Jakarta Mass Rapid Transit Project CP101&CP102 Inspection and Test Plan
Approval:
Jakarta Mass Rapid Transit Project CP101&CP102 Inspection and Test Plan
Contents
2. Checklist
Pre-cast Drainage Checklist
Concrete pour Checklist revD
Concrete Control on Site
Rigid Pavement Pour Checklist
Inspection of CBR Field
Field Density
TWJO-ITP-RDW-0020-revA Contents
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project
Description of Activity: Describes the inspection and test requirements for WMS No: ITP NO: TWJO-ITP-RDW-0020 revA
reinstatement at lebak bulus station.
1 Documentation
Before
Civil Engineer/
commencement of Approved
1.1 Good for construction drawings Approved drawings Construction NA NA P NA A
Temporary Road drawings
Manager
Widening activity
Before
Civil Engineer/
commencement of
1.2 Established Work Method Statement NA NA Construction NA NA P NA A
Temporary Road
Manager
Widening activity
2 Material Testing
Concrete
Once Before strength shall be QC Engineer Compressive
Establishing the concrete trial mix for
2.1 commencement of OCS Clause 5.3.1 equal to or more with QC strength NA P I A
concrete pavement
concreting than the design Manager reports
strength
Concrete
Once Before
strength shall be QC Engineer Compressive
Verifying the concrete compressive commencement of
2.2 NA equal to or more with QC strength P R I A
strength for pre-cast Drainage temporary widening
than the design Manager reports
activity
strength
3 Drainage Installation
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project
Description of Activity: Describes the inspection and test requirements for WMS No: ITP NO: TWJO-ITP-RDW-0020 revA
reinstatement at lebak bulus station.
W/I (W
Once Before Civil Engineer as per
Staking out level & position of As per Method As per Method Survey
3.1 commencement of and Survey NA P mention A
precast drainage Statement statement records
drainage installation Team in
checklist)
W/I (W
TWJO-ITP- as per
After Lean Concrete As per Method As per Method Civil Engineer or
3.2 Installation of Precast Drainage RDW-0018- NA P mention A
finished Statement statement his delegate
CHK-001 in
checklist)
Description of Activity: Describes the inspection and test requirements for WMS No: ITP NO: TWJO-ITP-RDW-0020 revA
reinstatement at lebak bulus station.
CBR of
Civil Engineer
Compaction Base course and testing Prior to lean concrete OCS clause 3.2.3 compacted soil TWJO-QC-
4.2 with QC NA P W A
(Testing CBR Field) work OCS clause 3.2.4 shall not be less 0001
Engineer
than 6%
5 Rigid Pavement
Prior to
Level and alignment check for As per MS for As per MS for Civil Engineer Survey
5.2 commencement of NA P I A
installed curbs Road Widening Road Widening with Surveyor records
concreting
TWJO-ITP-
Formwork material and preparation Prior to pouring
5.3 OCS clause 5.10 NA Civil engineer RDW-0016- NA P W A
checking concrete
CHK-001
TWJO-ITP-
Tie bar/dowel bar dimension and Prior to pouring
5.4 OCS clause 13.4 NA Civil engineer RDW-0016- NA P W A
position checking concrete
CHK-001
TWJO-ITP-
As per approved
5.5 Checking for thickness of concrete for every casting OCS clause 5.15.1 Civil Engineer RDW-0016- NA P W A
drawing
CHK-001
TOKYU-WIKA JOINT OPERATION
Surface Section CP101 & CP102
Construction of Jakarta Mass Rapid Transit Project
Description of Activity: Describes the inspection and test requirements for WMS No: ITP NO: TWJO-ITP-RDW-0020 revA
reinstatement at lebak bulus station.
TWJO-ITP-
Checking of curing and concrete
5.6 After every casting OCS clause 5.15.1 NA Civil Engineer RDW-0016- NA P I A
protection
CHK-001
OCS clause
5.7 Formwork removal After every casting OCS clause 5.15.3 Civil engineer NA NA P I A
5.15.1
6 Concrete Testing
Legends P: Perform R: Review I: For Information only H: Hold point W: Witness point NA: Not Applicable RW: Random Witness
Prepared by: Approved by:
Name: Name:
Signature: Signature:
All approved ITPs and related records shall be stored on TWJO server under Quality Assurance folder with a hard copy in office file.