
Return 2 1.15 0.90 0.80 1.66 m3
u/s& d/s cutoff 2 1.00 0.30 0.50 0.30 m3
Superstructure 1 4.30 0.60 1.30 3.35 m3 B = (0.4+0.8)/2 =0.6
Return 4 1.00 0.65 1.30 3.38 m3 B = (0.9+0.4)/2 =0.65
Return 2 1.15 0.65 1.30 1.94 m3
Profile wall 2 4.80 0.30 0.50 1.44 m3
Profile wall 4 1.60 0.95 1.30 7.90 B= (1.6+0.3)/2 = 0.95
Total 32.49 97.47 m3
4 Dry Stone pitching
Bed 1 6.20 1.00 0.30 1.86 m3
Side 2 6.20 1.85 0.30 6.88 m3
Total 8.74 26.23 m3
5 Formwork
Wall 2 4.30 0.80 6.88 m2
Wall 2 2.80 0.80 4.48 m2
Return 8 1.00 0.80 6.40 m2
Return 8 1.00 1.30 10.40 m2
Return 4 1.15 1.30 5.98 m2
Profile wall 2 4.80 0.50 4.80 m2
Side 4 0.90 1.30 4.68 m2
Wall, Outerface+Innerface 1 24.00 1.30 31.20 m2
Total 74.82 224.46 m2
S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earthwork in excavation 1 11.00 4.80 0.80 42.24 84.48 m3
2 Earthwork in backfilling, 1/3 of excav 1 14.08 28.16 m3
3 PCC (1:2:4)
Abutment wall, d/s 1 3.60 2.80 0.80 8.06 m3
Return 4 1.00 0.90 0.80 2.88 m3
Superstructure 2 3.60 0.60 1.30 5.62 m3
Return 4 1.00 0.60 1.30 3.12 m3
Profile wall 2 4.80 0.30 0.50 1.44 m3
Profile wall 4 1.60 0.95 1.30 7.90 m3
Cutoff 2 1.00 0.30 0.50 0.30 m3
Parapet 2 1.80 0.40 0.30 0.43 m3
Total 29.76 59.51 m3
4 Dry Stone pitching
Bed 1 6.40 1.00 0.30 1.92 m3
Side 2 6.40 1.85 0.30 7.10 m3
Total 9.02 18.05 m3
5 Formwork
Base 2 3.60 0.80 5.76 m2
Base 2 2.80 0.80 4.48 m2
Return 8 1.00 0.80 6.40 m2
Return 4 0.90 0.80 2.88 m2
Abutment wall, Outerface 1 11.60 1.30 15.08 m2
Innerface 1 8.40 1.30 10.92 m2
For RCC 1 4.40 1.00 4.40 m2
Side 2 4.40 0.30 2.64 m2
Side 2 1.80 0.30 1.08 m2
Total 53.64 107.28 m2
6 PCC (1:2:4) for RCC
Slab 1 4.40 1.80 0.30 2.38 4.75 m2
7 MS bar for RCC@1.25% 1 233.15 466.29 Kg
S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earth work in excavation in foundation
u/s cutoff 1 1.00 0.45 0.60 0.27 m 3
S.N. Description of work No. Length Breadth Height Quantity Total Qtty Remarks
1 Earth work in excavation
Bed 1 100 1.4 0.2 28 m3
Wall 2 100 0.5 1.2 120 m3
Total 148 148.00 m3
2 E/W in cutting in canal reshaping
WUA PART As per calculation sheet 6205.00 m3
2 E/W in backfilling, 1/3 of excav. 1 49.33 49.33 m3
3 P.C.C. for R.C.C. (1:2:4)
Bed 1 100 1.4 0.15 21 m3
Wall 2 100 1 0.1 20 m3
Total 41 41 m3
4 Formwork 2 100 1.15 230 230 m2
5 MS bar @ 0.5% of R.C.C. 1 1609.25 1609.25 Kg
Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs)
Conttr-. Conttr-. Conttr-. Conttr-. Conttr-. Conttr-
Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs)
Conttr-. Conttr-. Conttr-. Conttr-. Conttr-. Conttr-
Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs)
Amount (NRs)
Conttr-.
Amount (NRs)
Conttr-.
Amount (NRs)
Central Irrigation Development Division No. 1, Mahottari
Comparative Chart
Contract No. :-CIDD-1/AuP-1/MIP
Name of Project: Aurahi Irrigation Project, Mahendranagar, Dhanusha
Name of Work:- Side Intake, Overflow weir and Guide bund
Office Estimate Conttr-. Conttr-. Conttr-
S.N. Description of Work Unit Quantity Amount
Rate (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs)
(NRs)
1 Site clearance before and after construction all
complete L.S. 25000.00
2 Earth work excavation : Excavation for soft
clay & silty soils with initial lead & lift (Upto
10m lead & 1.5m lift.). m3 506.88 95.35 48331.01
3 Earth Filling for Embankment : Making bank
by all types of soils including breaking soil
lumps, hand compaction with sprinklng water
and simple dressing etc. all complete
m3 506.89 68.11 34524.28
4 Earth work : Excavation in foundation of
structures for required depth with initial lead &
lift (Upto 10m lead & 1.5m lift) m3 967.63 95.35 92263.52
5 Back filling work : Earth work for back
fillining in structures in 15cm thick layers and
hand compaction with all lead and lifts, all m3 622.54 34.05 21197.48
complete
6 Cement concrete works : Concreting (1:3:6
P.C.C. ) works in foundations, verticle faces,
walls (cement concrete), floors including
supply of materials all complete as per
m3 786.05 3972.07 3122245.62
specification
7 Cement concrete works : Concreting (1:2:4
R.C.C. ) works in verticle faces, walls (cement
concrete), slab including supply of materials
all complete as per specification
m3 53.78 4856.80 261198.70
Central Irrigation Development Division No. 1, Mahottari
Comparative Chart
Contract No. :-CIDD-1/AuP-1/MIP
Name of Project: Aurahi Irrigation Project, Mahendranagar, Dhanusha
Name of Work:- Side Intake, Overflow weir and Guide bund
Office Estimate Conttr-. Conttr-. Conttr-
S.N. Description of Work Unit Quantity Amount
Rate (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs)
(NRs)
8 Cement concrete works : Concreting (1:5:10
P.C.C. ) works for blinding including supply of
materials all complete as per specification m3 44.20 3129.04 138303.56
9 Steel gate : Supply, fitting and fixing of steel
slide gate (size 1.3m x 0.7m) structures for
side intake and H/R with rubber seal, painting,
& testing as per specification all complete
m2 1.82 30000.00 54600.00
10 Reinforcement Steel for R.C.C. works :
Supply of steel reinforcement, cutting,
bending, placing in position as shown in
drawing & binding by binding wire of
reinforcement steel bars for R.C.C. works
including supply of all required material all
complete as per specification Kg 58.72 59.78 3510.28
11 Boulder filling in Gabion Box : Boulder
supplying, placing the crate box in position
and filling the boulder in gabion box and
properly tightening the boxes etc. all complete
as per specification
m3 688.95 975.55 672105.17
12 Gabion Box : Supply of 10 S.W.G.wire and
weaving gabion box with double knotted
mesh size 10 cm x10 cm. all complete. m2 4106.10 154.15 632955.32
13 Form works : Making wooden forms including
selection of materials, measuring, cutting,
fixing, nailing as per specified drawings
including form's surface smoothing etc. all
complete m2 517.91 153.09 79286.84
Central Irrigation Development Division No. 1, Mahottari
Comparative Chart
Contract No. :-CIDD-1/AuP-1/MIP
Name of Project: Aurahi Irrigation Project, Mahendranagar, Dhanusha
Name of Work:- Side Intake, Overflow weir and Guide bund
Office Estimate Conttr-. Conttr-. Conttr-
S.N. Description of Work Unit Quantity Amount
Rate (NRs) Rate (NRs) Amount (NRs) Rate (NRs) Amount (NRs) Rate (NRs)
(NRs)
14 Rubber seal : Supplying, fitting and fixing of
Rubber seal and testing all complete as per rm 67.00 700.00 46900.00
15 specification
R.C.C. Hume Pipe : Supply of 60cm. Diameter
R.C.C. Hume pipe including laying, fitting,
fixing all complete rm 7.50 1493.50 11201.25
16 Dewatering : Dewatering during construction
as rquired job L.S. 30000.00
Sub-Total (NRs) 5273623.03
VAT @ 13% 685570.99
Total (NRs) 5959194.03
Above (+)& below (-) than Estimated Amount
Percentage above(+) & below(-)
Ranking from Lowest bidders
Conttr-.
Amount (NRs)
Development Division No. 1, Mahottari
omparative Chart
Conttr-.
Amount (NRs)
Development Division No. 1, Mahottari
omparative Chart
Conttr-.
Amount (NRs)
Central Irrigation Development Division No. 1, Mahottari
Bill Of Quantity
Contract No. :-CIDD-1/AuP-1/MIP
Name of Project: Aurahi Irrigation Project, Mahendranagar,Dhanusha
Name of Work:- Side Intake, Overflow weir and Guide bund
Package No.: 1
RATE
S.N. DETAILS OF WORK UNIT Quantity Amount (NRs)
(NRs)
Note: The calculated figures are considered upto 2 digits after decimal .