Bu Seth Co. is launching new product to be manufactured in their factory. The company
identified 11 activities.
Immediate
Activity Predecessor Duration (hrs) Path Duration
A - 2 ABCDEHJK 36
B A 3 ABCDEHIK 39 MOST CRITICAL
C B 6 ABCFGHJK 30
D C 6 ABCFGHIK 33
E D 9
F C 4
G F 5
H E&G 7
I H 5
J H 2
K I&J 1
First Path First Path
ABCDEHJK ES Duration EF ABCDEHJK LF Duration LS
A 0 2 2 K 36 1 35
B 2 3 5 J 35 2 33
C 5 6 11 H 33 7 26
D 11 6 17 E 26 9 17
E 17 9 26 D 17 6 11
H 26 7 33 C 11 6 5
J 33 2 35 B 5 3 2
K 35 1 36 A 2 2 0
11 6 17 17 9 26 33 2 35
D E J
11 0 17 17 0 26 33 3 38
0 2 2 2 3 5 5 6 11 26 7 33 38 1 39
A B C H K
0 0 2 2 0 5 5 0 11 26 0 33 38 0 39
11 4 15 15 5 20 33 5 38
F G I
11 16 31 31 6 26 33 0 38
PROGRAM EVALUATION & REVIEW TECHNIQ
ACTIVITY O P ML Expected Time Variance
A 3 11 6 6.3333333333 1.777778
B 4 13 7 7.5 2.25
C 7 16 10 10.5 2.25
D 7 15 10 10.3333333333 1.777778
E 10 19 12 12.8333333333 2.25
F 5 14 6 7.1666666667 2.25
G 6 15 6 7.5 2.25
H 8 18 9 10.3333333333 2.777778
I 6 15 6 7.5 2.25
J 3 10 5 5.5 1.361111
K 2 9 3 3.8333333333 1.361111
Square root
CRITICAL PATH
Ma Sha Keith Co. is launching new product to be manufactured in their factory. The
company identified 11 activities.
Immediate Duration
Activity Path Duration
Predecessor (weeks)
A - 3 ABCDEHJK 42 MOST CRITICAL
B A 5 ABCDEHIK 37
C B 6 ABCFGHJK 33
D C 7 ABCFGHIK 35
E D 2
F C 1
G F 6
H E&G 8
I H 4
J H 9
K I&J 2
14 7 21 21 2
D E
14 0 21 21 0
0 3 3 3 5 8 8 6 14
A B C
0 0 3 3 0 8 8 0 14
14 1 15 15 6
F G
14 14 29 29 2
Duration LS
2 40
9 31
8 23
2 21
7 14
6 8
5 3
3 0
Duration LS
2 35
4 31
8 23
2 21
7 14
6 8
5 3
3 0
Duration LS
2 31
2 29
8 21
6 15
1 14
6 8
5 3
3 0
Duration LS
2 33
4 29
8 21
6 15
1 14
6 8
5 3
3 0
23 31 9 40
J
23 31 0 40
23 8 31 40 2 42
H K
23 0 31 40 0 42
21 31 4 35
I
23 36 5 40
PROGRAM EVALUATION & REVIEW TECHNIQUE (P
ACTIVITY O P ML Expected Time Variance
A 6 15 2 4.8333333333 2.25
B 7 18 7 8.8333333333 3.361111
C 8 14 10 10.3333333333 1
D 9 16 10 10.8333333333 1.361111
E 3 18 12 11.5 6.25
F 2 12 5 5.6666666667 2.777778
G 6 18 7 8.6666666667 4
H 9 14 8 9.1666666667 0.694444
I 5 16 6 7.5 3.361111
J 9 18 1 5.1666666667 2.25
K 2 10 2 3.3333333333 1.777778
Square root
CRITICAL
The Pooh Co. is launching new product to be manufactured in their factory. The company
identified 11 activities.
Immediate
Activity Predecessor Duration (mins) Path Duration
A - 10 ABCDEHJK 155
B A 15 ABCDEHIK 158 MOST CRITICAL
C B 22 ABCFGHJK 115
D C 34 ABCFGHIK 128
E D 25
F C 13
G F 16
H E&G 17
I H 15
J H 12
K I&J 20
47 34 81 81 25 106
D E
47 0 81 81 0 106
0 10 10 10 15 25 25 22 47 106 17
A B C H
0 0 10 10 0 25 25 0 47 106 0
47 13 60 60 16 76
F G
47 62 122 122 30 106
Duration LS
20 135
12 123
17 106
25 81
34 47
22 25
15 10
10 0
Duration LS
20 138
15 123
17 106
25 81
34 47
22 25
15 10
10 0
Duration LS
20 95
2 93
17 76
16 60
13 47
22 25
15 10
10 0
Duration LS
20 108
15 93
17 76
16 60
13 47
22 25
15 10
10 0
123 12 135
J
126 3 138
123 138 20 158
K
123 138 0 158
123 15 138
I
123 0 138
PROGRAM EVALUATION & REVIEW TECHNIQUE
ACTIVITY O P ML Expected Time Variance
A 3 12 3 4.5 2.25
B 5 25 5 8.3333333333 11.11111
C 14 16 4 7.6666666667 0.111111
D 25 35 9 16 2.777778
E 6 14 7 8 1.777778
F 4 23 2 5.8333333333 10.02778
G 8 18 5 7.6666666667 2.777778
H 9 32 8 12.1666666667 14.69444
I 15 20 6 9.8333333333 0.694444
J 13 22 1 6.5 2.25
K 2 10 2 3.3333333333 1.777778
Square root
CRITICAL
The Pooh Co. is launching new product to be manufactured in their factory. The company
identified 11 activities.
Immediate
Activity Predecessor Duration (hrs.) Path Duration
A - 6 ABCDEHJK 42
B A 9 ABCDEHIK 45 MOST CRITICAL
C B 4 ABCFGHJK 41
D C 6 ABCFGHIK 44
E D 2
F C 6
G F 1
H E&G 5
I H 5
J H 2
K I&J 8
19 6 25 25 2 27
D E
19 0 25 25 0 27
0 6 6 6 9 15 15 4 19 27 5
A B C H
0 0 6 6 0 15 15 0 19 27 0
19 6 25 25 1 26
F G
19 3 28 28 1 27
Duration LS
8 34
2 32
5 27
2 25
6 19
4 15
9 6
6 0
Duration LS
8 37
5 32
5 27
2 25
6 19
4 15
9 6
6 0
Duration LS
8 33
2 31
5 26
1 25
6 19
4 15
9 6
6 0
Duration LS
8 36
5 31
5 26
1 25
6 19
4 15
9 6
6 0
32 2 34
J
35 3 37
32 37 8 45
K
32 37 0 45
32 5 37
I
32 0 37
PROGRAM EVALUATION & REVIEW TECHNIQ
ACTIVITY O P ML Expected Time Variance
A 3 12 3 4.5 2.25
B 5 25 5 8.3333333333 11.11111
C 14 16 4 7.6666666667 0.111111
D 25 35 9 16 2.777778
E 6 14 7 8 1.777778
F 4 23 2 5.8333333333 10.02778
G 8 18 5 7.6666666667 2.777778
H 9 32 8 12.1666666667 14.69444
I 15 20 6 9.8333333333 0.694444
J 13 22 1 6.5 2.25
K 2 10 2 3.3333333333 1.777778
Square root
CRITICAL
The Pooh Co. is launching new product to be manufactured in their factory. The company
identified 11 activities.
Immediate
Activity Predecessor Duration (hrs.) Path Duration
A - 3 ABCDEHJK 38
B A 5 ABCDEHIK 41 MOST CRITICAL
C B 6 ABCFGHJK 34
D C 9 ABCFGHIK 40
E D 1
F C 5
G F 4
H E&G 6
I H 8
J H 5
K I&J 3
14 9 23 23 1 24
D E
14 0 23 23 0 24
0 3 3 3 5 8 8 6 14 24 6
A B C H
0 0 3 3 0 8 8 0 14 24 0
14 5 19 19 4 23
F G
14 9 28 28 1 24
Duration LS
3 35
5 30
6 24
1 23
9 14
6 8
5 3
3 0
Duration LS
3 38
8 30
6 24
1 23
9 14
6 8
5 3
3 0
Duration LS
3 31
2 29
6 23
4 19
5 14
6 8
5 3
3 0
Duration LS
3 37
8 29
6 23
4 19
5 14
6 8
5 3
3 0
30 5 35
J
33 3 38
30 38 3 41
K
30 38 0 41
30 8 38
I
30 0 38
PROGRAM EVALUATION & REVIEW TECHNIQ
ACTIVITY O P ML Expected Time Variance
A 9 2 1.8333333333 1.361111
B 8 3 4 4.5 0.694444
C 4 5 8 6.8333333333 0.027778
D 5 6 6 5.8333333333 0.027778
E 1 4 31 21.5 0.25
F 2 8 2 3 1
G 3 1 4 3.3333333333 0.111111
H 4 5 3 3.5 0.027778
I 10 6 4 5.3333333333 0.444444
J 2 3 1 1.5 0.027778
K 3 2 2 2.1666666667 0.027778
Square root
CRITICAL PATH
Ma Sha Keith Co. is launching new product to be manufactured in their factory. The
company identified 11 activities.
Immediate Duration
Activity Path Duration
Predecessor (weeks)
A - 5 ABCDEHJK 50 MOST CRITICAL
B A 5 ABCDEHIK 49
C B 7 ABCFGHJK 45
D C 9 ABCFGHIK 48
E D 4
F C 7
G F 5
H E&G 8
I H 5
J H 6
K I&J 6
17 9 26 26 4
D E
17 0 26 26 0
0 5 5 5 5 10 10 7 17
A B C
0 0 5 5 0 10 10 0 17
17 7 24 24 5
F G
17 11 35 35 1
Duration LS
6 44
6 38
8 30
4 26
9 17
7 10
5 5
5 0
Duration LS
6 43
5 38
8 30
4 26
9 17
7 10
5 5
5 0
Duration LS
6 39
2 37
8 29
5 24
7 17
7 10
5 5
5 0
Duration LS
6 42
5 37
8 29
5 24
7 17
7 10
5 5
5 0
30 38 6 44
J
30 38 0 44
30 8 38 44 6 50
H K
30 0 38 44 0 50
29 38 5 43
I
30 39 1 44
PROGRAM EVALUATION & REVIEW TECHNIQ
ACTIVITY O P ML Expected Time Variance
A 6 15 2 4.8333333333 2.25
B 7 18 7 8.8333333333 3.361111
C 8 14 10 10.3333333333 1
D 9 16 10 10.8333333333 1.361111
E 3 18 12 11.5 6.25
F 2 12 5 5.6666666667 2.777778
G 6 18 7 8.6666666667 4
H 9 14 8 9.1666666667 0.694444
I 5 16 6 7.5 3.361111
J 9 18 1 5.1666666667 2.25
K 2 10 2 3.3333333333 1.777778
Square root
CRITICAL PATH
Ma Sha Keith Co. is launching new product to be manufactured in their factory. The
company identified 11 activities.
Immediate Duration
Activity Path Duration
Predecessor (weeks)
A - 4 ABCDEHJK 42 MOST CRITICAL
B A 6 ABCDEHIK 39
C B 8 ABCFGHJK 38
D C 3 ABCFGHIK 37
E D 6
F C 2
G F 5
H E&G 8
I H 1
J H 4
K I&J 3
18 3 21 21 6
D E
18 0 21 21 0
0 4 4 4 6 10 10 8 18
A B C
0 0 4 4 0 10 10 0 18
18 2 20 20 5
F G
18 12 32 32 2
Duration LS
3 39
4 35
8 27
6 21
3 18
8 10
6 4
4 0
Duration LS
3 36
1 35
8 27
6 21
3 18
8 10
6 4
4 0
Duration LS
3 35
2 33
8 25
5 20
2 18
8 10
6 4
4 0
Duration LS
3 34
1 33
8 25
5 20
2 18
8 10
6 4
4 0
27 35 4 39
J
27 35 0 39
27 8 35 39 3 42
H K
27 0 35 39 0 42
25 35 1 36
I
27 38 3 39
PROGRAM EVALUATION & REVIEW TECHN
ACTIVITY O P ML Expected Time Variance
A 6 15 2 4.8333333333 2.25
B 7 18 7 8.8333333333 3.361111
C 8 14 10 10.3333333333 1
D 9 16 10 10.8333333333 1.361111
E 3 18 12 11.5 6.25
F 2 12 5 5.6666666667 2.777778
G 6 18 7 8.6666666667 4
H 9 14 8 9.1666666667 0.694444
I 5 16 6 7.5 3.361111
J 9 18 1 5.1666666667 2.25
K 2 10 2 3.3333333333 1.777778
Square root