Documente Academic
Documente Profesional
Documente Cultură
Environment
Introduction
Throughout the world, the deterioration and corrosion of concrete structures has put strain
onto governments due to their high repair costs. In the UK in 1995, 26 billion was spent on
infrastructure maintenance and repair, roughly 50% of the governments total spending that
year on the construction industry, which was a threefold increase since 1981. In Birmingham,
28 million was spent to build the Midlands link motorway in 1962 but between 1972 and
1989 repair cost totalled 45 million and it has been estimated that over the next 15 years
costs could reach up to 120 million. Structural repair costs have been increasing year-on-
year as concrete continues to deteriorate due to weather conditions and vibrational movement.
The ability to anticipate structural damage and ware offers governments an opportunity to
repair damage before the severity increases, reducing costs. Current testing methods are often
time consuming and costly. These also include indirect cost such as traffic management,
diversions and road closures which will have to occur during the inspection of structures. If
periodic monitoring of concrete was implemented, this would allow early detection of
structural failure and deterioration which would reduce costs and help to allow appropriate
repair to be carried out. Integrated monitoring systems in reinforced concrete will offer the
ability to collect data to help improve concrete in the future.
(a) 20
Resistivity (lohm-cm)
15
5mm
10mm The Resistivity/Time Response graphs
10
15mm shown represent the change in
20mm resistivity for each electrode depth
5 with time.
30mm
40mm
(a) : CEM I concrete mix
0 (b) : CEM III/A concrete mix
0 25 50 75 100 125 150 (c) : CEM II/B-V
Time (Days)
(b) 70
60
Resistivity (kohm-cm)
50 10mm
15mm
40
20mm
30 30mm
20 40mm
50mm
10
0 25 50 75 100 125 150
Time (Days)
(c)
85
Resistivity (kohm-cm)
75
65 5mm
55 10mm
15mm
45
20mm
35
30mm
25
40mm
15
0 25 50 75 100 125 150
Time (Days)
Mean Cover Temperature/Time Response
(b) 12
10
8
CEM I
6
CEM III/A
4
CEM II/B-V
2
0
0 50 100 150
Time (Days)
The above graph shows the mean cover temperature recorded for each concrete mix
against time. Although thermistors were not placed at every depth, it was assumed that
due to concretes high thermal conductivity, the temperature throughout each concrete mix
would be the same as the regardless of depth.
Arrhenius Plots
(a) 3.0
2.8
2.6
2.4
5mm
ln(Resistivity)
2.2 10mm
2.0 15mm
20mm
1.8
30mm
1.6
40mm
1.4 50mm
1.2
1.0
3.50 3.52 3.54 3.56 3.58 3.60 3.62 3.64
1000/T (K-1)
(b) 4.15
3.95
3.75
10mm
ln(Resistivity)
3.55
15mm
20mm
3.35
30mm
3.15 40mm
50mm
2.95
2.75
3.49 3.54 3.59 3.64
1000/T (K-1)
(c) 4.45
4.25
4.05
3.85 5mm
ln(Resistivity)
10mm
3.65
15mm
3.45 20mm
30mm
3.25
40mm
3.05
2.85
3.48 3.53 3.58 3.63
1000/T (K-1)
Calculation of Ea/Rg from Measurements
CEM I
3.0
2.8
2.6
2.4 5mm
ln(Resistivity)
2.2 10mm
2.0 15mm
1.8 20mm
1.6 30mm
1.4 40mm
1.2 50mm
1.0
3.50 3.52 3.54 3.56 3.58 3.60 3.62 3.64
1000/Tk
The graph above titled CEM I is a copy of the Arrhenius plot for CEM I with a trendline.
Note that most data points are omitted for clarity. The trendline for each electrode is a straight
line of slope Ea/Rg. After obtaining the gradient of each slope, and multiplying it by the gas
constant Rg, a known value, the activation energy is calculated for each electrode depth.
These values are shown in the table below. This value of Ea is then used to normalise the
measured resistivity values to 25C. These values are displayed subsequently.
5
Resistivity (kohm-cm)
5mm
4 10mm
3 15mm
20mm
2
30mm
1
40mm
0 50mm
0 25 50 75 100 125 150
Time (Days)
25
Resistivity (kohm-cm)
20 5mm
10mm
15
15mm
10 20mm
5 30mm
40mm
0
0 25 50 75 100 125 150
Time (Days)