1.0 Objective:
BHEL has empanelled M/s Project and Development India Ltd. (PDIL) as third
party inspection agency on behalf of CQS to perform inspection of identified
purchased/bought out items (BOI). These guidelines are framed to ensure smooth
operation of inspection planning, carrying out stage /final inspection and reporting
for NTPC contracts.
2.0. Scope:
This covers processing of request for inspection, planning, coordination with
customer for joint inspection, conducting inspection and issuing final inspection
reports in respect of identified BOI/purchased ordered by various BHEL
manufacturing Units/Engineering Centres/Power Sector within India which
includes:
2.1. All Category-II (Cat-II) and Category-III (Cat-III) bought out items as per LOIs
2.2. Identified Category-I (Cat-I) bought out items as per annexure-I
3.0 SCOPE OF EXCLUSIONS:
3.1 Packages /BOIs ordered by BHEL PEM
3.2 Self manufactured items of BHEL manufacturing units and the raw materials,
inspected by manufacturing units which are further processed at BHEL
manufacturing units.
3.3 Already agreed third party inspection agency as per Quality Plan (items for which
TPI has been agreed specifically as agreed in the QP).
4.0 Definition:
PO -BHEL Purchase orders
Sub PO - Sub PO placed by BHELs main vendor on sub vendors
QP - NTPC approved Quality Plan for Cat-I & Cat-II items and
BHEL approved Quality Plan for other items
PM - PDIL Project Manager
Inspector - PDIL inspector
CHP -Customer Hold Point
MDCC -Material dispatch clearance certificate of NTPC
CQS -BHEL Corporate Quality Surveillance Group
Prepared by Reviewed by Approved by
5.0 Procedure:
5.1.6. On completion of inspection, PDIL shall issue final inspection report within 24
hours after completion of inspection enclosing all the relevant stage inspection
reports, final inspection/ test reports and verified document. The copy of final
report shall be sent to unit.
5.1.7. In the initial phase, the copy final inspect report with one copy of relevant
enclosures shall also be sent to concerned CQS Center.
5.2 For Joint Inspection with NTPC
5.2.1 PDIL will take up inspection of the item as per procedure given at 5.1.
5.2.2 In case of joint inspection with NTPC, a copy of inspection call shall be sent by
PDIL to concerned CQS center.
5.2.3 CQS center shall co-ordinate with NTPC to finalise schedule of inspection and
intimate PDIL.
5.2.4 PDIL shall carry out inspection alongwith NTPC representative as per QP
requirement.
5.2.5 PDIL representative is authorized to sign the inspection report and CHP etc. on
behalf of BHEL.
5.2.6 The PDIL representative shall coordinate with NTPC till completion of inspection
and issue of CHP/MDCC and enclose it with the final report.
5.2.7 Concerned CQS Centers shall arrange for resolution, in case of any problem.
5.3. For inspection by BHEL before NTPC inspection
5.3.1 PDIL will take up inspection of the item as per procedure given at 5.1.
5.3.2 PDIL will mention in the report that accepted and cleared for NTPC inspection.
The copy of report shall be given to the vendor for information.
The report shall be sent to BHEL/CQS/Unit QC. After review CQS/Units QC
shall submit the report to NTPC. The clarification if any shall be obtained from
PDIL by BHEL.
5.3.3 M/s PDIL shall ensure necessary coordination till completion of inspection and
issue of CHP/MDCC by NTPC.
5.3.4 M/s PDIL shall send the inspection report to Unit enclosing CHP/MDCC.
5.3.5 Concerned CQS Centers shall arrange for resolution, in case of any problem.
5.4. For inspection by BHEL and verification by NTPC
5.4.1 PDIL shall carry out inspection as per 5.1 above and mention accepted and
cleared for NTPC review. The final report shall be sent to CQS Centre/Unit QC.
5.4.2 CQS/Unit QC shall review the report and countersign it. If any clarification is
required from PDIL, the same shall be obtained by CQS/ Unit QC.
5.4.3 Depending upon jurisdiction of NTPC, CQS/Unit QC shall submit the report to
NTPC for review and obtain CHP/MDCC.
5.4.4 If CHP/MDCC is taken by CQS, it shall be sent to Unit by CQS along with the
countersigned report.
6.0. For activities covered under 5.2 and 5.3 above, parallel inspection call shall be
raised to NTPC-RIOs as per provision of NTPC contract including notice period
mentioned therein.
8.0. CQS will conduct audit/periodic audits to ensure compliance to the specification.
9.0. Feed backs/short comings as received from ultimate customer shall be intimated
to be PDIL for immediate corrective action. Preventive action (if any as decided
by BHEL NTPC shall also be communicated to PDIL for implementation.
13.0. Corporate Quality, BHEL shall conduct six- monthly review with PDIL/CQS
Centres/Unit Coordinators to review the operations.