Project Execution Plan for High Rise Building

Details how the construction will be executed, monitored and controlled.


YouTube Link https://youtu.be/_gikBOisPH8

Brief Description

The purpose of this presentation is to give an understanding of the Methods,

David H Moloney
Plant and Sequence to construct a high-rise building.

17th July 2016


This presentation can be used to engage Stakeholders and to get the Site Teams
commitment to the programme. Also can be used for Induction Training and as a
way to capture and share knowledge. Can be use to demonstrate entitlement
for delays and additional payment.

Project Execution Plan (PEP) details how a project will be executed, monitored
and controlled. High in Educational Value and easily understood. Recommended
for Continuing Professional Development (CPD)

This Presentation is innovative and has many beneficial uses.


Table of Contents
Floor Construction
Observation Deck on Floor 124
Floor Construction Cycle Time
General Items
Floor Construction Cycle time
Formwork types
Columns - Crane handled units
Core Walls - self climbing floor to floor
Slabs Formwork & Falsework Table forms Crane handled

Cycle Time
7 working days cycle per floor

Formwork Quantities
Column formwork = set (50%)
Core wall formwork = 1 set (100%)
Slab formwork = 2 sets (200%) Table forms

Programme

Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7


Columns Rebar, Shutter Rebar, Shutter & Strip shutters
& Pour 50% Pour 50%
Walls Pour walls Climb up Fix Rebar Fix shutters

Floor Strike & Move Slab Slab Slab Slab Pour slab
Forms Formwork Formwork Formwork Formwork 100%
Rebar MEP Rebar MEP Rebar MEP Rebar MEP
General Items
Floor Construction Overview

David H Moloney
Floor Construction Formwork Types
General Items
Shuttering to Columns

Brief Description

Column formwork can be moved with


only one crane lift complete with push-
pull props and concreting platform with
guard rails and ladder alternatively
moved by hand using transportation
wheels.
QUATTRO system by Peri
General Items
Shuttering Columns

David H Moloney
General Items
Shuttering to Core ( Lifts & Stairs)

Brief Description

Automatic climbing formwork system


lifts itself upwards on rails bolted to
the walls using hydraulic jacks

Doka Xclimb 60
General Items
Shuttering to Core ( Lifts & Stairs)

David H Moloney
Shuttering Self Climbing for Core
Concrete

Cycle Time 4 Days


General Items
Shuttering to Floor Slabs Table forms

Brief Description

Table forms are preassembled formwork


and false units and are moved
horizontally on wheels or a trolley and
vertically from floor to floor by crane or
by a lift fixed to the outside of the
building
General Items
Shuttering to Floor Slabs Table forms

Leapfrog
table forms
General Items
Shuttering Floor Slabs

David H Moloney
General Items
Shuttering Stairs
General Items
Shuttering Stairs

David H Moloney
Dubai High Rise Buildings

David H Moloney
Main Equipment
General Items
Climbing Tower Cranes

Brief Description

A climbing tower crane lifts itself up using a climbing


attachment with hydraulic jacks that surrounds the mast.
The climbing attachment lifts itself up off the erected mast
and inserts a new mast section.
Climbing Tower Cranes
Miscellaneous
Climbing Tower Cranes Tie-in Assembly
Miscellaneous
General Items
Concrete Pump Self Climbing

Brief Description

The concrete is pumped by a diesel powered, static


concrete pump, through a fixed 125 mm pipeline, to
the folding placing boom. The boom is mounted on
a steel column of up to 20 metres high. The column
is supported by a cross base or a system of floor
frames set into the concrete floors.
With floor frames , the whole column / boom
assembly can climb with the building as the work
progresses.
For placing concrete pumping is faster than using a
crane and skip and is less likely to be adversely
affected by high winds.
Concrete Pump
Miscellaneous
General Items
Protection Screen - Self climbing

Brief Description

Protection screens enclose the top floors of a high


rise enabling construction work to be carry out in
great safety, and protected from the weather.

The screen will contain any debris and tools that


would otherwise fall to the surface.

The Protection screen can be moved upwards


hydraulically or using a tower crane.
General Items
Ensuring Verticality

Brief Description

Leave 3 holes in the floor, forming a


right angle. Use a laser plumb bob and a
transparent sheet on the floors above.
"Jump" the laser every 5 or 6 floors.
General Items
Platforms, Chutes & Lifts
General Items
Platforms, Chutes & Lifts

David H Moloney
General Items
General Items
Contractors Temporary Site Facilities

Brief Description

Contractors Site facilities comprise:


Offices, Canteens, Toilets, Drying Rooms,
Stores, Plant Yard, generators and
Workshops.

David H Moloney
General Items
Dewatering

Brief Description

Construction dewatering is the removal or drainage of


groundwater and or surface / rain water usually by
pumping to keep the works dry.

David H Moloney
General Items
Dewatering

Brief Description

Construction dewatering is the removal or


drainage of groundwater and or surface /
rain water usually by pumping to keep the
works dry.

David H Moloney
General Items
Dewatering

David H Moloney
General Items
Site Hoarding examples

David H Moloney
General Items Temporary Electricity Supply & Tower Lights

David H Moloney
General Items Welfare Facilities

Toilets Washing

Canteen, Drying Room, Toilet & Generator

David H Moloney
Safety & Environmental
Emergency Phone Numbers & Response
Health, Safety & Environment
Dashboard is a single page, graphical representation of
HSE Monitoring & Reporting - Dashboard current HSE statistics and historical trends
Health, Safety & Environment
Health, Safety & Environment
Safety Precautions
Health, Safety & Environment
Signs Examples
Hazardous Substances Symbols
Health, Safety & Environment

COSHH stands for the


Control of Substances
Hazardous to Health

Shown are the new


hazard symbols
Air, Noise, Water & Soil Pollution
Environmentally Friendly Site
Health, Safety & Environment
Segregation of Waste
Health, Safety & Environment

Segregation of waste for proper disposal and


recycling. Less waste goes to landfill and
hazardous waste is treated to make it safe.

Colour Code for Skips & Bins


Health, Safety & Environment
Water Pollution Prevention
Existing Underground Utilities
Health, Safety & Environment

Brief Description

Before digging establish the


location and route of
underground utilities.

Locator to find Utilities


Spray Paint to mark pavement David H Moloney
Existing Underground Utilities & Overhead Cables - Safety Measures
Health, Safety & Environment

David H Moloney
Health, Safety & Environment
Trench - Safety Measures
Trench - Safety Measures
Health, Safety & Environment

David H Moloney
Earthworks
Excavate & Load, Cart, Tip & Return
Earthworks

Brief Description 7 minutes

Cycle Time for 7km haulage distance


using an Excavator 45 tonne weight
and Dumper with a 40 tonne capacity,
the cycle time is 34 minutes

7 km

14 minutes 7 km 14 minutes

3 minutes
Earthworks
Excavation for Trench with Stepped Faces
Earthworks
Excavation for Trench with Battered Faces
Concrete
Concrete Full Scale Trial Castings of Pier
Concrete

Brief Description

The full-scale trial casting(s) shall


demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.

BIM 3D Model Shutter Fibreglass

David H Moloney
Concrete Batching Plant David H Moloney
Concrete

Brief Description

Concrete batching plant comprises -


concrete mixer, control cabin, silos for
cement and fly ash, aggregate bins and
conveyor belt system to feed the mixer.
Also aggregate storage bays and water
storage tanks.

David H Moloney
Concrete Batching Plant
Concrete

David H Moloney
Concrete Batching Plant 3Nr.
Concrete

David H Moloney
Concrete Batching Plant - Liebherr Betomix Animation
Concrete
Concrete Batching Plant David H Moloney
Concrete

Brief Description
.
The mixing is computer controlled
and has a dynamic screen display,
showing the process. The material
storage capacity is, to match two
days concrete production.

David H Moloney
Concrete Batching Plant Computer Controlled
Concrete

David H Moloney
Concrete Mix Proportions per Cu M
Concrete

Brief Description
.
Details of Mix for C40
1. Concrete Grade C40
2. Cement Type = OPC
Materials Qty Units
3. Slump =125mm Cement 310 Kgs
4. Max size aggregate = 20mm
5. Max water / Cementitious ration =0.42 Fly ash 100 Kgs
Micro-silica 12 Kgs
Washed Sand 670 Kgs
Fine Sand 106 Kgs
Early age strength concrete is 10mm Crushed aggregate 400 Kgs
required for quick floor cycle
time 20mm Crushed aggregates 725 Kgs
Water 145 Ltr.
Additive Rheobuild 7.5 Ltr.
Reinforcement Cutting & Bending Yard
Concrete

Brief Description

Reinforcement in 12 m lengths.
Delivery in 3 ton Bundles

David H Moloney
Reinforcement Cutting & Bending
Concrete

David H Moloney
Reinforcement Cutting & Bending
Concrete

David H Moloney
Reinforcement Cutting & Bending Yard David H Moloney
Concrete

Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine

Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
David H Moloney
Reinforced Wall Construction Sequence
Concrete

Brief Description

The sequence to construct a reinforced concrete wall is as


follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.

Cycle Time
Pour per Day

David H Moloney
Reinforced Wall Construction Sequence
Concrete

David H Moloney
Vibrating Concrete
Concrete

David H Moloney
Piling
Piling
Piling Construction - Plant & Methods

Brief Description

Piling Plant, Equipment and Material;


Crawler Crane, Piling Hammer, Temporary Casing,
Piling Rig, Concrete Pump, Concrete Mixer Trucks,
Tremie Pipe and Reinforcement Cage
Piling
Piling Construction - Plant, Methods & Sequence
Piling
Piling Construction - Plant & Methods
Piling
Piling Construction - Vertical Piles
Pile Load Test
Piling

Brief Description

A jack is used to load the pile in steps and


gauges measure any settlement.

David H Moloney
Pile Load Test
Piling

David H Moloney
Progress Monitoring & Administration
Dashboard is a single page, graphical representation of current
Progress Monthly, Monitoring & Reporting - Dashboard progress and historical trends
Histogram Charts for Resources & Outputs

Brief Description

Histograms shows resources etc. for each month of a project.

Concrete per Location


Quantity for each month of the Project
Manpower per Discipline

Man-hours for each month of the Project


David H Moloney
Plant & Equipment List & Workers Job Titles
David H Moloney
Daily Work Record

Brief Description

Daily Work Records showing the


allocation of resources, materials and
work activities carried out daily.
Organogram

Brief Description

Shown are the line and


lateral relationships
between the various team
members and their relative
position in the site
organisation.
Staff Directory

Brief Description

List of staff and their


contact details
Quality Assurance
Dashboard is a single page, graphical representation of current
Quality Assurance Dashboard statistics and historical trends
Production by David H Moloney