Id Nombre de tarea Duracin Comienzo Costo Fin M6 M7 M8

S27 S28 S29 S30 S31 S32 S33 S34 S35 S36
1 OBRA: CERCO PERIMETRICO DE LA POSTA 52.81 das lun 06/11/17 S/ lun 06/11 S/ 266,056.34
MEDICA DE CALLEBAMBA 266,056.34 01/01/18
2 OBRAS PROVISIONALES 6 das lun 06/11/17 S/ 3,987.57 sb 06/11 S/ 3,987.57
11/11/17
3 CARTEL DE OBRA 1 da lun 06/11/17 S/ 1,271.00 mar 06/11 S/ 1,271.00
07/11/17
4 ALMACEN, OFICINA, CASETA 5 das mar 07/11/17 S/ 2,716.57 sb 07/11 S/ 2,716.57
P/GUARDIANIA 11/11/17
5 02 TRABAJOS PRELIMINARES 6 das lun 06/11/17 S/ 599.90 sb 06/11 S/ 599.90
11/11/17
6 LIMPIEZA DE TERRENO MANUAL 2 das lun 06/11/17 S/ 307.99 mi 06/11 S/ 307.99
08/11/17
7 TRAZO, NIVELACION Y REPLANTEO 4 das mi 08/11/17 S/ 291.91 sb 08/11 S/ 291.91
11/11/17
8 03 MOVIMIENTO DE TIERRA 18 das lun 06/11/17 S/ 10,271.51 vie 06/11 S/ 10,271.51
24/11/17
9 EXCAVACION PARA ZAPATA HASTA 1.00 6 das lun 06/11/17 S/ 159.33 sb 06/11 S/ 159.33
M. DE PROFUNDIDAD 11/11/17
10 EXCAVACION PARA CIMIENTO HASTA 6 das sb 11/11/17 S/ 6,960.12 sb 11/11 S/ 6,960.12
1.00 M. DE PROF. EN TERRENO 18/11/17
NORMAL
11 RELLENO CON MATERIAL PROPIO 4 das sb 18/11/17 S/ 536.16 mi 18/11 S/ 536.16
22/11/17
12 ELIMINACION DE MATERIAL EXCEDENTE 2 das mi 22/11/17 S/ 2,615.90 vie 24/11/17 22/11 S/ 2,615.90

13 04 CONCRETO SIMPLE 30 das lun 20/11/17 S/ 39,755.67 jue 21/12/17 20/11 S/ 39,755.67

14 SOLADO DE CONCRETO 1:12, E=0.20 M. 3 das lun 20/11/17 S/ 100.04 mi 20/11 S/ 100.04
PARA ZAPATAS 22/11/17
15 CONCRETO 1:10 + 30%P.G. PARA 9 das jue 23/11/17 S/ 22,817.29 sb 23/11 S/ 22,817.29
CIMIENTO CORRIDO 02/12/17
16 CONCRETO 1:8 + 25%P.M. PARA 8 das sb 02/12/17 S/ 5,079.54 lun 11/12/17 02/12 S/ 5,079.54
SOBRECIMIENTOS
17 ENCOFRADO Y DESENCOF. 10 das sb 02/12/17 S/ 11,758.80 mi 02/12 S/ 11,758.80
SOBRECIMIENTO H=30 CM. 13/12/17
18 05 OBRAS DE CONCRETO ARMADO 30 das lun 20/11/17 S/ 75,164.66 jue
21/12/17
19 ACERO PARA ZAPATAS GRADO 60 2 das lun 20/11/17 S/ 166.77 mi 20/11 S/ 166.77
22/11/17
20 CONCRETO EN ZAPATAS F'C=210 2 das mi 22/11/17 S/ 527.44 jue 23/11/17 22/11 S/ 527.44
KG/CM2
21 ACERO F'Y=4200 KG/CM2 EN 3 das vie 24/11/17 S/ 10,989.11 lun 27/11/17 24/11 S/ 10,989.11
COLUMNAS
22 CONCRETO EN COLUMNAS F'C=210 7 das mar 28/11/17 S/ 7,155.95 mar 28/11 S/ 7,155.95
KG/CM2 05/12/17
23 ENCOFRADO Y DESENCOFRADO 8 das mar 28/11/17 S/ 18,361.70 mi 28/11 S/ 18,361.70
NORMAL EN COLUMNAS 06/12/17
24 ACERO F'Y=4200 KG/CM2 EN VIGAS 8 das mi 06/12/17 S/ 4,070.55 jue 14/12/17 06/12 S/ 4,070.55

25 CONCRETO EN VIGAS F'C=210 KG/CM2 7 das jue 14/12/17 S/ 10,380.59 vie 22/12/17 14/12 S/ 10,380.59

26 ENCOFRADO Y DESENCOFRADO 7 das jue 14/12/17 S/ 23,512.55 vie 22/12/17 14/12 S/ 23,512.55
NORMAL EN VIGAS
27 06 MUROS Y TABIQUES 24 das lun 27/11/17 S/ 50,516.40 vie 22/12/17 27/11 S/ 50,516.40

28 MURO SOGA LADRILLO KK CARAVISTA 24 das mar 28/11/17 S/ 50,516.40 sb 28/11 S/ 50,516.40
23/12/17
29 07 REVOQUES Y ENLUCIDOS DE 12 das lun 11/12/17 S/ 51,081.05 sb 11/12 S/ 51,081.05
MOLDURA 23/12/17
30 TARRAJEO DE SUPERF. COLUMNAS 4 das lun 11/12/17 S/ 5,584.40 jue 14/12/17 11/12 S/ 5,584.40

31 TARRAJEO DE SUPERFICIE DE VIGAS 4 das jue 14/12/17 S/ 7,690.80 mar 19/12/17 14/12 S/ 7,690.80

32 ZOCALO DE CEMENTO MEZCLA 2 das mar 19/12/17 S/ 8,396.49 jue 21/12/17 19/12 S/ 8,396.49
CEMENTO-ARENA
33 VESTIDURA DE DERRAMES EN VOLADO 2 das jue 21/12/17 S/ 29,409.36 sb 21/12 S/ 29,409.36
DE VIGA DE CORONACION 23/12/17
34 08 PINTURA 12 das lun 18/12/17 S/ 9,007.56 sb 30/12/17 18/12 S/ 9,007.56

35 PINTURA OLEO MATE EN COLUMNAS 4 das lun 18/12/17 S/ 1,507.29 jue 21/12/17 18/12 S/ 1,507.29

36 PINTURA OLEO MATE EN VIGAS 4 das mar 19/12/17 S/ 4,372.97 sb 23/12/17 19/12 S/ 4,372.97

37 PINTURA OLEO MATE EN ZOCALO 4 das jue 21/12/17 S/ 3,127.30 lun 25/12/17 21/12 S/ 3,127.30

38 09 CARPINTERIA METALICA 6 das lun 25/12/17 S/ 7,672.02 sb 30/12/17 25/12 S/ 7,672.02

39 PORTON METALICO DE DOS HOJAS 4 das mar 26/12/17 S/ 5,901.55 vie 29/12/17 26/12 S/ 5,901.55

40 PUERTA METALICA 2 das vie 29/12/17 S/ 1,770.47 lun 01/01/18 29/12 S/ 1,770.47

41 10 TRANSPORTE DE MATERIALES 18 das lun 13/11/17 S/ 18,000.00 vie 01/12/17 13/11 S/ 18,000.00

42 FLETE TERRESTRE 18 das lun 13/11/17 S/ 18,000.00 vie 01/12/17 13/11 S/ 18,000.00

Tarea Resumen Hito inactivo solo duracin solo el comienzo Hito externo Divisin crtica
Proyecto: cronograma finLconpar
Fecha: sb 25/11/17 Divisin Resumen del proyecto Resumen inactivo Informe de resumen manual solo fin Fecha lmite Progreso